Predictive Maintenance Thermographin GIS 500KV Unit 3
Company
Device
Customer
Adityan ilmawan
Tester:
Standard 32Lens:
2279803Serial No.:testo 876
Jepara, Central Java
Desa Tubanan KecamatanKembang
Electrical Maintenance Division
11/25/2014Measuring Date:
Measuring Site:
Check Temperature and take thermograph photoTask
Jepara, Central Java
Desa Tubanan KecamatanKembang
PT KOMIPO PEMBANGKITANJAWA BALI
1/6Page
Predictive Maintenance Thermograph in GIS 500KV Unit 3
File: IV_00216.BMT
11/14/2014 MeasuringTime:
8:35:39 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Surge Arrester Phase R GIS 500 KV Unit 3
Remarks:
File: IV_00217.BMT
11/14/2014 MeasuringTime:
8:36:08 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Phase R GIS 500 KV Unit 3
Remarks:
File: IV_00218.BMT
11/14/2014 MeasuringTime:
8:36:41 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Voltage Transformer Phase R GIS 500 KV Unit 3
Remarks:
File: IV_00219.BMT
11/14/2014 MeasuringTime:
8:36:53 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Bushing Phase R GIS 500 KV Unit 3
Remarks:
2/6Page
Predictive Maintenance Thermograph in GIS 500KV Unit 3
File: IV_00220.BMT
11/14/2014 MeasuringTime:
8:37:28 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
V-Suspension Phase R GIS 500 KV Unit 3
Remarks:
File: IV_00221.BMT
11/14/2014 MeasuringTime:
8:38:01 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Phase R GIS 500 KV Unit 3
Remarks:
File: IV_00209.BMT
11/14/2014 MeasuringTime:
8:24:43 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Surge Arreste Phase S GIS 500 KV Unit 3
Remarks:
File: IV_00210.BMT
11/14/2014 MeasuringTime:
8:25:27 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Phase S GIS 500 KV Unit 3
Remarks:
3/6Page
Predictive Maintenance Thermograph in GIS 500KV Unit 3
File: IV_00211.BMT
11/14/2014 MeasuringTime:
8:25:56 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Voltage Transformer Phase S GIS 500 KV Unit 3
Remarks:
File: IV_00214.BMT
11/14/2014 MeasuringTime:
8:34:27 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
V-Suspension Phase S GIS 500 KV Unit 3
Remarks:
File: IV_00215.BMT
11/14/2014 MeasuringTime:
8:35:03 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Phase S GIS 500 KV Unit 3
Remarks:
File: IV_00203.BMT
11/14/2014 MeasuringTime:
8:21:08 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Surge Arreste Phase T GIS 500 KV Unit 3
Remarks:
4/6Page
Predictive Maintenance Thermograph in GIS 500KV Unit 3
File: IV_00204.BMT
11/14/2014 MeasuringTime:
8:22:07 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Phase T GIS 500 KV Unit 3
Remarks:
File: IV_00205.BMT
11/14/2014 MeasuringTime:
8:22:38 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Voltage Transformer Phase T GIS 500 KV Unit 3
Remarks:
File: IV_00206.BMT
11/14/2014 MeasuringTime:
8:23:07 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Bushing Phase T GIS 500 KV Unit 3
Remarks:
File: IV_00207.BMT
11/14/2014 MeasuringTime:
8:23:21 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
V-suspension Phase T GIS 500 KV Unit 3
Remarks:
5/6Page
Predictive Maintenance Thermograph in GIS 500KV Unit 3
File: IV_00208.BMT
11/14/2014 MeasuringTime:
8:23:58 AM
20.0Refl. temp. [C]:
0.95Emissivity:
Picture parameters:
Date:
Phase T GIS 500 KV Unit 3
Remarks:
Adityan ilmawan
,11/25/2014
6/6Page