2
“ eni Iraq b.v. - Zubair Oil Field Development Project” Work Package of Existing DGS Modification Form No. QIR -121 Report No.: BOLT TORQUE REPORT Sheet of Reference : Piping Fabrication & Erection Procedure No. 00250600DBPC4066M - (Attach. 2) SYSTEM TITLE or NO:_____________________ AREA / ISOMETRIC NUMBER : ___________________________ SHT NO :___________ DWG NO : ___________ JOINT REFERENCE/ LOCATION:______________________________ SPEC NO:________________________ FLANGE DETAILS (SIZE / RATING ) _____________________________________________________________ BOLT SIZE:___________________ NO OF BOLTS:________________BOLTING MATERIAL:____________________ REQUIRED TORQUE:_______________________________ NO OF STEPS _____________________________ WRENCH MANUFACTURER: ______________________________________________________________________ SERIAL NUMBER: ________________________ CALIBRATION DATE__________________________________ TIGHTENING SEQUENCE: REMARKS:

Attachment 2. - Form No. - QIR - 121

Embed Size (px)

DESCRIPTION

Attachment 2. - Form No. - QIR - 121

Citation preview

Page 1: Attachment 2. - Form No. - QIR - 121

“ eni Iraq b.v. - Zubair Oil Field Development Project”

Work Package of Existing DGS Modification

Form No. QIR -121

Report No.:

BOLT TORQUE REPORT Sheet of

Reference : Piping Fabrication & Erection Procedure No. 00250600DBPC4066M - (Attach. 2)

SYSTEM TITLE or NO:_____________________

AREA / ISOMETRIC NUMBER : ___________________________ SHT NO :___________ DWG NO : ___________

JOINT REFERENCE/ LOCATION:______________________________ SPEC NO:________________________

FLANGE DETAILS (SIZE / RATING ) _____________________________________________________________

BOLT SIZE:___________________ NO OF BOLTS:________________BOLTING MATERIAL:____________________

REQUIRED TORQUE:_______________________________ NO OF STEPS _____________________________

WRENCH MANUFACTURER: ______________________________________________________________________

SERIAL NUMBER: ________________________ CALIBRATION DATE__________________________________

TIGHTENING SEQUENCE: REMARKS:

Construction QCI Company

Name

Sign

Date