23
www.tbst.dk 3. november 2017 Authorization of infrastructure in Denmark and Norway - similarities and differences Liz Anette Stordahl, Principal Engineer, Norwegian Railway Authority ([email protected] ) and Mari Ruuhi, Danish Transport, Construction and Housing Authority ([email protected] )

Authorization of infrastructure in Denmark and Norway .../media/Dokumenter/07 Jernbane/11... · Authorization of infrastructure in Denmark and Norway - similarities and differences

  • Upload
    halien

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

www.tbst.dk

3. november 2017

Authorization of infrastructure in Denmark and Norway -

similarities and differences

Liz Anette Stordahl, Principal Engineer, Norwegian Railway Authority ([email protected]) and Mari Ruuhi,

Danish Transport, Construction and Housing Authority ([email protected])

www.tbst.dk

3. november 2017

Today’s program

1. Introduction

2. EU framework for infrastructure authorisations

3. Authorisation of infrastructure in Norway

4. Authorisation of infrastructure in Denmark

5. Concluding remarks

www.tbst.dk

3. november 2017

Areas of responsibility - Danish

Transport, Construction and Housing

Authority

www.tbst.dk

3. november 2017

Areas of responsibility – Norwegian

Railway Authority

www.tbst.dk

3. november 2017

1. Introduction

Norway Denmark

Network Ca. 4208 km Ca. 3476 km

Large projects • ERTMS• New Line Follobanen• New railway tunnel

Bergen• Intercity• New line for Bergen

light rail

• Electrification Program• Signalling Program• New Line CPH-Ringsted• Ringsted-Fehmarn• Fehmarn fixed link• New metro line,

Cityringen• Aarhus & Odense Light

Rail

Infrastructuremanagers

• 1 major state-owned infrastructure manager (Bane NOR)

• 3 IMs responsible for the urban rail system (tram and metro)

• 1 major state-owned infrastructure manager (Banedanmark),

• 3 regional IMs, • 1 privately owned IM

(Arriva)• 1 IM responsible for metro

www.tbst.dk

3. november 2017

1. Introduction

Norway Denmark

NSA NSA:- Safety Management &

Supervision- Technology & Operations- Cableways & Amusement

Devices- Legal- Administration

Infrastructure authorization: 4 employees (engineers) + 1-2 resources from legal department.

NSA/Centre for Railway: - Authorization of

infrastructure, rolling stock, training (Train Drives Regulation)

- Approval of safety rules- Licenses and safety

certificates/authorizations - Supervision- Issuing administrative rules

Infrastructure authorization: 10 employees (6 engineers, 2 lawyers, 2 generalists) and 2 consultants.

APIS statistics

Approx. 70 APIS annually, incl. approx. 10 for urban rail

Approx. 60 APIS annually, incl. approx. 20 for urban rail (S-bane)

www.tbst.dk

3. november 2017

Togkart.banenor.no

4219 km railway2459 km electrified

246 km double track

www.tbst.dk

3. november 2017

1. EU framework for infrastructure

authorisations

One common railway system

Interoperability directives

- Gives conditions to achieve interoperability

- Framework for how to seek authorisation from the NSA to place the infrastructure in service

Photo: Rune Fossum

www.tbst.dk

3. november 2017

Interoperability Directive (2008)

Article 15 – Procedure for placing in service

Article 20 – Placing in service of existing subsystems after renewal or upgrading

www.tbst.dk

3. november 2017

2. Authorisation of infrastructure in Norway

www.tbst.dk

3. november 2017

2. Authorisation of infrastructure in Norway

Notification ApplicationNSA answer NSA APIS

Meetings, visits to projectsDocumentation updated if needed

IM sendsdocumentation

NSA reviewsdocumentation- TSI- Use of ISA

IM sendsdocumentation

NSA gives APIS

IM sends notificaton for all changes, except maintenance work NSA decides if need for application, based on documentation, the

complexity of the project and the safety manangement of theproject

No Application

www.tbst.dk

3. november 2017

Documentation required for a notification

Contact person

Progress plans

Regulations, standards and TSIs to be used

System Definition

Safety Plan (according to Cenelec 5012x)

Risk analysis

Assessment if the change is considered significant (CSM-RA) based on:Failure consequence

Novelty used in implementing the change

Complexity of the change

Monitoring

Reversibility

Additionality

www.tbst.dk

3. november 2017

Evaluation of notification

Larger probability of

failure in system

Less probablility of

failure in system

Simple system

Poor safety

managment

system

Extensive

safety

managment

system

Complex system

www.tbst.dk

3. november 2017

Documentation required for an application

Documentation from the notification IF updated

Safety Report

Safety Case

Hazard log

(If any) derogation from IM technical rules

Maintenance Plan

If needed:

TSI documentation (NoBo certificate, declaration etc)

AsBo report

ISA report

www.tbst.dk

3. november 2017

Ideal world

Full operation Full operationCommissioning

Track out of use

Time

www.tbst.dk

3. november 2017

APIS (following dir.)

Full operation Full operationCommissioning

Time

NSA approval

No traffic allowed!

Commissioning report

Remaining assessment by NoBo

www.tbst.dk

3. november 2017

APIS (in practice – Norway)

Full operation Full operationCommissioning

Time

NSA approval

Full operation (conditional)

NSA approval

Track out

of use

ISV from NoBo

Remaining assessment by NoBo

www.tbst.dk

3. november 2017

3. Authorisation of infrastructure in

Denmark

www.tbst.dk

3. november 2017

3. Authorisation of infrastructure in

Denmark

Need for an APIS or approval

Significant change

•Evaluation of significance is done by an infrastructure manager according to its safety management system

Renewal/upgrade of e.g. a station (PRM TSI)

•NSA decides whether APIS needed due to the TSIs

Significantchange & renewal/upgrade

•Significanceevaluation by the IM and NSA decision regarding TSIs

Authorisation of level crossing protection (road side)

•Separate approval

www.tbst.dk

3. november 2017

APIS procedure in Denmark

DTCA issues APIS

Actual time for putting into service

SAR relate to: - Design- Plan for activities- Risks in connection

with construction and taking into service

Attachment 1 to SAR:Evaluation of the construction and the putting into service -has it been done safely?

Attachment 2 to SAR:All safety related activities must be finalized

Max. 3 weeks Max. 6 weeks

Max. 6 months

Safety Assessment Report (SAR)

Intermediate Statement of Verification (ISV) on design level and technical file

Certificate and technical file

NoBo

• System definition• Applicants

statement (art. 16, CSM-RA)

• EC-verification (on design level)

• Updated system definition (if changed)

• Updated applicants statement (art. 16, CSM-RA)

• Final system definition (if changed)

• Final applicants statement (art. 16, CSM-RA)

• EC-verification (as built)

Applicant

CSM

-RA

AsBo

Time

Application for APIS

“EU” APIS

www.tbst.dk

3. november 2017

5. Concluding remarks

EU

- A project description shallbe sent to a MS who decides

whether a new APIS is needed

- New APIS is required if the overall safety level of the

subsystem may be adverselyaffected by the change

- If a new APIS is needed MS decides to what extent the

TSIs need to be applied

DK

•CSM-RA used to determinewhether APIS is needed(significant; safetyadversely affected)

•TSIs applied if major work(NSA decision)

•APIS typically issued beforecommissioning, suppliedwith final documentationfor safety and TSIs

NO

•All projects are notified to NSA who decides whetherAPIS is needed

•CSM-RA only used to determine whether AsBo is needed

•TSIs applied if major work(NSA decision)

•APIS typically issued close to commissioning, in some cases with conditions (final documentation)

SE

•All projects are notified to NSA who decides whetherAPIS is needed

•List of changes that do/don'trequire APIS

•TSIs are applied to all changes (regardles volume)

•CSM-RA not used in the APIS process

•Time-limited national approval, APIS issued before putting into service/all final documents are received

UK

•IM decides if APIS needed(acceptance panel, NSA a member), justification to NSA

•CSM-RA one of the criteria for deciding if APIS needed

•TSIs applied if deemed so by IM. All projects are in scope unless there is agreement that they are not

•APIS issued before the infrastructure is used, usually with conditions/limitations

NL

•All projects are notified to NSA who decides whetherAPIS is needed

•CSM-RA used to determinewhether APIS is needed(significance)

•TSIs applied is APIS needed (NSA decision)

•Derogation issued first(construction), APIS issuedafter putting into service/ all final documents arereceived

www.tbst.dk

3. november 2017

5. Concluding remarks

DK NO SE UK NL

Review process 3 weeks 4 weeks(notification)

4 months (APIS)

4 months 4 weeks 8 weeks(notification)

8 weeks (APIS)

Fee 2017: 850 DKK/hour

2018: 800 DKK/hour

(approx. 114 € / 107 €)

No fee, the NSA examines the possibility for introducing a fee for the approvals

1.600 SEK/hour

and 2.800 SEK for each issued decision or approval

(approx. 166 €/hour and 292 €/decision or approval)

No fee, activities are funded by safety levy, which is based on the turnover of each railway service provider

Notification: 5000 €

APIS: 113 €/hour

www.tbst.dk

3. november 2017

Questions?

Thank you for your attention!