Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Att
ach
me
nt
E
Attachment E
EMISSIONS
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:04
ATTACHMENT NO E EMISSIONS
CONTENTS ATTACHMENT E.1 – EMISSIONS TO ATMOSPHERE............................................ E-1
Point Emissions to Atmosphere..............................................................................E-2
Fugitive and Potential Emissions........................................................................... E-5
ATTACHMENT E.2 – EMISSIONS TO SURFACE WATER...................................... E-7
Summary List of Emission Points........................................................................... E-7
Surface Water Philosophy...................................................................................... E-8
ATTACHMENT E.3 - EMISSIONS TO SEWER......................................................... E-9
Summary List of Emission Points........................................................................... E-9
ATTACHMENT E.4 – EMISSIONS TO GROUND................................................... E-11
ATTACHMENT E.5 – NOISE EMISSIONS.............................................................. E-12
ATTACHMENT E.6 – TABULAR DATA ON EMISSION POINTS............................E-16
FIGURES................................................................................................................. E-18
TABLES
Table E.1 Scheduled Emission Points to Atmosphere Source Characteristics......... E-3
Table E.2 Operational External Fixed Plant Noise Sources.....................................E-14
Table E.3 Tabular Data on Emission Points............................................................ E-16
FIGURES
Figure E.1 Location of Emissions to Atmosphere, Surface Water & Sewer.............E-18
Figure E.2 Operational Noise Source Locations................................................. E-18
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:04
ATTACHMENT NO E EMISSIONS
Proposed Renewable Bioenergy Plant E-1 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
ATTACHMENT E.1 - EMISSIONS TO ATMOSPHERE An Air Quality assessment undertaken by Odour Monitoring Ireland is included as
Chapter 8 of the EIS (Volume II). The assessment describes the potential impacts to
ambient air quality from the Huntstown Renewable Bioenergy plant. A worst case of
assessment was utilised throughout the study in order to assess any risk associated
with the operation of the plant. Particular attention is given to the potential exposure of
receptors to airborne pollutants resulting from the development and operation of the
plant. Sensitive receptors, including local business units and residential dwellings
within circa 1 kilometre (km) of the subject site and designated ecological sites up to
15 km have been included in the assessment.
The assessment has been carried out in line with all relevant guidelines. In terms of
odour, the EPA’s Air Dispersion Modelling from Industrial Installations Guidance Note
(AG4) was taken into account. This document was used to assess whether the plant
is likely to give rise to odour impact at identified sensitive receptors.
The air modelling study (using AERMOD Prime) demonstrates that emission levels as
a result of the operation of the plant will not result in any air quality impact in line with
Irish and European assessment criteria limits. The air quality emissions from each of
the gas utilisation engines will exhaust through a 28m stack, the flare will exhaust
through an 8m stack and the odour control system through a 25m stack.
In terms of odour, Huntstown Power Station (immediately north of the site), is
identified as the worst case receptor with a maximum predicted ground level
concentration (GLC) of odour less than or equal to 0.88 OuE/m3 at the 98th percentile
of hourly averages for the worst case meteorological year Dublin 2004. This is just
58% of the odour impact criterion of 1.5 OuE/m3 stated in Agency’s Guidance AG4
(page 70).
In addition, the maximum predicted odour concentration anywhere in the vicinity of the
plant (including inside and outside the boundary of the facility and within the fine grid
area of 4.0 km sq and 36 km sq and a course grid area of 361 km sq) will be less than
or equal to 1.0 OuE/m3 for the 98th percentile of hourly averages for the worst case
meteorological year Dublin Airport 2004. This is 66% of the worst case odour impact
criterion of 1.5 OuE/m3 stated Agency’s Guidance AG4 (page 70).
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:04
ATTACHMENT NO E EMISSIONS
Proposed Renewable Bioenergy Plant E-2 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Fugitive emissions of odours will be negligible as all buildings and processes
containing odorous activities will be of high containment integrity (near 100% integrity)
and all areas where odorous activities occur will be placed under negative extraction.
The Air Quality and Climate assessment demonstrates that the controls built into the
facility mean that emissions to air from the plant will have no significant adverse
effects on air quality. All predicted ground level concentrations (GLCs) at or beyond
the facility boundary will be in compliance with air quality limit values for both the
protection of human health and flora and fauna.
Point Emissions to Atmosphere
Summary List of Emission Points The plant will have three primary point source emissions as follows:
• A2-1: a single multi-flue stack which will discharge the residual levels of
pollutants from 2 x 2MW combined heat and power (CHP) engines and the
standby boiler to atmosphere at a height of 28m above ground level;
• A2-3: a standby gas flare which can be used to combust excess biogas when
combustion by the CHP or storage in the gas holder is unavailable;
• A2-4: odour control stack through which treated air from the odour control
system will be vented for dispersion to atmosphere at a height of 25m above
ground level.
The locations of the proposed scheduled emission points are presented on Figure E.1
at the end of this attachment. The grid reference for each is:
• A2-1: E311445, N241219
• A2-3: E311480, N241202
• A2-4: E311336, N241266
It should be noted by the Agency that Chapter 8 of the EIS refers to emission point
A2-2; this is captured in A2-1 as it is a single multi-flue stack and is therefore not
referenced in this Industrial Emissions License (IEL) application.
Plans of each of these emission points are included as the following drawings within
the Planning Drawings which accompany this application:
• PL27 – Odour Control System and Stack
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Proposed Renewable Bioenergy Plant E-3 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
• PL29 – Flare Stack
• PL30 – CHP Engine Containers and Stack
Further details of each of the three scheduled emission points are provided in Table
E.1 below including, emission point location, height, stack tip diameter, efflux velocity,
exhaust actual airflow volume, worst case building / structure height etc.
Table E.1 Scheduled Emission Points to Atmosphere Source Characteristics
Parameter Emission point
A2-1 (multi-flue stack)
Emission point A2-3
Emission point A2-4
Emission point description Gas Engines 1 & 2 combined
Flare Odour Control
Stack
X coordinate (m) 311445 311480 311336
Y coordinate (m) 241219 241202 241266
Stack height (m) 28 8 25
Stack tip diameter (m) 0.7 2.80 1.5
Volume flow (Am3/hr) 22,667 210,835 110,000
Flue gas temperature (K) 423 1273 293
Efflux velocity (m/s) 16.36 9.51 17.29
Stack orientation Vertical Vertical Vertical
Stack base level A.O.D (m) 77 77 77
Receptor height (normal breathing level) (m)
1.80 1.80 1.80
Max building / tank height (m) 25.42 25.42 25.42
Building base level A.O.D (m) 77 77 77
All pollutants likely to be emitted from the named emission points A2-1, A2-3 and A2-4
were taken account of in the impact assessment and include the following compounds
as listed in the Environmental Protection Agency (Industrial Emissions) (Licensing)
Regulations 2013 S.I. 137 of 2013:
• Carbon monoxide
• Oxides of nitrogen
• Sulphur dioxide
• Total particulates
• Total non-methane volatile organic compounds.
In addition to the compounds listed above, the following were also assessed:
• Odour units, and
• Ammonia
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Proposed Renewable Bioenergy Plant E-4 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Tables 8-18, 8-19, 8-20 and 8-25 contained within Chapter 8 of the EIS (Volume II)
should be referenced for further supporting information on each emission point.
These Tables outline the air phase gas concentration and mass emission rate of each
pollutant assessed within the dispersion model. Sections 8.97 to 8.138 of the
assessment reports on the modelling performed.
Tables The following Tables have been completed and are presented in the main application
form:
• Table E.1 (i) for boiler emissions (A2-1)
• Table E.1 (ii) for combined boiler and gas utilisation stack emissions (A2-1)
• Table E.1 (ii) for biogas flare emissions (A2-3), and
• Table E.1 (ii) for odour control stack emissions (A2-4), and
• Table E.1 (iii) for emissions points A2-1, A2-3 and A2-4
It was not considered necessary to complete Table E.1 (iv) for minor emission points
or E.1 (v) for fugitive and potential emissions. A number of measures, as outlined in
the Fugitive and Potential Emissions section below, are incorporated into the design
to ensure that fugitive emissions of odours are minimised from the plant.
Odour Abatement All odorous air will be vented through a three stage odour treatment process
comprising a biotrickling filter, plasma injection treatment and carbon polishing to
deodorise the collected air. Treated air will be vented through a 25m stack to provide
further dispersion as a final protection.
The overall system will be capable of achieving an exhaust odour threshold
concentration of less than 1,000 OuE/m3 with a typical value in the exhaust stream of
700 OuE/m3.
A comprehensive description and schematic of the odour control system are
presented in Attachment F.1 of this application.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Proposed Renewable Bioenergy Plant E-5 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Fugitive and Potential Emissions It was not considered necessary to complete Table E.1 (v) for fugitive and potential
emission points. There will be no fugitive emissions to atmosphere due to mitigation
measures incorporated into the design of the plant as outlined below.
Odour Emissions Potential impacts associated with odours have been considered within the Air Quality
and Climate Assessment. Measures incorporated into the design of the plant will
ensure that there are no fugitive emissions of odours to atmosphere, they include:
• All waste handling and pre-treatment activities will be carried out indoors at the
facility;
• All buildings and processes containing odorous activities will be of high
containment integrity (near 100% integrity);
• Extraction systems in the reception area of the main building will maintain
negative pressure inside all areas where waste is handled and processed.
This will encourage air to flow into the building, thus further preventing
uncontrolled egress of odour;
• All external process features, such as pipework and tanks, will be enclosed and
sealed, with negative extraction applied to ensure no fugitive emissions of odours
during operation;
• The waste intake buildings will be fitted with rapid roller doors which will be
interlocked and fitted with air curtains so as to maintain good building integrity in
terms of odour containment (main access doors only) when doors are opened
intermittently during delivery of feedstock;
• Pedestrian doors will remain closed and only open when access is required.
This will ensure the risk of egress of odour through building apertures is
minimised;
• All odorous air will be vented through a three stage odour treatment process to
deodorise the collected air. In addition, this treated air will be vented through a
25m stack to provide further dispersion as a final protection;
• There will be no emissions to atmosphere from the digestion tanks or other
process vessels containing odorous materials as waste will be contained
within fully sealed tanks; and
• The combustion of biogas by the CHP units or gas flare will destroy any
potentially odorous compounds contained in the biogas. The proposed design
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Proposed Renewable Bioenergy Plant E-6 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
of a 28m high stack is considered to represent a good level of environmental
performance, to ensure adequate dispersion.
Dust The process has been designed to control emissions of dust. Waste will be delivered
and pre-treated entirely in an enclosed building maintained under sub-atmospheric
pressures to contain, collect and treat dust and particles. The Air Quality assessment
demonstrates that dust and particulate emissions will not be significant during the
operational phase.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Proposed Renewable Bioenergy Plant E-7 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
ATTACHMENT E.2 - EMISSIONS TO SURFACE WATER A hydrological assessment undertaken by SLR Consulting Ltd. is included as Chapter
13 of the EIS (Volume II). The assessment describes the potential impacts to surface
water from the plant.
The report is based on a desk study review of published hydrological data for the
area, a review of previous hydrological investigations carried out at the Huntstown
Quarry complex, and a site walkover.
The site lies within the catchment of the Ballystrahan Stream which is a sub-
catchment of the Ward River to the north. All treated excess surface water runoff from
the site will drain from the existing quarry drainage network north to the Ballystrahan
Stream, which drains downstream to the Ward River and ultimately to the Irish Sea at
Swords.
The water quality in the Ballystrahan Stream is classified as ‘good’ however water
quality in the Ward River is ‘poor’, mainly due to diffuse agricultural pollution and
dredging. Drainage in the Ballystrahan Stream and Ward River has been augmented
by an Arterial Drainage Scheme implemented in the 1960s, with ongoing maintenance
by the Office of Public Works (OPW).
The combined discharge of treated water from Huntstown Quarry and Huntstown
Power Station is discharged to the Ballystrahan Stream under licence at the northern
boundary of the quarry site.
The site is not located in a flood prone area, however preliminary flood risk
assessment mapping by the OPW suggests that there could be some pluvial (rainfall)
flooding at the site in an extreme event. Mitigation measures have been proposed to
address the potential impacts and the residual impact of the proposed development
on the surface water environment is expected to be ‘imperceptible’.
Summary List of Emission Points There will be one point source emission to surface water (SW1) from the plant,
located at E-311412, N-241300. Only treated excess storm water runoff will be
discharged from this point to the existing quarry drainage network. It is estimated that
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Proposed Renewable Bioenergy Plant E-8 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
an average of approximately 12m3 per month of clean runoff will be discharged after
rainfall harvesting.
The location of the discharge point together with an outline of the surface water
drainage system is presented on Drawing PL37. Typical details for various elements
of the surface water drainage system are provided on Drawing PL38. All drawings
are located within the Planning Drawings which accompany this application.
Details of the characteristics of the surface water emissions are presented in Tables
E.2(i) and E.2(ii) of the main application form.
There will be no emissions of substances listed in the Schedule of EPA (Industrial
Emissions) (Licensing) Regulations 2013 S.I. No. 137 of 2013.
Surface Water Philosophy The surface water drainage system has been designed to discharge excess runoff
into the existing storm water open ditch to the north of the existing main access road.
It is estimated that an average of approximately 12m3 per month of clean runoff will be
discharged after rainfall harvesting.
A comprehensive description of the surface water philosophy and schematic are
presented in Attachment F.1 of this application.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Proposed Renewable Bioenergy Plant E-9 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
ATTACHMENT E.3 - EMISSIONS TO SEWER This section should be read in conjunction with Chapter 2 (Sections 2.62-2.71) of the
EIS (Volume II) and Appendix 13-3 (Section 2.4) of the EIS (Volume III) which
present details of the foul water drainage philosophy for the site.
Summary List of Emission Points There will be one point source emission to sewer (SE1) at E-311319, N-241278. It is
estimated that up to 200m3/day of treated process effluent will be discharged to the
sewer.
The discharge will not contain any List I substances as defined in the Annex to EU
Directive 2006/11/EC (as amended) but List II compounds may be present in trace
amounts.
The location of the discharge point at the south western boundary of the site together
with the foul sewer drainage layout plan is presented on Drawing PL39. Typical
details for various elements of the foul sewer drainage system are provided on
Drawing PL40. All drawings are located within the Planning Drawings which
accompany this application.
Details of the characteristics of the sewer emission point are presented in Tables
E.3(i) and E.3(ii) of the main application form.
Effluent Treatment System The plant incorporates an on-site Wastewater Treatment Plant (WwTP) (see Drawings
PL17-20), comprising the following elements:
• 1 no. process liquor tank which will acts as a storage facility for liquid
digestate from the centrifuge.
• 3 no. sequential batch reactor in which the biological process of removing
Biological Oxygen Demand (BOD) and ammonium takes place.
• 1 no. sludge tank for holding sludge recovered from the WwTP.
• 1 no. process water tank to hold process effluent to be recycled back to the
AD process or discharged to sewer.
• 1 no. pumping station for pumping treated process effluent to the mains
sewer.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Proposed Renewable Bioenergy Plant E-10 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Treatment Process This facility will treat separated liquid digestate from the centrifuge (water fraction)
stage of the AD process. Process water discharged from the wheelwashes and
vehicle wash will also be diverted to the onsite WwTP. However, it should be noted
that runoff from the washing of the main building floor will be captured and recycled
directly to the AD process. Wastewater effluent from the welfare facilities will be
discharged directly to the public sewer.
The treated process water from the WwTP is recycled into the main process and is
used to dilute the incoming feedstock. Excess treated process water that is not
required for the process will be discharged to the municipal sewer. It is estimated that
up to 200m3/day of treated process effluent will be discharged to the sewer. This
effluent will have a significantly reduced organic loading following the treatment in the
on-site WwTP, with a maximum population equivalent of approximately 750 (based on
1 PE = 54g of BOD per day).
Receiving Sewer Due to the low surface gradient and relatively flat nature of the topography, a
packaged pumped system with two standby pumps will be installed. A foul water
rising main of 100mm diameter will be constructed that will connect the plant with the
municipal sewer network at a point located on North Road (see Drawing PL39). The
rising main will extend to an outfall chamber to be located on the eastern side of the
North Road. From this point south, the foul water sewer line will change to a gravity
fed system and discharge into the existing foul water manhole. The distance from the
foul water discharge point on site to the existing manhole on the eastern side of the
North Road is approximately 1000m.
Effluent from the municipal sewer will ultimately be treated at the Ringsend WwTP
prior to discharge to the Irish Sea.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Proposed Renewable Bioenergy Plant E-11 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
ATTACHMENT E.4 - EMISSIONS TO GROUND There will be no direct discharge to ground from the plant. The plant will be
constructed on an impermeable surface with the main process tanks contained within
bunded areas with the capacity to store 110% of the content of the largest tank.
Mitigation measures contained within Chapter 12, Soils and Geology and Chapter
14, Hydrogeology of the EIS (Volume II) will ensure that there are no emissions to
ground.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Proposed Renewable Bioenergy Plant E-12 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
ATTACHMENT E.5 - NOISE EMISSIONS A Noise Impact Assessment undertaken by SLR Consulting Ltd. is included as
Chapter 10 of the EIS (Volume II). This section should be read in conjunction with
the assessment which considers the impact of the noise generated during both the
construction and normal operational phases of the plant on the nearest noise sensitive
locations (NSL’s).
The methodology for the noise assessment has been undertaken in accordance with:
• BS5228-1:2009 ‘Code of practice for noise and vibration control on
construction and open sites – Part 1: Noise’, and
• ‘Guidance Note for Noise: Licence Applications, Surveys and Assessments in
Relation to Scheduled Activities (NG4)’ published by the Environmental
Protection Agency (EPA) Office of Environmental Enforcement (OEE), 2012.
As detailed design engineering has not yet been undertaken, it should be noted by the
Agency that the provision of noise data in frequency bands is not available for this
assessment. In the absence of frequency level data this assessment uses sound
power levels, with a plus 5dB(A) tonal or impulsive adjustment added to each noise
source within the noise model to provide for the worst case scenario as provided for
in the EPA’s NG4 Guidance.
Noise predictions have been made using the noise software modelling program
Cadna-A. This program takes into account the distance between the sources and the
receptors, and the amount of attenuation due to atmospheric absorption. The
program assumes downwind propagation, and for this assessment it has been
assumed that the ground between the source and the receiver has an absorbency
value of 0.5.
Noise monitoring was undertaken at six monitoring locations which included four
NSL’s; a location at the boundary of the site and a location within the site. This
baseline monitoring establishes that the study area can be designated as ‘not an area
of low background noise’ in accordance with the standards set out in NG4.
The modelling undertaken as part of the assessment demonstrates that the NG4
noise criterion limits as prescribed for daytime, evening, and night-time are
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Proposed Renewable Bioenergy Plant E-13 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
comfortably met at all four NSL’s (Locations 1-4) and at Location 6, the site boundary
location. The construction noise assessment demonstrates that noise generated by
worst-case construction operations are within the specified limits at all of the locations
assessed.
Summary List of Emission Points The operational external fixed plant noise sources associated with the plant are
described in Table E.2 below with further details presented in Table E.5 (i) contained
within the main application Form. The location of emission points are provided on the
Figure E.2 at the end of this attachment.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Renewable Bioenergy Plant E-14 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Table E.2 Operational External Fixed Plant Noise Sources
Noise Source Number Plant Description
N1 & N2 2 x 2MW CHP Engines Gas engine fuelled by the biogas from the process. Generating renewable electricity for export to the national grid and heat for use in the process.
N2 28m CHP Stack
The CHP engines will discharge the residual levels of pollutants to atmosphere from a single multi-flue stack at a height of 28m above ground level.
N3 Biogas Flare
A standby gas flare which can be used to combust excess biogas when combustion by the CHP or storage in the gas holder is unavailable
N4 & N5 2 x Gas Boosters
Rotary machine which boosts the gas pressure to the required level for supply to the engines.
N6, N7 & N8 Positive Displacement Pumps Pumps used for pumping organic slurry from one tank to another.
N9 Odour Control Fan Centrifugal fan used to create the pressure drop to move air from the sources of odour to the odour treatment plant.
N10, N11, N12 & N13 4 x Digester Mixer Large big blade mixer, with an external gear box and electric motor.
N14 & N15 2 x Pasteuriser Mixer Mixer mounted on pasteuriser vessel to keep contents of pasteuriser tanks mixed.
N16 Standby Boiler Standby boiler used during commissioning and maintenance to provide heat to the digesters when the CHP engines are not running.
N17 Emergency Generator Packaged standby emergency generator. Provides electricity in the event of a power cut.
N18 SBR Blowers Rotary machine (Roots Type Blower) which takes ambient air and pressurises it sufficiently to be able to flow into the SBR tanks.
N20 to N25 Waste Pre-treatment
Stage 1 Supplier Dependant. Typically shredding, macerating, hammer mill, rotary chain. To break up the packaging.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Renewable Bioenergy Plant E-15 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
N20 to N25 Waste Pre-treatment
Stage 2 Supplier Dependant. Typically removing packaging through a screen/press.
N20 to N25 Waste Pre-treatment
Stage 3 Supplier Dependant. Typically conditioning the waste prior to mixing. i.e. mixing, straining or pressing.
N26 & N27 2 x Biomass Mixer Supplier Dependant. Typically a large mixing blade on top of a vessel to which water/slurry/liquid wastes are added and mixed.
N28 & N29 2 x Centrifuge Dewatering High speed machine which separate water and solids using gravity generated in the rotating machine. Solids are ejected by a screw within the machine.
N30, N31 & N32 3 x Centrifugal Pumps Used to pump water between tanks.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Renewable Bioenergy Plant E-16 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
ATTACHMENT E.6 - TABLULAR DATA ON EMISSION POINTS Please also see separate CD-Rom included with this application entitled IED Licence
Application Sections B.2, E.6 and F.3 which contains section E.6 in excel as required
by the Agency.
Table E.3 Tabular Data on Emission Points
Point Code Point Type Easting Northing Verified Emission
A2-1 A 311445 241219 N
CO, NO2, SO2, PM10, PM2.5, Total non methane, Volatile organic compounds,
NH3
A2-3 A 311480 241202 N
CO, NO2, SO2, PM10, PM2.5, Total non methane, Volatile organic compounds,
NH3
A2-4 A 311336 241266 N NH3
SW1 SW 311412 241300 N Treated storm water
SE1 SE 311319 241278 N BOD, COD, NH4, Suspended Solids, pH
N1 N 311445.438 241224.770 N dB(A)
N2 N 311449.564 241233.715 N dB(A)
N3 N 311428.464 241227.008 N dB(A)
N4 N 311443.746 241246.800 N dB(A)
N5 N 311442.732 241245.814 N dB(A)
N6 N 311457.154 241275.621 N dB(A)
N7 N 311502.850 241252.974 N dB(A)
N8 N 311474.071 241269.383 N dB(A)
N9 N 311339.170 241279.275 N dB(A)
N10 N 311497.018 241265.059 N dB(A)
N11 N 311513.921 241257.820 N dB(A)
N12 N 311488.779 241248.170 N dB(A)
N13 N 311505.668 241239.930 N dB(A)
N14 N 311461.294 241285.566 N dB(A)
N15 N 311454.069 241269.662 N dB(A)
N16 N 311446.788 241249.758 N dB(A)
N17 N 311388.909 241259.572 N dB(A)
N18 N 311328.743 241320.434 N dB(A)
N20 N
311391.175 241278.546
N dB(A)
N21 N N dB(A)
N22 N N dB(A)
N23 N N dB(A)
N24 N N dB(A)
N25 N N dB(A)
N26 N 311391.175 241278.546
N dB(A)
N27 N N dB(A)
N28 N 311357.130 241276.023 N dB(A)
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Renewable Bioenergy Plant E-17 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
N29 N 311362.088 241272.952 N dB(A)
N30 N 311319.911 241332.561 N dB(A)
N31 N 311327.038 241341.464 N dB(A)
N32 N 311322.163 241350.535 N dB(A)
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO E EMISSIONS
Renewable Bioenergy Plant E-18 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
FIGURES
Figure E.1 Location of Emissions to Atmosphere, Surface Water & Sewer
Figure E.2 Operational Noise Source Locations
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
4446
34
27
33
1
4
13
10
2
3
29
28
43
45
17
9
23
22
363738
3940
41
42
35
47
49
48
50
14
+78.000
+78.000
+79.335
1516
Site Layout and Proposed Emission and Sampling LocationsScale 1:1000 / A3
N
W
S
E
31 Rainey Street, Magherafelt, BT45 [email protected] www.visiondesign.org.uk
Tel: 028 7930 0866
NOTES
Scale Date
1. BASED ON 1:1000 & 1:2500 ORDNANCE SURVEY IRELANDDIGITAL MAPPING - MAP NO's. - 3063A, 3063C, 3062B, 3062C, 3062D,3130A, 3130B, 3131-01 & 3131-06
2. ORDNANCE SURVEY IRELAND LICENCE NO. AR 0116513 (C)ORDNANCE SURVEY & GOVERNMENT OF IRELAND
3. © COPYRIGHT RESTS WITH VISION DESIGNTHIS DRAWING MAY NOT BE REPRODUCED WHOLLY OR IN PARTWITHOUT THE EXPRESS WRITTEN PERMISSION OF VISION DESIGN
LEGEND
Revision Drawn By Chkd By Date Comments
CLIENT:
16.06.14RD RD-
Renewable Bioenergy PlantProposed Huntstown
Finglas, Dublin 11Huntstown, North Road,
Emission and Sampling Locations
Title - Site Layout and Proposed
June 20141:1000 / A3
2388 - Figure E.1
Huntstown Renewable BioEnergy PlantApplication Area (c 2.382 ha)
Existing wayleave for 220 kv cable to HuntstownPower Station
Proposed new sewer line from pumping station
KEY TO BUILDINGS AND PLANT
Proposed emission and sampling locations
Emission Ref Easting NorthingA2-1 (Combinedemission point)
311445 241219
A2-3 311480 241202A2-4 311336 241266SW1 311412 241300SE1 311319 241278
EMISSION REFERENCE TABLE
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
PAST.
PAST.
TO301PREPAST
31 Rainey Street, Magherafelt, BT45 [email protected] www.visiondesign.org.uk
Tel: 028 7930 0866
NOTES
Scale Date
1. BASED ON 1:1000 & 1:2500 ORDNANCE SURVEY IRELANDDIGITAL MAPPING - MAP NO's. - 3063A, 3063C, 3062B, 3062C, 3062D,3130A, 3130B, 3131-01 & 3131-06
2. ORDNANCE SURVEY IRELAND LICENCE NO. AR 0116513 (C)ORDNANCE SURVEY & GOVERNMENT OF IRELAND
3. © COPYRIGHT RESTS WITH VISION DESIGNTHIS DRAWING MAY NOT BE REPRODUCED WHOLLY OR IN PARTWITHOUT THE EXPRESS WRITTEN PERMISSION OF VISION DESIGN
LEGEND
Revision Drawn By Chkd By Date Comments
CLIENT:
16.06.14RD RD-
Renewable Bioenergy PlantProposed Huntstown
Finglas, Dublin 11Huntstown, North Road,
Operational Noise Source Locations
Title: Site Layout and Location of
June 20141:1000 / A3
2388 - Figure E.2
N
W
S
E
Location of operational fixed plant noise sources(see table E.2 for descriptions)N21
Point Source Reference Table
Point CodePointType Easting Northing
N1 N 311445 241225
N2 N 311450 241234
N3 N 311428 241227
N4 N 311444 241247
N5 N 311443 241246
N6 N 311457 241276
N7 N 311503 241253
N8 N 311474 241269
N9 N 311339 241279
N10 N 311497 241265
N11 N 311514 241258
N12 N 311489 241248
N13 N 311506 241240
N14 N 311461 241286
N15 N 311454 241270
N16 N 311447 241250
N17 N 311389 241260
N18 N 311329 241320
N20 N
311391 241279
N21 N
N22 N
N23 N
N24 N
N25 N
N26 N311391 241279
N27 N
N28 N 311357 241276
N29 N 311362 241273
N30 N 311320 241333
N31 N 311327 241341
N32 N 311322 241351
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
Att
ach
me
nt
F
Attachment F
CONTROL & MONITORING
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
CONTENTS ATTACHMENT F.1 – TREATMENT, ABATEMENT & CONTROL ............................ F-1
Air Quality ............................................................................................................. F-1
Surface Water Drainage ....................................................................................... F-7
Foul Water Drainage .......................................................................................... F-10
Noise Abatement ................................................................................................ F-11
Process Control Monitoring ................................................................................ F-12
Inspection, Maintenance and Monitoring ............................................................ F-13
Contingency Plans for Plant Breakdown ............................................................. F-13
ATTACHMENT - F. 2 – EMISSIONS MONITORING & SAMPLING ....................... F-15
Air Monitoring Methodology ................................................................................ F-15
Surface Water Monitoring Methodology .............................................................. F-16
Sewer Monitoring Methodology .......................................................................... F-17
Noise Monitoring Methodology ........................................................................... F-17
Dust Monitoring Methodology ............................................................................. F-17
ATTACHMENT - F. 3 – TABULAR DATA.............................................................. F-18
FIGURES ............................................................................................................... F-19
TABLES
Table F.1 Proposed Emissions Monitoring and Sampling Points ............................ F-15
Table F.2 Permitted Rating Noise Levels ............................................................... F-17
Table F.3 Tabular Data on Monitoring and Sampling Points .................................. F-18
FIGURES
Figure F.1 Schematic of Odour Control System ..................................................... F-19
Figure F.2 Schematic of Anaerobic Digestion Process Flow .................................. F-19
Figure F.3 Schematic of Surface Water Drainage System Flow ............................. F-19
Figure F.4 Schematic of Foul Water Drainage System Flow .................................. F-19
Figure F.5 Location of Proposed Emissions Monitoring & Sampling Points for Atmosphere, Surface Water and Sewer ................................................................. F-19
Figure F.6 Location of Proposed Noise Monitoring Locations ................................. F-19
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-1 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
ATTACHMENT F.1 - TREATMENT, ABATEMENT & CONTROL This attachment provides an overview of the main abatement and control aspects of
the plant. A number of the assessments contained within the Environmental Impact
Statement (EIS) should be read in conjunction with this attachment, namely Chapters
8 (Air Quality and Climate), 10 (Noise and Vibration), 12 (Soils and Geology), 13
(Hydrology) and 14 (Hydrogeology). These chapters provide detailed information on
abatement and treatment procedures for the activity under the mitigation sections.
All drawings referenced as PL within this Attachment are presented within the
Planning Drawings which accompany this application.
Table F.1(i) has been completed for each emission point, these tables are presented
within the application form.
All measures outlined below are in accordance with Best Available Techniques (BAT)
as prescribed in the European Commission’s Reference Document on Best Available
Techniques for the Waste Treatment Industries 2006 (WT BREF).
Air Quality This section should be read in conjunction with Chapter 8 of the EIS (Volume II). The
main emissions to atmosphere from the site will arise from two CHP units (discharging
products of combustion), from the biogas flare stack (discharging products of
combustion), and from the odour control system (discharging treated air from the main
building and process pipes and tanks). As part of the EIS, air dispersion modelling
was carried out for the emissions to atmosphere (AERMOD Prime (12060)) in order to
provide the most conservative dispersion estimates. This demonstrated that the
ground level concentrations of the modelled parameters will be less than their
corresponding environmental assessment levels and no international or Irish air
quality standards are forecast to be exceeded. The stack heights presented below for
each of the three point source emissions to air are therefore considered to represent a
good level of environmental performance, to ensure adequate dispersion.
• A2-1: a single multi-flue stack which will discharge the residual levels of
pollutants from 2 x 2MW combined heat and power (CHP) engines and the
standby boiler to atmosphere at a height of 28m above ground level;
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-2 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
(The Agency should note that A2-1 in this application refers to the combined
emission points of A2-1 and A2-2 referenced in the EIS).
• A2-3: a standby gas flare which can be used to combust excess biogas when
combustion by the CHP or storage in the gas holder is unavailable;
• A2-4: odour control stack through which treated air from the odour control
system will be vented for dispersion to atmosphere at a height of 25m above
ground level.
Odour Control A three stage odour control system, comprising a biotrickling filter, plasma injection
treatment and carbon polishing, will be located immediately adjacent to the main
building. The odour control system will be based on the principles of good odour
management including:
• Odour containment;
• Odour capture;
• Odour extraction; and
• Odour treatment.
In terms of odour containment, the main building will be sealed with a near 100% leak
proof building fabric. All external process features, such as pipework and tanks, will be
enclosed and sealed, with negative extraction applied to ensure no fugitive emissions
of odours during operation. All waste handling and pre-treatment activities will be
carried out indoors at the facility. The building will be placed under negative pressure.
A total extraction volume flow rate of up to 110,000 Nm3/hr will be applied to the main
building and any external process pipework and tanks at which odour extraction is
deemed necessary. The waste intake buildings will be fitted with rapid roller doors
which will be interlocked and fitted with air curtains so as to maintain good building
integrity in terms of odour containment (main access doors only) when doors are
opened intermittently during delivery of feedstock. Pedestrian doors will remain closed
and only open when access is required.
In terms of odour capture, a network of extraction pipework will be fitted throughout
the main building and process equipment so as to provide negative pressure
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-3 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
extraction to all odour generation areas / tanks/ sumps located within the facility
boundary. This will be ducted to the odour control system for treatment.
Two variable speed driver (VSD) controlled fans will be connected to the ductwork
whereby odourous air will be extracted and ducted to the odour treatment plant. The
three stage odour treatment plant will consist of a biotrickling filter, followed by plasma
injection, and finally carbon polishing, prior to all treated air being vented through a
25m high stack for final dispersion.
The biotrickling filter stage will be filled with an organic media upon which micro-
organisms such as bacteria and fungi can grow. The micro-organisms will degrade
any malodorous particles within the air that is passed through the filter, thus removing
any potential odour.
The biotrickling filter will consist of two filter bed containers 6.5m wide by 26.50m long.
Each filter bed will have a bed height of 4.5m. There will be two filtration beds stacked
over each other giving a total biofiltration system height of 14.60m. The filtration bed
media will consist of an inorganic media thereby allowing the beds to be stacked 5m
in height unlike traditional wood chip media. The media has excellent pore structure,
porosity, structural integrity, is free draining and is totally inert. The typical lifespan of
such media is approximately 15 to 20 years. The total bed media volume will be
1,550m3. The extracted air will pass through these filter beds which will provide a true
residence time of 40 seconds. Each biotrickling filter will be an enclosed structure
protected from the external environment.
Nutrient rich liquor will be recirculated intermittently within the filter bed system in
order to create the optimum conditions for the biological filter to successfully achieve
the necessary scrubbing of the extracted air.
All liquor drained from the biotrickling system will be filtered using two high efficiency
self cleaning filters to a filter pore size of less than 100µm. This liquor will be pumped
to an aerated holding tank where essential nutrients will be dosed at a specific rate in
order to ensure the biological system has sufficient essential macro and micro
nutrients present for effective biological activity and degradation. The pH and
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-4 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
conductivity of the liquor will be monitored and adjusted as required within this
bioreactor.
Following biotrickling filtration, the air will be passed through a vane eliminator
capable of removing greater than 99.5% of water droplets greater than 2µm. At this
stage the air will enter a mixing chamber where plasma injection will occur. Plasma
injection will perform additional odour treatment whereby the plasma oxidant will mix
and degrade residual odours within the air stream that have not been captured within
the biotrickling stage.
This will then be pumped forward to a dual annual carbon filtration vessel whereby
any remaining residual odours will be filtered from the air stream. The annular bed
carbon filtration system will be divided into two separate streams. Each bed will have
a retention time of approximately 2.2 seconds and contain general purpose steam
activated bituminous coal 4mm pellet carbon media. The carbon media will become
impregnated with the plasma thereby also further enhancing the oxidative potential of
the carbon / plasma combination system.
All treated air will be exhausted through a single 25m stack. The overall system will be
capable of achieving an exhaust odour threshold concentration of less than 1,000
OuE/m3 with a typical value in the exhaust stream of 700 OuE/m3.
The system has been designed with 100% duty and 50% standby in mind so that
odour treatment coverage is available during routine maintenance of either system.
Figure F.1 at the end of this attachment shows a schematic of the odour control
system.
Dust The process has been designed to control emissions of dust. Waste will be delivered
and pre-treated entirely in an enclosed building maintained under sub-atmospheric
pressures to contain, collect and treat dust and particles. The Air Quality Assessment
demonstrates that dust and particulate emissions will not be significant during the
operational phase.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-5 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Combined Heat and Power Plant & Biogas Treatment The biogas produced from the AD process will be converted to electricity and heat in
the CHP plant which will comprise two units, each rated at 2MWe. Combustion gas
emissions from the two CHP units, and the standby boiler, will be discharged to the
atmosphere at a height of 28m above ground level via two flues within a single
combined wind shield stack.
Biogas can contain hydrogen sulphide (H2S) generated from the degradation of
protein matter in the organics. In order to limit the SOx emissions from the CHP, H2S
in the biogas will be controlled by the addition of ferric chloride to the digestion tanks.
Ferric chloride locks sulphides up as salts within the sludge preventing the
volatilisation into the biogas. In addition the biogas will be treated in a gas scrubber
prior to the CHP, which will also provide for H2S removal, as well as drying the biogas
to remove moisture (condensate) using a dehumidifier. The condensate will be
recirculated to the AD process.
The combustion of biogas in the CHP plant will destroy any potentially odorous
compounds contained in the gas.
Gas Holder Biogas passes to the CHP units from the digester tanks via a gas holder. The biogas
holder is a double membrane system with c.1,800m3 capacity, and has two primary
functions. Firstly the gasholder is a safety device maintaining system pressure for the
digestion and feed buffer tanks. When liquid is pumped out of one of the tanks the
gasholder provides biogas to replace the lost volume hence maintaining system
pressure. Similarly when biogas is produced within a tank the gasholder acts as a
storage volume for this gas hence preventing an increase in gas pressure.
Secondly the gasholder acts as a buffer for biogas production and use. The
combined heat and power plant uses biogas at a fixed rate, whereas biogas
production may vary slightly above and below this figure. The gasholder acts as a
buffer to allow the CHP to operate at a constant rate with varying gas production.
The gasholder acts as the pressure regulating device in the gas system. Air is blown
into an outside bag which surrounds the inner gasbag. The air outlet is restricted by a
regulating valve to create a constant air pressure in the outer bag (20 – 25mbarg),
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-6 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
and this in turn pressurises the gas to the same pressure. By maintaining the gas at a
positive pressure at all times the risk of oxygen (from air) being drawn into the gas
system from a leak or relief valve is eliminated and hence the potential for an
explosive mixture of methane and air is eliminated within the process plant.
Figure F.2 at the end of this attachment shows a schematic of the Anaerobic
Digestion Process Flow.
Gas Flare The flare stack (c.8.2m tall) is designed to operate in the event that more biogas is
generated than is used. The flare stack will normally only be required to operate when
the CHP units are not in use for routine maintenance and are unavailable to use the
biogas produced by the digester. The expected availability of CHP engines is >93%.
There are two CHP units and normally only 1 engine will be off line (for maintenance)
at a time. The duty of the flare is designed to the maximum hourly biogas production
rate.
The function of the flare stack is to prevent the gasholder from becoming overfull,
which would in turn result in over pressurisation of the gas system. The combustion
of biogas in the gas flare will destroy any potentially odorous compounds contained in
the biogas.
Pressure Relief Valves The gas holder and digester tanks will be fitted with a pressure and vacuum relief
valve that will protect against excessively high or low pressures which, could occur
under abnormal fault conditions such as in the very unlikely event that both CHP units
and the flare stack are all unavailable at the same time. This device is a safety device
and will not operate under normal working conditions, however under abnormal
conditions this valve is designed to release biogas to the air. The availability of CHP
is expected to be >93% (for each engine) and availability of the flare >95%, therefore
the risk of PRV venting equals 0.02%.
Standby Boiler A dual fuel (biogas and diesel) standby boiler will be located adjacent to the CHP units
to provide hot water for pasteurisation and digester heating requirements in the event
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-7 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
that the CHP units go out of service (planned or unplanned). The boiler will also
provide heat during the commissioning phase of the plant. Storage for hot water is
provided immediately adjacent to the boiler.
A summary of all incorporated operational and construction phase mitigation
measures and techniques to prevent or reduce air emissions from the plant are
summarised in Chapter 8 of the EIS (Volume II).
Surface Water Drainage This section should be read in conjunction with Chapter 13 of the EIS (Volume II).
The site has been evaluated for Sustainable Drainage Systems (SuDS) and the most
suitable measures have been incorporated into the surface water management
system design for the plant. The SuDS measures incorporated are designed to
manage and control surface water runoff from the development and also to treat the
runoff in order to remove any suspended solids and hydrocarbons prior to discharge.
Rainwater harvesting is a key measure included in the management of surface water
runoff for the plant. Rainfall runoff from the site will be stored and attenuated within
above and underground storage tanks and pipework, and will be used for ancillary
processes such as washwater for the floor of the reception, processing and storage
areas of the main building, as well as in the vehicle and wheelwash facilities. Excess
runoff will be discharged from the site to the surface water drainage network at a
controlled release rate. There will be no discharge of process effluent, other than to
the foul sewer.
The surface water drainage system has been designed to discharge excess runoff
into the existing storm water open ditch to the north of the existing main access road.
The greenfield run-off rate in the local area of North Dublin is approximately 6l/s per
hectare, which equates to approximately 10.5 l/s from the subject site into the existing
ditch. It is estimated that an average of approximately 12m3 per month of clean runoff
will be discharged after rainfall harvesting which is significantly lower than the
greenfield runoff rate from the subject site.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-8 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
The preliminary design of the surface water drainage system was undertaken by SLR
utilising WinDes software package and considers the 1 in 100 year storm, together
with an additional allowance of 20% to cater for the effects of climate change.
Run-off from the following sources is classified as ‘grey water’ and is routed through
the proposed surface water drainage system:
(i) Roof run-off;
(ii) External pavement and hardstanding run-off; and
(iii) Run-off ordinarily collected from within the bunded tank farms (assuming no
leakages have been identified).
Surface water from sealed pavement around the proposed plant will be collected by
surface gullies and transferred via a sealed pipework system to a manhole close to
the northern site boundary (identified as SWMH21 on Drawing PL37). If being
discharged from site, surface water run-off will pass from this point through a silt trap
and oil / water separator and discharge through a pipe running beneath the quarry
access road to the outfall at the existing open ditch located beyond the verge on the
northern side of the access road. The water discharged to this ditch will ultimately flow
northwards via the existing drainage network to the Ballystrahan Stream and the Ward
River.
Surface water run-off from the building roof will be collected in roof gullies and carried
by downpipes and drains to an overground stormwater storage tank adjacent to the
western containment bund. This tank will provide a maximum of 2,000m3 storage
capacity and is intended to store captured run-off from the site, pending its re-use on-
site, thereby conserving mains water.
Water will be pumped from the carrier drains to the storage tank provided there is
storage capacity available. When the overground stormwater tank is full, roof run-off
will be diverted into the pavement run-off system and routed toward the outfall. A
control system will be incorporated that will divert roof run-off to the overground
storage tank as and when storage capacity is available.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-9 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Any rain water collecting within the bunded tank farms will be pumped via a small
drainage sump into the surface water drainage system, provided there is no evidence
of potential contamination or spill within the bunded area.
The rate of discharge to the drainage ditch on the northern side of the access road will
be limited to the greenfield discharge rate by a flow control device (eg. Hydro-Brake)
fitted at manhole SWMH21. In designing the drainage system, it is assumed that
during a design storm event, there will be no storage capacity available at the
overground tank and that large diameter pipework will provide appropriate storm water
attenuation. In addition to attenuation within the sealed pipe system, a stormwater
storage crate system will provide approximately 450m³ of attenuation capacity
upstream of manhole SWMH21.
Water held in the sub-surface attenuation tank will be pumped to the overground
storage tank, as and when there is excess storage capacity available.
Systems are built into the design of the site to ensure that environmental media are
not impacted in the event of abnormal operations such as a fire event. The outfall to
the quarry drainage can be manually shutdown in the event of a fire. The systems are
based on the principle of segregating potentially contaminated surface waters and
ensuring suitable storage and containment is present in the event of contaminated
firewater being generated.
In the event of a fire, the contained system will allow firewater to be rerouted to either
the underground attenuation tank or storm water tank for retention on site until quality
analysis of the water is undertaken which will inform an appropriate and safe method
of disposal. Contaminated waters are therefore prevented from reaching the quarry
drainage network, ground or groundwater.
An outline of the proposed surface water drainage system is provided on Figure F.3
and also on Drawing PL37. Surface water drainage design calculations are provided
in Appendix B of the SLR Consulting Proposed Drainage Strategy Report presented in
Appendix 13-3 of the EIS (Volume III). Typical details for various elements of the
surface water drainage system are provided on Drawing PL38.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-10 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
A summary of all incorporated operational phase mitigation measures and techniques
to avoid pollution as a result of surface water emissions are summarised in Chapter
13 of the EIS (Volume II).
Foul Water Drainage An on-site Wastewater Treatment Plant (WwTP) is an important element of the
proposed plant. This facility will treat separated liquid digestate from the centrifuge
stage of the AD process. Process water discharged from the wheelwashes and
vehicle wash will also be diverted to the onsite WwTP. However, it should be noted
that runoff from the washing of the main building floor will be captured and recycled
directly to the AD process.
The WwTP will utilise aerobic sequential batch reactor (SBR) technology and the
process will perform as a combined activated sludge and settlement tank removing
ammonia and BOD and solids from the liquid stream such that the treated liquid is of a
suitable quality to be recycled to the biomass mixers located in the pre-treatment area
of the main building or to be discharged to the municipal sewer.
Each SBR will operate on 4 cycles per day of 6 hours per cycle. Each cycle will
consist of a fill and aerate period followed by an aeration period. Once the ammonia
has been aerobically converted to nitrate / nitrite the aeration will stop to allow solids
to settle and following the settlement period the top fraction of liquid will be decanted
into the treated process water balance tank from where it will be recycled into the AD
process.
During the aerobic conversion of ammonia, alkalinity is consumed by the process and
it is therefore necessary to add alkalinity. This alkalinity is added in the form of caustic
soda which, is dosed directly to the SBRs under automatic pH control (from a tank
mounted pH meter). The caustic soda addition will be such that pH is maintained at
7.0 to 7.5 within the SBRs. Caustic Soda will be contained within a dedicated bunded
tank located outside the WwTP bund wall and will be pumped to the SBRs by dual
containment pipework.
Air blowers for the WwTP plant are located immediately outside the tank farm bund
wall in acoustic containers.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-11 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
The treated process water from the WwTP is recycled into the main process and is
used to dilute the incoming feedstock. Excess treated process water that is not
required for the process will be discharged to the municipal sewer. A foul water rising
main will be constructed as part of this proposed development that will connect the
plant with the municipal sewer network at a point located on North Road (see Drawing
PL39). Further details on the connection of the plant to the municipal sewer network
are provided in Sections 2.65 to 2.70 of Chapter 2 of the EIS (Volume II).
It is estimated that up to 200m3/day of treated process effluent will be discharged to
the sewer. This effluent will have a significantly reduced organic loading following the
treatment in the on-site WwTP, with a maximum population equivalent of
approximately 750 (based on 1 PE = 54g of BOD per day).
A schematic of the foul drainage system in presented in Figure F.4.
Noise Abatement Table E.2 in Attachment E.5 presents the operational fixed plant noise sources. The
main generators of noise will be the CHP engines, SBR blowers and the waste pre-
treatment activities that will be undertaken inside the main building.
The CHP engines and the SBR blowers will be housed in acoustic enclosures with a
minimum Rw of 24 dB(A), whilst the standby boiler and gas boosters will be housed in
containers with a minimum Rw of 24 dB(A).
The waste pre-treatment operations will take place in the main building. This building
will be constructed using Kingspan wall and roof panels. The wall panels will have a
minimum sound reduction index (Rw) value of 24dB(A), whilst the roof panels will
have a minimum Rw value of 26dB(A). The access roller shutter doors will remain
closed in between vehicles entering and exiting the building.
The noise assessment presented in Chapter 10 of the EIS (Volume II) demonstrates
that the EPA NG4 noise criterion limits as prescribed for daytime, evening, and night-
time are comfortably met at all four noise sensitive locations (NSL) assessed. These
limits are also met at the site boundary location. Therefore, mitigation measures to
reduce operational noise are considered unnecessary.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-12 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Process Control Monitoring All aspects of the plant will be controlled and monitored by a central electronic
Supervisory Control and Data Acquisition (SCADA) telemetry control system. The
system will allow for maintenance of optimum conditions required at the various
stages of the plant to ensure safe and efficient operation of the plant.
The SCADA system will be designed, installed and commissioned to receive and
control all plant and equipment including the CHP units on site. The system has clear
screen pictures representing each stage of the process, ensuring that the operational
staff will have a quick and easy overview of the plant operation.
Instrumentation equipment will be located throughout the plant to ensure safe
operation of the plant and will allow measurement of the plant’s operation and
performance. These will include measurements of the feed rates into tanks; level
controllers in the digester tanks; temperature transducers to continuously measure the
temperature within the tanks; the quality of the gas produced; links to the gross and
parasitic meters; and the discharge from the tanks. Measuring instrumentation will be
independently calibrated as required and applicable certificates will be contained and
held on record.
All data collected in the system can be used to generate reports both for internal use
as well as reporting to external authorities. The control system will also be able to
store data to record historical trends.
The SCADA system will include a service modem that will allow remote operation of
the plant. It will be possible for the technology provider to remotely connect to the
plant to provide support.
This system will incorporate alarm tagging so as to ensure consistent performance
over the lifetime of the plant. All alarms will be received by the operator via mobile
phone and are prioritised. Therefore any situations that develop during night-time,
weekends and holiday periods will be remotely detected by the operator. This
together with the remote connection facility will allow the operator to evaluate the
importance of the incident and to determine the level of action required.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-13 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Inspection, Maintenance and Monitoring Infrastructure, surfacing and equipment within the site (including tanks, bunds, pipes,
structures, roads, hardstand areas, drains etc.) will be inspected on a regular basis to
check for equipment malfunctions, structural deterioration, operator errors and leaks
and will be maintained and repaired as necessary. Tanks will be fitted with level
indicators to prevent overfilling. In addition, the operator will undertake visual checks
on all plant and equipment at least once a week and, if deemed necessary, bring
forward any planned maintenance or undertake remedial works.
Site operatives will undertake regular monitoring for evidence of spillage and leakage.
Records of all visual and scheduled inspections and details and certificates (where
appropriate) of any maintenance work will be regularly updated and maintained.
Maintenance schedules for equipment will be regularly reviewed and updated.
In the event of damage or deterioration being detected, all maintenance work will be
carried out in conformance with the operators Health and Safety Policy.
A general piping inspection will be carried out at least once every five years and will
include inspection for outer corrosion, pipe support integrity and function of safety
devices. A general tank inspection will be carried out every 3 to 15 years depending
on the tank type and will include an internal inspection and pressure test.
Contingency Plans for Plant Breakdown The entire site process will be constantly monitored on a SCADA system to
continuously assess the performance of the plant and identify any adjustments
necessary to prevent technical issues arising. Should any problems, malfunctions or
breakdowns occur within the AD process, treatment will be stopped until such time as
the problems are rectified. If necessary incoming feedstock will be diverted to
alternative facilities to prevent any build up within reception halls.
All of the plants abatement systems will also be connected to the sites’ SCADA
system which will ensure plant shutdown in the event of any abatement system failure
or breakdown.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-14 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
In the event of a power cut or ‘black-out’ the plant will automatically shutdown.
Feedstock will be prevented from entering the process during periods of automatic
shutdown and most electrical/electronic equipment, motors and fans will cease
operating except those required to cool the plant and provide emergency lighting.
In the event of a black out, however, such motors and fans will require an emergency
power supply. This will be provided by a backup or emergency electrical generator
powered by a diesel motor. Detection of a power supply failure to critical motors and
fans will activate the automatic shutdown system and the emergency power generator
simultaneously. The automatic shutdown system will then restart the critical motors
and fans using the emergency generator. The emergency generator will be controlled
manually. The backup generator will be tested but only used during automatic
shutdowns or a black-out.
The site manager will be responsible for directing all Operations and Maintenance
(O&M) activities on site. Fulltime on-site Plant Maintenance Engineers will work to
proactively manage the maintenance of the plant. This work will involve the immediate
resolution of any technical problems that may arise.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:05
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-15 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
ATTACHMENT F. 2 - EMISSIONS MONITORING & SAMPLING Details of the proposed emissions monitoring and sampling points for the plant are
presented in Table F.1 below. The location of sampling points for emissions to
atmosphere, surface water and sewer are presented in Figure F.5 at the end of this
attachment and in Drawing PL07. Proposed noise monitoring locations are presented
in Figure F.6 and Figure 10-1 of Chapter 10 of the EIS (Volume II).
Detailed plans of emission points are presented in Drawings PL27, PL29, PL30, PL37
and PL39 of the Planning Drawings which accompany this application.
Table F.1 Proposed Emissions Monitoring and Sampling Points
Reference Description
A2-1 Combined gas engines (x2) and standby boiler discharge point - 28m discharge stack
A2-3 Standby gas flare – 8m discharge stack
A2-4 Odour control system – 25m discharge stack
SW1 Located at northern site boundary after the hydrocarbon interceptor and silt trap.
SE1 Located at south western boundary of subject site at the package pump station
N1 Residential property c.707m east of the centre of the subject site
N2 Residential property c.535m northeast of the centre of the subject site
N3 Residential property c.640m south of the centre of the subject site
N4 Residential/Commercial property c.450m east of the centre of the subject site
N6 Subject site southern boundary location
Tables F2(i) and F2(ii) have been completed as relevant and are presented within the
licence application form.
Air Monitoring Methodology An inherent part of the licensing system is the setting of emission limit values (ELV)
on discharges to atmosphere. The Agency sets these limits having regard to the
principles of BAT and the overriding imperative that ground level pollutant levels
beyond the boundary remain below the appropriate Air Quality Standards (e.g. World
Health Organisation Air Quality Guidelines).
All monitoring will be undertaken in line with the Agency’s Guidance Note on Site
Safety Requirements for Air Emissions Monitoring (AG1) and Air Emissions
Monitoring Guidance Note (AG2).
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:06
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-16 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
To demonstrate compliance with an ELV the monitoring of the CHP and Standby
Boiler at A2-1 will be conducted post abatement so that the exhaust gases are
representative of those that are released to atmosphere.
Measurement will be undertaken when the process is at a maximum sustainable level
and where emissions are stable or as close to that level as is reasonably practical.
Odour monitoring will be carried out on the emissions from the odour control system.
This will comprise annual dynamic olafctometry testing by an independent specialist
consultancy. In addition, facility staff will carry out periodic odour patrols along the site
boundary and will record the findings in a daily log.
Surface Water Monitoring Methodology The methodology to be employed in monitoring the storm water discharge from the
proposed site at SW1 will be in line with the Agency’s Guidance on the setting of
trigger values for storm water discharges to off-site surface waters at EPA IPPC and
Waste Licensed Facilities (2012).
It is not envisaged that the licence will specify ELVs for the proposed discharge from
SW1 as the discharge will only consist of uncontaminated storm water runoff. Trigger
levels, if set by the Agency; will be monitored by analysing grab samples collected
when emissions are taking place. A documented response programme in the event
of reaching or exceeding trigger level values will be put in place.
A visual examination of the storm water discharges shall be carried out daily. A log of
such inspections shall be maintained.
Grab samples will be collected at the outfall from the Oil Interceptor. Samples will be
collected weekly and visually checked for evidence of contamination. At quarterly
intervals the sample will be tested for ph, BOD, COD, Mineral Oils and Total
Suspended Solids.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:06
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-17 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Sewer Monitoring Methodology It is proposed that monitoring of pH, BOD, COD, Suspended Solids and Ammonium
(NH4) will be undertaken on a quarterly basis. The methodology for monitoring during
operation is to be agreed with the Agency.
Noise Monitoring Methodology The noise assessment presented in Chapter 10 of the EIS (Volume II) defines each of
the baseline monitoring locations including four noise sensitive locations and one
boundary location as being ‘not an area of low background noise’ in accordance with
the standards set out in the Agency’s Guidance Note for Noise: License Applications,
Surveys and Assessments in Relation to Scheduled Activities (NG4). The permitted
rating noise level for areas defined as ‘not an area of low background noise’ as
presented in the NG4 guidance is presented in the Table below.
Table F.2 Permitted Rating Noise Levels
Designation Daytime Noise
Criterion, dB LAr,T Evening Noise
Criterion, dB LAr,T Night-Time Noise Criterion, dB LAr,T
All other Areas 55.0 50.0 45.0
It is proposed that noise monitoring will be undertaken annually at the four noise
sensitive locations (N1-N4) and one boundary location (N6) as presented in Figure
F.6.
Dust Monitoring Methodology In line with Condition 14 of the grant of planning permission (reg. Ref. FW13A/0089)
dust deposition monitoring will be conducted in accordance with VDI 2119
‘Measurement of Dustfall, Determination of Dustfall using Bergerhoff Instrument
(Standard Method)’, German Engineering Institute. The monitoring will be carried out
annually and one event will be undertaken between May and September.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:06
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-18 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
ATTACHMENT F. 3 - TABULAR DATA
Table F.3 Tabular Data on Monitoring and Sampling Points
Point Code
Point Type Easting Northing Verified Emission
A2-1 S 311445 241219 N CO, NOx SO2, TPM, NH3, TNMVOC
A2-4 S 311336 241266 N Odour, NH3
SW1 S 311412 241300 N pH, BOD, COD, Mineral Oils, SS
SE1 S 311319 241278 N pH, BOD, COD, SS, NH4
N1 M 312095 241135 N db(A)
N2 M 311920 241380 N db(A)
N3 M 311558 240659 N db(A)
N4 M 311762 241545 N db(A)
N6 M 311357 241188 N db(A)
The data presented above is also contained in excel format as required by the Agency
within a separate CD-Rom entitled IED Licence Application Sections B.2, E.6 and F.3.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:06
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-19 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
FIGURES
Figure F.1 Schematic of Odour Control System
Figure F.2 Schematic of Anaerobic Digestion Process Flow
Figure F.3 Schematic of Surface Water Drainage System Flow
Figure F.4 Schematic of Foul Water Drainage System Flow
Figure F.5 Location of Proposed Emissions Monitoring and Sampling Points for Atmosphere, Surface Water and Sewer
Figure F.6 Location of Proposed Noise Monitoring Locations
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:06
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-20 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Figure F.1 Schematic of Odour Control System
Odour Control System
Bio-Trickling Plasma Injection Carbon Filtration System
Main Building
WwTP
Stack (Dispersion)
AD Tanks
Pasteurisation
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:06
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-21 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Figure F.2 Schematic of Anaerobic Digestion Process Flow
Digester
Gas Holder
Gas treatment (H2S Scrubber Dehumidifier)
Thermal Output
Electrical Output
Back-Up Flare
Stand-By Boiler
CHP Engines
(Back-up)
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:06
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-22 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Figure F.3 Schematic of Surface Water Drainage System Flow
Main Building
Roof
Roads, Paved Surfaces &
Hardstanding Areas
Open Storm
Water Ditch
Containment Bunds
Over-ground Storage Tank
Under-ground
Attenuation Tank
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:06
ATTACHMENT NO F CONTROL & MONITORING
Proposed Renewable BioEnergy Plant F-23 Stream BioEnergy Ltd. Huntstown, North Road, Finglas, Dublin11
Figure F.4 Schematic of Foul Water Drainage System Flow
Centrifuge
(Liquid Fraction)
WwTP
SBR Technology
Foul Water Raising
Main
Municipal Sewer
Network
Process
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:06
L
A
N
D
S
C
A
P
E
A
R
E
A
S
4446
34
27
33
1
4
13
10
2
3
29
28
43
45
17
9
23
22
363738
3940
41
42
35
47
49
48
50
14
+78.000
+78.000
+79.335
1516
N
W
S
E
31 Rainey Street, Magherafelt, BT45 [email protected] www.visiondesign.org.uk
Tel: 028 7930 0866
NOTES
Scale Date
1. BASED ON 1:1000 & 1:2500 ORDNANCE SURVEY IRELANDDIGITAL MAPPING - MAP NO's. - 3063A, 3063C, 3062B, 3062C, 3062D,3130A, 3130B, 3131-01 & 3131-06
2. ORDNANCE SURVEY IRELAND LICENCE NO. AR 0116513 (C)ORDNANCE SURVEY & GOVERNMENT OF IRELAND
3. © COPYRIGHT RESTS WITH VISION DESIGNTHIS DRAWING MAY NOT BE REPRODUCED WHOLLY OR IN PARTWITHOUT THE EXPRESS WRITTEN PERMISSION OF VISION DESIGN
LEGEND
Revision Drawn By Chkd By Date Comments
CLIENT:
16.06.14RD RD-
Renewable Bioenergy PlantProposed Huntstown
Finglas, Dublin 11Huntstown, North Road,
Atmosphere, Surface Water and Sewer
Monitoring and Sampling Points for
Title - Location of Proposed Emissions,
June 20141:1000 / A3
2388 - Figure F.5
Huntstown Renewable BioEnergy PlantApplication Area (c 2.382 ha)
Existing wayleave for 220 kv cable to HuntstownPower Station
Proposed new sewer line from pumping station
KEY TO BUILDINGS AND PLANT
Proposed Emissions Monitoring and SamplingPoints for Atmosphere, Surface Water and Sewer
Emission Ref Easting NorthingA2-1 (Combinedemission point)
311445 241219
A2-3 311480 241202A2-4 311336 241266SW1 311412 241300SE1 311319 241278
EMISSION REFERENCE TABLE
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:06
7
9
.
0
0
7
9
.
0
0
79.00
7
9
.
0
0
7
9
.
0
0
7
9
.
0
0
7
9
.
0
0
7
9
.
0
0
79.00
7
9
.
0
0
7
9
.
0
0
7
9
.0
0
7
9
.
0
0
7
9
.
0
0
7
9
.
0
0
7
9
.
0
0
7
9
.
0
0
7
9
.
0
0
7
9
.
0
0
7
9
.
0
0
7
9
.
0
0
7
9
.
0
0
8
0
.
0
0
8
0
.
0
0
8
0
.0
0
N3
N6 N1
N2
N4
31 Rainey Street, Magherafelt, BT45 [email protected] www.visiondesign.org.uk
Tel: 028 7930 0866
NOTES
Scale Date
1. BASED ON 1:1000 & 1:2500 ORDNANCE SURVEY IRELANDDIGITAL MAPPING - MAP NO's. - 3063A, 3063C, 3062B, 3062C, 3062D,3130A, 3130B, 3131-01 & 3131-06
2. ORDNANCE SURVEY IRELAND LICENCE NO. AR 0116513 (C)ORDNANCE SURVEY & GOVERNMENT OF IRELAND
3. © COPYRIGHT RESTS WITH VISION DESIGNTHIS DRAWING MAY NOT BE REPRODUCED WHOLLY OR IN PARTWITHOUT THE EXPRESS WRITTEN PERMISSION OF VISION DESIGN
LEGEND
Revision Drawn By Chkd By Date Comments
CLIENT:
16.06.14RD RD-
Renewable Bioenergy PlantProposed Huntstown
Finglas, Dublin 11Huntstown, North Road,
Locations
Title - Proposed Noise Monitoring
June 20141:4000 / A3
2388 - Figure F.6
N
W
S
E
Huntstown Renewable BioEnergy PlantApplication Area (c 2.382 ha)
Location and number of noise monitoring points
Proposed directional signage locations
Monitoring Point Easting NorthingN1 312095 241135N2 311920 241380N3 311588 240659N4 311762 241545N6 311357 241188
MONITORING POINT REFERENCE TABLE
N6
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 15-07-2014:23:47:06