Upload
dinhliem
View
222
Download
5
Embed Size (px)
Citation preview
1
1
[3] Optimization study on network planning
Japan International Cooperation Agency (JICA)
2
Base-500kV-network in 2020
2010: Double Circuits from North to South2020: Power Grids in North and South RegionSeries CapacitorsPower Flow
from North to Center & South Region tending to grow uneven Distribution of Hydropower and Coal-fired Power Plants
THAILAND
existing220kV
- 2010
500kVTransmission Line
- 2020
existing
Base-500kV-network in 2020
YalyPlei Ku
Da Nhim
Phu Lam
LAOSNORTHERN AREA
VIET NAM
CHINA
CAMBODIA
Quang Ninh
Soc Son
Nha Trang
Nam Theun 2
Ban Paam
SOUTHERN AREA
CENTRAL AREA
Lai Chau
HOA BINH
Quang Tri
Da Nang
Sam Bor
Tanh Dinh
O Mon
Dong Nai
Ha Tinh
Nho Quang
Son La
Phu MyDi Linh
Dien Nguyentu
THAILAND
4
500 kV series capacitors
Possibility of Shaft-twist Vibration stopping GeneratorsNecessary for EVN:
Interactive Studies between Series Capacitors and Generators Determining Countermeasures
5
Evaluation of system reliability Criteria
N-0Power Supply is possible on Normal State of System.
N-1Power Supply is still possible; even if a Circuit Fault happened.
6
Permissible power flow in base-500kV-network in 2020
Between North and Center RegionN-0
1,300 MW
N-10 MW
When a large Amount of Power is produced in Central Region
2
7
Permissible power flow in base-500kV-network in 2020
Central1 , 3 0 0MW
N-0North
South
Central0 MW
N-1North
South
Limit of Thermal Capacity
8
Permissible power flow in north-center 2 circuitscenter-south 3 circuits
Central1 , 6 0 0 MW
North
South
Central1 , 1 0 0 MW
North
South
N-0 N-1
Limit by the static stability
Limit of Thermal Capacity
9
Summary of reinforcement scenarios of 500kV-network up to 2020
Central –
South
North –
Central
3
3
2
2
Number of Circuits
4
3
3
2N-1N-0
2,2002,200467 Case 4
1,1002,200[- about 20]
350[+ about 50]
Case 3
1,1001,600[- about 10]
82[+ about 10]
Case 2
01300[-]
-[-]
Base-500 kV-Network
Limit Power Flow North - Central
(MW)[Reduced Expenditure]
(mil. USD/y)
Construction Cost
(mil. USD)[Increased
Expenditure](mil. USD/y)
Reinforcement Scenarios
10
Thac Ba
PhaLaiUongBi
Hai Phong
Ninh BinhThanh Hoa
ChemHa Dong
Ha TinhVinh
Dong Hoi
Yaly VinhSonPlei Ku
QuyNhon
Song Hinh
ThacMoDa Nhim
BaoLocTri An
BaRia
TraNocRachGiaCaiLay
Phu Lam
THAILAND
LAOS
NORTHERN AREA
VIET NAM
CHINA
CAMBODIA
Be
KrongBuk
Dinh
Mai Dong
Hoc Mon
LEGEND
500kV Transmission Line (existing)220kV Transmission Line (existing)
500kV Substation (existing)220kV Substation (existing)Hydropower Plant (existing)Thermal Power Plant (existing)
Nho Quang
Di Linh
Phu MyNha Be
Thuong Tin
Quang Ninh
Dong Nai3&4
Nhon TrachSong May
500kV Transmission Line (- 2010)
500kV Substation (- 2010)
500kV Transmission Line (- 2020)
500kV Substation (- 2020)
Son La
Soc Son
Nha Tran
Dien Nguyentu
Nam Theun 2
Ban Paam
SOUTHERN AREA
CENTRAL AREA
Lai Chau
HOABINH
Vie Tri
Quang Tri
Da Nang
Doc Soi
Sam Bor
Tanh Dinh
O Mon
Center-South 3 circuits
500 kV Plei Ku - NhaTrang
ACSR 330 mm2 x 4 x 1cct 300 km
Construction Cost : about 82 mil. USD
11
Location of PSPP in north region
Hoa Binh
Son La
Nho Quang
Soc SonViet TriPSPP
500 kV System in North Region
12
Study conditionsTwo Routes Passing near PSPP Site 500kV for Transmission Lines of PSPP (economical)No Room for Installation of New Bays in Hoa Binh S/S
3
13
Study conditionsIn Case of a Circuit Fault
Remote Generator Shedding through Telecommunication System not allowed Power Control of PSPP allowed
14
Study conditionsA Drop of 1,000 MW during Off-peak Period is acceptable or not.
Cases of Connection with: One CircuitDouble Circuits
15
Optimum method of connection
In Comparison of Power LossesPossible Connections from the Viewpoint of System Reliability
16
Transmission Line with a Single Circuit
Hoa Binh
Nho Quang
Soc SonViet TriPSPP
Son La Single Circuit to South Single Circuit to North
17
Transmission Line with Two Circuits
Double Circuits to South
Double Circuits to North
Single Circuit to North and South
18
Difficulty in Determining Optimum Connection
No Detailed Route Design of Transmission Lines from Son La
Difference of Cost Merit of Power-Losses between South Route Case and North Route Case
Least-loss-case depending on Operation of Generators during Off-peak Time
4
19
Further Study
In comparison of:Cost Merit of Power LossesConstruction Cost Differences among Five Cases
In consideration with:Admissibility of PSPP Drop in Case of a Single Circuit FaultRoute of Transmission Lines from Son La Operation of Generators in North System
20
The End of Session
1
1
[4] Financial study
Japan International Cooperation Agency (JICA)
2
Approach for financial study
Study items
No.1:Financial situation of EVNNo.2:Financial prospects of EVNNo.3:Financial impact of the JICA study plan No.4:Fund raising methods
3
Study items No.1
Financial situation of EVNPast financial performance
ProfitabilityFinancial stabilityCash flow
4
Major financial statisticsPast profitability : generally stable
Ne t S ale s (B illio n VND)
0
5 ,0 00
10 ,0 00
15 ,0 00
20 ,0 00
25 ,0 00
1 997 1 998 1999 20 00 2 001 2002
Pro fitability Ratio
0 .0 %
5 .0 %
10 .0 %
15 .0 %
20 .0 %
25 .0 %
1997 1998 1999 2000 2001 2002
Gross Margin Ratio Ope ratin g P ro fit Ratio
Ne t P ro fit Ratio
5
Major financial statistics
Past financial stability : generally stable
* The balance sheet 2000 was restated in 2001
Current Ratio
0.0%
50.0%
100.0%
150.0%
200.0%
250.0%
300.0%
1997 1998 1999 2000 2001 2002
Equ ity Ratio
0 .0%
10 .0%
20 .0%
30 .0%
40 .0%
50 .0%
60 .0%
70 .0%
1997 1998 1999 2000 2001 2002
6
Major financial statisticsPast cash flow : aggressive investment
Cash Flow by Activity (Bllion VND)
-15000
-10000
-5000
0
5000
10000
1997 1998 1999 2000 2001 2002
NCF From Oprating NCF From Investing
NCF From Financing Net Increase (Decrease)
2
7
Study items No.2
Financial prospects of EVNEVN financial projection for the next 6 years
Overview of the financial projectionProfitabilityCash flow
8
Study items No.2
Financial prospects of EVNOverview of the financial projection
Prepared by EVN finance and accounting dept.Projected period: 2003~2008Revisions of the electricity tariff:5.9¢(4/2004~), 6.5¢(4/2005~), 7.0¢(4/2006~)
Electricity demand:base case of the revised 5th M/P
9
Financial prospects of EVNProfitability : strong growth
EVN Projected Total Revenue
0
500
1000
1500
2000
2500
3000
3500
4000
4500
2003 2004 2005 2006 2007 2008
Mill
on
US$
EVN Projected Net Income
0
100
200
300
400
500
600
2003 2004 2005 2006 2007 2008
Mill
ion
US$
10
Financial prospects of EVNCash flow
Net cash flow: continuously low levelAnnual investment and borrowings: drastically increased from 2005EVN Projected Cashflow (1)
-200
-100
0
100
200
300
400
500
600
700
800
2003 2004 2005 2006 2007 2008
Mill
ion U
S$
Self Cash Generation Net Cashflow End of Year Cash
EVN Projected Cashflow (2)
500
1000
1500
2000
2500
2003 2004 2005 2006 2007 2008
Mill
ion
US
$
Net Investment Borrowing
11
Study items No.2
Financial prospects of EVNAnalysis of the financial projection
Profitability: strong growthCash flow: negative trend from 2006The difference of annual investment
Comparison of Annual Investment(Million USD)
2003 2004 2005 2006 2007 2008 Totala. EVN Projection 1,165 1,291 1,966 2,012 1,937 1,944 10,315b. Revised 5th M/P* 1,341 1,758 2,500 2,427 2,638 2,369 13,033c. Diff. (a.-b.) -176 -467 -534 -415 -701 -425 -2,718 * Excluded IPP Investment
12
Study items No.3
Financial impact of the JICA study planOverview of the financial simulations
Projected period : 10 years (2003-2012)Prepared statements :
income statement and cash flow statementElectricity tariff : EVN tariff scheduleLong-term investment plan : the JICA study planFuel, O&M, Power purchase costs :
estimated costs of the JICA study
3
13
Study items No.3
Financial impact of the JICA study planFinancial simulations focused on financing conditions
CASE 1 :Same financing conditions used in EVN’s
financial projection CASE 2 :Revised financing conditions
14
Financial simulation CASE 1
Profitability Revenue: steady growth
Net profit: steady profit for 2003-2007,
decrease from 2007, deficit from 2010 CASE 1 : Prospective Total Revenue
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Mill
ion
US$
CASE 1 : Prospective Net Profit
-200
-150
-100
-50
0
50
100
150
200
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Mill
ion U
S$
15
Financial simulation CASE 1
Cash flowNet cash flow: negative from 2005
Yearend cash balance:negative from 2009
Annual debt repayment:increases every yearCASE 1 : Prospective Cash Flow (1)
-4,000
-3,000
-2,000
-1,000
0
1,000
2,000
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Mill
ion U
S$
Net Cashflow End of Year Cash
CASE 1 : Prospective Cash Flow (2)
0
500
1,000
1,500
2,000
2,500
3,000
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Mill
ion U
S$
Principle Repayment Borrowing
16
Financial simulation CASE 1
Results of CASE 1Profit:
Decreases from 2007, deficit from 2010Cash flow:
Cash balance becomes negative at 2009 yearend, cash shortage continues
Major cause of shortage is increase of annual debt repayment
Investment plan of the JICA study is not practical under the financing condition of EVN
17
Study items No.3
CASE 2 Revised financing conditions:
Extension of repayment periodNetwork projects: extend 15 to 20 yearsODA projects: extend additional 5 years
Change of fund sourceSeveral generation projects:change commercial borrowings to ODA
18
Financial simulation CASE 2
Profitability Net profit:
Deficit on 2011 only
Slight improvement from Case 1Comparison of Net Income
-200
-150
-100
-50
0
50
100
150
200
250
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012Mill
ion
US$
CASE 2 CASE 1
4
19
Financial simulation CASE 2
Cash flowInternal sources: significant improvement from CASE 1
Yearend cash balance: positive throughout projected period
Annual debt repayment: reduced in later half of projected period
Comparison of Internal Sources
-1,200
-1,000
-800
-600
-400
-200
0
200
400
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Millio
n U
S$
CASE 2 CASE 1
Comparison of Principle Repayment
0
500
1,000
1,500
2,000
2,500
3,000
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Mill
ion U
S$
CASE 2 CASE 1
20
Financial simulation CASE 2
Results of the CASE 2Profitability:
Slight improvement from CASE 1 Reduced interest expenses by use of ODA and internal
source fundsCash flow:
Positive cash balance throughout projected period Reduced annual debt repayment compared to CASE 1
Use of ODA loan and extension of repayment period are effective for implementing the investment plan of the JICA study
21
Study items No.4
Fund raising methodsUse of ODA loanExtension of debt repayment periodChange of the fund source from commercial borrowings to ODA loans for network projects
22
The End of Session
1
1
Japan International Cooperation Agency (JICA)
[5] Peaking Power Sources Potential Study
Study Flow
Financial evaluation
Power system
Planning and
Analysis
Project design and site survey
Environmental survey
Other Peaking Power Sources
Pumped Storage Potential
Optimal Power Development Master Plan
3
Possibility of PSPP Installation
What is PSPP ?Priority candidate sites selectionOptimum installed capacityPreliminary design
4
What is PSPP? (1)Peak time
(Generating)Off Peak time
(Pumping)
Upper Reservoir
Power HouseLowerReservoir
Pumped Storage Power Plant
Customers
Factories
Hydro and Thermal Power Plants
Substation
Houses
Upper Reservoir
Power HouseLower Reservoir
Pumped Storage Power Plant
Customers
Factories
Hydro and Thermal Power Plants
Substation
Houses
Peak time
(Generating)
Off Peak time(Pumping)
Upper Reservoir
Power HouseLowerReservoir
Pumped Storage Power Plant
Customers
Factories
Hydro and Thermal Power Plants
Substation
Houses
Upper Reservoir
Power HouseLower Reservoir
Pumped Storage Power Plant
Customers
Factories
Hydro and Thermal Power Plants
Substation
Houses
5
What is PSPP? (2)
0 6 12 18 24Hour
Demand
(MW)
Improved load curve
Plant factor and Fuel efficiency of Thermal power plants are improved
Power utilized by Pumped storage power
Power generated by Pumped storage power
0 6 12 18 24Hour
Demand
(MW)Power utilized by Pumped storage power
Power generated by Pumped storage power
6
Possibility of PSPP Installation
What is PSPP ?Priority candidate sites selectionOptimum installed capacityPreliminary design
2
7
(1)Flow of PSPP Potential Study
Criteria Setting
Geographical Study
Site Survey (1)
Site Survey (2)
Preliminary design and cost estimationfor the highest priority project
38 sites 10 sites
10 sites 4 sites
4 sites 3 sites
Technical criteriaEnvironment criteria
8
Prioritization according to the 1st Site Survey Results
Project Site Name (P5) (P11B) (JN1) (JN3) (JN18) (JN5) (JN9) (JN6) (JS6) (JS11)
Economic Value (US$/kW)
750 770 910 760 790 680 820 760 730 820
B / C 1.10 1.08 0.93 1.09 1.05 1.20 1.02 1.09 1.13 1.02
Tentative eveluation scores of EnvironmentalAssesment
1.0 1.0 2.0 1.2 1.9 1.2 1.7 1.4 2.0 1.4
Priority Rank AA A C AA B AA B A A B
9
Criteria for Prioritization
AA superior and no significant and no significant
A superior and some or some
B feasible and ditto or ditto
C uneconomical or significant or significant
PriorityRank
Criteria
Economyand/or Technical problems
Natural/SocialEnvironmental
negative impacts
and/or
10
Prioritization according to the 2nd Site Survey Results
Phu Yen East Phu Yen West Bac Ai1000 1000 1000230 240 350560 520 360
SocialImpacted directly :
74households(385people)
Impacted directly :300households(1700people)
Impacted directly :63households(330people)
Natural Limited directimpacts
Significant impactson aquatic system
Significant impactson ecosystem
Project cost 630 US$ / kW 700 US$ / kW 660 US$ / kWT/L cost 40 mln.US$ 45 mln.US$ 50 mln.US$
1 2 31 3 21 2 2
Environmental runkEconomical rank
Comprehensive rank
EnvironmentalImpacts
Economy
Installed Capacity(MW)Design Discharge (m3)
Effective Head (m)
Items
11
Locations of priority PSPPs
Bac Ai
Phu Yen West
Phu Yen East
12
Possibility of PSPP Installation
What is PSPP ?Priority candidate sites selectionOptimum installed capacityPreliminary design
3
13
Optimal Installed capacity(Phu Yen East)
(Pumping energy by Coal)
0.50
0.60
0.70
0.80
0.90
1.00
1.10
1.20
1.30
1.40
1.50
750 900 1,050
Installed Capacity (MW)
B/C
-20
-15
-10
-5
0
5
10
15
20
B-C
(m
il. U
S$
)
1,200
optimal
B/C 6 hrB/C 7 hrB/C 8 hrB-C 6 hrB-C 7 hrB-C 8 hr
14
Possibility of PSPP Installation
What is PSPP ?Priority candidate sites selectionOptimum installed capacityPreliminary design
15
Preliminary Design and Cost Estimation(Phu Yen East Optimum Case)
: 1200 MW
: 271 m3/s: 559 m: 7 hr
: 6.9 x106m3
: Full Faced Pond (Asphalt): Concrete Gravity: 3,700 m
: 185,000 m3
: Single-Stage Francis (3 x 400MW)
Waterway total length (Lt)Underground P/H Cavern VolumePump-Turbine
Upper Dam TypeLower Dam Type
Installed Capacity (P)Designed Discharge (Qd)Effective Head (Hd)Peak Duration TimeEffective Reservoir Capacity
Specifications
16
Design Drawings (General Outline)
17
Design Drawings (Upper reservoir)
18
EL.180.600
EL.185.500
EL.190.000
EL.229.500
CL of Turbine
CL of Turbine
EL.195.000
EL.200.500
EL.206.500
EL.215.500
EL.180.600
EL.200.500
EL.195.000
EL.191.000
EL.206.500
EL.229.500
EL.185.500
EL.215.500
Erection Bay
TRANSFORMER TRANSFORMER TRANSFORMER
CL of Turbine CL of Turbine CL of Turbine
Ventilation Tunnel B
Access Tunnel
Motor &Generator
Ventilation Tunnel A
Motor &Generator
Motor &GeneratorEL.200.500
EL. 195.000
EL.206.500
CABLE
Design Drawings (Powerhouse)
4
19
Design Drawings (Lower reservoir)
20
Preliminary Design and Cost Estimation(Phu Yen East)
: 720 million US$
: 600 US$/kW
: 1.17 (1.47*)
F.I.R.R. : 6.1 (7.8*) %
Unit Construction Cost
B / C
Construction Cost
* : in the case of Pumping Energy by Hydropower
Economic Evaluation
21
Development Schedule
Total Time Required : 14 yearsPreparation for F/S : 1 year
F/S & EIA : 2 years
Finance Procurement : 1 year
Detail Design : 2 years
Tender & Contract : 1 year
Construction period : 7 years
22
The End of Session