88
June 2016 Bandon Road Upgrade Between Richmond Road, Marsden Park and Windsor Road, Vineyard Options Report

Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

June 2016

Bandon Road Upgrade

Between Richmond Road, Marsden Park and Windsor Road, Vineyard

Options Report

Page 2: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

2

THIS PAGE LEFT INTENTIONALLY BLANK

Page 3: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

3

Contents

EXECUTIVE SUMMARY 4

1 INTRODUCTION 8

1.1 Background 8 1.2 Purpose of this report 9 1.3 The study area 9 1.4 Summary 14

2 PROJECT NEED AND STRATEGIC CONTEXT 15

2.1 Project need 15 2.2 North West Growth Centre Road Network Strategy objectives 16 2.3 Bandon Road project specific objectives 17 2.4 Strategic context 17 2.5 Transport demand and analyses 20 2.6 Summary 23

3 COMMUNITY AND STAKEHOLDER CONSULTATION 24

3.1 Community involvement 24 3.2 Government agency and stakeholder involvement 25 3.3 Other involvement 26 3.4 Summary 27

4 CORRIDOR OPTION IDENTIFICATION AND ASSESSMENT 28

4.1 North West Growth Centre Road Network Strategy 28 4.2 The Bandon Road corridor options 28 4.3 Constraints and opportunities 31 4.4 Bandon Road corridor assessment and selection 38 4.5 Option assessment 42 4.6 Summary 61

5 CONCLUSIONS AND NEXT STEPS 62

5.1 Preferred corridor option 62 5.2 Next steps 63

APPENDICES 64

Page 4: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

4

Executive Summary

This document details the option development and evaluation process for the upgrade of Bandon

Road between Richmond Road, Marsden Park and Windsor Road, Vineyard. The upgrade of Bandon

Road including a grade separated crossing of the Richmond railway line. The Bandon Road upgrade

forms part of the medium term work of the North West Growth Centre Road Network Strategy

announced by the NSW Government in November 2014 and confirmed in July 2015. The Strategy

covers the area of the North West Priority Land Release Area (NWPLRA), formerly the North West

Growth Centre. The Strategy identifies the road network upgrades required to support development

within the NWPLRA that is expected to occur over the next 20 to 30 years. The proposed road

network upgrades would be developed in three key phases; short, medium and long-term phases,

subject to funding availability (refer to Figure1.3).

A Value Management workshop was held on 17 December 2015 to review the options that had been

investigated as part of the strategic development of a Bandon Road connection between Richmond

Road, Marsden Park and Windsor Road, Vineyard. The aim of the workshop was to select a preferred

corridor from fourteen options (refer to Figure 1.4). After consultation with the key stakeholder group

in attendance at the Value Management workshop, Option M (refer to Figure 4.5) was selected as the

preferred option.

Project Need

The NWPLRA is around 10,000 hectares in size and includes parts of The Hills Shire Council,

Blacktown City Council and Hawkesbury City Council local Government areas. Over time, it is

estimated 70,000 new dwellings will be built in the NWPLRA for about 200,000 residents. The rise in

resident and worker population across the NWPLRA will be accompanied by increases in t raffic

between now and until full development of the NWPLRA occurs (refer to Section 2.4.1). The existing

road network does not have the capacity to meet the expected growth in transport demand that will

result from this population increase. This lack of capacity within the existing road network to meet

future traffic demand is forecast to result in unacceptable increases in congestion and delay,

deterioration in accessibility across the region and impact on road and rail customers.

The Bandon Road upgrade which includes an underpass of the Richmond railway line at Vineyard is

needed to:

1. Accommodate forecast growth in traffic across the region

2. Provide an additional crossing of the Richmond railway line to lessen existing and forecast

congestion at the Garfield Road level crossing as the NWPLRA develops.

Bandon Road Upgrade Objectives

The Bandon Road upgrade is required to accommodate travel across the Richmond railway line

generated by the forecast growth in the NWPLRA. The upgrade will:

Provide an important part of the road network within the NWPLRA to support the

Government’s urban land release strategy for the NWPLRA through the provision of increased

road capacity to meet existing and future traffic and transport growth

Provide the infrastructure necessary to ultimately close 2 existing level crossings located at

Bandon Road, Vineyard and Level Crossing Road, Vineyard

Reduce congestion caused by the existing Garfield Road railway level crossing at Riverstone

Reduce travel times between Windsor Road and Richmond Road and reduce congestion

across the Richmond railway line at Garfield Road.

Page 5: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

5

Bandon Road preferred corridor selection

A total of fourteen Bandon Road corridor upgrade options were identified in consultation with the

Department of Planning and Environment (DP&E) and other key stakeholders subsequent to the

confirmation of the Road Network Strategy for NWPLRA in July 2015. A Value Management

workshop was held on 17 December 2015 to review these fourteen options and seek input from

stakeholders. The agencies represented at the Workshop included DP&E, Roads and Maritime

Services (Roads and Maritime), The Hills Shire Council, Blacktown City Council, Hawkesbury City

Council, Transport for NSW (TfNSW), TransGrid and the NSW Member for Riverstone.

The Bandon Road preferred corridor

Option M (refer to Figure 4.5) was identified as being the preferred corridor for a number of reasons

including:

Topography – the preferred corridor utilises the existing topography to minimise the length of bridge

required across Eastern Creek and minimises fill earthworks volumes within the floodplain. The

preferred option would aim to minimise flood impact.

Land Use – the preferred corridor provide good connectivity to Marsden Park North and good access

to areas of land located above the 1% AEP (1 in 100 year flash and backwater flood level). The Option

would serve both sides of Bandon Road and would utilise an existing length of Park Road as part of

the Bandon Road corridor. It would minimise effects on land that can be developed within the

Riverstone West precinct and limit direct effects on existing businesses and residences on the

northern side of Bandon Road between the Richmond railway line and Windsor Road.

Environment – The preferred corridor facilitates environmental impact mitigation although some issues

require continued examination. The Bandon Road Preliminary Environmental Investigation concluded

that there would be likely impact on small areas of Shale Plains Woodland (Cumberland Plain

Woodland critically endangered ecological community (TSC Act and EPBC Act)) and Shale / Gravel

Transition Forest (EPBC Act, critically endangered; TSC Act endangered). These areas are located

immediately to the west of Park Road and to the north of the existing Bandon Road extent. All are

located on biocerti fied lands. Potential impact on habitat for threatened flora including Grevillea

juniperina subsp. Juniperina (TSC Act, vulnerable), for which there are previous records on the

southern side of the existing Bandon Road extent and near Park Road. Any impact would most likely

be in biocertified areas.

Constructability and Risks – The preferred corridor minimises impact on the TransGrid transmission

lines and the creek crossings would be above the 1% AEP (1 in 100 year flash flood level, with further

investigation into level of backwater flood immunity to be undertaken in the next design stage). The

corridor connects to the recently constructed signalised intersection of Richmond Road and Elara

Boulevard (New Precinct Road B in Figure 4.2) within the Marsden Park precinct and would therefore

complement precinct planning in the area.

Road Function – Bandon Road would join Richmond Road at the recently constructed Richmond

Road and Elara Boulevard (New Precinct Road B) intersection within the Marsden Park precinct. This

intersection with the recently constructed traffic signals at Elara Boulevard would be consistent with

the internal Marsden Park precinct road network while providing good spacing of intersections along

Richmond Road north of Garfield Road West.

Strategic – The preferred corridor is generally consistent with the Roads and Maritime North West

Growth Centre Road Network Strategy for the NWPLRA facilitating east-west connections between

Windsor Road and Richmond Road. This corridor would provide an alternative route to the Garfield

Road east-west route across the Richmond railway line. The corridor would provide good connectivity

to the Marsden Park North precinct compared to other options.

Page 6: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

6

Public and active transport - The preferred corridor would be central to the Marsden Park North

precinct meaning bus feeder access could be optimised. The corridor alignment would maximise

accessibility and connectivity with the neighbouring precincts. The corridor would facilitate connectivity

beyond the NWPLRA because the intersection of Bandon Road with Elara Boulevard means east-

west connectivity for through trips is maximised. This would benefit precinct traffic, cross regional bus

services and through vehicle movements. The corridor could facilitate good pedestrian and cyclist

access by virtue of its central alignment which would provide efficient access between the Marsden

Park North precinct and planned retail centre and sporting facilities in the Marsden Park precinct.

The assessment of options also concluded:

The point of intersection with Richmond Road would be around one kilometre north of the

Garfield Road intersection providing good separation of signalised intersections along the

arterial road

Option M is central to the Marsden Park North precinct which will enable a higher order road

within the preferred corridor to efficiently provide access across the precinct once developed

The corridor would minimise impact on the central vegetation conservation zone, riparian

corridors and threatened ecological communities

The preferred corridor would promote planning of new integrated neighbourhoods because it

minimises severance of planned neighbourhoods and would minimise impact on precinct and

resident amenity

The preferred corridor would facilitate the ability to stage precinct development over time

between now and full development

The preferred corridor could service a range of dwelling yields.

North West Growth Centre Road Network Strategy

The North West Growth Centre Road Network Strategy Map has been updated March 2016 to show

the Bandon Road preferred corridor, see opposite page.

Next Steps

The next steps include:

1. Community consultation of the Bandon Road preferred corridor

2. Consider consultation feedback and refine preferred corridor if required

3. Start Bandon Road preferred corridor reservation.

4. Develop Concept Design and Environmental Assessment.

Page 7: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

7

Updated May 2016

Page 8: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

8

1 Introduction

1.1 Background

The North West Priority Land Release Area (NWPLRA), formerly known as the North West Growth

Centre spans three council areas, The Hills Shire Council, Blacktown City Council and Hawkesbury

City Council. The area, which today has a population of about 5,000 residents, is forecast to

accommodate around 70,000 dwellings for 200,000 residents and a work force of about 40,000 over

the next 20 to 30 years. This growth will be accommodated within a number of priority land release

precincts (Figure 1.2), each being released and developed in stages. As at March 2016, the Marsden

Park and Marsden Park (Industrial) precincts have been rezoned, released and (partially) developed.

Another nine precincts have been rezoned and released for development (refer to Section 2.4.1).

Riverstone and its surrounding areas are integral to the NWPLRA where the growth in resident and

worker populations is forecast to generate an increase in traffic to, from and through the area. In

November 2014 the NSW Government released the North West Growth Centre Road Network

Strategy for the NWPLRA, formerly the North West Growth Centre. This Strategy identified road

crossing locations of the Richmond railway line within the NWPLRA (Figure 1.3). The Strategy

identifies the road network upgrades required to support development within the NWPLRA that is

expected to occur over the next 20 to 30 years. The proposed road network upgrades would be

developed in three key phases, the short, medium and long term phases, subject to funding

availability.

In the short term the Strategy proposes that Roads and Maritime Services:

Work with Blacktown City Council to develop local strategies and to improve traffic flow within

the Riverstone Town Centre and access to Westminster Street bridge

- In July 2015, Roads and Maritime Services sought feedback from the community on

new traffic signals that were proposed at the intersection of Westminster Street and

Railway Terrace, Schofields. Environmental approval for new traffic signals was

granted in November 2015.

- In November 2015, Roads and Maritime Services sought feedback from the

community on the Denmark Link Road a new link road between Garfield Road West,

Riverstone and Westminster Street bridge, Schofields.

Begin planning for the Bandon Road corridor between Richmond Road, Marsden Park and

Windsor Road, Vineyard. This is the subject of this report

Work with the Department of Planning and Environment and Blacktown City Council to

reserve a road corridor along Garfield Road between Richmond Road and Windsor Road for

future widening

Complete work on Stage 2 of Schofields Road between Tallawong Road and Veron Road at

Schofields.

In the medium term the Strategy proposes that Roads and Maritime Services:

Build Stage 3 of Schofields Road between Veron Road, Schofields and Richmond Road,

Marsden Park

Build the Bandon Road underpass and create a new road connection between Richmond

Road to Windsor Road

Page 9: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

9

Has the potential to close the railway level crossings at Bandon Road and Level Crossing

Road at Vineyard once Bandon Road underpass of the Richmond railway line is open to traffic

Once Bandon Road and Schofields Road are both opened to t raffic, consider heavy vehicle

restrictions through the Riverstone Town Centre with the Garfield Road level crossing to

remain until grade separation of Garfield Road and the Richmond railway line occurs in the

long term.

In the long term when about 75 per cent of the NWPLRA is developed, the Strategy proposes that

Roads and Maritime Services:

Upgrade Garfield Road between Richmond Road, Marsden Park and Windsor Road,

Riverstone

Build a grade separated crossing in the Garfield Road corridor at Riverstone and remove the

Garfield Road level crossing.

The North West Growth Centre Road Network Strategy was confirmed in July 2015.

1.2 Purpose of this report

This report documents the option development and evaluation process for the upgrade of Bandon

Road between Richmond Road, Marsden Park and Windsor Road, Vineyard. The report aims to:

Explain the strategic context and need for the upgrade.

Establish a study area for the upgrade and present relevant issues and constraints.

Document community and stakeholder involvement.

Describe the corridor options development and assessment process including the

methodology for the selection of the preferred corridor.

Present the preferred corridor.

Outline the next steps for the proposal development.

1.3 The study area

Riverstone is located in Sydney’s NWPLRA (formerly North West Growth Centre (NWGC)), about 48

km north-west of the Sydney CBD (refer to Figure 1.1). The NWPLRA is about 10,000 hectares in

size and includes parts of The Hills Shire Council, Blacktown City Council and Hawkesbury City

Council local Government areas. It is divided into 16 ‘precincts’ that are being progressively released

and rezoned for sustainable urban development (refer to Figure 1.2). The NWPLRA will be supported

by a Major Centre at Rouse Hill and be serviced by the Sydney Metro Northwest (formerly North West

Rail Link) and the Richmond railway line. Over time, some 70,000 new dwellings will be built in the

NWPLRA for about 200,000 residents.

Page 10: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report 10

Figure 1.1 – Regional Context

Figure 1.2 – The North West Priority Land Release Area (NWPLRA) Precincts, June 2014

Page 11: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report 11

In the broader study area there are four existing railway crossings that accommodate general traffic

access (excluding the level crossing near King Street); the Garfield Road level crossing, the crossing

at Westminster Street bridge, the Bandon Road level crossing and Level Crossing Road at Vineyard.

The grade separated railway crossing at Bandon Road will be one of five additional grade separated

road crossings required between Vineyard and Quakers Hill Parkway to efficiently accommodate

forecast traffic demand. The five crossings of the Richmond railway line identified in the Strategy from

north to south are located at Bandon Road, Garfield Road, Westminster Street, Schofields Road and

Burdekin/Townson Road. Sections of the Schofields Road upgrade are under construction by Roads

and Maritime while the Burdekin/Townson crossing will be delivered by Blacktown City Council.

The study area within which the Bandon Road upgrade corridor options have been identified

embraces an area between Windsor Road and Richmond Road through the Riverstone, Ri verstone

West and Marsden Park North precincts.

Figure 1.3 overleaf shows the identified road crossing locations of the Richmond railway line within

the NWPLRA. The Strategy identifies the road network upgrades required to support development

within the NWPLRA that is expected to occur over the next 20 to 30 years. The broader study area

within which the Strategy investigations were undertaken focused on the Riverstone and Schofields

areas bounded by Richmond Road, Bandon Road, Windsor Road, Old Windsor Road, Sunnyholt

Road, Quakers Hill Parkway and the M7 Motorway.

Page 12: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

12

Figure 1.3 – Confirmed North West Growth Centre Road Network Strategy (Updated November

2015 to include Denmark Link Road)

1.3.1 The corridor selection study area

During 2014, the Bandon Road corridor options identification and assessment process undertaken as

part of the development of the North West Growth Centre Road Network Strategy announcement

concluded that a northern alignment option referred to as Option A2 (an extension of Bandon Road)

was a preferred alignment and recommended for more detailed assessment. Refer to Figure 4.4 in

chapter 4. Bandon Road option A2 extended Bandon Road westwards past the sewage treatment

plant and electricity substation to join with Richmond Road.

Page 13: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report 13

Part of the North West Growth Centre Road Network Strategy’s short-term work is to begin planning

for the Bandon Road corridor between Richmond Road, Marsden Park and Windsor Road. Further

options identification, refinement, and assessment for the Bandon Road upgrade was undertaken

subsequent to the exhibition of the North West Growth Centre Road Network Strategy for the

NWPLRA. Using Option A2 as the base alignment, multiple corridor options were identified in

consultation with relevant Government agencies and assessed on the basis of agreed criteria. A

Value Management workshop was held on 17 December 2015 to review fourteen options (Figure 1.4)

and seek input from stakeholders. The agencies represented at the Workshop included DP&E, Roads

and Maritime, The Hills Shire Council, Blacktown City Council, Hawkesbury City Council, TfNSW,

TransGrid and the NSW Member for Riverstone.

The outcome of the Value Management workshop and the options selection process is detailed in

Chapter 4 of this report. Figure 1.4 shows the Bandon Road corridor options assessed at the Value

Management workshop.

Figure 1.4 – The fourteen Bandon Road Corridor Options Assessed at the December 2015

Value Management workshop

Page 14: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

14

1.4 Summary

The key messages in Chapter 1 are as follows:

1. A North West Growth Centre Road Network Strategy for the NWPLRA (formerly the North

West Growth Centre) was announced by the NSW Government in November 2014 and

confirmed in July 2015

2. The Strategy identifies upgrades to the road network required to support the development of

the NWPLRA in three stages; in the short, medium and long term over the next 20 – 30 years

3. The North West Growth Centre Road Network Strategy identifies the need for five grade

separated crossings of the Richmond railway line north of Quakers Hill Parkway. These

crossings are located at:

- Bandon Road at Vineyard (currently a level crossing on the Richmond railway line and the

subject of this report)

- Garfield Road at Riverstone (currently a level crossing on the Richmond railway line, would

be upgraded to a grade separated crossing of the Richmond railway line in the long term)

- Westminster Street bridge at Schofields (the existing bridge over the Richmond railway line)

- Schofields Road at Schofields (Stage 2 is currently under construction. Stage 3 is expected

to start construction in mid-2016)

- Burdekin Road and Townson Road at Schofields (proposed by Blacktown City Council)

4. The provision of a grade separated Richmond railway crossing at Bandon Road and a road

link between Richmond Road, Marsden Park and Windsor Road, Vineyard is the key medium

term component of the Strategy planned for delivery after 2021 subject to funding availability

5. The study area within which the Bandon Road upgrade corridor options have been identified

embraces an area between Windsor Road and Richmond Road through the Vineyard,

Riverstone, Riverstone West and Marsden Park North precincts

6. Corridor selection has occurred in accordance with the process outlined in Chapter 4 and

summarised in Figure 4.3.

Page 15: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

15

2 PROJECT NEED AND STRATEGIC CONTEXT

2.1 Project need

The rise in resident and worker population across the NWPLRA will be accompanied by increases in

traffic between now and until full development of the NWPLRA occurs (refer to Section 2.5). At full

development the population of the NWPLRA is estimated to be 200,000 people. The existing road

network does not have the capacity to meet the expected growth in transport demand that will result

from this population increase. This lack of capacity within the existing road network to meet future

traffic demand is forecast to result in unacceptable increases in congestion and delay, a deterioration

in accessibility across the region and impact on road and rail customers.

The Bandon Road upgrade which includes an underpass of the Richmond railway line at Vineyard is

needed to:

1. Accommodate forecast growth in light and heavy vehicle traffic across the region

2. Provide an additional crossing of the Richmond railway line to lessen existing and forecast

congestion at the Garfield Road level crossing as the NWPLRA develops.

There are four existing Richmond railway line crossings that accommodate general traffic access

(excluding the King Street level crossing) which includes the:

Garfield Road level crossing

Two lane bridge over the Richmond railway line at Westminster Street

Bandon Road level crossing (currently no connection to Richmond Road); and

Level Crossing Road near Vineyard.

The North West Growth Centre Road Network Strategy identifies the need for five grade-separated

crossings of the Richmond railway line north of Quakers Hill Parkway. These crossings are located at:

Bandon Road at Vineyard (currently a level crossing on the Richmond railway line and the

subject of this report)

Garfield Road at Riverstone (currently a level crossing on the Richmond railway line, would

be upgraded to a grade separated crossing of the Richmond railway line in the long term)

Westminster Street bridge at Schofields (the existing bridge over the Richmond railway line)

Schofields Road at Schofields (Stage 2 is currently under construc tion. Stage 3 is expected to

start construction in mid-2016)

Burdekin Road and Townson Road at Schofields (proposed by Blacktown City Council).

Analysis shows that, four additional traffic lanes in each direction crossing the Richmond railway line

are required between Vineyard and south of Riverstone (between Bandon Road and north of

Westminster Street) to efficiently accommodate forecast traffic demand. Currently there are seven

lanes crossing the Richmond railway line (four eastbound lanes and three westbound lanes) within the

NWPLRA between Bandon Road and Westminster Street. This analysis took into account the existing

two-lane bridge at Westminster Street and the planned road crossings at Schofields Road and

Burdekin/Townson Roads. The need for the Bandon Road corridor underpass of the Richmond railway

line occurs in the medium term after 2021. The exact timing is dependent upon population and

employment growth across the NWPLRA.

Page 16: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

16

The Bandon Road upgrade is justified on the grounds that the work will support access to and from

current and future development within the NWPLRA. The work will reduce average travel times under

forecast traffic conditions.

In the medium and longer term, the risks of not upgrading the Bandon Road corridor are as follows:

In the absence of the planned additional railway crossings, there will be inadequate road

capacity to accommodate east-west traffic movement across the Richmond railway line as the

NWPLRA develops. The traffic study undertaken by Parsons Brinckerhoff in 2014 notes that

by 2036 the volume of traffic crossing the Richmond railway line between Burdekin Road and

Bandon Road is expected to be around 9,000 veh/hr (excluding Quakers Hill Parkway) in the

peak direction meaning about 11 lanes (in the peak direction) would be required to

accommodate forecast demand by 2036. Not providing additional lanes would result in

deterioration in peak and off peak traffic flow at existing crossing locations (Bandon Road,

Garfield Road and Westminster Street bridge)

Traffic volumes along lower order roads would increase beyond their functional capacity,

especially at locations such as Westminster Street bridge. Under the Do Minimum case,

Westminster bridge traffic could in theory increase to in excess of 1,200 veh/hr in the AM peak

compared with approximately 650 veh/hr in 2014 in the absence of grade separated crossings

at Bandon and Garfield Roads (Parsons Brinckerhoff, 2015). This higher volume is not

possible at the Westminster Street bridge due to geometric constraints

Traffic queues and delays along both approaches of Garfield Road at the railway level

crossing would further deteriorate.

2.2 North West Growth Centre Road Network Strategy

objectives

The broader objectives of the North West Growth Centre Road Network Strategy for NWPLRA are to:

1. Provide a road network within the NWPLRA to support the Government’s urban land release

strategy for the NWPLRA through the provision of increased road capacity to meet existing

and future traffic and transport growth

2. Improve road and train user safety by providing the infrastructure necessary to ultimately close

four existing level crossings located at Garfield Road at Riverstone, north of King Street at

Riverstone, Bandon Road at Vineyard and Level Crossing Road at Vineyard

3. Reduce travel times between Windsor Road and Richmond Road

4. Reduce the number of through heavy vehicle movements through and near the Riverstone

Town Centre

5. Reduce congestion and delays across the Garfield Road railway level crossing at Riverstone.

6. Provide alternative routes to cross the Richmond railway line and improve traffic flow

efficiency and reduce delays during incidents

7. Provide a Strategy that caters for bus services across the region, contributes to increased bus

(and rail) travel mode shares and reduces the reliance on private vehicle travel as the

NWPLRA develops

8. Deliver benefits for pedestrians, cyclist and less mobile people in terms of accessibility,

connectivity, safety and amenity as part of the short, medium and long term Strategy

9. Enhance flood evacuation access across the NWPLRA consistent with SES flood evacuation

planning.

Page 17: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

17

2.3 Bandon Road project specific objectives

The Bandon Road upgrade is part of the medium-term work of the North West Growth Centre Road

Network Structure. The Bandon Road upgrade is required to accommodate travel across the

Richmond railway line generated by the forecast growth in the NWPLRA. The upgrade will:

1. Provide an important part of the road network within the NWPLRA to support the

Government’s urban land release strategy for the NWPLRA through the provision of increased

road capacity to meet existing and future traffic and transport growth

2. Provide the infrastructure necessary to ultimately close 2 existing railway level crossings

located at Bandon Road, Vineyard and Level Crossing Road, Vineyard

3. Reduce congestion caused by the existing Garfield Road railway level crossing at Riverstone

4. Reduce travel times between Windsor Road and Richmond Road and reduce congestion

across the Richmond railway line at Garfield Road.

2.4 Strategic context

The NWPLRA, which today has a population of around 5,000 residents, is forecast to accommodate

about 70,000 dwellings for around 200,000 residents and a workforce of about 40,000 over the next

20 to 30 years. Riverstone and its surrounding areas where the growth in resident and worker

populations is forecast to generate an increase in traffic to, from and through the area. The rise in

resident and worker population across the NWPLRA will be accompanied by increases in traffic

between now and full development of the NWPLRA. The existing road network will not be able to meet

the expected growth in transport demand. The NSW Government has responded with the release of

the North West Growth Centre Road Network Strategy for NWPLRA in November 2014 after

consultation with the community and stakeholders. The Strate gy was confi rmed in July 2015 and

identifies the need for five grade-separated crossings of the Richmond railway line north of Quakers

Hill Parkway at:

Bandon Road, Vineyard (currently a level-crossing of the Richmond railway line)

Garfield Road, Riverstone (currently a level-crossing of the Richmond railway line)

Schofields Road, Schofields (in progress as part of the Schofields Road upgrade project)

Westminster Street bridge, Schofields (existing with limited capacity)

Burdekin Road, Quakers Hill (planned).

After considering the community feedback and the general support for the North West Growth Centre

Road Network Strategy, Roads and Maritime is continuing to work with the community, stakeholders

and the Government to develop the individual projects that form part of the short, medium and long -

term proposed road network upgrades. This work includes:

Improving traffic flow within Riverstone Town Centre and access to Westminster Street bridge

Planning for a Bandon Road corridor between Richmond Road and Windsor Road (the

subject of this report), including the Bandon Road underpass of the Richmond railway line

Completing construction of Schofields Road between Windsor and Richmond roads by 2018,

which will link the Rouse Hill and Marsden Park town centres

Planning for the upgrade of Garfield Road between Richmond and Windsor roads

Planning for a grade-separated railway crossing along the Garfield Road corridor at

Riverstone.

Page 18: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

18

Roads and Maritime began consulting with the community on the installation of traffic lights at

Westminster Street and Railway Terrace intersection, and the Denmark Link Road project from

Garfield Road West to the Westminster Street bridge, in the second half of 2015.

2.4.1 Land use change across the NWPLRA

The NWPLRA is divided into 16 development precincts as shown in Figure 1.2. Development has

started in some of the precincts, and is at various stages of planning in the others. As at March 2016,

the Marsden Park and Marsden Park (Industrial) precincts have been rezoned, released and (partially)

developed. Another nine precincts have been rezoned and released for development. Collectively,

these precincts have planned to provide land for about 40,000 homes based on 2012 Bureau of

Statistical Analysis (BSA) data (formerly Bureau of Transport Statistics (BTS). Development in the

primarily industrial Riverstone West, Marsden Park Industrial, and Box Hill Industrial precincts targets

the creation of up to 38,000 jobs. Additional employment within the Riverstone precinct is targeted at

1,400 jobs. A further two precincts, Vineyard and Riverstone East, are expected to provide land for

about 7,800 additional homes.

Traffic and transport demand analyses undertaken to inform the North West Growth Centre Road

Network Strategy for the NWPLRA and the Bandon Road corridor selection process were based on

Bureau of Statistical Analysis (formerly Bureau of Statistics) supplied population and employment

forecasts, August 2012 Release. These differed in some cases from the Department of Planning and

Environment master plan job estimates, so changes were made to incorporate some increase in

employment and to assume population and employment forecasts increase by the same agreed

growth percentage of seven per cent. This equates to 2,045 jobs and 13,252 residents in excess of

the August 2012 Bureau of Statistical Analysis employment forecasts. Refer to Appendix 2 for more

detail.

2.4.2 Relevant transport goals, strategies and policies

The corridor selection and assessment process has been undertaken having regard to other strategy

and policy documents including those listed below:

State Priorities NSW Making It Happen (NSW Government, September 2015) –

In September 2015, the NSW Premier unveiled 30 priorities, including 12 “Premier Priorities”, for the

state to grow the economy, deliver infrastructure, protect the vulnerable, and improve health,

education and public services across NSW. The priorities will allow the government to measure and

deliver projects that create a stronger, healthier and safer NSW. The 30 State Priorities will be

measured against the best available indicators of economic growth, infrastructure delivery, service

provision and other measures of community wellbeing and safety across NSW.

Building Infrastructure – Improving road travel reliability

Infrastructure projects will be delivered on time and on budget across the state. The growing

population continues to place pressure on existing infrastructure. Over the next 15 years, NSW will

require infrastructure to support 40 per cent more train trips, 30 per cent more car trips and 31 per

cent more households.

Improving road travel reliability is a State priority with 90 per cent of peak travel on key routes to be on

time. Congestion across metropolitan Sydney is estimated to already cost up to $5 billion per annum,

and will rise to $8 billion by 2021 if nothing is done. To ensure consistency of journey times on key

roads continues to improve, the NSW Government is working to make better use of existing road

Page 19: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

19

infrastructure, build extra road capacity and encourage commuters to use public transport and to

undertake off-peak travel more often. This will enable business and the community to move around

the city with greater ease, reducing travel times, boosting productivity and reducing business costs.

The Bandon Road corridor is consistent with these priorities as it will enhance existing infrastructure,

reduce travel times and congestion and improve road user safety.

Safer Communities – Reducing Road Fatalities

The Government is committed to making NSW roads the safest in the country. Each year there are

42,000 recorded road crashes with more than 26,000 people injured in NSW. The aim is to reduce

road fatalities by 30 per cent from 2011 levels by 2021. Analysis has found that the Bandon Road

upgrade would reduce crashes when compared to a do-nothing case thereby reducing the probability

of injuries and fatalities.

Strong Budget and Economy – Encouraging Business Investment

The Government’s focus is to improve the ease of doing business in NSW, continue with historic level

if infrastructure investment and maintain fiscal discipline to provide certainty to business and improve

conditions. The Bandon Road upgrade will deliver freight benefits including improved travel times and

travel time reliability which in turn will result in improved business confidence and increased

commercial investment both within the region and along the corridor. Reducing vehicular traffic

through and near the Riverstone Town Centre will also improve local business confidence and town

centre viability.

State Infrastructure Strategy 2012-2032, (Infrastructure NSW, 2012) - The Strategy details the

State’s infrastructure needs for the next 20 years. The Strategy recognises that major arterial roads

across the greater Sydney region and Central Coast will require improvement to meet population

growth. The Bandon Road corridor is consistent with the Strategy in this regard.

A Plan for Growing Sydney, 2014 (Department of Planning and Environment) – The Plan

released in December 2014 seeks to “improve transport connections to provide better access between

centres in the subregion and centres in other subregions, particularly in the NWPLRA, and with regional

NSW, including freight connections.” (2014, p 120). The Bandon Road corridor is consistent with the

Plan.

NSW Long Term Transport Master Plan (Transport for NSW 2012) - This Plan establishes the

framework to guide transport decision making in NSW for the next 20 years, defining transport

priorities and funding to inform investment and decisions. The Plan outlines specific actions to

address the challenges of the Sydney region after consultation conducted in 2012. The Plan identifies

“Developing new transport connections for greenfield areas as they grow to support the North West

Growth Centre” as a transport challenge.

Sydney’s Cycling Future – Cycling for Everyday Transport (TfNSW 2013) - The document

includes a number of actions to promote and improve cycling which are relevant to the upgrade,

including the provision of appropriate bicycle facilities. The Bandon Road corridor is consistent with

this document, as it would most likely involve provision of bicycle facilities in the form of shared

pathways and compliant outer shoulders for breakdowns and on -road cyclists although these have yet

to be defined.

Roads and Maritime Services Strategy 2014 – 2018 – The four year strategy acknowledges that 63

per cent of all freight in the country passes through NSW. The document sets out Roads and

Maritime’s goals for the development of the Roads and Maritime networks. It acknowledges that the

freight task is forecast to double by 2031 and there is a need to upgrade key roads to accommodate

the movement of freight which has a large bearing on the productivity of the state.

Page 20: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

20

National Road Safety Strategy 2011-2020 (Australian Transport Council, 2011) - Aims to reduce

death and serious injury on Australian roads. A target of this Strategy is to reduce fatalities and

crashes by at least 30 per cent between 2011 and 2020. The upgrade works seek to reduce the

current annual crash rate by upgrading the road crossings and providing grade separation of

crossings.

NSW Road Safety Strategy (TfNSW, 2012) - The NSW Road Safety Strategy 2012-2021 sets

objectives for road safety in NSW for the decade commencing 2012. NSW is committed to reducing

fatalities to less than 4.3 per 100,000 population by 2016 together with at least a 30 per cent reduction

in fatalities and serious injuries by 2021. The upgrade work would contribute to crash rate reductions

through grade separation of the Richmond railway line.

North West Growth Centre - Bus Servicing Plan (TfNSW, 2012) – The document details the bus

servicing needs of the NWPLRA. Riverstone is a key interchange in the ‘long -term’ bus network, with

multiple proposed regional bus services operating through or to this town centre. The Bandon Road

corridor would be utilised by some of these services.

Connections: Towards 2017 (TfNSW, 2014) - TfNSW’s revised and updated corporate plan, the

document summarises the agency’s priorities for the period 2014 -2017. The upgrade is closely

aligned with Objective 4: A safer and more sustainable transport system, as it will support

sustainability through reduced greenhouse emissions, offer improved access to public and active

transport choices and embed safety considerations in the planning, development, delivery and

operation of the upgrade works. The Bandon Road corridor would also embed environmental

considerations in the planning, development and delivery of the proposed road upgrades.

Blacktown Local Environmental Plan, 1988 and Hawkesbury Local Environmental Plan, 2012 -

The Program work is located within both the Blacktown and Hawkesbury Local Government areas.

Under both LEP’s the Bandon Road corridor would be permitted without consent.

The upgrade is justified on the grounds that the work will support access to and from current and

future development within the NWPLRA. The work will reduce average travel times under forecast

traffic conditions.

2.5 Transport demand and analyses

This Options Report draws on outputs from traffic and transport analysis undertaken by Parsons

Brinckerhoff and documented in report entitled North West Growth Centre and Riverstone Corridor

Traffic Study – Options Assessment Report, 28 January 2015. That analysis was in part based on

mesoscopic traffic modelling (using AIMSUN software) used to test road network options

(combinations of railway line crossing alignments) and to inform the analysis of the relative merits of

alignment and network options. The analysis uses Bureau of Statistical Analysis data (formerly

Bureau of Transport Statistics) and DP&E land use data that assumes around 70,000 households, a

population of 200,000 people and 32,600 jobs within the wider study area for the assumed year of full

development, 2036. The analysis also considered the implications of a higher employment scenario

(52,500 jobs versus 32,600).

2.5.1 Traffic analyses

In the study area today, there are four railway crossings that accommodate general traffic access; the

Garfield Road level crossing, the crossing at Westminster Street bridge, the Bandon Road level

crossing and Level Crossing Road at Vineyard. Analysis shows that, four additional traffic lanes in

Page 21: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

21

each direction (a total of eight lanes) crossing the railway line are required between Vineyard and

south of Riverstone (between Bandon Road and north of Westminster Street) to efficiently

accommodate forecast traffic demand. This analysis took into account the existing two-lane bridge at

Westminster Street and the planned road crossings at Schofields Road and Burdekin/Townson

Roads. Four of these traffic lanes would be provided on Bandon Road.

Five grade separated railway crossings are proposed at Bandon Road, Garfield Road, Westminster

Street, Schofields Road and Burdekin/Townson Road as part of the North West Growth Centre Road

Network Strategy. Sections of the Schofields Road upgrade are under construction by Roads and

Maritime while the Burdekin/Townson crossing will be delivered by Blacktown City Council.

Today, the Garfield Road railway level crossing contributes to traffic congestion resulting in long

delays to traffic on either side of the Richmond railway line. These delays are forecast to increase with

the expansion of development and traffic volume increases across the NWPLRA. Heavy vehicles

experience delays at the level crossing because it is the only state road route and the principal heavy

vehicle route in the area. The proportion of heavy vehicles in Garfield Road West in 2014 was around

22 per cent and on Garfield Road East was around 13 per cent. The proportion of heavy vehicles in

Riverstone Parade was as high as 17 per cent and in Railway Terrace it was around 11 per cent.

With the short, medium and long term work in place, each of the road crossings of the Richmond

railway line are forecast to accommodate the following (two way) peak hourly traffic volumes by 2036

(Parsons Brinckerhoff, 2015):

Bandon Road: 1,870 and 1,510 veh/hr, AM and PM peaks, respectively.

Garfield Road: 2,540 and 2,380 veh/hr, AM and PM peaks, respectively.

Westminster Street: 170 and 130 veh/hr, AM and PM peaks, respectively.

Schofields Road: 2,690 and 2,540 veh/hr, AM and PM peaks, respectively.

Burdekin Road: 1,900 and 1,560 veh/hr, AM and PM peaks, respectively.

Quakers Hill Parkway: 4,050 and 3,900 veh/hr, AM and PM peaks, respectively.

Total across railway line: 13,220 and 12,020 veh/hr, AM and PM peaks, respectively.

Once grade separated, the railway crossing at Bandon Road is forecast to accommodate about 15 per

cent of total traffic peak hour traffic crossing the Richmond railway line in the area between Bandon

Road in the north and Quakers Hill Parkway in the south. That is, about 15 per cent of the 13,220

veh/hr referred to above. Parsons Brinckerhoff estimates (2015, Appendix G1) forecast that in 2036,

around 25 per cent of the eastbound AM peak volumes across the Richmond railway line on Bandon

Road would be heavy vehicles. In the PM peak the corresponding westbound heavy vehicle

proportion is forecast to be around 18 per cent. These forecast percentages assume that a heavy

vehicle restriction is in place at the Garfield Road grade separated crossing. The percentages are

high and reaffirm the importance of the Bandon Road crossing and corridor as an additional heavy

vehicle route with Schofields Road and Quakers Hill Parkway. These roads are forecast to

accommodate high heavy vehicle percentages in 2036, around 16 per cent and 14 per cent,

respectively.

In the medium term as transport demands increase, an additional grade separated crossing of the

Richmond railway line will be needed along the Bandon Road corridor. This crossing is strategically

positioned to accommodate through heavy vehicle movements while minimising impact upon nearby

residential areas and the Riverstone Town Centre.

Page 22: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

22

With the Bandon Road crossing in place, an additional grade separated crossing of the Richmond

railway line will be required further to the south along the Garfield Road corridor around the time the

NWPLRA reaches about 75 per cent of its remaining population and employment development,

estimated to occur after 2031.

Crash reduction and safety – In the 5 years between 2009 and 2013 there were 30 crashes along

Garfield Road within 500 metres either side of the level crossing. On Bandon Road near the level

crossing there were 7 crashes over the same period. Three (3) of these crashes were injury crashes

with no fatalities. Three were 3 rear end crashes. At the Westminster Street bridge there were 6

crashes during the 2009-2013 period, 4 of which were injury crashes with no fatalities.

The medium and longer term work would grade separate through traffic movements at key crossing

locations and reduce heavy vehicle traffic on Garfield Road near the Riverstone Town Centre with

consequent reductions in crash rates. Seven (or 23 per cent) of the 30 crashes between 2009 and

2013 involved a heavy vehicle. Casualty crashes per year are forecast to remain constant until the

opening of the grade separated crossing at Bandon Road and the reduction in heavy vehicle traffic on

Garfield Road at the level crossing.

Heavy vehicles and freight - The proportion of heavy vehicles in Garfield Road West in 2014 was

around 22 per cent and on Garfield Road East around 13 per cent. The proportion of heavy vehicles

in Riverstone Parade was as high as 17 per cent and in Railway Terrace it was around 11 per cent. In

the medium term with the introduction of the Bandon Road corridor between Richmond Road and

Windsor Road, there is expected to be a reduction in heavy vehicle numbers through the Riverstone

Town Centre. This is because the northern crossing of the Richmond railway line via Bandon Road

will accommodate some of these heavy vehicle movements reducing the numbers needing to cross

the railway line at Garfield Road. Parsons Brinckerhoff analysis (Table G1.2, 2015) shows that with

both the Bandon Road and Garfield Road grade separated crossings in place, heavy vehicle volumes

on Garfield Road could reduce by up to 180 veh/hr in the AM and 100 veh/hr in the PM between 2021

and 2036. Parsons Brinckerhoff (2015) analysis indicates that the Bandon Road underpass and

corridor offers heavy vehicle travel time savings compared to the 2036 Do Minimum scenario. For

vehicles travelling between Windsor Road and the M7 Motorway that would have otherwise had to

cross the railway line at Garfield Road travel time savings could be as high as eleven minutes.

2.5.2 Multi modal considerations

A road within the Bandon Road corridor will need to accommodate local and cross regional pedestrian

and cyclist access needs. This is most likely to take the form of a shared path on one but possibly

both sides of a carriageway built within the 43 metre wide road reservation.

Presently, buses (route service 661) service Vineyard Railway Station via Wallace and Bandon

Roads. There will be the need for the Bandon Road upgrade to accommodate peak and off peak

scheduled bus services as the West Riverstone, Marsden Park and Marsden Park North precincts

develop. The Bandon Road corridor will play an important role as a spine road providing bus access

to lower order roads servicing the residential areas across the precincts. There is also the possibility

that the corridor will also need to accommodate cross regional services linking to stations on an

extended Sydney Metro Northwest rail link.

Page 23: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

23

2.5.3 Other considerations

There are a range of other considerations that have been taken into account in the options

assessment and selection process. These include constructability, archeological site impact,

construction timing, and environmental impact assessment considerations.

2.6 Summary

The key messages in Chapter 2 are as follows:

1. The Bandon Road upgrade and grade separated crossing of the Richmond railway line are

needed to accommodate forecast growth in traffic across the region and to lessen congestion

at the Garfield Road level crossing as the NWPLRA develops

2. By 2036 around eleven lanes (in the peak direction) would be required to accommodate

forecast demand. Four of these eleven lanes will be provided by the Bandon Road corridor

3. Once grade separated, the railway crossing at Bandon Road is forecast to accommodate

around 15 per cent of total traffic peak hour traffic crossing the Richmond railway line in the

area between Bandon Road in the north and Quakers Hill Parkway in the south. That is,

around 15 per cent of 13,220 veh/hr

4. With both the Bandon Road and Garfield Road grade separated crossings in place, heavy

vehicle volumes on Garfield Road could reduce by up to 180 veh/hr in the AM and 100 veh/hr

in the PM

5. The Strategy provides for Bandon Road to be upgraded and extended to link Windsor and

Richmond Roads after 2021. The exact timing is dependent upon population and employment

growth across the NWPLRA and subject to funding availability

6. The Bandon Road corridor extends across multiple NWPLRA precincts including the West

Riverstone, Marsden Park North, Vineyard and Riverstone precincts

7. The Bandon Road upgrade is consistent with the State Priorities NSW Making It Happen

(NSW Government, September 2015) unveiled by the NSW Premier in 2015

8. The transport analysis underpinning the Strategy and the Bandon Road upgrade is based on

2012 Bureau of Statistical Analysis data (formerly Bureau of Trans port Statistics). The

forecasts assumed about 70,000 households, a population of 200,000 people and 32,600 jobs

within the NWPLRA at full development. The Strategy analysis also considered the

implications of higher employment scenarios

9. The Bandon Road grade separated crossing of the Richmond railway line will help in relieving

traffic volumes using the Garfield Road railway crossing with consequent reductions in

crashes.

Page 24: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

24

3 COMMUNITY AND STAKEHOLDER

CONSULTATION

3.1 Community involvement

Government agencies have examined numerous options for the Riverstone railway crossing since

before 1995. In October 2012, Transport for NSW (TfNSW) announced the Garfield Road overpass as

a preferred grade separated solution to replace the existing Garfield Road railway level crossing. After

further consultation with Blacktown City Council, the Minister for Roads and Freight advised that any

alternatives that demonstrated similar transport and cost outcomes to the preferred option would also

be considered. In November 2013, Roads and Maritime published a community consultation report

summarising the project history and identified two viable options for community consultation:

A new four-lane road overpass on the existing alignment of Garfield Road. This would require

widening of Garfield Road to the south outside the current road reservation

A new four- lane road overpass at Castlereagh Street.

This Community Consultation Report also included the assessment of a rail way crossing aligned with

Loftus Street. The report concluded that due to the impact and constraints of this option, the Garfield

Road and Castlereagh Street options were recommended for further investigation. Community

consultation was subsequently undertaken by Roads and Maritime from November 2013 to February

2014, with the intention of obtaining feedback to help in the development and selection of a preferred

option. After this community consultation it was decided to review the grade separated railway

crossing needs, preferred locations and possible timings of road crossings over the Richmond railway

line having regard to the updated development program across the NWPLRA. This investigation was

undertaken during 2014. Parsons Brinckerhoff undertook the transport analyses in support of the

investigation and documented its findings in the North West Growth Centre and Riverstone Corridor

Traffic Study – Options Assessment Report, 28 January 2015.

Agency and stakeholder consultation was facilitated by Roads and Maritime during the preparation of

the North West Growth Centre Road Network Strategy for the NWPLRA. The key community

interactions in the 2014-2015 period included:

1. Release of the Community Update – Proposed Road Network Strategy for NWGC in

November 2014

2. Release of the North West Growth Centre and Riverstone Corridor Traffic Study Summary

Report, November 2014

3. Distribution of the Community Update – Proposed Road Network Strategy for NWGC to an

area covering Riverstone, Vineyard and Marsden Park North and Marsden Park and a

broader section of the NWPLRA in November 2014. Roads and Maritime received twenty

three comments in response to the North West Growth Centre Road Network Strategy that

was publicised to the community in the November 2014. These responses were analysed,

reviewed and responded to in a community consultation report issued in July 2015. The

twenty three comments were received in response to a consultation involving the distribution

of around 17,000 copies of the community update within and surrounding the NWPLRA

4. Four community information sessions held in November 2014 by Roads and Maritime in

support of the public exhibition of the Strategy

Page 25: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

25

5. Door knocking of directly affected local residents in Riverstone and Vineyard during November

2014 including:

- Garfield Road businesses and some residences between Riverstone Parade and

Piccadilly Street

- Residences on Castlereagh Street between Oxford Street and Railway Terrace.

- Loftus Street businesses

- Bandon Road properties

- Camberwell Road properties

- Wallace Road properties between Bandon Road to about 600 metres to the north

of Bandon Road.

6. Information provided on the Roads and Maritime web page to enable interested parties to

keep abreast of project development

7. Notification in relation to proposed geotechnical work at the intersection of Westminster Street

and Railway Terrace, March 2015

8. Release of Community Update – Confirming Road Network Strategy for NWGC in July 2015

9. Have your say notification about the proposed traffic signals at the intersection of Westminster

Street and Railway Terrace, July 2015

10. Have your say community update for Denmark Link Road in November 2015

11. Westminster Street and Railway Terrace Intersection Upgrade, Schofields North West Growth

Centre Short Term Traffic Improvement Projects – Community Consultation Report, January

2016.

Community consultation in relation to the preferred Bandon Road corridor addressed in this report will

be initiated as part of the release of this document.

Table 3.1 – Public consultation since November 2014 Strategy public exhibition

DATE ACTION / PUBLIC DOCUMENT

November 2014 Announced proposed North West Growth Centre Road Network Strategy.

Distributed community update throughout NWPLRA. Door knocking

across Riverstone, Vineyard and Riverstone West precinct

November 2014 Four community information sessions

March 2015 Notification in relation to proposed geotechnical works

July 2015 Confirmation of North West Growth Centre Road Network Strategy for

the NWPLRA

July 2015 Proposed new traffic lights at the intersection of Westminster Street and

Railway Terrace, Schofields. Have your say notification letter delivered

November 2015 Community update for Denmark Link Road including door knock and two

information sessions.

3.2 Government agency and stakeholder involvement

Consultation with local Councils and other Government agencies has been ongoing since early 2014

and the setting up of the Riverstone Working Group meetings by Roads and Maritime. Blacktown City

Council and Hawkesbury City Council were closely involved with the Parsons Brinckerhoff Studies

(North West Growth Centre and Riverstone Corridor Traffic Study – Options Assessment Report, 28

Page 26: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

26

January 2015 and North West Growth Centre and Riverstone Corridor Traffic Study – Interim Traffic

Management Measures Report, February 2015) and Strategy development from its inception in early

2014. Council officers attended the Working Group meetings and Value Management workshops in

2014.

During 2015 Roads and Maritime continued to hold discussions with DP&E, Councils, Utility providers

and other key stakeholders within the NWPLRA in relation to the Bandon Road corridor options.

A Bandon Road corridor Value Management workshop was held on 17 December 2015 to select a

preferred corridor from fourteen options. Option M was selected as the preferred corridor.

3.3 Other involvement

During and after the announcement of the Strategy, Road and Maritime has held discussions with

utility authorities to work out strategies for dealing with major work impact on their assets. Some face

to face meetings have been held with property owners whose properties are either fully or partially

impacted by the Strategy.

Roads and Maritime proposes to seek comment on the preferred alignment corridor. Comments

received will be considered as part of the proposal development process. Further consultation will be

carried out in future inviting the community to provide comments on the concept design and the

Review of Environmental Factors (REF).

3.3.1 Stakeholders consulted

Government agency consultation has occurred throughout the development of the North West Growth

Centre Road Network Strategy for NWPLRA and more recently for the Bandon Road corridor options

selection process. In the 2014 / 2015 period, primarily as part of the development of the North West

Growth Centre Road Network Strategy, Roads and Maritime actively sought the views of the following

stakeholders. These stakeholders have also been involved in the development of the preferred

corridor for Bandon Road:

Department of Planning and Environment

Transport for NSW

NSW Member for Riverstone

Blacktown City Council and Hawkesbury City Council

Sydney Trains

State Emergency Services

Utility providers (Ausgrid, Jemena, Endeavour Energy, Telstra, Sydney Water)

3.3.2 Continued consultation with wider stakeholder group

The following stakeholders have been identified as having potential interest in the upgrade proposal:

NSW Department of Planning and Environment

Sydney Catchment Authority

Transport for NSW

Blacktown City Council

Hawkesbury City Council

The Hills Shire Council

Page 27: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

27

Environmental Protection Authority and the Office of Environment and Heritage

The local Aboriginal Community

Emergency Services

Optus, Telstra, Jemena, Endeavour Energy, TransGrid (including Bandon Road Substation)

Roads and Maritime Services

Sydney Trains

Local community.

3.4 Summary

The key messages in Chapter 3 are as follows:

1. Agency and community consultation in relation to the crossings of the Richmond railway line

has been facilitated by TfNSW and Roads and Maritime for several years. Most recently

Roads and Maritime has sought the views of various stakeholders in the development of the

North West Growth Centre Road Network Strategy for NWPLRA. The Strategy was

announced in late 2014 and confirmed in July 2015

2. Consultation with local Councils and other Government agencies has been ongoing since

early 2014 and the setting up of the Riverstone Working Group meetings by Roads and

Maritime

3. A Value Management workshop was held on 17 December 2015 to review the corridor options

for Bandon Road between Richmond Road, Marsden Park and Windsor Road, Vineyard.

Roads and Maritime sought feedback from key stakeholders at this workshop. The agencies

represented at the Workshop included DP&E, Roads and Maritime, The Hills Shire Council,

Blacktown City Council, Hawkesbury City Council, TfNSW, Trans Grid and the NSW Member

for Riverstone

4. Roads and Maritime proposes to seek comment on the preferred Bandon Road corridor.

Comments received will be considered as part of the proposal development process. Further

consultation will be carried out in the future by inviting the community to provide comments on

the concept design and the Review of Environmental Factors (REF).

Page 28: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

28

4 CORRIDOR OPTION IDENTIFICATION AND

ASSESSMENT

4.1 North West Growth Centre Road Network Strategy

Roads and Maritime worked with key stakeholders to develop the North West Growth Centre Road

Network Strategy. The Bandon Road corridor between Richmond Road, Marsden Park and Windsor

Road, Vineyard was identified as part of this Strategy. This Strategy was released in November 2014

and confirmed in July 2015. Refer to Figure 1.3 for the North West Growth Centre Road Network

Strategy.

4.2 The Bandon Road corridor options

Roads and Maritime continued to work with key stakeholders after the release and confirmation of the

North West Growth Centre Road Network Strategy in order to identify a preferred Bandon Road

corridor. A Value Management workshop was held on 17 December 2015 to review and assess

fourteen (14) options that were developed based on stakeholder feedback. Refer to Figure 4.1 for the

options that were developed. The agencies represented at the Workshop included the Department of

Planning and Environment (DP&E), Roads and Maritime, The Hills Shire Council, Blacktown City

Council, Hawkesbury City Council, TfNSW, TransGrid and the NSW Member for Riverstone. These

options included:

1. Option A – (or A2) the initial Roads and Maritime corridor alignment option

2. Option B – variation on option A with modified eastern alignment running to the south of the

Riverstone Sewage Process Plant and Pacific Power Substation

3. Option C – northernmost alignment running outside West Riverstone precinct intersecting with

Richmond Road at Precinct Road A

4. Option D – northern alignment running outside West Riverstone precinct intersecting with

Richmond Road at Precinct Road A

5. Option E – northern alignment running outside West Riverstone precinct intersecting with

Richmond Road at Precinct Road B

6. Option F – central alignment running inside West Riverstone precinct and along Park Road

intersecting with Richmond Road at Precinct Road B

7. Option G – central alignment running inside West Riverstone precinct with western alignment

north of Option E and intersecting with Richmond Road at Precinct Road B

8. Option H – central alignment with eastern section similar to Option L, western section similar

to Option E and a modified central section. Intersects with Richmond Road at Precinct Road

B

9. Option I – variation on Option H with modified central section further to the south

10. Option J – central alignment with eastern section similar to Option L but with modified central

and eastern sections. Intersects with Richmond Road at Precinct Road B

11. Option K – variation on Option J with modified western section slightly to the south

12. Option L – central alignment via Park Road reservation and intersecting with Richmond Road

at Precinct Road B

Page 29: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report 29

13. Option M – central alignment via Park Road reservation but intersecting with Richmond Road

at Precinct Road A

14. Option N – variation on Option L with modified eastern section north of the transmission lines

and intersecting with Richmond Road at Precinct Road B.

The criteria used in the selection and assessment of a preferred corridor was as follows:

Consistent with NWPLRA Road Network Strategy

Minimises flood effect within the Eastern Creek, South Creek and Wianamatta Creek

floodplain

Uses the existing topography to minimise earthworks required by Bandon Road

Encourages road-based public transport utilisation, and connection to other public transport

modes

Allows for the use of Bandon Road to serve as a spine road rather than a boundary road

Connect residential and employment zones land uses within the NWPLRA

Provide a value for money alignment for the NSW Government

Connects with a previously identified intersection in Marsden Park precinct

Facilitates potential to space intersections at appropriate intervals to serve the nearby land

Encourage public transport utilisations from both sides of Bandon Road

Improves accessibility

Provides suitable connectivity between Marsden Park North Precinct, Vineyard, and

Riverstone West precincts

Provides suitable connectivity to NWPLRA precincts

Facilitates connection beyond NWPLRA

Promotes active transport connectivity.

Page 30: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

30

Figure 4.1 – Bandon Road Options assessed at value management workshop, December 2015

Page 31: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

31

4.3 Constraints and opportunities

4.3.1 Landform, geology and soils

The topography comprises gently undulating rises, accompanied by a flat to gently sloping alluvial

plain and flat terrace tops. The topography has been locally modified in places. The area is underlain

by Bringelly Shale, comprising shale, claystone, laminate and sandstone. All nearby creeks are

underlain by quaternary alluvium comprising fine-grained sand, silt and clay.

The area is located within the largely fluvial soils landscapes of the South Creek Group, Berkshire

Park Group and the Blacktown Group. According to the Australian Soil Resource Information System

(ASIRS) the probability of encountering acid sulphate soils (ASS) is considered low to extremely low.

There is no clear correlation of salinity and soil type across the study area.

The previous and current land use in the study area is likely to present a low contamination risk for

future development. This conclusion is consistent with the assessment made of other areas of the

NWPLRA, insofar that ground conditions ‘are unlikely to impose significant constraints in the design

and construction of road [infrastructure]’ (Roads and Maritime Services, 2013).

4.3.2 Hydrology and flooding

There are four principal surface water features in the area, Eastern Creek, Bells Creek (a tributary of

Eastern Creek), First Ponds Creek and a small unnamed creek just to the east of Richmond Road. All

run north south and form part of the wider Nepean catchment. Development controls prevent any

further degradation of the Creeks’ significant habitat and recreational values. These controls include

limitations on land-use density, water quality controls and restrictions on the degree to which

impervious areas are directly connected to the creeks (Parsons Brinckerhoff, 2015).

Regional groundwater is considered to be at a significant depth, about 20 metres below ground level.

More localised perched groundwater or water bearing zones are anticipated in the lower lying areas

along all four creeks. In these areas, groundwater could be experienced at less than three metres

below the existing ground level during flooding. The groundwater depths can be confirmed by

reviewing registered bores. However, a review of bores to the west undertaken for the North of

Grange Avenue to South Creek Floodplain REF confirmed groundwater at depths ranging from 2.4

metres (perched groundwater) to 20 metres (Roads and Maritime, 2013).

4.3.3 Biodiversity

Biodiversity information obtained thus far in the options assessment process has been limited to a

consideration of the existing vegetation. The NWPLRA has been biodiversity certified, although there

are areas where the certi fication does not apply. All of the Bandon Road corridor options cross non -

certified land.

Parsons Brinckerhoff (2015) note that the study area falls within the Sydney Basin Bioregion on the

Cumberland Plain between Marsden Park and Riverstone. Although highly -fragmented and likely

disturbed from previous developments, the vegetation and communities within the study area are

diverse. They include a mix of remnant native vegetation, dis turbed vegetation and more recent exotic

tree planting (planted vegetation). Noteworthy stands of endangered ecological communities (EEC)

Page 32: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

32

can be found, including large areas of intact Cumberland Plain Woodland to the north and south of

Loftus Street and Garfield Road West.

Broad scale vegetation mapping of the study area was undertaken by NSW National Parks and

Wildlife Service in 2002. At the time of publication this showed there to be six vegetation communities

present within the study area; four threatened ecological communities (TECs) and three EECs. The

development of the NWPLRA during the period since the mapping was prepared means that these

communities are likely to be less-well represented in the study area.

Roads and Maritime would be bound to the provisions of the NSW Threatened Species Conservation

Act 1995 and Commonwealth Environment Protection Biodiversity Conservation Act 1999 if

developing any of this land (if it is not already developed). It may also be bound to additi onal

conditions relating to the need to prepare management plans, recovery plans or threat abat ement

plans; obtain approval from NSW Office of Environment and Heritage (OEH) before clearing the land;

and/or the need to survey the land for the presence of Green and Golden Bell Frog.

There is no statutory requirement for Roads and Maritime to assess the impact of the options on any

TECs / EECs located on biodiversity certified land. Roads and Maritime is however committed to

mitigating impact on threatened or endangered communities that has been covered by the certification

process.

Photograph 1 – Looking east along Bandon Road at railway level crossing, December 2015

The Bandon Road Preliminary Environmental Investigation concluded that the main environmental

issues associated with the study area were identified as the potential for direct and indirect (visual /

setting) impact on items of historic heritage, although none of the corridor options currently under

consideration would directly affect known items. Potential impact on threatened ecological

communities listed under the TSC Act and the EPBC Act, noting most of the threatened ecological

communities potentially affected by the options corridors are in biocerti fied areas. Development of

Page 33: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

33

roads on biocerti fied lands should consider impact on threatened species, populations, endangered

ecological communities, but will not require a threatened species assessment and a Species lmpact

Statement under the EP&A Act and TSC Act. Referral, assessment or approval under the EPBC Act

will also not be required in relation to biocertified lands. Potential for direct impact on Key Fish Habitat.

Potential impact on existing surface flow patterns and potential changes to the flooding regime.

Potential for erosion and sedimentation during construction. Potential for air quality impact during

construction and operation. Construction and operational noise impact on noise sensitive receivers.

Positive and negative socio-economic effects due to changes in traffic routes.

4.3.4 Other considerations

Noise

Ambient and background noise levels have not been measured across the study area. Parsons

Brinckerhoff (2015) advise noise monitoring was conducted close to the Richmond Road / Garfield

Road West junction as part of the North of Grange Avenue to South Creek Floodplain REF (Roads

and Maritime, 2013). This confi rms the existing baseline noise environment is reasonably influenced

by road traffic noise, especially during the daytime. The Bandon Road Preliminary Environmental

Investigation recommends a construction and operational noise assessment be undertaken during the

detailed environmental assessment stage.

Heritage

A review of the Aboriginal Heritage Information Management System (AHIMS) undertaken during

2014 by Parsons Brinckerhoff confirms there were around 36 recorded sites within the Strategy study

area. The study area lies within a landscape that was important to, and intensively used by, Aboriginal

people in the past. The greatest areas of Aboriginal archaeological potential are anticipated to be

along the river corridors of First Ponds Creek, Bells Creek, South Creek and Eastern Creek. The

potential will be greatest where these areas have not been previously disturbed.

The area has been used for pastoral agricultural purposes since European settlement. A review of

Commonwealth, State and Local registers confirm there to be two items of State significance and 23

items of local significance within the study area. The most important items are:

Windsor Road and Old Windsor Road Precinct (listed on the Roads and Maritime Heri tage

and Conservation Register)

Riverstone Railway Station (listed on the State Heritage Register).

Land use

Existing land use zoning is covered by the Blacktown City Council and Hawkesbury City Council

LEPs. Future land use zoning for the NWPLRA (West Schofields, Riverstone West, Riverstone,

Riverstone East and Marsden Park North) is set out in the SRGC SEPP.

Current key land uses comprise:

1(a) General Rural

2(a) Residential

4(a) General Industrial

5(b) Special Uses (Arterial Road and Arterial Road Widening)

5(c) Special Uses (Local Road and Local Road Widening).

Page 34: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

34

The key future proposed zones include:

B7 Business Park

E2 Environmental Conservation

IN1 General Industrial

IN2 Light Industrial

R2 Low Density Residential

RE1 Public Recreation

SP2 Infrastructure (Classified Road and Local Road Widening).

Roads and Maritime is able to progress the development of road infrastructure work under clause 94

of the State Environmental Planning Policy (Infrastructure) 2007 (ISEPP). The provisions of other

planning instruments do not typically apply in favour of the ISEPP as is the case with the Blacktown

and Hawkesbury LEPs and the SRGC SEPP.

The SRGC SEPP defines the zoning that will apply to the area once the growth centres are

developed. Each of the above future zoning allocations has its own focus (e.g. industry, recreation,

residential, business, environmental conservation) they identify development that is permitted and

development that is prohibited. In the case of roads they are permit ted to be developed across all

zones as it is recognised that road development is needed to service development. As such, the

construction of new road(s) along the Bandon Road corridor would be consistent with the future land

use zonings within the NWPLRA.

The upgrade options will reduce available land, the most sensitive uses in this regard is the land set

aside for environmental conservation and public recreation. This inc ludes land parallel and next to

Eastern Creek (environmental conservation) and Christian college (recreation).

Road network planning and hierarchy

The Marsden Park precinct is located on the western side of Richmond Road. The Indicative Layout

Plan (ILP) for the Marsden Park precinct shows three east -west internal precinct roads have an

intersection with Richmond Road. For the purpose of this report these are referred to as Precinct

Roads A, B and C. Refer to Figure 4.2. Precinct Road A is the northernmost road with Elara

Boulevard (Precinct Road B) located further to the south. Precinct Road C is in effect an extension of

Garfield Road to the west of Richmond Road, although the classification of the road internal to the

Marsden Park precinct is at this stage unknown. It is anticipated it will be a higher order road though

not necessarily a classified arterial road. An important criterion in the assessment of the options is the

point at which the extended Bandon Road intersects with Richmond Road. This criteria has two

elements, the first being the compatibility of that point of intersection with the road system internal to

the Marsden Park precinct. The second, achieving an acceptable separation (distance) along

Richmond Road between this proposed point of intersection and the existing (and upgraded)

intersection of Richmond Road and Garfield Road. Refer to criteria in Table 4.1.

The functional classification (including total lane numbers) of the Marsden Park internal precinct roads

has yet to be confirmed. The optimal location for a new four way intersection on Richmond Road in

terms of arterial traffic flow efficiency and intersection spacing is at either Precinct Road A or Elara

Boulevard (New Precinct B). The ILP shows an indicative school site on Precinct Road A to the west

of Richmond Road. In this regard, it would be preferable to avoid routing through traffic from a

Bandon Road extension through to Precinct Road A. A Bandon Road / Richmond Road intersection

further to the south at Precinct Road B would therefore be the optimal intersection location. It would

still be located around one kilometre north of the Garfield Road intersection and would be acceptable

from a strategic arterial road development perspective.

Page 35: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

35

Electricity easements and other utilities

There are three existing TransGrid (or other) electricity transmission line easements running north -

south through the study area. All have a north south orientation. A 60 metre wide easement traverses

the northern sector of the Marsden Park North precinct while two parallel easements (one 60 metres

wide and the other 80 metres wide) traverse the central sector and also impact the West Riverstone

precinct. A photograph looking west from Riverstone Parade across Eastern Creek shows some of

the TransGrid utilities, as in Photograph 2. There is also an existing east-west running Endeavour

Energy easement along Bandon Road as shown in Photograph 3.

Page 36: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

36

Figure 4.2 – Marsden Park Precinct Roads A, Elara Boulevard (B) and C

Page 37: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

37

Photograph 2 – Looking west along TransGrid easement from Riverstone Parade, December

2015

Photograph 3 – Looking west along Bandon Road near Substation, December 2015

Page 38: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

38

4.4 Bandon Road corridor assessment and selection

The Bandon Road corridor identification and assessment process has occurred in two broad stages:

1. Route selection process for the North West Growth Centre Road Network Strategy - Pre North

West Growth Centre Road Network Strategy announcement - The Bandon Road alignment

options identification and assessment process undertaken as part of the development of the

Road Network Strategy for NWPLRA

2. Selection of preferred Bandon Road corridor - Post North West Growth Centre Road Network

Strategy announcement - Options identification, refinement, and assessment underway

subsequent to the exhibition of the abovementioned Strategy and now forming the basis of

this report.

The corridor selection process is summarised in Figure 4.3 overleaf.

4.4.1 North West Growth Centre Road Network Strategy route selection

process for Bandon Road

During 2014 Roads and Maritime Services consulted with stakeholders to develop route options for

crossing locations of the Richmond railway line that were used to prepare the North West Growth

Centre Road Network Strategy. Two value management workshops were held as part of the

development, selection and assessment process for crossing options.

The investigations leading up to the exhibition of the Strategy are documented in two reports:

1. A January 2015 Parsons Brinckerhoff report entitled North West Growth Centre and

Riverstone Corridor Traffic Study – Options Assessment Report, 28 January 2015.

2. A February 2015 Parsons Brinckerhoff report entitled North West Growth Centre and

Riverstone Corridor Traffic Study – Interim Traffic Management Measures Report.

Mesoscopic traffic modelling (using AIMSUN software) was used to test road network options

(combinations of railway line crossing alignments) and to inform the analysis of the relative m erits of

each option. The options were developed based on the volume-capacity analysis, traffic flow

efficiency, connection to town centres and employment areas, provision for heavy vehicles and

provision for an efficient bus network.

Multi-criteria analysis was undertaken as part of the assessment of crossing option to inform the North

West Growth Centre Road Network Strategy for the NWPLRA. This analysis concluded alignment

option A2 (Bandon Road Extension) was a preferred corridor and recommended for more detailed

assessment. The new option extended Bandon Road westwards so it:

Continues past the sewage treatment plant and electricity substation

Crosses Eastern Creek at a location where the existing topography would mean reduced

earthworks

Joins Richmond Road at a new intersection currently proposed with Richmond Road that is

identified in current Marsden Park precinct planning for Marsden Park.

Page 39: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

39

Dec 2015 - Value Management Workshop: Option M identified as preferred Bandon

Road option.

2015 - Bandon Road options identified in consultation with agencies.

July 2015 - Road Network Strategy for North West Growth Centre confirmed.

Nov 2014 - North West Growth Centre Road Network Strategy released for public

comment.

2014 - A northern option along the alignment of Bandon Road identified as preferred corridor for North West Growth

Centre Road Network Strategy (Option A2)

2014 - Broad options assessed at Value Management Workshop

2014 - Desktop review identifies shortlisted railway crossing and alignment options

north and south of Riverstone Town Centre

Figure 4.3 – The Bandon Road Corridor Selection Process

Page 40: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

40

A comparison of the three Bandon Road alignment options (A, A1 and A2) was carried out and

concluded:

Alignment A has higher impact on a non-classified riparian corridor and threatened ecological

communities

Alignments A and (to a lesser extent) A1 rely on delivery of the Spine Road within the

Riverstone West Precinct

Alignment A2 would reduce noise impact by accommodating traffic remote from future

residences on Riverstone Parade

Alignments A1 and A2 have slightly better economic justification than Alignment A

Alignments A1 and A2 attract more traffic to the Bandon Road crossing

Alignment A2 provides the greatest amount of traffic relief to the southern crossings.

Alignments A, A1 and A2 are shown in Figure 4.4 overleaf.

Page 41: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

41

Figure 4.4 – Alignment Options A, A1 and A2 identified in 2014 (pre-Strategy announcement)

Page 42: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

42

4.5 Options assessment

4.5.1 Assessment criteria

The criteria used in the assessment and comparison of corridor options is summarised in Table 4.1

below.

Table 4.1 – Bandon Road Upgrade Corridor Assessment Criteria

NO. CRITERIA DESCRIPTION

1 Consistency with Roads

and Maritime Road

Network Strategy for

NWPLRA

Facilitates east-west connections between Windsor Road

and Richmond Road

Provides an alternative route (to Garfield Road West) east-

west route across the Richmond railway line

Accommodates 43m wide road (reservation) corridor

2 Minimises flood effect

within the Eastern

Creek, South Creek and

Wianamatta Creek

floodplain

Alignment minimises reliance on landfill by landowners within

Marsden Park North precinct

Avoids landfill in flood flow areas

3 Uses the existing

topography to minimise

earthworks required by

Bandon Road

Alignment minimises cut and fill and achieves a favourable

cut and fill balance

4 Encourages road-based

public transport

utilisation, and

connection to other

public transport modes

An alignment that minimises bus route kilometres

An alignment that facilitates access to and interchange with

Richmond railway line railway stations and future Sydney

Metro Northwest stations

5 Allows for the use of

Bandon Road to serve

as a spine road rather

than a boundary road

Location serves the wider Marsden Park North precinct

Complements areas with access to Garfield Road West

linking to Riverstone

Provides opportunities for connections within the Marsden

Park North precinct

6 Connect residential and employment zones land

uses within the NWPLRA

Facilitates efficient intra and inter precinct transport between

residential and employment zones

7 Provide a value for

money alignment for the NSW Government

An alignment that could be delivered at minimal cost to the

Government and Community while maximising benefits

realisation

Page 43: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

43

NO. CRITERIA DESCRIPTION

8 Connects with a

previously identified

intersection in Marsden

Park precinct

Aligns with planned collector road serving Marsden Park

North

9 Facilitates potential to

space intersections at

appropriate intervals to

serve the nearby land

Maximises separation between intersections with traffic lights

along Richmond Road

10 Encourage public

transport utilisations from both sides of

Bandon Road

An alignment that will enable cost effective feeder bus access

to precincts as they develop to the north and south of the

corridor

11 Improves accessibility An alignment that facilitates efficient multi modal accessibility

to and from NWPLRA precincts

12 Provides suitable

connectivity between

Marsden Park North,

Vineyard, and

Riverstone West

precincts

Connects and facilitates access between local precincts

13 Provides suitable

connectivity to NWPLRA

precincts

Connects and facilitates access between precincts across

broader NWPLRA

14 Facilitates connection

beyond NWPLRA

An alignment that accommodates cross regional travel

including public transport and heavy vehicles

15 Promotes active

transport connectivity

An alignment that facilitates pedestrian and cyclist access on

likely future desire lines.

4.5.2 Options evaluation against the criteria

The initial assessment and comparison of the fourteen options was undertaken against the criteria. A

summary of these findings is provided in Table 4.2. After this initial review a first round cull of the

various options was undertaken at the December 2015 Value Management workshop which resulted

in the selection of Option M as the Bandon Road preferred corridor. A summary of the outcomes of

this cull process is provided in Table 4.3.

Page 44: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

44

Table 4.2 – Corridor Option Assessment and Comparison

Op

tio

n

Topography / Flooding Land use If structure is above 1 in 100 flash and backwater

Co

nstr

ucta

bilit

y a

nd

ris

ks

Road function

W ithin Riverstone W est and

Vineyard precinct

W ithin Marsden

Park North precinct

W ithin Riverstone W est and

Vineyard precinct

W ithin Marsden

Park North precinct

Across Eastern

Creek

W ithin

Marsden Park North potential earthwork

s areas

Valu

e fo

r m

on

ey

Co

nn

ects

wit

h a

pre

vio

usly

id

en

tifi

ed

in

ters

ecti

on

in

Mars

den

Park

p

recin

ct

Po

ten

tial

to s

pace in

ters

ecti

on

s at

ap

pro

pri

ate

in

terv

als

to

serv

e th

e n

earb

y

lan

d

En

co

ura

ge p

ub

lic t

ran

sp

ort

uti

lisati

on

s

fro

m b

oth

sid

es o

f B

an

do

n R

oad

Imp

roves accessib

ilit

y

Co

nn

ecti

vit

y

betw

een

M

ars

den

Park

N

ort

h P

recin

ct,

V

ineyard

, an

d R

ivers

ton

e

West

pre

cin

cts

Pro

vid

es su

itab

le co

nn

ecti

vit

y t

o N

WP

LR

A

pre

cin

cts

Facilit

ate

s co

nn

ecti

on

beyo

nd

NW

PLR

A

Acti

ve t

ran

sp

ort

co

nn

ecti

vit

y

A

Sits separate to the existing terrain

requiring large volumes of fill or extensive

bridge length to link between Riverstone West and

Marsden Park North precincts

Reliant on earthworks being completed

or additional fill earthworks required to

contain road within the Marsden Park North

precinct.

Avoids negatively impacting high value

developable area in Riverstone West precinct

Serves a limited area on northern side of

proposed road alignment than some other options

>1200m bridge or extensive fill

earthworks across Eastern Creek.

Additional length of around 880m fill

with culverts required beyond the fill

proposed by the fill required by the proponents

of Marsden Park North precinct.

Requires earthworks platforms for Marsden Park

North to have been undertaken by precinct proponents

otherwise location requires earthworks or structure.

Multiple crossings of electricity easements.

Limited due to length of structure

across Eastern Creek and potential

flood mitigation measures required to cross

the 1% AEP flash and backwater flood

zone

Yes Point of intersection on

Richmond Road is at New Precinct Street A.

Yes Maximises separation between

signalised intersections along Richmond Road.

Yes Alignment passes through

the centre of the Marsden Park North

precinct.

Yes Yes Yes Yes Yes Alignment passes through the

centre of the Marsden Park North precinct.

Page 45: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

45

Op

tio

n

Topography / Flooding Land use If structure is above 1 in 100 flash and backwater

Co

nstr

ucta

bilit

y a

nd

ris

ks

Road function

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

Across

Eastern Creek

W ithin Marsden

Park North potential earthwork

s areas

Valu

e fo

r m

on

ey

Co

nn

ects

wit

h a

pre

vio

usly

id

en

tifi

ed

in

ters

ecti

on

in

Mars

den

Park

p

recin

ct

Po

ten

tial

to s

pace in

ters

ecti

on

s at

ap

pro

pri

ate

in

terv

als

to

serv

e th

e n

earb

y

lan

d

En

co

ura

ge p

ub

lic t

ran

sp

ort

uti

lisati

on

s

fro

m b

oth

sid

es o

f B

an

do

n R

oad

Imp

roves accessib

ilit

y

Co

nn

ecti

vit

y

betw

een

M

ars

den

Park

N

ort

h P

recin

ct,

V

ineyard

, an

d R

ivers

ton

e

West

pre

cin

cts

Pro

vid

es su

itab

le co

nn

ecti

vit

y t

o N

WP

LR

A

pre

cin

cts

Facilit

ate

s co

nn

ecti

on

beyo

nd

NW

PLR

A

Acti

ve t

ran

sp

ort

co

nn

ecti

vit

y

B

Difficult to get an underpass

to work across the Richmond railway line and through

the Riverstone West precinct due to existing

topography in Riverstone West precinct.

Reliant on earthworks being

completed or additional fill earthworks

required to contain road within the Marsden

Park North precinct.

Sits within the Riverstone

West precinct south of the existing TransGrid

substation and Sydney Water sewer treatment

plant. Potential issue with segregation

of developable land into small wedges.

Issue with impact on the Vineyard

Railway Station Potential to conflict with

previously released ILP.

Serves a limited area on northern

side of proposed road alignment than some other options

>650m bridge

Additional length of around

880m fill with culverts required beyond the

fill proposed by the fill required by the

proponents of Marsden Park North precinct.

More costly to construct a bridge with a

straight and a radius than simpler geometry

Very minimal crossing of the oil and gas pipeline in Riverstone

West precinct Skewed structure across the Richmond

railway line more costly and complex to construct.

Possibly require a bridge over the Richmond railway line instead of

underpass, located at the highest point in the existing terrain. This

would also have issues with grading to existing if developed.

Limited due to issues of

alignment passing through Riverstone West

precinct, and across the Richmond

railway line

Yes Point of intersectio

n on Richmond Road is at New Precinct

Street A.

Mostly, however potential for

problems in Riverstone West precinct.

Yes The eastern

alignment could provide good bus access to

Vineyard Railway Station and to the West

Riverstone precinct.

Yes Yes although slightly

circuitous in eastern section.

Yes, however problemati

c connection with Vineyard precinct

directly to the north of Riverstone West

precinct

Yes Yes Could provide pedestrian and cyclist east-west

access to and

through West Riverstone precinct.

Page 46: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

46

Op

tio

n

Topography / Flooding Land use If structure is above 1 in 100 flash and backwater

Co

nstr

ucta

bilit

y a

nd

ris

ks

Road function

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

Across

Eastern Creek

W ithin Marsden

Park North potential earthwork

s areas

Valu

e fo

r m

on

ey

Co

nn

ects

wit

h a

pre

vio

usly

id

en

tifi

ed

in

ters

ecti

on

in

Mars

den

Park

p

recin

ct

Po

ten

tial

to s

pace in

ters

ecti

on

s at

ap

pro

pri

ate

in

terv

als

to

serv

e th

e n

earb

y

lan

d

En

co

ura

ge p

ub

lic t

ran

sp

ort

uti

lisati

on

s

fro

m b

oth

sid

es o

f B

an

do

n R

oad

Imp

roves accessib

ilit

y

Co

nn

ecti

vit

y

betw

een

M

ars

den

Park

N

ort

h P

recin

ct,

V

ineyard

, an

d R

ivers

ton

e

West

pre

cin

cts

Pro

vid

es su

itab

le co

nn

ecti

vit

y t

o N

WP

LR

A

pre

cin

cts

Facilit

ate

s co

nn

ecti

on

beyo

nd

NW

PLR

A

Acti

ve t

ran

sp

ort

co

nn

ecti

vit

y

C

Sits separate to the existing

terrain requiring large volumes of fill or

extensive bridge length to link between Riverstone

West and Marsden Park North precincts.

Large potential effect on

flooding due to extensive crossing of existing

floodplain. Does not directly connect

onto main area of Marsden Park North developme

nt area.

Avoids negatively impacting

high value developable area in Riverstone West

precinct.

Sits separate to the existing currently

developable area. Requires extensive

bridge length and would require substantial volumes of fill.

Limited connectivity to main potential developable

area and Option C location for Bandon Road.

>2500m up to ~4200m bridge

Any fill used to replace this bridge length

would have a negative effect on flood plain storage and

flood water flows.

Relies on an unapproved cut / fill strategy.

Significant risk and major work issues, if lots are not

developed north of the South / Wianamatta Creek (linked to unapproved cut

/ fill strategy). Bridge length up to ~4200m.

No No Would intersect

with Richmond Road north of New

Precinct Street A.

Extremely limited due to

separation from main Marsden Park North precinct.

Extremely limited due to

separation from main Marsden Park

North precinct.

No Alignment passes

through northern sector and bypasses Marsden

Park North precinct.

No Alignment runs

outside West Riverstone precinct.

Limited Reduced Limited Alignment remote from

future pedestrian and cyclist desire lines.

Page 47: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

47

Op

tio

n

Topography / Flooding Land use If structure is above 1 in 100 flash and backwater

Co

nstr

ucta

bilit

y a

nd

ris

ks

Road function

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

Across

Eastern Creek

W ithin Marsden

Park North potential earthwork

s areas

Valu

e fo

r m

on

ey

Co

nn

ects

wit

h a

pre

vio

usly

id

en

tifi

ed

in

ters

ecti

on

in

Mars

den

Park

p

recin

ct

Po

ten

tial

to s

pace in

ters

ecti

on

s at

ap

pro

pri

ate

in

terv

als

to

serv

e th

e n

earb

y

lan

d

En

co

ura

ge p

ub

lic t

ran

sp

ort

uti

lisati

on

s

fro

m b

oth

sid

es o

f B

an

do

n R

oad

Imp

roves accessib

ilit

y

Co

nn

ecti

vit

y

betw

een

M

ars

den

Park

N

ort

h P

recin

ct,

V

ineyard

, an

d R

ivers

ton

e

West

pre

cin

cts

Pro

vid

es su

itab

le co

nn

ecti

vit

y t

o N

WP

LR

A

pre

cin

cts

Facilit

ate

s co

nn

ecti

on

beyo

nd

NW

PLR

A

Acti

ve t

ran

sp

ort

co

nn

ecti

vit

y

D

Sits separate to the existing

terrain requiring large volumes of fill or

extensive bridge length to link between Riverstone

West and Marsden Park North precincts.

Large potential effect on

flooding due to extensive crossing of existing

floodplain.

Avoids negatively impacting

high value developable area in Riverstone West

precinct.

Sits separate to the existing currently

developable area. Limited connectivity to

main potential developable area and Option D location for

Bandon Road Requires extensive bridge length

and would require substantial volumes of fill.

>2600m up to ~4200m bridge

Any fill used to replace this bridge length

would have a negative effect on flood plain storage and

flood water flows.

Relies on an unapproved cut / fill strategy

Significant risk and major work issues, if lots are not

developed north of the South / Wianamatta Creek (linked to unapproved cut

/ fill strategy). Bridge length up to ~4200m.

No No Would intersect

with Richmond Road north of New

Precinct Street A.

Extremely limited due to

separation from main Marsden Park North precinct,

but potentially marginally better than Option C.

Extremely limited due to

separation from main Marsden Park

North precinct, but potentially marginally

better than Option C.

No Alignment passes

through northern sector and bypasses Marsden

Park North precinct.

No Alignment runs

outside West Riverstone precinct.

Limited Reduced Limited Alignment remote from

future pedestrian and cyclist desire lines.

Page 48: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

48

Op

tio

n

Topography / Flooding Land use If structure is above 1 in 100 flash and backwater

Co

nstr

ucta

bilit

y a

nd

ris

ks

Road function

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

Across

Eastern Creek

W ithin Marsden

Park North potential earthwork

s areas

Valu

e fo

r m

on

ey

Co

nn

ects

wit

h a

pre

vio

usly

id

en

tifi

ed

in

ters

ecti

on

in

Mars

den

Park

p

recin

ct

Po

ten

tial

to s

pace in

ters

ecti

on

s at

ap

pro

pri

ate

in

terv

als

to

serv

e th

e n

earb

y

lan

d

En

co

ura

ge p

ub

lic t

ran

sp

ort

uti

lisati

on

s

fro

m b

oth

sid

es o

f B

an

do

n R

oad

Imp

roves accessib

ilit

y

Co

nn

ecti

vit

y

betw

een

M

ars

den

Park

N

ort

h P

recin

ct,

V

ineyard

, an

d R

ivers

ton

e

West

pre

cin

cts

Pro

vid

es su

itab

le co

nn

ecti

vit

y t

o N

WP

LR

A

pre

cin

cts

Facilit

ate

s co

nn

ecti

on

beyo

nd

NW

PLR

A

Acti

ve t

ran

sp

ort

co

nn

ecti

vit

y

E

Sits separate to the existing

terrain requiring large volumes of fill or

extensive bridge length to link between Riverstone

West and Marsden Park North precincts

Large potential effect on

flooding due to extensive crossing of existing

floodplain but would connect onto proposed

future potential earthworks platform.

Avoids negatively impacting

high value developable area in Riverstone West

precinct.

Runs parallel to existing TransGrid

electricity line easement on northern side through developable

area which limits the developable land to the north.

Requires extensive bridge length and would

require substantial volumes of fill.

>1700m to around 2400m

bridge Any fill used to replace some of

this bridge length would have a negative effect on

flood plain storage and flood water flows

Additional length of around

450m of additional fill with culverts once

reaching land higher than 1% AEP flash and

backwater flood level

Relies on an unapproved cut / fill strategy

Minimal Yes Point of intersectio

n on Richmond Road is at New Precinct

Street A.

Limited as there is limited land

use on northern side of proposed road

location within Marsden Park North precinct

Limited as there is limited

land use on northern side of proposed

road location within Marsden Park

North precinct

Limited Limited Alignment runs

outside West Riverstone precinct.

Limited Yes Limited Could accommodat

e likely future pedestrian and cyclist desire lines through and

within the Marsden Park North precinct.

F

Long length of bridge

Sits within the existing Park Road corridor

Long length of bridge between end of Park

Road to Riverstone West and Vineyard precincts

Avoids negatively impacting high value

developable area in Riverstone West precinct.

Utilises existing Park Road corridor to serve both

existing and future land use needs.

>1800m bridge Any fill used to

replace some of this bridge length would have

a negative effect on flood plain storage and flood water

flows

Additional length of around 300m of

additional fill with culverts once reaching

land higher than 1% AEP flash and backwater

flood level.

Long length of bridge requiring bridge structure to be developed

on both curve and straight which would be more complex

Minimal Yes Point of intersection on

Richmond Road is at New Precinct Street A.

Yes Yes Alignment would facilitate

good bus access and minimise route

kilometres.

Yes Yes Alignment runs within West

Riverstone and Marsden Park North precincts.

Yes Yes Yes Could accommodate likely future

pedestrian and cyclist desire lines.

Page 49: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

49

Op

tio

n

Topography / Flooding Land use If structure is above 1 in 100 flash and backwater

Co

nstr

ucta

bilit

y a

nd

ris

ks

Road function

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

Across

Eastern Creek

W ithin Marsden

Park North potential earthwork

s areas

Valu

e fo

r m

on

ey

Co

nn

ects

wit

h a

pre

vio

usly

id

en

tifi

ed

in

ters

ecti

on

in

Mars

den

Park

p

recin

ct

Po

ten

tial

to s

pace in

ters

ecti

on

s at

ap

pro

pri

ate

in

terv

als

to

serv

e th

e n

earb

y

lan

d

En

co

ura

ge p

ub

lic t

ran

sp

ort

uti

lisati

on

s

fro

m b

oth

sid

es o

f B

an

do

n R

oad

Imp

roves accessib

ilit

y

Co

nn

ecti

vit

y

betw

een

M

ars

den

Park

N

ort

h P

recin

ct,

V

ineyard

, an

d R

ivers

ton

e

West

pre

cin

cts

Pro

vid

es su

itab

le co

nn

ecti

vit

y t

o N

WP

LR

A

pre

cin

cts

Facilit

ate

s co

nn

ecti

on

beyo

nd

NW

PLR

A

Acti

ve t

ran

sp

ort

co

nn

ecti

vit

y

G

Hugs close to TransGrid electricity

substation meaning Minimal earthworks leading to

bridge. Minimal length of structure

could be achieved across Eastern Creek.

Reliant on connecting to an

unapproved earthworks platform location. But

minimises potential negative issues.

Issue with travelling underneath the TransGrid

electricity easement with a bridge structure

Avoids negatively impacting

high value developable area in Riverstone West

precinct.

Crosses the precinct in a less desired

way from development of land use perspective.

Pushes the proposed road near to the northern edge of the main

earthworks platform reducing the proposed roads

effectiveness relating to road function.

Potential 600m to 1000m

bridge depending on earthworks needs

Additional length of around

1400m of additional fill would be required below the

1%AEP flash and backwater flood level land.

Relies on an unapproved cut / fill strategy

Minimal Yes Point of intersectio

n on Richmond Road is at New Precinct

Street A.

Limited as there is limited land

use on northern side of proposed road

location within Marsden Park North precinct

Limited as there is limited

land use on northern side of proposed

road location within Marsden Park

North precinct

Limited Limited

Yes Yes Limited

Page 50: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

50

Op

tio

n

Topography / Flooding Land use If structure is above 1 in 100 flash and backwater

Co

nstr

ucta

bilit

y a

nd

ris

ks

Road function

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

Across

Eastern Creek

W ithin Marsden

Park North potential earthwork

s areas

Valu

e fo

r m

on

ey

Co

nn

ects

wit

h a

pre

vio

usly

id

en

tifi

ed

in

ters

ecti

on

in

Mars

den

Park

p

recin

ct

Po

ten

tial

to s

pace in

ters

ecti

on

s at

ap

pro

pri

ate

in

terv

als

to

serv

e th

e n

earb

y

lan

d

En

co

ura

ge p

ub

lic t

ran

sp

ort

uti

lisati

on

s

fro

m b

oth

sid

es o

f B

an

do

n R

oad

Imp

roves accessib

ilit

y

Co

nn

ecti

vit

y

betw

een

M

ars

den

Park

N

ort

h P

recin

ct,

V

ineyard

, an

d R

ivers

ton

e

West

pre

cin

cts

Pro

vid

es su

itab

le co

nn

ecti

vit

y t

o N

WP

LR

A

pre

cin

cts

Facilit

ate

s co

nn

ecti

on

beyo

nd

NW

PLR

A

Acti

ve t

ran

sp

ort

co

nn

ecti

vit

y

H

Hugs close to TransGrid electricity

substation meaning minimal earthworks leading to

bridge. Minimal length of structure

could be achieved across Eastern Creek.

Large earthworks remote to

the unapproved earthworks platforms for

Marsden Park North. This is particularly true north

of the TransGrid electricity lines that cross

Eastern Creek. There would be a substantial

increase in fill required compared to options that go

south of the TransGrid easement that crosses

Eastern Creek.

Avoids negatively impacting

high value developable area in Riverstone West

precinct.

Runs parallel to existing TransGrid

electricity line easement on northern side through developable

area which limits the developable land to the north.

Requires extensive earthworks.

Around 600m to 660m

bridge depending on earthworks needs

Additional length of around

2,100m of additional fill with culverts once

reaching land higher than 1% AEP flash and

backwater flood level

Relies on an unapproved cut / fill strategy

Separated earthworks structure from main

earthworks within Marsden Park North precinct for an additional

approximate 1,000m

Minimal Yes Point of intersectio

n on Richmond Road is at New Precinct

Street A.

Limited as there is limited land

use on northern side of proposed road

location within Marsden Park North precinct

Limited as there is limited

land use on northern side of proposed

road location within Marsden Park

North precinct

Limited Although alignment is

central to the Marsden Park North precinct.

Limited Although alignment

passes through each precinct.

Limited Yes Limited

Page 51: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

51

Op

tio

n

Topography / Flooding Land use If structure is above 1 in 100 flash and backwater

Co

nstr

ucta

bilit

y a

nd

ris

ks

Road function

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

Across

Eastern Creek

W ithin Marsden

Park North potential earthwork

s areas

Valu

e fo

r m

on

ey

Co

nn

ects

wit

h a

pre

vio

usly

id

en

tifi

ed

in

ters

ecti

on

in

Mars

den

Park

p

recin

ct

Po

ten

tial

to s

pace in

ters

ecti

on

s at

ap

pro

pri

ate

in

terv

als

to

serv

e th

e n

earb

y

lan

d

En

co

ura

ge p

ub

lic t

ran

sp

ort

uti

lisati

on

s

fro

m b

oth

sid

es o

f B

an

do

n R

oad

Imp

roves accessib

ilit

y

Co

nn

ecti

vit

y

betw

een

M

ars

den

Park

N

ort

h P

recin

ct,

V

ineyard

, an

d R

ivers

ton

e

West

pre

cin

cts

Pro

vid

es su

itab

le co

nn

ecti

vit

y t

o N

WP

LR

A

pre

cin

cts

Facilit

ate

s co

nn

ecti

on

beyo

nd

NW

PLR

A

Acti

ve t

ran

sp

ort

co

nn

ecti

vit

y

I

Hugs close to TransGrid electricity

substation meaning minimal earthworks leading to

bridge. Minimal length of structure

could be achieved across Eastern Creek.

Reliant on connecting to an

unapproved earthworks platform location. But

minimises potential negative issues.

Issue with travelling underneath the TransGrid

electricity easement with a bridge structure

Stays away from negatively

impacting high value developable area in Riverstone

West precinct.

Pushes the proposed road near to the

northern edge of the main earthworks platform reducing the

proposed roads effectiveness relating to road function.

Benefit of connectivity directly to southern side

of TransGrid electricity easement across Eastern

Creek.

Potential 600m to 1000m

bridge depending on earthworks need

Additional length of around

1300m of additional fill would be required below the

1%AEP flash and backwater flood level land.

Reduced reliance on an unapproved cut

/ fill strategy

Yes Yes Point of intersectio

n on Richmond Road is at New Precinct

Street A.

Yes Yes Yes Yes Yes Yes Yes

Page 52: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

52

Op

tio

n

Topography / Flooding Land use If structure is above 1 in 100 flash and backwater

Co

nstr

ucta

bilit

y a

nd

ris

ks

Road function

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

Across

Eastern Creek

W ithin Marsden

Park North potential earthwork

s areas

Valu

e fo

r m

on

ey

Co

nn

ects

wit

h a

pre

vio

usly

id

en

tifi

ed

in

ters

ecti

on

in

Mars

den

Park

p

recin

ct

Po

ten

tial

to s

pace in

ters

ecti

on

s at

ap

pro

pri

ate

in

terv

als

to

serv

e th

e n

earb

y

lan

d

En

co

ura

ge p

ub

lic t

ran

sp

ort

uti

lisati

on

s

fro

m b

oth

sid

es o

f B

an

do

n R

oad

Imp

roves accessib

ilit

y

Co

nn

ecti

vit

y

betw

een

M

ars

den

Park

N

ort

h P

recin

ct,

V

ineyard

, an

d R

ivers

ton

e

West

pre

cin

cts

Pro

vid

es su

itab

le co

nn

ecti

vit

y t

o N

WP

LR

A

pre

cin

cts

Facilit

ate

s co

nn

ecti

on

beyo

nd

NW

PLR

A

Acti

ve t

ran

sp

ort

co

nn

ecti

vit

y

J

Hugs close to TransGrid electricity

substation meaning minimal earthworks leading to

bridge. Minimal length of structure

could be achieved across Eastern Creek.

Less reliant on connecting

to an unapproved earthworks platform location.

Minimises potential negative issues.

Issue with travelling underneath the TransGrid

electricity easement with a bridge structure

Stays away from negatively

impacting high value developable area in Riverstone

West precinct.

Pushes the proposed road near to the

southern side of the existing TransGrid easement running

parallel to Park Road. Benefit of creating

parallel road to Park Road. Benefit of connectivity

directly to southern side of TransGrid electricity easement

across Eastern Creek.

Potential 600m to 1000m

bridge depending on earthworks need

Additional length of around

1200m of additional fill would be required below the

1%AEP flash and backwater flood level land.

Reduced reliance on an unapproved cut

/ fill strategy. Minimises wasted land associated with

existing TransGrid electricity easement.

Yes Yes Point of intersectio

n on Richmond Road is at New Precinct

Street A.

Yes Yes Yes Yes Yes Yes Yes

Page 53: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

53

Op

tio

n

Topography / Flooding Land use If structure is above 1 in 100 flash and backwater

Co

nstr

ucta

bilit

y a

nd

ris

ks

Road function

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

Across

Eastern Creek

W ithin Marsden

Park North potential earthwork

s areas

Valu

e fo

r m

on

ey

Co

nn

ects

wit

h a

pre

vio

usly

id

en

tifi

ed

in

ters

ecti

on

in

Mars

den

Park

p

recin

ct

Po

ten

tial

to s

pace in

ters

ecti

on

s at

ap

pro

pri

ate

in

terv

als

to

serv

e th

e n

earb

y

lan

d

En

co

ura

ge p

ub

lic t

ran

sp

ort

uti

lisati

on

s

fro

m b

oth

sid

es o

f B

an

do

n R

oad

Imp

roves accessib

ilit

y

Co

nn

ecti

vit

y

betw

een

M

ars

den

Park

N

ort

h P

recin

ct,

V

ineyard

, an

d R

ivers

ton

e

West

pre

cin

cts

Pro

vid

es su

itab

le co

nn

ecti

vit

y t

o N

WP

LR

A

pre

cin

cts

Facilit

ate

s co

nn

ecti

on

beyo

nd

NW

PLR

A

Acti

ve t

ran

sp

ort

co

nn

ecti

vit

y

K

Hugs close to TransGrid electricity

substation meaning minimal earthworks leading to

bridge. Minimal length of structure

could be achieved across Eastern Creek.

Less reliant on connecting

to an unapproved earthworks platform location.

Minimises potential negative issues.

Issue with travelling underneath the TransGrid

electricity easement with a bridge structure

Stays away from negatively

impacting high value developable area in Riverstone

West precinct.

Pushes the proposed road near to the

southern side of the existing TransGrid easement running

parallel to Park Road. Benefit of creating

parallel road to Park Road. Benefit of connectivity

directly to southern side of TransGrid electricity easement

across Eastern Creek.

Potential 600m to 1000m

bridge depending on earthworks need

Additional length of around

1200m of additional fill would be required below the

1%AEP flash and backwater flood level land.

Reduced reliance on an unapproved cut

/ fill strategy. Minimises wasted land associated with

existing TransGrid electricity easement.

Yes Yes Point of intersectio

n on Richmond Road is at New Precinct

Street A.

Yes Yes Yes Yes Yes Yes Yes

L

Improves length of bridge required to

gap between Riverstone West and Marsden

Park North

Requires minimal flood plain crossing

below 1% AEP flood level

Minimises disruption to Riverstone

West precinct high value proposed land area

Serves both sides of Bandon Road with controlled

access Utilises part of Park Road existing road

reservation which would need to be widened.

Around 600m to 660m bridge

depending on earthworks needs

1200m fill with culverts

TransGrid line at Eastern Creek may make bridge

construction more problematic / costly

Yes Yes Point of intersection on

Richmond Road is at New Precinct Street A.

Yes Yes The alignment would be

central to the Marsden Park precinct

meaning bus feeder access could be

optimised.

Yes Central alignment provides

good accessibility.

Yes Yes Yes Yes Would accommodate likely future

pedestrian and cyclist desire lines through and within the

Marsden Park North precinct.

Page 54: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

54

Op

tio

n

Topography / Flooding Land use If structure is above 1 in 100 flash and backwater

Co

nstr

ucta

bilit

y a

nd

ris

ks

Road function

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

Across

Eastern Creek

W ithin Marsden

Park North potential earthwork

s areas

Valu

e fo

r m

on

ey

Co

nn

ects

wit

h a

pre

vio

usly

id

en

tifi

ed

in

ters

ecti

on

in

Mars

den

Park

p

recin

ct

Po

ten

tial

to s

pace in

ters

ecti

on

s at

ap

pro

pri

ate

in

terv

als

to

serv

e th

e n

earb

y

lan

d

En

co

ura

ge p

ub

lic t

ran

sp

ort

uti

lisati

on

s

fro

m b

oth

sid

es o

f B

an

do

n R

oad

Imp

roves accessib

ilit

y

Co

nn

ecti

vit

y

betw

een

M

ars

den

Park

N

ort

h P

recin

ct,

V

ineyard

, an

d R

ivers

ton

e

West

pre

cin

cts

Pro

vid

es su

itab

le co

nn

ecti

vit

y t

o N

WP

LR

A

pre

cin

cts

Facilit

ate

s co

nn

ecti

on

beyo

nd

NW

PLR

A

Acti

ve t

ran

sp

ort

co

nn

ecti

vit

y

M

Optimises length of bridge to

topography of existing levels, while minimal additional fill

earthworks required in Riverstone West

Utilises Park Road and stays

in more locations greater than 1% AEP flood

level

Good access to areas

above 1% AEP flood level.

Serves both sides of Bandon Road

with controlled access. Good connectivity to

Marsden Park North compared to other options

Utilises part of Park Road which is an existing road easement.

Potential 600m to 1000m

bridge depending on earthworks needs

850m fill with culverts

Benefit in building earthworks

underneath TransGrid line at Eastern Creek, with bridge occurring

to north of this easement Benefit of creek crossing

immediately east of Richmond Road being above 1% AEP flash and

backwater flood level.

Yes Yes Point of intersectio

n on Richmond Road is at New Precinct

Street B (Elara Blvd traffic signals).

Yes Yes The alignment

would be central to the Marsden Park

precinct meaning bus feeder access

could be optimised.

Yes Central alignment maximises

accessibility. Superior alignment to Option L.

Yes Connectivity

maximises. Superior to Option L.

Yes Superior to Option L.

Yes Intersection with New

Precinct B street means east-west connectivit

y for through trips is maximised.

Superior to Option L.

Yes. Good accessibility

to planned Marsden Park precinct retail centre and sporting

facilities.

Page 55: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

55

Op

tio

n

Topography / Flooding Land use If structure is above 1 in 100 flash and backwater

Co

nstr

ucta

bilit

y a

nd

ris

ks

Road function

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

W ithin Riverstone

W est and Vineyard precinct

W ithin Marsden

Park North precinct

Across

Eastern Creek

W ithin Marsden

Park North potential earthwork

s areas

Valu

e fo

r m

on

ey

Co

nn

ects

wit

h a

pre

vio

usly

id

en

tifi

ed

in

ters

ecti

on

in

Mars

den

Park

p

recin

ct

Po

ten

tial

to s

pace in

ters

ecti

on

s at

ap

pro

pri

ate

in

terv

als

to

serv

e th

e n

earb

y

lan

d

En

co

ura

ge p

ub

lic t

ran

sp

ort

uti

lisati

on

s

fro

m b

oth

sid

es o

f B

an

do

n R

oad

Imp

roves accessib

ilit

y

Co

nn

ecti

vit

y

betw

een

M

ars

den

Park

N

ort

h P

recin

ct,

V

ineyard

, an

d R

ivers

ton

e

West

pre

cin

cts

Pro

vid

es su

itab

le co

nn

ecti

vit

y t

o N

WP

LR

A

pre

cin

cts

Facilit

ate

s co

nn

ecti

on

beyo

nd

NW

PLR

A

Acti

ve t

ran

sp

ort

co

nn

ecti

vit

y

N Hugs close to TransGrid electricity

substation meaning minimal earthworks leading to

bridge. Minimal length of structure

could be achieved across Eastern Creek.

Large earthworks remote to

the unapproved earthworks platforms for

Marsden Park North. This is particularly true north

of the TransGrid electricity lines that cross

Eastern Creek. There would be a substantial

increase in fill required compared to options that go

south of the TransGrid easement that crosses

Eastern Creek.

Stays away from negatively

impacting high value developable area in Riverstone

West precinct.

Runs parallel to existing TransGrid

electricity line easement on northern side of the existing TransGrid

electricity easement across Eastern Creek which limits

the connectivity to developable land.

Serves both sides of Bandon Road with controlled access.

Utilises part of Park Road which is an existing road

easement.

Around 600m to 660m

bridge depending on earthworks needs

Additional length of around

1,100m of additional fill with culverts once

reaching land higher than 1% AEP flash and

backwater flood level

Separated earthworks structure from

main earthworks within Marsden Park North precinct for an

additional approximate 500m

Minimal Yes Point of intersectio

n on Richmond Road is at New Precinct

Street A.

Yes Yes Yes Alignment provides

good accessibility. Not to same

extent as Option M.

Yes Good connectivit

y but not to same extent as Option M.

Yes Not to same

extent as Option M.

Yes Intersection with New

Precinct A Street means east-west connectivit

y for through trips is not as high as Option M.

Yes. Accessibility to planned

Marsden Park precinct retail centre and sporting facilities

inferior to that provided by Option M.

Page 56: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

56

4.5.3 Value Management workshop

The December 2015 Value Management Workshop concluded Option M was the Bandon Road preferred corridor. Refer to Appendix 3 for a copy off the Value Management Report. The options were considered having regard to their performance relative the objectives and selection criteria

referred to above. The Value Management participants agreed that several options were not worthy of further consideration and these where eliminated from further consideration for the reasons outlined in Table 4.3 below.

Table 4.3 – Bandon Road Upgrade Corridor Option Assessment

OPTION ADVANTAGES (A) / DISADVANTAGES (D) RATING

A A - Nil

D - Bridge length greater than 1,200 metres

Delete in favour of Option I

0

B A - Nil

D - Segregation of land use

D - Curved rather than straight bridge

D - Works best with rail overbridge, impact on Vineyard Railway St

0

C A - Nil

D - Poor arterial road and intersection outcome

D - Requires extensive bridge length

0

D A - Nil

D - Poor arterial road and intersection outcome

D - Requires extensive crossing of the floodplain

D - Requires extensive bridge length

0

E A - Nil

D - Requires extensive bridge length (circa 2,500 metres) and extensive

crossing of the floodplain

D - Potential segregation of land issues

0

F A - Nil

D - Requires extensive bridge length (circa 2,500 metres) and extensive

crossing of the floodplain

0

G A - Avoids the TransGrid easement.

D - Heavily reliant on additional land fill (1,400m3 above 1% flood level).

0

H A - Avoids the TransGrid easement

D - Requires a large quantity of land fill (2,100m3) which needs to be offset

0

I A - Avoids the TransGrid easement on the southern side minimising

earthworks and flood storage impact

D - Requires bridge under the TransGrid lines

0

J Preferred over Option I

A - Has a slightly more direct corridor alignment than Option K at the

western end

A - Potentially less noise impact on development areas compared to

Options L and M

A - Less impact on prime development land compared to Options L and M

D - Requires bridge under the TransGrid lines while Option M does not.

1

Page 57: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

57

OPTION ADVANTAGES (A) / DISADVANTAGES (D) RATING

D - Has potential Aboriginal heritage issues compared to Options L and M

(Park Road alignment)

D - Creates a boundary road rather than a spine road

D - Provides for a less optimum connection to Marsden Park compared to

Option M

D - Creates smaller segregated development areas

K Similar to Option J

A - Less environmental and heritage impact compared to Option J

D - Western corridor alignment less direct compared to Option J

1

L A positive alignment Option from a Roads and Maritime perspective

A - Bridge is located at the narrowest point

A - Utilises the existing Park Road reservation

A - Allows for more development land due to Park Road alignment

A - Co-ordination of utilities has already occurred along Park Road

D - Requires bridge under the TransGrid lines while Option M does not

D - Provides for a less optimum connection to Marsden Park compared to

Option M

D - Proximity to existing school on Park Road

1

M A positive alignment Option from a Roads and Maritime perspective that

addresses some of the issues associated with Option L

A - Provides a wider potential opening for the Creek

A - Avoids construction under TransGrid lines

A - Optimum point of intersection on Richmond Road at Elara Boulevard

A - A generally straight corridor alignment

A - A generally more direct corridor between Windsor and Richmond roads

A - A superior flood evacuation outcome

D - A slightly greater volume of earthworks compared to Option L

D - Some impact upon vegetation

1

N A - Nil

D - An alignment to the north of the TransGrid easement which is not

supported by Roads and Maritime

D - Excessive fill volumes required.

0

A - Advantage

B - Disadvantage

0 - Option eliminated from further consideration.

1 - Option retained for further consideration.

After further discussion amongst the Value Management participants the following key point were

agreed:

While Option J was preferred over Option I and would have a slightly more di rect corridor

alignment than Option K at the western end, it would require a bridge under the TransGrid

lines, has potential Aboriginal heritage issues, would be less optimum as a spine road, would

have a less favourable connection to Marsden Park and would create smaller segregated

development areas. On this basis it was not seen as a preferred corridor

The group agreed that in terms of the differentiating factors for options between the Richmond

railway line and Windsor Road, it was preferred to widen to the southern side of the existing

Bandon Road. However, further investigations would be undertaken during the design

development process to optimise the alignment and to add value

Page 58: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

58

Option K was seen by the participants to be similar to Option J but with possibly fewer

environmental and heritage impact. Conversely, the western corridor alignment of Option K

was considered less direct than Option J

Option L was considered to be a potentially feasible option in the view of Roads and Maritime.

The bridge is located at the narrowest point of the existing land form next to Eastern Creek,

the corridor utilises the existing Park Road reservation, it would allow for more development

land due to the Park Road alignment within which co-ordination of utilities has already

occurred

The key differentiators between Options L and M was the fact that Option L would require a

bridge under the TransGrid lines whereas Option M would not, and Option M providing a

better point of connection with Richmond Road and the Marsden Park precinct

It was agreed options to minimise environmental impact at the western end of the alignment

would be investigated

It was agreed Roads and Maritime would continue to work with the DP&E and Councils to

integrate the proposed alignment with precinct planning directions

It was agreed the already approved zone planning in the Riverstone precinct would be

modified in response to the adoption of Option M as the preferred Bandon Road corridor.

4.5.4 Bandon Road preferred corridor – Option M

Option M was selected as the preferred corridor location for Bandon Road at the conclusion of the

Value Management workshop. The Option M corridor is shown in Figure 4.5. The reasons for the

selection of Option M are as follows:

Topography – Utilises the existing topography to minimise the length of bridge required

across Eastern Creek and minimises fill earthworks volume within the floodplain; m inimal

bridge length/structure and minimises flood impact

Land Use – Good connectivity to Marsden Park North; good access to areas of land located

above the 1% AEP (1 in 100 year flash and backwater flood level). Serves both sides of

Bandon Road. The corridor would utilise an existing length of Park Road as part of the

Bandon Road corridor. Minimises effects on developable land within the Riverstone West

precinct. Limits direct effects on existing businesses and residences on the northern side of

Bandon Road between the Richmond railway line and Windsor Road

Environment – The preferred corridor facilitates environmental impact mitigation although

some issues require continued examination. The Bandon Road Preliminary Environmental

Investigation concluded there would be likely impact on small areas of Shale Plains Woodland

(Cumberland Plain Woodland critically endangered ecological community (TSC Act and EPBC

Act)) and Shale / Gravel Transition Forest (EPBC Act, critically endangered; TSC Act

endangered). These areas are located immediately to the west of Park Road and to the north

of the existing Bandon Road extent. All are located on biocertified lands. Potential impact on

habitat for threatened flora including Grevillea juniperina subsp. Juniperina (TSC Act,

vulnerable), for which there are previous records on the southern side of the existing Bandon

Road extent and near Park Road. Any impact would most likely be in biocertified areas

Constructability and Risks – Minimises impact on the TransGrid transmission lines. The

creek crossings would be above the 1% AEP backwater flood level. Connects to existing

signalised intersection of Richmond Road and Elara Boulevard (New Precinct Street B)

Page 59: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

59

Road Function – Bandon Road would join Richmond Road at the recently constructed

Richmond Road and Elara Boulevard (New Precinct Street B) intersection within the Marsden

Park precinct. This intersection with the recently constructed traffic signals at Elara Boulevard

would be consistent with the internal Marsden Park precinct road network while providing

good spacing of intersections along Richmond Road

Strategic – It is generally consistent with the Roads and Maritime North West Growth Centre

Road Network Strategy for the NWPLRA facilitating east-west connections between Windsor

Road and Richmond Road. This corridor would provide an alternative route to Garfield Road

east-west route across the Richmond railway line. The corridor would provide good

connectivity to the Marsden Park North precinct compared to other options

Public and active transport – The alignment could be central to the Marsden Park North

precinct meaning bus feeder access could be optimised. The corridor alignment would

maximise accessibility and connectivity with neighbouring precincts , and facilitate access to

and from Vineyard Railway Station. The corridor would facilitate connectivity beyond the

NWPLRA because the intersection with Elara Boulevard (New Precinct B) means east-west

connectivity for through trips is maximised. This would benefit precinct traffic, cross regional

bus services and through vehicle movements. The corridor could facilitate good pedestrian

and cyclist access by virtue of its central alignment which would provide efficient access

between the Marsden Park North precinct and planned retail centre and sporting facilities in

the Marsden Park precinct.

Page 60: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade Options Report

60

Figure 4.5 – The Bandon Road Preferred Corridor – Option M

Page 61: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

61

4.6 Summary

The key messages in Chapter 4 are as follows:

1. A total of fourteen Bandon Road corridor options were identified

2. Some of the options are similar with only slight variations in sections of the al ignments, for

example, Options L, M and N differ only slightly in their alignments near the existing

transmission line easement to the west of Eastern Creek although they do differ in terms of

bridge locations and the point of intersection with Richmond Road

3. Key constraints and opportunities were identified in the assessment process and include the

extent of cut and fill (required for the road upgrade itself and to accommodate precinct

development across the study area), impact upon flooding, avoidance of vegetation

conservation zones, utilities impact and precinct development

4. Each option was assessed against the assessment criteria and considered at the December

2015 Bandon Road Value Management Workshop

5. Options J, K L and M were considered to be potentially feasible corridor options

6. Option M is the preferred corridor for Bandon Road for the reasons outlined in Chapter 4.

Page 62: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

62

5 CONCLUSIONS AND NEXT STEPS

5.1 Bandon Road preferred corridor – Option M

The assessment of options concluded Option M is the preferred Bandon Road corridor. Option M is

generally consistent with the Roads and Maritime North West Growth Centre Road Network Strategy

for the NWPLRA, facilitating east-west connections between Windsor Road and Richmond Road. An

updated map of the North West Growth Centre Road Network Strategy (March 2016) showing the

preferred Bandon Road corridor is shown in the executive summary. The corridor would provide an

alternative route to the Garfield Road east-west route across the Richmond railway line. The corridor

would also provide good connectivity to the Marsden Park North precinct compared to other options.

Option M utilises existing topography to minimise bridge lengths and fill earthworks volumes within the

floodplain. The preferred corridor would also minimise flood impact. The corridor connects to the

recently constructed signalised intersection of Richmond Road and Elara Boulevard and would

complement precinct planning in the area. It would also provide good spacing of intersections along

Richmond Road north of Garfield Road West. Option M would provide good connectivity to Marsden

Park North and good access to areas of land located above the 1% AEP (1 in 100 year flash and

backwater flood level). The preferred corridor would serve both sides of Bandon Road and would

utilise an existing length of Park Road as part of the Bandon Road corridor. It would minimise effects

on developable land within the Riverstone West precinct and limit direct effects on existing businesses

and residences on the northern side of Bandon Road between the Richmond railway line and Windsor

Road. Compared to other options, the Bandon Road preferred corridor – Option M would have

comparatively fewer environmental impact.

The preferred corridor would be central to the Marsden Park North precinct meaning bus feeder

access could be optimised. The corridor alignment would maximise accessibility and connectivity with

neighbouring precincts. The corridor would facilitate connectivity beyond the NWPLRA because the

intersection with Elara Boulevard means east-west connectivity for through trips is maximised. This

would benefit precinct traffic, cross regional bus services and through vehicle movements. The

corridor could facilitate good pedestrian and cyclist access by virtue of its central alignment which

would provide efficient access between the Marsden Park North precinct and planned retail centre and

sporting facilities in the Marsden Park precinct.

The assessment of option M also concluded:

The point of intersection with Richmond Road would be around one kilometre north of the

Garfield Road intersection providing good separation of intersections with traffic lights along

the arterial road.

The alignment of Option M is central to the Marsden Park North precinct which will enable a

higher order road within the Corridor to efficiently provide access across the precinct once

developed

The corridor would minimise impact on the central vegetation conservation zone, riparian

corridors and threatened ecological communities

The corridor would promote planning of new integrated neighbourhoods because it minimises

severance of planned neighbourhoods and would not have adverse impact on precinct and

resident amenity

The corridor would facilitate the ability to stage precinct development over time between now

and full development

Page 63: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

63

It could service different growth scenarios.

5.2 Next steps

The next steps include:

1. Community consultation of the Bandon Road preferred corridor

2. Consider consultation feedback and refine preferred corridor if required

3. Start Bandon Road corridor reservation.

4. Develop concept design and environment assessment.

Page 64: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

64

Appendices

Appendix 1: Terms and Definitions

TERM DEFINITION

Levels of Service A qualitative descriptor of the road environment describing the ability of

vehicles to manoeuvre. ‘A’ represents complete freedom to accelerate or

manoeuvre. “F’ represents high levels of congestion

Project scope The geographic and physical description of a road project undertaken

during the planning process. Scope may vary with further project

development

Heavy vehicles Classes 3-12 under the Austroads’ vehicle classification system. Does not

include short vehicles (e.g. cars, motorbikes or short vehicles towing

another)

Crash rates The number of reported crashes on a road as a proportion of the traffic

usually expressed as per 100 million vehicle kilometres

Accessibility The potential ability of an individual or group to reach a destination. It is

distinguished from mobility which is the propensity of that individual or

group to make a journey

Traffic Modelling A process that predicts future traffic volumes on the basis of trip

generation, destination attractiveness and geographic options to make

those trips

Base Case In economic appraisal, the case which represents “business as usual” or

“Do Minimum”. The costs and benefits of that case are compared to the

improved case options

Stakeholder An individual or organisation potentially affected by, or who have an

interest in, a proposed project

Sustainability The concept that, in carrying out current actions (e.g. building a road)

there should be positive net benefits for future generations.

Page 65: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

65

Appendix 2: Treatment of Employment Estimates in 2014 Strategy Analysis

Forecasts of future traffic demand have been estimated for 2026 and 2036. One of the purposes of the

modelling exercise is to incorporate recent changes in land use planning assumptions into the traffic

model to enable the most up-to-date forecasts to be used for the assessment of options.

A comparison was undertaken between the latest version of Bureau of Statistical Analysis’ Sydney

Strategic Travel Model (STM) and the most recent information from the DP&E. The latest version of

STM incorporates the Bureau of Statistical Analysis Population and Employment Forecasts, August

2012 Release. An update to these forecasts is imminent, but was not available for this study.

The comparison between the Bureau of Statistical Analysis Population and Employment Forecasts

and most recent Planning master plans is summarised in Table 4.2. The analysis revealed:

Dwelling forecasts have increased by seven per cent from about 65,000 to 70,000 households

Population forecasts have increased by about 10 per cent from 185,600 to 203,400 people

(around 200,000)

The latest DP&E master plan forecasts of employment for the Box Hill Industrial, Marsden

Park Industrial and Riverstone West precincts are 57 per cent higher than the Bureau of

Statistical Analysis forecasts (38,000 compared to 24,300 jobs). An additional 1,400 jobs are

forecast to be created within the Riverstone Precinct, however, these appear to be within the

Bureau of Statistical Analysis forecast of 6,289 jobs. Overall about 40,000 new jobs could be

created within the NWPLRA.

This large difference in employment estimates was attributed to:

The DP&E master plan job estimates being maximums, assuming full development, with all

development occurring with the maximum density of employees

Limits on total employment across the Sydney Greater Metropolitan Areas. Therefore if a high

density of employees were to occur in the North West Growth Centre, reduced employment

would need to be assumed elsewhere in Sydney.

Bureau of Statistical Analysis applies a control to its employment forecasts to spread the number of

growth in jobs across Sydney. Its forecasts are considered to be the ‘most likely’ rather than the

‘maximum potential’. For the purposes of the Parsons Brinckerhoff study (2015), the Bureau of

Statistical Analysis process was assumed to represent a reasonable basis for planning and assessing

the future road network demand. To incorporate some increase in employment, and to avoid skewing

travel patterns between residents commuting out of the study area and employees driving to jobs

within the study area, it was assumed that population and employment forecasts will increase by the

same agreed growth percentage – seven per cent. This equates to 2,045 jobs and 13,252 residents in

excess of the August 2012 Bureau of Statistical Analysis employment forecasts.

Page 66: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

Bandon Road Upgrade

Options Report

66

Appendix 3: Bandon Road Corridor - Options Assessment Value Management Workshop -

Report, December 2015

Page 67: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

rms.nsw.gov.au/nwplra

1300 367 561

Riverstone NWGC

Roads and Maritime Services

Locked Bag 973

Parramatta NSW 2124

June 2016 RMS 16.207

ISBN: 978-1-925507-27-0

Page 68: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshopReportTierneyPageKirklandPtyLtdLEADERSINFACILITATIONSuite507,AshingtonCourt147KingStreetSYDNEYNSW2000Telephone1 1300TPKTPK(875875)Telephone2 (02)90453306E-Mail [email protected] www.tpk.com.au

December 2015

Page 69: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland

TableofContents1 EXECUTIVESUMMARY......................................................................1

1.1 KEYOUTCOMESFROMTHEVALUEMANAGEMENTWORKSHOP.......................2

2 INTRODUCTION................................................................................3

2.1 WORKSHOPMETHODOLOGY.....................................................................32.2 WORKSHOPREPORT................................................................................3

3 INFORMATIONPHASE......................................................................4

3.1 WELCOME-SURESHSURENDRAN.............................................................4

3.2 THEWORKSHOPPROCESS–DECLANTIERNEY..............................................43.3 DEPARTMENTOFPLANNING(DOP)OVERVIEW–EVELYNIVINSON..................4

3.4 OBJECTIVES,BACKGROUNDANDSCOPE–YVONNETSUKAME.........................43.5 THEAVAILABLEOPTIONS–DAMIANGOULDER.............................................4

4 ANALYSISPHASE..............................................................................5

4.1 WORKSHOPOBJECTIVES...........................................................................5

4.2 PROJECTOBJECTIVES...............................................................................54.2.1 Broadobjective...............................................................................6

4.3 ASSUMPTIONS.......................................................................................64.3.1 Facts................................................................................................6

4.3.2 Workingassumptions.....................................................................7

4.3.3 Questionable...................................................................................74.3.4 Incorrect..........................................................................................7

5 OPTIONASSESSMENT.......................................................................8

5.1 CULLINGOFOPTIONS..............................................................................85.2 KEYFEATURESSHORTLISTEDOPTIONS.........................................................9

5.3 PROSANDCONSASSOCIATEDWITHEACHOPTION.........................................9

5.3.1 OptionA..........................................................................................105.3.2 OptionB..........................................................................................10

5.3.3 OptionC..........................................................................................10

5.3.4 OptionD..........................................................................................105.3.5 OptionE..........................................................................................10

5.3.6 OptionF...........................................................................................105.3.7 OptionG..........................................................................................11

5.3.8 OptionH..........................................................................................11

5.3.9 OptionI...........................................................................................115.3.10 OptionJ...........................................................................................11

5.3.11 OptionK..........................................................................................115.3.12 OptionL...........................................................................................11

5.3.13 OptionM.........................................................................................12

5.3.14 OptionN..........................................................................................12

Page 70: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland

6 CREATIVEPHASE..............................................................................13

6.1 IDEAGENERATION...................................................................................13

7 JUDGEMENTPHASE..........................................................................14

7.1 IDEASRECOMMENDEDFORIMPLEMENTATION.............................................14

7.2 IDEASRECOMMENDEDFORINVESTIGATION.................................................14

7.3 IDEASDEEMEDTOBEIMPRACTICAL............................................................14

8 WORKSHOPOUTCOMES...................................................................15

9 ACTIONPLAN...................................................................................15

APPENDICESAppendix1 Listofparticipants

Page 71: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page1

1 Executivesummary

TheNSWGovernmentisfundingthedevelopmentofaroadnetworkstrategyinresponsetothedevelopmentoftheNorthWestGrowthCentre(NWGC),whichisexpectedtoexpandtoabout200,000newresidentsoverthenext20to30years.Thisriseinpopulationanddevelopmentwillgenerateasignificantincreaseintrafficinthearea.

RoadsandMaritimehasdevelopedaNWGCRoadNetworkStrategy,whichincludesaseriesofroadnetworkupgradestosupporttheexpectedgrowth.Theseupgradesarebeingdeliveredinthreekeyphases:short,mediumandlong-term,subjecttofundingavailability.

Theproposedshort-termworkincludesplanningfortheBandonRoadunderpassatRichmondrailwayline,VineyardandroadlinkbetweenWindsorRoadandRichmondRoad.

Inthemedium-termtheNWGCRoadNetworkStrategyaimstoprovidealternativeroutesforvehicles.BuildingtheBandonRoadconnectionbetweenWindsorRoadandRichmondRoadthatwouldprovideanadditionalrouteforvehiclestocrosstheRichmondrailwayline.ThiswouldassistinreducingcongestionalongGarfieldRoadandreducetraveltimesbetweenWindsorRoadandRichmondRoad.BandonRoadisalsoexpectedtoenhancethefloodevacuationaccessacrosstheNWGC.NWGCRoadNetworkStrategy-

Page 72: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page2

RMShasinvestigatedanumberBandonRoadcorridorupgradeoptionsinconsultationwithvariousstakeholdersincludingadjacentcouncilsandtheDepartmentofPlanningandEnvironment.

TheareabetweenWindsorRoadandRichmondRoadisconstrainedbyvariousfactors-utilities,floodproneareas,AboriginalandNon-Aboriginalheritagesites,environmentallysensitiveareas,etc.

TheValueManagement(VM)workshopwasconvenedtoengagewithkeyprojectstakeholderstoguidetheselectionofthepreferredcorridoroptiontobeadopted,whichwouldbefurtherrefinedduringtheconceptdesignanddetailedenvironmentalassessmentstage.

Thesessionwasusedtoconfirmthe“non-negotiables”regardingtheproject.Itenabledassumptionstobetestedandprovidedanopportunityforparticipantstofloatvalueenhancementproposalsforconsiderationandassessmentbythegroupasawhole.

TheindependentlyfacilitatedvaluemanagementandoptionsevaluationworkshopwasheldonThursday,17December2015,atMantraParramatta,ParkesStreet,Parramatta.

1.1 KeyoutcomesfromtheValueManagementworkshop

Havingcompletedtheworkshopprocessthefollowingoutcomes/agreementsemerged:

Ø ThegroupagreedthatintermsofthedifferentiatingfactorsforoptionsattheWindsorRoadend,itwaspreferredtowidentothesouthernsideoftheexistingBandonRoad.However,furtherinvestigationswouldbeundertakenduringthedesigndevelopmentprocesstooptimisethealignmentandtoaddvalue.

Ø TheparticipantsunanimouslyconfirmedOptionMasthegroup’spreferredoptiononthebasisoftheinformationdisseminatedanddiscussedattheworkshop.

Ø Itwasagreedthatoptionstominimiseenvironmentalimpactsatthewesternendofthealignmentwouldbeinvestigated.

Ø ItwasagreedthatRMSwouldcontinuetoworkwiththeDP&EandCouncilstointegratetheproposedalignmentwithprecinctplanningdirections.

Ø ItwasagreedthatthealreadyapprovedzoneplanningintheRiverstoneprecinctwouldbemodifiedinresponsetotheadoptionofOptionMasthepreferredupgradealignment.

Inthecourseoftheworkshop,thegrouplistedassumptionsbeingmadeasaresultoftheinformationpresented,theproposedoptionsandothermatters.Thesewerediscussedwithmanybeingclassifiedasfacts,orineffect-“mini-decisions”.RefertoSection4.3fordetails.

Page 73: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page3

2 Introduction

2.1 Workshopmethodology

Theworkshoputilisedastructuredprocesstoensurethatkeyissueswereidentifiedandthatthealignmentoptionultimatelyendorsedbythegroupbestmeetsessentialrequirementsandprojectobjectives.Theentiresessionwascharacterisedbyastrongcommitmenttoteamworkandcooperation.Theprocesswasfocussedondevelopingacommonunderstandingoftheestablishedstrategicobjectivesanduserrequirementssothatoptimumoutcomesareachieved.

Centraltothesuccessofthesessionwastheinclusionofkeyprojectstakeholders.ThelistofparticipantsisprovidedinAppendix1.

Theworkshopprocessconfirmedthe:

Ø workshopandprojectobjectives,andwentonto:

Ø testtheassumptionsbeingmade;Ø updateparticipantsonthealignmentoptionsavailable;and

Ø evaluatethoseoptions;Theprocessthenenabledparticipants:

Ø tosuggestideastoimprovetheendorsedalignment;

Ø tocreateanactionplantoensurethatthenecessaryactivitiesareundertakeninatimelymanner;andfinally

Ø toconfirmaseriesofrecommendations/agreementstoenabletheprojecttoproceed.

2.2 Workshopreport

Theinformationcontainedinthisreporthasbeendistilledfromthepreworkshopbriefingsandthedatageneratedduringthesession.Thereportseekstoprovideanoverviewoftheprojectandtooutlinetheworkshopmethodology.Itsummarisestheinformationpresentedbytheparticipantsanddescribestheprocessundertakentodeveloptheoutcomesandrecommendationsthatresulted.

Itisanticipatedthatthisdocumentwillprovideassistanceindeterminingthefinalprojectdirection,specificationandscopeandwillbeausefulreferencedocumentastheproject/designevolves.

Page 74: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page4

3 Informationphase

3.1 Welcome-SureshSurendran

Sureshwelcomedtheparticipantstotheworkshopandthankedeveryoneformakingthenecessarytimeavailable.

Hepointedouttheimportanceofhavinginputfromabroadrangeofstakeholderswithdisparateviews,sothattheoptionultimatelyadoptedwillbestsatisfycommunity,functionalandfutureneeds.

3.2 Theworkshopprocess–DeclanTierney

Declanoutlinedtheproposedworkshopmethodologyandencouragedthegrouptobeopenandforthcomingastheycontributetodiscussionsthroughouttheday.

Heexplainedthattimewasshortandthereforegettingthoughalltheitemsontheagendawouldbechallenging.Hecommittedtocompletingtheprocessasefficientlyaspossible.

3.3 Departmentofplanning(DoP)overview–EvelynIvinson

EvelynspokeabouttheDepartmentofPlanning’soverallapproachtolanduseandrelease.

ThegroupwasaskedtolistanyassumptionsasaresultofwhatEvelyndiscussed.TheseareincludedSection4.3.

3.4 Objectives,BackgroundandScope–YvonneTsukame

YvonneusedaPowerPointpresentationtobringparticipantsuptospeedregardingtheprojectobjectivesandbackground.SeeSections4.2&4.2.1.

3.5 Theavailableoptions–DamianGoulder

Damianusedanelectronicpresentation/sketchestooutlinetheavailableoptionsandtohighlightspecificaspectofthealignmentsunderconsideration.Thismaterialwasreferredtoregularlyduringtheworkshoptoprovidecontextandtoaddressqueries.

Page 75: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page5

4 Analysisphase

The“AnalysisPhase”oftheworkshopwasusedtogainanunderstandingoftheunderlyingissuesandconstraintswiththepotentialtoimpacttheoptionsbeingconsidered.Itenabledparticipantstoclarifyobjectives,toexpressconcernsandtomakesuggestionsregardingthestrategicalignmentspresented.

4.1 Workshopobjectives

Itisimportantthatparticipantsareinagreementregardingthepurposeofaworkshopandactivitiesthatwilldeliverthedesiredoutcomes.Thishelpsmaintainfocusduringdiscussionsandkeeptheprocessontrack.Preliminaryworkshopobjectiveswerecirculatedpriortothesessionandthesewerepresentedtothegroupfordiscussion/endorsement.

Itwasagreedthatpursuingthefollowinggoalswouldhelpachievethedesiredoutcome:Ø Toconfirmtheoverallobjectivesunderpinningtheproject.

Ø Toupdateparticipantsoncurrentstatusoftheproject.

Ø Tointroducetheoptionsinvestigated.

Ø Toidentifyissuesandconcerns.

Ø Toagreeatasetofselectioncriteriaagainstwhichtoevaluatetheavailableoptions.

Ø Toassesstherelativemeritsoftheoptionsagainsttheselectioncriteria.

Ø Togenerateideasastohowtheavailableoption(s)couldbeimproved.

Ø Toreachrecommendations/agreements

Ø Todevelopanactionplantoensurethatprojectmilestonesareachievedandthatworkshopoutcomesareimplemented.

4.2 ProjectObjectives

ItwasrecognisedthattheNorthWestGrowthCentreRoadNetworkStrategyobjectiveswerenotavailableforadjustment.Nonetheless,theywererevisitedtoensurethatallparticipantswereconversantwiththeirinclusionsandthattheoptionsunderreviewwerealignedwiththesestrategicgoals.Theyare:

Ø ProvidearoadnetworkwithintheNWGCtosupporttheGovernment’surbanlandreleasestrategyfortheNWGCthroughtheprovisionofincreasedroadcapacitytomeetexistingandfuturetrafficandtransportgrowth.

Ø ImproveroadandtrainusersafetybyprovidingtheinfrastructurenecessarytoultimatelyclosefourexistinglevelcrossingsatGarfieldRoadatRiverstone,northofKingStreetatRiverstone,BandonRoadatVineyardandLevelCrossingRoadatVineyard.

Ø ReducetraveltimesbetweenWindsorRoadandRichmondRoad.

Ø ReducethenumberofthroughheavyvehiclemovementsthroughandneartheRiverstonetowncentre.

Ø ReducecongestionanddelaysacrosstheGarfieldRoadraillevelcrossing.Ø ProvidealternativeroutestocrosstheRichmondraillineandimprovetraffic

flowefficiencyandreducedelaysduringincidents.

Page 76: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page6

Ø ProvideaStrategythatcatersforbusservicesacrosstheregion,contributestoincreasedbus(andrail)travelmodesharesandreducestherelianceonprivatevehicletravelastheNWGCexpands.

Ø Deliverbenefitsforpedestrians,cyclistandlessmobilepeopleintermsofaccessibility,connectivity,safetyandamenityaspartoftheshort,mediumandlongtermProgram.

Ø EnhancefloodevacuationaccessacrosstheNWGCconsistentwithSESNWGCfloodevacuationplanning.

Theobjectiveswerediscussedandwereconfirmedtobeasfollows:

4.2.1 Broadobjective

TheparticipantsconfirmedthatthecorridoroptionspresentedattheVMworkshophadbeendevelopedwiththesestrategicobjectivesinmind.Inaddition,thefollowingbroadobjectiveinrespectoftheBandonRoadupgradewasestablished,asfollows:Ø Toaddresscurrentroadnetworkcongestionandsupportresidentialand

employmentgrowthintheregion.

4.3 Assumptions

Thegroupmemberswereaskedtolistassumptionsbeingmaderegardingtheproposedoptionsandtheinformationderivedfromtheearlierpresentations.ThesewerethendiscussedbythegroupindetailandeachwascategorisedasbeingaFact,aWorkingAssumption,QuestionableorIncorrect.

Theresultsfollow:

4.3.1 Facts

Ø CurrentlytheBandonRoadprojectisfundedonlyforplanning.Ø TheDP&Elanduseandinfrastructureplanwillbeexhibitedinthefirsthalfof

2016.Ø TfNSWisdevelopingaroadframeworkforthewholeofSydneyandBandon

Roadwillbeidentifiedasoneofthefutureprojectsinthatstrategy.

Ø TheuptakeoflandwithintheNWGCisoccurringfasterthanoriginallythoughtandthereforeroadinfrastructureneedstomatchthatuptake.

Ø MarsdenParkPrecinctwasplannedfor10,000dwellingsbuttodateCouncilhasreceivedDAandpre-DAapplicationsfor17,000.

Ø BandonRoadbetweentherailwaylevelcrossingandWindsorRoadiscurrentlydesignatedaregionalroadandisexpectedtobecomeastateroadwhentheupgradeiscompleted.

Ø ThenecessarylandfortheupgradecanbeacquiredinMarsdenParknorthPrecinct.

Ø Landacquisitionsmayresultintheneedtochangelanduseplanningadjacenttothecorridor.

Ø ApreliminaryarchaeologystudyhasbeenpreparedonbehalfofDP&Ewhichwillbeusedtoupdatetheconstraintsmap.

Ø AboriginalheritageiscapturedintheexistingRMSarchaeologicalreportpreparedbyKelleherNightingale.

Ø Theupgradewillbefourlaneswithprovisionforsixlanesinthefuture.Ø Thedesignwillprovideforanintegratedtransportcorridor.

Page 77: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page7

Ø TheroadnetworkinvestigationisalignedwiththeDoPhousingprojections/analysisfortheNWGC.

Ø Thewidthofthecorridorthatwillbereservedwillhavethecapacityforupgradetosixlanes.

Ø Aminimumof18monthswillberequiredforacquisitions,andthiswillbeincorporatedintheprogramfordeliveringtheproject.

Ø TheRichmondrailwaylinemaybeduplicatedinthefuture(10to20years).Ø Theunderpassoftherailwaylinewillbedesignedwiththefutureduplication

oftheRichmondrailwaylineinmind.Ø TherewillbeanimpactonAboriginalHeritage,whichwillbemanagedthrough

theREF.

Ø TheroadcorridorwillbeincorporatedaspartoftheprecinctplanningforMarsdenParkNorthandVineyardPrecincts.

Ø TheroadcorridorwilltakeintoconsiderationincreaseddensityasindicatedbyBlacktownCityCouncil.

Ø Thisroadisnotaregionalfloodevacuationroute.Ø Theupgradeisnotbeingdesignedtobeabovethe1in100yearfloodlevelfor

itsentirelength.Ø FloodingandfloodstorageisamajorissueinthevicinityofBandonRoad/the

upgrade.Ø Someoptionsassumethatcurrentlyunapprovedfillingproposalswilloccur.

Ø Europeanheritageisnotamajorconstrainttoanycorridoralignment.

Ø TheM9corridoralignmentisnotcurrentlyknownbutisexpectedtobeknownpriortocommencementofconstructionofthisproject.

Ø WallaceRoadwillberealignedtoconnectwithRiverstoneParadeandHamiltonStreetasarationalised/improvedfloodevacuationroute.

4.3.2 Workingassumptions

Ø ItisproposedtoconstructBandonRoadwhentheNWGCdevelopmentreaches25%ofultimatepopulationcapacity,itisestimatedthatthiswillbein2021(subjecttoavailabilityoffunding).

Ø TheoriginallyplannedminimumnumberofdwellingsfortheNWGCistwoorthreetimeslowerthanthenumberthatislikelytobeconstructedbasedonpreviouslyreceiveddevelopmentapplications.

Ø Theroadwillhavenoimpactontheregional1in100yearfloodstorage.Ø PartofBandonRoadmaybeafloodevacuationrouteattheeasternendon

thebasisthatitwouldprovideaflood-freelinktothefloodevacuationroute.

4.3.3 Questionable

Ø ThedesignintentionofprovidingfourlanesupgradabletosixonBandonRoadwillneedtoberevisitedinlightofdevelopmentoccurringwithintheNWGCandbeyond.

4.3.4 Incorrect

Noneoftheassumptionslistedwerefoundtobeincorrect.

Page 78: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page8

5 OptionAssessment

Inthisphaseoftheworkshop,theparticipantswereaskedtoconsidereachoftheavailableoptionsinmoredetailinanefforttoidentifytheconfigurationthatbestmeetsprojectobjectives.

Onceagain,RMS’ssketchesanddrawingswerereferencedtoensuretheworkshopattendeeshadacommonunderstandingoftheproposalsunderconsideration.

Thegroupwasaskedtoconsidertheadvantagesanddisadvantagesassociatedwiththevariousoptionsunderinvestigation.Thiswasdonetoassistinnarrowingdownthelisttoarriveatthepreferredoptiontobetakenforward.WithregardtotheWindsorRoadendofthealignment,thegrouphadlittledifficultyinagreeingthepreferredalignmentastheoptionswerelimitedbytheconstraintsthatexist.Accordingly,thegroupendorsedwideningonthesouthernsideoftheexistingBandonRoad.Howeveritwasagreedthatfurtherinvestigationswouldbeundertakenasthedesignisdevelopedtoexploreoptionstofinetunethealignmenttoachievetheoptimumconfiguration.Next,theworkshopfocussedonassessingtheremainderofthecorridoroptions,essentiallythealignmentswestoftheRichmondRailwayLine,whichnumbered14intotal(optionsA–N).SeeSketchbelow.

5.1 Cullingofoptions

Theoptionswerediscussedregardingtheirperformancerelativetotheobjectivesthathadbeensetfortheproject.Thegroupagreedthatseveralwerenotworthyoffurtherconsideration,astheyfailedtomeetprojectrequirements/objectives.

Thegroupallocatedaratingof“0”tooptionsthatitwasagreedwouldbeexcludedfromfurtherassessment.Thoserated“1”wereconsideredtohavemeritandwereshortlistedforexaminationingreaterdetail.

Page 79: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page9

Option Outcome Rating

A Thisoptionwillbeconsideredfurther(deletedinfavourof 0OptionI).

B Thisoptionisnotpreferredduetopoorperformance 0relativetoobjectives.

C Thisoptionisnotpreferredduetopoorperformance 0relativetoobjectives.

D Thisoptionisnotpreferredduetopoorperformance 0relativetoobjectives.

E Thisoptionisnotpreferredduetopoorperformance 0relativetoobjectives.

F Thisoptionisnotpreferredduetopoorperformance 0relativetoobjectives.

G Thisoptionisnotpreferredduetopoorperformance 0relativetoobjectives.

H Thisoptionisnotpreferredduetopoorperformance 0relativetoobjectives.

I ThisoptionispreferredoverOptionA. 0

J ThisoptionispreferredoverOptionI. 1

K ThisoptionissimilartoOptionJ. 1

L ThisisapositivealignmentfromanRMSperspective. 1

M ThisisapositivealignmentfromanRMSperspectiveand 1addressessomeissueswithOptionL.

N ThisoptionisnotpreferredbyRMS. 0

5.2 Keyfeaturesshortlistedoptions

Theshortlistedoptionsweredeterminedonthebasisofthefollowingkeyattributes:Ø Requiresshorterbridges-lowercost.Ø MinimisesearthworksneartheTransGridsubstation.Ø ConnectstoanalreadyidentifiedintersectionatMarsdenPark.

Ø AvoidstheTransGrideasementonthesouthernside,therebyminimisingearthworksandfloodstorageimpacts.

Ø Hugsthe1in100yearfloodcontourwherepossibleandthereforeminimisesfillrequired

5.3 Prosandconsassociatedwitheachoption

Next,inordertodocumentthelogicassociatedwiththedeletionoftheoptionsmentionedaboveaswellastherationaleunderpinningtheshortlistingofoptionsandtheeventualrecommendationtothepreferredalignment,theparticipantsdiscussedtheadvantagesanddisadvantagesassociatedwitheach.

Theresultsfollow.

Page 80: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page10

5.3.1 OptionA

Pros/advantages Cons/disadvantages

• None. • Requiresextensivelengthofbridge(>1,200m).

5.3.2 OptionB

Pros/advantages Cons/disadvantages

• None.

• Segregationoflanduse.

• Curvedbridgeratherthanstraight.

• Worksbestwitharailwayoverbridge.

• ImpactsonVineyardRailwayStation.

5.3.3 OptionC

Pros/advantages Cons/disadvantages

• None. • Extensivecrossingofthefloodplain.

• Wouldnotmeetthearterialroadfunction.

• Requiresextensivelengthofbridge(>2500m).

5.3.4 OptionD

Pros/advantages Cons/disadvantages

• None. • Extensivecrossingofthefloodplain.

• Requiresextensivelengthofbridge(>2600m).

• Wouldnotmeetthearterialroadfunction.

5.3.5 OptionE

Pros/advantages Cons/disadvantages

• None. • Extensivecrossingofthefloodplain.

• Requiresextensivelengthofbridge(>1700m).

• Potentialsegregationoflandissues.

5.3.6 OptionF

Pros/advantages Cons/disadvantages

• None. • Extensivecrossingofthefloodplain.

• Requiresextensivelengthofbridge(>1800m).

Page 81: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page11

5.3.7 OptionG

Pros/advantages Cons/disadvantages

• AvoidstheTransGrideasement. • Heavilyreliantonadditionalfill(1,400m3above1%floodlevel).

5.3.8 OptionH

Pros/advantages Cons/disadvantages

• AvoidstheTransGrideasement. • Requiresalargequantityoffill(2,100m3)whichneedstobeoffset.

• Doesnotconnectwiththedevelopedareastothesouth.

5.3.9 OptionI

Pros/advantages Cons/disadvantages

• AvoidstheTransGrideasementtothesouthernsideminimisingearthworksandfloodstorageimpact.

• BridgerequiredunderneaththeTransGridlines.

5.3.10 OptionJ

Pros/advantages Cons/disadvantages

• HasaslightlymoredirectlinethanOptionKatthewesternend.

• PotentiallylessnoiseimpactsondevelopedareasoverOptionsLandM.

• LessimpactonprimedevelopmentlandoverOptionsLandM.

• BridgerequiredunderneaththeTransGridlinescomparedtoOptionM.

• HaspotentialAboriginalheritageissuesascomparedtotheParkRoadoptions(LandM).

• Createsaboundaryroadratherthanaspineroad.

• ProvidesalessdesirableconnectionatMarsdenParkcomparedtoOptionM.

• Createssmallsegregatedareas.

5.3.11 OptionK

Pros/advantages Cons/disadvantages

• SimilartoOptionJwithlessenvironmental/heritageimpacts.

• HasaslightlylessdirectlinethanOptionJatthewesternend.

5.3.12 OptionL

Pros/advantages Cons/disadvantages

• Bridgeislocatedatthenarrowestpoint.

• UtilisesanexistingcorridorofParkRoad.

• ProvidesalessdesirableconnectionatMarsdenParkcomparedtoOptionM.

• BridgerequiredunderneaththeTransGridlinescomparedtoOptionM.

Page 82: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page12

Pros/advantages Cons/disadvantages

• ProvidesmoredevelopablelandbyusingpartoftheexistingParkRoadcorridor.

• Co-ordinationofutilitieshasalreadyoccurredinParkRoad.

• ProximitytotheexistingschoolonParkRoad.

5.3.13 OptionM

Pros/advantages Cons/disadvantages

• Providesawiderpotentialopeningforthecreek.

• AvoidsconstructionunderTransGridcables.

• ConnectswithamoresuitableintersectionatMarsdenPark(therecentlyconstructedElaraBlvd).

• Overallastraighteralignment.

• Moredirectrouteandthereforemoreattractive.

• Providesabetterfloodevacuationcontribution.

• ImprovesnetworkefficiencyonRichmondRoad.

• SmallincreaseinearthworksoverOptionL.

• Someimpactonidentifiedareasofvegetation.

5.3.14 OptionN

Pros/advantages Cons/disadvantages

None. • ThisalignmentistothenorthoftheTransGrideasementwhichisnotsupportedbyRMS.

• Excessivevolumeoffillrequired.

Page 83: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page13

6 Creativephase

6.1 Ideageneration

Sections3,4and5ofthisreportsummarisetheoutcomesofthefirstthreestagesoftheworkshopprocess-theInformation,AnalysisandOptionAssessmentphases.Theunderstandingsthatweredevelopedandtheinformationsharedanddiscussedprovidedaplatformforageneralbrainstormingofideastoimproveprojectoutcomes.Theideaswerealsoaimedatachievingtheprojectobjectivesbearinginmindtheconstraintsandissuesdiscussedearlierintheworkshop.

Theparticipantswereencouragedtocomeupwithideasastohowproblematicissuescouldberesolved.Theywereaskedtobeaswide-rangingaspossibleintheirthoughtprocessestoensurethatdueconsiderationwasgiventoimprovinganyaspectsoftheproject.

Thegoalwastorecordanyidea,regardlessofitslikelihoodofbeingimplemented.Inotherwords,initiallytheobjectivewastocollectasmanyideasaspossiblewithoutsubjectingthemtoanyformofscreeningorjudgement.Thisoccurredwhentheflowofsuggestionshadceased.

Theideasgeneratedtogetherwiththegroup’sassessmentofeachareincludedbelow.

Page 84: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland

7 Judgementphase

TheideasforoptionimprovementgeneratedintheCreativePhasewereassessedbythegroupintermsofpracticality,viabilityandcosteffectiveness.Eachideawasdiscussedandratedusingthefollowingcriteria. Recommendedforimplementation;

GoodIdea-needsfurtherinvestigation;orNotpractical.

Followingassessmentoftheidea,therationaleunderpinningtherankingwasarticulated.Theresultsofthediscussionfollow:

7.1 Ideasrecommendedforimplementation

“CANWE….?” Rationale Who/when

MakethelatestversionsofstudiesavailabletoRMSfromMarsdenParkNorthprecinct.

• WouldmakethelatestversionsofstudiesavailabletoRMSfromMarsdenParkNorthprecinct.

EvelynIvinsonJanuary2016

7.2 Ideasrecommendedforinvestigation

“CANWE….?” Rationale Who/when

RelocateOptionMslightlynorthatthewesternportion(retainthehingepointattheintersection).

• Thismayhelptominimiseenvironmentalimpacts–visual,Aboriginalheritageandthreatenedspecies(faunaandflora).

DesigndevelopmentteamOngoing

7.3 Ideasdeemedtobeimpractical

None.

Page14

Page 85: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland Page15

8 Workshopoutcomes

Havingcompletedtheworkshopprocessthefollowingoutcomes/agreementsemerged:

Ø ThegroupagreedthatintermsofthedifferentiatingfactorsforoptionsattheWindsorRoadend,itwaspreferredtowidentothesouthernsideoftheexistingBandonRoad.However,furtherinvestigationswouldbeundertakenduringthedesigndevelopmentprocesstooptimisethealignmentandtoaddvalue.

Ø TheparticipantsunanimouslyconfirmedOptionMasthegroup’spreferredoptiononthebasisoftheinformationdisseminatedanddiscussedattheworkshop.

Ø Itwasagreedthatoptionstominimiseenvironmentalimpactsatthewesternendofthealignmentwouldbeinvestigated.

Ø ItwasagreedthatRMSwouldcontinuetoworkwiththeDoPandCouncilstointegratetheproposedalignmentwithprecinctplanningdirections.

Ø ItwasagreedthatthealreadyapprovedzoneplanningintheRiverstoneprecinctwouldbemodifiedinresponsetotheadoptionofOptionMasthepreferredupgradealignment.

9 ActionPlan

Thegroupidentifiedthefollowingasadditionaltaskstopursue.

No Action Who When

1 ForwardthepreferredalignmenttotheprecinctplannersatameetingbetweenRMSandprecinctproponents

EvelynIvinson 31Jan16

2 InvestigatehowtheBandonRoadcorridormayconnecttothewidernetworkatthewestandeast

DamianGoulder 28Feb16

Page 86: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland

Appendices

Page 87: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland

Appendix1Participants/apologies

Page 88: Bandon Road Upgrade - Roads and Maritime Services · Bandon Road Upgrade Options Report . 3 . Contents. EXECUTIVE SUMMARY 4. 1 INTRODUCTION 8. 1.1 Background 8. 1.2 Purpose of this

BandonRoadUpgradeProjectOptionsAssessmentValueManagementWorkshop-Report

December2015 TierneyPageKirkland

AttendeesOrganisation Participant RoleonprojectRoadsandMaritimeServices

PeterWilliams PrincipalManager,ProjectDevelopment

SureshSurendran SeniorProjectDevelopmentMgr DamianGoulder ProjectDevelopmentManager YvonneTsukame ProjectDevelopmentManager KaliGupta ProfessionalServicesContractor SherrisseCollard ProjectDevelopmentOfficer PhilipBrogan Advisor RoyNunes PropertyOfficer ShahKshitij Network&SafetyServices JamesSuprain Network&SafetyServices DraganStefanovski LeadRoadDesigner PhilipCampbell RoadDesignManager JenniferWarren EnvironmentOfficer AnthonyEland EnvironmentManager GregFlynn StrategicLandUse DorotaMears WHSPartnerDept.ofPlanning EvelynIvinson LandUse/PrecinctPlanningBlacktownCityCouncil NadeemShaikh Traffic&TransportManager RobertPeterson ForwardPlanningEngineer ZaraTai StrategicPlannerHawkesburyCityCouncil PhilipPleffer StrategicPlanningCoordinatorTransportforNSW KenAmegor ExternalInterfaceManager HendrikVanieperen TransportPlannerTransGrid LindaButler SeniorLandEconomistParliament KevinConolly LocalMP,RiverstoneTierneyPageKirkland DeclanTierney WorkshopFacilitator RobynThelander AssistantFacilitator

ApologiesOrganisation Participant RoleonprojectRoadsandMaritimeServices

GrahamChristy SeniorProjectManager

AndrewPopoff SeniorLandUsePlanner GordonFarrelly MgrNetworkOptimisation

Planning(Sydney) MichaelSheridan UrbanDesigner JosephFanous EnvironmentManager JohnBetts ProjectAssurance&

CoordinationManager EmmaBrindley-Hawke LiaisonManager JenniferGatt SeniorC&SEOfficerDept.ofPlanning BruceColeman Director,LandRelease MichaelWoodland ConsultantBlacktownCityCouncil FionaMcDermott NWGCPrecinctPlanningTransportforNSW TimDewey SeniorTransportPlanner