Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
Decision 22742-D01-2019
ATCO Electric Ltd. 2018-2019 Transmission General Tariff Application July 4, 2019
Alberta Utilities Commission
Decision 22742-D01-2019
ATCO Electric Ltd.
2018-2019 Transmission General Tariff Application
Proceeding 22742
July 4, 2019
Published by the:
Alberta Utilities Commission
Eau Claire Tower
1400, 600 Third Avenue S.W.
Calgary, Alberta T2P 0G5
Telephone: 310-4AUC (310-4282 in Alberta)
1-833-511-4AUC (1-833-511-4282 outside Alberta)
Email: [email protected]
Website: www.auc.ab.ca
The Commission may, within 30 days of the date of this decision and without notice, correct
typographical, spelling and calculation errors and other similar types of errors and post the
corrected decision on its website.
Decision 22742-D01-2019 (July 4, 2019) i
Contents
1 Decision summary ................................................................................................................. 1
2 Introduction and background .............................................................................................. 2
3 Responses to previous Commission directions ................................................................... 7
4 Terms and conditions of service .......................................................................................... 8
5 Forecasting methodology and key assumptions ................................................................. 8 5.1 Manpower ...................................................................................................................... 8
5.1.1 Full-time equivalents ........................................................................................ 8
5.1.2 Vacancy rates .................................................................................................. 16 5.1.3 Severance costs ............................................................................................... 19
5.2 Compensation ............................................................................................................... 23 5.2.1 Labour escalation ............................................................................................ 23
5.2.1.1 In-scope escalation ............................................................................. 23 5.2.1.2 Out-of-scope escalation ..................................................................... 25
5.2.2 Variable pay program ..................................................................................... 31
5.2.2.1 Reserve for VPP ................................................................................ 31 5.2.2.2 Variable pay forecast ......................................................................... 35
5.2.2.3 Treatment of VPP reserve account balance ....................................... 40 5.3 Other escalators ............................................................................................................ 41
5.3.1 Contractor and other inflation ......................................................................... 41
5.3.1.1 Contractor inflation rate ..................................................................... 42
5.3.1.2 Other inflation rate ............................................................................. 42
6 Fuel costs .............................................................................................................................. 43
7 Operating costs .................................................................................................................... 44 7.1 Forecasting accuracy .................................................................................................... 45
7.1.1 USA 561 – Transmission Operations – Control Centre .................................. 46 7.1.2 USA 563 and 569 – Overhead Line Maintenance .......................................... 46 7.1.3 USA 566 – Miscellaneous Transmission Expense ......................................... 47 7.1.4 USA 567 – Annual Structure Payments.......................................................... 48 7.1.5 Vegetation management.................................................................................. 49
7.1.5.1 Reserve for vegetation management .................................................. 49
7.1.5.2 2018-2019 Forecast vegetation management costs (USA 571.1) ...... 50
7.1.6 USA 575 – IT Support .................................................................................... 51
8 Transmission depreciation ................................................................................................. 52 8.1 Deferral account for IFRS-related depreciation rate issues ......................................... 54 8.2 Fort McMurray wildfire ............................................................................................... 56
9 Income taxes ........................................................................................................................ 57 9.1 Income tax .................................................................................................................... 57
9.1.1 Income tax - general........................................................................................ 57 9.1.2 Allowance for funds used during construction ............................................... 62
9.2 Income tax deferral accounts ....................................................................................... 69
9.2.1 Deferral accounts AET is seeking to continue ................................................ 70
9.2.1.1 Statutory rates deferral account for income tax ................................. 70 9.2.1.2 Deduction of deferrals for income taxes ............................................ 70
9.2.2 Deferral accounts AET is seeking to discontinue ........................................... 71 9.2.2.1 Capital repair costs deferral account .................................................. 71 9.2.2.2 Income tax deductible capital costs deferral account ........................ 72
10 Taxes other than income tax .............................................................................................. 75
11 Rate base .............................................................................................................................. 77 11.1 Direct assigned capital projects .................................................................................... 78 11.2 Transmission capital maintenance ............................................................................... 79 11.3 General property and equipment .................................................................................. 83
11.4 Thickwood development project .................................................................................. 86 11.5 Kearl Line (line 9L101) relocation .............................................................................. 90 11.6 Direct assigned capital deferral account .................................................................... 103
11.7 Engineering, supervision and general costs ............................................................... 106 11.8 Construction work in progress refund ........................................................................ 107
12 Necessary working capital ................................................................................................ 115
13 Isolated generation operating costs ................................................................................. 117
14 Shared services and common group costs....................................................................... 119 14.1 Shared services ........................................................................................................... 119
14.2 Shared services - productivity factor ......................................................................... 122
14.3 Common group costs ................................................................................................. 124
15 Corporate administration and general ........................................................................... 128 15.1 Office Supplies and Expenses (USA 921) ................................................................. 128
15.2 IT G&A expense (USA 934)...................................................................................... 131 15.3 Allocation of costs to Alberta PowerLine .................................................................. 133
15.4 Allocation of head office rent costs ........................................................................... 138 15.5 Reserve for injuries and damages .............................................................................. 155
16 Financing and credit metrics ........................................................................................... 156 16.1 Credit metrics ............................................................................................................. 156 16.2 Cost of debt ................................................................................................................ 159
17 Revenue offsets and recoveries from affiliates ............................................................... 164
18 Order .................................................................................................................................. 171
Appendix 1 – Proceeding participants .................................................................................... 172
Appendix 2 – Oral hearing – registered appearances ........................................................... 173
Appendix 3 – Summary of rulings and procedural requests ................................................ 174
Appendix 4 – Summary of Commission directions addressed in application ..................... 176
Appendix 5 – Summary of Commission directions to be addressed in future applications
............................................................................................................................. 179
Appendix 6 – Transcript, Volume 2, 2019-01-22 - Ruling on CCA request to mark two
exhibits ............................................................................................................... 180
Appendix 7 – Summary of Commission directions ................................................................ 181
List of tables
Table 1. Comparison of revenue requirements for 2017-2019 .............................................. 4
Table 2. Forecast capital expenditures and additions for test period ................................... 5
Table 3. Summary of opening rate base additions from 2015-2017 GTA forecast.............. 5
Table 4. Summary of the process and schedule ...................................................................... 6
Table 5. AET FTE forecast - Original application June 16, 2017 ......................................... 9
Table 6. AET FTE forecast – Omissions and updates filing November 10, 2017 ................ 9
Table 7. AET FTE forecast – Application update September 4, 2018 ................................ 10
Table 8. Summary of forecast complement for 2015-2017 test period ............................... 14
Table 9. Summary of vacancy rates 2015-2017 ..................................................................... 17
Table 10. AET severance costs (application update) .............................................................. 19
Table 11. AET severance costs ................................................................................................. 19
Table 12. Labour inflation forecast 2018-2019 ....................................................................... 23
Table 13. Recent wage settlements in the Alberta utility market (per cent increase) ......... 24
Table 14. VPP reserve account balances ................................................................................. 32
Table 15. Variable pay program costs ..................................................................................... 35
Table 16. VPP payout percentages and average VPP payout percentage ............................ 38
Table 17. Forecast inflation rates – labour, contractors and other 2018-2019 .................... 41
Table 18. Actual/Forecast fuel costs ......................................................................................... 43
Table 19. Transmission direct operating costs ........................................................................ 44
Table 20. Direct O&M costs for USA 566 ............................................................................... 47
Table 21. Direct O&M costs for USA 567 ............................................................................... 48
Table 22. Direct O&M costs for USA 571 ............................................................................... 50
Table 23. AET historical and forecast depreciation expense 2015-2019 .............................. 53
Table 24. Summary of income tax expense ............................................................................. 57
Table 25. Statutory tax rates..................................................................................................... 58
Table 26. AET’s forecasting accuracy for taxable temporary differences and total federal
taxable income ........................................................................................................... 59
Table 27. Calculation of income tax using AET’s current methodology for treatment of
AFUDC, based on Mr. Hoshowski’s exchange with Commission counsel .......... 65
Table 28. Calculation of income tax if AFUDC was treated the same as other capital
project costs when the asset was put into service ................................................... 67
Table 29. Calculation of income tax if AFUDC deduction was taken in year incurred but
AFUDC not added to utility earnings before tax ................................................... 68
Table 30. 2014-2017 actual and 2018-2019 forecast capital repair costs .............................. 71
Table 31. AET – 2015-2019 taxes other than income tax ....................................................... 76
Table 32. TCM and isolated generation forecast expenditures and additions ..................... 80
Table 33. Snapshot of AET assets and renewal forecast ........................................................ 81
Table 34. Summary of transmission necessary working capital ......................................... 116
Table 35. Isolated operating costs 2015-2017 ........................................................................ 118
Table 36. CCA submission on approved versus actual isolated generation operating costs
................................................................................................................................... 118
Table 37. Shared services comparison ................................................................................... 120
Table 38. Office supplies and expenses .................................................................................. 128
Table 39. Changes in general-other costs included in USA 921 .......................................... 130
Table 40. IT G&A expense ...................................................................................................... 131
Table 41. Reconciliation of changes in USA 934 for 2017-2018 .......................................... 132
Table 42. Forecast head office rent ........................................................................................ 152
Table 43. Credit metrics scenarios with and without federal FIT ...................................... 156
Table 44. Credit metrics scenarios which include federal FIT ............................................ 157
Table 45. Credit metrics scenarios which exclude federal FIT ........................................... 157
Table 46. Forecast long-term debt issues during test period ............................................... 160
Table 47. Forecast 2018 long-term debt rate ......................................................................... 160
Table 48. Forecast 2019 long-term debt rate ......................................................................... 160
Table 49. AET 2019 forecast, 2018 actual debt issue and current 30-year bond rates ..... 161
Table 50. Revenue offset forecasts by component for test years ......................................... 164
Table 51. Historical comparison of forecast and actual affiliate revenues ......................... 167
Table 52. Historical comparison of overhead recovery rates for affiliate services ............ 169
Decision 22742-D01-2019 (July 4, 2019) 1
Alberta Utilities Commission
Calgary, Alberta
ATCO Electric Ltd. Decision 22742-D01-2019
2018-2019 Transmission General Tariff Application Proceeding 22742
1 Decision summary
1. This decision reflects the Alberta Utilities Commission’s determinations following its
review of the 2018-2019 transmission general tariff application (GTA) of ATCO Electric Ltd.
(AET). The Commission found that not all of the forecast revenue requirements for the 2018-
2019 test period were reasonable and, consequently, revised or denied them.
2. The AET forecasts the Commission did not accept include:
The level of full-time equivalents (FTEs)
2019 escalation (inflation) rates
2018 severance costs
Costs and allocations with respect to ATCO Park
Cost allocations concerning Alberta PowerLine Limited Partnership (Alberta PowerLine)
Costs with respect to the Variable Pay Program (VPP)
Certain operating and maintenance (O&M) costs
Head office allocation costs and method regarding Alberta PowerLine
The Commission did not approve AET’s request to treat TCM project number 50463 for
line 9L101 (Kearl line) as a system cost
3. The Commission deferred its findings related to the Fort McMurray wildfire. It will issue
its decision contemporaneously with Proceeding 21609 for ATCO Electric Ltd. – Distribution’s
(AED) Z factor application related to the Fort McMurray wildfire. As a result, it is necessary that
certain aspects of AET’s application remain outstanding as placeholder amounts until such time
that the Commission renders its decision on matters pertaining to the Fort McMurray wildfire.
These placeholders are enumerated further in Section 8.2 of this decision.
4. The Commission directed that AET maintain certain deferral accounts including:
right-of-way payments;
debenture rate;
income tax capital repair costs and deductible capital cost deferral accounts;
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 2
taxes other than income; and
direct assigned capital.
5. The Commission did not agree with all changes AET requested to existing deferral
accounts.
6. The Commission also directed that the following reserve accounts be maintained by
AET: the reserve for injuries and damages (RID), VPP, vegetation management, and the rate
case. It did not agree with all changes AET requested to existing reserve accounts.
7. The Commission found that AET has complied with a number of the directions contained
in its 2015-2017 GTA decision (Decision 20272-D01-2016),1 and other related decisions, as
identified in Appendix 4 of this decision. The Commission approved AET’s continued use of its
terms and conditions of service, as filed.
8. The Commission made certain determinations on a placeholder basis that will be adjusted
in the compliance filing in this proceeding or in the next GTA. These placeholders are:
AET’s 2019 severance costs; and
how the costs and mechanics of the variable pay program (VPP) will be applied.
9. The Commission accepted AET’s forecasts of depreciation expense, capital additions on
direct assigned projects, capital maintenance projects, and general property, plant and equipment
projects. AET’s request to maintain its treatment of construction work in progress (CWIP) was
approved by the Commission.
10. The Commission ordered AET to submit a compliance filing with respect to its 2018-
2019 Transmission GTA by August 8, 2019, to reflect the findings and directions in this
decision.
2 Introduction and background
11. On June 16, 2017, AET filed a GTA with the Commission for each of the test years 2018
and 2019.
12. Subsequent to filing its initial application, AET filed updates, starting in June 2017 and
continuing into January 2019. Information on the updates is listed below:
November 10, 2017 – omissions and updates (O&U) filing which included updates on
capital, FTE employees, property taxes, inflation, O&M costs, long-term debt,
International Financial Reporting Standards (IFRS), terms and conditions, and directions
from Commission decisions issued after the filing of the original application.
Exhibit 22742-X0342.
1 Decision 20272-D01-2016: ATCO Electric Ltd., 2015-2017 Transmission General Tariff Application,
Proceeding 20272, August 22, 2016.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 3
November 14, 2017 – application update to reflect new or changed information provided
in round 1 information requests (IRs) and directions from Commission decisions issued
after the filing of the original application.2 Exhibit 22472-X0001.01.
June 25, 2018 – application update incorporating 2017 actual results from AET’s 2017
Rule 0053 report that was filed May 15, 2018.4
September 4, 2018 – revisions to various parts of the application, including the
withdrawal of AET's request to refund previously collected construction work in progress
(CWIP) in-rate-base balances; removal of the productivity factor; changes to the forecasts
for capital, O&M expenses, shared services, long-term debt, and isolated generation; and
directions from Commission decisions issued after the filing of the original application.5
September 6, 2018 – application update to reflect new or changed information provided
in round 2 IRs and directions from Commission decisions issued after the filing of the
original application.6
January 14, 2019 – application revisions provided in rebuttal evidence, including updates
to AET’s common group FTEs and the business case for the 9L101 Kearl Line
Relocation (Project 50463), and a comprehensive list of responses to all three rounds of
IRs to comply with a Commission direction.7
13. As part of its application and associated updates, AET ultimately sought the following:
Commission approval for revenue requirements of $691.7 million in 2018 and
$699.5 million in 2019.
AET rates, to be paid by the Alberta Electric System Operator (AESO) for the use of
AET’s facilities over the test period, based on AET’s approved forecast revenue
requirements.
The continued use of previously approved deferral and reserve accounts during the test
period for the following costs:
o defined benefit special payments
o flow-throughs
o income taxes relating to:
(i) statutory rates
(ii) deductions of deferrals for tax purposes
o directly assigned capital
o rate case reserve
o reserve for injuries and damages
o variable pay program reserve
2 Exhibit 22742-X0001.01, later replaced on September 6, 2018, by Exhibit 22742-X0001.02. 3 Rule 005: Annual Reporting Requirements of Financial and Operational Results. 4 Exhibit 22742-X0396. 5 Exhibit 22742-X0533. 6 Exhibit 22742-X0001.02, updated application. 7 Exhibit 22742-X0618, AET rebuttal evidence.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 4
o effects of IFRS
The discontinuance of the following previously approved deferral and reserve accounts
for the test period:
o right-of-way payments
o income taxes relating to:
(i) capital repair costs
(ii) deductible capital costs
o debenture rates
o vegetation management
Commission approval for the use of updated depreciation parameters supported by the
depreciation study prepared for AET by Concentric Advisors Ltd. (Concentric).
The continued use of federal future income taxes (FIT) for inclusion in revenue
requirements.
The continued use of placeholders during the test period for the following:
o common group costs
o IT common matters costs (based upon GTA IT volumes)
o defined benefit plan pension costs
o line insurance costs
Commission approval, under Section 27(1) of the Isolated Generating Units and
Customer Choice Regulation, for the replacement and addition of isolated generating
units.
14. The breakdown of the 2018 and 2019 revenue requirements are shown in the table below.
The revenue requirement increases show an annual increase of 2.7 per cent in 2018 and 1.1 per
cent in 2019.
Table 1. Comparison of revenue requirements for 2017-2019
Description 2017 actual Test period
2018 2019
($ million)
Revenues
Transmission tariffs 673.8 691.7 699.5
Deferral accounts (0.3) - -
Total Revenues 673.5 691.7 699.5
Costs
Fuel 6.9 7.1 7.9
Operating costs 170.4 155.7 153.2
Depreciation 148.4 191.5 195.1
Return on rate base 341.5 311.1 311.2
Income tax expense 38.1 34.4 40.3
Revenue offsets (32.0) (8.2) (8.1)
Total costs 673.5 691.7 699.5
Transmission tariffs 691.7 699.5
Revenue at existing rates 673.8 673.8
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 5
Description 2017 actual Test period
2018 2019
($ million)
Increase 17.9 25.7
% cumulative increase 2.7% 3.8%
% annual increase 2.7% 1.1%
Source: Based on Exhibit 22742-X0002.04, Schedule 3-1 Revenues and Costs.
15. A summary of forecast capital expenditures and capital additions for the test period is as
follows:
Table 2. Forecast capital expenditures and additions for test period
2018 forecast 2019 forecast
Expenditures Additions Expenditures Additions
($ million)
Direct assigned - system 116.7 122.1 56.5 99.5
Direct assigned - customer 14.6 25.2 79.0 30.9
Capital maintenance 83.3 83.2 88.0 93.3
Telecommunication 15.6 20.7 16.1 16.4
SCADA/EMS 3.7 2.7 2.5 5.4
Isolated generation 7.1 6.7 7.1 8.6
Direct general property, plant and equipment (PP&E)
1.1 1.3 7.9 7.8
Buildings 2.4 2.8 1.8 1.8
Software 10.3 14.5 11.5 16.3
Net salvage (6.1) (4.0)
Total 254.8 273.2 270.4 276.2
Source: Exhibit 22742-X0002.04, Schedule 10-4 Transmission Capital Expenditures.
16. AET requested Commission approval of additional opening rate base additions of $37.5
million above the amounts approved in AET’s 2015-2017 General Tariff Application, as shown
below:
Table 3. Summary of opening rate base additions from 2015-2017 GTA forecast
Category
Approved 2015-2017 GTA forecast additions (incorporating R&V
Decision 22094-D01-20178)
2015-2017 actual additions
Variance in additions to rate base
($ million)
Transmission Capital Maintenance 302.2 322.2 20.0
General Property and Equipment 15.8 33.3 17.5
Total 318.0 355.5 37.5
Source: Information derived from Exhibit 22742-X0001.02, application, Table 1.6 – PDF page 15, paragraph 28.
17. The Commission assigned Proceeding 22742 to the application and provided notice of the
application to parties on the Commission’s eFiling System on June 20, 2017. Statements of intent
to participate (SIPs) were due on July 4, 2017.
8 Decision 22094-D01-2017: Application for Review of Decision 20272-D01-2016, ATCO Electric Ltd., 2015-
2017 Transmission General Tariff Application, August 22, 2016, Proceeding 22094, March 16, 2017.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 6
18. The Commission received SIPs from the following parties:
AltaLink Management Ltd. (AltaLink)
Office of the Utilities Consumer Advocate (UCA)
Consumers’ Coalition of Alberta (CCA)
Industrial Power Consumers Association of Alberta (IPCAA)
Alberta Direct Connect Consumers Association (ADC)
19. IPCAA, the CCA and the UCA actively participated in the proceeding. ADC and
AltaLink were not actively involved in testing the application. Parties that registered as
interveners for this proceeding are listed in Appendix 1 to this decision. Parties that participated
in the oral hearing are listed in Appendix 2 to this decision.
20. A summary of the main process steps is provided below:
Table 4. Summary of the process and schedule
Process step Deadline
Round 1 IRs to AET August 30, 2017
Round 1 IR responses from AET September 25, 2017
Responses to outstanding IRs (Part 1) from AET October 31, 2017
Responses to outstanding IRs (Part 2) from AET November 10, 2017
Filing of undertakings by parties that wished to receive AET
confidential information February 7, 2018
AET’s delivery of confidential information to parties that signed
undertakings February 12, 2018
Further and better responses to IRs from AET May 11, 2018
Filing of AET’s Rule 005 reporting May 15, 2018
Further and better responses to IRs from AET May 18, 2018
Round 2 IRs to AET June 8, 2018
Round 2 IR responses from AET June 25, 2018
Further and better responses to IRs from AET August 10, 2018
Round 3 IRs to AET October 5, 2018
Round 3 IR responses from AET November 2, 2018
Further and better responses to IRs from AET November 21, 2018
Intervener evidence December 7, 2018
IRs on intervener evidence December 21, 2018
IR responses from interveners on intervener evidence January 4, 2019
Rebuttal evidence from AET January 14, 2019
Oral hearing – commencement January 21, 2019
Oral hearing – conclusion (seven hearing days – one-week break from
January 28 to February 1) February 6, 2019
Argument March 15, 2019
Reply argument April 5, 2019
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 7
21. Throughout the proceeding, the Commission issued several rulings and procedural
requests in response to motions brought by AET, the CCA and the UCA. A summary of the
rulings and procedural requests in the proceeding is provided in Appendix 3.
22. On January 22, 2019, the Commission issued an oral ruling denying the CCA’s request to
mark two aids to cross-examination-related exhibits on the record of this proceeding. The
Commission ruled on the test of admissibility of an aid to cross-examination. The full ruling
from the official transcripts is attached to this decision as Appendix 6.
23. The Commission considers that the record for this proceeding (22742) closed on April 5,
2019, the date for filing reply argument.
24. The Commission is a public body and, as such, unless otherwise directed, all documents
submitted to the Commission, as well as all decisions of the Commission, are publicly available.
The Commission granted confidential treatment to a portion of the evidence on the record of this
proceeding and held a portion of the proceeding in camera. This decision reflects the
Commission’s findings from all of the evidence on the record of this proceeding, including
evidence provided in the confidential portion of this proceeding.
25. In reaching the determinations throughout this decision, the Commission has considered
all relevant materials comprising the record of this proceeding, including the evidence and
arguments provided by each party. Accordingly, references in this decision to specific parts of
the record are intended to assist the reader in understanding the Commission’s reasoning relating
to a particular matter and should not be taken as an indication that the Commission did not
consider all relevant portions of the records with respect to a particular matter.
26. This decision deals with the contentious cost items forecast in the application, updates
and any matters that the Commission has otherwise determined are required to be specifically
addressed. If a matter or request for approval included in AET’s application is not addressed in
the findings, that matter or request is approved for the purposes of this GTA decision.
3 Responses to previous Commission directions
27. In its application, AET responded to 9 directions issued in Decision 20272-D01-2016 in
respect of ATCO Electric Ltd.’s 2015-2017 transmission GTA. AET also responded to one
direction from Decision 21206-D01-2017 issued in respect of the ATCO Electric 2013 and 2014
transmission deferral accounts and annual filings, one direction from Decision 22860-D01-2018
regarding the AET 2015-2017 transmission GTA second compliance filing, and one direction
from Decision 22859-D01-2018 regarding the AET common group compliance filing. In the
current decision, the Commission has reviewed the record as it pertains to all outstanding
directions. Where the Commission has identified issues or concerns with AET’s responses to a
direction, the Commission has provided reasons for its specific findings. Where no specific
finding is provided, the Commission has determined that AET’s responses comply with the
directions given and that no further action is required.
28. Where the Commission has determined that AET has complied with a direction, it is set
out in Appendix 4 of this decision. The Commission is satisfied that AET has adequately
addressed and responded to the following directions:
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 8
directions 47, 71, 73, 84, 97(1), 97(2) and Other Matter No. 9 from Decision
20272-D01-2016;
Direction 16 from Decision 21206-D01-2017;
Direction 1 from Decision 22860-D01-2018; and
Direction 1 from Decision 22859-D01-2018.
29. Directions 18, 21 and 27 from Decision 20272-D01-2016 remain outstanding and are
intended to be considered in a future depreciation study. They are listed in Appendix 5 and are
not addressed further in this decision.
4 Terms and conditions of service
30. AET provided a copy of the terms and conditions of service (T&Cs) under which it
operates, as Attachment 3.1 of its application.9
Commission findings
31. As there are no proposed changes to AET’s T&Cs, the Commission confirms AET’s
continued use of the T&Cs approved in Decision 22073-D01-2017.
5 Forecasting methodology and key assumptions
5.1 Manpower
5.1.1 Full-time equivalents
32. In its original application, filed June 16, 2017, AET provided its FTE forecast, which was
based on its activity-based forecasting methodology. AET stated that its forecast of FTEs
remained stable throughout the test period.10 A summary of AET’s originally filed FTE forecast
is provided below:
9 Exhibit 22742-X0001.02, updated application, Attachment 3.1, ATCO Electric Ltd. Transmission Terms and
Conditions, PDF pages 129-140. 10 Exhibit 22742-X0001.01, paragraphs 40-41.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 9
Table 5. AET FTE forecast - Original application June 16, 2017
Schedule Description 2015
Actuals 2016
Actuals 2017
Forecast
Test period
2018 2019
Schedule 5-5
2015-17 GTA complement - 2018-19 GTA forecast - total
918.0 741.8 736.3 729.0 725.0
Vacancy (negative) indicates higher complement than applied for
-67.7 2.9 18.4 18.3 18.2
Final adjusted complement 985.6 738.9 717.9 710.7 706.7
Vacancy rate -7.4% 0.4% 2.5% 2.5% 2.5%
Schedule 25-5
2015-17 GTA complement - 2018-19 GTA forecast - total
273.9 202.8 161.7 159.9 158.8
Vacancy (negative) indicates higher complement than applied for
67.7 71.8 4.0 4.0 4.0
Final adjusted complement 206.3 131.0 157.7 155.9 154.8
Vacancy rate 24.7% 35.4% 2.5% 2.5% 2.5%
Total AET
2015-17 GTA complement - 2018-19 GTA forecast - total
1,191.9 944.6 898.0 888.9 883.7
Vacancy (negative) indicates higher complement than applied for
0.0 74.7 22.4 22.3 22.2
Final adjusted complement 1,191.9 869.9 875.5 866.6 861.5
Vacancy rate 0.0% 7.9% 2.5% 2.5% 2.5%
Final adjusted complement by area
Total O&M 343.2 272.2 273.3 280.1 278.3
Capital 848.7 597.7 602.2 586.5 583.2
1,191.9 869.9 875.5 866.6 861.5
Source: Exhibit 22742-X0002, 00-2018-2019 GTA schedules, Sch 5-5 and Sch 25-5.
33. In its O&U filing submitted November 10, 2017, AET adjusted its FTE forecast. AET
repeated that its FTE forecast was based on its activity-based forecasting methodology and that
its overall forecast of FTEs remained stable throughout the test period.11 The table below shows
the updated forecasts for 2018 and 2019:
Table 6. AET FTE forecast – Omissions and updates filing November 10, 2017
Schedule Description 2015
Actuals 2016
Actuals 2017
Forecast
Test period
2018 2019
Schedule 5-5
2015-17 GTA complement - 2018-19 GTA forecast - total
918.0 741.8 734.5 740.9 743.0
Vacancy (negative) indicates higher complement than applied for
-67.7 -0.5 30.5 18.5 18.6
Final adjusted complement 985.6 742.3 704.0 722.4 724.5
Vacancy rate -7.4% -0.1% 4.2% 2.5% 2.5%
Schedule 25-5
2015-17 GTA complement - 2018-19 GTA forecast - total
273.9 202.8 168.3 150.3 149.2
Vacancy (negative) indicates higher complement than applied for
67.7 71.8 6.4 3.8 3.7
11 Exhibit 22742-X0001.01, paragraphs 39-40.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 10
Schedule Description 2015
Actuals 2016
Actuals 2017
Forecast
Test period
2018 2019
Final adjusted complement 206.3 131.0 161.9 146.6 145.5
Vacancy rate 24.7% 35.4% 3.8% 2.5% 2.5%
Total AET
2015-17 GTA complement - 2018-19 GTA forecast - total
1,191.9 944.6 902.8 891.2 892.3
Vacancy (negative) indicates higher complement than applied for
0.0 71.2 36.9 22.3 22.3
Final adjusted complement 1,191.9 873.4 865.9 869.0 870.0
Vacancy rate 0.0% 7.5% 4.1% 2.5% 2.5%
Final adjusted complement area
Total O&M 343.2 275.6 260.2 277.8 280.5
Capital 848.7 597.7 605.6 591.2 589.5
1,191.9 873.4 865.9 869.0 869.9
Source: Exhibit 22742-X0002.01, 00-2018-2019 GTA schedules, Schedule 5-5 and Schedule 25-5.
34. In its application update filed September 4, 2018, AET stated that it, once again, needed
to revise its FTE forecast, this time as a result of changes to its O&M and capital program
forecasts:12
Table 7. AET FTE forecast – Application update September 4, 2018
Schedule Description 2015
Actuals 2016
Actuals 2017
Actuals
Test period
2018 2019
Schedule 5-5
2015-17 GTA complement - 2018-19 GTA forecast - total
918.0 741.8 750.3 654.1 613.8
Vacancy (negative) indicates higher complement than applied for
-67.7 -0.5 95.9 16.4 15.3
Final adjusted complement 985.6 742.3 654.3 637.7 598.5
Vacancy rate -7.4% -0.1% 12.8% 2.5% 2.5%
Schedule 25-5
2015-17 GTA complement - 2018-19 GTA forecast - total
273.9 202.8 203.3 144.7 136.0
Vacancy (negative) indicates higher complement than applied for
67.7 71.8 56.8 3.6 3.4
Final adjusted complement 206.3 131.0 146.5 141.1 132.6
Vacancy rate 24.7% 35.4% 27.9% 2.5% 2.5%
Total AET
2015-17 GTA complement - 2018-19 GTA forecast - total
1,191.9 944.6 953.6 798.8 749.8
Vacancy (negative) indicates higher complement than applied for
0.0 71.2 152.7 20.0 18.7
Final adjusted complement 1,191.9 873.4 800.9 778.9 731.0
Vacancy rate 0.0% 7.5% 16.0% 2.5% 2.5%
Final adjusted complement by area
Total O&M 343.2 275.6 245.8 221.8 215.6
Capital 848.7 597.7 555.1 557.1 515.5
12 Exhibit 22742-X0533, paragraph 23.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 11
Schedule Description 2015
Actuals 2016
Actuals 2017
Actuals
Test period
2018 2019
1,191.9 873.4 800.9 778.9 731.0
Source: Exhibit 22742-X0002.04, AET GTA Schedules, Schedule 5-5 and Schedule 25-5.
35. The CCA stated in its argument that the reason AET’s FTE forecast keeps changing is
that AET is no longer incurring costs on a common group basis and has consolidated specific
department staff into the shared services groups.13
36. The CCA referenced an exchange during the oral hearing in which Mr. Goguen,14 witness
for AET, admitted that AET tracks its labour costs but not its FTEs. The CCA asserted that
AET’s FTE forecast lacked certainty and did not reflect expected efficiencies from its shared
services model. The CCA added that statements by AET that it was starting to see “synergies and
best practices”15 and “hoping for more in the coming years,”16 led the CCA to presume further
efficiencies are likely, and justified disallowing a portion of AET’s forecast labour costs.17
37. AET responded that it “does not have a system to specifically track FTEs by cost centre
or uniform system of accounts (USA)… As explained, the difficulty with the Aids-to-Cross is
that AET could not easily go back in time and reallocate FTEs to functions that are now
performed under the shared services initiative.”18 However, AET submitted that this does not
mean that it cannot accurately forecast its FTE requirements for the test years, using its activity-
based forecasting methodology that has previously been approved by the Commission. Rather,
the challenge for AET is to go back in time and recreate what the FTE situation would
previously have been, so that a historical comparison can be made between (1) the number of
FTEs performing the functions now imbedded in the shared services initiative and (2) the cost
centres with which these FTEs, or portions thereof, had formerly been associated. AET added:
As explained by AET, the difficulty in tracking FTEs over time is because the persons
occupying these positions change over time or are charged to different cost centres at
different points in time. As confirmed, the challenge is not with respect to tracking the
costs, as the employees are tracked on a timesheet basis. Rather, the challenge is with
respect to tracking the FTEs over time and in particular, going back in time, and
attempting to create an FTE picture that can now accurately be compared to an FTE
picture under the shared services model. [footnotes removed]”
…
AET submits that any suggestion that it cannot track FTEs and, therefore, cannot develop
or manage its business is simply incorrect. The challenges faced by AET during this
proceeding relate mainly to an attempt to recreate a historical FTE picture, so that it can
be directly compared to a very different, current period optic, such as where the shared
services initiative now exists. In order to develop this information, AET would have to
employ an onerous and time consuming manual process to dissect each FTE into its
various components and then follow every single employee through the last several years
to understand each position they have held, every group they have worked for and how
13 Exhibit 22742-X0722, CCA final argument, paragraph 304. 14 Transcript, Volume 6, page 975, line 12 to page 979 line 15. 15 Transcript, Volume 6, page 979, lines 8-9. 16 Transcript, Volume 6, page 979, line 10. 17 Exhibit 22742-X0722, CCA final argument, paragraph 303-305. 18 Exhibit 22742-X0725, AET final argument, paragraphs 93.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 12
their allocations have changed over time, on an actual and/or forecast basis over multiple
years. As noted, AET simply does not have the tools to support such a process.19
[footnotes removed]
38. In its reply argument, the CCA stated that AET’s argument was confusing and surprising
and should be afforded no weight by the Commission. The CCA offered as an example, that
while AET said it does not have a system to track FTEs by cost centre or USA, it could still
accurately forecast its FTE requirements for the test years. The CCA argued that AET could not
reasonably be certain of its future resource requirements if it does not track its historical resource
requirements.20
Commission findings
39. In its argument, AET confirmed that while it does track labour costs, as employees are
tracked on a timesheet basis, its challenge lies in tracking FTEs over time and, especially, in
trying to recreate an FTE picture from the past that can be compared to an FTE picture under the
current shared services model.
40. At the oral hearing, Mr. Hoshowski, witness for AET, explained how AET tracks its costs
by FTE and cost centre under the new shared services initiative:
So with the implementation of the shared-services initiative, there have been new cost centres
created which pulls together all of the people that have been pulled out of the respective
companies to form these functional groups. So going back in time, under ATCO Electric for those
functional groups that became shared services, those individuals would have resided previously
within a variety of different ATCO Electric cost centres.21
41. Mr. Hoshowski also pointed to the difficulty in replicating FTEs by functions under the
shared services model for 2018 and 2019, and “rewinding the clock back to the 2015, 2016 and
2017 periods [to determine] what the equivalent of those same costs based on the services
provided”22 would represent. He confirmed that he could not provide 100 per cent assurance that
the costs are identical but, rather, that any comparison would be on a best efforts basis.23
42. Additional testimony from Mr. Bothwell, witness for AET, addressed the difficulty that
AET has in tracking FTEs through the various functions or cost centres FTEs occupy at different
times within the company. Mr. Bothwell stated that AET’s systems are not set up to track
individual FTEs. Instead, they aggregate FTE positions by cost centres. As such, it is not
possible for AET to take FTEs that were formerly part of functional groups in separate ATCO
companies and reconstruct or reconstitute them for purposes of comparison in the new shared
services functions they now occupy.
43. Mr. Bothwell provided further testimony on how AET’s forecasts are derived, as follows:
… we track the positions and the cost centres. They – the FTEs all add up. It's when you
asked me to tie the position in 2017 to the way it was forecast for 2017, which is a
forecast we provided in 2015. And then on top of that we do org changes in the actuals
19 Exhibit 22742-X0725, AET final argument, paragraphs 94 and 98. 20 Exhibit 22742-X0726, CCA reply argument, paragraph 37. 21 Transcript, Volume 6, page 973, lines 7-15. 22 Transcript, Volume 6, page 983, lines 24-25 and page 984 line 1. 23 Transcript, Volume 6, page 985, lines 2-12.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 13
during that same period of time. That's when it starts getting – you know, that 1.0 total
that makes up one full person's FTE, that's where it ends up in five, six, seven different
lines and in different forecasts. We might have forecast it in this cost centre for these
years, but the actual might be in a totally different cost centre, depending on how we
organize our structure.24
… We can track it, but it is -- for the FTE-level information, because we don't have an
Oracle system that does FTEs for us or some other system that accounts for FTEs for us,
it is a purely manual process. And the need to -- in hindsight, the need to track people's
names to the positions to the day they -- it's not that we don't have all this information, we
just don't have this information in a system that allows us to just spit out the simple
answer whereas our accounting system can because it doesn't worry about who -- what
the person's name was that was in that position.25
44. As demonstrated in the testimony above, AET cannot provide historical comparisons of
FTEs, and was not able to validate that the historical costs26 were comparable, in part, because of
the difficulty in directly tracking these FTEs and associated costs by cost centre.
45. In Decision 22859-D01-2018,27 AET’s common group compliance filing, the
Commission set out what it expected of AET when providing comparative figures in connection
with organizational structure changes such as the common group. AET provided the following
explanation in the common group compliance filing proceeding, as noted at paragraph 44 of the
decision:
44. In response to the IR, ATCO Electric - Transmission stated:
…
AET would like to note that the overall number of FTE’s in the Common Group
Proceeding are less than the FTE’s established in the 2015-2017 GTA 2nd
Compliance filing Schedule 25-5. Given that the original placeholder included in …
AET’s 2015-2017 GTA application was developed specifically to support AET
functions, and the Common Group forecast was prepared based on the allocation of a
wider group of common ATCO Electric employees, a comparison cannot be done on
an individual FTE basis between the two applications. [footnote removed]
46. In paragraphs 45 to 49 of that decision, the Commission found AET’s IR response that it
cannot compare and explain the differences between what was approved in its 2015-2017 GTA
and the Common Group forecast was not credible. The Commission expected that at least some
form of analysis would have been undertaken to reconcile the forecast common group costs with
the placeholders approved in the 2015-2017 GTA second compliance filing. The Commission
found that AET had not provided sufficient evidence to support a finding that the requested FTEs
and dollar amounts were reasonably justified. AET was directed, on a go-forward basis, to
provide all cost-information for every ATCO affiliate, comprising the total costs and supporting
detail that substantiate and justify the costs allocated to, or from, AET’s transmission function.
24 Transcript, Volume 6, page 968, lines 12-25. 25 Transcript, Volume 6, page 969, line 25 to page 970, line 11. 26 Exhibit 22742-X0608. 27 Decision 22859-D01-2018: ATCO Electric Ltd. Transmission Common Group Compliance Filing,
Proceeding 22859, March 20, 2018.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 14
47. Similar to the Commission’s findings in Decision 22859-D01-2018, the Commission is
concerned with AET’s ability to properly account for its allocation of costs for the common
group and, as supported by the testimony of the AET witnesses in the oral hearing, for shared
services as well. The Commission finds that the level of detail supporting the FTEs and
associated costs that may at one time have resided in AET only, or as part of the common group,
but may now be associated in whole or in part with the shared services group, is limited.
48. As confirmed by AET, it derives its FTE requirements for the test period years using the
Commission's approved activity-based forecasting methodology. In past GTAs, the Commission
reviewed AET’s “activity-based” FTE forecasting accuracy. For example, in its 2015-2017 GTA,
AET sought approval of the following forecast FTE levels:28
Table 8. Summary of forecast complement for 2015-2017 test period
Test period
Description 2015 2016 2017
Schedule of transmission manpower (FTEs) - Schedule 5-5(1)
Complement - 2015-2017 GTA forecast - permanent 944.6 868.6 890.4
Complement - 2015-2017 GTA forecast - temporary 32.6 31.4 30.5
Complement - 2015-2017 GTA forecast - total 977.2 900 920.5(3)
Schedule of corporate manpower (FTEs) - Schedule 25-5(1)
Complement - 2015-2017 GTA forecast - permanent 276.8 254.1 255.3
Complement - 2015-2017 GTA forecast - temporary 5.2 5.9 5.7
GTA complement - 2015-2017 GTA forecast - total 282 260 261
Schedule of total company complement
Complement - 2015-2017 GTA forecast - permanent 1,221.40 1,122.70 1,145.70
Complement - 2015-2017 GTA forecast - temporary 37.8 37.3 36.2
Complement - 2015-2017 GTA forecast - total(2) 1,259.20 1,160.00 1,181.50
Source: (1)Proceeding 20272, Exhibit 20272-X1101, schedules 5-5 and 25-5. (2)Proceeding 20272, Exhibit 20272-X1069. (3)The Commission observes ATCO Electric has hard-coded this value into the referenced exhibits.
49. AET’s updated 2015-2017 GTA forecast was submitted on February 23, 2016. During
the course of that proceeding, AET provided a headcount of 941 people as of the end of
December 2015.
50. In Decision 20272-D01-2016, the Commission identified concerns about workforce
reductions in AET's 2015 forecasts of its 2016 FTEs, as follows:29
The Commission finds that ATCO Electric’s forecasted FTE requirements for 2016 are
not sufficiently justified in the wake of its 2015 workforce reductions, notwithstanding
the fact that ATCO Electric stated that it is properly staffed based on its assessment of the
newly anticipated base level of work to be completed. The Commission approves only
28 Decision 20272-D01-2016, Table 3. Summary of forecast complement for test period. 29 Decision 20272-D01-2016, paragraph 83.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 15
the following requested FTE additions for 2016 that are required to complete work
related to cyber security and Alberta Reliability Standards as set by the AESO.
51. In Decision 20272-D01-2016, the Commission approved an additional 3.5 FTEs in 2016,
which resulted in a total of 944.6 FTEs being allowed for 2016 (as shown in Table 5 above). The
variance between AET’s 2015-2017 applied-for GTA FTE forecast and the approved FTE
amount was 215.4 FTEs30 notwithstanding that most of the 337 positions terminated were
eliminated in the last quarter of 2015.31 In its 2015-2017 GTA argument, AET developed its FTE
requirements using the same “activity-based” budgeting approach as filed in this proceeding.32
52. In its O&U filing, AET provided an FTE forecast of 865.9 FTEs for 2017 (Table 6
above). As shown in the application update (Table 7 above), the 2017 actual total for FTEs was
800.9. The difference between these two application updates is 65 FTEs33 or eight per cent. In the
Commission’s view, this 2017 variance further demonstrates the inability of AET to adequately
forecast its FTEs for shared services, due to the uncertainties and technical challenges involved.
53. For the above reasons, the Commission finds that AET has failed to justify its requested
FTEs and associated dollar amounts in the test years. Based on the past FTE forecasts noted
above and the inability of AET to accurately track FTEs by cost centre through various
organizational changes, including the new shared services initiative, the Commission cannot
reasonably rely on the FTE forecasts filed by AET. The Commission, therefore, directs AET to
use its 2018 actual FTEs as the approved FTE complement for 2018. The 2018 FTEs are
approved as the opening 2019 FTE complement. The Commission notes that the direction for
2018 is consistent with AET’s Rule 005 reporting, which reflected 716.1 FTEs in 2018.34
54. For the purposes of this decision and the compliance filing to follow, the Commission
directs AET not to offset the impacts of the reduction to capital FTEs with an increase in
contractor costs.
55. In Decision 22860-D01-2017,35 the Commission stated the following:
25. It appears to the Commission that the average base salary (total labour dollar per
FTE) method used by ATCO Electric to adjust O&M labour dollars, as a result of
changes in O&M FTEs, differs from how ATCO Electric may be forecasting labour
dollars for O&M FTEs in its GTA. As shown in Table 3, the amounts for labour dollar
per O&M FTE and total labour dollar per FTE are not the same. Therefore, to ensure that
neither ATCO Electric nor its customers are unjustly advantaged or disadvantaged by any
variance between the forecasted labour dollar for an O&M FTE and the use of the
average base salary when O&M FTE adjustments are required, ATCO Electric is directed
in all future applications to use the amounts included in its GTA forecast for each FTE
30 Calculated as: 1,160 FTEs – 944.6 FTEs. 31 Exhibit 20272-X0735, AET-AUC-2015DEC30-012(b). 32 Exhibit 20272-X1298, ATCO Electric argument, paragraph 59. 33 Calculated as: 865.9 FTEs – 800.9 FTEs. 34 ATCO Electric - Transmission 2018 Rule 005: Annual Reporting Requirements of Financial and Operational
Results, Schedule 8. 35 Decision 22860-D01-2017: ATCO Electric Ltd. 2015-2017 Transmission General Tariff Application Second
Compliance Filing, Proceeding 22860, November 21, 2017.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 16
position when calculating the dollar impacts to FTE adjustments, unless specifically
directed otherwise by the Commission.36
56. Given that the Commission’s direction to reduce AET’s FTE forecast in 2019 is not a
reduction to specific identifiable positions, AET is directed to calculate the impact of its O&M
FTE reductions using the average O&M salary per FTE and its capital FTE reductions using the
average capital salary per FTE.
57. In Decision 20272-D01-2016, the Commission found that the mid-year convention
should apply to the removal of an FTE in the year of its forecast removal if the utility is not
expecting to fill the position through promotion or an external hire going forward. This treatment
shall continue to apply regardless of the underlying reason for removal.37
58. In its compliance filing to this decision, AET is directed to confirm, for the positions it
has forecast to eliminate in 2019, that they have been removed in accordance with the findings
and directions in this section, using the mid-year convention.
5.1.2 Vacancy rates
59. The vacancy rate represents a ratio of the estimated number of vacant FTE positions to
the total number of approved FTE positions for a given period, and is used to reduce the forecast
labour costs to reflect that a certain number of positions will, on average, be vacant in the
forecast period.38
60. In its application, AET proposed that a 2.5 per cent vacancy rate be applied to its forecast
labour complement (also known as full-time equivalents or FTEs) for each of 2018 and 2019. In
deriving its vacancy rate, AET stated that it had assumed a gradual recovery of the Alberta
market, which is consistent with lower levels of staff turnovers in 2016.39
61. In its evidence, Bema Enterprises Ltd. (Bema)40 stated that Alberta is going though a
period of uncertainty, as demonstrated by the Alberta Government reducing its growth forecast
from prior estimates for 2018 and 2019. Bema acknowledged that these revised growth estimates
could support a lower turnover rate, and consequently a lower vacancy rate because there may be
fewer employment options in the marketplace. However, given AET’s history of workforce
reductions, Bema submitted that it should be expected that additional vacancies will occur as
AET continues to “look for efficiencies in shared services and other areas.”41
62. Bema observed that the vacancy rate for administrative and general employees in
Schedule 25-5 of the application was 35.4 per cent in 2016, while the vacancy rate in operations
and maintenance Schedule 5-5 was -0.1 per cent in 2016, neither of which Bema considered
36 Decision 22860-D01-2017, paragraph 25. 37 Decision 20272-D01-2016, paragraph 101. 38 Decision 3539-D01-2015: EPCOR Distribution & Transmission Inc. 2015-2017 Transmission Facility Owner
Tariff Proceeding 3539, October 21, 2015, paragraph 148. 39 Exhibit 22742-X0001.02, updated application, paragraph 52. 40 The CCA retained Bema as its consultant for this proceeding. Bema submitted evidence on behalf of the CCA
during this proceeding. In this decision, when the Commission refers to the CCA, the reference is to the CCA
itself or to its consultant, Bema, as may be applicable. 41 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 462.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 17
consistent with the 2.5 per cent for the test years.42 Bema provided a summary of AET’s actual
vacancy rate for the period covering AET’s prior GTA period of 2015-2017, as follows:
Table 9. Summary of vacancy rates 2015-2017
2015 2016 2017
(%)
Operations and maintenance (Schedule 5-5) -7.4 -0.1 12.8
Administrative and general (Schedule 25-5) 24.7 35.4 27.9
Total 0.0 7.5 16.0
Source: Exhibit 22742-X0592, CCA - Evidence of Bema, paragraph 463.
63. Bema suggested that a more practical vacancy rate should reflect historical results. Using
the historical rates and applying its own judgment, Bema recommended that the Commission
approve a vacancy rate of five per cent for operations and maintenance staff and 10 per cent for
administration and general staff, for each of 2018 and 2019.43
64. In rebuttal evidence, AET stated that Bema’s recommended vacancy rates for 2018 and
2019, based on adjusted 2015-2017 vacancy rates, is flawed. AET submitted that its forecast
vacancy rate of 2.5 per cent, which is lower than its historical vacancy rates, is reasonable in
2018 and 2019, for the following reasons:
Material changes in the organizational structure and the significant emphasis on
increased efficiencies and cost reduction initiatives across the organization in 2016-
2017 have rendered actual vacancy rates for this period both irrelevant and unreliable
for forecasting future years.
Material workforce reductions in 2018 to right-size the workforce based on the 2018-
2019 economic outlook and to account for the significant efficiencies achieved in
2016-2017 and forecast to be achieved in 2018-2019 have already been fully
incorporated into the total gross forecast complement in the September 2018
application update, to which the 2.5% vacancy rate is applied.
The stabilization of AET’s workforce through the absence of large-scale changes,
including restructuring and workforce reductions, in combination with increased
focus on employee engagement, communication and fair market compensation.44
65. The CCA requested that the Commission discount AET’s statement that its 2018
workforce reductions have already been fully incorporated into the most recent application
update in considering AET’s forecast vacancy rate. Bema pointed out that AET made much the
same argument in the 2015-2017 GTA, specifically, that the 2015 workforce reductions would
result in lower vacancies in 2016 and 2017. Yet, as Table 9 demonstrates, the opposite occurred.
According to the CCA, the 2018 and 2019 vacancy rates should be considered conservative, as
they are generally lower than the actual vacancy rates achieved in 2016 and 2017. The CCA
urged the Commission to approve Bema’s recommended five per cent vacancy rate for
42 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 461. 43 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraphs 474-475. 44 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 115.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 18
operations and maintenance staff and 10 per cent vacancy rate for administration and general
staff for each of 2018 and 2019.45
66. AET argued that it does not expect the 2016 and 2017 vacancy rates to be indicative of
the vacancy rates it will experience in 2018 and 2019, and further argued that Bema’s
recommended vacancy rate of five per cent for operations and maintenance and 10 per cent for
administrative and general staff is arbitrary and based on the “judgment”46 of Bema’s
Mr. Madsen.
Commission findings
67. In its evidence, Bema stated that a vacancy rate should reflect historical results. In
coming to its recommended vacancy rate of five per cent for operations and maintenance (O&M)
staff and 10 per cent for administration and general (A&G) staff, for 2018 and 2019, Bema used
the historical vacancy percentages from 2016 and 2017 as a guide and then applied its own
judgment.
68. However, in Decision 20272-D01-2016, the Commission recognized the economic
environment in setting vacancy rates:
The Commission finds it reasonable to expect a lower level of employee turnover in the
current economic environment and, therefore, accepts ATCO Electric’s argument in
support of a 2.5 per cent vacancy rate for 2016 and 2017. ATCO Electric’s vacancy rates
are approved as filed.47
69. Further, as argued by AET, historical vacancy rates include the reduction in FTEs
resulting from workforce reductions. By relying on historical vacancy rates in developing its
recommended vacancy rates, Bema has, in effect, built further workforce reductions into its
recommendations. Bema’s recommendations also reflect the expectation that additional
vacancies will occur as a result of AET looking “for efficiencies from its shared services and
other areas.”48
70. The Commission does not agree with the CCA’s proposal to superimpose historical
vacancy rates on forecast FTEs, as doing so would incorporate further workforce reductions. The
vacancy rate should not be used as the mechanism that adjusts for FTEs and labour forecast
dollars approved in the test period, when those adjustments are made separately in the section
dealing with FTE forecasts. The Commission finds that any FTE or position reductions should be
addressed through adjustments to staffing level requirements, that is, FTEs, in those test periods.
71. As discussed in paragraph 53 above, the Commission directed AET to use 2018 actual
FTEs as its 2018 FTE approved complement. The use of 2018 actuals reflects zero vacant FTEs
for 2018. Accordingly, a vacancy rate of zero per cent for 2018 is approved.
72. Consistent with Decision 20272-D01-2016, and AET’s explanation in its rebuttal
evidence of the factors affecting vacancy rates, the Commission finds it reasonable to expect a
lower level of employee turnover in the current economic environment and the stabilization of
45 Exhibit 22742-X0722, CCA final argument, paragraphs 446-449. 46 Exhibit 22742-X0725, AET final argument, paragraph 88. 47 Decision 20272-D01-2016, paragraph 108. 48 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 462.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 19
AET’s workforce in the test year. The Commission agrees with AET that these factors support a
2.5 per cent forecast vacancy rate in 2019. AET’s vacancy rate of 2.5 per cent for 2019 is
approved, as filed.
5.1.3 Severance costs
73. In its September 4, 2018 update, AET explained that it had identified efficiencies in the
manner it executes O&M work activities, and had reduced the volume of capital project work.
These two work measures resulted in reductions to AET’s workforce that, in turn, resulted in
severance costs that AET is now seeking to recover in the 2018-2019 test period. AET submitted
that the workforce reductions will result in lower costs for ratepayers in the current and future
test periods.49
74. AET stated that its workforce reductions result in an increase to revenue requirement of
$7.2 million in 2018 relative to the forecasts included in its O&U filing. AET produced the
following table showing that the total increase in severance costs in the test period was
$7.6 million in 2018, and $0.3 million in 2019.
Table 10. AET severance costs (application update)
Test Period 2018
Actuals 2019
Update
($ million)
O&U (Exhibit 22742-X0002.01, Schedule 25-5, USA 921) 0.4 0.3
Application Update (Exhibit 22742-X0002.04, Schedule 25-5, USA 921) 7.6 0.3
Total Increase/(Decrease) 7.2 0.0
Exhibit 22742-X0533, AET 2018-2019 GTA - September 4, 2018, Update, paragraph 36, Table 10: Severance.
75. In response to an undertaking provided to Commission counsel during the oral hearing,
AET provided a revised forecast of its severance costs, as follows:
Table 11. AET severance costs
Position(s) Amount
($ million)
2018 paid #1 to #129 and #132 6.0
2019 paid #130, #131 and #133 0.1
2019 forecast #134 to #155 1.5
Total 2019 1.6
Total severance #1 to #155 7.6
Source: Exhibit 22742-X0700, Undertaking 54.
76. In its evidence, Bema stated that “where an AET employee is terminated and that
employee has provided services to an affiliate, then the affiliate should bear a portion of the cost
of the severance for that employee.”50 Bema noted that AET allocated severance costs based on
49 Exhibit 22742-X0533, AET 2018-2019 GTA - September 4, 2018 Update, paragraphs 21-22. 50 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 478.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 20
common group allocations, but suggested that the allocations used may not be the final allocators
approved by the Commission. Bema therefore recommended that AET be directed to use the
final approved common group allocators to allocate severance costs for all common group
employees severed.51
77. Based on its review of AET’s severed positions that are not part of the allocated common
group employees, Bema determined that in each year there were additional charges to affiliates
beyond the charges included in the common groups. Bema stated that AET’s severed workers
provided affiliates with approximately 13.1 per cent of their labour time based on a three-year
average between 2014 and 2017. Therefore, 13.1 per cent of the severance costs should be
allocated to affiliates rather than AET. Based on the results of its analysis, Bema recommended
that the Commission deny $1.0 million of AET’s requested $7.9 million in severance costs.52
78. AET pointed out that Bema had incorrectly considered AED to be an affiliate in the
calculation of severance costs. This was an error because AED has an affiliate exemption. In its
rebuttal evidence, AET provided revised calculations to reflect the affiliate exemption and
removed AED in calculating the percentages of total labour provided to affiliates. Based on
AET’s calculations, the three-year average of severance costs would be 2.12 per cent, and not the
13.1 per cent calculated by Bema. Taking the 2.12 per cent figure for severance costs attributable
to affiliates results in an allocation of severance costs to affiliates of $0.2 million in 2018. AET
stated that its use of an affiliate overhead rate of 23 per cent, rather than its calculated overhead
rate of 21 per cent, adequately covers its forecast severance costs related to affiliate work of
$0.2 million in 2018 and a forecast of zero in 2019.53
79. In response to AET, the CCA noted the following exemption granted in Decision 2004-
054 by the Alberta Energy and Utilities Board (board), the Commission’s predecessor:
(1) In respect of transactions between ATCO Electric Transmission and ATCO
Electric Distribution, exemption is granted from the requirements set out in Section 3.3.1,
Shared Use of Employees, of the ATCO Group Inter-Affiliate Group Code of Conduct
solely for the purposes and in the manner described in the Application and approved by
this Decision.54
80. The CCA concluded on the basis of the above decision that AET’s claim that AED is not
an affiliate for the purposes of calculating severance cost adjustments should be rejected. The
CCA submitted that Bema’s recommended disallowance of $1.0 million of AET’s applied-for
severance costs remained valid.
81. AET argued in reply that if additional severance were to be allocated to AED based on
Bema’s evidence and the CCA’s argument, it would result in double counting. AET submitted
that its proposed method for allocating severance costs is transparent and reasonable, and that
severance costs for all other affiliates is recovered through the affiliate overhead rate.55
51 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraphs 478-481. 52 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraphs 482-488. 53 Exhibit 22742-X0618, AET rebuttal evidence, PDF pages 118-120 54 Decision 2004-054: ATCO Electric Ltd., Code of Conduct Exemptions, Application 1317784-1, July 28, 2004,
page 11. 55 Exhibit 22742-X0727, AET reply argument, paragraphs 98-101.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 21
82. No party objected to the actual amounts of severance paid in respect of each individual
position severed.
Commission findings
83. With respect to actual severance costs for 2018 and the updated forecasts provided in
response to the undertaking, the Commission finds that the actual and updated forecast amounts
awarded to severed employees by AET were reasonable in the circumstances. The remaining
required determination for the Commission is what amount of severance costs should be
recovered in rates.
84. In response to a Commission IR,56 AET provided its termination and severance policies
for both in-scope and out-of-scope employees. AET also confirmed that the termination and
severance policies for both in-scope and out-of-scope employees are common to all ATCO
companies.57 However, the in-scope termination polices do not apply on an ATCO-wide basis.
Rather, they are specific to each respective collective agreement such as that with the Canadian
Energy Workers Association (CEWA).58
85. AET witness, Mr. Goguen, confirmed that the determination of severance amounts was
based on years worked in all ATCO companies, and not just AET.59
86. AET confirmed that in allocating the forecast severance costs used in the 2018 forecast
labour allocation, AET used employees’ years of service. In some instances, there were
employees who spent time in another ATCO company, such as AED. The following exchange
provides an example of an employee who was severed and the calculation of how much time that
severed employee spent in each of AET and AED:
Q. MS. SABO: Now, moving back to Exhibit 558 again, I would like to look at Position
Number 7 on line 7, Column 7, which is the total years of service.
A. MS. GOODE: Yes.
Q. And this employee had 39 -- 31.9 years of service. Yes? And that's from Column –
A. MS. GOODE: Yes, that is what is shown here.
Q. Right. The percentage of service for this employee, and you can take this subject to
check, is approximately 97 percent of time ATCO Electric Distribution, so 30.8 divided
by 31.9. And 3 percent, which was 1.1 divided by 31.9 for ATCO Electric Transmission.
A. MS. GOODE: Yes, I can take that subject to check. I'd like to provide a little bit of
context around this for further understanding. ATCO Electric Transmission did not exist
in our Oracle HR or financial system as a standalone entity, I'll say. So what you will see
in Column G of Exhibit 558 is -- I believe it was January of 2013, subject to check -- that
ATCO Electric Transmission became its own, I'll call it, Oracle entity within our system.
So every employee will show less than five years of service with ATCO Electric
Transmission. That is not to say, however, that they were not performing transmission
56 Exhibit 22742-X0557.01, AET-AUC-2018OCT04-004. 57 Transcript, Volume 6, page 916, lines 3-7. 58 Exhibit 22742-X0688, Exhibit 22742-X0688 - Subject to Check - Goguen to Sabo. 59 Transcript, Volume 6, page 916, lines 8-24.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 22
services when they were part of ATCO Electric. So the remaining of their -- of all of
these employees who, by default, are showing in Column 5, entitled “ATCO Electric
Distribution” were not performing solely Distribution functions. That's just the default of
ATCO Electric prior to the creation of ATCO Electric Transmission standalone company.
Q. Okay. So those ATCO Electric Distribution numbers would be, for lack of a better
word, a blended number between -- because T&D would have been accounted for
together?
A. MS. GOODE: That is correct.
Q. Okay. So given that additional clarification, looking at the same position, Number 7
on line 7 of that exhibit, the allocation of severance was 100 percent to ATCO Electric
Transmission. Yes?
A. MS. GOODE: That is correct. I was also checking the updated attachment to
Undertaking 16, which also shows that that position was a 100 percent ATCO Electric
Transmission employee, which means that they were not in a common group providing
services.
Q. Okay. And given the Oracle system limitations, Ms. Goode, how are we assured that
that allocation should be 100 percent to ATCO Electric Transmission when the ATCO
Electric Distribution column is – you know, would be -- does not differentiate between
services for ATCO Electric Distribution compared to ATCO Electric Transmission prior
to the date you said?
A. MS. GOODE: To clarify, the cost allocators shown in Column H of Exhibit 559 is --
in 2018, that is where this employee resides and provides service. Again, with respect to
Position 7, they were a 100 percent Transmission employee in 2018, and may, in prior
years, have provided some services to other companies or been employed by another
ATCO company. However, the converse is also true, whereby ATCO Electric -- an
ATCO Electric 100 percent employee severance is allocated fully to ATCO Electric. If,
for example, there was an employee who transferred from ATCO Electric Transmission
to ATCO Power and was severed from ATCO Power, being a non-regulated, non-ATCO
company, that entity at the time of termination would bear the costs of the severance. If
you'll give me a second, I'd just like to reference one other exhibit.60
87. Ms. Goode later confirmed that the date upon which the Oracle HR system recognized
AET as its own reporting entity was January 2014 and not January 2013. For position number 7
using 2014 as the starting point, AET still allocated 1.1 years out of four years (2014-2017), or
approximately 28 per cent of that position’s time to AET. Yet, based on AET’s 2018 forecast of
that individual’s labour allocation, AET applied to recover 100 per cent of that individual’s
severance payment in this application.
88. In other words, AET severance payments are based on the total time an employee has
worked in any ATCO group company. However, AET allocated the severance payment amounts
included in its revenue requirement forecast based on where the severed position was providing
its services in 2018. The Commission does not find this to be a reasonable allocation of
severance payments.
60 Transcript, Volume 5, page 949 line 14 to page 952 line 25.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 23
89. The Commission finds that the allocation of 100 per cent of severance costs, as
demonstrated by the example for position number 7, is not reasonable because instead of
reflecting that employee’s years of service with AET as a percentage of total years employed
within the ATCO group of companies, it allocates the entire cost of severance to AET regardless
of that employee’s years of service with other ATCO entities. Further, there are enterprise
system limitations that require manual verification of the years an employee spent with AET in
order to determine the correct allocation of years of service between AET and other ATCO
Group companies. In particular, there is no transparency into the time allocated for severed
employees to AET’s transmission function prior to 2014.
90. For the above reasons, AET is directed to provide in its compliance filing a recalculation
of its 2018 severance costs based on the proportion of years of service each severed position
provided to the transmission function, as identified in Exhibit 22742-X0698.
91. In response to Undertaking 53, AET updated, for positions severed or forecast to be
severed, the years of service based on ATCO company information. For positions #134 to #155,
AET did not provide the years of service, as they were forecast to be eliminated during 2019, and
numbers were not available at the close of record. AET forecast $1.5 million of severance for
those positions in 2019. Given the above findings, the Commission approves AET’s 2019
severance costs of $1.5 million on a placeholder basis. The placeholder amount is limited to the
22 positions identified by AET in Undertaking 53 and Undertaking 54 (exhibits 22742-X0697 to
22742-X0700), which are forecast to be eliminated in 2019. The Commission will review the
historical service years within ATCO companies to determine the final approved amounts in
AET’s next GTA.
5.2 Compensation
5.2.1 Labour escalation
92. AET has applied for the following labour inflation rates for the 2018-2019 test period:
Table 12. Labour inflation forecast 2018-2019
2018 2019
Test Year Test Year
(%)
Inflation
Labour – In-scope 2.0 2.0
Labour – Out-of-scope 2.7 3.0
Source: Exhibit 22742-X0001.02, updated application, PDF page 20.
93. The Commission will address the in-scope and the out-of-scope inflation rates separately
in the subsections below.
5.2.1.1 In-scope escalation
94. AET explained that the in-scope inflation increase reflects the overall average increases
for employees belonging to the Canadian Energy Workers Association (CEWA), as well as
increases for the remaining employees not in CEWA. AET explained that its current agreement
with CEWA was ratified on July 12, 2017 and covers the years 2017 and 2018. The agreement
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 24
called for inflation increases of 1.75 per cent in 2017 and 2.00 per cent in 2018. AET applied for
in-scope labour inflation increases of 2.0 per cent in each of 2018 and 2019.61
95. In response to a Commission IR,62 Bema recommended that the Commission deny AET’s
2017 actual in-scope labour escalation of 1.75 per cent and direct AET to adjust base salaries to
use the approved zero per cent in-scope labour escalation rate. Bema also recommended that the
Commission deny AET’s applied for in-scope labour escalation rates in 2018 and 2019 and
approve zero per cent for both years. The combined effect of removing the inflationary increases
would be a reduction in salaries of 5.86 per cent. As further support for its recommendations,
Bema referred to the Alberta government’s November 30, 2018 Economic Outlook and to the
price differential between West Texas Intermediate (WTI) and Western Canadian Select (WCS)
to suggest that:
Alberta is entering a period of significant uncertainty. To the extent the oil price discount
remains high and WTI remains low, there may very well be additional layoffs in Alberta.
Certainly, absent significant changes to the supply constraints in Alberta for oil and gas,
it is highly unlikely that significant growth will occur in Alberta in the forecast test
period.63
96. Bema stated that AET had not accounted for the impact of the price differential or the
recent downturn in economic forecasts.64
97. AET opposed Bema’s recommendations for in-scope compensation in 2018 and 2019. In
rebuttal evidence, AET highlighted that the collective agreement with CEWA contains
provisions for contract arbitration. AET explained that contract arbitration is final and binding
upon the parties, making it unworkable for AET to negotiate a zero per cent wage increase in
2018 or 2019, even in a weakened Alberta economy. AET submitted that its applied-for, in-
scope inflation rates of 2.0 per cent for each of 2018 and 2019, are representative of economic
conditions in Alberta and that these percentages factor in market comparators. AET provided the
following table depicting recent wage settlements for Alberta utilities:65
Table 13. Recent wage settlements in the Alberta utility market (per cent increase)
Company Union 2013 2014 2015 2016 2017 2018 2019
ATCO Gas NGEA 3.5 3.5 3.5 3.75 Note 1 1.75
ATCO Pipelines NGEA 3.0 3.5 3.5 2.75 Note 1 2
ATCO Electric CEWA 3.5 3.5 3.5 3.75 1.75 2.0
ATCO Electric Yukon CEWA 3.5 3.5 3.5 3.25 1.75 2.0 2.0
Northland (NWT) CEWA 3.5 3.5 3.5 2.5 1.5 2.0
Northland (YK) CEWA 3.5 3.5 3.0 3.0 1.75 2.0 2.0
AltaGas CEP 1947 2.0 3.0 3.0 2.0 2.0 2.0
AltaLink UUWA 3.5 3.5 4.0 2.5 2.5 2.35 3.0
AltaLink IBEW 3.5 3.5 4.0 3.5 2.35 2.35
Capital Power IBEW 3.75 3.5 3.5 2.5 2.0 2.0
61 Exhibit 22742-X0001.02, updated application, paragraphs 45-46. 62 Exhibit 22742-X0612, CCA-AUC-2018DEC19-009. 63 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 424. 64 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 424. 65 Exhibit 22742-X0618, AET rebuttal evidence, pages 182-183.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 25
Company Union 2013 2014 2015 2016 2017 2018 2019
Capital Power CEP 1947 3.75 3.5 3.75 3.75 2.0 2.0
Capital Power CSU 3.75 3.5 2.5 2.0 2.0 2.5
Medicine Hat Power IBEW 3.5 3.5 3.5 3.0 0.0 2.0 2.0
ENMAX CUPE38 3.0 3.5 3.5 3.5 1.25 2.25 3
ENMAX IBEW 3.0 4.0 3.5 3.5 3.75
EPCOR IBEW 3.75 3.5 3.5 2.5 2.5 2.35
EPCOR CSU52 3.5 3.5 3.0 2.25 2.15 2.35 2.75
FortisAlberta UUWA 4.0 3.25 3.5 3.5 3.75 1.5 2.25
Milner Power UUWA 3.0 3.5 3.75 4.0
TransAlta IBEW254 3.75 3.5 3.5 3.75 0 1.5 1.75
TransAlta UUWA100 3 3 3.0 0.0 0.0 0.0
Average including ATCO 3.4 3.5 3.4 3.0 1.8 1.9 2.3
Average excluding ATCO 3.4 3.5 3.4 2.8 1.9 1.9 2.5
Note 1: For 2017 ATCO Gas and ATCO Pipelines settlements included a lump sum payment.
98. AET argued that the 2.0 per cent in-scope labour inflation rate for 2018 is not a forecast
and is not subject to uncertainty. The collective agreement with CEWA was ratified in 2016 and
resulted in an increase for 2018 of 2.0 per cent. Further, the agreed upon 2.0 per cent labour
inflation rate is in line with the industry comparator average.66
Commission findings
99. The Commission accepts the 2.0 per cent in-scope labour inflation rate for 2018 that was
negotiated and reflected in the agreement with CEWA. AET confirmed in argument that “The
2.0% In-Scope Labour inflation for 2018 is not a forecast and is not subject to uncertainty.”67
In addition, the Commission finds that the evidence supports this amount because it is similar to
inflation rates for other Alberta utilities in 2018, as shown in Table 13.
100. Based on a review of the 2019 comparative data in Table 13, which is somewhat less
comprehensive than that for 2018, the Commission finds that a 2.0 per cent increase for in-scope
employees is consistent with the 2019 wage settlements of Alberta utilities and is reasonable in
light of the current economic outlook. For these reasons, the Commission approves AET’s
2.0 per cent in-scope labour inflation rate, as filed, for each of 2018 and 2019.
5.2.1.2 Out-of-scope escalation
101. In its application, AET forecast a 2.7 per cent labour inflation rate in 2018, and 3.0 per
cent labour inflation rate in 2019, for out-of-scope employees. AET stated that its requested
increases were consistent with salary increases projected by Mercer Canada Ltd. (Mercer).
Mercer’s 2017 “Total Compensation Review” was included in the application.68 An August 2018
update was included as Attachment 1.4(a) of the updated application filed by AET on
September 4, 2018.
66 Exhibit 22742-X0725, AET final argument, paragraph 77. 67 Exhibit 22742-X0725, AET final argument, paragraph 77. 68 Exhibit 22742-X0001.02, updated application, Attachment 1.4.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 26
102. In AET’s proposed labour escalators for out-of-scope employees, AET also took into
consideration incremental adjustments and promotional increases that are related to employee
progression and compression.69
103. AET submitted that Mercer’s total compensation review analysis demonstrates that
AET’s out-of-scope employees’ compensation level is 10 per cent below the market midpoint.
AET stated that its objective was to be at the mid-point of the market.70
104. In argument, the CCA adopted the evidence of Bema, and asserted that the Commission
should approve an out-of-scope compensation escalation rate of 2.25 per cent in 2018 and zero
per cent in 2019. The CCA insisted that the Commission prorate AET’s approved salary inflation
amounts to account for the fact that AET’s labour inflation increases are not effective January 1
of any particular year. The CCA summarized its arguments for a lower compensation escalation
rate, some of which are broadly applicable to total compensation, as follows:71
AET’s existing salaries are entirely reasonable and sufficient to compensate AET’s
employees during the test period. In fact, AET’s employees may be over compensated
from the perspective of base salary;
AET’s 2018 workforce reductions further limit the need for salary increases in the test
period;
AET’s bias towards paying base salary increases but not paying VPP has resulted in
over compensation of base salary and is inappropriate;
AET’s salary expectations remain unadjusted despite subdued economic growth in
Alberta both in 2018 and 2019; and
The ATCO group of companies' CEO has overall discretion to determine the pay
components for employees including out-of-scope escalation and thus there is a risk
that any amounts approved beyond the already approved 2018 salary increases will
not actually be implemented.72
105. The CCA also submitted that weight should not be afforded to the Mercer report as
support for AET’s proposed out-of-scope labour increases because it relies on outdated
information that is also based on arbitrarily determined parameters and is inconsistent from year-
to-year. The first study was completed in March 2015 and filed in AET’s 2015-2017 GTA and
the second study was completed in February 2017 and filed in the original application. The CCA
asserted that the data points from these two studies are very outdated and cannot be
representative of salary expectations in 2018 and 2019.73 Further, the companies considered to be
AET peer groups in the 2014 Mercer Total Compensation Study (MTCS) differed from those in
the 2018 MTCS update. The CCA argued that the difference in peer groups is arbitrary and does
not support reliance on the information between the two total compensation studies.74
69 Exhibit 22742-X0001.02, updated application, paragraph 47. 70 Exhibit 22742-X0001.02, updated application, paragraph 48. 71 Exhibit 22742-X0722, CCA final argument, paragraphs 442-443. 72 Exhibit 22742-X0722, CCA final argument, paragraph 442. 73 Exhibit 22742-X0722, CCA final argument, paragraphs 409-410. 74 Exhibit 22742-X0722, CCA final argument, paragraph 425.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 27
106. As explained by AET in its argument, Mercer provides analyses of salary escalation
projections provided by companies with jobs similar to those of AET's out-of-scope employees.
These analyses also reflect the current and near term economic environment in Alberta. AET
provided the following explanations of the two components of the Mercer study – salary
escalation projections and total remuneration review:
2018-2019 Salary Escalation Projections
… Mercer’s 2018-2019 Salary Escalation Projections provides base salary actual and
projected increases information for 2018 and 2019. Mercer initially provided base salary
increase projection information in the original Application, which was updated in the
Application Update. In his Expert Testimony, Mr. Yung provided an update to the 2018-
2019 Salary Escalation Projections. The updated 2018-2019 Salary Escalation Projections
demonstrate that AET's peer group 2018 actual salary increase budget was 2.8% at the
median. This information was not subject to debate and reflects actual 2018 data. For
comparison, AET's actual out-of-scope inflation adjustment in 2018 was 2.65%, which is
lower than the median of 2.8% for AET's peers. Furthermore, Mercer's updated analyses,
which should be considered very reliable given it was updated in December 2018,
demonstrates a median 2019 projected salary increase budget of 2.7% for AET's Peer
Group.75
Total Remuneration Review
… the Mercer 2017 Total Remuneration Review benchmarks AET’s out-of-scope
employees' total compensation against AET's peers in the marketplace. The Total
Remuneration Review provides an analysis on AET's competitive position on total
remuneration. The Total Remuneration Review is based on using target compensation, as
opposed to actual compensation for purposes of assessing incentive compensation. Actual
compensation may vary depending on factors such as overall business results and
individual employee performance, and therefore, would provide a less accurate view of
the intended compensation level for employee positions.76 [footnotes removed]
107. AET stated that Mercer’s analysis, based on survey data from April 2018, shows that
AET’s compensation level is, on average:
(a) seven per cent below P50 on total remuneration;
(b) one per cent below P50 on base salary; and
(c) two per cent below P50 on target total cash (includes base salary and target short-
term incentives).77
108. AET disputed the CCA’s argument on the lack of comparators that have participated in
Mercer’s 2015 peer group study and in its current 2018 study. AET provided the following
argument:
If one were to rely on the “old peer group” from 2015 to assess AET’s competitiveness,
as suggested by Bema, all that would be shown is how AET compares to the companies
that it competed with in the marketplace in 2015. It would not be indicative of the
companies that AET currently competes with for employee talent. Of course, there will
be some overlap year-over-year with respect to AET's competitors for employee talent.
However, for the competitive benchmarking to be a valid and reliable indicator of AET’s
75 Exhibit 22742-X0725, AET final argument, paragraph 60. 76 Exhibit 22742-X0725, AET final argument, paragraph 61. 77 Exhibit 22742-X0725, AET final argument, paragraph 62.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 28
current positioning, the peer group must be appropriately updated to reflect changes in
AET’s peers based on current information. Mercer has explained the changes made to the
AET peer group, including the reasons for adding and removing specific organizations. In
this regard, the Mercer updated AET peer group includes a greater percentage of Utility
organizations, as compared to the 2015 peer group.78 [footnotes removed]
109. AET re-confirmed that its ability to rely on other internal factors to gauge its market
competitiveness is limited79 and, therefore, AET must rely on industry compensation
professionals such as Mercer to maintain its competitiveness.80
110. In reply argument, the UCA observed that while AET was requesting 2.7 per cent and 3.0
per cent for out-of-scope labour inflation for 2018, and 2019, respectively, AET’s witness, Mr.
Goguen, stated that actual inflation for out-of-scope labour in 2018 was 2.65 per cent.81 The
UCA advocated that the best available information should be used for the 2018 out-of-scope
inflation rate, which is 2.65 per cent.82
111. AET stated that data collected to calculate the median projected salary increase of 2.7 per
cent for AET’s peer group, was collected in the fourth quarter of 2018 by Mercer. AET asserted
that its peer companies would have taken into consideration any "economic uncertainty" in
determining their projected salary increase budgets for 2019.83
112. The UCA submitted that for future GTAs, the Commission should exclude the
incremental costs of promotions from any future estimates of budgeted salary increases. The
UCA’s rationale was “that although a promoted person is likely earning more money than he or
she did in their previous position, they may well be earning less than the person who was in the
same job before them. The salary of the person they are replacing would already be accounted
for in the budget, and therefore there is no incremental cost stemming from the promotion.”84
Commission findings
113. AET witness, Mr. Goguen, confirmed that the Mercer study is the only empirical
evidence AET has advanced to justify its proposed out-of-scope labour inflation.85 In an
exchange with CCA counsel, Mr. Yung of Mercer acknowledged that its studies are limited to
those companies that choose to pay to participate in the MTCS:
Q. Thank you. And are you able to explain why some companies respond to the survey in
one year and then do not respond in other years?
A. MR. YUNG: I can give you a few more likely reasons anyways. I can't say these are
the only reasons that apply, but it could include things like, first, the company might not
be around anymore. For example, I can highlight that there are a few companies within
the 17 group, they just got taken out by another company in terms of corporate
transaction. They don't exist, so they can't really participate. And second, it could be
78 Exhibit 22742-X0725, AET final argument, paragraph 68. 79 Exhibit 22742-X0657, Undertaking 13. 80 Exhibit 22742-X0725, AET final argument, paragraph 72. 81 Transcript, Volume 1, page 150, lines 2-5. 82 Exhibit 22742-X0729, UCA reply argument, paragraphs 3-6. 83 Exhibit 22742-X0727, AET reply argument, paragraph 42. 84 Exhibit 22742-X0729, UCA reply argument, paragraph 7. 85 Transcript, Volume 2, page 309 lines 1 to line 17.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 29
because they have -- they're trying to save survey participation fees, and, as a result, they
might not choose to participate. So there are many possible reasons. But the one thing I
do want to highlight is the sample we used in the ATCO Electric studies have been
representative in both cases. So there shouldn't be any questioning of how reliable the
sample is 86
114. Mr. Yung, using “ATCO Electric’s Competitive Positioning” table in its application,87
explained how P50 was calculated:
Q. Yes. I think we were here not that long ago. And I was trying to understand your
discussion with Ms. Sabo about the median -- averages of medians. So the example you
used was business support services, and it says, number of ATCO matches in the next
column. And am I correct in saying that by that, we mean number of ATCO matches of
benchmarks? So there's eight companies that we can draw data from for this row?
A. MR. YUNG: So perhaps I will use that number, the eight as the example. So there are
eight ATCO Electric Transmission employees where we're able to find benchmark
position -- benchmark data within the peer group, and we compiled the median 25, 70
percentile, so on and so forth. So there are eight AET jobs included in that average
calculation for that level.
Q. And you took their -- so where does the median come from?
A. MR. YUNG: So the median would be -- think of it as -- because there are eight jobs,
there would be a median for each of the eight benchmark positions –
Q. Mm-hm.
A. MR. YUNG: -- from within the peer group. So there are eight medians. And the
$71,000 at the P50 column –
Q. Is the average.
A. MR. YUNG: -- would be the average of those eight medians.88
115. Mr. Goguen explained how AET uses the Mercer survey information to determine its out-
of-scope employees' salary adjustments.
Q. Thank you. So given that response, Mr. Goguen or Mr. Palladino, how does ATCO
Electric weigh the survey results in determining salaries for, say, that same level,
business support services, you know, with salaries targeted at $71,000 at P50?
A. MR. GOGUEN: So back to our desire to reach the P50. When we are reviewing base
pay adjustments annually, the data that we have is actually obviously each individual
within groups, et cetera. And that includes where they are at relative to the P50 for that
said position, be it business support, technical, or otherwise. We talked about earlier that
we have a budget that we assign accordingly, and we, depending on the role,
performance, et cetera, would adjust accordingly, with the aim, ultimately, to try to get
everybody close to that P50, realizing there's a delta here that's significant for the eight
86 Transcript, Volume 1, page 118 line 13 to page 119 line 6. 87 Exhibit 22742-X0001.02, updated application, PDF page 55. 88 Transcript, Volume 2, page 301 line 21 to page 310 line 24.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 30
positions that we've talked about. But that's how we would look at it and adjust
accordingly. And ultimately we'll have individuals that will be above P50 and some
below, again, depending on tenure in the role, experience, et cetera, et cetera. [emphasis
added]
116. Mr. Goguen confirmed that in determining salaries AET uses the MCTS and Total
Compensation Review data and considers AET’s budget and individual performance and roles.
AET has employees who are above or below P50, based on these items.89 The Commission
considers that while the MCTS and the Total Compensation Review provide information on
whether AET’s compensation is competitive at the 50th percentile, AET still retains discretion on
salary increases and labour inflation given that it also considers its budget and individual
performance.
117. The Commission also agrees with the recent findings in ATCO Pipelines’ 2019-2020
General Rate Application in Decision 23793-D01-2019, where that Commission panel found:
The Commission has reviewed the Mercer report and finds that it is only one factor in
assessing the level of required wage increases. The Mercer report does not supplant
management judgement and other economic factors that must be considered before
determining the salary level required to attract and retain talent. The Commission
considers that it is very difficult for any study to incorporate intangible factors such as the
economic climate in Alberta, risk of job loss, labour productivity and the unemployment
rate.
Target total compensation includes items such as variable pay, perquisites, long-term
incentive pay, pension and savings, and health and group benefits. Although some of
these items are not included for recovery in ATCO Pipelines’ revenue requirement, the
Commission considers that it is incumbent upon ATCO Pipelines’ management to review
whether these forms of compensation are required to retain and attract employees. ATCO
Pipelines can and should vary these items to meet its objectives with respect to total
compensation. The target total compensation data from Mercer is only one measure that
the Commission uses in approving out of-scope labour forecasts.90 [footnote removed]
118. AET confirmed that it awarded 2.65 per cent salary inflation to its out-of-scope
employees91 in 2018. The Commission finds that this actual 2018 amount is reasonable given that
it is based on the most up-to-date information on the record for 2018. The Commission approves
a 2.65 per cent inflation increase, and determines that it is reasonable to approve this as final for
2018.
119. AET submitted that its in-scope inflation rate forecast of 2.0 per cent for 2019 was
representative of economic conditions in Alberta and that this percentage takes into account
market comparators.92 The Commission is not persuaded that the current Alberta economic
climate supports an out-of-scope labour escalation rate of 3.0 per cent in 2019. Rather, the
Commission finds that an out-of-scope labour escalation rate of 2.0 per cent for 2019 better
89 Transcript, Volume 2, page 271 line 12 to page 272 line 4. 90 Decision 23793-D01-2019, ATCO Pipelines 2019-2020 General Rate Application, Proceeding 23793, June 25,
2019, paragraphs 221-222. 91 Exhibit 22742-X0727, AET reply argument, paragraph 49. 92 Exhibit 22742-X0618, AET rebuttal evidence, pages 182-183.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 31
reflects current labour inflation rates, similar to what the Commission approved for AET’s in-
scope inflation rate.
120. For the above reasons, AET is directed to incorporate out-of-scope inflation rates of 2.65
per cent for 2018 and 2.0 per cent for 2019 in its compliance filing to this decision.
121. In its submissions, the CCA asserted that AET’s labour forecasts do not appear to prorate
the out-of-scope inflation, and recommended that the Commission direct AET to prorate the
annual salary inflation by three-quarters.93 At the oral hearing, AET commented that:
A. [the] latter part of the first quarter is usually when we see our salary adjustments for
out-of-scope individuals, and usually they take effect at that point in time. He added that
the labour forecasts assume an April 1st effective day for wage increases.94
…
A. MR. GOGUEN: Roughly April 1st, yeah.
Q. Okay. And did your labour forecasts assume an April 1st effective date for wage
increases for the out of scope?
A. MR. GOGUEN: Subject to check, yes, I believe our forecasts would take that into
account.95
122. For confirmation purposes, AET is directed to demonstrate in its compliance filing, with
calculations, that it has prorated its out-of-scope labour inflation to reflect increases awarded on
April 1 of each year.
5.2.2 Variable pay program
123. In this section, the Commission makes three broad findings, two with respect to the
mechanics of the Variable pay program reserve account and one addressing the associated
forecast.
5.2.2.1 Reserve for VPP
124. AET is seeking the continuation of the VPP reserve account. However, it has requested
that the mechanics of the reserve account be altered to be symmetrical in nature. The VPP
reserve mechanics are designed to work in the following manner, as stated in Decision 20272-
D01-2016:
The Commission directs ATCO Electric to set up a VPP reserve account in its no cost
capital schedules in Section 29 of ATCO Electric’s revenue requirement schedules.
Regarding the mechanics of the reserve account, ATCO Electric will not be eligible to
recover costs in excess of the approved VPP forecast amounts for a given year, and will
not be permitted to carry over unused VPP funds for use in future years of the current
application. Approved, but unused, VPP amounts in any given GTA test period will be
added to the VPP reserve account for the next GTA test period. In the Commission’s
view, this approach will address the legitimate need to maintain funding for ATCO
Electric’s VPP in support of its recruitment, retention and operational performance goals,
93 Exhibit 22742-X0722, CCA final argument, paragraph 438. 94 Transcript, Volume 1, page 147 line 21 to page 148 line 15. 95 Transcript, Volume 1, page 148 lines 10-15.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 32
while insuring that any incentive to withhold VPP amounts otherwise payable to eligible
employees based on their performance, in order to increase the utility’s retained earnings,
is removed.96
125. AET proposed that approved, but unused, VPP amounts be carried forward and added to
the next test year’s VPP reserve account. Additionally, AET proposed that any VPP payments
made in excess of the approved forecast for any given test year be recovered through the reserve
in a future test year. AET suggested that the symmetrical treatment would allow AET to react to
changes in the marketplace that occur during the test period.97 AET claimed that the VPP reserve
account ensures that customers are not harmed by the inclusion of the VPP amounts requested by
AET in its revenue requirement.98
126. The VPP reserve account balance was provided by AET, and is reproduced in the table
below:
Table 14. VPP reserve account balances
Cross-reference 2015
Actual 2016
Actual 2017
Actual
Test Period
2018 2019
Opening balance - - 4.6 5.8 8.2
Approved / Applied-for expenditure
Sch 25-11, Line 19 - 4.6 5.0 5.3 5.4
Reserve adjustment - -
Actual / Forecast expenditure Sch 25-11, Line 19 - - (3.8) (2.9) (5.3)
Closing balance - 4.6 5.8 8.2 8.3
Mid-year Balance S. 29-1 - 2.3 5.2 7.0 8.2
Source: Exhibit 22742-X0002.04, MFR Schedule 29-5.
127. In its evidence, Bema recommended that the Commission deny AET’s requested change
to the reserve account mechanics and instead that the Commission maintain the existing reserve
account for the 2018-2019 test period.99 Bema provided a number of reasons in support of
continuing the existing reserve account mechanics, the three primary reasons being:
AET’s requested “symmetrical” treatment in the reserve account would not be
symmetrical from the perspective of ratepayers, as ratepayers already paid the full VPP in
past years and now AET is requesting that ratepayers be fully exposed if AET decided to
pay out more VPP than forecast in an attempt to retain its employees.100
96 Decision 20272-D01-2016, paragraph 192. 97 Exhibit 22742-X0001.02, AET updated application, paragraph 603. 98 Exhibit 22742-X0727, AET reply argument, paragraph 303. 99 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 91. 100 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 74.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 33
In Bema’s opinion, it is not in the public interest for ratepayers to reimburse AET’s
shareholders for a decision to compensate employees above the 100 per cent target
payout.101
AET continues to not pay 100 per cent of the approved VPP. Bema noted that in 2016,
AET paid 82 per cent of its approved VPP amount, and in 2017, AET paid only 58 per
cent of the approved VPP amount.102
128. Bema recommended that the Commission direct AET to refund the reserve balances in
2018 and 2019, to bring the closing balance of the reserve account to zero dollars on a forecast
basis in each year.103
129. In its rebuttal evidence, AET rejected Bema’s recommendation to make the closing
reserve account balance zero dollars on a forecast basis in each year. AET pointed out that
Bema’s recommendation ignores the payment lag that occurs as a result of VPP payments
“occurring in the year following the year in which they are awarded (i.e., VPP awarded for 2017
performance is paid in 2018).”104 AET added that the reserve account adjustments advanced by
Bema are not required and are flawed. According to AET, the reserve account is operating as
intended and customers are receiving a benefit tied to the accumulated positive reserve account
balance.105
130. The CCA submitted that it seeks to preserve the status quo in terms of how the reserve
account works, given that nothing has changed with AET’s VPP to warrant a change to the
reserve account mechanics. The CCA adopted, and requested that the Commission approve,
Bema’s recommendations provided in evidence, because:
Other Alberta utilities are not permitted to recover costs above 100 per cent of the
approved target payout from ratepayers, as this excess payout has been properly
considered to be a shareholder cost by the Commission;
AET itself exacerbated the risk of employees leaving the company because of the non-
payment of VPP to employees, which it then refuted in the oral hearing. It is thus AET,
not ratepayers, that should bear the costs of paying VPP above the target payout of 100
per cent. Additionally, given that the past non-payment of VPP resulted in improved
earnings for AET’s shareholders, it would be inappropriate for ratepayers to compensate
AET’s shareholders now if they are truly required to pay VPP above the 100 per cent
target payout;
ATCO Ltd.’s CEO retains 100 per cent discretion and veto power on the payment of
VPP;
AET’s VPP, despite the implementation of a reserve account in the 2015- 2017 test
period, still does not pay a target level of VPP to its employees, and further the VPP
does not clearly align with ratepayer interests; and
101 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 76. 102 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 92. 103 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 97. 104 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 14 105 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 14.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 34
AET’s payment history demonstrates a consistent payment of VPP well below the target level.
Therefore, modifying the reserve account to allow for symmetrical treatment and, thus, payments
above 100 per cent target would not be reasonable.106
131. The CCA noted that the VPP reserve account is accumulating a balance that will not be
refunded to ratepayers based on the current VPP reserve mechanics. The CCA recommended that
the Commission deny AET’s request for symmetrical treatment of the VPP reserve account and
require AET to refund the balance that has accumulated in the reserve account.
132. AET argued that its request to be able to carry approved, but unused, VPP amounts
forward in any year is fair and reasonable and does not operate to the disadvantage of customers.
AET submitted, “Rather, customers are fully protected by the existence of the Reserve and the
fact that AET must still demonstrate the reasonableness of the amounts incurred.”107
Commission findings
133. In Decision 20272-D01-2016, the Commission also found:
It remains unclear to the Commission, based on the above exchange, whether ATCO
Electric will pay VPP amounts in 2016 and 2017. Mr. DeChamplain confirmed that all
decisions with respect to VPP payment amounts at ATCO Electric “are subject to [the
ATCO Ltd.] CEO’s approval” based on economic conditions, apparently even if all of the
utility’s internal performance criteria are otherwise met. This suggests to the Commission
that, were it to approve ATCO Electric’s forecast expenditures for VPP in 2016 and
2017, there is no assurance that VPP payments will actually be made even if employees
achieve or exceed all their performance targets. The result is that, unlike other forecast
expenditures which may or may not be incurred because of external factors outside of
ATCO Electric’s control, VPP amounts, which are fully within ATCO Electric’s control
to pay, can be withheld from employees to the benefit of shareholders (and the cost of
ratepayers) based on directions received from the CEO of ATCO Electric’s ultimate
parent company.108
134. In this proceeding, both AET and the CCA agree that the VPP reserve account is
operating as intended. The Commission agrees. Moreover, the reasons the reserve account was
approved in Decision 20272-D01-2016 remain valid, and the structure of the VPP has not
materially changed since the inception of the VPP reserve account.
135. In directing AET to set up the VPP reserve account in the last GTA, the Commission
provided explicit directions on the mechanics of the VPP reserve account. In Decision 20272-
D01-2016, the Commission gave the following direction for AET to establish an asymmetrical
VPP reserve account:
The Commission directs ATCO Electric to set up a VPP reserve account in its no cost
capital schedules in Section 29 of ATCO Electric’s revenue requirement schedules.
Regarding the mechanics of the reserve account, ATCO Electric will not be eligible to
recover costs in excess of the approved VPP forecast amounts for a given year, and will
not be permitted to carry over unused VPP funds for use in future years of the current
application. Approved, but unused, VPP amounts in any given GTA test period will be
106 Exhibit 22742-X0722, CCA final argument, paragraph 40. 107 Exhibit 22742-X0725, AET final argument, paragraph 49. 108 Decision 20272-D01-2016, paragraph 189.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 35
added to the VPP reserve account for the next GTA test period. In the Commission’s
view, this approach will address the legitimate need to maintain funding for ATCO
Electric’s VPP in support of its recruitment, retention and operational performance goals,
while insuring that any incentive to withhold VPP amounts otherwise payable to eligible
employees based on their performance, in order to increase the utility’s retained earnings,
is removed.109
136. These VPP reserve account mechanics are deliberately asymmetrical. They are not
intended to operate in the same manner as the VPP deferral account the Commission removed in
Decision 2013-358. To grant AET’s request would, in effect, allow the VPP reserve account to
act as a deferral account. The Commission previously explained in Decision 2013-358,110 why it
removed deferral account treatment for AET’s VPP and these concerns have not changed.
137. For these reasons, the Commission denies AET’s request to amend the mechanics of the
VPP reserve account to be symmetrical in nature.
5.2.2.2 Variable pay forecast
138. AET has a VPP for its out-of-scope employees as part of its total compensation package.
Over time, AET has developed and refined its VPP based on market requirements, and on AET’s
overall corporate objectives and corporate metrics. In the current application, AET applied for
VPP in the amounts identified in the table below:
Table 15. Variable pay program costs
Description
2015 2016 2017 Test period
Actuals Actuals Actuals 2018 2019
($ million)
Transmission direct O&M - 566 - 1.0 0.5 0.8 0.8
Direct assigned capital - 1.1 1.0 2.4 2.5
Non-direct assigned capital - 1.3 1.2 1.4 1.4
Transmission 3.3 2.6 4.5 4.6
Isolated generation O&M - 557 - 0.0 0.0 0.0 0.0
Isolated generation - 0.0 0.0 0.0 0.0
Corporate O&M - 920 - 0.5 0.3 0.7 0.8
Corporate - 0.5 0.3 0.7 0.8
Total 3.8 2.9 5.3 5.4
Summary
Transmission O&M VPP - 1.5 0.8 1.5 1.6
Transmission direct assigned capital VPP - 1.1 1.0 2.4 2.5
Transmission non-direct assigned capital VPP - 1.3 1.2 1.4 1.4
Total transmission VPP - 3.8 2.9 5.3 5.4
Source: Exhibit 22742-X0002.04, MFR Schedule 25-11.
109 Decision 20272-D01-2016, paragraph 192. 110 Decision 2013-358, paragraphs 72-73.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 36
139. Bema submitted that a variable pay compensation program should align payment with the
interests of ratepayers. Bema asserted that because ratepayers pay the forecast variable
compensation on AET’s behalf, through their rates, AET employees should be incented by way
of the compensation they receive to act in ratepayers’ interests. Bema stated that AET did not
provide enough information to allow Bema to adequately assess whether ratepayers' interests are
being served by AET’s VPP.111
140. Bema suggested that AET should amend its VPP to remove veto power from ATCO
Ltd.’s CEO, and recommended that AET be directed to re-design its VPP using AltaLink’s short-
term incentive plan program as a model. Bema proposed that AET’s VPP should be awarded
based on the following:112
30 per cent weighting to reliability,
20 per cent weighting to safety,
30 per cent weighting to economic/operational savings, and
20 per cent weighting to individual goals.
141. AET, in its rebuttal evidence, disputed Bema’s assertion that AET’s VPP is not aligned
with ratepayer interests, stating:
… To provide additional clarity, all AET employees have a duty of care to the safe,
reliable and economic operation of the interconnected electric system. This is factored
into each individual employee’s performance plan set each year. AET’s VPP is an
individual-based structured plan as opposed to a prescribed formulaic plan that is broad
in nature. Bema’s notion that the VPP program does not meet the needs of customers and
employees is ill-informed and completely incorrect. All employee goals - including those
related to safety, reliability, customer, and financial goals - are to the benefit of customers
when they are achieved.113
142. AET explained that “the amount of VPP paid out in a year is driven not only by the
performance of AET’s employees, but also based on the actual economic circumstances that
exists at the time of payout.”114 AET further stated that the ATCO Ltd. CEO is in the best
position to consider economic factors that extend beyond those affecting only AET.
AET indicated that its VPP does not strictly focus on individual performance, but includes other
factors such as a work team’s performance, and organization-wide performance.115
143. In argument, the CCA stated that examples of common goals provided by AET were
selective and subjective, since they could not be quantified.116 The CCA stated:
If a goal is not quantifiable, and instead is open to a great deal of subjectivity, it becomes
almost impossible to determine how that goal may benefit ratepayers. Accordingly, the
CCA submits that based on the limited evidence available on the record of the
111 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraphs 151-152. 112 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraphs 163-165. 113 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 27. 114 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 29. 115 Exhibit 22742-X0618, AET rebuttal evidence, PDF pages 29-30. 116 Exhibit 22742-X0722, CCA final argument, paragraph 165.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 37
proceeding, AET’s goals are not clearly aligned with ratepayer interests and thus it
appears to be inappropriate for ratepayers to fund AET’s VPP.117
144. The CCA recommended that the Commission direct AET, in its next GTA, to undertake a
comprehensive review of its VPP. However, the CCA also suggested that there is sufficient
evidence to “deny AET’s VPP program payments from inclusion in revenue requirement for
2018 and 2019 in their entirety.”118 The CCA stated that if the Commission considers it
appropriate for AET to recover its VPP costs in its revenue requirement, then it agreed with
Bema’s recommendation that AET’s forecast VPP payments be approved at between 60 and 80
per cent of the target payout.119
145. In argument, AET stated:
… the role of the Commission in this proceeding is to determine the reasonableness of
the quantum of its VPP forecast for the Test Years. It is the responsibility of AET’s
management to structure the overall compensation plan for the company and, with
respect, it is not the role of the Commission to dictate the manner in which a company
structures its compensation for its employees. While the CCA urged the Commission to
adopt certain actions in its initially filed Evidence, it acknowledged in its IR responses to
the Commission, that the relief it was requesting was beyond the Commission’s
jurisdiction.120 [footnotes removed]
146. AET added that VPP is an integral part of AET's total compensation package and it
assists in attracting and retaining skilled employees.121 AET explained that its VPP is structured
to take into account the individual objectives which would be set for each employee. The plan
for each individual includes aspects related to the achievement of corporate metrics as well as
individual goals. The payout under the plan can be influenced by prevailing market conditions.
As noted, AET's VPP is not a “formula-based” plan; but rather is designed around the individual
and is set based on interactions between the specific employee and that employee's leader.122
147. In reply argument, the CCA agreed with AET that the Commission should not manage
AET’s VPP, but added that the Commission has the authority to determine whether AET’s own
management of its VPP is reasonable, and to determine the amount of VPP that should be
included in AET’s revenue requirement.123 It submitted that AET’s VPP payout is arbitrary, and
does not incent employee behaviour that provides benefits to ratepayers.124
148. In reply argument, AET explained that VPP is not a guaranteed payment but, rather, one
that is based on a solid plan considering various aspects of company performance, including
operational, management, customer and safety matters. AET indicated that it establishes
appropriate goals on an individual basis for all employees eligible for VPP and appropriately
assesses employees’ performance against such objectives and pays VPP accordingly.125
117 Exhibit 22742-X0722, CCA final argument, paragraph 166. 118 Exhibit 22742-X0722, CCA final argument, paragraph 169. 119 Exhibit 22742-X0722, CCA final argument, paragraph 170. 120 Exhibit 22742-X0725, AET final argument, paragraph 412. 121 Exhibit 22742-X0725, AET final argument, paragraph 409. 122 Exhibit 22742-X0725, AET final argument, paragraph 410. 123 Exhibit 22742-X0726, CCA reply argument, paragraph 237. 124 Exhibit 22742-X0726, CCA reply argument, paragraph 239. 125 Exhibit 22742-X0727, AET reply argument, paragraph 300.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 38
Commission findings
149. In Decision 20272-D01-2016, the Commission approved AET’s VPP forecast and stated,
“ATCO Electric has not exceeded an actual payout of 83 per cent of its forecast VPP amount
since the deferral account treatment was removed. Its VPP forecasts for 2016 and 2017 are
approved at 80 per cent of the eligible employee payout amounts.”126
150. In a Commission IR, AET was asked to provide the number of employees that received
VPP payouts in percentage ranges requested by the Commission, and to provide the average VPP
payout percentage. In response, AET provided the following:127
Table 16. VPP payout percentages and average VPP payout percentage
VPP payout percentage (%)
2013 2014 2015 2016 2017
0 10 278 477 356 42 24
11 20 0 17 0 0 1
21 30 0 37 0 0 10
31 40 1 97 0 9 16
41 50 3 33 0 105 176
51 60 2 27 0 99 33
61 70 6 11 0 22 41
71 80 17 24 0 14 27
81 90 39 11 0 5 4
91 100 73 0 0 30 5
101 110 103 1 0 22 5
111 120 72 0 0 7 0
121 130 44 0 0 1 1
131 140 20 0 0 1 1
141 150 40 0 0 1 0
Total 699 735 356 361 346
Average VPP payout percentage (%)
66 15 0 59 51
151. Based on the response from AET above, the average VPP payout percentage was 55 per
cent128 for 2016 and 2017. AET is responsible for demonstrating the reasonableness of its
forecast amounts and the above table shows that the actual payouts are not consistent with the
historical forecasts prepared by AET. Further, it is unrealistic for the Commission to assume that
all of the employees eligible for VPP will meet 100 per cent of the targets set for them, and that
all FTEs eligible for VPP will be with AET when the VPP payouts are made in the test period.
152. In response to a Commission IR, AET stated that “It is of the view that AUC and
interveners have the opportunity to test the reasonableness of the variable pay payout through
information requests and oral hearing questioning as is the case for all other costs presented in a
126 Decision 20272-D01-2016, paragraph 191. 127 Exhibit 22742-X0417.01, AET-AUC-2018JUN08-039(d). 128 Calculated as: (59% + 51%)/2.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 39
general tariff application.”129 In the hearing, Mr. Palladino explained how corporate and
individual objectives are set as follows:
So the point I was making there, and this is a -- when you have an organization that is this
large and this complex in terms of the various functions that we undertake as an
organization, the objectives that Mr. Goguen has, ideally we'd like to be able to translate
those right down to the field base level and say, “The work that you do here, this is how it
impacts the overall organization.”
Often what we find, though, is that when you get down to the frontline field-based group
of employees where -- their primary function is to ensure the safe, reliable, and economic
delivery of the system. So what does that mean at the end of the day? It means keeping
the lights on, building new extensions, in a safe and quick manner. That's what their
primary focus is.
So when they think, "Well, the work that I do, how does that impact Mr. Goguen’s
overall objectives?" And that's a challenge that we have ultimately, is translating those
overall -- overarching objectives right down to the level of the frontline teams where they
can see how my work impacts the overall organization. And that's often the -- the
difficulties that we have.130
153. AET’s Mr. Goguen explained how the company assesses an individual’s performance:
A. MR. GOGUEN: Well, the assessment of the payout, if I can use that term, which is
done obviously after the year, would be assessed based on the role of the individual. If
they spent part of their year supporting an affiliate and part of the year the utility, we
would essentially get feedback from all parties to understand the performance, if you
will. We would then assess accordingly, calibrate accordingly, and ultimately the payout,
as with any other element, would be allocated appropriately as per the affiliate code and
our allocation methodologies.
Q. So when you're talking about assessing the role of the individual in that answer, I'm
taking that to mean an ATCO Electric Transmission employee. And does ATCO Electric
Transmission, in assessing its employees' performance, utilize a more broad, company-
wide goal rather than a transmission-specific goal?
A. MR. GOGUEN: As I mentioned, they're very individualistic. So each employee would
set up goals at the beginning of the year with their supervisor, their leaders, and
ultimately that's what they are measured on from their performance perspective. And then
as we calibrate and look at the company as a whole, that's when, again, the calibration
happens between the various individuals.
Q. So has AET provided on the record of this proceeding a comprehensive list of all the
employee goals that are included within the forecast VPP for 2018 and 2019?
A. MR. GOGUEN: We have not. That would amount to a tremendous amount of -- each
employee, Mr. Wachowich, as I mentioned, have their own performance plan,
essentially.131
129 Exhibit 22742-X0417.01, AET-AUC-2018JUN08-038(c), PDF pages 145-146. 130 Transcript, Volume 2, page 300, line 22 to page 301, line 19. 131 Transcript, Volume 1, page 29, line 16 to page 31, line 4
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 40
154. Based on this testimony, AET assesses performance and determines VPP payout amounts
on an individualistic basis. The Commission finds it difficult to assess the basis for VPP payouts
without reviewing individual performance against goals prescribed for each individual. In
addition, there is significant discretion in the organization to deny or to significantly reduce VPP
payments based on corporate goals, economic conditions and other criteria. It is therefore
difficult for the Commission to rely with any confidence on AET’s VPP forecasts.
155. There is also a clear trend of AET underpaying VPP relative to the approved VPP
amounts in any given year. Although the mechanics of the VPP account as currently structured
allow AET to carry over unused VPP payment amounts, as pointed out by Bema, “AET
continues to not pay 100 per cent of the approved VPP.”132 Bema noted that in 2016, “AET paid
82 per cent of its approved VPP amount, and in 2017, AET paid only 58 per cent of the approved
VPP amount.”133
156. In light of the evidence and testimony on the record, AET’s VPP forecasts are approved
at 80 per cent of the eligible employee payout amounts. This determination is consistent with the
Commission’s previous VPP approval in Decision 20272-D01-2016. In its compliance filing to
this decision, AET is directed to reflect the Commission’s findings and directions regarding
VPP, including those findings with respect to FTEs and labour inflation rates, which affect
eligible employee payout amounts. In implementing this direction, AET is to take into account
the mechanics of the reserve account detailed in Section 5.2.2.3 Treatment of VPP reserve
account balance below.
5.2.2.3 Treatment of VPP reserve account balance
157. The Commission observes that, to the end of 2018, AET has accumulated $2.9 million134
in the VPP reserve account that relates to VPP amounts that were approved but not paid out in
2016 and 2017. In effect, any additional funding of VPP through revenue requirement in 2018
would further inflate the reserve balance because of the lag between 2018 VPP
obligations/accruals and 2019 VPP payments made in respect thereof. Similarly, the 2019 VPP
funding would inflate the reserve balance because 2019 VPP will not be paid until 2020.
158. In response to a CCA IR, AET confirmed:
AET does not consider that it would be more appropriate to first utilize the rolled forward
opening balance to fund applied for expenditures before seeking additional funding. AET
is of the view that forecast 2018 and 2019 VPP costs relate to these test periods and as
such should be incorporated and collected as part of the applied for tariffs; as opposed to
deferring the collection of these costs. AET would also like to highlight that the
referenced closing balance of $8.3 million for 2019 does not consider the 2019 VPP
payment, which due to timing would be paid in 2020, and be applied against the opening
2020 reserve balance. Therefore, due to timing the closing 2019 reserve balance is higher
than it otherwise would be.135
159. In its evidence, Bema recommended that the Commission direct AET to bring the closing
balance of the VPP reserve account to zero dollars on a forecast basis in each year. Bema
132 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 92. 133 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 92. 134 Calculated as: (4.6 – 3.8) + (5.0 – 2.9). 135 Exhibit 22742-X0572.02, AET-CCA-2018OCT05-014, PDF page 27
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 41
suggested that the required adjustments be reflected as a reduction to AET’s applied for
operating costs.136 The Commission notes that even if the reserve account was drawn down to
zero, the reserve balance would begin to accumulate again because of the lag in VPP payouts
relative to approved VPP amounts for any given year.
160. The Commission has denied AET’s request to amend the mechanics of the VPP reserve
account to be symmetrical in nature, as detailed above. The Commission also agrees with the
CCA that the VPP reserve account balance should be targeted to be as close to zero by the end of
the GTA test periods as possible. The Commission notes in this regard, that there is no benefit to
AET shareholders, ratepayers or employees in maintaining a positive balance in the VPP reserve
account as any positive balance is designated as zero cost capital. On the other hand, requiring
ratepayers to provide VPP funds projected to be spent, but that may not be spent not only for a
period of one or more years after those VPP funds are collected, but for one or more successive
test periods, is prima facie harmful to customers. In its compliance filing AET is directed to
provide options on how it could best operate the VPP reserve account to avoid an increasing
accumulated balance i.e. the VPP reserve account balance should trend as close to zero as
possible.
5.3 Other escalators
5.3.1 Contractor and other inflation
161. In its application, AET provided a summary of key assumptions with respect to its
forecasting methodology. From that information, the Commission has prepared the following
table which details the inflation rates forecast for labour, contractors and other categories of
costs:
Table 17. Forecast inflation rates – labour, contractors and other 2018-2019
2018 Forecast 2019 Forecast
(%)
Labour – in scope 2.0 2.0
Labour – out of scope 2.7 3.0
Contractors 2.2 2.3
Other 2.1 2.1
Source: Extracted from Exhibit 22742-X0001.02, Table 1.9 Key Assumptions, PDF page 20.
162. Evidence filed by Bema, on behalf of the CCA, provided a review of the economic
environment in Alberta concluding that there was a relationship, albeit a simplistic one, between
the forecast of West Texas Intermediate (WTI) and the impact that WTI forecast should have on
AET’s applied-for inflation rates. Bema stated that the Alberta economy has changed since the
filing of AET’s application. Bema supported this assertion by providing opinions from the
Alberta Government website indicating that the government itself was anticipating weaker
economic growth for the province.137
163. Given that Alberta has entered a period of significant uncertainty, Bema recommended
that the Commission should consider the discussions it presented on the recent downturn in
economic forecast for 2019 and the fact that AET has not fully incorporated these changes in its
136 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 97. 137 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraphs 407, 410, 422.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 42
forecasts. Bema noted that AET had not revised its forecast inflation rates even after reflecting
the workforce reductions in 2018.138
164. AET did not agree with the assertions made by Bema with respect to the impact of the
uncertainty in Alberta’s economy and the correlation of oil prices to forecast salary adjustments.
5.3.1.1 Contractor inflation rate
165. AET applied for forecast contractor inflation rates of 2.2 per cent and 2.3 per cent for the
years 2018 and 2019, respectively. The contractor inflation rate is calculated using a composite
of other inflation rate, and the inflation rates used for both in- and out-of-scope labour (discussed
in Section 5.2.1 above). The calculation of the applied-for contractor inflation rate was provided
in response to a Commission IR,139 and subsequently updated during the oral hearing by way of
undertaking. In response to the undertaking, AET used the same labour inflation rates as those
applied-for but incorporated more recent Alberta CPI information. This resulted in contractor
inflation rates of 2.4 per cent and 2.2 per cent for the years 2018 and 2019, respectively.140
5.3.1.2 Other inflation rate
166. AET’s forecast inflation rate applicable to all other categories of costs was determined
using an average of Alberta CPI forecast rates from a number of government and financial
institutions as of January 30, 2017,141 and resulted in an applied-for other inflation rate of 2.1 per
cent for both 2018 and 2019.
167. The calculation of the other inflation rate was provided in response to a Commission IR,
and subsequently updated during the oral hearing by way of undertaking. Using more recent
Alberta CPI information, as of January 2019, resulted in other inflation rates of 2.4 per cent and
2.0 per cent for the years 2018 and 2019, respectively.142
168. AET argued that the results included in the undertaking were consistent with the
contractor inflation rates used in AET’s application and submitted that the applied-for contractor
and other inflation rates were reasonable and should be approved as filed.143
169. The CCA had “no extensive reply to AET’s argument in relation to contractor and other
inflation,” other than to note that, should the CCA’s recommendations for reductions to AET’s
forecast labour inflation rates be accepted by the Commission, it would lead to a reduction in
AET’s forecast contractor inflation rates.144
Commission findings
170. Based on the information provided by AET in response to IRs and undertakings, the
Commission finds AET’s applied-for forecast contractor inflation rates of 2.4 per cent for 2018
and 2.2 per cent for 2019 to be reasonable. Based on AET’s explanation in the undertaking,145 the
138 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 407. 139 Exhibit 22742-X0217.01, AET-AUC-2017AUG30-010, PDF pages 5-6. 140 Exhibit 22742-X0675, Undertaking 39, Attachment 1. 141 Exhibit 22742-X0217.01, AET-AUC-2017AUG30-010, PDF pages 5-6. 142 Exhibit 22742-X0675, Undertaking 39, Attachment 1. 143 Exhibit 22742-X0725, PDF pages 30-31. 144 Exhibit 22742-X0726, CCA reply argument, paragraph 31. 145 Exhibit 22742-X0675, Undertaking 39, Attachment 1.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 43
Commission approves other inflation rates of 2.4 per cent for 2018, and 2.0 per cent for 2019.
The forecast contractor inflation rates and other inflation rates are approved, subject to any
applicable findings and directions elsewhere in this decision; specifically, Commission findings
on inflation rates used for both in- and out-of-scope labour.
6 Fuel costs
171. In its application, AET mentioned that it owns and operates eight generation plants
serving isolated communities. It stated that diesel fuel powers six of those plants, while the two
remaining plants serving Jasper are powered by natural gas and diesel (Jasper Palisades) and
hydro (Astoria Hydro). In addition to isolated community plants, AET owns 66 isolated
generating plants for substation and telecommunication power supply backup and four isolated
plants for primary telecommunication power supply. Most of those plants operate on propane
and three operate on diesel. AET provided its actual and forecast fuel costs in Table 4-1 of the
application, as reproduced below:146
Table 18. Actual/Forecast fuel costs
2015 2016 2017 2018 2019
Actuals Actuals Actuals Test period
($ million)
Isolated generation fuel 6.0 5.0 7.2 7.0 7.8
Transmission plants and propane fuel 0.0 0.0 0.0 0.1 0.1
Total 6.0 5.0 7.2 7.1 7.9
Increases/(Decreases) in test period 0.0 (1.0) 2.2 (0.1) 0.8
Impact of price 0.0 (1.2) 0.2 0.2 1.2
Impact of volume 0.0 0.2 0.9 0.9 (0.4)
Impact of carbon levy 0.0 0.0 1.2 0.6 0.0
Source: Exhibit 22742-X0001.02, updated application, Table 4-1, PDF page 141.
172. AET stated that, for the test period, it is pursuing the interconnection of the Garden River
isolated community site to the Alberta electrical grid and is reconfiguring the Indian Cabins and
Fawcett River microgeneration plants into renewable hybrid plants. These projects led to a
decreased diesel fuel consumption forecast for the test period.
173. AET argued that despite overall fuel volume reductions, it is forecasting increased fuel
costs due to the carbon levy and increased commodity pricing. AET stated the September 2018
update reflects the most up-to-date information available on the record147 and observed that the
fuel forecast had not been the subject of intervener evidence, nor questioning at the oral hearing.
Therefore, the forecasts should be approved as filed.
174. The CCA advised the Commission that it had no reply to AET’s arguments in relation to
fuel costs.
146 Exhibit 22742-X0001.02, updated application, Table 4-1, PDF page 141, footnotes removed. 147 Exhibit 22742-X0725, AET final argument, paragraph 111.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 44
Commission findings
175. The Commission has reviewed the fuel cost forecast provided by AET. Table 4.2 in the
application provides details on AET’s fuel cost calculation and forecast. Given Table 4.2, the
Commission finds the price and volume assumptions used by AET for its natural gas, propane
and diesel forecasts to be reasonable.
176. However, the Commission notes that the Alberta provincial government repealed the
carbon tax effective June 4, 2019.148 The Commission takes notice of this repeal and directs AET,
in its compliance filing to this decision, to remove the effects of the repeal of the carbon tax from
its fuel cost forecast for the months in 2019 that are affected by this legislative change. The
Commission accepts AET’s 2018 fuel cost forecast, as filed in its updated application.
7 Operating costs
177. In its application, AET stated that it has forecast operating costs consistent with the
previously approved activity-based forecast methodology. AET further described its process in
developing activity-based forecasts as follows:
Functional areas within AET perform an annual assessment of resources to ensure that
activities performed in each area are relevant and required to fulfill legislative and
regulatory obligations, provide ongoing safe and reliable transmission services to
customers, and meet business needs during the Test Period.149
178. The following table summarizes AET’s direct operating costs:
Table 19. Transmission direct operating costs150
2015 2016 2017 2018 2019
USA account Actuals Actuals Actuals Test period
($ million)
USA 560 – Supervision & Engineering 5.0 3.6 3.5 3.4 3.5
USA 561 – Control Centre 3.2 3.6 3.4 4.1 4.3
USA 562 – Station Maintenance 13.6 11.3 11.4 8.4 9.0
USA 563/569 – Overhead Line Maintenance 4.1 3.5 3.6 2.5 2.6
USA 567 – Annual Structure Payments 8.6 6.6 6.7 6.9 7.3
USA 571.1 – Vegetation Management 9.3 9.1 6.7 10.9 11.1
USA 575 – IT Support 3.4 3.1 3.0 3.0 2.9
Subtotal 47.2 40.8 38.3 39.2 40.7
USA 566 – Miscellaneous Transmission Expense non-Affiliate
15.1 12.7 12.3 12.2 12.2
Net Direct O&M 62.3 53.4 50.5 51.4 52.9
USA 566 – Miscellaneous Transmission Expense Affiliate
24.4 22.6 26.1 3.3 3.3
Total direct O&M 86.6 76.0 76.6 54.7 56.3
148 Bill 1: the Carbon Tax Repeal Act received Royal Assent on June 4, 2019. 149 Exhibit 22742-X0001.02, updated application, paragraph 97. 150 Exhibit 22742-X0001.02, updated application, paragraph 98, Table 5.1.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 45
7.1 Forecasting accuracy
179. Bema, on behalf of the CCA, provided several comments on AET’s operating costs and
forecasting accuracy, describing its process as follows:
The Bema evidence began by first reviewing AET’s historical forecasting accuracy for
each USA account. However, Bema’s evidence did not simply stop there and propose a
generalized reduction to AET’s forecast costs based only on the forecasting accuracy
analysis. Rather, Bema then specifically reviewed the evidence available to support
AET’s forecast costs, which included the core evidence in AET’s application,
information provided in information responses, AET’s GTA schedules and other analysis
relied upon by Bema. Based on this combined evidence, Bema recommended
adjustments to some of AET’s forecast operating costs. Accordingly, the Bema evidence
was not simply an isolated analysis of AET’s forecasting accuracy as AET attempted to
have the Commission believe.151
…
Additionally, to ensure improved accuracy in preparing its evidence, Bema specifically
excluded certain costs where they were the subject of deferral accounts, reserve accounts,
other Bema analysis or if they were affiliate in nature and required to be offset. These
types of transactions can skew the results of an analysis of past forecasting accuracy. For
example, including AET’s flow through affiliate transactions that have a revenue offset
would improperly suggest that the actual costs are higher, which would be misleading.
Accordingly, the CCA submits that significant weight should be given to the
recommendations of Bema in relation to AET’s forecast operating costs.152
180. To support its position, the CCA provided a table comparing approved ROE ($ and %)
and actual ROE ($ and %) for the years 2008-2017. The CCA identified that, for that period,
actual ROE tended to exceed approved ROE, and it concluded that the positive variances could
only come from items without deferral account treatment, such as operating costs, income taxes,
revenue offsets and non-direct assigned capital.153
181. AET responded to the CCA's position as follows:
Contrary to the submissions of the CCA, AET has provided detailed information, not
only with respect to its historic forecasting accuracy, but also variance explanations
which allow the Commission to understand the variance experienced from forecast to
actual, including specifically information associated with the efficiency gains achieved
by AET over the last Test Period, which are now embedded and reflected in the 2018 and
2019 Test Year forecasts. As noted, the benefits of AET adopting various initiatives
during this time period are now being passed on to customers in the form of reduced
rates.154
Commission findings
182. For purposes of this section, the Commission will not take a global approach to its
determinations. Instead, it will only consider the issues related to non-labour costs. The
Commission considers that a high-level analysis of forecasting accuracy has value only to the
151 Exhibit 22742-X0722, CCA final argument, paragraph 186. 152 Exhibit 22742-X0722, CCA final argument, paragraph 193. 153 Exhibit 22742-X0722, CCA final argument, paragraphs 202-204. 154 Exhibit 22742-X0727, AET reply argument, paragraph 104.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 46
extent that it shows a consistent trend of under spending relative to its forecasts, that cannot be
reasonably explained by specific cost drivers. The Commission views that it should, where
possible, evaluate forecast accuracy for each of the specific cost categories, where cost category
information and support for increases is available, to determine the reasonableness of the
applied-for amounts. Accordingly, the Commission has reviewed, in other sections of this
decision, the forecasts for AET’s labour costs derived from FTEs and labour rates affected by
escalation factors. Therefore, in the subsection below, the Commission will limit its findings to
those accounts where non-labour issues have been identified.
7.1.1 USA 561 – Transmission Operations – Control Centre
183. AET stated that most of the cost increases for this account for the test period were
associated with the reallocation of network services and operations costs from USA 562 to
USA 561.155
184. The CCA recommended a disallowance of $200,000 for 2018 and $400,000 for 2019. It
was the CCA’s position that AET did not adequately explain several items, including why new
Alberta Reliability Standards (ARS) require increased O&M costs and why there were increases
in SCADA (System Control and Data Acquisition) service agreement costs.156
185. AET responded that the CCA ignored the full-year impact of the 11 new ARS
implemented in October 2017 and the oral testimony regarding SCADA-related software and
service agreements.
Commission findings
186. As this section pertains to non-labour issues, the Commission will confine itself to
SCADA-related software and service agreements. All other issues identified with this account
are labour-related. The AET testimony of Mr. Bothwell was that the increased SCADA licence
costs are due to the increase in SCADA locations, that is, the increase in volume of use.157
187. The Commission accepts the evidence on why there were increases in SCADA costs, that
is, because of volume of use, and approves the forecast for non-labour costs for this account for
each of the test years, as filed.
7.1.2 USA 563 and 569 – Overhead Line Maintenance
188. The CCA questioned why the forecast for general operating expenses increased by
$100,000 for each of 2018 and 2019. The CCA recommended that costs for this account be
reduced by $100,000 for 2018 and $200,000 for 2019.158
189. AET stated that increases in the general operating expenses category of these USA
accounts are associated with increases in the aerial (fixed wing and helicopter) program as part
of its maintenance optimization initiatives. AET added:
Specifically, AET has incorporated the use of ultraviolet, infrared and high-resolution
imagery captured from aircraft and the use of helicopter-assisted climbing inspections on
155 Exhibit 22742-X0001.02, updated application, paragraph 150. 156 Exhibit 22742-X0722, CCA final argument, paragraphs 224-226. 157 Transcript, Volume 3, page 450, line 19 to page 451, line 1. 158 Exhibit 22742-X0722, CCA final argument, paragraphs 244-248.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 47
(primarily) lattice tower transmission lines to largely replace maintenance activities that
previously required technicians to climb structures to collect the same information. While
the costs in the General Operating Expenses category have increased since 2015, they are
more than offset through labour and contractor cost savings …159
190. The CCA argued that AET did not explain why the aerial program costs have increased
since 2016 and pointed out that the magnitude of the increases exceeded inflation.160
191. In its reply argument, AET stated that increased utilization, increased capabilities and
new technology have resulted in modest increases in aircraft costs, but have offset labour costs
which otherwise would have been charged to this account.161
Commission findings
192. The Commission accepts the submission from AET that the increasing use of the aerial
program replaces certain maintenance practices, which reduce labour and contractor costs. For
this reason, the Commission approves AET’s forecast costs for this account for each of the test
years.
7.1.3 USA 566 – Miscellaneous Transmission Expense
193. AET described the costs for this account as follows:
AET captures the costs associated with the following activities in USA 566: salary
continuance (such as sick and bereavement leave), safety initiatives such as safety
meetings and safety-specific training, technical training, variable pay, relocation costs
and administrative activities. These costs are incurred by the FTEs assigned to the other
direct transmission O&M accounts, including engineering, operations, and station and
overhead line maintenance.162
…
This account includes labour costs of the Cyber Security Office, Asset Management
Office, staff for vegetation management program and work methods specialist. This
account also contains costs relating to facilities that are owned by AED and occupied by
AET staff. A portion of the capital costs associated with these buildings was previously
included in AET’s rate base, but ownership has been fully transferred to AED.163
194. AET provided the following table to illustrate its forecast costs for this account:
Table 20. Direct O&M costs for USA 566164
2015 2016 2017 2018 2019
Actuals Actuals Actuals Test Period
($ million)
Direct O&M cost 39.4 35.2 38.4 15.5 15.6
Affiliate and affiliate cost of goods sold 24.4 22.6 26.1 3.3 3.3
Non-affiliate 15.1 12.7 12.3 12.2 12.2
159 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 47. 160 Exhibit 22742-X0722, CCA final argument, paragraph 249. 161 Exhibit 22742-X0727, AET reply argument, paragraph 118. 162 Exhibit 22742-X0001.02, updated application, paragraph 226. 163 Exhibit 22742-X0001.02, updated application, paragraphs 227-228. 164 Exhibit 22742-X0001.02, updated application, paragraph 226, Table 5.14.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 48
195. In argument, the CCA submitted that AET had not demonstrated the need for an increase
in general operating expenses after moving the building facility costs back into general operating
expenses in 2018 and 2019. The CCA recommended a disallowance of $500,000 for each of the
test years.165
196. In its rebuttal evidence, AET explained that the General Operating Expense category
increase in 2018 was due to increased costs associated with Crown dispositions for facilities on
Crown land, and for road use payments.166 The increase in external contractor charges was due to
building facility charges being captured under this category.167
197. The CCA argued that Crown dispositions and road use cost increases account for only
$300,000 of AET’s proposed cost increases and that therefore at least $200,000 of the cost
increase in general operating expenses had yet to be explained.168
198. In its reply argument, AET stated that it “provided detailed information with respect to
the cost variance, being mainly due to services to outside parties cost of sales, which appears as
a revenue offset.”169
Commission findings
199. The Commission accepts AET’s explanation that increases for external contractor
charges and general operating expenses were due to building facility costs and crown
dispositions. The Commission also accepts the submission from AET that the cost variance due
to services to outside parties has a revenue offset. Therefore, the Commission accepts AET’s
forecast costs for USA 566.
7.1.4 USA 567 – Annual Structure Payments
200. AET is required by the Surface Rights Act to pay annual compensation to landowners for
transmission structures located on their property. These costs are recorded in USA 567. Among
the costs included in this account are the annual structure payments and any costs relating to
Surface Rights Board (SRB) proceedings. AET provided the following evidence of direct O&M
costs for USA 567, which included a forecast increase in compensation applications to the SRB:
Table 21. Direct O&M costs for USA 567
2015 2016 2017 2018 2019
Actuals Actuals Actuals Test period
($ million)
Direct O&M cost 8.6 6.6 6.7 6.9 7.3
Source: Exhibit 22742-X0001.02, updated application, PDF page 185.
201. With the completion of the Eastern Alberta Transmission Line (EATL) and the Central
East Transmission Development (CETD), and the elimination of uncertainty regarding annual
165 Exhibit 22742-X0722, CCA final argument, paragraph 266. 166 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 50. 167 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 50. 168 Exhibit 22742-X0722, CCA final argument, paragraphs 259-261. 169 Exhibit 22742-X0727, AET reply argument, paragraph 120.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 49
structure payments for those projects, AET is proposing to discontinue the deferral account for
annual structure payments.170
202. The CCA noted that AET’s forecasting accuracy for this account was within one per cent
of the approved forecast in the most recent two years and equal to the approved forecast in the
most recent five years. The CCA supported AET’s request to remove the annual structure
payments deferral account.171 However, the CCA argued that absent base increases from the
addition of new transmission facilities, there should not be notable increases in costs,172 and it
recommended that the Commission disallow $100,000 and $400,000 in costs in 2018 and 2019,
respectively.173 The CCA stated that its request was reasonable as AET confirmed, in its rebuttal
evidence, that 2018 forecast SRB costs were less than the applied-for amounts but AET still
expected the 2019 SRB costs to be consistent with its forecast.174
203. In reply argument, AET noted that the increased costs for SRB hearings related to
renewal agreements for the EATL, CETD and Hanna Region Transmission Development
(HRTD).175
Commission findings
204. Although there may be more certainty regarding actual annual structure payments, the
Commission agrees that there is uncertainty regarding SRB costs consistent with AET’s
$200,000 reduction in its forecast costs for 2018.
205. Given the uncertainty with SRB costs, the Commission denies AET’s request to
discontinue the existing deferral account for annual structure payments. AET is directed to
reflect, in its compliance filing to this decision, the $200,000 reduction for the 2018 test year.
The Commission also accepts the CCA arguments regarding the 2019 forecast and directs AET
to reduce the 2019 forecast by $200,000.
7.1.5 Vegetation management
7.1.5.1 Reserve for vegetation management
206. In Section 1.4 of the application,176 AET requested discontinuance of the reserve for
vegetation management. The reserve was established in Decision 20272-D01-2016, pursuant to
which the Commission directed AET to set off amounts spent in excess of the approved forecast
for a given test year against amounts included in the approved forecast(s) for subsequent years
within the specific test period. Approved but unused amounts within any given test period would
be added to the reserve account balance for start of the next test period.177
207. AET described past challenges in securing contractors to execute its planned vegetation
management program. It submitted that these challenges have now been addressed through
diversification of contractors and other changes in its approach to vegetation management. AET
170 Exhibit 22742-X0001.02, updated application, paragraph 195. 171 Exhibit 22742-X0722, CCA final argument, paragraphs 268-269. 172 Exhibit 22742-X0722, CCA final argument, paragraph 270. 173 Exhibit 22742-X0722, CCA final argument, paragraph 272. 174 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 54. On PDF page 55, AET stated that costs associated
with SRB proceedings are expected to be $0.2 million less than originally forecast in 2018. 175 Exhibit 22742-X0727, AET reply argument, paragraph 34. 176 Exhibit 22742-X0001.02, updated application, paragraph 10, Table 1.4. 177 Exhibit 22742-X0001.02, updated application, paragraph 604.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 50
indicated that, with its comprehensive forecast for vegetation management for the test period and
the availability of contractor resources, the uncertainty regarding the vegetation management
account is substantially reduced and the reserve account is no longer required.
208. The CCA challenged AET’s assertions on forecasting accuracy, in particular, pointing
out that AET’s accuracy with respect to 2015 was due entirely to the Commission having
approved only actual costs for that year. Further, the CCA observed that the Commission
directed a 25 per cent reduction in forecast relative to applied-for costs for 2016 and 2017 and
that, in those years, AET achieved the reduced costs approved by the Commission. The CCA
asserted that, had applied-for costs been approved, AET’s forecasting accuracy would have been
as consistently poor as it has been in prior years.178
Commission findings
209. The Commission directs AET to maintain its reserve for vegetation management. As
noted by the CCA, the variance for 2015 was limited because the Commission accepted actual
results rather than forecasts for that year.
210. AET has stated that:
Evidence provided by AET herein confirms that AET’s forecasting accuracy has been
very high from 2015 to 2018, particularly given that the mechanics of the Reserve
Account that applied during the 2016 and 2017 period permitted AET to advance
treatments from 2017 to 2016.179
211. AET’s statement shows that the vegetation management reserve account has supported
stability and AET’s management of its forecast costs. As a result, there is merit in maintaining
this reserve account. The Commission finds that the reserve account should be continued and
therefore directs AET to maintain the use of the vegetation management reserve account.
7.1.5.2 2018-2019 Forecast vegetation management costs (USA 571.1)
212. AET provided the following direct O&M costs for USA 571.1 (Vegetation management):
Table 22. Direct O&M costs for USA 571180
2015 2016 2017 2018 2019
Actuals Actuals Actuals Test period
($ million)
Direct O&M Cost 9.3 9.1 6.7 10.9 11.1
213. AET stated that the forecast increases for 2018 and 2019 for vegetation management
relate to an escalation in its mechanical programs in preparation for conversion to herbicide
treatments.
214. In evidence and argument, AET claimed that its ability to achieve substantial cost savings
in the execution of its vegetation management program relies on its aggressive approach to
mechanical treatments that are to be followed by herbicide treatments. AET indicated that any
178 Exhibit 22742-X0722, CCA final argument, paragraphs 108-109. 179 Exhibit 22742-X0725, AET final argument, paragraph 52. 180 Exhibit 22742-X0001.02, updated application, paragraph 198, Table 5.10.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 51
deferral with respect to its programs in the test years would delay the achievement of cost
savings from the herbicide treatments.181 AET added that 2018 actuals were tracking to meet
forecast costs, as shown in its updated application.182
215. The CCA submitted that AET is forecasting its highest ever vegetation management costs
for the 2018-2019 test period183 and, therefore, it recommended a 25 per cent reduction in AET’s
forecast costs for each of the two test years.184 As an alternative to the 25 per cent reduction, the
CCA recommended that the use of 2018 actual costs would be reasonable. The CCA added that
if AET’s 2018 actual costs are close to the forecast, then AET should not be opposed to this
alternative for 2018. The CCA would, however, continue to propose a 25 per cent reduction to
the 2019 forecast costs.185
216. AET replied that, based on the best information to date, 2018 actuals were on track to
meet the forecast expenditure provided in the application update.186 It added that it is on track to
complete the conversion of its rights-of-way to herbicide treatment by 2020, and thereafter to
deliver to ratepayers the benefits associated with such conversion.
Commission findings
217. The Commission shares some of the concerns expressed by the CCA regarding the level
of vegetation management costs. However, the Commission does not agree with the CCA that a
25 per cent reduction in 2018-2019 vegetation management expenditures is reasonable. For
2018, the Commission accepts the evidence of AET that 2018 actual expenditures were tracking
close to forecast and approves AET’s 2018 forecast. For 2019, the Commission agrees with the
CCA that a reduction is warranted because there is insufficient support that the forecast work for
vegetation management must be completed in 2019. Accordingly, the Commission directs that
AET reduce the forecast vegetation management costs for 2019 by 10 per cent in its compliance
filing to this decision.
218. Further, the Commission directs AET to provide, in its next GTA, a detailed breakdown
of the savings and lower forecast expenses realized as a result of the transition by AET from a
primarily mechanically based vegetation management program to one that is primarily based on
the application of herbicides.
7.1.6 USA 575 – IT Support
219. AET is forecasting a modest cost decrease of $100,000 to USA 575 during the test
period. The reductions from 2018 to 2019 are largely associated with lower distributed
applications and support resulting from the implementation of cloud-based technology, lowering
the requirements for maintenance costs, storage and application hosting.187
220. The CCA recommended a reduction in this account of $300,000 in each of the test years.
In its rebuttal evidence, AET showed that only 37 per cent of the costs in this account vary with
the number of IT users, and the CCA accepted the premise that costs were not 100 per cent
181 Exhibit 22742-X0722, CCA final argument, paragraph 108. 182 Exhibit 22742-X0725, AET final argument, paragraph 127. 183 Exhibit 22742-X0722, CCA final argument, paragraph 105. 184 Exhibit 22742-X0722, CCA final argument, paragraph 108. 185 Exhibit 22742-X0722, CCA final argument, paragraphs 112-113. 186 Exhibit 22742-X0727, AET reply argument, paragraph 128. 187 Exhibit 22742-X0001.02, updated application, paragraph 225.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 52
correlated with the number of users. However, the CCA questioned the calculation of the
forecast number of users. While noting AET’s revised calculations suggesting a reduction to this
account of $100,000 for 2018 and $200,000 for 2019,188 the CCA submitted that additional
reductions may be warranted if the Commission directs reductions in AET’s FTE forecast.189
221. AET replied that it incorporated the changes in IT users and equipment in its forecast, as
demonstrated in its rebuttal evidence, and that the costs for this account should be approved as
filed.190
Commission findings
222. The Commission accepts the submission of AET that its forecast for expenses in this
account reflects a reduced number of IT users. However, the Commission directs AET to adjust
its forecast for this account based on the Commission’s determinations regarding forecast FTEs
in Section 5.1.1 of this decision.
223. Further, on June 5, 2019, the Commission issued Decision 20514-D02-2019191 regarding
the ATCO Utilities IT common matters proceeding. AET is directed to reflect any changes
arising from the directions in that decision in its compliance filing to this decision. AET is
further directed to provide schedules detailing how the determinations from Decision 20514-
D02-2019 are reflected in its compliance filing.
8 Transmission depreciation
224. In support of its forecast 2018-2019 depreciation expense calculations, AET submitted a
technical update to its depreciation rates, as of December 31, 2017. The technical update was
prepared by Larry Kennedy of Concentric Advisors ULC (Concentric)192 and used the most
recently approved depreciation parameters of average service life, Iowa curve and dispersion,
and net salvage percentages approved by the Commission in Decision 20272-D01-2016.193 These
three depreciation parameters were applied to actual December 31, 2017, plant in-service
balances for the purpose of updating AET’s depreciation rates and to derive the 2018-2019
forecast depreciation expense. Additionally, AET’s amortization of accumulated depreciation
differences amount is the same amount approved in Decision 20272-D01-2016.
225. The Commission has summarized AET’s historical and forecast depreciation expense in
the following table:
188 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 57, Table 3. 189 Exhibit 22742-X0722, CCA final argument, paragraphs 283-288. 190 Exhibit 22742-X0722, AET reply argument, paragraphs 128-131. 191 Decision 20514-D02-2019: The ATCO Utilities (ATCO Gas and Pipelines Ltd. And ATCO Electric Ltd.)
Information Technology Common Matters Proceeding, Proceeding 20514, June 5, 2019. 192 Exhibit 22742-X0001.02, updated application, Attachment 31.1, PDF pages 1047-1174. 193 Decision 20272-D01-2016, ATCO Electric Ltd. 2015-2017 Transmission General Tariff Application.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 53
Table 23. AET historical and forecast depreciation expense 2015-2019
2015 Actual 2016 Actual 2017 Actual 2018 Forecast 2019 Forecast
($ million)
Transmission 112.6 160.3 174.9 178.2 180.1
Amortization of reserve differences – transmission
5.3 5.4 5.4 5.3 5.3
Direct general PP&E 28.7 29.3 17.7 20.1 22.0
Farm, irrigation transmission 1.1 1.3 1.7 1.5 1.6
Total gross provision 147.7 196.4 199.7 205.2 209.1
Vehicle depreciation capitalized (3.6) (3.6) (3.1) (3.6) (3.6)
Amortization of contributions (7.8) (9.3) (9.8) (10.1) (10.4)
Total depreciation expense 136.3 183.5 186.8 191.5 195.1
Collection (refund) of previously collected capitalized pension contributions
6.2 4.0 (38.4) - -
Total depreciation expense 142.5 187.5 148.4 191.5 195.1
Source: Extracted from Exhibit 22742-X0002.04, MFR schedules 6-1 and 6-2.
226. AET stated that the increase in 2018 depreciation expense over 2017, is due to the one-
time refund of previously collected capitalized pension costs.194 195 During the years 2018 and
2019, the forecast increase in depreciation expense is due primarily to anticipated growth in rate
base.196
227. Neither the UCA nor the CCA commented on AET’s technical update or the calculation
of depreciation expense.
228. There was discussion on whether it would be reasonable for AET to change its
capitalization of salvage costs by adopting a methodology similar to that used by EPCOR
Distribution & Transmission Inc (EPCOR). AET and the CCA shared the view that such a
determination should not be made within the context of a single GTA and is best explored within
a generic-type proceeding where corollary issues such as intergenerational equity may be
examined from the viewpoint of all Alberta utilities.
229. In argument, AET addressed Alberta PowerLine’s (APL) treatment of net salvage as it
relates to the West Fort McMurray 500-kV Transmission (WFMAC) Project. AET confirmed
that APL’s commercial arrangement with the AESO precludes the collection of funds for future
net salvage costs during the 35-year contract. While the CCA submitted that this arrangement is
not in the public interest, it agreed with AET that the “treatment of the cost of salvage for the
194 Exhibit 22742-X0001.02, updated application, Attachment 3.2, Analysis of Transmission Rate Increase,
Schedule 3-2, lines 4-5 and 18-19, PDF page 126. 195 Exhibit 22742-X0001.02, updated application, paragraph 601: “… In Decision 20272-D01-2016 (para. 1311),
the AUC also directed AET to propose a method in the 2015-17 GTA Compliance Filing to refund the
accumulated difference resulting from the change in accounting treatment of capital pension costs, including
related income tax impacts. In AET’s Compliance Filing to Decision 20272-D01-2016 (Proceeding ID 22050),
the accumulated capitalized pension costs was proposed to be refunded as part of AET’s approved 2017 tariff.
On June 19, 2017, the AUC issued Decision 22050-D01-2017, which in Appendix 2, approved AET’s proposed
refund for the accumulated capitalized pension costs.” 196 Exhibit 22742-X0001.02, updated application, paragraph 67.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 54
WFMAC Project should be given no weight regarding how the cost of salvage should be
recovered for AET assets” particularly as the terms of the agreement were set in a competitive
process.197
Commission findings
230. The Commission has examined AET’s technical update and observes that AET has
continued to rely on the depreciation parameters and the amortization of reserve differences
amount approved in Decision 20272-D01-2016. Accordingly, and given the application and
other information on the record, the Commission finds the resulting depreciation rates and
depreciation expense calculations to be reasonable. AET’s depreciation expense is approved,
subject to any applicable findings and directions included elsewhere in this decision.
231. The Commission has examined parties’ evidence with respect to the salvage
methodologies used by EPCOR and APL. While the Commission will make no change to AET’s
depreciation methodology or depreciation rates in this proceeding, the Commission directs AET,
as part of its next depreciation study, to compare AET’s average service lives and net salvage
percentages for its five largest plant accounts (on a dollar amount basis) to those of other electric
transmission utilities in the province.
8.1 Deferral account for IFRS-related depreciation rate issues
232. AET stated that under International Financial Reporting Standards (IFRS), it is required
to review its depreciation rates annually, and to implement new depreciation rates for IFRS
purposes, if necessary. For this reason, AET requested the “ability to file an application with the
Commission seeking approval of new depreciation rates”198 through a deferral account, should
such circumstances arise.
233. When asked in an IR whether it had ever been required to update its depreciation rates (as
a result of the Commission-approved depreciation parameters) under IFRS reporting
requirements, AET responded that “There have been no years since the implementation of IFRS
where AET has not found its depreciation rates, as resulting from Commission–approved
depreciation parameters, to be in accordance with IFRS.”199
234. According to AET, an example of a circumstance that would prompt it to file an
application to seek a new depreciation rate would be a legislative change directing it to retire
diesel generation units by a certain year. This would necessitate a change in the estimated service
life of the asset and would meet the deferral account criterion of a factor affecting the forecast
that would not be under the control of the company. Such circumstances would also not be
reasonably forecastable and the resulting variance in forecast depreciation could produce a loss
or gain of significant magnitude. AET submitted that if such an instance were to occur within the
test period, it would seek approval to flow the change in depreciation expense through its IFRS
deferral account and file an updated depreciation study for the assets as part of the annual
deferral account application.200
197 Exhibit 22742-X0725, AET final argument, paragraph 159, and Exhibit 22742-X0726, CCA reply argument,
paragraphs 101-103. 198 Exhibit 22742-X0001.02, updated application, paragraph 238. 199 Exhibit 22742-X0200.02, AET-AUC-2017AUG30-002, PDF pages 2-3. 200 Exhibit 22742-X0200.02, AET-AUC-2017AUG30-002, PDF pages 2-3.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 55
235. During the oral hearing, AET witness, Mr. Hoshowski, confirmed that in a case where
“there would be a fundamental change in the underlying lives of those assets that would require
us to record different depreciation and review those changes in asset lives, then the utility would
seek to have deferral account treatment afforded to consider that.”201 Mr. Hoshowski did not
provide an example of circumstances that would necessitate deferral treatment beyond that
provided in AET’s IR response, but he clarified that “certainly it would be something of a
substantial nature that wouldn’t have been considered in the underlying study that was provided
in the context of the GTA or the technical update …”202
236. AET further clarified that the request to include changes to depreciation rates under IFRS
requirements would be an expansion in the scope of AET’s existing IFRS deferral account and
not the creation of a new IFRS-related deferral account.
237. Mr. Hoshowski acknowledged that the Commission had previously denied deferral
account treatment for IFRS-related changes in depreciation rates in AET’s 2013-2014 GTA.
However, he stated that there still exists an underlying need for the deferral account
notwithstanding the extensive regulatory process currently afforded to the examination of
depreciation parameters and the fact that there had been no instances of IFRS-required changes
requested in relation to depreciation rates.203
238. The Commission requested Bema’s opinion with respect to AET’s proposal for IFRS-
related deferral treatment related to the implementation of new depreciation rates, as follows:
… would a retirement “from causes not reasonably assumed to have been anticipated or
contemplated in prior depreciation or amortization provisions” include the circumstances ATCO
Electric stated it anticipates could lead to a requirement under IFRS “for its approved
depreciation parameters (and, as a result, depreciation rates) to be updated within the test period
due to a significant change in the estimated life of assets” by virtue of, for example, “a legislative
change directing AET to retire its diesel generation units by a certain year”?204
239. Bema considered there were two questions at issue: “First, does IFRS require AET to
update its approved depreciation rates used for regulatory purposes for a change such as that
contemplated in AET’s response? Second, is the Commission required to reflect such a change
for regulatory purposes through AET’s revenue requirement?”205
240. With respect to the first question, Bema stated that, based on its experience, there were
various approved methodologies for capital recovery through depreciation among Alberta
electric utilities. However, it was not aware that any utilities had identified a difference between
IFRS and regulatory accounting as it pertained to depreciation. Bema submitted that while IFRS
requires an entity to update its depreciation estimate every year, the detailed nature of a
regulatory depreciation study is adequate to meet the requirements of IFRS for a two-year test
period.
201 Transcript, Volume 5, page 818, lines 20-25. 202 Transcript, Volume 5, page 819, lines 4-9. 203 Transcript, Volume 5, pages 817-818. 204 Exhibit 22742-X0612, CCA-AUC-2018DEC19-003, PDF pages 7-9. 205 Exhibit 22742-X0612, CCA-AUC-2018DEC19-003, PDF page 8.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 56
241. With respect to the second question, Bema stated that, under Rule 026,206 the Commission
is not bound to reflect such a change for regulatory purposes through AET’s revenue
requirement.207
242. In argument, the CCA concluded that the Commission should deny AET’s request to
flow certain changes in depreciation rates through a deferral account within a test period. This
was based on the CCA’s view that the depreciation rates approved by the Commission are not
required to align with IFRS. The CCA stated that it appeared that “AET may also be trying to
permit changes related to extraordinary retirements that occur in a current period to be flowed
through the [IFRS-related] deferral account.”208
243. In reply argument, AET clarified that it was “not requesting a deferral account for IFRS
to deal with changes in depreciation rates,” but “requesting an extension of the current IFRS
deferral account to include changes in depreciation rates.” AET submitted that changes in
depreciation rates as a result of IFRS do meet the criterion established for the creation of a
deferral account and, therefore, its requested extension of the current IFRS deferral account was
reasonable in the circumstances and should be approved, as filed.209
Commission findings
244. In this section, the Commission makes a finding specific to AET's request to expand the
scope of its existing IFRS deferral account that would allow it to seek approval of new
depreciation rates as a result of IFRS requirements. The Commission makes no finding in this
section with respect to the operation of, or the amounts currently included in, AET’s existing
IFRS deferral account.
245. AET, in its written evidence and oral testimony during the hearing, described various
scenarios and outcomes that might precipitate an IFRS-related change to a depreciation rate. The
Commission is not persuaded that a requirement under IFRS that AET review its depreciation
rates annually is, in and of itself, sufficient to support an expansion of the existing deferral
account notwithstanding AET's claims that such requirement creates greater uncertainty in
depreciation rates.
246. Accordingly, the Commission denies AET’s request to expand the scope of its existing
IFRS deferral account to permit it to seek approval of new depreciation rates through that
account, simply because IFRS requires AET to review depreciation rates annually.
247. Having made this finding, the Commission does not need to address the evidence of AET
or the CCA with respect to whether the Commission, under Rule 026, is required to align the
depreciation rates it approves for regulatory purposes, with those reported under IFRS.
8.2 Fort McMurray wildfire
248. The Commission deferred its findings related to the Fort McMurray wildfire. As a result,
it is necessary that certain aspects of AET’s application remain outstanding as placeholder
206 Rule 026: Regulatory Account Procedures Pertaining to the Implementation of the International Financial
Reporting Standards. 207 Exhibit 22742-X0612, CCA-AUC-2018DEC19-003, PDF pages 7-9. 208 Exhibit 22742-X0722, CCA final argument, paragraph 775. 209 Exhibit 22742-X0727, AET reply argument, paragraphs 304-305.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 57
amounts until such time as the Commission renders its decision on matters pertaining to the Fort
McMurray wildfire. The Commission identifies the following placeholders:
(a) The proposed capital addition in 2017 of TCM Project 00073: Fort McMurray
Wildfire Transmission Asset Restoration in the amount of $7.6 million for assets
damaged and requiring restoration as a result of the wildfire.
(b) The proposed retirement of the original historical cost of AET’s asset Account 453
– Poles and fixtures destroyed and retired from service in the amount of $1.899
million.
(c) The proposed recovery of $0.664 million through AET’s amortization of reserve
differences mechanism, of the net book value of AET’s asset Account 453 – Poles
and fixtures destroyed and retired from service.
(d) The recovery of $0.321 million through AET’s RID account, for power restoration
efforts related to damage caused by the Fort McMurray wildfire.
249. Furthermore, the Commission has similarly made no finding with respect to the issue
raised by the UCA of cross-subsidization of Fort McMurray wildfire-related expenditures
between ATCO Electric Ltd.’s distribution and transmission functions.
9 Income taxes
9.1 Income tax
9.1.1 Income tax - general
250. AET uses the future income tax (FIT) method for federal income taxes and the flow-
through method for provincial income taxes. AET did not request any changes to the income tax
method used in the test period. AET stated the reason for the continuation of the calculation of
FIT for federal income tax is to support AET’s credit metrics and AET’s proposed FFO-to-debt
ratio of nine to 13 per cent.210
251. AET’s summary of the income tax expense it is seeking to recover for 2018 and 2019, as
well as the source of the observed year-over-year tax expense variance is reproduced in the table
below:
Table 24. Summary of income tax expense
2016 Actual
2017 Actual
2018 Test year
2019 Test year
($ million)
Income tax expense 36.2 38.1 34.4 40.3
Increases/(Decreases) in test period (3.7) 5.9
210 Exhibit 22742-X0001.02, updated application, paragraphs 246-247.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 58
2016 Actual
2017 Actual
2018 Test year
2019 Test year
($ million)
Due to:
Collection of Future Taxes on Temporary Differences
(5.3) (5.4)
Increase/(Decrease) in utility earnings (8.1) 1.6
Impact of lower/(higher) tax deductions 9.8 9.7
Increases/(Decreases) in test period (3.7) 5.9
Source: Exhibit 22742-X0001.02, updated application, Table 7.4 – Tax Expense, paragraph 266.
252. AET calculated its tax expense using the applicable federal and provincial tax rates at the
time it filed its application. The tax rates used in the calculation of income tax expense are
included in the table provided below:
Table 25. Statutory tax rates
2018 2019
(%)
Federal income tax 15.00 15.00
Provincial income tax 12.00 12.00
Source: Exhibit 22742-X0001.02, AET 2018-2019 General Tariff Application, Table 7.1 – Tax Rates, paragraph 248.
253. Temporary tax differences occur when the reporting of a revenue or expense for financial
reporting purposes differs from the reporting of the revenue or expense for income tax purposes.
For the purposes of AET’s revenue requirement, forecast temporary tax differences are included
in AET’s forecast of income tax during the test period. The temporary tax differences, if they
relate to a deferral account, would be a true-up by AET in a DACDA proceeding.
254. Bema's evidence included an analysis of AET's forecasting accuracy for taxable
temporary differences and total federal taxable income. The results of Bema’s analysis are
provided in the table below:211
211 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraphs 628-629
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 59
Table 26. AET’s forecasting accuracy for taxable temporary differences and total federal taxable income
AET’s historical forecasting accuracy for temporary differences
Year Variance
2013 $49.3M in higher taxable temporary differences, resulting in a variance of 38% from approved
2014 $75.4M in higher taxable temporary differences, resulting in a variance of 46% from approved
2015 $40.8M in higher taxable temporary differences, resulting in a variance of 18% from approved
2016 $0.8M in higher taxable temporary differences, resulting in a variance of 0% from approved
2017 $57.1M in higher taxable temporary differences, resulting in a variance of 35% from approved
Total $223.3M of higher taxable temporary differences, resulting in a variance of 25% from approved
AET’s historical forecasting accuracy for federal taxable income
Year Variance
2013 $38.7M lower taxable income, resulting in a variance of 241% from approved
2014 $80.9M lower taxable income, resulting in a variance of 660% from approved
2015 $51.5M lower taxable income, resulting in a variance of 121% from approved
2016 $21.0M higher taxable income, resulting in a variance of 256% from approved
2017 $28.7M lower taxable income, resulting in a variance of 79% from approved
Total $178.8M lower taxable income, resulting in a variance of 1,301% from approved
Source: Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraphs 628-629.
255. Bema described AET’s historical forecasting accuracy for taxable temporary differences
and taxable income as “very low,” and noted that for every year, except 2016, the variance from
approved was to the benefit of AET.212
256. Bema conceded that a portion of the variances included in the table above would be
subject to deferral account treatment. It added, however, that it was unable to determine how
much of the variances have been, or are still to be, settled in a DACDA as a result of AET not
having up-to-date deferral account applications.213 However, Bema observed that a significant
portion of the forecast temporary tax differences are not associated with direct assigned capital
additions and, therefore, are not subject to a deferral account true-up.214
257. In Bema’s estimation, three of AET’s tax deductions are understated: stock handling,
isolated overhauls and removal and abandonment.215
258. Based on its analysis, Bema requested the Commission to direct AET to make the
following adjustments to the test years’ forecast temporary difference tax deductions:
(i) Increase stock handling by $0.5 million in both 2018 and 2019;
(ii) Increase isolated overhauls by $0.4 million in 2018 and $0.1 million in 2019; and
212 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 630. 213 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 631. 214 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraphs 633-634. 215 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraphs 635-636.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 60
(iii) Increase removal and abandonment by $2.0 million in both 2018 and 2019.216
259. In its rebuttal evidence, AET argued that Bema failed to explain why 2017 should be
used as a benchmark for the 2018 and 2019 forecast stock handling, isolated overhauls and
removal and abandonment deductions. Based on its 2013 to 2017 actual tax deductions for stock
handling, isolated overhauls and removal abandonment, AET stated that there is no year-over-
year pattern that should lead to basing the tax deductions for stock handling, isolated overhauls
and removal and abandonment on any specific year. AET explained how it developed its stock
handling, isolated overhaul, and removal and abandonment forecasts, and why 2017 actual
results have no bearing on corresponding amounts in 2018 and 2019:
• Stock Handling - Stock handling charges relate to overhead costs of procurement,
handling and warehousing of inventory. The forecast is dependent on the capital
program forecasted each year. As the capital program differs from year to year (i.e.
planning, engineering, or construction), so does the deduction for stock handling,
therefore 2017 actuals are unlikely to appropriately reflect a reasonable estimate for
the 2018 and 2019 forecasts.
• Isolated Overhauls – Isolated overhauls relate to the refurbishment of isolated
generation units. The forecast is based on the determination of asset condition and
regulatory compliance of the isolated generation assets. The isolated generation
assets that were determined to require refurbishment in 2017 are not necessarily the
same assets identified in the 2018 and 2019 forecasts. Therefore, the forecasts for
2018 and 2019 are developed independently. An illustrative example of why prior
periods can not be used as a basis for the current period forecast are the isolated
overhauls for Jasper Palisades generating units. With the interconnection of Jasper
occurring in 2019, AET is not forecasting isolated overhauls at Jasper Palisades in
2018 or 2019. However, AET completed required isolated overhauls in prior periods
at Jasper Palisades and reflected the income tax deduction. Please refer to the
business case filed in Exhibit 22742-X0171.03 for Project 90130: 2018-2019
Refurbish/Replace Engines for details of the forecasted isolated overhauls for 2018
and 2019.
• Removal and Abandonment – Removal and abandonment relates to the costs incurred
for the demolishing, dismantling, tearing down or removing of an asset from its
original location or position. The deduction is based on the estimated cost of
retirement forecast for capital assets that are coming to an end of their useful life. The
capital assets in 2017 that came to an end of their useful life would not be the same
assets that are coming to an end of their useful life in 2018 or 2019. Therefore, the
forecasts for 2018 and 2019 are developed independently of 2017 actuals.217
260. The CCA argued that the increased stock handling, isolated overhauls and removal and
abandonment tax deductions, as recommended in Bema’s evidence, are reasonable given that
AET has failed in its onus to show that “its forecast is reasonable and not understated.”218 219 The
CCA also noted that there were upcoming provincial and federal elections that may result in
216 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 637. 217 Exhibit 22742-X0618, AET rebuttal evidence to CCA and UCA, PDF pages 174-175. 218 Exhibit 22742-X0722, CCA final argument, paragraph 702. 219 Exhibit 22742-X0722, CCA final argument, paragraphs 701-704.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 61
changes to income tax rates. It recommended that the Commission direct AET to update its
income tax rates to the statutory rates in place at the time of its compliance filing.220
261. AET, in reply argument, stated that it has clearly demonstrated that its income tax
forecast “is activity-based and is tied to the underlying Capital Program that is driving the
various forecast income tax deductions.”221
Commission findings
262. In response to a Commission IR, Bema calculated the impact of its recommended
adjustments to the stock handling, isolated overhauls and removal and abandonment tax
deductions to be a reduction of $0.3 million per year to AET’s revenue requirement.222 The CCA
acknowledged that the revenue requirement impact of its recommendation is not as great as that
of other recommendations it has made, however, it submitted that “it remains inappropriate for
AET to continuously and consistently over earn above its approved income taxes” and that “[t]he
Commission is required to ensure that all forecast costs are just and reasonable and this includes
AET’s income taxes.”223
263. The Commission notes AET’s forecasts of the stock handling, isolated overhauls and
removal and abandonment tax deductions are based on its forecast capital work. As described in
Section 11 – capital projects, the Commission found AET’s capital forecasts to be reasonable.
Included in those approved capital project costs are expenses such as stock handling, isolated
overhauls and removal and abandonment. The Commission finds there is no need to alter these
expenses as it cannot divorce the review of these expenses from the corresponding tax
deductions. As a result, the Commission denies the CCA’s recommendations.
264. In its forecast, AET used a 15 per cent tax rate for federal income taxes and a 12 per cent
tax rate for provincial income taxes for both 2018 and 2019. The Commission approves the 2018
applied-for tax rate of 15 per cent for federal income tax and 12 per cent for provincial income
tax. The Alberta government, in Bill 3: Job Creation Tax Cut (Alberta Corporate Tax
Amendment) Act,224 reduced the general provincial corporate tax rate from 12 per cent to 11 per
cent. Bill 3 came into force on June 28, 2019 and amends sections 21 and 22 of the Alberta
Corporate Tax Act, changing the provincial tax rate as of July 1, 2019. The Commission takes
notice of the Legislative Assembly of Alberta’s passing of Bill 3 and directs AET, in its
compliance filing, to adjust for any changes in its provincial tax rate.
265. Given that AET’s request to maintain federal FIT is related to maintaining support for its
credit metrics, the Commission’s determination on AET’s continued use of FIT will be made in
the credit metric portion of this decision.
220 Exhibit 22742-X0726, CCA reply argument, paragraphs 112-113. 221 Exhibit 22742-X0727, AET reply argument, paragraph 157. 222 Exhibit 22742- X0612, CCA-AUC-2018DEC19-013, PDF page 35. 223 Exhibit 22742-X0722, CCA final argument, paragraph 698 224 https://open.alberta.ca/dataset/8597b610-1826-43d5-bdb1-3f5ba938875d/resource/7fce8356-f05f-4fd5-a84e-
cc7364f43c77/download/special-notice-ct-vol-5-no-52-job-creation-tax-cut.pdf
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 62
9.1.2 Allowance for funds used during construction
266. The financing or interest cost of a capital investment that occurs during the construction
of a capital project is accumulated and capitalized. This financing or interest cost is called an
allowance for funds used during construction (AFUDC).
267. AFUDC is discussed in this section because it is included in the calculation of income tax
expense. It would appear from the examples and calculations provided in the tables in this
section, in turn, that AET's current treatment of AFUDC for the purposes of calculating its
income tax expense, involves either:
Charging customers current tax expense by adding AFUDC to the total utility earnings
before tax, as exhibited by the differences in current tax expense in the “Build”
columns [(33.2) in Table 29 compared to 0.0 in Table 27 for each “Build” year]; or
Removing AFUDC from its undepreciated capital cost pool and charging customers
current tax expenses over the asset's service life, as demonstrated by the differences in
the current tax expense total [0.0 in Table 28 compared to 66.5 in Table 27].
268. An AET witness, Mr. Hoshowski, was questioned about the AFUDC amounts included in
the calculation of AET’s income tax expense in schedules 7-3 “Determination of Federal
Taxable Income” and 7.4 “Schedule of Transmission Capital Cost Allowance” of the application
found at Exhibit 2.04 and a corresponding IR response at Exhibit 417 (IR 12).225 With respect to
IR 12:
Q. My general understanding of utility earnings before tax is it is regulated revenue
minus operating expenses. Is that right?
A. MR. HOSHOWSKI: Yes, I would agree with that characterization.
Q. How is AFUDC regulated revenue?
A. MR. HOSHOWSKI: It's a regulated revenue in the sense that at some future point,
that will be collected from customers when those balances are being applied to the
underlying capital projects that they're attributable to. So this is recognizing in the period
for which AFUDC arose that it's appropriately added to the utility earnings.
Q. Moving down to the "add/deduct" section on line 70 which is titled "AFUDC," why
has ATCO Electric deducted 11.7 million of AFUDC in the calculation of taxable
income?
A. MR. HOSHOWSKI: So in terms of the deduction, the AFUDC is recognized as an
overhead cost to the capitalized item. So it's deducted in the current period given that it's
overhead in nature.
A. MR. HOSHOWSKI: But -- sorry. Regardless, on our CCA schedules, when this -- in
the 2019 period, when this deduct is taken in the aforementioned line 70 and recognized
that it's a current period expense and the deduction is taken there, the equivalent offset to
the CCA amount that's being claimed in that period is also adjusted for that AFUDC
225 Transcript, Volume 5, page 807, line 8 to page 813, line 5, and Transcript, Volume 6, page 877, line 6 to
page 878, line 24.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 63
amount, recognizing that it was already taken as a deduction in the current period. So the
UCC balance, moving forward, would reflect that.
269. Commission counsel then referred Mr. Hoshowski to Schedule 7.4, the schedule for
transmission capital cost allowance, and he explained the difference between schedules 7.3 and
7.4 in terms of the recording of CWIP and AFUDC:
A. MR. HOSHOWSKI: No, these are different amounts, and I'll walk you through the
difference in terms of what's reflected on Schedule 7-3 versus this 7-4 schedule for
AFUDC. So the amount being considered within Schedule 7-3 is the AFUDC that arises
and applied to those projects in the current period that may or may not be going into
service. So that represents the amount of AFUDC that is I'll call it or characterize it as
created when we look at the underlying projects that have construction work in progress
balances for that test period. The amount that shows up on Schedule 7-4 is the actual
amount of AFUDC that has been capitalized to these projects that have gone into service
in 2018 -- sorry, in 2019. So that's the differentiation. It's reflective, I guess, of when
those assets go into service. So recognizing that some assets might go into service the
year that that work commences or that some assets might go into service over a longer
two-year timeframe. Once those assets go into service and we claim the CCA tied to
those assets, the AFUDC that's taken and reflected on this schedule is the amount that's
gone into service for that project in its entirety.
Q. And if we could go back to Schedule 7.7-3 [sic; Schedule 7.3] under the 2019 test
period. Line 71 is titled "CCA-Federal" with CCA, of course, referring to capital cost
allowance. The amount deducted for CCA on line 71, which is 304.3 million, does not
include amounts related to AFUDC because these amounts are previously removed from
the UCC pool; is that right?
A. MR. HOSHOWSKI: That's correct.
Q. ATCO Electric adds the accumulated AFUDC costs incurred on a project to the costs
of a project; correct?
A. MR. HOSHOWSKI: Correct.
Q. And then AFUDC gets added to ATCO Electric's rate base, and it is eventually
recovered through depreciation.
A. MR. HOSHOWSKI: It's recovered through both depreciation and return, yes.
Q. And staying on Schedule 7-3, line 69 is titled "Depreciation/Amortization of
Contributions." That depreciation amount would include some portion of capitalized
AFUDC that was added to the costs of a project; correct?
A. MR. HOSHOWSKI: Yes, that's correct.
Q. So based on our discussion, it appears that ATCO Electric adds AFUDC twice for the
purposes of adjusting income for tax -- sorry, twice for the purposes of adjusting income
for tax purposes: first when the amount of AFUDC is added to utility earnings before tax,
and second, on an annual basis for the portion of AFUDC that is being depreciated
through the life of an asset. However, ATCO Electric only deducts AFUDC once in the
year the cost's incurred, which creates a tax expense payable from which ATCO Electric
collects its revenue requirement. Is that right?
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 64
A. MR. HOSHOWSKI: There's a bit to digest there, Ms. Graham. And without perhaps
further thinking this process through in terms of how AFUDC flows from the onset or its
creation all the way to this end point and how it's factored into the determination of our
various add-backs and deducts within the test period, I'll take your assertion as being
accurate subject to check. …
Transcript Volume 6, page 877, line 6 to page 878, line 24:
A. MR. HOSHOWSKI: Good morning. I just have a couple of transcript corrections I just wanted
to provide on the record for clarity. And that I would just like to, subsequent to that, address a
subject to check following a discussion on Friday that I had with Ms. Graham.
…..
The subject to check that I would like to discuss as contained in the transcripts, Volume
5, at page 813, this was a discussion that I was having with Ms. Graham on the topic of
AFUDC and the underlying tax treatment. The question posed to me by Ms. Graham
starts at line 13 of 812 of the transcripts, and it is as follows:
So based on our discussion, it appears that ATCO Electric adds AFUDC twice for the
purposes of adjusting income for tax -- sorry, twice for the purposes of adjusting income
for tax purposes: first when the amount of AFUDC is added to utility earnings before tax,
and second, on an annual basis for the portion of AFUDC that is being depreciated
through the life of an asset. However, ATCO Electric only deducts AFUDC once in the
year the cost's incurred, which creates a tax expense payable from which ATCO Electric
collects its revenue requirement. Is that right?"
So after reviewing the transcripts and reviewing our historical treatment of AFUDC, I
would disagree that it creates a tax payable, and the disagreement comes as the other
deduction occurs when depreciation expense is included in utility earnings before tax.
Thank you.”
270. In its argument, AET summarized its discussion with Commission counsel regarding the
treatment of AFUDC as follows:
AFUDC is included in the calculated total of utility earnings, before tax, to ensure that
there is no impact on utility earnings or revenue requirement from the corresponding tax
deduction, as AFUDC is a form of a non-cash capitalized interest and it is deductible for
income tax purposes. This ensures that the AFUDC deduction has a corresponding
addition to net the tax impact to zero, as AFUDC not collected when incurred, but rather
over the life of the asset when the project is included in Rate Base. Likewise, when
calculating future taxes, the revenue (or utility earnings before tax) directly attributable to
AFUDC is not a component of the future income tax calculations and, as such, the
AFUDC revenue line item is not included, even though it is identified as a temporary
item on Schedule 7-3. AET submits that this is not a new practice and has been applied
similarly in past revenue requirement calculations. [footnotes removed]226
271. Based on the discussion between the AET witness and Commission counsel, provided
above, the Commission has prepared an illustrative calculation of income tax using AET’s
current methodology for treatment of AFUDC:
226 Exhibit 22742-X0725, AET final argument, paragraph 165.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 65
Table 27. Calculation of income tax using AET’s current methodology for treatment of AFUDC, based on Mr. Hoshowski’s exchange with Commission counsel
Build In-service Total Yr-2 Yr-1 Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Revenue 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 246.2
Depreciation (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (246.2)
Net income - - - - - - - - - - - - -
AFUDC 123.1 123.1 - - - - - - - - - - 246.2
Utility earnings before tax
123.1 123.1 - - - - - - - - - - 246.2
Add/Deduct
Depreciation - - 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 246.2
Capital cost allowance - - - - - - - - - - - - -
AFUDC (123.1) (123.1) - - - - - - - - - - (246.2)
Taxable income - - 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 246.2
Current tax [(Taxable income * 15% federal tax rate) + (taxable income * 12% provincial tax rate)]
- - 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 66.5
Future income tax expense (Taxable income * -15% federal tax rate)
18.5 18.5 (3.7) (3.7) (3.7) (3.7) (3.7) (3.7) (3.7) (3.7) (3.7) (3.7) -
Assumptions used for calculations: Rate base = 246.2 AFUDC from ATCO Electric's originally proposed CWIP-in-rate base refund. 10-year asset for depreciation, no mid-year convention used for simplicity. Eight-year asset for tax deduction purposes (capital cost allowance), no mid-year used for simplicity. Revenue = the recovery of depreciation component in revenue requirement. WACC = 0% to remove impacts of return.
272. In its argument, AET stated that “AFUDC is included in the calculated total of utility
earnings, before tax, to ensure that there is no impact on utility earnings or revenue requirement
from the corresponding tax deduction, as AFUDC is a form of a non-cash capitalized interest and
it is deductible for income tax purposes.”227 The Commission has reflected this statement in the
“Build” columns of the Table 27.
273. As confirmed by the AET witness, AFUDC is included in the cost of a capitalized project
and, as a result, forms a portion of AET’s depreciation expense.228 AET, through its revenue
requirement, receives amounts to compensate it for this expense. These amounts have been
reflected in the “Revenue” and “Depreciation” lines in calculating the “Net Income” and “Utility
Earnings Before Tax” totals in Table 27.
274. Depreciation expense is subtracted from revenue to arrive at a net income for financial
reporting purposes. However, for the purposes of calculating a company’s income to determine
227 Exhibit 22742-X0725, AET final argument, paragraph 165. 228 Transcript, Volume 5, page 811, line 25 to page 812, line 12.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 66
its taxes payable, depreciation expense is not permitted to be deducted. Instead, the federal and
provincial governments permit a company to deduct a “capital cost allowance” for the purposes
of calculating taxable income. In Table 27 above, the Commission has added back AET’s
depreciation expense to arrive at the “Taxable Income” from which the federal and provincial tax
rates are then applied. As confirmed by the AET witness, amounts related to AFUDC do not
accumulate in the UCC pool. Therefore, a capital cost allowance deduction is not taken because
the AFUDC deduction has already been taken (as reflected in the “Build” columns).229
275. The Commission used the same information, as described above, but instead of adding
AFUDC to the “Utility Earnings Before Tax” and deducting AFUDC in the year the capitalized
interest was incurred (the “Build” period), the Commission assumed that the AFUDC amount
was added to the undepreciated capital cost (UCC) pool along with the rest of the project costs at
the time the asset was placed in service, and amortized over a theoretical eight-year period
(capital cost allowance). As demonstrated in Table 28 below, the addback of depreciation and
deduction of the capital cost allowance related to the AFUDC, over the life of the asset, results in
a current tax expense total of zero and a future income tax expense total of zero.
229 Transcript, Volume 5, page 809, line 8 to page 811, line 24.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 67
Table 28. Calculation of income tax if AFUDC was treated the same as other capital project costs when the asset was put into service
Build In-service
Total Yr-2 Yr-1 Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Revenue 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 246.2
Depreciation (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (246.2)
Net income - - - - - - - - - - - - -
AFUDC - - - - - - - - - - -
Utility earnings before tax
- - - - - - - - - - - - -
Add/Deduct
Depreciation - - 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 246.2
Capital cost allowance related to AFUDC
- - (30.8) (30.8) (30.8) (30.8) (30.8) (30.8) (30.8) (30.8) - - (246.2)
AFUDC - - - - - - - - - - -
Taxable income - - (6.2) (6.2) (6.2) (6.2) (6.2) (6.2) (6.2) (6.2) 24.6 24.6 -
Current tax [(Taxable income * 15% federal tax rate) + (Taxable income * 12% provincial tax rate)]
- - (1.7) (1.7) (1.7) (1.7) (1.7) (1.7) (1.7) (1.7) 6.6 6.6 -
Future income tax expense (Taxable income * -15% federal tax rate)
- - 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 (3.7) (3.7) -
Assumptions used for calculations: Rate base = 246.2 AFUDC from ATCO Electric's originally proposed CWIP-in-rate base refund. 10-year asset for depreciation, no mid-year convention used for simplicity. Eight-year asset for tax deduction purposes (capital cost allowance), no mid-year used for simplicity. Revenue = the recovery of depreciation component in revenue requirement. WACC = 0% to remove impacts of return.
276. The same outcome, where the total current tax and total future income tax expenses equal
zero as was the case in Table 28, can be similarly achieved with AET’s practice of deducting
AFUDC in the year the capitalized interest occurs, by removing the AFUDC amount that AET
adds to its “Utility Earnings Before Tax,” as demonstrated in Table 29 below:
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 68
Table 29. Calculation of income tax if AFUDC deduction was taken in year incurred but AFUDC not added to utility earnings before tax
Build In-service Total
Yr-2 Yr-1 Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10
Revenue 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 246.2
Depreciation (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (24.6) (246.2)
Net income - - - - - - - - - - - - -
AFUDC - - - - - - - - - - -
Utility earnings before tax - - - - - - - - - - - - -
Add/Deduct
Depreciation - - 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 246.2
Capital cost allowance - - - - -
AFUDC (123.1) (123.1) - - - - - - - - - - (246.2)
Taxable income (123.1) (123.1) 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 24.6 -
Current tax [(Taxable income * 15% federal tax rate) + (Taxable income * 12% provincial tax rate)]
(33.2) (33.2) 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 -
Future income tax expense (Taxable income * -15% federal tax rate)
18.5 18.5 (3.7) (3.7) (3.7) (3.7) (3.7) (3.7) (3.7) (3.7) (3.7) (3.7) -
Assumptions used for calculations: Rate base = 246.2 AFUDC from ATCO Electric's originally proposed CWIP-in-rate base refund. 10-year asset for depreciation, no mid-year convention used for simplicity. Eight-year asset for tax deduction purposes (capital cost allowance), no mid-year used for simplicity. Revenue = the recovery of depreciation component in revenue requirement. WACC = 0% to remove impacts of return.
277. It would appear from the explanation provided in paragraphs 268 and 269 above, and
based on the examples and calculations provided by the Commission in tables 27, 28 and 29, that
there may be an error in AET’s treatment of AFUDC for the purposes of calculating its income
tax expense.
Commission findings
278. In the CCA’s reply argument, it acknowledged that it had not reviewed AET’s method
for calculating AFUDC in its income taxes, and recommended that the Commission allow for
further review of AET’s accounting of AFUDC in its income taxes in the compliance filing.230
The Commission sees merit in the CCA’s request. AET is directed to demonstrate in its
compliance filing to this decision, using the information that is currently available on the record
of this proceeding, that its treatment of AFUDC in its calculation of income tax expense does not
involve either of the two potential errors described in paragraph 267 above.
230 Exhibit 22742-X0726, CCA reply argument, paragraphs 110-111.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 69
279. In its argument, AET stated that it has treated AFUDC similarly in the past.231 AET is
directed, in its compliance filing to this decision, to provide a proposal to correct any prior
AFUDC-related errors in its calculation of income taxes, which were subsequently collected
through revenue requirement in prior years.
9.2 Income tax deferral accounts
280. AET requested continuance of two income tax deferral accounts - statutory tax rates and
deductions of deferral for tax purposes. AET requested discontinuance of two income tax
deferral accounts - capital repair costs and deductible capital costs.
281. In Decision 2010-189,232 the Commission considered the following criteria when
evaluating the need for a deferral account:
materiality of the forecast amounts
uncertainty regarding the accuracy and ability to forecast the amounts
whether or not the factors affecting the forecasts are beyond a utility’s control, and
whether or not the utility is typically at risk with respect to the forecast amounts.233
282. In addition, the Commission has also considered a symmetry factor, as described below:
In another Board decision, also referenced in Decision 2003-100, the Board, when
examining the merits of an application for a deferral account on the facts of that
proceeding, took the view that “deferral accounts should not be for the sole benefit of
either the company or the customers.” Deferral accounts, rather, should “provide a degree
of protection to both the Company and the customers from circumstances beyond their
control,” and hence “[s]ymmetry must exist between costs and benefits for both the
Company and its customers.” The Board also noted that it expected that “the individual
mechanisms involved in the use of each deferral account should be applied in a consistent
and fair manner in both test years and non-test years”.234
283. In Decision 22570-D01-2018, the 2018 Generic Cost of Capital decision, the
Commission commented on the evaluation of income tax deferral accounts, as follows:
The Commission finds that the five criteria listed by the ATCO Utilities should form the
basis upon which any deferral accounts for income taxes for the transmission utilities
should be decided. In addition, the Commission considers that the symmetry factor
detailed in paragraphs 71-74 of Decision 2010-189 should also be considered, as
“symmetry must exist between costs and benefits for both the Company and its
customers.” However, the Commission will not make any specific findings with respect
to income tax deferral accounts for the transmission utilities in this decision. The
Commission considers that determinations with respect to tax deferral accounts for the
transmission utilities are best made on the basis of a utility’s specific circumstances and
on a case-by-case basis, and considering the criteria articulated in this decision.235
231 Exhibit 22742-X0725, AET final argument, paragraph 165. 232 Decision 2010-189: ATCO Utilities, Pension Common Matters, Proceeding 226, Application 1605254-1,
April 30, 2010. 233 Decision 2010-189, paragraph 72. 234 Decision 2010-189, paragraph 73. 235 Decision 22570-D01-2018: 2018 Generic Cost of Capital, Proceeding 22570, August 2, 2018, paragraph 116.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 70
284. The Commission will address AET’s deferral accounts in the subsections that follow in
accordance with the above deferral account test.
9.2.1 Deferral accounts AET is seeking to continue
9.2.1.1 Statutory rates deferral account for income tax
285. In testimony, Mr. Hoshowski confirmed that the intention of this deferral account is
purely to account for the statutory income tax rates levied both at the provincial and the federal
level.236 As shown in Table 2 above, AET used the statutory tax rates of 15 per cent in both 2018
and 2019 for federal income tax and 12 per cent for provincial income tax. AET stated that it
would apply carrying costs for income tax to adjustments recorded in the deferral account, in
accordance with Rule 023.237 AET requested that it be allowed to continue the statutory rate
deferral account, as income tax rates are subject to change.238
Commission findings
286. The Commission accepts AET’s submissions that the statutory rates deferral account for
federal income tax and provincial income tax, are subject to change, are beyond the utility’s
control, the forecast amounts can be material, there is uncertainty regarding the ability to forecast
the amounts and the utility is at risk for forecast income tax amounts. Also, the symmetry test is
satisfied because this account provides a degree of protection to both the utility and the
customers from circumstances beyond their control i.e., statutory tax rates. For these reasons, the
Commission approves the continuation of AET’s statutory rates deferral account.
9.2.1.2 Deduction of deferrals for income taxes
287. In its application, AET described the genesis of the deduction of deferrals for income
taxes:
The deducting of deferrals for income tax purposes stems from Commission Decision
2001-93 on the 2000 Pool Price Deferral Accounts proceeding. In that decision, the
Commission directed ATCO Electric to calculate the loss carry forward and the effect on
income tax payable in 2001 to 2002 taking into account the collection of revenues in
2002. That decision, in essence, instructed ATCO Electric to pursue the tax treatment of
deferrals so that any deferrals not collected during the year could be used as an income
tax deduction. Once these deferrals were collected in future years, they would be added to
taxable income. As a result of deducting the 2000 deferrals for income tax purposes, AET
now is required to apply this tax treatment to deferrals on an ongoing basis.239
288. No party objected to the continuation of this deferral account.
Commission findings
289. The Commission agrees with AET that this deferral account is still required. This account
continues to meet the five deferral account criteria specified in Decision 2010-189. Accordingly,
the Commission approves AET's request to continue the deduction of deferral for income taxes
account.
236 Transcript, Volume 5, page 806 line 20 to page 807 line 7. 237 Exhibit 22742-X0001.02, updated application, paragraph 254. 238 Exhibit 22742-X0001.02, updated application, paragraph 253. 239 Exhibit 22742-X0001.02, updated application, paragraph 255.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 71
9.2.2 Deferral accounts AET is seeking to discontinue
290. In its application, AET claimed that the probability of significant benefit accruing to, or
significant harm befalling, itself or its customers from the removal of two deferral accounts (one
for capital repair costs and one for deductible capital costs), was low. Therefore, it requested that
these deferral accounts be discontinued.240 Both of these accounts adjust for capital costs; capital
repair costs are a subset of deductible capital costs. Because these accounts are interrelated, the
Commission has described and included argument on these accounts separately in the
subsections below but the Commission findings jointly address these accounts.
9.2.2.1 Capital repair costs deferral account
291. In terms of AET’s deferral account for capital repair costs, AET explained that capital
repair costs are capital expenditures that are permitted to be deducted in the year they are
incurred.241 The capital repair cost deferral account refunds or collects the differences between
the capital repair amounts forecast to be claimed, as tax deductions, in the test period and the
actual amounts claimed, as tax deductions.242
292. AET prepared the following breakdown of historical and forecast capital repair costs:243
Table 30. 2014-2017 actual and 2018-2019 forecast capital repair costs
Line 2014 2015 2016 2017 2018 2019
No. Type of capital repair Actual Actual Actual Actual Forecast Forecast
($ Million)
1 Capital Maintenance
2 Life Extension 0 1.3 0.7 6.2 2.6 2.8
3 Replacement - - - - 0.5 0.3
4 Safety/Environment 4.4 3.3 1.9 1.9 4.1 0.4
5 Mitigate Equipment Problems - - - - - -
6 Pole Treatment 0.3 0.5 0.1 0.1 - -
7 Cathodic Protection 0 0.1 - 0 - -
8 Study 0 0 2.4 0.1 0.2 0.2
9 Total Capital Repair Costs 4.7 5.1 5.1 8.3 7.4 3.7
Source: Exhibit 22742-X0001.02, updated application, paragraph 263, Table 7.2 – Capital Repair Costs.
293. AET stated that the prior four years of true-up balances were immaterial. There was a
2014 refund of $100,000, a 2015 refund of $700,000, a 2016 refund of $200,000 and a 2017
refund of $800,000.244
240 Exhibit 22742-X0001.02, updated application, paragraph 265. 241 As outlined in Rainbow Pipe Line Co v Canada, [1999] TCJ No 604 and Rainbow Pipe Line v Canada, [2002]
FCJ No 92. 242 Exhibit 22742-X0001.02, updated application, paragraph 262. 243 Exhibit 22742-X0001.02, updated application, paragraph 263. 244 Exhibit 22742-X0001.02, updated application, paragraph 264.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 72
294. Bema noted that the total refund to customers from 2014-2017 was a cumulative $1.8
million and recommended that the deferral account treatment for capital repair costs be
continued. Bema supported the continuance of this deferral account based on the following:
(i) AET’s historical forecasting accuracy for these costs is poor and suggests that AET has
minimal control over the actual costs that are incurred;
(ii) In the last four years, there have been consistent refunds to customers, which suggests
that removing the deferral account may result in increased risks of ratepayers paying a
greater amount of costs than are truly required;
(iii) AET’s 2018 and 2019 forecast of costs do not appear reasonable in comparison to the
actual costs incurred from 2014 to 2017, with the 2019 forecast particularly
appearing to be understated. This fact supports the conclusion that continued
uncertainty exists in the forecast costs; and
(iv) The refunds under the deferral account have not been immaterial.245
295. AET stated that during the past ten years, the capital repair cost deferral account has
resulted in $1.0 million being collected from customers, which works out to $0.1 million per year
on average. AET pointed out that its capital repair cost income tax deductions represent an
impact on revenue requirement of $1.3 million and $0.7 million for the 2018- and 2019 test
years, respectively. AET stated that the revenue requirement impact of its capital repair costs, as
a percentage of total forecast revenue requirement, is substantially lower than the equivalent
percentages for fuel that led to the removal of its fuel deferral account in Decision 2013-358.246
AET argued that it fully justified its request to discontinue the “Capital Repair Costs” deferral
account as the amounts are immaterial and the amounts can be forecast with certainty.
296. The CCA referred to Bema’s revised position contained in its response to a Commission
IR247 that variances in the approved versus actual costs are likely due less to AET’s lack of
control and due more to poor forecasting on the part of AET. The CCA stated that “if the
Commission removes the deferral account treatment, the forecast for capital repair costs, in 2018
and 2019, should be at least equal to the 2017 capital repair costs of $8.3M or equal to 9.1% (the
2017 percentage of capital maintenance costs) of the 2018 and 2019 forecast capital maintenance
dollars, which would be $9.3M and $9.7M.”248
9.2.2.2 Income tax deductible capital costs deferral account
297. AET explained that the income tax deductible capital cost deferral account is in place to
address any changes in how various items (which are listed below) are treated in the test period
245 Exhibit 22742-X0592, paragraphs 106-112. 246 Decision 2013-358: ATCO Electric Ltd. 2013-2014 Transmission General Tariff Application, Application
1608610-1 Proceeding 1989, September 24, 2013, paragraph 38, where the forecast fuel costs representing
approximately 1.3 per cent of the total forecast revenue requirement and in 2014 the corresponding figure is
approximately 1.1 per cent, where these percentages were not found to be significant. 247 Exhibit 22742-X0612, CCA-AUC-2018DEC19-007(b), PDF page 18. 248 Exhibit 22742-X0722, CCA final argument, paragraph 98.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 73
as a result of a federal tax filing with the Canada Revenue Agency (CRA). Any future changes
would be captured in this deferral account.249
298. The items that are currently included in this deferral account are:
Gross Additions;
AFUDC;
Increase in Extension Contributions;
Depreciation on Automotive Equipment;
Meals and Expenses;
Engineering, supervision and general (ES&G) Running Costs;
Stock Handling Costs;
Easement Costs (Rights of Way);
Capital Repair Costs;
Isolated Overhauls Capitalized; and
Dismantling Costs (Removal and Abandonment).250
299. In justifying its request for the removal of this deferral account, AET stated, “Since the
inception of this deferral account in 2009, no deferral balances have arisen over the period, up to
and including 2017 as there have been no changes in how the above referenced items were
treated from those as advanced in the various approved test periods.”251 AET further stated that
given there has been no change in the treatment of these items by AET and no changes are
anticipated in the test period, it was seeking to discontinue this deferral account.
300. Bema recommended that the Commission deny AET’s request to discontinue the deferral
account for deductible capital costs. Bema stated that AET “cannot control whether the
Government of Canada implements changes or whether the CRA’s interpretation of the tax
treatments changes over time.”252 253
Commission findings
301. The capital repair costs deferral account is a subset of the income tax deductible capital
costs deferral account, and the Commission considers that both deferral accounts are still
required. In Decision 2009-215,254 the Commission made the following determinations:
67. AE’s current Capital Repair Cost deferral account, referenced in AE’s Argument,
captures part of a broader category of costs which may be capitalized for accounting
purposes but deducted as an expense for income tax purposes (referred to hereinafter as
249 Exhibit 22742-X0001.02, updated application, paragraph 259. 250 Exhibit 22742-X0001.02, updated application, paragraph 260. 251 Exhibit 22742-X0001.02, updated application, paragraph 261. 252 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 144. 253 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraphs 143-146. 254 Decision 2009-215: ATCO Electric Ltd., 2009-2010 General Tariff Application – Regulatory Treatment of
Income Tax Refund, Proceeding 86, Application 1578371-1, November 12, 2009.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 74
“Income Tax Deductible Capital Costs”). The Rainbow Pipeline and Canderel decisions
addressed examples of costs that fall within this broader category. Since the flow-through
income tax method is used by AE, this requires AE to evaluate these types of potential
deductions.
68. The Commission notes the conflicting incentives and imbalance that arise
between shareholders and customers when customer rates are finalized but income tax
reassessments and refunds may be requested and received by a utility outside of the test
years. While the income tax legislation and its regulations allow for retroactive changes
to be made in the calculation of income tax expense resulting in an income tax refund to
the benefit of shareholders, the Commission must adhere to the principle against
retroactive ratemaking, the prospectivity principle and the principle of regulatory
certainty.
69. The Commission considers that, without an expansion of the scope of AE’s
Capital Repair Cost deferral account, similar circumstances may arise in the test years
and in the future wherein capitalized costs may be permitted to be expensed for income
tax purposes, similar to the circumstances in which the Additional Deductions were
taken, and with a similar result…
70. The Commission finds that the use of the Income Tax Deductible Capital Cost
deferral account will allow AE to continue to pursue income tax deductions for use with
the flow-through income tax method and mitigate the risk that the CRA might disallow
these deductions. As was recommended by the UCA, the Income Tax Deductible Capital
Cost deferral account will address substantive changes for this broader group of income
tax deductions while not delaying their implementation until the next GTA application.
ATCO Electric Ltd. amend the scope and change the name of its existing Capital
Repair.255 [footnotes removed]
302. In that decision, the Commission also ordered ATCO Electric Ltd. to amend the scope
and change the name of its existing capital repair cost deferral account to include all income tax
deductible capital costs, effective January 1, 2009.256
303. During the hearing in the current proceeding, Mr. Hoshowski provided testimony
regarding income tax legislation and its regulations allowing retroactive changes to be made in
the calculation of income tax expense and the logistics associated with retroactive adjustments:
A. MR. HOSHOWSKI: Yes, that provision remains unchanged with the ability of the
taxable entity to go back and file or refile a tax return for a certain period with the
underlying consideration for a reassessment of certain line items.
Q. And do you know how many years you can go back?
A. MR. HOSHOWSKI: My understanding is seven, subject to check.
Q. Do conflicting incentives and imbalances arise between shareholders and customers
when customer rates are finalized but income tax reassessments and refunds may be
requested and received by a utility outside of the test years?
A. MR. HOSHOWSKI: Certainly those were the considerations before the Commission
previously, which brought the inception of this deductible capital cost deferral account
255 Decision 2009-215, paragraphs 67-70. 256 Decision 2009-215, paragraphs 72.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 75
back in the 2009 period and issued under AUC Decision 2009-215. It has been our
experience over this timeframe that ATCO Electric, subject to check, has not sought
reassessments with regards to the filed positions for income tax deductions since that
deferral account arose.
Q. So do those conflicting incentive and imbalances still remain, or are you saying it just
hasn't -- because it hasn't happened since the deferrals were put in place, those are
minimized?
A. MR. HOSHOWSKI: So, yes, as we -- as we sit here today, there hasn't been anything
in terms of us going back as a result of new findings with regards to the various
deductions that we take for tax purposes. And I'm not aware of anything going forward.
Certainly in terms of the context of the test period that's before us, once again, I'm not
aware of any changes in positions or new tax rulings that are out there with regards to the
deductions that we have. Once -- or if a case arises where there is a new deduction that
arises, certainly on a go-forward basis, we would take that deduction and reflect that in
our income tax for that current period and then move forward, carrying forward with that
same deduction into future test periods. So to the extent that, yes, a utility could find new
deductions or new deductions arise in the test period, the utility would be incented to find
those with, of course, the future benefits of that accruing to -- accruing to customers
thereafter.257
304. Part of the Commission’s rationale for implementing the income tax deductible capital
cost deferral account, which includes capital repair costs, was based on concerns relating to
conflicting incentives and imbalances that arise between shareholders and customers when
customer rates are finalized but income tax reassessments and refunds may be requested and
received by a utility outside of the test years. The Commission is not persuaded that the historical
trend of deferral account balances should determine whether this account is still required. As
confirmed by Mr. Hoshowski, the status quo does not indicate that there will not be changes “in
positions or new tax rulings” regarding deductions. Therefore, it is not unreasonable to expect
that there could be changes in deductions or reassessments that could affect up to seven years of
returns. There could be a material difference between a prior period’s forecast and the actual
amounts if a new tax ruling or assessment were to occur. The Commission, therefore, finds that
these deferral accounts are still required and AET’s request to discontinue these deferral
accounts is denied.
305. The Commission approves, subject to directions issued in other sections of this decision,
the forecast amounts AET included in each of these deferral accounts for the test years.
10 Taxes other than income tax
306. AET forecast expenses related to taxes other than income tax (other taxes) in the amounts
of $47.1 million and $50.2 million for the years 2018 and 2019, respectively.
307. In its application, AET identified the sections of the Alberta Municipal Government Act
under which its property is assessed. Tax assessments must be reported to Alberta Municipal
Affairs as of December 31 each year. AET also described the methods and guidelines used to
arrive at linear property assessed values for various facilities e.g., machinery and equipment for
257 Transcript, Volume 5, page 813, line 6 to page 815, line 8.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 76
substations and communications. After the assessments are reviewed by Municipal Affairs, AET
reviews the categories of linear assessments for completeness. Once this information is
disseminated by Alberta Municipal Affairs to the municipalities, the municipalities issue the tax
notices for payment.
308. Historical actual and forecast amounts are summarized in the following table:
Table 31. AET – 2015-2019 taxes other than income tax
2015 Actual
2015 Approved
2016 Actual
2016 Approved
2017 Actual
2017 Approved
2018 Forecast
2019 Forecast
($ million)
33.7 33.7 37.8 39.0 45.7 52.0 47.1 50.2
Source: Exhibit 22742-X0002.04, MFR Schedule 5-1.
309. AET stated that expenses for other taxes, primarily related to property tax, increased
during the period 2015-2019 due to inflation and growth in its transmission system. However,
2017 property taxes were lower than approved amounts because of a new regulated rate for
direct current (DC) lines that resulted in lower assessment values for new transmission lines and
substations.258
310. The CCA stated that it did not consider any adjustments were necessary for AET’s
forecasts of other taxes. However, the CCA noted that costs for other taxes have steadily
increased since 2013. For AET’s next GTA, the CCA recommended that the Commission direct
AET to identify potential incentives and cost saving measures that could be implemented going
forward to mitigate the overall costs for other taxes.259
311. The CCA pointed to a commitment AltaLink Management, Inc. made in its 2017-2018
negotiated settlement agreement to “explore if there are acceptable ways to reduce the amount of
property taxes that it is required to pay and to file the results of its review in the 2019-2020 GTA
application.”260
312. AET outlined its ongoing cost saving strategies261 to manage taxes other than income
taxes it is paying to municipalities as follows:
Reviewing annual assessments for accuracy and appealing where appropriate.
Reporting non-assessable costs for new substation and communication equipment.
Evaluating the need to renegotiate property tax amounts (which was observed by
AET for other oil and gas companies as having a very low likelihood of success).
258 Exhibit 22742-X0001.02, updated application, paragraphs 66 and 233-237. 259 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraphs 307-308. 260 Exhibit 22742-X0612, CCA-AUC-2018DEC19-004, PDF pages 10-11, which referenced Exhibit 21341-
X0210, AML 2017-18 GTA Negotiated Settlement Agreement, paragraph 16, PDF page 14. 261 Exhibit 22742-X0618, AET rebuttal evidence, PDF pages 58-59.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 77
313. AET concluded that since it has established measures in place that it uses on an ongoing
basis to mitigate taxes other than income taxes, there was no need for a direction from the
Commission to identify further tax mitigation measures in AET’s next GTA.
314. In argument, the CCA pointed to an exchange between Commission counsel and the
Bema witness that explored other cost-saving practices, such as the timing of when an asset goes
into service as that can affect the year in which the asset is first included in the valuation for
property taxes.262
315. The CCA maintained its recommendation that, since property tax represents
approximately 30 per cent of AET’s applied for operating expenses over the test years, the
Commission should direct AET to “identify potential cost savings measures that have been and
those that may be able to be implemented going forward.”263
Commission findings
316. AET has identified the strategies it uses on an ongoing basis to evaluate the
reasonableness of both its assessed property values and taxes other than income tax expense.
Other taxes payable are difficult to forecast, in part, because they are not entirely within the
control of AET. For these reasons, Bema's recommendation that AET report in its next GTA on
future tax mitigation measures it is considering implementing is unnecessary at this time.
Nonetheless, AET’s responsibility to report and explain variances between actual and forecast
other taxes remains unchanged as this information is very useful to the Commission and
interveners. No change to AET's filing for GTA purposes is required.
317. The Commission, however, remains interested in a specific scenario raised by the Bema
witness during the oral hearing. The scenario deals with when an asset is placed into utility
service and the corresponding impact to the asset valuation used for property tax purposes.
Accordingly, AET is directed to explore the timing of the capitalization of its assets as an
acceptable method to potentially reduce the amount of property taxes it would otherwise be
required to pay, and to report, at the time of its next GTA, whether such timing can or should be
taken into account on a go-forward basis.
318. AET’s taxes other than income taxes are approved as filed, subject to any applicable
findings and directions elsewhere in this decision.
11 Rate base
319. In the application, AET explained that its capital forecast for the 2018-2019 test period is
informed by the AESO’s Long-Term Transmission Plan published in late December 2017. This
capital forecast includes capital maintenance plans due to aging infrastructure, growth within the
service area, and customer connections determined through direct customer interaction.
Customer projects to support interconnection with renewable generation are also included in the
forecast.264
262 Exhibit 22742-X0722, CCA final argument, PDF pages 85-86. 263 Exhibit 22742-X0722, CCA final argument, PDF page 86. 264 Exhibit 22742-X0001.02, updated application, PDF page 322.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 78
320. Large system capital projects have been identified as part of the AESO’s Long-Term
Transmission Plan and are included in the forecast based on the AESO’s current requirements
and directions. These projects are in the early stages of development and AET’s capital
expenditures forecast for the 2018-2019 test period mainly covers costs associated with
completing the facility applications, detailed engineering and procurement of materials. To
accommodate the priorities that have been identified by the AESO, the Central East Transfer Out
Plan interconnection from the Red Deer area to Tinchebray has taken precedence over the
Grande Prairie area reinforcement plan in the test period.
321. A number of customer renewable projects including large scale solar, wind, and battery
storage development projects, are proposed within AET’s service area. These renewable projects
have typically gone through an initial estimation stage with customers to provide indicative
pricing to assist in narrowing the scope of alternatives. Most of these projects are at an early
stage of development.
322. AET stated that it applies a consistent, process driven approach to the management of
capital projects, both direct assigned and capital maintenance. This approach includes continuous
improvement of processes to ensure that learnings from existing projects, regulatory
advancements and changes to AESO rules are implemented within projects consistently and
effectively. In accordance with minimum filing requirements (MFR), AET provided business
cases in support of its capital forecast. These business cases are accompanied by financial
analyses where competing alternatives are being evaluated based on their relative economic
merits.
11.1 Direct assigned capital projects
323. AET detailed its forecast direct assigned capital project expenditures and additions
through the test period in the application.265 AET explained that, for direct assigned projects, the
AESO is responsible for submitting a Need Identification Document (NID) to the AUC for
approval. To assist in the review of forecast expenditures for direct assigned projects in this
application, business cases were provided for direct assigned capital projects over $500,000.
These business cases provide information regarding the current status of the project, including
the AESO’s NID submission to the AUC. A schedule of project milestone dates and capital
expenditure forecasts for direct assigned projects over $5 million was also provided.266
324. AET further explained that the direct assigned capital expenditure forecast consists of
distinct project types including system, customer, and renewable projects. Renewable projects
are made up of wind, solar and battery storage customer requests in the project queue located
within AET’s service territory. The forecast capital expenditures for direct assigned capital
projects increased from 2017 through the test period due to delays in the Jasper Interconnection
project, and to expected expenditures on several large projects that are in progress, with
construction activities scheduled through the test period.
325. In argument, AET stated that direct assigned capital forecast expenditures are $131.3
million in 2018 and $135.6 million in 2019. Although these expenditures are lower than during
265 Exhibit 22742-X0001.02, updated application, PDF page 363. 266 Exhibit 22742-X0009, Attachment 10.2, Schedule of DA Projects.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 79
the height of system expansion, AET nonetheless acknowledged that they are material in nature
and higher than actual expenditures in 2016 and 2017.267
326. AET explained that the most significant expenditures through the test period are
associated with major transmission system development identified by the AESO: Project 54904:
Jasper Transmission Interconnection; and Project 55737: Thickwood Hills Transmission
Development.
327. With the exception of the Thickwood project, which is addressed elsewhere by the
Commission in this decision, AET maintained that the balance of the direct assigned capital
projects included in AET's forecast were not subject to material questioning. AET stated that it
filed business cases268 to support each of these direct assigned projects, in accordance with the
Commission’s direction 92 in Decision 2013-358. AET submitted that its forecasts for direct
assigned capital project expenditures and additions for the test period should be approved, as
filed.
Commission findings
328. The Commission notes that AET has filed numerous exhibits supporting the direct
assigned projects under review in this application. These exhibits include, among other things,
information relating to the NID, facility application, PPS (Proposal to Provide Service) estimate,
monthly reports and customer contribution decisions for the relevant projects.269 AET's forecast
was also supported by correspondence from the AESO.270
329. Direct assigned capital projects are subject to a deferral account. Consequently, the actual
expenditures on these projects will be subject to a detailed prudence review in future direct
assigned capital deferral account (DACDA) applications prior to final acceptance of these costs.
330. Given the above evidence, the Commission approves AET’s forecast with respect to
direct assigned capital projects.
11.2 Transmission capital maintenance
331. AET stated that the transmission capital maintenance (TCM) program supports asset
renewal activities, which are funded from capital investment. The TCM program is designed
to:271
• Manage transmission assets in accordance with life cycle asset strategies; and
• Prioritize asset replacement and maintenance requirements through capital investment.
332. TCM activities range from small asset improvements to major asset replacements and
major facility rebuilds. AET’s forecast expenditures and additions shown in Table 32 below
include the TCM and Isolated Generation programs:
267 Exhibit 22742-X0725, AET final argument, page 88. 268 Exhibit 22742-X0013.02. 269 Exhibits 22742-X0014 to 22742-X0170. 270 Exhibit 22742-X0001.02, updated application, PDF pages 460-461. 271 Exhibit 22742-X0001.02, updated application, PDF page 328.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 80
Table 32. TCM and isolated generation forecast expenditures and additions
2015 Actuals 2016 Actuals 2017 Actuals 2018 Test period 2019 Test period
($ million)
Expenditures 99.2 113.5 101.0 109.7 113.47
Additions 105.0 93.3 123.9 113.3 123.47
Source: Exhibit 22742-X0001.02, updated application, Table 10.2.
333. AET explained that it used an asset management framework, which is aligned with the
ISO 55000 international standard for asset management, to ensure a holistic and effective TCM
program. This approach reviews asset status and performance through its entire life cycle from
cradle to grave, enabling AET to consider the trade-off between existing risks, performance
(reliability) and costs. The asset management framework enables AET to better refine and focus
required TCM activities.272
334. AET stated that the major drivers for TCM projects can be classified into the following
four primary groupings:
Safety/Environment: This project driver relates to managing hazards and risks to
employees, the general public and the environment;
Regulatory: This driver enables AET to meet regulatory requirements. These regulatory
requirements are often intended to protect public safety or preserve the integrity of the
electric system;
Technical: This driver enables AET to manage asset risks. The risks could arise from
reliability, asset condition, asset compatibility issues, capacity increase, performance
improvement and emergency restoration; and
Productivity: This driver relates to projects that enhance productivity or provide
economic savings.
335. AET explained that it is facing a growing stock of aging assets. It further explained that
as part of its asset management program, an asset management framework was developed to
better manage challenges with the aging fleet of assets, including safety, regulatory and
operational needs. The framework utilizes inputs, such as asset condition, performance, system
impact, load flow studies and the AESO Long-Term Plan, to develop a risk-based, prioritized
short and long-term forecast for AET’s TCM program.273
336. According to AET, at a high level, given the volume of aging transmission assets and
asset renewal needs, its Table 10.4274 (reproduced below) showed stable renewal rates for a
selection of key transmission assets. AET submitted that this demonstrated that it is appropriately
using its asset management framework to target asset renewals, based on risk, and that these
renewal rates are reasonable and sustainable.
272 Exhibit 22742-X0001.02, updated application, PDF page 331. 273 Exhibit 22742-X0001.02, updated application, PDF pages 332-334. 274 Exhibit 22742-X0001.02, updated application, PDF page 335.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 81
Table 33. Snapshot of AET assets and renewal forecast
Transformer 72-240 kV breaker
Transmission line
Protection relays
Telecom Tower
Automation & monitoring
Control building
RTU PLC
Inventory
Inventory 252 693 11,004
km 3,553 157 113 114 194
Age
Life expectancy (LE) in years
40-45 35-50 55-80 20-35 45 15 15 35
% at or above LE
16% 9% 8% 8% 3% 4% 37% 13%
At or within 5 years of LE
25% 15% 14% 21% 6% 19% 40% 26%
At or within 10 years of LE
33% 20% 27% 37% 9% 58% 100% 38%
Forecast conclusions
10-year renewal rate baseline
5/yr 10/yr 150 km/yr 175/yr 3/yr 12-20
/yr 12-20 /yr 4/yr
2018-2019 (2 year) TCM program renewal volume
10 replacements/ refurbishments (7 to be retired)
16 replacements, 2 new additions (4 to be retired)
93 km (rebuild project
2018-2025)
252 (multiple
relays to be replaced
with single devices)
4 11 16
4 replacements,
4 major refurbishment
s
Source: Exhibit 22742-X0001.02, updated application, PDF page 319..
337. AET’s actual/forecast TCM expenditures and additions for the 2015-2017 period, as well
as the forecast for 2018-2019 were shown in Table 10.6 of the application.275 Details with respect
to the forecast were provided in related sections as well as in the business cases provided in
appendices.276
338. AET stated that it had substantially completed the capital maintenance work forecast that
was approved in Decision 20272-D01-2016. In this application, AET sought approval of the
actual capital additions in 2015-17 to be included in the 2018 opening rate base. Consistent with
paragraph 872 of Decision 20272-D01-2016, AET provided business cases for any projects
completed in 2015-2017 with forecast costs over $500,000 which were not contemplated in the
2015-2017 GTA. As well, consistent with paragraph 873 of Decision 20272-D01-2016, AET
provided an analysis in this application of the variance between the forecast capital additions
approved in the 2015-2017 GTA and the 2015-16 actual and 2017 updated forecast capital
additions.277
275 Exhibit 22742-X0001.02, updated application, PDF pages 343-344. 276 Exhibits 22742-X0171 and 22742-X0172. 277 Exhibit 22742-X0001.02, updated application, PDF pages 398-430, Appendix 10.A.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 82
339. The CCA did not comment on AET’s forecast TCM program in its intervener evidence.
However, it did express concerns with respect to the Thickwood project and the Kearl line
relocation, both of which are dealt with elsewhere in this decision.
340. In argument, the CCA noted that it had issued several information requests to AET about
its forecast costs. After reviewing AET’s responses to those requests, the CCA advised that it
considered the record to be sufficient for the Commission to rule on the reasonableness of AET’s
applied for capital maintenance expenditures.
341. In its argument, AET stated that it was requesting approval of the actual non-direct
assigned capital additions in 2015-17 to be included in its 2018 opening rate base. AET noted
that it had provided detailed variance explanations in its application for the projects contributing
to the $20.0 million variance.278
342. AET further noted that none of the interveners presented any evidence to refute the
factual drivers for AET's TCM program or the risks to system safety and reliability that the
forecast TCM program is intended to address. AET's TCM program was also subject to little
questioning at the hearing. AET supplied additional information respecting the various sub-
programs in further support of its forecast.279
343. Interveners submitted no evidence with respect to AET’s TCM forecast.
Commission findings
344. Concerns raised with the Thickwood and Kearl line projects are addressed in
sections 11.4 and 11.5 of this decision.
345. AET discussed and supported its TCM forecast in the application280 through numerous
business cases,281 as well as in response to numerous information requests submitted by both the
interveners and the Commission. In considering and reviewing this evidence, the Commission
finds AET’s TCM forecast to be reasonable and it is approved.
346. In its next GTA, however, AET is directed to file variance analyses reflecting the actual
expenditures, explanations for variance from forecast and the current status of projects not
completed. As previously directed in Decision 20272-D01-2016,282 AET is also directed to file
business cases, at the time of filing its next GTA, for projects with a forecast value greater than
$500,000 that are planned to be completed in the test period but not forecast in the current
application.
347. The Commission also examined the proposed adjustments to opening rate base. AET
supplied variance analyses in the application283 as well as further detail in the business cases.284
278 Exhibit 22742-X0725, AET final argument, PDF page 62 refers to 22742-X0001, Table 10.14, pages 357-359
and Appendix 10.A, pages 398-429. 279 Exhibit 22742-X0725, AET final argument, PDF pages 68-84. 280 Exhibit 22742-X0001, PDF pages 327-362. 281 Exhibit 22742-X0171. 282 Decision 20272-D01-2016, paragraph 872. 283 Exhibit 22742-X0001.02, updated application, PDF pages 358-362 and 397-428. 284 Exhibit 22742-X0171.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 83
The Commission considers this evidence to be persuasive and AET’s proposed adjustments to
opening rate base are approved.
11.3 General property and equipment
348. AET explained that general property and equipment (GP&E) consists of software, tools,
equipment, vehicles and building capital projects necessary for AET to support safe and reliable
transmission service. GP&E is grouped into two categories, GP&E-Software285 and GP&E-
Other,286 which were detailed in the application.
349. AET’s forecast expenditures for GP&E-Other consisted of:
Direct general property, plant and equipment (PP&E), which is further broken down as:
o tools, instruments and equipment
o transportation equipment
Land, buildings and structures.
350. Tools, instruments and equipment include the replacement or addition of items required
for staff to complete their assigned tasks safely and effectively. As discussed in the 2015-2017
GTA compliance filing,287 AET’s forecast for the 2018-2019 test period reflects the 2015 and
2018 workforce reductions since tools, instruments and equipment for employees affected by
those workforce reductions were returned to stores. AET subsequently redistributed these items
as required by utilizing stores and reducing purchases going forward.288
351. Transportation equipment includes the normal replacement of vehicles and heavy
equipment as units reach end-of-life. Replacements of vehicles and heavy equipment are based
on mileage, condition and the age of the vehicle. Similar to the 2018-2019 forecast for tools,
instruments and equipment, AET’s 2018-2019 transportation equipment forecast reflects the
2015 and 2018 workforce reductions.289 Vehicles for employees affected by 2015 workforce
reductions were returned and inventoried. AET subsequently redistributed these items as
required by utilizing the inventoried assets and reducing purchases going forward. While, in
most cases, units returned from the 2015 workforce reduction were used as replacements for
backfills, it was determined in 2017 that vehicles which were not suitable for backfill
replacements or for which repairs were not financially reasonable would be sold at auction.
Vehicles for employees affected by 2018 workforce reductions were returned and inventoried.
AET indicated that it will subsequently redistribute these items, on an as-required basis, by
utilizing inventoried assets and reducing purchases going forward.290
352. With respect to the GP&E-other portion of its GP&E forecast, AET noted that it had filed
business cases for tools and equipment, transportation equipment and lands, buildings and
structures.291
285 Exhibit 22742-X0001.02, updated application, PDF page 380. 286 Exhibit 22742-X0001.02, updated application, PDF page 386. 287 Exhibit 22050-X0143, paragraph 28. 288 Exhibit 22742-X0001.02, updated application, PDF page 387. 289 Exhibit 22742-X0001.02, updated application, PDF page 387. 290 Exhibit 22742-X0001.02, updated application, PDF page 387. 291 Exhibit 22742-X0171.03.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 84
353. AET stated that it had substantially completed the GP&E capital work forecast approved
in the 2015-2017 GTA and was seeking approval for the actual capital additions in 2015-2017 to
be included in the 2018 opening rate base. Consistent with paragraph 872 of Decision 20272-
D01-2016, AET provided business cases for any projects completed in 2015-2017 with costs
over $500,000 which were not contemplated in the 2015-2017 GTA.292 As well, consistent with
paragraph 873 of Decision 20272-D01-2016, AET provided an analysis of the variance between
the forecast capital additions approved in the 2015-2017 GTA and the 2015-2016 actual and
2017 updated forecast capital additions.293
354. In its argument with respect to the GP&E opening rate base, AET noted an error in Table
10.B.2294 of the application. The 2015-2017 actuals in that table are expenditures, as opposed to
actual software additions.295 For clarity, AET supplied corrected amounts to reflect the actual
software additions. AET referenced the variance analyses and business cases supplied in support
of the actual 2015-2017 software additions.296
355. With respect to the GP&E-software portion of the GP&E forecast, AET submitted that it
had provided full and complete business cases to support the proposed projects with expenditures
of more than $500,000.297 AET noted that no party submitted evidence addressing AET's forecast
GP&E-software project expenditures. Given the limited questioning on AET's GP&E-software
projects, AET submitted that the forecast GP&E-software expenditures and additions should be
approved, as filed.298
356. With respect to its transmission asset management program (which is also part of AET's
GP&E-software), AET noted that in Direction 71 of Decision 20272-D01-2016, the Commission
directed AET to file a comprehensive asset management program business case, itemizing
historical and go-forward work and cost requirements. In response, AET stated that a business
case299 had been filed and sought approval for additions from 2013-2017 as well as expenditures
in the test period to enhance AET's asset management systems and processes, while ensuring
alignment with industry best practices.
357. AET maintained that there were no material issues raised and that no intervener
submitted evidence regarding AET's asset management program scope, opening rate base and
forecast costs, nor were there any questions on this program at the oral hearing. As such, AET
requested that the asset management program scope, opening rate base and forecast costs
included in its application be approved, as filed.
358. In argument, the CCA stated that it had reviewed AET’s GP&E forecast, and, in
particular, the information technology and vehicle cost items. The CCA was concerned with
AET’s forecast capital expenditures of $10.3 million and $11.5 million on the GP&E-software
portion of GP&E in 2018 and 2019, respectively, given historical capital expenditures were $4.2
292 Exhibit 22742-X0001.02, updated application, Appendix 10.B, pages 430-432. 293 Exhibit 22742-X0001.02, updated application, PDF page 389. 294 Exhibit 22742-X0001.02, updated application, PDF page 430. 295 Expenditures refers to the cash spent on an item or project in a given year while additions is the dollar amount
added to rate base in a year. 296 Exhibit 22742-X0725, AET final argument, page 63 refers to Exhibit 172.03. 297 Exhibit 22742-X0725, AET final argument, page 85 refers to Exhibit X0172.03. 298 Exhibit 22742-X0725, AET final argument, page 86. 299 Exhibit 22742-X0172.03, PDF pages 61-112.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 85
million in 2015 and $7.9 million in 2016.300 While AET’s costs increased in 2017 to $15.8
million,301 the CCA maintained there was no adequate explanation for the sustained increase over
the 2015 and 2016 levels.
359. The CCA was also concerned with 2019 vehicle capital expenditures of $4.1 million
given the historical levels of $1.2 million in 2016 and ($1.0) million in 2017.302 In particular, the
CCA was concerned that AET may not be properly considering leasing vehicles as a lower cost
option to purchasing them outright. In this regard, the CCA submitted that a regulated utility
would have an inherent bias towards adding capital to its rate base and thus would be naturally
opposed to leasing.
360. In reply argument, AET noted that the CCA chose not to address AET's IT forecast in
evidence, nor at the hearing. As such, AET submitted that the CCA comment that "there is no
adequate explanation for AET's forecast IT capital expenditures”303 should be ignored. AET
added that it had provided comprehensive business cases for all of the IT expenditures over
$500,000 in the test period.304 AET maintained that the CCA chose not to comment on the
substance of the business cases.
361. AET noted that the CCA expressed similar vague concerns regarding AET's
transportation equipment project305 forecast expenditures and whether AET had adequately
considered leasing as an option. AET pointed out that the leasing option was, in fact, considered
within its business case.306
Commission findings
362. The Commission notes that the interveners expressed some general concern with GP&E
forecast expenditures but did not submit any evidence on this issue. The CCA did suggest, with
respect to GP&E-other, that leasing should have been considered as an alternative to purchasing
vehicles.
363. The Commission notes that AET supplied a lease versus purchase analysis in its business
case.307 AET explained that the lease/rental of equipment is problematic primarily because of
limited equipment availability. Given this is typically specialized equipment, it is not available
for use on a casual basis and long term contracts are normally required. Rental equipment is also
unlikely to be available in emergencies. In AET’s view, equipment rental will always be costlier
than purchase because rental companies cannot control their assets ‘in-the-field.’ Therefore,
rental companies set rental/lease rates based on the least favorable life-expectancy, damage
projection, expected use, and resale value. A risk premium and a profit margin is added to that
300 Exhibit 22742-X0722, CCA final argument, page 221 refers to Exhibit 22742-X0002.04, AET GTA Schedules,
Schedule 10-4. 301 Exhibit 22742-X0722, CCA final argument, page 221 refers to Exhibit 22742-X0002.04, AET GTA Schedules,
Schedule 10-4. 302 Exhibit 22742-X0722, CCA final argument, page 221 refers to Exhibit 22742-X0002.04, AET GTA Schedules,
Schedule 10-4. 303 Exhibit 22742-X0722, CCA final argument, paragraph 764. 304 Exhibit 22742-X0171.03. 305 Exhibit 22742-X0172.03, Tab 4-3, PDF pages 220-238. 306 Exhibit 22742-X0172.03, PDF pages 223-224. 307 Exhibit 22742-X0172.03, pages 244-248.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 86
cost. AET maintained that lease or rental is a short term solution as costs can easily exceed cost
of ownership by mid-life of the equipment.308
364. The Commission also notes that AET's criteria for light duty vehicles included keeping
the vehicle for seven years or 250,000 kilometers.309 The Commission has considered AET’s
submissions in the business case as well as its responses to information requests and finds them
to be reasonable. In particular, the Commission does not consider leasing light duty vehicles to
be a viable option given the service life expectations of AET.
365. The Commission also examined AET’s GP&E-software forecasts, and, in particular, the
Oracle E-Business upgrade program and the asset management program. The Commission notes
that, in the Oracle business case, AET stated that premier vendor support for AET’s Oracle EBS
system has ended and an upgrade was required.310 AET further explained:311
Oracle’s Premier level of support is required because it is the only level of support that
ensures certification with new versions of third party vendor software such as operating
system software and applications that E-Business integrates with. Without the upgrade,
product fixes and security patches for these third party systems may need to be suspended
which would impact overall availability, reliability, and protection against security
vulnerabilities.
366. Similarly, and as directed in Decision 20272-D01-2016, AET filed a business case for the
asset management program.312
367. The Commission and interveners submitted numerous information requests to AET with
respect to these programs as well as the other forecast expenditures. The Commission finds the
evidence filed regarding AET’s forecast GP&E expenditures to be reasonable and sufficient, and
the proposed programs necessary. They are approved as filed. In its next GTA, AET is directed
to file variance analyses reflecting the actual capital expenditures, explanations for variance from
forecast and the current status of projects not completed.
368. The Commission also examined the proposed adjustments to opening rate base. AET
supplied a variance analysis in the application313 as well as further detail in the business cases,314
in particular, the asset management business case. The Commission considers this evidence to be
persuasive and the adjustments to opening rate base are approved.
11.4 Thickwood development project
369. In its evidence, the CCA noted that AET’s September 2018 application update315 included
a materially revised forecast of 2018 and 2019 direct assigned capital additions and expenditures.
2018 direct assigned capital additions increased by $107.9 million and 2019 direct assigned
capital additions decreased by $198.1 million. The CCA stated that the primary driver for this
308 Exhibit 22742-X0172.03, page 230. 309 Exhibit 22742-X0172.03, page 231. 310 Exhibit 22742-X0172.03, page 2. 311 Exhibit 22742-X0172.03, page 3. 312 Exhibit 22742-X0172.03, pages 60 – 112. 313 Exhibit 22742-X0001.02, updated application, PDF pages 430-432. 314 Exhibit 22742-X0172.03. 315 Exhibit 22742-X0533, 2018-2019 GTA September 4 2018 Update.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 87
change was AET’s transfer of $102.4 million of the Thickwood development project capital
additions from 2019 into 2018.316
370. The CCA also noted that the decision to advance the in-service date from 2019 to 2018
was AET’s, and not the AESO’s, even though AET had to secure the AESO's approval for the
in-service date change before it could take effect.317
371. In this regard, AET confirmed the following in response to a CCA information request:318
There were no identified negative consequences to the safe and reliable operation of the
transmission system that would have been encountered if the in service date was
maintained in January 2019.
372. According to the CCA, as there was no pressing reliability or safety-based need to
advance the in-service date to 2018 for the Thickwood development project, it appears that the
decision to do so was based entirely on economic considerations.319 AET stated that accelerating
the in-service schedule would allow for the saving of AFUDC costs.320 The CCA did not dispute
this. However, as AET confirmed in response to the CCA’s information request, shifting the
costs into 2018 simply replaced the AFUDC that would have been incurred in 2019 with return
on capital in 2018.321 AET determined that the AFUDC that was saved was $6.6 million, and that
this amount was offset by return on capital in 2018.322 Finally, the CCA noted that, by
accelerating the in-service date, AET triggered an additional $0.4 million of depreciation charges
which consists of $0.2 million in 2018 and $0.2 million in 2019.
373. The CCA stated that there was no safety or reliability-based need to accelerate the in-
service date, and the savings cited by AET in relation to AFUDC were not, in fact, true savings
given the return on capital included in revenue requirement. In the CCA's view,323 AET’s
decision had inter-generational equity implications as it was requiring current customers to pay a
cost that future customers would have otherwise incurred.
374. The CCA noted that in Decision 20272-D01-2016, the Commission considered a similar
scenario, albeit for a much larger asset, specifically EATL (Eastern Alberta Transmission Line).
However, in that case, AET sought to transfer $37 million of EATL-related depreciation expense
into 2016 from 2015, given that the asset was energized in December 2015.324 The Commission
denied AET’s request and directed that the depreciation be included in 2015.325
375. While acknowledging that the circumstances in Proceeding 20272 were unique, the CCA
considered that they were instructive. In the CCA’s opinion, absent a reasonable justification
based on system reliability or safety, AET should not have accelerated the in-service date for the
Thickwood development project solely to reduce AFUDC. Accordingly, the CCA recommended
316 Exhibit 22742-X0533, 2018-2019 GTA September 4 2018 Update – Narrative, PDF page 11, Table 1b. 317 Exhibit 22742-X0570.01, AET, AET-CCA-2018OCT05-004(c), PDF page 13. 318 Exhibit 22742-X0570.01, AET, AET-CCA-2018OCT05-004(e), PDF page 14. 319 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 185, refers to above footnote and IR
response. 320 Exhibit 22742-X0570.01, AET, AET-CCA-2018OCT05-004(d), PDF page 14. 321 Exhibit 22742-X0570.01, AET, AET-CCA-2018OCT05-004(f), PDF pages 13 and 14. 322 Exhibit 22742-X0570.01, AET, AET-CCA-2018OCT05-004(f), PDF page 14. 323 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, pages 185 and 186. 324 AUC Decision 20272-D01-2016, PDF page 93, paragraph 409. 325 AUC Decision 20272-D01-2016, PDF page 93, paragraph 412.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 88
that the Commission direct AET to revise its 2018 and 2019 revenue requirements and capital
additions to reflect the addition of the Thickwood development project in 2019 rather than 2018.
376. In its rebuttal evidence, AET maintained the CCA's assertion that AET “transferred the
addition of Thickwood into 2018 for no reason other than to reduce AFUDC”326 was false. In its
September 2018 application update, AET provided an updated Thickwood development project
forecast, driven by the in-service date being advanced from January 2019 to November 2018.
This resulted in an increase in 2018 capital additions of $107.9 million and a decrease of capital
additions of $198.1 million in 2019. However, AET asserted that this change was not undertaken
to “reduce AFUDC.” Rather, this change was to accurately reflect the project’s completion and
energization in 2018. AET submitted that its reference to reducing AFUDC was made simply to
highlight some of the financial implications of the change and not as a justification for advancing
the in-service date.
377. AET submitted that it did not incur additional costs on the project to complete it in
November 2018 as opposed to January 2019. According to AET, the early completion of the
project was a consequence of successful project execution, not an increase in labour and
execution costs to achieve an earlier in-service date. This was clearly indicated within the
monthly project reports filed in the application, and within the approved change orders filed with
the AESO.327
378. AET also stressed that the term “acceleration” as used by the CCA was inaccurate – the
project was executed on budget and ahead of schedule. An acceleration, as the CCA implied,
would imply that an additional capital expense would be required to complete the project ahead
of schedule. This was simply not the case and the completion of the project in 2018 was a result
of good construction practice and risk management, limiting potential project delays.
379. AET further argued that the reference made by the CCA to Decision 20272-D01-2016 for
the EATL project was not, as the CCA has indicated “…a similar scenario, albeit for a larger
asset.” In the case of the Thickwood development project, the scenario was the complete
opposite of what was being sought in the EATL case. In the latter, AET sought to shift
depreciation expense into future years from the year of project capitalization. The Commission
denied this adjustment. As noted by the CCA, the Commission “…directed that depreciation be
included in 2015.”328 AET maintained that AUC Decision 20272-D01-2016 actually supports
AET’s current position in that by advancing the in-service date for the Thickwood development
project as part of its September 2018 application update, depreciation expense would be incurred
in 2018, based on the complete capitalization of the asset in 2018, as opposed to being deferred
to 2019.
380. In summary, AET stated that it did not incur additional costs to achieve a 2018 in-service
date on this project and has throughout the project process advised the AESO of project forecasts
and schedule updates through a series of change orders. AET submitted that it managed this
project appropriately, and the adjustment of the in-service date is accurate as it aligns with the
project energization and results in a decrease in total capital cost from the originally filed
forecast.
326 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, PDF page 186, paragraph 603. 327 Exhibit 22742-X0570.01, AET-CCA-2018OCT05-004(b) Attachment 1, PDF pages 15-29. 328 Exhibit 22742-0592, CCA - Evidence of Bema Enterprises, paragraph 602, PDF page 186.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 89
381. In its argument, the CCA noted that whether or not additional costs were incurred to
advance the in-service date of the Thickwood development project was only one factor to be
considered. Another factor for the Commission to consider is whether advancing the in-service
date of an asset so that it becomes part of the regulated rate base earlier than would otherwise be
the case has consequences from the perspective of intergenerational equity.
382. The CCA submitted that its recommendation addressed this concern and resulted in the
removal of costs that should not be recovered in rates in 2018. The CCA further claimed that its
recommendation would not harm AET as it would essentially restore AET to where it otherwise
would have been had the Thickwood development project been energized in early 2019 as
originally planned.
Commission findings
383. The CCA has argued that AET unreasonably and unnecessarily advanced the in-service
date of this project, causing an increase in return and depreciation in 2018 in spite of there being
no pressing reliability or safety-based need for an earlier in-service date. The CCA also
maintained that there was an element of intergenerational inequity attending this change. That is,
ratepayers in 2018 would be adversely affected in having to begin paying for an asset that is not
yet required to be in service.
384. AET explained that it did not incur additional costs on the project to complete it in
November 2018 as opposed to January 2019. AET also pointed out that customers saved $6.6
million in AFUDC costs that would otherwise have been incurred if the project was not
capitalized until 2019. AET explained that the early completion of the project was a consequence
of successful project execution, not an increase in labour and execution costs to achieve an
earlier in-service date.
385. The Commission accepts the explanations of AET. The Commission acknowledges that
capitalizing the project in 2018 did lead to an increase in return and depreciation. However, as
AET has noted, this was largely offset by a decrease in AFUDC. The Commission also notes that
the current increase in return and depreciation will be further offset by decreases in future return
and depreciation. The Commission expects that the financial impacts of such variances will tend
to cancel each other out over time provided that the time value of money is taken into
consideration.
386. Regarding the request for relief on the basis of intergenerational inequity, the
Commission notes that large capital programs almost always involve some degree of
intergenerational inequity because the optimum timing for constructing a transmission asset
seldom matches the current need. Consistent with the mid-year convention and over the course
of a given year, some projects will be completed and capitalized earlier than forecast, while
others will be completed later than forecast. It should be noted that Thickwood Development
project is also a direct assigned project and actual capital expenditures will be adjusted in the
next DACDA proceeding. For these reasons, the CCA's recommendation is rejected.
387. As directed in paragraph 317 above, AET is to explore the timing of the capitalization of
assets as it affects municipal tax assessments and forecasts. In the case of the Thickwood
Development project, this timing may affect capital additions to rate base.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 90
11.5 Kearl Line (line 9L101) relocation
388. In the application, AET filed a business case supporting the relocation of the 240-kV line
9L101 Kearl line329 (Kearl line) as requested by Fort Hills Energy (FHELP) to accommodate its
oilsands expansion project. The Kearl line is part of transmission line L9900, which AET
purchased from Imperial Oil Resources Ventures Limited (IORVL or Imperial) in 2012.
389. AET explained that, in past decisions,330 the Commission approved the purchase of the
Kearl line by AET and accepted the line as a system asset, forming part of the North Fort
McMurray Transmission Development.
390. AET stated that it is obligated to relocate this line, under the FHELP Power Line
Encroachment and Consent Agreement that was assigned to AET as part of the purchase of the
Kearl line from Imperial. AET requested confirmation that the costs associated with relocating
the Kearl line continue to be system costs, and that approval of the Kearl line relocation be
forecast as a system cost.
391. AET maintained that the project met the requirements of the 2003 relocation principles
set out by the Commission’s predecessor in board Decision 2003-043. AET submitted that the
current relocation project is in the public interest because it avoids the sterilization of mine
resources, was a prerequisite to achieving landowner consent at the time of construction, and that
the relocation risks were known at the outset, when approval was given for the purchase and
systemization of the Kearl line in Decision 2012-193.331
392. AET’s business case, later updated, included an analysis of four alternatives, A, B, C and
D, for the relocation of the Kearl line. A detailed description of the facilities associated with each
of these alternatives, along with the proposed life cycle for each alternative was provided in
AET's business case.
393. AET recommended Alternative A because:
Alternative A presented the lowest initial project cost to meet the relocation
requirement.
Based on updated routing assumptions and refined estimates, the economic analysis
indicated that the CPV (Cumulative Present Value) of revenue requirement for
Alternatives A and B were effectively the same.
Alternative A had the least overall impact to land use and environmental features, the
greatest stakeholder and agency acceptance, the greatest use of disturbed/developed
areas and the lowest initial project cost requirement.332
394. The CCA submitted evidence recommending Alternative C and requesting that AET
perform additional work to further explore Alternative C and to assess whether the risks
identified by AET333 could be addressed. It submitted that AET's preferred alternative could
329 Exhibit 22742-X0171, pages 825-849. 330 Decision 2011-276, Approval of AESO NID; 2012-193, Approval of AET purchase and systemization of line;
2012-283, Addition of asset to AET rate base. 331 Exhibit 22742-X0171, page 826. 332 Exhibit 22742-X0171, page 837. 333 Exhibit 22742-X0171, page 834, AET business case describes Alterative C.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 91
result in significant additional line relocations and duplication of effort in the future.334 Further, it
noted that the Kearl line had previously been a customer-specific asset and is now a system asset.
The CCA stated that all Alberta ratepayers are paying for relocation costs that would have
otherwise been paid by the customer connected to the line had it remained a customer-specific
asset.335
395. The CCA observed that the cost of AET’s Alternative C is $38.0 million (or 324 per cent)
higher than Alternative A and $12.9 million (or 35 per cent) higher than Alternative B. The CCA
submitted that the benefit of Alternative C, however, is that it may extend the life of the assets,336
and is greater than the six year life of Alternative A and 24 year life of Alternative B.
396. In rebuttal evidence, AET explained that it took a conservative approach to uncertainty in
the business case and throughout the economic analysis of the alternatives. This included
considering worst-case scenarios for the year of future relocation (applying a 2027 in-service-
date for the future re-route in Alternative A and a 2045 in-service-date for the future re-route in
Alternative B). With these risk-based, worst-case scenarios applied, AET stated that the result
continues to be lower initial capital investment for Alternative A, which results in a lower CPV
of revenue requirement for this project.337 AET indicated that the difference between the CPV
values of revenue requirement for Alternative A and Alternative B are effectively equivalent
over the lifecycle of the asset.338
397. In argument, the CCA noted AET’s acknowledgement that there was significant
uncertainty with respect to the mine development.339 The CCA maintained that since AET
proposed that the costs of these new and replacement lines were to be borne by ratepayers, the
mine owner has no cost responsibility related to any changes required to the transmission line.
Consequently, the mine owner has no price signal to guide its behaviour for substantial costs
borne by others. The CCA argued that by introducing a price signal to the mine owner, it would
be compelled to take into account the costs to ratepayers and thereby optimize social costs. The
CCA acknowledged that the existing line has been purchased by AET and forms part of AET’s
rate base. However, the CCA submitted that the costs of the transmission line relocations need to
be examined under the specific circumstances of the proposed project.340
398. The CCA noted that AET had conceded that costs specifically related to the requirements
of the participant might not be designated as system related:
MR. PALLADINO: I suppose we can get into discussion depending on the relocation
requirements and how they relate to the system facilities in that area. To the extent that a
system line or a portion of a system line may be deemed to be specifically related to the
requirements of the participant seeking the relocation, and if it's deemed not to be in the
public interest to consider that portion to be a system line but, rather, one that is more
334 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 186. 335 Exhibit 22742-X0171.03, TCM Business Cases, PDF pages 827 and 828. 336 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 192, assets would have service lives of 60 to
65 years. 337 Exhibit 22742-X0570.01, PDF page 30, AET-CCA-2018OCT05-005. 338 Exhibit 22742-X0618, AET rebuttal evidence, page 162. 339 Exhibit 22742-X0722, CCA final argument, page 197, refers to Exhibit 22742-X0618, AET Rebuttal Evidence
to CCA and UCA, PDF page 162. 340 Exhibit 22742-X0722, CCA final argument, page 198.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 92
participant related, I suppose the Commission could have that as part of its consideration
when a relocation is under -- is looked at.341
399. The CCA submitted that the Commission has the jurisdiction to determine whether the
costs of line relocations are primarily and specifically related to the mine owner. Based on the
record, the CCA argued that it appeared that no benefits to other customers or ratepayers arise
from the relocation of the Kearl line. As such, the CCA concluded that the costs associated with
the Kearl line relocation could be designated as participant related.
400. The CCA said that if one assumed that the double circuit 240 kV lines are capable of
serving hundreds of Megavolt-Amperes, it is possible that the lines are relatively lightly loaded,
and that the value of the loop itself is accordingly diminished.
401. The CCA also submitted that it is possible that the lines comprising the North Fort
McMurray Transmission Development may have been overbuilt to supply the required load.342
Referring to the single line diagram provided by AET to the CCA in an undertaking,343 the CCA
suggested that if the loads on the Kearl line can have adequate reliability using radial lines served
from Joslyn 849S to Secord 2005S and from Black Fly 934S to McClelland 957S, this could
obviate the need to incur substantial, potentially duplicative costs to keep moving the
transmission line to keep the loop closed.344
402. The CCA further stated that if the reliability of a radial line was inadequate for the mine
owner, the mine could pay a contribution to have the transmission line relocated and rebuilt. The
CCA argued that such an arrangement would restore a price signal to the mine owner by
motivating it to take into account the cost of moving transmission lines in its mining
development plans. The CCA submitted that having price signals in place that drive optimal
societal behaviour and the allocation of limited resources is in the public interest.345
403. In argument, AET continued to support Alternative A on the basis that it presented the
best opportunity to defer project capital costs346 and is the lowest cost option for customers. AET
added that Alternative A allows AET to identify shorter, long-term routes based on the dynamic
mining development plan and continued discussions with the mine owner.347
404. AET also noted that during the hearing it had clarified the various line relocations that
had occurred in the past on components of the 240 kV line from McClelland to Joslyn (9L101
and 9L32) with Commission counsel.348 In so doing, AET pointed out that the 240 kV lines in the
area349 are located on oilsands development leases where large scale oil development is
occurring, resulting in a high probability that relocation would be required to allow for orderly
341 Transcript, Volume 4, page 578, line 16 to page 579, line 2, Mr. Palladino to Mr. Wachowich. 342 Exhibit 22742-X0722, CCA final argument, page 200. 343 Exhibit 22742-X0650, Undertaking 32 Palladino to Wachowich, PDF page 2. 344 Exhibit 22742-X0722, CCA final argument, page 200. 345 Exhibit 22742-X0722, CCA final argument, page 200. 346 Exhibit 22742-X0171.04, page 837. 347 Exhibit 22742-X0725, AET final argument, page 79, also refers to Exhibit 22742-X0618, pages 162-170. 348 Transcript, Volume 6, pages 1004-1008. 349 Exhibit 22742-X0650.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 93
and prudent development of oilsands activity in the area. The 240 kV lines that form part of the
backbone transmission system in the area are all considered to be system assets.350
405. AET maintained that the rationale for treating the Kearl relocation costs as system is
consistent with the board’s previously developed relocation principles as articulated in Decision
2003-043. AET noted that, in that proceeding, both AET and the Transmission Administrator351
agreed that, where a line will clearly need to be moved to enable orderly and economic mining
activities identified prior to the decision to locate the line, the leaseholder should not have to
fund the move.352 AET further noted that the board, in the decision, considered it would be more
appropriate to defer the consideration of line relocation costs to a point in time in the future, if
and when it was required to move the transmission line. The board did, however, set down the
relocation principles to guide the determination of responsibility for relocation costs.353
406. With respect to the public interest, AET noted that in Decision 21306-D01-2016 the
Commission stated that it will generally weigh the benefits of a proposed project against the
costs to be incurred by customers.354 To properly measure the benefits of the proposed relocation,
AET submitted that the Commission must take into account the broader public interest in the
efficient development of oilsands resources. AET explained the vast nature of system lines in
northeast Alberta that are located on oilfield lands355 and indicated that the extraction of a
significant amount of mineable ore might only be possible by relocating system transmission
facilities. AET maintained that applicable legislation was in place to protect the public interest in
the development of oilsands activity356 and that the requested relocation was not a purely private
benefit to the mine owner but also has considerable benefits in the public interest.
407. Additionally, AET stated that the Kearl system facilities are similar to many of the
transmission system lines that form part of the North-East Loop that traverse oilsands mining
areas. AET argued that a determination that participants must pay the cost of relocating a system
line to accommodate active oilsands operations may make siting future transmission
development more challenging.357
408. AET also provided arguments distinguishing the current application from that in
Proceeding 2901 (Decision 2014-009) and in Proceeding 21306 (Decision 21306-D01-2016).
409. In its reply argument, the CCA stated that AET had co-mingled the public interest issue
with the system versus participant issue, which the CCA submitted are separate issues. The CCA
said that the Commission should first decide if the proposed Kearl line relocation is in the public
interest and then decide who is responsible for the costs. The CCA noted that AET had relied on
the Oil Sands Conservation Act to support its position that the proposed Kearl line relocation is
350 Transcript, Volume 6, page 1010. 351 The predecessor to the AESO. 352 Decision 2003-043, page 13. 353 Exhibit 22742-X0725, AET final argument, page 80, refers to Decision 2003-043, page 14. 354 Decision 21306-D01-2016 at para 112. 355 Transcript, Volume 6, pages 1009-1010. 356 Transcript, Volume 6, pages 1014-1015. 357 Exhibit 22742-X0725, AET final argument, page 82.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 94
in the public interest.358 The CCA argued that the relocation may be in the public interest at some
point in time, but the real issue is who should pay for it.359
410. The CCA noted that AET relied on relocation principles from Decision 2003-043.360 The
last principle states that the “cost of relocating a local transmission line required to serve the
party requesting the relocation should be the responsibility of that party.”361 The CCA submitted
that the relocation principles set out in Decision 2003-043 need to be considered in context. At
the time of the decision, Alberta transmission system costs were relatively low compared to
today and might arguably have contributed to electricity rates that were highly competitive with
other jurisdictions in Canada. The CCA stated that today, Alberta has become one of the highest
transmission cost jurisdictions in the world and that the threat of customers seeking to bypass the
transmission system or leave the system entirely has become a real threat to the system’s
economic viability. This, the CCA argued, creates a strong case to send price signals to those
entities, including customers, that trigger further substantial cost increases on the transmission
system with little or no benefit to other customers.362
411. In its reply argument, AET suggested that the CCA was speculating in its evidence that
the looped system, of which the Kearl line is a part, “may not be necessary” and that customer
loads could be met with “radial lines” and the use of “portable generation.”363 AET claimed the
CCA’s speculation was in reality a collateral attack on Decision 2011-276.364 AET explained that
the looped system serves not only the Fort Hills mine but is part of the larger Fort McMurray
looped system and serves the needs of multiple customers. The construction of L9900 by
Imperial, its subsequent systemization, and construction of the looped system were independent
of the Fort Hills mine. AET argued that any speculation as to whether FHELP could operate
adequately with or without the looped system365 is both without basis and irrelevant as it does not
consider the overall reliability needs of the Fort McMurray system and all affected customers.
Commission findings
412. The Commission is required to make two decisions with respect to the Kearl line
relocation:
(1) were approval to be granted for the Kearl line relocation in Proceeding 24246, from
whom should the capital expenditures for the line relocation be recovered: the
owner of the Fort Hills mine (customer) or the system’s customers? and
(2) if the Kearl line relocation costs are to be recovered from the system’s customers,
what quantum of AET’s forecast capital expenditures for TCM project number
50463, 9L101 Kearl Line Relocation Project should be approved?366
358 Exhibit 22742-X0725, AET final argument, PDF page 79, paragraph 256 to PDF page 82, paragraph 262. 359 Exhibit 22742-X0726, CCA reply argument, page 30. 360 Exhibit 22742-X0725, AET final argument, PDF page 80, paragraph 257. 361 Exhibit 22742-X0725, AET final argument, PDF page 81, second bullet. 362 Exhibit 22742-X0726, CCA reply argument, page 32. 363 Exhibit 22742-X0722, CCA final argument, paragraphs 680-685. 364 Exhibit 22742-X0171.04, PDF pages 827-828. 365 Exhibit 22742-X0722, CCA final argument, paragraphs 684-686. 366 See Exhibit 24246-X0039 and Exhibit 22742-X0730 for the scoping letter of the facilities and rates
proceedings.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 95
413. The Commission addresses each of these questions below.
(1) Allocation of line relocation costs
414. An overview of the origins of the Kearl line and its past regulatory treatment leading to
the purchase of this line by AET is set out in Decision 2014-283. Some of this history has been
provided in this section to assist in understanding the Commission’s determination regarding
AET’s request to have the Kearl line relocation costs classified as system costs and therefore
paid for by the system’s customers.
415. Imperial received a permit and license to construct the Kearl line in 2009.367 The Kearl
line was part of the Kearl Oil Sands Industrial Site Designation (ISD).368 While Imperial
constructed the line initially, Imperial was aware of the possibility that it would be selling the
asset as a system requirement.
416. In Decision 2009-154, the Commission approved the addition of a second conductor. In
the decision, the Commission stated:
19. Alberta Electric System Operator (AESO) has requested that IORVL add a
second conductor to the Transmission Line so that this Line is built to serve as a system
facility, if and when AESO determines that such service is required.
20. IORVL believes it is in the public interest to initially construct the transmission
facility to meet the potential future system access service requirement contemplated by
AESO.
21. IORVL is prepared to assume responsibility for the costs and risks associated
with the alteration given that a future transfer of the transmission facility to a system
facility is not decided at this time. IORVL acknowledges that any such transfer would be
subject to a future need determination by AESO and approval by the Commission.
22. Although IORVL is prepared to assume all of the costs associated with the
second conductor, it expects that should the 240-kV line be required in the future as a
system asset by AESO, it would seek the opportunity to recover reasonable costs incurred
by it at that time.
417. In 2010, the AESO filed a needs identification document application with the
Commission, which recommended utilizing Imperial’s transmission line L9900 to create a 240-
kV loop in the area. In Decision 2011-276, the Commission approved the need as applied for.369
In that decision, the proposed project was described as follows:
The transmission facilities proposed to meet the need include construction of a new
double circuit 240-kilovolt (kV) transmission line with a single side strung from Salt
Creek 977S substation to a new substation designated as Black Fly 934S substation,
continuing north and terminating at a new substation designated as McClelland 957S
substation on transmission line L9900. Transmission line L9900 is under construction by
Imperial Oil Resources Ventures Limited. With a connection to transmission line L9900,
367 Decision 2012-193 refers to approvals U2009-055 and U2009-394. 368 Decision 2012-193 refers to Approval U2009-039. 369 Proceeding 774, North Fort McMurray Transmission Development.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 96
a looped 240-kV electric system would provide reliable service to the north Fort
McMurray area.370
418. AET received approval to purchase the line and systemize the asset in Decision 2012-
193. In the decision, the Commission stated:
6. … The applied for transfer and alterations reflect what was granted in the
aforementioned need approval. The AESO has directed ATCO to submit the current
application to meet the specifications outlined in the AESO Functional Specifications, in
accordance with Section 35 of the Electric Utilities Act.
…
8. ATCO and Imperial have reached an agreement whereby ATCO will purchase
and operate transmission line L9900 (the transmission line). This will allow ATCO to
integrate the transmission line into ATCO’s electrical system and to utilize the
transmission line as part of the AIES. A looped transmission system will then be created
to enhance transmission system reliability in the Fort McMurray area, as discussed in
Decision 2011-276.
419. Approval to add the purchase to AET’s rate base was granted in Decision 2014-283.
420. AET has now been requested by the owner of the Fort Hills mine to move the Kearl line
that forms part of the looped transmission system in the Fort McMurray area. The CCA has
submitted that this proposed line relocation should be a customer cost on the basis that the
relocation is intended only for the benefit of the customer.
421. Section 17 of the Hydro and Electric Energy Act authorizes the Commission to determine
compensation to be paid under an application to relocate a transmission line. Section 17 states:
17(1) The Commission may, on any terms and conditions it considers proper, direct a
permittee or licensee to alter or relocate any part of the permittee’s or licensee’s
transmission line if in the Commission’s opinion the alteration or relocation would be in
the public interest.
(2) The Commission may, in an order under subsection (1), provide for the payment of
compensation and prescribe the persons by whom and to whom the compensation is
payable.
(3) When an order under this section provides for the payment of compensation, the
Commission may at any time provide that if agreement on the amount of compensation
cannot be reached between the parties, the amount is to be determined by the Alberta
Utilities Commission on the application of either party.
422. The Commission considers that the following factors must be addressed in determining
this matter:
(a) Does the relocation of this Kearl line change the nature of the looped 240-kV
system for which the need and purchase of this line was approved?
370 Decision 2011-276 refers to Approval U2011-216.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 97
(b) If the answer is no, are there any other factors which would suggest to whom these
relocation costs should be allocated?
(a) Does the relocation change the nature of the looped 240-kV system?
423. The AESO is the system planner and in this role, it has the jurisdiction and legislative
responsibility to plan the transmission system including the alleviation of system constraints.371
As well, the AESO is required to submit for Commission approval a tariff that sets out rates to be
charged for system access service and the terms and conditions that apply to each class of
service.372 Under Section 8 of the current AESO tariff, the AESO sets out the manner in which it
classifies participant and system-related costs for the purposes of a connection project. This
provision states, in part, as follows:
3(1) All costs of a connection project will be classified as either participant-related or
system-related.
(2) Participant-related costs will be those costs related to a contiguous connection project
including costs associated with:
…
(d) line moves or burials of existing transmission line;
…
(h) salvage labour required to remove existing transmission facilities to allow the
installation of new or replacement facilities for a connection project, except where the
cost of the removed facilities is treated as a capital maintenance cost by the owner of the
transmission facility;
(3) System-related costs will be those costs related to a connection project including non
contiguous components of the project and any costs associated with:
(a) looped transmission facilities, which are facilities that increase the number of
electrical paths between any two (2) substations, excluding the substation serving the
market participant and which exclude any new radial transmission line;
(b) radial transmission facilities which, within five (5) years of commercial operation, are
planned to become looped as part of a critical transmission development or regional
transmission system project:
(i) in the ISO’s most recent long-term transmission system plan;
(ii) in a needs identification document filed with the Commission; or
(iii) as the ISO reasonably expects will be required in the future;
424. As noted above, the AESO determined that the Kearl line was required as part of a
looped system and it was on this basis that the Commission approved the purchase of this line by
AET from Imperial and indicated that these line costs should be systemized and therefore
recovered from the system’s customers.
371 Sections 33 and 34 of the Electric Utilities Act. 372 Section 30 of the Electric Utilities Act.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 98
425. There is no evidence on the record to suggest that any of the proposed alternatives set out
in the business case would result in the 240-kV system no longer being a looped system.
Although these alternatives and approval of the relocated Kearl line is yet to be determined in
Proceeding 24246, no evidence has been put forward to suggest that the line, if relocated, would
no longer form part of a looped system.
(b) Are there any other factors which would suggest to whom these costs should be
allocated?
426. Parties have referred to Decision 2003-043 wherein the Commission’s predecessor, the
board, enumerated certain principles that could be considered in assessing cost responsibility for
relocation of transmission lines. The board stated:
Notwithstanding that the Board considers relocation costs to be better dealt with in [sic.]
the future, the Board considers that it would be appropriate to set down some broad
principles that would generally guide the Board in determining cost responsibility for
relocation costs. These principles may assist parties in coming to commercial agreements
should they so desire:
The Board must be satisfied as to the balance between the public interest and the
interest of any affected party.
• The sterilization of mineable ore, and direct and unavoidable conflict with the
infrastructure and development required to mine the ore, is a reasonable cause for
the relocation of a transmission line.
• A valid mineral lease and an applied for/approved mine plan should exist at the
time the move is requested.
• The TA’s customers should be required to incur relocation costs, as a system
cost, when there is a reasonable cause to move a system transmission line,
provided that:
o A valid mineral lease existed prior to the construction of the
transmission line; o A practical alternative route is available; and
o There are no unusual negative impacts on the AIES that cannot be
reasonably addressed.
The cost of relocating a local transmission line required to serve the party
requesting the relocation should be the responsibility of that party.373
[emphasis in original]
427. The Commission further addressed these principles in Decision 21306-D01-2016 where it
was asked to determine how to allocate the costs of a transmission line that had already been
moved. The Commission stated:
Based on its review of the prior decisions cited by the parties, the Commission finds that
these decisions do not specify that in each instance where a transmission line move is
proposed to avoid sterilization, the cost of the transmission line move would necessarily
be borne by ratepayers.
…
The Commission has discretion under Section 17(1) of the Hydro and Electric Energy
Act to direct a permittee or licensee to alter or relocate the permittee’s or licensee’s
373 Decision 2003-043, PDF page 18.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 99
transmission line on any terms and conditions it considers proper. The Commission’s
prerogative to impose conditions could include a requirement that the altered or the
relocated transmission facilities have different characteristics or specifications than
originally proposed. Section 17(2) of that same act provides authority for the
Commission to determine compensation under an application by either party. For
example, the Commission could order the party requesting the relocation to pay some or
all of the costs.374
428. The Commission also stated:
The discussion of the 2003 relocation principles in the proceeding leading to
Decision 2011-520 came about due to the desire of some participants to obtain certainty
with respect to compensation for future transmission line moves proposed to avoid
sterilization of mineable ore. Significantly, consistent with the findings of the board in
Decision 2003-043, the Commission, likewise, only indicated that the 2003 relocation
principles would be considered as and when future applications pursuant to Section 17 of
the Hydro and Electric Energy Act were received.
…
It is accordingly notable that subsequent to Decision 2011-520, in Decision 2014-242, in
respect of the AESO’s 2014 tariff application, the Commission rejected certain changes
proposed by the AESO with respect to the criteria for classifying certain types of
transmission facility projects as system-related costs for the purposes of the AESO’s
contribution policy. Furthermore, in Decision 3473-D02-2015, in respect of the AESO’s
compliance filing application, pursuant to Decision 2014-242, the Commission
established a Commission-initiated proceeding that will include investigation into the
principles to be applied in determining whether the costs of transmission projects should
be classified as system-related.
In the Commission’s view, the forthcoming review of system-related costs in the
aforementioned Commission-initiated proceeding, is a further indication that the 2003
relocation principles may be modified in future applications for a transmission line move
where a transmission line would sterilize mineable ore. The Commission, therefore, finds
the 2003 relocation principles may evolve or change over time.375 [footnotes removed]
429. Notwithstanding these comments, the Commission proceeded to evaluate the allocation
of costs on the basis of the principles set out in Decision 2003-043 along with other arguments
presented, namely the fact that the parties had entered into a cost allocation agreement. It was the
existence of this agreement that led to the determination that CNRL should be responsible for
paying the relocation costs. The Commission stated:
123. Given that no evidence has been provided to show that the relocation of the
transmission facilities exceeded ATCO’s estimated cost of performing this service and
given that CNRL agreed to pay the full costs of the 9L66/9L32 line move project, the
Commission finds no basis to warrant interference with the terms of the agreement. For
the reasons given above, the Commission finds that CNRL has not demonstrated that the
agreement pertaining to the 9L66/9L32 line move project results in a rate, toll or charge
that is insufficient, excessive, unjust or unreasonable in the circumstances. Accordingly,
the Commission will not employ the provisions of Section 81 of the Public Utilities Act
374 Decision 21306-D01-2016, paragraphs 44 and 46. 375 Decision 21306-D01-2016, paragraphs 55, 57 and 58.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 100
to alter the terms of the agreement including the rate charged to CNRL for the 9L66/9L32
line move project.376
430. Parties have directed the Commission’s attention to other decisions as well. They have
referred to Decision 2014-009. This decision is brief and does not deal with the issue of cost
allocations.
431. With respect to the specific principles enumerated in Decision 2003-043, the board, when
it established these principles, did so on the understanding that when balancing the public
interest and the interest of an affected party, that, provided there is a reasonable cause to move a
system transmission line, the costs for the relocation should be systemized provided that “a valid
mineral lease existed prior to the construction of the transmission line; a practical alternative
route is available; and there are no unusual negative impacts on the AIES that cannot be
reasonably addressed.”377
432. In this proceeding, the Commission has been asked to provide a finding regarding the
allocation of costs associated with a proposed relocation of a portion of a transmission system
line and it is within these restricted circumstances that the Commission has made its
determination.
433. As set out in Decision 2003-043, the board established several principles to provide
guidance when determining who should be responsible for the payment of relocation costs. In
this proceeding, because there is a proposed move of a portion of a transmission system line, the
following facts contribute to a finding that these relocation costs could be allocated to the
system’s customers:
(a) The relocated line is expected to continue to be part of a looped system;
(b) A valid mineral lease exists and existed prior to the construction of the line; and
(c) Practical alternative routes are available, but are to be tested in Proceeding 24246.
These are the alternatives described in the business case as A, B, C and D.
434. The remaining factor identified by the board is whether there are “unusual negative
impacts on the AIES that cannot be reasonably addressed.” The board did not elaborate on what
it meant by this principle. However, this factor appears to address physical issues rather than cost
issues regarding a transmission line relocation.
435. As stated above, when it established these factors, the board did so on the basis that these
factors are demonstrative of a “reasonable cause” to support moving a system transmission line
and the attributed costs of the move to the system’s customers. An example provided by the
board of a reasonable cause was “the sterilization of mineable ore, and direct and unavoidable
conflict with the infrastructure and development required to mine the ore.”
436. AET has asserted that the Kearl line prevents the owner of the Fort Hills mine from
accessing some of the mineable ore and on that basis, has asserted that this resource is sterilized.
In the present case, the Commission finds that AET has not demonstrated that the public interest
376 Decision 2003-043, paragraph 123. 377 Decision 2003-043, PDF page 18.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 101
balance weighs in favour of assigning all of the costs of the relocation to the system’s customers
simply on the basis that the owner of the Fort Hills mine has claimed that access to mineable
resources will be prevented in this area. In the oral hearing, the Commission asked AET directly
about this matter and AET’s response was:
The rationale that -- from Fort Hills' perspective is that if we don't move the line, the
sterilization of the mineable ore in that area would prevent them from getting access to
anywhere between 500 million to 750 million barrels of recoverable bitumen.378
437. This response and the evidence on the record, including the business case discusses the
impact on the owner of the Fort Hills mine but fails to examine the financial benefits to the
public of extracting this bitumen.
438. Although not filed as evidence in this proceeding, the Commission nonetheless also
reviewed AET’s response to IRs in Proceeding 24246, the related facility application, which is
currently before the Commission.
ATCO-AUC-2019FEB26-004
Preamble: The Commission acknowledges that the transmission line must be relocated to
gain access to recoverable bitumen. However, the Commission would like to understand
what, if any, analysis was undertaken by ATCO or the mine owner to demonstrate that
the resource would in fact be sterilized if some or all of the relocation cost was
determined to be participant-related rather than system-related
Request:
a) Is it ATCO’s position that the mine owner may withdraw its request to relocate the
line if the mine owner is required to pay the cost of the relocation, and therefore
sterilize the resource?
b) If the answer to (a) is no, on what basis does ATCO conclude there will be resource
sterilization?
c) If an economic analysis was undertaken to assess whether recovery of the
approximately 500 to 750 million barrels of recoverable bitumen is uneconomic when
factoring in the cost of the line relocation, please provide the analysis.
AET RESPONSE
a) It is ATCO Electric’s understanding that this relocation is required by the mine
owner, FHELP, to accommodate ongoing development of the Fort Hills mine.
However, ATCO recognizes that any party that has requested a line relocation, or any
electric project for that matter, may withdraw its request prior to commencement of
the project for various reasons. However, in ATCO’s view this has no bearing on the
potential sterilization of resources in the current circumstances.
b) Failure to relocate the line will result in the mine operator being unable to access and
recover the mineable bitumen, resulting in resource sterilization. ATCO relies on the
assessment by the mine owner that failure to relocate the line would result in the
sterilization of as much as approximately 500 million to 750 million barrels of
recoverable bitumen [Exhibit 24246-X0018, pages 5-6].
378 Transcript, Volume 6, page 1015.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 102
The Commission's question appears to suggest that resource sterilization occurs when
resource extraction becomes uneconomic because the mine owner must bear the cost
of relocation. AET submits that this characterization of the relocation criteria is not
correct. Resource sterilization occurs where access to the resource is impeded by the
current location of a transmission line. Resource sterilization is not contingent on
whether relocation costs are classified as a system or participant cost. In this case,
failure to relocate the line would result in resource sterilization because the mine
owner would be unable to access mineable bitumen.
If the Commission is to adopt an economic test for resource sterilization that "there is
sterilization only where the line cannot economically be relocated’, the Commission
would paradoxically be stating that a line relocation is only eligible for systemization
of associated costs where "the applicant cannot economically justify the relocation".
ATCO submits that this cannot be a correct application of the 2003 relocation
criteria, and further, is not consistent with the Commission’s obligation, when
assessing whether relocation costs should be system costs, to “weigh the benefits of a
proposed project against the costs to be incurred by ratepayers” (Decision 21306-
D01-2016, para. 112).
c) See responses to 004(a) and (b). No such analysis was undertaken, as this is not
required in order to determine the case for resource sterilization.
ATCO-AUC-2019FEB26-005
a) In Table 2.0-1, ATCO has applied the 2003 relocation principles from Decision
2003-043 to the circumstances in this case in order to support its position that the
relocation costs are properly considered system-related. Please comment on what
other factors, if any, should be considered when assessing whether the line relocation
as a cost to ratepayers is in the public interest.
AET RESPONSE
a) In Decision 21306-D01-2016, the Commission stated that when assessing the public
interest, the Commission will generally weigh the benefits of a proposed project
against the costs to be incurred by ratepayers.
…
In this Proceeding, the benefits of relocating the systemized 9L101 line include the
extraction of a significant quantity of additional mineable ore that would otherwise
be sterilized were the line to remain in this location. Continued mining in the area
will only be possible by relocation of the transmission line and will provide
additional economic opportunities to individuals in Alberta, generate a number of
construction and operational jobs, and provide a significant financial benefit to
municipal, provincial and federal governments. To characterize the relocation as a
private benefit to only the mine owner would ignore the considerable benefits in the
public interest of both the continued benefit of mining the ore.
…
439. The Commission disagrees with AET’s assertion that an inquiry into whether a mineral
resource becomes sterilized should be undertaken without regard for consideration of the costs to
relocate the line and who would bear such costs. It is the weighing of these costs relative to the
benefits of relocation that could lead the Commission to determine that it is in the public interest
to allocate the relocation costs of a transmission system line to the system’s customers. However,
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 103
apart from AET’s broad assertions, AET has failed to meet its onus in demonstrating to the
Commission that it is in the public interest to assign the relocation costs to the system’s
customers.
440. Moreover, the Commission agrees with the CCA that given the high costs of transmission
in Alberta, it is in the public interest to send price signals to customers for the costs they cause.
441. In Decision 21306-D01-2016, the Commission also considered whether there was a
contractual arrangement that allocated relocation costs. The Commission notes that AET has
claimed that it is obligated to relocate the line as part of the purchase agreement entered into with
Imperial.379 The asset purchase and sales agreement was provided on the confidential record of
this proceeding.380 The Commission has reviewed the agreement and does not consider there to
be any contractual basis compelling AET to recover relocation costs from the system’s
customers. Consequently, unlike factors weighed by the Commission in Decision 21306-D01-
2016, in these specific circumstances, it cannot consider the provisions of the agreement as
determining who should pay relocation costs.
442. After careful consideration of the above factors, and provided that AET receives an order
from the Commission in Proceeding 24246 to relocate the Kearl line pursuant to Section 17(1) of
the Hydro and Electric Energy Act, the Commission finds that the costs of the relocation should
be the responsibility of the owner of the Fort Hills mine.
443. Nothing in this decision restricts a panel of the Commission from determining a future
relocation of the Kearl line or the costs associated with that relocation.
(2) Forecast capital expenditures for Kearl line
444. Given the above finding the forecast capital expenditures381 in the amount of $1.0 million
and $3.0 million in 2018 and 2019, respectively, are denied.
11.6 Direct assigned capital deferral account
445. The direct assigned capital deferral account (DACDA) is a deferral account designed to
mitigate the risk to both AET and its customers flowing from capital projects that are directly
assigned by the AESO to a transmission utility. The direct assigned capital projects are typically
large and entail execution risks382 in terms of cost and time that are difficult for the utility to
forecast. The account captures the actual costs relative to the forecast costs. As the individual
projects are closed, the utility files an application to true up the actual to forecast costs and adjust
rate base for approved differences.
446. In its evidence, Bema observed that the DACDA has removed significant volatility in
revenue requirements since it was approved by the Commission. Additionally, absent the
DACDA, ratepayers would have paid substantially more for the assets than necessary.383
However, Bema questioned whether the DACDA, in its current design, is necessary going
forward. Bema noted that in 2018 and 2019, AET’s forecast direct assigned capital additions are
379 Exhibit 22742-X0171. 380 Exhibit 22742-X0171, Conf-01. 381 Exhibit 22742-X0171.04, 2-0 TCM business case, PDF page 826. 382 Such risks can include landowner issues, weather and regulatory delay. 383 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 13.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 104
$147.4 million and $130.5 million, respectively, which are either less than or generally
consistent with the actual/forecast non-direct assigned capital additions in 2018 and 2019 of
$131.9 million and $149.7 million, respectively. There is no deferral account for non-direct
assigned capital additions. Bema noted that non-direct assigned capital additions are trued up as
part of an opening rate base adjustment within AET’s next GTA.384
447. Bema suggested that AET’s future direct assigned capital additions are likely to be in the
range of $30 million to $50 million per year ignoring the potential for future system projects. In
Bema’s opinion, this base level of direct assigned capital should be well within AET’s control to
manage on a forecast basis absent a deferral account.385 It was Bema’s understanding that, prior
to the implementation of the original performance-based regulation regime and capital trackers,
distribution utility owners often had their entire capital program subject to forecast risk.386
448. Bema recommended that the Commission adjust the DACDA process to include specific
criteria for the 2018 and 2019 forecast test periods. According to Bema, only those projects that
meet the following criteria should qualify for deferral account treatment:
(a) Any direct assigned capital project with a combined increase in net rate base (after
considering customer contributions) of greater than $50 million;
(b) Any direct assigned capital project with a combined increase in net rate base (after
considering customer contributions) of greater than $25 million but less than $50
million, that has a variance from the PPS (Proposal to Provide Service) estimate of
greater than 20 per cent; or
(c) Any direct assigned capital project with a combined increase in net rate base (after
considering customer contributions) of greater than $10 million but less than
$50 million that has had its capital additions shift into a different year from that
originally forecast.387
449. In the CCA’s view, all other direct assigned capital additions should be subject to normal
forecast risk given the comparatively modest impact those additions are likely to have on the
forecast revenue requirement.
450. In rebuttal evidence, AET did not support the changes to its DACDA recommended by
Bema. AET stated that the deferral account in its current form served its intended purpose by
mitigating risk to both AET and customers. AET stated that a reduction in the total amount of
direct assigned projects does not equate to an increase in AET’s ability to control the timing and
cost of these projects.388
451. AET noted that its direct assigned capital represents 54 per cent and 47 per cent of its
total capital program in 2018 and 2019, respectively, which AET considered significant in terms
of its ability to control its overall capital program. It added that despite the reduced scale of the
direct assigned capital program in the test period compared to 2015, for example, the fact
384 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 14. 385 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 15. 386 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 16. 387 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 51. 388 Exhibit 22742-X0618, AET rebuttal evidence, page 8.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 105
remained that the quantum, timing and cost of direct assigned projects remain out of AET’s
control and, instead, are largely subject to directions from AESO NID applications and decisions
from the AUC (NID and facility applications to establish the need for projects as well as scope,
for example, routing considerations).389
452. AET submitted that it has a significantly higher level of control of the factors and
considerations it takes into account when developing its non-direct assigned project GTA
forecasts. The same level of control is not available for direct assigned projects given the
directions and decisions from the AESO, the AUC and the government of Alberta.
453. AET supplied a list of projects from the current and previous test period that, in its view,
highlighted the appropriateness of deferral account treatment. AET stated that its opinion was
informed by the Commission’s findings in Decision 2010-189390 containing the four factors that
are highlighted by Bema’s evidence, namely the:391
(a) Materiality of the forecast amounts;
(b) Uncertainty regarding the accuracy and ability of forecast the amounts;
(c) Whether or not the factors affecting the forecasts are beyond the utility’s control;
and
(d) Whether or not the utility is typically at risk with respect to the forecast amounts.
454. The fifth factor in Decision 2010-189 is symmetry and was not referenced by the CCA.
Commission findings
455. The Commission acknowledges the CCA’s submissions with respect to amending the
criteria to evaluate when DACDAs should be relied upon. The Commission observes that all
transmission utilities have an account that is similar to or the same as AET’s and these accounts
have been in existence for several years to reconcile direct assigned capital forecasts and actual
amounts that are subject to the decisions of the AESO for AET’s direct assigned projects. The
Commission finds that it is reasonable, absent compelling grounds to the contrary or a change in
circumstances that would suggest the DACDA would not meet the factors in Decision 2010-189,
not to modify the AET DACDA in this proceeding.
456. The symmetry factor found in Decision 2010-189 states:
In another Board decision, also referenced in Decision 2003-100, the Board, when
examining the merits of an application for a deferral account on the facts of that
proceeding, took the view that “deferral accounts should not be for the sole benefit of
either the company or the customers.” Deferral accounts, rather, should “provide a degree
of protection to both the Company and the customers from circumstances beyond their
control,” and hence “Symmetry must exist between costs and benefits for both the
Company and its customers.” The Board also noted that it expected that “the individual
mechanisms involved in the use of each deferral account should be applied in a consistent
and fair manner in both test years and non-test years.” This will be referred to as the
symmetry factor. [footnotes removed]
389 Exhibit 22742-X0618, AET rebuttal evidence, page 9. 390 Decision 2010-189: ATCO Utilities Pension Common Matters, Proceeding 226, Application 1605254-1,
April 30, 2010. 391 Exhibit 22742-X0618, AET rebuttal evidence, page 10, refers to Exhibit 22742-X0592, paragraph 25.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 106
457. Applying the symmetry factor, the Commission also considers that the current structure
has worked well to protect the interests of both AET and its customers for both the costs and
benefits of utility service, a fact acknowledged by the CCA itself.392
11.7 Engineering, supervision and general costs
458. AET’s engineering, supervision and general (ES&G) costs were detailed in the
application.393 This category of costs is separate from supervision and engineering costs to
support O&M. Those costs are included in USA 560.394
459. Consistent with previous applications, AET’s policy, based on International Accounting
Standards (IAS) 16 property, plant and equipment395 is to include in capital all costs that relate to
the construction of a capital project. The ES&G accounting policy was provided as an
attachment to the application. AET provided a brief explanation of the costs typically included in
ES&G.396
460. AET explained that ES&G costs decreased from 2015 to 2016 due to staff reductions
attributable to fewer capital project-related activities. The forecast ES&G costs for the 2018-
2019 test period remained consistent with the 2016 actuals and 2017 forecast. The ES&G rate is
calculated by dividing ES&G costs by capital expenditures. However, AET explained that the
relationship between ES&G costs and capital expenditures is not linear and the workload of
many of the functional groups (such as Accounts Payable, Human Resources, Fixed Assets
groups) included in ES&G does not directly correspond to capital expenditures.397
461. For 2017 and for the 2018-2019 test period, the ES&G rate decreased from 2016 due
mainly to capital expenditures being higher in 2017 and in the 2018-2019 test period relative to
2016.398
462. In argument, AET noted that it explained in its direct evidence399 that it updated the
values in Schedule 10-6, Schedule of Transmission ES&G, to correct for some costs that were
inadvertently excluded in the application update400 and indicated that it would reflect the required
changes in its compliance filing. As no significant issues were raised regarding ES&G, AET
submitted that its ES&G forecast for the test period should be approved, as filed.401
463. In reply argument, the CCA stated that ultimately all forecast ES&G costs would be
assessed for reasonableness either in a future DACDA application or in AET’s opening rate base
at the time of its next GTA.
392 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 33. 393 Exhibit 22742-X0001.02, Schedule 10-6 and Table 10.25. 394 Exhibit 22742-X0001.02, updated application, PDF page 391. 395 Exhibit 22742-X0001.02, updated application, PDF page 391, refers to International Financial Reporting
Standards, International Accounting Standard 16 for property, plant and equipment. 396 Exhibit 22742-X0001.02, PDF page 392. 397 Exhibit 22742-X0001.02, PDF page 393. 398 Exhibit 22742-X0001.02, PDF page 393. 399 Transcript, Volume 2 pages 355-347. 400 Exhibit 22742-X0533, the application update dated September 4, 2018. 401 Exhibit 22742-X0725, AET final argument, page 89.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 107
Commission findings
464. The Commission has examined the evidence in the application, in particular
Schedule 10-6,402 as well as the responses to IRs. Given this evidence, the forecast ES&G
amounts are approved as filed, subject to any changes necessary due to findings or directions
elsewhere in this decision.
465. The Commission agrees with the observation of the CCA that ES&G costs will be
reviewed either in a future DACDA application or as part of AET’s next opening rate base when
actuals are known and can be assessed for reasonableness.
11.8 Construction work in progress refund
466. In its original application, AET proposed to refund previously collected revenues related
to the construction work-in progress (CWIP)-in-rate base accounting treatment for AESO direct
assigned capital projects in the 2013-2016 period. It was AET's intention to refund
$130.8 million in each of 2018 and 2019 ($261.6 million total), including return on the CWIP
balances and income tax amounts collected in revenue requirement. In return, AET proposed to
add $123.1 million of AFUDC to rate base in each of 2018 and 2019 ($246.2 million total).403
467. In its September 4, 2018 application update, AET withdrew its CWIP-in rate-base refund
proposal. AET explained that since it prepared and filed its original application in the first half of
2017, its parent companies had experienced changes in circumstances, including a credit rating
downgrade issued by Standard & Poor's (S&P) in July 2017.404
468. Mr. Bell, on behalf of the UCA, supported AET’s initial proposal for the CWIP-in-rate
base refund. In his evidence, Mr. Bell stated that the collection of CWIP-in-rate base had resulted
in higher than necessary costs, with the result that customers paid higher than necessary rates for
the services they received. This is because CWIP-in-rate base allows for the collection of return
and income tax related to CWIP balances, effectively pre-funding the construction costs of new
assets. In Mr. Bell’s view, this pre-funding of assets created intergenerational inequities. That is,
during the “big build,” customers paid costs that were properly “due to”405 future customers.
Mr. Bell asserted that the refund of CWIP in-rate-base amounts, as initially proposed by AET,
would have put current customers in the same position they would have been in had the CWIP-
in-rate base credit metric relief not been granted.
469. Mr. Bell submitted that the S&P downgrade was largely a result of the pressure on credit
metrics caused by the Edmonton to Fort McMurray transmission line. He argued that this line
was not an AET asset and maintained that AET’s regulated customers should not be forced to
subsidize the credit metrics of one or more unregulated ATCO entities. He added that, for the
same time period, DBRS Limited (DBRS) issued no similar credit downgrade to AET’s parent
companies.406
402 Exhibit 22742-X0001.02, PDF pages 447-449. 403 Exhibit 22742-X0001.02, updated application, Section 3.8, page 117. 404 Exhibit 22742-X0533, paragraph 5. 405 Exhibit 22742-X0599, page 8. 406 Exhibit 22742-X0599, page 9.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 108
470. The UCA also noted that in the updated application, AET referred to “prevailing”
economic conditions407 as a reason to withdraw its offer to refund CWIP balances. The UCA
understood this to mean the “poor” economic conditions. The UCA submitted that, if this is what
AET actually meant, then those very same prevailing economic conditions dictate that a refund
of CWIP-in-rate base be issued to provide economic relief to present day customers.
471. Finally, the UCA noted that while the aim of including CWIP-in-rate base was to
improve credit metrics for AET, which may benefit customers, the UCA claimed it also
benefitted all of the ATCO group of companies. The UCA submitted that AET's customers
deserve to be reimbursed for having paid more than $200 million in higher than necessary rates
to provide AET with a source of financing for CWIP. The UCA proposed, pursuant to Rule 023:
Rules Respecting Payment of Interest, that customers be refunded an additional $31.5 million in
carrying costs on the $261.2 million refund.408
472. In rebuttal evidence, AET submitted that the UCA's claim that “the collection of funds
related to CWIP-in-rate base results in customers paying costs in excess of what would normally
be incurred” was factually incorrect and inconsistent with the findings provided in the AUC’s
Decision 2011-134409 on AET’s 2011-2012 GTA. In particular, AET noted, the Commission
stated as follows:410
532. The Commission also notes that by suspending the current construction work in
progress accounting procedures, in the long run, the overall cost to customers for new
assets is less than what it would be under the current … AFUDC accounting practice.
This is because it is always more expensive to postpone payment of an asset due to the
interest or return cost associated with postponing payments. As a simple analogy,
suspending this relief is similar to financing a home by putting a larger down payment on
a home at the outset. The home is less costly in the long run because the down payment
has reduced the amount of interest paid over the life of the mortgage. Therefore, in the
long run, the suspension of current construction work in progress accounting measures
[i.e., AFUDC] reduces the total cost of an asset because it reduces the amount of return
customers pay to the utility.
473. AET also maintained that there were no findings in Decision 2011-134 supporting the
UCA’s claims that customers were “forced to subsidize AET and ATCO” or that there was any
cross-subsidization occurring between AET and its affiliates as result of AET receiving approval
of the CWIP-in-rate base treatment during the 2011-2016 period. AET noted that the
Commission's decision to allow CWIP-in-rate base during the “big build” was made with
customers’ interests in mind. If no credit relief had been provided, CU Inc. may have
experienced a credit rating downgrade which would have led to higher borrowing costs for the
utility and, in turn, higher rates for customers.
474. AET stated that the UCA’s assertion that S&P provided a credit rating downgrade based
on the Fort McMurray transmission line ignored the evidence on the record and the clear
statement from S&P in the downgrade report that, “Over the past few years, these metrics have
407 Exhibit 22742-X0533, paragraph 5. 408 Exhibit 22742-X0599, page 12. 409 Decision 2011-134: ATCO Electric Ltd. 2011-2012 Phase I Distribution Tariff 2011-2012 Transmission
Facility Owner Tariff Application 1606228-1 Proceeding 650, April 13, 2011. 410 Decision 2011-134, paragraph 532.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 109
declined as the company411 embarked on a significant capital program.”412 AET claimed that this
statement suggested the “big build” had an impact on its parents’ credit rating. AET added that in
its most recent credit ratings report dated September 27, 2018, S&P clearly stated that the Fort
McMurray transmission line is excluded from its credit metric calculations.413
475. AET also responded to the UCA’s suggestion that customers have been “out of pocket for
over $200 million,”414 and deserved to be compensated for having financed CWIP. AET
submitted that this statement failed to recognize the inherent trade off between the CWIP-in-rate
base treatment and the AFUDC treatment. AET noted that in paragraph 532 of AUC Decision
2011-134 (reproduced above), the Commission explained that, in the long run, the overall cost to
customers for new assets was less than what it would be under the traditional AFUDC method.
476. AET submitted that no accumulated CWIP-in-rate base balance exists to which carrying
costs should be applied.415 AET explained that, under the traditional AFUDC method, the utility
internally funds the debt and equity obligations, as these are required (annually, at a minimum),
for its capital program prior to the asset going into service. As the utility funds the costs for these
obligations, the utility is then permitted to capitalize these costs and recover these financing costs
through return, depreciation and income tax over the life of the asset. As these financing costs
were funded through customer rates, AET did not capitalize any of these costs as it would have
done under the traditional AFUDC method. Since AET used the funds received from its
approved tariffs to meet its financing obligations as they arose, AET was left with no residual
funds provided by customers. As such, AET submitted that there was no basis to support
applying carrying charges to the amounts funded though CWIP-in-rate base.
477. In argument, ADC and IPCAA submitted that the Commission should approve AET’s
originally proposed refund in the 2018-2019 test period of $261.3 million in CWIP, collected
between 2013 and 2016.
478. ADC and IPCAA noted that the S&P credit report stated, in part:
A significant contributor to the stressed credit metrics is construction of the Edmonton to
Fort McMurray transmission line, which will continue to pressure credit metrics in the
medium term … Because we consider CU Ltd. and CU Inc. core to ATCO under our
group rating methodology criteria, we have equalized the ratings on the subsidiaries with
those on the parent.416
479. ADC and IPCAA argued that the reason for the S&P downgrade was largely a result of
the pressure on credit metrics caused by the Edmonton to Fort McMurray transmission line. As
this was not an AET asset, AET customers should not be asked to subsidize credit metrics for
AET’s parent. As such, it was the view of ADC and IPCAA that the S&P credit downgrade to
411 In the Commission’s view, the company in this context means ATCO Ltd. based on the following: “S&P Global
Ratings lowered its long-term corporate credit and senior unsecure debt ratings on Calgary, Alta.-based ATCO
Ltd. (ATCO), and its subsidiaries Canadian Utilities Ltd. (CU Ltd.) and CU Inc., to ‘A-’ from ‘A’.” See Exhibit
X22742-X0264.01, response to AET-UCA-2017AUG30-016(b), Attachment 10, page 2 of 7. 412 Exhibit 22742-X0264.01, AET-UCA-2017AUG30-016(b) Attachment 10. 413 Exhibit 22742-X0618, AET rebuttal evidence, Appendix A. 414 Exhibit 22742-X0599, Bell evidence on behalf of UCA, PDF page 11. 415 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 200. 416 Exhibit 22742-X0721, ADC IPCAA final argument, paragraph 13.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 110
AET's parent companies was irrelevant and, thus, provided no basis for withdrawing the earlier-
proposed refund.
480. ADC and IPCAA also stated that the need for CWIP-in-rate base to support the “big
build” has ended. They submitted that the associated balances must be refunded and doing so
now would not only minimize any intergenerational inequity, but would meet a pressing need for
lower rates for industrial electricity customers in the face of Alberta’s challenging economic
climate.
481. In its argument, the CCA opposed the CWIP in-rate base refund for the following
reasons:417
(i) Many of the reasons and conditions that supported a refund in AltaLink
Management Ltd.’s (AltaLink) 2015-2016 GTA are not present in the current
AET 2018-2019 GTA;
(ii) The refund of previously collected CWIP-in-rate base will result in a rate shock
for ratepayers of as much as 20 per cent in 2020 relative to 2019418 when base
rates no longer include the one-time refund;
(iii) The base rates going forward will be permanently higher for future ratepayers
beginning in 2020, which is not in the public interest; and
(iv) A refund is not needed to offset current forecast increases in the 2018 and 2019
test periods, both in the context of AET’s application and in the broader context
of regulated revenues for Alberta’s electric distribution and transmission utilities.
482. In its argument, the UCA continued to support the refund, stating that the customers of
today should not be required to prepay costs that are rightly attributable to customers of the
future, with the sole benefit being to potentially reduce rates in the future.419
483. The UCA noted that while AET relied upon different credit rating agency reports to
support its decision to remove the CWIP refund from its application, no witness from either of
the agencies that prepared those reports appeared during the oral hearing. In the absence of a
rating agency witness capable of speaking to any of the credit ratings reports filed on the record
of this proceeding, the UCA maintained that all parties and the Commission were required to rely
solely on information provided on the face of the documents.420
484. The UCA submitted that based upon a review of the credit ratings reports filed in this
proceeding, it was apparent that the pressure on ATCO Ltd.’s credit ratings, and the credit
downgrade for AET's parents in the July 25, 2017 S&P report, was overwhelmingly the result of
unregulated activities, rather than those of a regulated entity like AET. The UCA pointed out that
S&P expressly stated that the Edmonton to Fort McMurray transmission line was a “significant
contributor to the stressed credit metrics.”421
417 Exhibit 22742-X0613, CCA-AUC-2018DEC19-012 Attachment 1, Sections 2.1-2.3. 418 Exhibit 22742-X0722, CCA final argument, paragraph 175. 419 Exhibit 22742-X0599, page 8. 420 Transcript, Volume 4, page 619, lines 13-18. 421 Exhibit 22742-X0724, UCA final argument, page 11.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 111
485. The UCA also noted that S&P stated that it has “equalized the ratings on the subsidiaries
with those on the parent.”422 The UCA submitted423 that this seemed to imply that the parents’
ratings have been weighted down because of the unregulated activities of the ATCO group of
companies. In the absence of evidence to the contrary, it appeared to the UCA that customers of
regulated entities were being asked to provide support to the credit metrics of unregulated
entities. The UCA considered this inappropriate and unfair.424
486. The UCA noted that the Commission has ruled on the issue of refunding previously
collected CWIP-in-rate base amounts before, such as in Decision 3524-D01-2016 dealing with
AltaLink’s 2015-2016 GTA.425 The UCA further noted that there were similarities between
AltaLink’s proposed refund of CWIP balances and the CWIP refund that was initially proposed
by AET in this proceeding.
487. In light of the similarities between this proceeding and Proceeding 3524 for AltaLink, the
UCA submitted that the CWIP refund is in the public interest. Specifically, the evidence on the
record provides that the CWIP refund would not result in intergenerational inequities426 and
the resulting FFO-to-debt ratio would be sufficient to maintain a credit rating in the lower “A”
range. The CWIP refund is further supported by the fact that AET ratepayers continue to face
the economic challenges in Alberta that were present when AET initially proposed the CWIP
refund.427
488. The UCA referred to Commission counsel's questioning of Mr. Bell on whether the
refund should be treated as no-cost capital.428 Mr. Bell stated on the question of carrying costs
versus no cost capital that: “They to me are two ways to try to get to the same thing, to
compensate customers for the fact that the utility had those funds at their disposal in the
intervening year. And so I see either as acceptable. I prefer the Rule 23, but either would be
acceptable.”429
489. AET commented on the UCA's recommendation that the CWIP refund occur over the
2018-2019 period, given the prevailing economic conditions. In this regard, AET noted that
in each of the Commission's past three decisions dealing, respectively, with AET's 2011-
2012, 2013-2014 and 2015-2017 test periods, where the CWIP-in-rate base treatment was
approved, there was no stipulation or expectation expressed that a refund to customers
would occur once AET returned to the traditional AFUDC method or, indeed, at any point in
the future. AET submitted that it has provided strong support for not implementing a refund
of the CWIP-in-rate base due to both the credit rating downgrade by S&P in July 2017, as
well as the current economic circumstances in Alberta. In its rebuttal evidence, AET
included the most recent S&P credit rating report, dated September 27, 2018. In this report,
S&P noted the removal of the initially proposed CWIP-in-rate base refund and reflected this
422 Exhibit 22742-X0611, PDF page 6, UCA-AET-2018DEC21-001(b). 423 Exhibit 22742-X0264.01, AET-UCA-2017AUG30-16(b), Attachment 10, PDF pages 98-99. Also noted in
Exhibit 22742-X0721, ADC and IPCAA final argument, paragraph 13. 424 Exhibit 22742-X0724, UCA final argument, paragraph 29. 425 Decision 3524-D01-2016, AltaLink Management Ltd.’s (“AML”) 2015 – 2016 General Tariff Application. 426 Exhibit 22742-X0202, PDF page 77, AET-CCA-2017AUG30-132 (b). 427 Exhibit 22742-X0599, page 22. 428 Transcript, Volume 7, page 1297-1300. 429 Transcript, Volume 7, page 1300, lines 12-16.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 112
in its "base case" scenario.430 As such, AET submitted that the request included in its
application update be approved, as filed.
490. In its reply argument, the UCA noted that in decisions 2011-453 and 2013-407, in which
the Commission approved CWIP-in-rate base treatment for AltaLink, the Commission made no
reference to a future refund of CWIP once AltaLink returned to the AFUDC method or at any
other point in the future. Nevertheless, the Commission approved the refund of previously
collected CWIP-in-rate base amounts in Decision 3524-D01-2016.13
491. AET noted that, in their argument,431 ADC and IPCAA maintained that it was appropriate
to return to ratepayers the temporary relief provided to AET. AET disagreed with this assertion
and noted that ADC and IPCAA provided no evidence to support why such a course of action is
required or appropriate. AET made it clear that it was under no obligation to bring forward a
proposal to refund past CWIP-in-rate base amounts.
492. AET challenged the UCA's insistence on attributing the credit rating downgrade in July
2017 to non-regulated activities.432 According to AET, this selective view of the S&P reports
ignores the comments actually made by S&P, namely, that: “Over the past few years, these
metrics have declined as the company embarked upon a significant Capital Program.”433
493. Finally, AET observed that in approving AET's original request to include CWIP-in-rate
base treatment, the Commission, in Decision 2011-134,434 confirmed that it must have regard to
the impact its decision will have on the financial health of the utility it regulates. AET submitted
that the same considerations apply in the circumstances of this application. AET stated that it had
valid and legitimate concerns regarding the potential for a further credit rating downgrade, based
on the observations made by S&P in its September 2018 report.
Commission findings
494. In Decision 3524-D01-2016,435 associated with a refund of CWIP in AltaLink’s 2015-
2016 GTA, the Commission made the following determinations:
For the above reasons, the Commission finds it to be in the public interest to approve
AltaLink’s proposed refund of the previously collected CWIP-in-rate base amounts,
subject to the following adjustments:
AltaLink is permitted to refund the CWIP-in-rate base amounts collected for
DACDA projects, with the exception of those projects that have been finalized in
Decision 2013-407 or in Decision 2044-D01-2016.
The amount of the accumulated return, depreciation and taxes accruing to AltaLink
on the AFUDC portion of capital additions that would have been added to rate base
in the years 2012 to 2014 will be accounted for in the DACDA proceedings for each
430 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 213. 431 Exhibit 22742-X0721, ADC and IPCAA final argument, page 1. 432 Exhibit 22742-X0724, UCA final argument, pages 8-9. 433 Exhibit 22742-X0264, page 98. 434 Decision 2011-134: ATCO Electric Ltd. 2011-2012 Phase I Distribution Tariff 2011-2012 Transmission
Facility Owner Tariff, Application 1606228,-1 Proceeding 650, April 13, 2011. 435 Decision 3524-D01-2016: AltaLink Management Ltd. 2015-2016 General Tariff Application, Proceeding 3524,
Application 1611000-1, May 9, 2016.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 113
of the relevant projects. AltaLink is to adjust all DACDA projects not approved on a
final basis in Decision 2013-407 or in Decision 2044-D01-2016 to include AFUDC
in accordance with normal historic regulatory accounting practices in its compliance
filing and file an update that includes the relevant AFUDC-related amounts in
Proceeding 3585.
Customers and AltaLink are to be kept revenue neutral from any adjustment made to
the above DACDA projects in AltaLink’s applications, by refunding the accumulated
return on CWIP balances that were paid to AltaLink, in addition to any return earned
on those amounts, calculated based on the WACC for the period from the date on
which the amounts were received, and accounting for any other impacts.436
495. The principle, which was espoused in Decision 3524-D01-2016 for AltaLink dealing with
the application for a refund of CWIP-in-rate base, was that customers and the utility are to be
kept revenue neutral from any adjustment made to capital projects, by refunding the accumulated
return on CWIP balances paid. In addition to any balances paid, adjustments are made to returns
earned on those amounts, calculated based on the weighted average cost of capital for the period
from the date on which the amounts were received, and accounting for any other impacts.437 The
adjustment of CWIP accounts for customers effectively contributing funds in excess of what
would have been required through AltaLink's revenue requirement under AFUDC.438
496. In its September 2018 application update, AET’s original proposal to refund accumulated
return on CWIP balances was withdrawn by AET. Mr. Bell, on behalf of the UCA, stated that
AET’s original proposal to refund accumulated return on CWIP-in-rate base, puts customers on a
level playing field because “during the period of the big build, customers were effectively
required to pre-fund construction costs of assets in rates in support of utility credit metrics.”439
The UCA accepted this position of Mr. Bell and recommended that the CWIP amount of
$261.2 million be refunded to customers.440
497. AET stated that it withdrew its request for a CWIP-in-rate base refund because its parent
experienced changes in circumstances, including a credit rating downgrade in 2017. The UCA
opposed AET’s withdrawal of its request and argued that AET should be required to refund its
previously collected CWIP-in-rate base amounts and re-apply the capitalized interest (which is
AFUDC) in accordance with normal historical regulatory accounting practices.
498. Parties registered in the proceeding are split in their views as to whether AET should
refund previously collected CWIP-in-rate base amounts. The UCA, ADC, and IPCAA requested
that the Commission direct AET to refund the CWIP-in-rate base amounts, while the CCA and
AET are opposed to any suggestion that AET be required to refund these amounts.
499. The UCA, as acknowledged by its witness, Mr. Bell, did not review AET’s original
proposal in detail:
Q. Okay. And did you review ATCO Electric's calculations of its proposed refund for the
CWIP in rate base?
436 Decision 3524-D01-3524, paragraph 953. 437 Decision 3524-D01-2016, paragraph 953. 438 Decision 21827-D01-2016, paragraph 81. 439 Exhibit 22742-X0599, Bell evidence on behalf of the UCA, page 8. 440 Exhibit 22742-X0724, UCA final argument, paragraph 64.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 114
A. I reviewed them in general, and -- but I didn't do any detailed calculations to validate
them.441
500. The UCA’s primary ground for requesting that AET be directed to refund previously
collected CWIP-in-rate base amounts, relates to intergenerational inequity. In the UCA’s view,
“customers of today should not be required to prepay costs that are rightly attributed to
customers of the future, with the sole benefit being to potentially reduce rates in the future.”442
501. With respect to financing the costs of capital assets, in Decision 2011-134, the
Commission stated the following:
549. The Commission, pursuant to Section 122 of the Electric Utilities Act, when
approving a tariff, must have regard to the impact that its decision will have on the
financial health of the utility it regulates. As well, the Commission must also ensure that
it minimizes the effects on consumer rates. In circumstances where capital expenditures
are forecast to be much higher than in the past, the traditional rate regulatory accounting
approach may not allow the Commission to effectively carry out those tasks. Therefore,
the Commission must respond. In this proceeding, the Commission has chosen to respond
by allowing the utility to recover the financing costs of the assets (but not the costs of the
assets) through rates today so that the utility can maintain its financial health and keep its
interest costs and other financing costs down during the construction period. Further,
customers are not burdened by higher interest and other financing costs today and
customers ultimately pay less overall for the new assets that may be approved and
constructed.443
502. In past decisions approving AET’s request for collecting CWIP-in-rate base to support its
credit metrics during what has been referred to as the “big build” period, the Commission took
into account that AET’s credit metric relief from CWIP-in-rate base would reduce the financing
costs, which would be passed onto customers through lower future rates. AET was allowed to
include CWIP-in-rate base in its revenue requirement from 2011 to 2016, with the Commission
determining that credit metric support from CWIP-in-rate base was no longer required in 2017.444
503. In this proceeding, the Commission must determine whether refunding the accumulated
return on CWIP balances paid by AET’s ratepayers assists in preserving the financial integrity of
the utility and/or avoids causing it financial hardship. Consistent with earlier established
principles, the Commission also considers that customers and the utility must be kept revenue
neutral from any adjustments made to capital projects, should a refund of the accumulated return
on CWIP balances be ordered. The Commission finds insufficient evidence on the record of this
proceeding to support the recommendation of the UCA, ADC and IPCAA for AET to issue a
refund of CWIP-in-rate base. In particular, there is no evidence to suggest that such a refund
would be revenue neutral, nor have any calculations of the proposed refund been verified or
subjected to critical scrutiny.
504. The Commission accepts AET’s position that no CWIP-in-rate base refund is required or
was ever a condition of granting CWIP-in-rate base at first instance. The Commission is also not
441 Transcript Volume 7, page 1298, lines 3-6. 442 Exhibit 22742-X0724, UCA final argument, paragraph 19. 443 Decision 2011-134, paragraph 549. 444 Decision 20272-D01-2016, paragraph 1310.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 115
persuaded in the circumstances of this proceeding that a claim of intergenerational inequity or
concerns about the FFO-to-debt ratio alone are sufficient to require a CWIP refund.
505. Parties extensively commented on the circumstances of a previous AltaLink refund of
CWIP-in-rate base. The Commission notes that the AltaLink CWIP-in-rate base refund that was
ultimately approved by the Commission in Decision 22930-D01-2017445 was related to a broader
proposal for credit relief. This is illustrated in paragraph 2 of Decision 3524-D01-2016, dealing
with AltaLink’s 2015-2016 GTA, where the Commission accepted the tariff relief and credit
metric support for:
The use of subordinated debt.
The discontinuance of the collection of CWIP-in-rate base amounts and the return to
AFUDC accounting effective January 1, 2015.
The refund to customers of the CWIP-in-rate base amounts for capital projects for the
years 2012 to 2014.
The application of the future income tax method for calculating income taxes for 2015
and the flow-through method for calculating income taxes for 2016.
506. The circumstances for a CWIP refund for AET are not comparable to those in the
AltaLink proceeding. The Commission accepts that AET has withdrawn its CWIP-in-rate base
proposal because of the credit rating downgrade.
507. For these reasons, the Commission denies the UCA’s proposal to direct AET to refund
previously collected CWIP-in-rate base amounts.
12 Necessary working capital
508. Necessary working capital is added to total rate base when payment of expenses occurs in
advance of the receipt of revenues.
509. In Decision 20272-D01-2016, the Commission directed AET to “prepare and file an
updated comprehensive lead/lag study as part of its next GTA application.”446 AET complied
with this direction by filing its 2016 lead/lag study in the current application. AET submitted that
the methodology used to prepare its study was consistent with its “previously approved 2013
study.” The 2016 study resulted in a change of lead/lag days from 212.81 to 223.10, mainly due
to “an increase in the operating expense lag for flow-through property tax payments to AED.”447
510. AET stated that the 2016 lead/lag days were applied to the 2016 actual revenues and
operating expenses to determine the net transmission operating expense lag. The updated
weighted revenue lag days, based on the 2016 actual revenues, were then applied to the 2016
445 Decision 22930-D01-2017: AltaLink Management Ltd., 2015-2016 General Tariff Application Third
Compliance Filing, Proceeding 22930, December 22, 2017. 446 Decision 20272-D01-2016, paragraph 1231, Direction 84. 447 Exhibit 22742-X0001.02, updated application, paragraphs 487-490.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 116
lead lag results for income tax, depreciation, interest expense, preferred equity and common
equity to determine the net lag days for these components of working capital.
511. A summary of the proposed necessary working capital by component is shown in the
table below:
Table 34. Summary of transmission necessary working capital
Description
2015 Actuals
2016 Actuals
2017 Actuals
Test period
2018 2019
($ million)
Operating expense 12.9 11.4 12.2 8.7 8.6
Income tax expense (1.9) 0.4 0.2 0.4 1.3
Materials & Supplies inventory 3.7 3.7 3.2 2.9 2.5
Rate case expense 1.9 1.0 0.2 (0.3) (0.2)
Goods & services tax 0.4 0.3 0.3 0.1 0.1
Depreciation expense 16.8 22.6 23.0 23.6 24.0
Unamortized debt costs 16.3 16.6 15.9 15.5 15.3
Unamortized preferred share costs 0.2 0.0 0.0 0.0 -
Interest expense (19.3) (19.4) (18.8) (18.4) (18.4)
Preferred equity (0.0) (0.0) (0.0) (0.0) (0.0)
Common equity (retained earnings component) 9.3 11.0 11.6 9.9 9.9
Common equity (dividend component) (0.1) (0.1) (0.2) (0.1) (0.1)
Total necessary working capital 40.2 47.3 47.7 42.2 43.0
Source Exhibit 22742-X0002.04, GTA schedules, Schedule 11-1
512. The CCA submitted that AET’s working capital calculation does not properly reflect the
timing of its VPP payment because “AET [ATCO Electric - Transmission] is receiving the
revenues well in advance of requiring a payment of VPP.”448 Specifically, the CCA stated, “AET
receives revenues in its revenue requirement for the payment of VPP but does not actually pay
VPP until the following year, often at the end of the first quarter….”449
513. Similarly, the CCA argued that the timing of AET’s base salary increases was delayed to
the beginning of the second quarter, resulting in a delay of when actual payments were made
compared to when forecast payments were to be received.450
514. As a result, the CCA requested that the Commission direct AET to revise its working
capital calculations to properly reflect the timing of the VPP payments and the base pay salary
increases.
515. AET rejected the CCA’s assertion that an adjustment was required to its necessary
working capital calculations for VPP payments. It pointed out that during the oral hearing,
448 Exhibit 22742-X0722, CCA final argument, paragraph 769. 449 Exhibit 22742-X0722, CCA final argument, paragraph 768. 450 Exhibit 22742-X0722, CCA final argument, paragraph 770.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 117
AET’s witness, Mr. Hoshowski, “outlined where the lag in the VPP payments is reflected in the
GTA schedules and the lead/lag study.”451
516. AET also challenged the CCA submission that an adjustment to necessary working
capital was required to account for the timing of base pay salary increases. It explained as
follows:
… The referenced increase in base salary and the associated delay is only applicable to
out-of-scope employees, whose salary increases typically occur on April 1, versus in-
scope employees whose increases occur effective January 1 each year. AET submits that
no adjustment is required, given that AET develops its O&M/A&G labour forecast for
out-of-scope labour based on the labour costs that properly consider the economic
increase in labour costs on April 1 and properly reflects this over the remaining nine
months of the year …452
Commission findings
517. The Commission observes that the majority of the decrease in necessary working capital
for the test period relative to 2016 and 2017 actuals, as shown in Table 34 above, results from an
increase in the operating expense lag for flow-through property tax payments to AED. This then
lowers the number of net lag days being used for the operating expense working capital
calculation from 30.2 days to 20.1 days.
518. The Commission has reviewed the 2016 lead/lag study included in the application. The
Commission finds that AET has complied with Direction 84 from Decision 20272-D01-2016,
which required the filing of an updated comprehensive lead/lag study.
519. After reviewing the responses provided by AET to the CCA’s proposed adjustments to
necessary working capital based on the timing of VPP payments and base pay salary increases,
the Commission finds that the concerns underlying the CCA's proposed adjustments were
without foundation. AET has adequately responded to the CCA’s request for adjustments to
necessary working capital by explaining that the lag in VPP is reflected in its schedules and with
the reasons why an increase to account for base pay salary increases is not required. The
Commission therefore rejects the CCA’s recommendations.
520. The Commission approves the necessary working capital test period forecasts as filed
subject to any adjustments that may be required based on the direction above. The Commission
directs AET, in the compliance filing, to reflect all findings and determinations in this decision
that affect the necessary working capital calculations.
13 Isolated generation operating costs
521. AET included isolated generation operating costs in Section 22 of its application. The
updated forecast isolated generation operating costs for 2018-2019, are reflected in the table
below:
451 Exhibit 22742-X0727, AET reply argument, paragraph 186. 452 Exhibit 22742-X0727, AET reply argument, paragraph 188.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 118
Table 35. Isolated operating costs 2015-2017
2015 2016 2017 2018 2019
Actuals Actuals Actuals Test year Test year
($ million)
Operating costs 7.1 5.7 5.5 5.4 5.3
Increases (Decreases) in Forecast/Test period (1.4) (0.2) (0.1) (0.1)
Due to:
Combustion engines/Turbine operations (0.6) (0.1) (0.1) 0.0
Combustion engines/Turbine maintenance (0.5) (0.1) 0.1 (0.1)
Other expenses (0.2) 0.0 (0.1) (0.1)
Source: Exhibit 22742-X0001.02, updated application, Table 22.2 – Isolated Operating Costs, PDF page 515.
522. AET explained that it owned and operated eight generation plants serving isolated
communities, one plant serving an industrial customer and a fleet of eight mobile generator sets
for emergency backup services. In addition, AET maintains 66 isolated generating plants for
telecommunication and substation backup generation, four isolated generating plants for main
supply to isolated telecommunication sites and one synchronous condenser at the Arcenciel
substation.453
523. AET stated that forecasts of decreased costs reflected the interconnection of the Garden
River site in December 2017 and were partially offset by contingency requirements at Jasper
Palisades because of the delay in the Jasper interconnection project.454
524. In final argument, AET submitted that no material issues arose regarding forecast isolated
generation operating costs. AET requested that the amounts for the test years be approved, as
filed.455
525. The CCA provided the following table regarding past isolated generation operating costs:
Table 36. CCA submission on approved versus actual isolated generation operating costs
Year Approved456 Actual Variance
(Approved – Actual)
($ million)
2015 6.3 7.1 (0.8)
2016 7.8 5.7 2.1
2017 8.1 5.5 2.6
Total 3.9
Source: Exhibit 22742-X0726, CCA reply argument, paragraph 144.
526. The CCA argued that the combined variance (where actuals are less than the approved
amounts) over the previous three-year test period of 2015-2017 was 17.6 per cent in AET’s
favour. The CCA stated that the variance is material and reflects low forecasting accuracy for
those costs. Further, given the removal of isolated generation operating costs for communities
like Jasper and the potential for further efficiencies, the CCA recommended that AET’s forecast
453 Exhibit 22742-X0001.02, updated application, paragraphs 493-494. 454 Exhibit 22742-X0001.02, updated application, paragraph 497. 455 Exhibit 22742-X0725, AET final argument, paragraph 304. 456 Exhibit 22742-X0726, CCA reply argument, paragraph 144, derived from Proceeding 22860, Exhibit 22860-
X0006.01 (ATCO Electric Transmission Second Compliance Filing to Decision 22050-D01-2017),
Attachment 4, Schedule 5.1.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 119
for operating costs be reduced by five per cent in addition to any other adjustments, such as
escalation rates, FTEs and vacancy rates.457
Commission findings
527. The Commission notes that the CCA’s submissions on isolated generation operating costs
were brought forward only in reply argument. The CCA chose not to address this issue in its
evidence (Exhibit 22742-X0595), during the oral hearing, or in final argument. By advancing the
issue only in reply argument, the CCA has provided AET with no opportunity to respond. The
Commission weighs the CCA’s submissions on this matter accordingly.
528. In its application, AET elaborated upon its forecast as follows:
Decreases during the Test Period are primarily associated with reduced labour
requirements as a result of role consolidation and reduced maintenance requirements due
to the interconnection of Garden River in December 2017. These cost reductions are
offset by contingency requirements at Jasper Palisades because of the delay in the Jasper
Interconnection project. Based on a risk assessment, the resulting delays require an
updated contingency plan for the 16 months of operation remaining until Jasper is
interconnected. This plan involves renting, installing and removing a temporary natural
gas engine if a large (greater than 2.8MW) engine were to fail while Astoria Hydro is not
able to generate sufficient capacity. This updated contingency plan is required to ensure
the reliability of the isolated system prior to interconnection.458 [emphasis added]
529. According to Table 22.1459 of AET’s updated application, the Jasper Interconnection
Project is expected to be completed on December 30, 2019. It appears to the Commission that
any benefits from the Jasper Interconnection Project will not be realized until 2020. In addition,
the Commission notes that forecast isolated operating costs are projected to marginally decline in
each of the test years relative to 2016 and 2017 actuals. The Commission finds this consistent
with the delay for the Jasper Interconnection Project.
530. The Commission accepts the submissions from AET regarding the timing of the Jasper
Interconnection Project. Further, the Commission considers that the CCA was not specific as to
what further potential efficiencies are available to AET, nor how it derived the five per cent
reduction in operating costs it recommended. The CCA’s requested reduction to the forecast
costs is denied.
531. Therefore, subject to Commission determinations in other parts of this decision, the
Commission approves AET’s isolated generation operating costs as filed.
14 Shared services and common group costs
14.1 Shared services
532. In the application, AET stated that as part of its ongoing efforts for continuous
improvement, AET and the ATCO group of companies have been developing a comprehensive
457 Exhibit 22742-X0726, CCA reply argument, paragraphs 144-147. 458 Exhibit 22742-X0001.02, updated application, paragraph 497. 459 Exhibit 22742-X0001.02, updated application, paragraph 495.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 120
ATCO-wide460 shared services model for certain common functions. This model will bring
together similar work functions to provide standardized internal services on a cost recovery basis
consistent with the ATCO Group Inter-Affiliate Code of Conduct. Examples of these functional
areas include financial services, treasury, regulatory, human resources, fleet and facilities
management, and supply chain. Some of these functions currently reside within ATCO’s
corporate office, some reside within the individual ATCO companies and operating divisions,
and some are currently performed and allocated to a common group function.461 Common group
functions are those performed at an ATCO Electric group level with the costs being allocated to
the operating divisions, AET and AED.
533. In its application update,462 AET explained that it had updated its forecasts to include
2018 actual common costs up to July 2018. The remaining 2018 forecasts were based on the
approved activity-based forecasting methodology, including the updated cost factors known as of
July 2018 (e.g., workforce reductions). Considering that the updated forecast included
efficiencies gained in the first half of 2018 through the re-evaluation of work and staffing
requirements, including shared service groups, AET stated that the reductions that were intended
to be captured by the productivity factor initially proposed and later withdrawn, were now
embedded in the updated revenue requirements for 2018 and 2019.
534. AET also presented an analysis that captured the forecast costs to be allocated to AET for
the functions outlined under the shared services model,463 and compared this to the forecast costs
included in the application update for the same functions. AET stated that the table below shows
the costs were not materially different from each other:
Table 37. Shared services comparison
Operating costs 2018 comparison 2019 comparison
($ million)
GTA forecast costs – related to shared service functions 7.2 6.6
Shared services costs – allocated to AET 7.0 6.9
535. In AET’s view, the comparison in the table demonstrates that the activities and functions
result in costs that need to be incurred regardless of whether they are directly embedded in
AET’s forecast or allocated through the shared services model.
536. Given the lack of information about AET’s forecast shared services allocations, the CCA
recommended that the Commission either consider the shared services initiative and related
allocations as part of a future AET GTA or in a generic proceeding to consider the impact of the
shared services allocations on all of the ATCO subsidiaries. The CCA identified a list of issues
with respect to AET’s shared services allocation that it maintained were not adequately
explained.464
460 Refers to ATCO Ltd. This is a corporate-wide initiative. 461 Exhibit 22742-X0001.02, updated application, page 10. 462 Exhibit 22742-X0533, page 30. 463 Exhibit 22742-X0417, page 6. 464 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, pages 180-181.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 121
537. AET concurred with the CCA that the new shared services model should be tested as part
of AET’s next GTA indicating that testing the new methodology in the current GTA would not
be feasible, nor would it promote regulatory efficiency.465
538. In its argument, AET noted that in response to AET-AUC-2018JUN08-002,466 it provided
an update on the shared services initiative, including the operating model of the shared services
functions. AET added:
During the course of questioning by Commission Counsel, an Aid-to-Cross (Ex. X0648),
was introduced and questions posed to AET regarding the use of a KPMG report for
purposes of determining allocation factors under the shared services methodology. This
Aid-to-Cross is a KPMG report filed in the ATCO Pipelines GRA, that is currently
before the Commission. AET acknowledged that it was aware of the KPMG report, but
did not file it in this case, as it was not relying upon it for purposes of supporting the
reasonableness of the amounts allocated to AET for the 2018 and 2019 Test Years.
Rather, as detailed in its Application Update, AET continues to rely upon costs based on
the approved activity-based forecasting methodology. AET has confirmed, as outlined
above, that there was no material difference in the forecast cost derived under either
methodology. Therefore, it was not appropriate to file the KPMG report in this
proceeding (4T707-711).
In the end result, AET submits that the amounts included in its 2018-2019 GTA forecasts
properly reflect the costs associated with the shared services that AET will utilize during
the Test Period. This is based on an assessment of the most recent information available
and supports the quantum of costs included in AET’s Application for approval. As noted,
AET's allocation methodology for shared services costs will be explored in greater detail
in its next GTA.467
539. The CCA acknowledged AET’s argument that there was no material difference between
the costs it was proposing based on its September 2018 updated application and those proposed
in the KPMG report468 filed in ATCO Pipelines’ 2019-2020 GRA proceeding (Proceeding
23793). However, the CCA countered that the information from the KPMG report had not been
vetted in this proceeding and therefore cannot be assigned any weight as evidence. The CCA
maintained that the Commission should approve the cost reductions it had proposed for
individual O&M accounts.469
Commission findings
540. The Commission notes that AET’s application relies on operating cost forecasts based on
the existing activity-based forecasting methodology. The shared services initiative has not been
fully implemented nor has AET requested that the Commission approve the new methodology in
the current proceeding. The Commission considers that further review of the shared services
initiative should be deferred to a future proceeding where it can be thoroughly examined. The
shared services initiative and approval of a new shared services methodology was a live issue in
465 Exhibit 22742-X0618, AET rebuttal evidence, page 156. 466 Exhibit 22742-X0417. 467 Exhibit 22742-X0725, AET final argument, paragraphs 144-145. 468 Exhibit 22742-X0648. 469 Exhibit 22742-X0726, CCA reply argument, paragraphs 84-85.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 122
the ATCO Pipelines’ proceeding (Proceeding 23793). In Decision 23793-D01-2019470 issued on
June 25, 2019, the Commission directed ATCO Pipelines to coordinate with AET to ensure
consistent information on the shared services initiative in each of their next GRA and GTA,
respectively. The Commission went on to enumerate the nature of the information required,
including the filing of cost information for all ATCO affiliates to substantiate the costs allocated
to all regulated ATCO entities. The Commission in the current proceeding similarly directs AET
to coordinate with ATCO Pipelines to ensure that both utilities provide the same or substantially
similar information in the same format in support of the shared services in their next respective
GRA and GTA, preferably filing common documents wherever possible. The information should
include evidence supporting the functions created, justifying total FTEs and costs before
allocation to the participating ATCO companies (AET and all other regulated and non-regulated
ATCO entities), and include any analysis, studies and calculations that explain and support the
reasonableness and accuracy of the allocation methodologies. The Commission finds that it
would also be beneficial to show all calculations that demonstrate the split between O&M and
capital under the shared services initiative in the next GRA and GTA. This common information
will allow for a proper testing of the shared services and for the provision of company specific
information to support shared services costs included in the proposed revenue requirements.
Accordingly, the Commission directs AET to provide the evidence, analyses, studies and
calculations noted above as well as any underlying assumptions for the split between O&M and
capital in its next GTA.
541. The Commission acknowledges that of the ATCO companies, AED and ATCO Gas are
under performance-based regulation and are subject only to minimum filing requirement
schedules. However, further information about common costs are required to support the costs
allocated to AET. As such, AET is directed, on a go-forward basis, to provide all cost
information for every ATCO affiliate, comprising the total costs and supporting detail that
substantiate and justify the costs allocated to AET relative to the other regulated and non-
regulated ATCO companies under the shared services initiative.
542. The forecast operating costs are addressed in other areas of this decision, specifically, in
Section 7 (O&M) and Section 15 (Corporate administration and general).
14.2 Shared services - productivity factor
543. In its original application, AET proposed that a productivity factor of 0.3 per cent be
applied against the 2018 and 2019 operating and capital maintenance forecasts to reflect the
potential savings from its shared services initiative (discussed in Section 14.1). In AET’s
September 2018 application update, the productivity factor was withdrawn and AET stated:
AET has updated the forecast to include 2018 actuals up until July 2018 and factored
those components into costs for the remaining 2018 period based on the approved
activity-based forecasting methodology, including efficiencies such as workforce
reductions. It is important to note that these activities and functions result in costs that
need to be incurred regardless of whether they are directly imbedded in AET or allocated
through the shared service model.471
470 Decision 23793-D01-2019: ATCO Pipelines, 2019-2020 General Rate Application, Proceeding 23793, June 25,
2019. 471 Exhibit 22742-X0001.02, updated application, paragraph 25.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 123
544. Bema recommended that the Commission approve a 0.3 per cent productivity factor,
based on total operating and capital maintenance costs to adjust for likely efficiencies that may
be gained as AET’s shared services initiative continues to mature.472 The CCA argued the
following based on Bema’s recommendations with respect to the productivity factor:
Accordingly, while Bema has proposed a productivity factor of 0.3%, it is important to
emphasize a few important considerations. First and foremost, the proposed productivity
factor should not be taken as an alternative to the other proposed operating costs
reductions proposed by Bema. To the contrary, this productivity factor is an additional
reduction applied only after AET’s forecast operating costs reflect known efficiencies
that should be gained or otherwise are adjusted for unsupported or unreasonable costs. In
other words, the 0.3% productivity factor reflects the potential further efficiencies that
AET should be expected to achieve after the proposed reductions are implemented as
Bema recommends.473
545. In its argument, the CCA acknowledged that there was no analytical or statistical basis
for the 0.3 per cent productivity factor it was recommending.474
546. In its rebuttal evidence, AET reiterated its opposition to including the productivity factor,
explaining that it was introduced over a year and a half ago when AET was still considering how
to deal with shared services. AET stated that it now has included efficiencies such as workforce
reductions into the forecast, making the productivity factor no longer relevant or appropriate.475 It
added that:
… Including known and likely costs in a forecast is supported in Bema’s evidence, where
they state “AET’s forecast costs should include all known or likely efficiencies to ensure
that the costs approved by the Commission have a reasonable chance of reflecting actual
costs.” In the September update, given the length of time since the original Application,
AET has included “known or likely efficiencies” in the forecast. As a result, it would be
inappropriate to apply an additional productivity factor to the forecast, as this would
constitute double counting of these savings that are know [sic] embedded in the new
forecasts. [footnote and emphasis removed]476
547. The CCA emphasized that the productivity factor is not intended to adjust for known
efficiencies. Rather, it is intended to adjust for unknown but likely efficiencies. According to the
CCA, it is clear that AET’s forecast has only adjusted for known efficiencies, not unknown but
likely efficiencies.477 As a result, including the productivity factor would not result in double
counting.478
472 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 581. 473 Exhibit 22742-X0722, CCA final argument, paragraphs 626-628 and Transcript, Volume 7, page 1214, line 1 to
page 1216, line 5. 474 Exhibit 22742-X0612, CCA-AUC-2018Dec19-015, PDF pages 40-41. 475 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 153. 476 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 153. 477 Exhibit 22742-X0722, CCA final argument, paragraph 630. 478 Exhibit 22742-X0722, CCA final argument, page 186.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 124
Commission findings
548. In its updated application, AET stated that it considered actual amounts to the end of
July 2018 and used the activity-based forecasting methodology to determine its forecast
operating amounts. The forecast amounts contain known or likely efficiencies.
549. The CCA, by its own admission, acknowledged that the 0.3 per cent productivity factor is
not analytically or statistically based. The CCA stated it did not conduct a thorough review of
different productivity factors that may be appropriate for AET. In response to questioning from
Commission counsel, the CCA reiterated its position that an additional productivity factor
adjustment was required to reflect an incentive to achieve further efficiencies beyond known or
likely efficiencies.479
550. The Commission is not persuaded by the CCA’s argument given that AET has included
in its updated application forecast operating costs incorporating known or likely efficiencies. In
the Commission’s view, the CCA has failed to provide sufficient analytical or statistical evidence
to reasonably support a 0.3 per cent productivity factor to account for unknown efficiencies that
might arise from AET’s shared services during the test period. Without such evidence to support
the CCA’s position, it is impossible for the Commission to determine whether double counting
would result if a 0.3 per cent productivity factor was approved. Therefore, the Commission
denies the CCA’s request to have a 0.3 per cent productivity factor applied to the shared services
included in AET’s operating and capital maintenance forecasts for 2018 and 2019.
14.3 Common group costs
551. AET stated that the allocators used in this application are consistent with those allocators
approved in Decision 21701-D01-2017480 for the ATCO Electric Transmission Division
Common Group Application.481 AET explained that the allocation of the common group costs
within ATCO Electric Ltd., both the transmission and distribution divisions, was planned to
continue while the overall shared services initiative outlined in the application continues to take
shape.482
552. In addition to the common groups483 included in the common group application, AET also
included key customer accounts and forestry operations in this application. AET stated that the
combination of the key customer accounts and forestry operations groups streamlined and
provided operational efficiencies in these areas.484 AET also explained that ATCO outsourced its
payroll function to a non-related third party, Automatic Data Processing (ADP). The costs for the
payroll services provided to AET are directly billed and have been recorded in USA 921.
553. AET provided an overview of the allocation methodologies and percentages that have
been used to quantify the impact of the common groups on the transmission costs in the
application. In particular, Appendix 3 provided a summary of cost allocators, the allocation
percentages to AET, and the amount allocated under each method for the 2018-2019 test period
479 Transcript, Volume 7, starting at page 1213, line 16 and ending at page 1217, line 10. 480 Decision 21701-D01-2017: ATCO Electric Ltd,. Transmission Common Group Application, Proceeding 21701,
July 4, 2017. 481 Exhibit 22742-X0001.02, updated application, page 9. 482 Exhibit 22742-X0001.02, updated application, page 569. 483 Exhibit 22742-X0001.02, updated application, page 570, paragraphs 530-531 contain list of common groups. 484 Exhibit 22742-X0001.02, updated application, page 570.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 125
as compared to the allocators submitted as part of the common group application.
Appendixes 4.1 and 4.2 provided a detailed breakdown of ATCO Electric Ltd.’s485 2018 and
2019 forecast total common group costs and FTEs by each functional group that apply to both
transmission and distribution. These functional groups were also discussed in detail as part of the
Common Group Study, Attachment 27.1. The summary identified those common group costs
which are allocated to AET and AED as well as those FTEs and associated costs forecast to
support ATCO affiliates.486
Inclusion of deferral account revenue in net revenue calculation
554. In its evidence, Bema raised a concern with the calculation of net revenues, which affects
the common group cost allocators. Bema recommended that AET include its deferral account
revenues in the calculation of the net revenue amount used in its allocations. Bema stated that
deferral accounts are an essential component of regulatory accounting and that the Commission
has concluded they will be recorded as regulatory assets and liabilities for regulatory accounting
purposes whether or not they are recorded under IFRS.487 Accordingly, Bema submitted that
AET’s approach to ignoring the regulatory accounting impacts of deferral accounts in its
reported regulated revenue requirement was inappropriate. Further, it was Bema’s view that
AET’s simple reliance on its IFRS reported revenue ignored that AET was required to reconcile
under Rule 005: Annual Reporting Requirements of Financial and Operational Results, all
adjustments between IFRS and AET’s regulatory accounting.488
555. The CCA asserted that AET’s argument for the exclusion of deferral revenues in the net
revenue calculation was inconsistent with its argument for the inclusion of CWIP in the net
property plant and equipment (PP&E) calculation.489
556. In rebuttal evidence, on the issue of deferral account revenues, AET pointed to an IR
response490 from the common group proceeding (Proceeding 21701), to illustrate that it was
being consistent in its exclusion of such revenues and was not “cherry picking” the results. AET
also submitted that the current approach was administratively simple.491
557. AET noted that including deferral revenues in the calculation of net revenue would not
have a material impact on the 2018-2019 GTA application. AET reproduced a table from its IR
responses to CCA492 which illustrated that including deferral revenues results in an increase in
allocated costs to AET of just $0.1 million for each of 2018 and 2019.
558. The CCA insisted that deferral account revenues are just as much a component of a
utility’s revenue requirement as any other element such as operating costs and income taxes. In
fact, deferral accounts often are used to true up amounts related to items such as operating costs
and income taxes. Accordingly, the CCA maintained its recommendation that deferral account
485 Exhibit 22742-X0001.02, updated application, page 580, refers to total ATCO Electric common costs, both
transmission and distribution. 486 Exhibit 22742-X0001.02, updated application, page 580. 487 Exhibit 22742-X0592, page 173. 488 Exhibit 22742-X0592, page 173. 489 Exhibit 22742-X0592, page 175. 490 Proceeding 22859, Exhibit 22859-X0052, AET-CCA-2017NOV03-005. 491 Exhibit 22742-X0417.01, AET-AUC-2018JUN08-031(a). 492 Exhibit 22742-X0456.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 126
revenues be included in net revenues. In its view, if net revenues are to be a cost allocator, then
all revenues affecting the calculation of net revenues should be considered by the Commission.493
Inclusion of CWIP in net PP&E
559. Another issue raised by Bema was AET’s proposal to include CWIP in the calculation of
net PP&E. Bema submitted that CWIP should be excluded.494 It also challenged AET’s claim that
its proposal was consistent with past practice. The CCA noted that the Commission discontinued
CWIP-in-rate base in 2017 per Decision 20272-D01-2016, but approved it in 2016.495 According
to AET’s 2016 Rule 005 filing, Schedule 4.1-T, AET included $220.0 million of CWIP in its
opening January 1, 2016 net PP&E and $178.9 million of CWIP in its closing December 31,
2016 balance.
560. Bema considered that these balances are material and will increase the costs being
allocated to AET relative to AED. Bema stated that, from the perspective of consistency, it is
unclear whether AED included CWIP in its net PP&E calculations for cost allocation purposes in
the 2018-2019 test years. Bema further observed that AET has not consistently included CWIP
in net PP&E, as confirmed by AET in Proceeding 22859, the common group compliance
filing.496
561. The CCA maintained that the traditional AFUDC method was the usual means employed
by the Commission and was also the method most recently approved for use by AED and AET in
2017. Therefore, the principle of consistency strongly supported the exclusion of CWIP from net
PP&E in the cost allocation method.497
562. With respect to regulatory accounting treatment, the CCA noted that the Commission has
accepted two different approaches to regulatory accounting over time. The CCA pointed out,
however, that CWIP has not been approved by the Commission for inclusion in the rate base for
the current forecast test period. Accordingly, the principle of consistency in regulation suggests
that the regulatory accounting treatment of actual costs should reflect the current regulatory
accounting treatment for forecast costs.498
563. Finally, under IFRS, the CCA noted IAS 16 required that an asset be in the location and
condition necessary for it to provide the service intended by management before that asset can be
capitalized to PP&E. CWIP is by its very nature an asset that is more akin to inventory, or as the
name states, “work-in-progress.” Costs incurred before an asset is placed in service do not meet
the requirement that it is in the “location and condition necessary for it to provide the service
intended by management.” Additionally, in this case, the accounting treatment under IFRS
aligned with the regulatory accounting treatment under traditional AFUDC accounting where
CWIP is not included in rate base. Therefore, the CCA submitted IFRS accounting further
supported the exclusion of CWIP from net PP&E.
493 Exhibit 22742-X0722, CCA final argument, page 181. 494 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 177. 495 Decision 20272-D01-2016, paragraphs 1307-1310. 496 Exhibit 22742-X0592, page 176, refers to Proceeding 22859 (AET Common Group Compliance filing),
Exhibit 22859-X0052, AET Information Responses to CCA, PDF pages 13-14, response to AET-
CCA2017NOV03-006(d). 497 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 177. 498 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 177.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 127
564. In rebuttal evidence, AET confirmed that both AET and AED did include CWIP in the
calculation of net PP&E for cost allocation purposes consistent with past practices. AET
submitted that the identical treatment of CWIP by both AED and AET should address all of
Bema’s concerns around this topic.499
565. AET added that the use of net PP&E, inclusive of CWIP, is a longstanding practice that
has been approved by the Commission on a number of occasions. The methodology for the net
PP&E component of the allocation formula was previously approved in AET’s 2013-2014 GTA
Second Compliance filing (resulting in Decision 2014-348).500 It was recently approved once
again as part of AET’s common group application in Decision 21701-D01-2017, which
determined the allocation of costs between AED and AET for the 2016-2017 period. Therefore,
AET submitted that the principle of consistency strongly supported the inclusion of CWIP in net
PP&E in the cost allocation method.501
566. Finally, AET noted that the CCA had expressed concern that including CWIP would
increase the costs being allocated to AET relative to AED.502 AET stated that it performed an
analysis503 which determined that the removal of CWIP from net PP&E had no material impact
on revenue requirement in either 2018 or 2019. As such, AET submitted that the CCA’s
argument that the costs allocated to AET relative to AED would increase, was not correct.504
Commission findings
567. The CCA has argued that the Commission recognizes deferral account balances as
regulatory assets and liabilities and that it makes sense to record all the accounting impacts of
these accounts. Also, deferral account balances are included in Rule 005 reporting. The CCA
also argued that deferral account revenues were related to regulatory costs and that shifting costs
or revenues from one period to another does not negate the fact that they affect the revenue
requirement of the entity.
568. AET argued that the current practice was administratively simple and any change would
not have a material impact.
569. The Commission finds the arguments of the CCA to be more persuasive. The
Commission considers that it would be more consistent if deferral revenues were included in the
determination of the allocation factor and with AET’s treatment of deferral revenues in Rule 005.
In the Commission’s view, these deferral revenues can still affect the revenue requirement of the
entity, and the deferral revenues of direct assigned capital are a function of, and reflect, the
actual capital invested. Therefore, AET is directed to include deferral account revenues in
calculating net revenue for purposes of the common cost group allocation methodology.
570. On the question of whether CWIP should be included in PP&E for the purpose of
determining cost allocation, the Commission finds the arguments of AET to be more persuasive.
499 Exhibit 22742-X0618, AET rebuttal evidence, page 149. 500 Decision 2014-348: ATCO Electric Ltd., 2013-2014 Transmission General Tariff Application Second
Compliance Filing, Application 1610733-1 Proceeding 3337, December 15, 2014. 501 Exhibit 22742-X0618, AET rebuttal evidence, page 149. 502 Exhibit 22742-X0618, AET rebuttal evidence, page 149 refers to Exhibit 22742-X0592, paragraph 566. 503 Exhibit 22742-X0457, in response to a Round 2 IR from the CCA, AET-CCA-2018JUN08-018(g)
Attachment 1. 504 Exhibit 22742-X0618, AET rebuttal evidence, page 150.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 128
In the Commission’s view, including CWIP in PP&E more accurately reflects the actual capital
invested. The Commission also accepts that it is consistent with prior practice. Therefore, AET is
directed to continue to include CWIP in the net PP&E allocator.
15 Corporate administration and general
571. Administration and general (A&G) costs include general administration, office supplies
and expenses, outside services employed, insurance premiums, injuries and damages, regulatory
expenses, miscellaneous general expenses, head office rent, information technology (IT)
operating expenses, and maintenance of company-owned houses. AET forecast $47.8 million in
2019 and $40.6 million in 2019 for its A&G costs,505 which are operating costs. The forecast for
the 2018 test year included significant changes because of severance costs related to workforce
reductions, which are addressed in Section 5.1.3 of this decision. The increase was also due to
inflation. Office rental costs, which are also part of A&G, are addressed in Section 15.4. After
removing severance costs from the analysis, the total forecast A&G costs are relatively stable
compared to prior years and over the test period. The individual accounts that make up A&G are
reviewed below.
15.1 Office Supplies and Expenses (USA 921)
572. Office supplies and expenses include supplies and expenses incurred in support of the
corporate function. Examples of such costs include fringe and employee benefits, travel
expenses, membership fees, severance costs as well as donations and licence fees. Donations and
licence fees are not included for revenue requirement purposes.506
573. AET forecast office supplies and expenses are $15.9 million and $8.7 million for the
2018 and 2019 test years, respectively. The 2018 forecast for this account included $7.6 million
in severance costs, and severance costs are addressed in Section 5.1.3 of this decision. The
increase in this forecast from 2017 to 2018 is mainly due to the payment of severance costs
related to workforce reductions. Severance costs are included in the “General Admin Other”
expense line item within this account.507 AET illustrated its forecast for this account in Table 25.3
of the application, which is reproduced below:
Table 38. Office supplies and expenses
2015
Actuals 2016
Actuals 2017
Actuals 2018
Test year 2019
Test year
($ million)
Operating costs – USA 921 20.2 8.4 7.8 15.9 8.7
Increases/(Decreases) in test period (Schedule 25-2)
(11.8) (0.6) 8.1 (7.2)
Source: Exhibit 22742-X0001.02, updated application, PDF page 528.
574. In its evidence, Bema submitted that the major cause of the increases in 2018 and 2019
for USA 921 appears508 to be fringe and employee benefits combined with the general-other cost
505 Exhibit 22742-X0002, Schedule 25-1. 506 Exhibit 22742-X0002, Schedule 25-2 and Exhibit 22742-X0592, page 99. 507 Exhibit 22742-X0001.02, updated application, PDF page 539, “Schedule 25-2, line 38. 508 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 100.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 129
category.509 Bema described AET’s explanation of the cost increases in Schedule 25-2 as “high
level,” referring only to increases in “general administrative costs ($0.4M [million]), corporate
communication related costs ($0.3M), fringe ($0.3M), and training ($0.1M).”510 Bema’s review
lead it to conclude that the costs of fringe and employee benefits would increase by $1.0 million
in 2018 and $0.9 million in 2019 over 2014 levels, and not by the $0.3 million cited by AET and
that the general-other costs would increase to $1.3 million in each of 2018 and 2019, compared
to an average of only $0.4 million per year between 2013 and 2016.
575. The CCA submitted that, based on Bema’s review of the GTA schedules, the revised
application and AET’s responses to a CCA information request, AET did not explain this
variance from earlier levels.
576. The CCA suggested that a more reasonable forecast of fringe and employee benefits in
each of 2018 and 2019 is $1.6 million, which is an average of actual costs incurred in the years
2013, 2014, 2016 and 2017 (removing 2015 due to the large severance payment) and is greater
than the $1.5 million in actual costs incurred by AET in 2017, which affords AET some inflation
in the costs. The CCA submitted that if AET considered that additional fringe and employee
benefits would be incurred for the 2018 severance costs, then it should quantify and support
those costs.
577. The CCA stated that AET does not appear to have explained any of the increase in costs
over historical 2013 to 2016 levels of general-other costs other than an increase in training costs
of $0.1 million. The CCA stated that AET had failed to explain and justify the costs incurred in
2017 and the expected costs in 2018 and 2019. The CCA calculated the historical annual average
cost for general-other from 2013 to 2016 to be $0.4 million, with 2016 actual costs of
$0.5 million. The CCA recommended a cost figure of $0.6 million in each of 2018 and 2019,
which it submitted is consistent with historical levels, but also factors in 2016 costs of
$0.5 million in addition to a $0.1 million increase for training costs.511
578. The CCA’s recommendations amounted to disallowances of $0.9 million and $0.8
million of fringe and benefits costs in 2018 and 2019, respectively, and of $0.8 million of
general-other costs in each of 2018 and 2019.
579. In rebuttal evidence, AET explained that Exhibit 22742-X0002.04, which is AET’s
schedule of impacts of inflation on operating costs, does say that there is a year-over-year
increase in fringe expense of $0.3 million between 2017 and 2018, but that the increases of
$1.0 million in 2018 and $0.9 million in 2019, respectively, as compared to 2017 are related to
fringe and employee benefits, not simply fringe benefits. The total increase of $1.0 million
includes a $0.3 million increase to fringe benefits (which mainly increased CPP/EI, employee
flex benefits and share purchases) and a $0.7 million increase because of various other benefits,
including long-service awards ($0.2 million), retirement allowances ($0.1 million), the Employee
Assistance Program ($0.1 million), and bursaries ($0.1 million).512
509 Exhibit 22742-X0237, response AET-CCA-2017AUG30-040. AET identifies General-Other as a portion of
General Operating Expenses. 510 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 105 refers to Exhibit 22742-X0002.04, AET
2018-2019 GTA MFR Schedules, Schedule 25-2. 511 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 106. 512 Exhibit 22742-X0618, AET rebuttal evidence, page 71.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 130
580. AET claimed that the CCA had miscalculated the average general-other costs for 2013 to
2016. AET stated that the correct average was $0.7 million, not the $0.4 million calculated by the
CCA. AET argued that correcting for this error would raise the CCA's recommended amount to
$0.9 million per year. AET also contested the CCA's assertion that it had provided no
explanation for the proposed increase in this account, outside of higher training expenses. AET
stated that it provided a variance explanation in Schedule 25-2 of Exhibit 22742-X0002.04 that
included increased general administrative costs (including bank charges, couriers, and phone
costs), increased corporate communication-related costs (mainly related to communications
focusing on health and safety issues, changes in corporate procedures, employee engagement,
and customer education), and increased training. AET also provided a table, reproduced below,
to explain the forecast over 2016 actuals:513
Table 39. Changes in general-other costs included in USA 921
($ million)
2016 Actuals 0.6
General administration costs 0.4
Corporate communications costs 0.3
Training costs 0.2
Outsourcing of payroll to ADP 0.1
Relocation expenses (0.1)
Other items less than $0.1M (0.1)
2018/2019 Forecast 1.4
Source: Exhibit 22742-X0618, page 72.
581. In argument, the CCA maintained that its calculations regarding general-other costs were
correct, explaining that it had removed the disallowed pension COLA (cost of living
adjustments) amounts. It referred to an exchange between the AET panel and the CCA counsel
that confirmed this adjustment was correct.514 The CCA also commented on Table 6 supplied by
AET, stating that simply listing cost increases does not demonstrate that those cost increases are
reasonable compared to actual 2016 costs.515
582. In reply argument, AET stated that the CCA was mistaken in removing pension cost-of-
living adjustments from general-other costs because the cost-of-living adjustment, along with all
other pension costs, are not included in “general-other” expenses but, rather, are part of “Fringe
& Employee Benefits.”516 AET submitted that the CCA had incorrectly deducted an amount for
disallowed pension COLA in the “general-other” expenses in its calculations.
Commission findings
583. The Commission accepts AET’s explanation for the increase in fringe benefits given the
inflationary pressures on the specific cost items of CPP and employee benefit premiums. With
respect to the other employee benefits identified, however, it is not clear to the Commission how
a proposed increase of $0.7 million per year is justified, given that FTEs are declining. For these
reasons, the Commission approves a marginal increase of $0.1 million and AET is directed to
513 Exhibit 22742-X0618, AET rebuttal evidence, page 72. 514 Transcript, Volume 3, page 474, lines 6-24, Ms. Goode to Mr. Wachowich. 515 Exhibit 22742-X0722, CCA final argument, page 94. 516 Exhibit 22742-X0727, AET reply argument, page 68 refers to Exhibit 22742-X0592, page 100.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 131
reduce its forecast spending on fringe and benefit costs by $0.6 million for each of the test years
and to reflect this reduction in its compliance filing to this decision.
584. The Commission finds that the CCA’s proposed reduction for the general-other cost
category is excessive. The Commission, however, agrees with the CCA’s comments that AET
failed to justify or explain its proposed increases and some reduction is warranted. As such, AET
is directed to reduce its forecast general-other expenses by $0.4 million for each of the test years
and to reflect this reduction in its compliance filing. Bema calculated the historical annual
average cost for general-other expenses from 2013 to 2016 to be $0.4 million, and the
Commission accepts that this calculation shows that historical trend of $0.4 million per year
provides a more reasonable forecast for general-other expenses in the test years.
585. The Commission notes that the above reductions result in an allowed forecast of
$7.7 million for each of the test years for this account, which is $0.1 million less than the 2017
actual amount. Given AET’s workforce reductions, the Commission does not consider this to be
an unreasonable result, particularly since the total office supplies and expenses forecast for 2018
was $15.9 million, the 2019 forecast was $8.7 million, and the 2017 actuals were $7.8 million.
15.2 IT G&A expense (USA 934)
586. In the application, AET explained IT services charged to operating costs include costs to
operate, maintain and distribute existing and new IT applications required by AET to manage its
financial, human resources and operational activities (e.g., Oracle and Maximo IT systems).
These services also include charges for the provision of hardware (e.g., PCs, laptops, monitors);
network, voice (telecommunications), data storage and printing management and infrastructure;
and ad hoc service requests.517 AET illustrated the forecast in the following table:
Table 40. IT G&A expense
2015
Actuals 2016
Actuals 2017
Actuals 2018
Test year 2019
Test year
($ million)
Operating costs – USA 934 3.8 4.2 3.8 3.9 3.7
Increases/(Decreases) in test period (Schedule 25-3)
0.4 0.4 0.1 0.2
587. AET explained that in its September 4, 2018 application update, the 2018 forecast for
USA 934 was reduced slightly as a result of the A&G position reductions in 2018. The forecast
for 2019 was also updated from $3.3 million to $3.7 million. This change was the result of the
deferral of the cost savings (system hosting, data storage, support and licensing) from upgrading
Oracle E-Business to a cloud-based platform because of the delay in the project in-service date
from December 2017 to October 2018, net of a decrease in IT costs as a result of the full-year
impact of the 2018 FTE reductions.
588. In its evidence, Bema noted that the costs incurred for this account were related entirely
to external contractor charges.518 Given that AET’s IT support is provided by an external third
party, the CCA maintained that the resulting charges should be relatively stable both in terms of
517 Exhibit 22742-X0001.02, updated application, page 534. 518 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 113.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 132
volume and rates throughout each year, absent significant usage or price changes. In the CCA’s
view, it was unusual that AET’s forecasting accuracy has been so low.519
589. The CCA recommended a reduction similar to USA 575 for IT Support,520 where it noted
that there has been a reduction in users and equipment as a result of AET’s staff terminations in
2018. The CCA considered that a similar reduction of 11 per cent in 2018 as compared to 2017
and a further 2.5 per cent reduction in 2019 over 2018 would be reasonable. The CCA calculated
that these reductions would result in forecast costs of $3.4 million in 2018, and $3.3 million in
2019, noting that the 2019 amount, as revised, would match the previously applied-for amount in
AET’s original application. In the CCA’s view, this was reasonable since AET has not supported
the increase in costs in its updated application for this account. The CCA stated that these
reductions would lower forecast expenses by $0.5 million and $0.4 million in 2018 and 2019,
respectively.
590. In rebuttal evidence, AET disputed the CCA’s claim that its forecast accuracy was low,
noting that over the period 2013-2017, actuals were only four per cent below forecast. AET
argued that there was no reasonable basis to presume that costs for IT services should be stable
over time as long as the services in question continue to be provided by a third-party supplier.
AET stated that it made management decisions in the last test period to implement cost-reduction
initiatives for this account and that actual costs in 2017 were below approved levels by
$1.5 million mainly due to lower application support services, e.g., storage, disaster recovery,
hosting and maintenance. These cost reductions were achieved by a management decision to
move to a cloud-based storage system, which was not part of the approved forecast. According to
AET, pursuing efficiencies and implementing prudent cost-savings measures throughout a test
period should not be construed as evidence of the inability to forecast costs.
591. AET stated that the expenses in this account were 80 per cent fixed and did not fluctuate
with changes in users or FTEs as the requirement for the IT applications remains. AET indicated
that IT applications for which costs are included in USA 934 include Oracle E-Business
applications and Enterprise Planning and Budgeting Cloud Service.521 AET claimed that if the
CCA’s recommendations were adjusted to apply to only the 20 per cent of expenses that are
variable, AET’s 2018 and 2019 forecast expenses for this account would be seen to be
reasonable. AET stated that its forecasts are supported as shown in the table reproduced below:
Table 41. Reconciliation of changes in USA 934 for 2017-2018
2017 Actuals (Schedule 25-1) 3.8 Temporary cost of running concurrent Oracle systems 0.3 Cost reductions due to decreased number of users and units of equipment (0.1) $3.8M x 20% variable costs x 11%
Savings in application support services (0.1) 2018 Forecast (Schedule 25-1) 3.9 Cost reductions due to decreased number of users and units of equipment (0.1) $3.8M x 20% variable costs x
(11% + 2.5%)
Savings in system hosting, data storage, support and licensing costs (0.1) 2019 Forecast (Schedule 25-1) 3.7
Source: Exhibit 22742-X0618, AET rebuttal evidence, PDF page 80,Table 7.
519 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, pages 114-116. 520 Exhibit 22742-X0722, CCA final argument, paragraphs 334-337. 521 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 78.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 133
592. AET acknowledged the CCA was correct in assuming that some cost savings in user fees
will be realized in the test period as a result of staff reductions, but explained that this would be
offset by increased IT application costs for 2018. AET explained that it has moved from on-
premise Oracle E-Business to a cloud-based Oracle E-Business solution, requiring that the on-
premise Oracle system be available to facilitate all financial historical reporting for the
organization, as the new cloud-based system will retain financial data from October 2018
forward. This added $0.3 million in IT costs for 2018 over and above the previous ongoing
application costs.
593. In argument, the CCA acknowledged there was some merit to AET’s position that the
bulk of its IT costs were fixed. However, it continued to claim that some reduction may be
warranted and it recommended a reduction of $0.1 million in each of 2018 and 2019.
Commission findings
594. The Commission accepts AET’s submission that its forecast expenses for this account
reflect fewer users and increased IT application expenses due to the move to a cloud-based
Oracle E-Business IT solution. However, the Commission directs AET to adjust its forecast
expenses for this account based on the Commission’s reduction in forecast FTEs found
elsewhere in this decision.
595. Further, on June 5, 2019, the Commission issued Decision 20514-D02-2019 in the ATCO
Utilities IT common matters proceeding. With respect to USA 934, AET is directed to reflect
any changes arising from the directions in that decision in its compliance filing to this decision.
AET is further directed to provide schedules detailing how the determinations in Decision
20514-D02-2019 are reflected in the compliance filing to this decision.
15.3 Allocation of costs to Alberta PowerLine
596. ATCO Ltd., through its subsidiary Canadian Utilities Limited, is a joint owner with
Quanta Services CC Canada, Ltd. of Alberta PowerLine General Partner Ltd. (Alberta
PowerLine GP). Alberta PowerLine Limited Partnership (Alberta PowerLine) is a subsidiary of
Alberta PowerLine GP. Alberta PowerLine owns 100 per cent of the Fort McMurray West 500-
Kilovolt Transmission Line Project (APL project). The development of the Fort McMurray West
facility was awarded to Alberta PowerLine under the AESO’s competitive process in May 2013.
The competitive process was approved by the Commission in Decision 2013-044522 and Alberta
PowerLine was later awarded the APL project. A September 28, 2017 project agreement
between the AESO and Alberta PowerLine specified the payment provisions, price adjustment
mechanisms, and other provisions governing the terms and conditions of service between Alberta
PowerLine and the AESO.523
597. Alberta PowerLine is an affiliate of AET. AET provides management services, O&M
services, route development and design build management services to Alberta PowerLine under
a service concession arrangement. Amounts for contracted services provided by AET to Alberta
522 Decision 2013-044: Alberta Electric System Operator, Competitive Process Pursuant to Section 24.2(2) of the
Transmission Regulation Part B: Final Determination, Proceeding 1449, Application 1607670-1, February 14,
2013. 523 Decision 23161-D01-2018: Alberta PowerLine LP, Tariff Application, Proceeding 23161, January 23, 2018.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 134
PowerLine are reflected in the 2018-2019 GTA as affiliate cost of goods sold. In its application,
AET stated that the transmission line is expected to be completed in 2019.
598. At issue in this decision is the methodology for allocating head office costs given that
AET provides services to Alberta PowerLine.
599. AET’s head office costs are allocated based on a formula that takes into account equal
weightings of total assets, net revenues and labour costs. AET confirmed that it is not until the
in-service date of the APL project that Alberta PowerLine would become an operating entity
within the pool and would therefore be allocated head office costs. Because of the head office
costs allocation methodology, there would be “a two-year lag regarding the inputs to the costs
that are in question.”524
600. In an IR response to the Commission, AET stated:525
There are no head office/Canadian Utilities Limited costs being directly allocated to
Alberta PowerLine in Schedules 25-8 to 25-8-3. This is because the most recent audited
numbers used to calculate the allocation percentages is 2016, and at this time Alberta
PowerLine is considered a start-up organization with only preconstruction costs being
incurred.
601. Bema noted in its evidence that AET’s head office costs are currently not allocated to
Alberta PowerLine but head office costs are allocated to all other affiliates of AET.
602. The CCA took no position on AET’s approach to accounting for Alberta PowerLine in its
financial statements. However, for regulatory purposes, the assets have a regulatory rate base
value, and thus a net PP&E value can be calculated. The CCA recommended that the
Commission direct AET to quantify the gross and net PP&E values for Alberta PowerLine on the
same basis as AET calculates its gross and net PP&E in its GTA schedules for other affiliates
and to report those values in its compliance filing. The CCA also recommended that AET be
directed to calculate its revenue and labour costs on the same basis as the costs are presented in
AET’s own GTA schedules.526
603. The CCA submitted that the Commission’s normal approach for head office cost
allocations is to rely on the actuals two years prior to the first test year. The CCA considered that
the use of the most recent 2017 actual results is more appropriate. Accordingly, the CCA
recommended that AET’s head office costs be allocated to Alberta PowerLine for both the 2018
and 2019 test years based on the 2017 values.
604. AET explained that the services provided to Alberta PowerLine were accounted for under
a service concession arrangement and that the transmission line is not recognized as PP&E but as
a long-term accounts receivable as amounts are due from the AESO.527 In particular, AET
explained that Alberta PowerLine did not record PP&E on its balance sheet but, rather, recorded
a financial asset representing the amounts due from the AESO in accordance with IFRS.528 The
testimony, of AET witness, Ms. Goode was that the total value of the transmission assets that
524 Transcript, Volume 3, page 546, lines 6-9, Mr. Hoshowski’s response to Mr. Wachowich. 525 Exhibit 22742-X0417.01, AET-AUC2018JUN08-045(b). 526 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 165. 527 Exhibit 22742-X0417.01, AETAUC-2018JUN08-045(c). 528 Exhibit 22742-X0669.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 135
Alberta PowerLine would record as PP&E as opposed to the costs of the asset actually recorded
are not significantly different in magnitude.529 AET maintained there was no justification for
changing the previously approved head office allocation given that the allocation formula uses
total assets and that the recording of Alberta PowerLine as a financial asset is not significantly
different from what it would record as “PP&E.”
605. In rebuttal evidence, AET objected to the CCA’s recommendation that head office costs
be allocated to Alberta PowerLine, and that AET be directed to calculate its net revenue and
labour costs, for the purposes of allocating head office costs, on the same basis as the costs are
presented in AET’s GTA schedules rather than using actual audited data.530 AET argued that the
CCA’s recommendation that head office costs for 2018 and 2019 be allocated to Alberta
PowerLine based on a single year, 2017, rather than the year that is two years prior to the test
year is not warranted. AET maintained that the Commission’s use of audited financial data from
the year that is two years prior to the first test year, in this case 2016, is supported by the
methodologies for cost allocation included in AET’s last two GTA decisions.531 AET submitted
the CCA is cherry-picking and ignoring the recent findings of the Commission with respect to
the use of actual audited data from the second prior year. AET maintained that over time, yearly
fluctuations in the inputs of the allocation formula will average out, as long as the formula
remains in place.
606. AET confirmed that the head office allocation formula is based on each company’s total
assets, not a regulatory rate base amount. In particular, Alberta PowerLine did not have a
regulatory rate base. Rather, its tariff is set out in the project agreement between Alberta
PowerLine and the AESO and is not calculated based on Alberta PowerLine’s investment in
utility assets. Additionally, AET submitted that assets normally only have regulatory rate base
value once they are put into service. As Alberta PowerLine’s assets will not be in service until
2019 and Alberta PowerLine will only begin collecting tariff revenue when the assets are put
into service, AET maintains that net PP&E should not be used.
607. AET clarified that Alberta PowerLine does not actually have labour costs as services
were provided by contractors, including AET and a non-affiliate company. AET records the fully
burdened costs charged to Alberta PowerLine by each contractor as contractor costs, not labour
costs. The ATCO companies, including AET, do not include contractor costs in the head office
allocation formula.
608. Finally, AET explained that as a start-up organization, Alberta PowerLine did not have
any tariff revenue for 2016, the year on which the head office allocation for the 2018 and 2019
test years is based and it should not be allocated any head office costs for 2018 and 2019.
However, even if 80 per cent of Alberta PowerLine’s net revenues and total assets from its
audited financial statements for 2016 were included in the head office allocation formula on
Schedule 25-8-1 of the application (equal to CUL’s ownership interest),532 the impacts on AET’s
forecast revenue requirements for 2018 and 2019 would be insignificant. AET supplied
529 Transcript, Volume 4, page 562, lines 8-16. 530 Exhibit 22742-X0618, AET rebuttal evidence, pages 137-139. 531 Decision 20272-D01-2016, paragraphs 131, 884 and 1275; and Decision 2013-358: ATCO Electric Ltd., 2013-
2014 Transmission General Tariff Application, Proceeding 1989, Application 1608610-1, September 24, 2013,
page 954. 532 Exhibit 22742-X0002.04.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 136
Table 14533 to illustrate these amounts, which it forecast would be $0.05 million for 2018, and
$0.06 million for 2019.
609. In argument, the CCA maintained that Alberta PowerLine is a significant asset that will
be in place during the test period and that will alter the level of actual head office resources
allocated to Alberta PowerLine. The CCA argued that although AET charges its internal labour
costs to Alberta PowerLine as contractor costs, this does not change the fundamental point that
contractor costs are similar to labour costs and are not being properly taken into account by the
current head office allocation model. To address these concerns, the CCA recommended that the
Commission consider more current information for Alberta PowerLine and alter the mechanics
of the head office allocation formula specific to Alberta PowerLine for labour costs. The CCA
submitted that the Commission should direct AET to utilize an amount for internal labour costs
based on the contracted manpower charges received from AET that are equivalent to the internal
labour that an entity like Alberta PowerLine would otherwise normally retain.534
610. In its argument, the UCA submitted that there is “… something fundamentally wrong
with the current allocation formula for head office costs, which results in no allocation of these
costs to Alberta PowerLine, another ATCO affiliate. It is difficult to accept that such an
allocation is fair or reasonable, or that it does not result in other affiliates subsidizing Alberta
PowerLine’s fair share of these costs.”535
611. In reply argument, the CCA stated that Alberta PowerLine is a new entity that was not
considered in the 2015-2017 GTA and it would not be reasonable to knowingly exclude more
recent and relevant information available to the Commission about Alberta PowerLine in
considering how to allocate head office costs. The same could not be said for other entities
included in the current calculation because they are not new entities undergoing significant
changes.536 The CCA submitted that this circumstance is also a significant change in facts that is
novel to the issues that were considered by the Commission in Decision 20272-D01-2016 and
thus warrants further attention.
Commission findings
612. In the Commission’s view there are two questions to be determined with respect to the
allocation of costs to Alberta PowerLine:
(a) For the allocation of head office costs in the 2018-2019 test years, should financial data
from two years preceding the first test year be used, or should data from more recent
year(s) be used to allocate head office costs to Alberta PowerLine?
(b) Should head office costs be allocated to Alberta PowerLine during the test years on the
basis of the labour costs incurred by AET on its behalf but which were charged out as
contractor costs?
613. With respect to the first question, the currently approved practice for allocating head
office costs is to use actual data from the second year preceding the first test year. AET has
533 Exhibit 22742-X0618, AET rebuttal evidence, page 139. 534 Exhibit 22742-X0722, CCA final argument, page 178, also refers to Madsen testimony, Transcript, Volume 7,
page 1200 line 15 to page 1201, line 4, Mr. Madsen to Ms. Sabo. 535 Exhibit 22742-X0724, UCA final argument, paragraph 89. 536 Exhibit 22742-X0726, CCA reply argument, page 51.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 137
argued that it would be unfair to deviate from this practice stating that, over time, yearly
fluctuations in the inputs of the allocation formula would average out, as long as the formula
remains in place. The CCA suggested that Alberta PowerLine is a new entity that was not
considered in the 2015-2017 GTA and as a new entity it was reasonable for the Commission to
consider if the findings from Decision 20272-D01-2016 should apply to Alberta PowerLine head
office costs.
614. The Commission has considered the arguments of the parties on which year to use as the
base year for determining allocations, if any, to Alberta PowerLine. In Decision 2013-211,537
Decision 2013-358,538 and Decision 20272-D01-2016,539 the Commission determined that the
actual data from the year that is two years prior to the first test year in a GTA should be used for
the corporate cost allocator and for head office costs. In the normal course of events, the head
office cost allocation would be calculated in the manner approved in these prior decisions.
However, the Commission agrees with the CCA that the use of the most recent 2016 actual
results does not reflect Alberta PowerLine because, while the labour costs are accounted for
under the service concession agreement, the current head office costs allocation does not take
account of the use of head office resources by Alberta PowerLine.
615. Additionally, the Commission takes notice that, subsequent to the close of the hearing on
June 24, 2019, Canadian Utilities Limited has sold its 100 per cent ownership interest in Alberta
PowerLine.540 During the course of the proceeding, AET confirmed that it is not until the in-
service date of the APL project that Alberta PowerLine would become an operating entity within
the pool and would therefore be allocated head office costs. AET argued that over time yearly
fluctuations in the inputs of the allocation formula will average out. The Commission considers
there is some merit to these arguments notwithstanding the sale as evidenced by the cost
allocation data provided by AET for 2018 and 2019 in Undertaking 38.541
616. The Commission is not convinced that the unique circumstances of Alberta PowerLine
require an adjustment to the allocation formula which has been consistently used in AET’s
GTAs. The use of the second year audited data in the allocation formula promotes consistency,
data reliability and avoids forecasting error. For these reasons, the Commission directs that head
office cost allocations continue to be calculated based on the actual, audited financial data of the
second year preceding the first test year of the GTA.
617. With respect to the second question, the development of a proxy for direct labour, the
Commission considers that some amount should be attributed to Alberta PowerLine. The
Commission considers it unreasonable that Alberta PowerLine should be able to avoid an
allocation of costs based on this factor solely because its labour billings from AET are recorded
as contractor costs. Alberta PowerLine clearly requires labour and that labour is being supplied
by AET. AET is therefore directed to propose, in its compliance filing, a proxy for labour,
537 Decision 2013-111: The ATCO Utilities, Corporate Costs, Proceeding 1920, Application 1608510-1, March 21,
2013, paragraph 134. 538 Decision 2013-358, paragraphs 131, 884 and 954. 539 Decision 20272-D01-2016, paragraphs 1273-1275. 540 Canadian Utilities Limited, News Release, Canadian Utilities Limited Sells Ownership Interest in Alberta
PowerLine and Offers Indigenous Communities the Opportunity to Participate, June 24, 2019,
https://ml.globenewswire.com/Resource/Download/b585ae57-66cc-4917-ab38-9b7fed620e6f. 541 Exhibit 22742-X0673, Undertaking 38.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 138
including its rationale and calculations, that will be used in the head office cost allocation
calculation to account for Alberta PowerLine.
15.4 Allocation of head office rent costs
618. Throughout AET’s and interveners' submissions on the allocation of head office rent
costs, various ATCO Group entities were referred to as the parent of AET. Where ATCO Ltd.,
CU Inc., and Canadian Utilities Limited are mentioned, the reference is to a “parent” of AET.
Where ATCO group of companies is used, that reference is to all ATCO companies, and not to
an AET parent company.
619. In its application update542 filed September 4, 2018, AET forecast a $1.2 million increase
in head office rent in each of the years 2018 and 2019. Head office costs are related to functions
such as corporate governance, and financial and administrative services that cannot be directly
charged to subsidiaries. Head office costs are included in corporate administration and general
expenses. The bulk of the increase in forecast head office rent in each of the test years was
attributed to the move to a new corporate head office building in southwest Calgary, called
ATCO Park. ATCO Park is considered to be a Class A building.543
620. AET explained that the forecast allocation of head office costs to AET is included in
USA 930.2544 and represents its allocated share of head office rent, including lease space at
ATCO Park for head office employees.545 AET further explained that the forecast allocation of
head office costs is shown on its MFR schedules 25-3 and 25-9 in the total amount of $12.6
million for 2018 and $12.8 million for 2019. Of those total amounts, AET stated that $1.8
million in each of 2018 and 2019 was AET's total forecast allocation of head office rent costs546
of which $1.6 million was attributable to ATCO Park.547
621. In addition to the allocation of head office rental costs through USA 930.2 AET
explained that the rental costs for space leased for AET employees are forecast in USA 931.1.548
This amount includes AET employees housed at ATCO Park. AET stated it had very few (21)
employees at ATCO Park.549 Being an affiliate transaction (whether for renting space at ATCO
Centre, as was formerly the case, or now for ATCO Park), these costs are also reflected in
Schedule 30-8 — Schedule of Corporate O&M Affiliate Costs, line 17.550 Given the small staff
complement of AET in Calgary, AET explained that with the relocation of AET employees to
ATCO Park in Calgary, AET's forecast lease costs in Calgary were unchanged at $0.1 million.551
The actual costs for USA 931.1 were $1.5 million in 2017 and were forecast to be $1.5 million in
2018 and 2019.
542 Exhibit 22742-X0533, page 25. 543 Transcript, Volume 3, page 539, lines 2-13. 544 The account is “Miscellaneous General Expense,” also shown at Exhibit 22752-X0002, Schedule 30-8. 545 Transcript, Volume 3, page 494; Exhibit 22742-X0571 and Exhibit 22742-X0578; AET-CCA-20180CT05-
013(e). 546 Exhibit 22742-X0002.04, MFR Schedule 25-9, line 21. 547 Exhibit 22742-X0578, AET-CCA-20180CT-013(a), attachment 1. 548 Exhibit 22742-X0001.02, updated application, PDF page 106, Schedule 25-3, line 106 549 Exhibit 22742-X0696. 550 Exhibit 22742-X0001.02, updated application, PDF page 740. 551 Exhibit 22742-X0434, PDF page 49.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 139
622. In an IR response to the Commission, AET explained the increases in head office rent, as
follows:
Overall, $1.1 million of ATCO Electric’s increase in costs in 2018 is attributable to the
move to ATCO Park.
The increase in costs is a result of two primary drivers. The first driver being increases in
rented square feet from approximately 85,000 in the ATCO Centre downtown to 155,000
square feet in ATCO Park. This increase is primarily attributable to additional meeting
space, training and development rooms, larger areas for employees to collaborate such as
breakout rooms, and space for future expansion. The second driver is the increase of
leasing rates from $20 per square feet at the ATCO Centre to $32 per square feet at
ATCO Park. In 2018, ATCO Electric’s share of these costs is 21.0% compared to 19.8%
in 2016.552
623. AET stated that the business decision to proceed with ATCO Park and to locate corporate
office staff there was made in 2013 by the ATCO Group, not AET, with the ultimate "go/no
go"553 decision residing solely with ATCO Ltd.
624. ATCO Ltd. is the tenant on the lease. The landlord is ATCO Investments Ltd., and the
lease with ATCO Ltd. was effective August 1, 2017. The lease included the first year lease cost
of $32 per sq. ft., escalating $1 per sq. ft. for each year of the 10-year lease, resulting in the tenth
year having a lease cost of $41 per sq. ft.554 The lease was based on 123,000 sq. ft. of rentable
area on four floors of ATCO Park.
625. AET confirmed on the record that it did not sign any lease or sublease for space in ATCO
Park and that the lease signed by ATCO Ltd. is not legally binding on AET. As a result, the
ATCO Ltd. lease neither confers any benefits or legal rights upon AET nor imposes any costs or
legal obligations upon it.
626. AET explained that the occupancy rate of its existing ATCO Centre in downtown
Calgary was expected to reach 98 per cent by the end of 2014 based on the projected growth rate
from 2012 to 2013. During the years leading up to 2013, AET’s efforts to address capacity issues
with its existing office space included reducing cubicle sizing, increasing the number of bullpen-
type spaces, and placing up to four persons in offices intended for one employee. While this
provided a workable solution for the short-term, a long-term solution was required that would
also allow for leasing rate predictability.555
627. As noted above, AET stated that the plan for ATCO Park was approved in 2013. In 2014,
the building design was completed, and the agreement with the general contractor was signed.
Construction started in April 2015. AET stated that in 2013, Alberta’s economy was still
expected to remain strong. In its rebuttal evidence, AET provided attachments showing the then
FMV of commercial office space, in Royal Bank of Canada (RBC) reports dated December 2013
and December 2014. These reports reflected expectations of continued vibrant economic
conditions in the province.556 AET also supplied a report from Colliers International for the first
552 Exhibit 22742-X0557, pages 153-154. 553 Exhibit 22742-X0725, AET final argument, paragraphs 334 and 352. 554 Exhibit 22742-X0571, AET response to AET-CCA-2018OCT05-013. 555 Exhibit 22742-X0618, AET rebuttal evidence, page 123. 556 Exhibit 22742-X0618, AET rebuttal evidence, pages 131-134.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 140
quarter of 2013 noting that while market demand for downtown Calgary office space had
softened, rental rates for Class A office space in the downtown core remained high at $39 per
square foot (sq. ft.). During the same period, vacancy rates for commercial office space were at
4.35 per cent.557
628. In correspondence issued to parties prior to the receipt of argument, the Commission
requested that parties address a number of questions respecting the legal principles that should
guide the Commission’s deliberations on the matter of determining a reasonable allocation of
head office rent to AET, and to include a discussion of the relevant jurisprudence.558 Parties’
responses to these questions, a number of which are summarized below, were helpful to the
Commission.559
629. AET submitted a number of arguments in support of the forecast head office rent costs
allocated to it, including the following:
In determining just and reasonable rates, the Commission must have regard for the costs
allocated to a utility subsidiary from a parent organization on a forecast basis.560 AET has
an obligation to pay its share of head office costs allocated to it because head office costs
and functions are necessary to provide utility service.561 A just and reasonable tariff has to
be fair to both customers and the utility.562
The appropriate test to use when assessing the reasonableness of affiliate services is
found in Section 4.2.1 of the ATCO Group Inter - Affiliate Code of Conduct (code of
conduct),563 which is no more than fair market value of such services.564 While the code of
conduct was not directly applicable to the ATCO Park lease, AET submitted that the
Commission may look to it for guidance on how to assess the reasonableness of the head
office rent costs allocated to AET.
The salient time for assessing the reasonableness of the forecast costs to be included in
head office rent costs allocated to AET should be fixed at the time the decision was made
to proceed with ATCO Park, that is, 2013. The reasonableness of the rental rate cannot be
appropriately assessed with hindsight.565 Instead, the reasonableness of forecast head
office costs should be assessed at the fair market value for rental rates in 2013.566
ATCO Ltd. was “fully entitled to enter into commercial agreements for the acquisition of
required services, such as leased space, including with its affiliates.”567 AET referred to
557 Exhibit 22742-X0618, AET rebuttal evidence, page 135. 558 Exhibit 22742-X0719. 559 The full arguments and reply arguments of AET, the CCA and the UCA are found at exhibits 22742-X0722,
22742-X0724, 22742-X0725, 22742-X0726, 22742-X0727, and 22742-X0729. 560 Exhibit 22742-X0725, AET final argument, paragraph 340. 561 Exhibit 22742-X0725, AET final argument, paragraph 356. 562 Exhibit 22742-X0727, AET reply argument, paragraph 254. 563 ATCO Group Inter-Affiliate Code of Conduct, Appendix 5 to Decision 2003-040, May 22, 2003. 564 Exhibit 22742-X0725, AET final argument, paragraph 344. 565 Exhibit 22742-X0725, AET final argument, paragraph 337. In paragraph 352 of AET’s argument, it states that
in the specific circumstances of ATCO Park, the commitment to proceeding with the building was made in
2013. The execution of the ATCO Park Lease in 2017 was merely a formalization of the commitment made in
2013 to proceed with ATCO Park. 566 Exhibit 22742-X0725, AET final argument, paragraph 358. 567 Exhibit 22742-X0725, AET final argument, paragraph 347.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 141
Decision 2014-169, related to the 2010 Evergreen proceeding for the provision of IT and
customer care and billing services,568 where the Commission found that FMV (Fair
Market Value) pricing should not be influenced by the nature of the affiliate
transaction.569
630. AET submitted that it is frequently the case that the term of commercial leases (and of
other types of agreements) is for a period of many years. This would particularly be the case for
a newly constructed building. AET observed that eight of the leases listed in its evidence were
for terms of 10 years or longer.570 AET submitted that the term of the ATCO Park lease was
reasonable in light of all the evidence on the record of this proceeding. Additionally, AET stated
it was not uncommon for leases to have escalation clauses. This is demonstrated by rental rates
in the comparator leases571 and over the initial seven years of an AltaLink lease.572
631. Bema’s evidence noted the increase in both the square footage and the leasing rate per sq.
ft. that AET is forecasting over the test period. Bema compared the lease rates at ATCO Park to
the lease rates that AltaLink was paying. AltaLink’s Commission-approved lease rate was $20.43
per sq. ft. through to the year 2026.573 The lease rate at ATCO Park, in contrast, started at $32 per
sq. ft. in 2018 and escalated by an additional $1 per sq. ft. each year for the next ten years. In
addition, AET’s forecast lease rate at ATCO Park was considerably higher than the $20 per sq.
ft. rate AET had been paying at ATCO Centre until just prior to the move to ATCO Park.574
632. Bema asserted that it was common knowledge that the Calgary office rental market has
been economically depressed for several years along with much of the Alberta economy.
Vacancy rates for commercial real estate have been at or near all-time highs and rental rates have
been in decline for years. Bema cited two real estate annual reports for 2016 and 2017 by Jones
Lang LaSalle (JLL) that show lease rates for prime space on 8 avenue south in Calgary had
declined by 24 per cent in 2016575 and a further 10 per cent in 2017.576
633. Further, Bema noted that the arrangement between AET and ATCO Ltd. is essentially an
affiliate rather than independent arm's length arrangement and that there are inherent risks in
affiliate-type transactions. Specifically, the question of how much profit is embedded in the lease
rate is important, yet that information is not available in this proceeding. Additionally, given that
the transaction for office space is with AET's parent, ATCO Ltd., Bema maintained that AET
faces a much greater onus to demonstrate that the costs being incurred are competitive and
represent fair market value. Given that no business case has been provided to support the
decision to move to ATCO Park, and that a business case would normally include a quantitative
568 Decision 2014-169 (Errata) ATCO Utilities (ATCO Gas, ATCO Pipelines and ATCO Electric Ltd.) 2010
Evergreen Proceeding for Provision of Information Technology and Customer Care and Billing Services Post
2009 (2010 Evergreen Application) Proceeding 240 Application 1605338-1, February 6, 2015. ATCO cites
paragraphs148,165, 166 and 434 of this decision. 569 Exhibit 22742-X0725, AET final argument, paragraph 334-348 570 Exhibit 22742-X0694. 571 Exhibit 22742-X0694. 572 Exhibit 22742-X0594 PDF page 14. 573 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 156. 574 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 157, refers to Attachment 2 of evidence. 575 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 158, refers to JLL’s website:
http://www.jll.ca/canada/en-ca/news/241/canadas-most-expensive-streets. 576 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 158, refers to JLL’s website:
http://www.jll.ca/canada/en-ca/news/253/bay-street-avenue-des-canadiens-de-montreal-among-the-
mostexpensive-streets-in-canada.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 142
and qualitative analysis of the various options that were available, Bema argued that there was no
evidence to support a finding that AET’s decision to purchase these services was reasonable,
especially at the rental rates and square footage being unilaterally allocated to AET by its parent.
Bema submitted affiliate services should be retained at the lesser of cost or market value.577
634. Bema also noted that the amount of square footage being leased at ATCO Park has
increased significantly from the old square footage under lease without any reasonable
justification for that increase. While productivity gains and improved work spaces may be
beneficial, Bema maintained that AET has not provided evidence that these benefits will be
obtained and has not fully explained why it is necessary that those benefits should be paid for by
ratepayers.578
635. Bema recommended that the Commission approve head office rent equal to the most
recent ATCO Centre rent of $20 per sq. ft. and apply that rate to the previously leased space of
85,000 sq. ft. This would reduce AET’s forecast head office rent costs by approximately $1.2
million in each of 2018 and 2019.
636. The CCA maintained that AET’s argument that 2013579 is the appropriate time to assess
the reasonableness of rental costs for ATCO Park be dismissed in its entirety. The CCA argued
that costs, and the rates based upon those approved costs, must be just and reasonable. The CCA
also argued that it was “important to point out that in this case, ATCO Ltd., AET’s parent,
decided to enter into a long-term rental agreement with its affiliate, ATCO Investments Ltd.
through the ATCO Park Lease.”580 Accordingly, the CCA submitted that the critical
determination to be made by the Commission is whether the real estate rental rates AET is
requesting the Commission to flow through to regulated ratepayers based on non-arm’s length
transactions between AET's unregulated parent and AET are just and reasonable. In addition, the
CCA noted that AET itself did not enter into any specific contractual or binding agreement for
real estate services with any of its affiliates,581 nor is AET even a party to the lease.582 It would be
unfair for ratepayers to bear the costs of an agreement that AET had no part in negotiating.583
637. Among the other arguments made by the CCA in opposing the ATCO Park rental costs
being allocated to AET by its parent are the following:
Section 2.7 of the Code of Conduct states it is not binding on the authority of the
Commission and does not “detract from, reduce or modify in any way, the powers of
the EUB [now the AUC] to deny, vary, approve with conditions, or overturn, the
terms of any transaction or arrangement between a Utility and one or more Affiliates
that may be done in compliance with this Code.”584 Under Section 4.2.1 of the code,
the “utility shall pay no more than fair market value.” The code of conduct definition
577 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 160. 578 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, page 161. 579 Exhibit 22742-X0722, CCA final argument, paragraph 581, page 171 580 Exhibit 22742-X0722, CCA final argument, referring to Exhibit 22742-X0571, AET Reponses Round 3 to
CCA, PDF page 5. 581 Exhibit 22742-X0722, CCA final argument, paragraph 482. 582 Exhibit 22742-X0722, CCA final argument, paragraph 526. 583 Exhibit 22742-X0726, CCA reply argument, paragraph 218. 584 Exhibit 22742-X0722, CCA final argument, paragraphs 518-519.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 143
of FMV requires the price to be one that is at least equal to an open and unrestricted
market between informed and prudent parties, acting at arms length.585
A lease agreement is significantly different from an agreement to purchase a physical
asset. The CCA explained that when a utility purchases a physical asset, that purchase
is made at a specific point in time, based on information known or that ought to have
been known at that time. By asking the Commission to approve a long-term lease
agreement, the utility is effectively asking the Commission to accept that the utility
has made a reasonable assessment of the future costs that would be incurred in the
market and that the long-term lease agreement will be more reasonable than otherwise
subjecting itself to rental changes in each year.586 The CCA further stated that the key
determination the Commission is required to make is whether the costs AET is
requesting to pass on from its parent in each year going forward are just and
reasonable. That assessment of reasonableness can either be performed by the
Commission up front in this proceeding and be resolved for the term of the ATCO
Ltd. lease agreement or can be performed during each test period based on the
information available to the Commission in that test period.587
It was ATCO Ltd.’s choice to enter into a long-term lease for future operating costs,
and nothing prohibits the Commission from utilizing current market-based
information to assess the justness and reasonableness of forecast operating costs AET
is seeking to flow through to its customers.588
Contrary to AET’s submissions, the Commission’s findings in Decision 2014-169, do
not support AET’s position589 that “the key observation from this finding is that the
Commission confirmed that its examination of Fair Market Value pricing should not
be influenced by the affiliate nature of the transaction.”590 The CCA submitted that the
Commission’s findings in Decision 2014-169, in fact, support the CCA’s position,
where the Commission went on to state that “This is not a cost of service proceeding
for ATCO I-Tek.”591 The CCA maintained that the instant proceeding was likewise
not a cost of service proceeding for the ATCO group of companies. Instead,
Proceeding 22742 is a cost of service proceeding for AET established to test whether
the forecast costs of AET are just and reasonable.
638. The CCA recommended that the Commission approve a lease rate of $20 per sq. ft.
because that represents the FMV for similar properties in downtown Calgary, and is therefore a
just and reasonable rate to be recovered from ratepayers.592
639. In argument and reply argument, the UCA submitted that Section 121 of the Electric
Utilities Act requires the Commission to ensure that a tariff is “just and reasonable.” Section 122
(h) provides that the Commission must provide the owner of an electric utility a reasonable
585 Exhibit 22742-X0722, CCA final argument, paragraph 523. 586 Exhibit 22742-X0722, CCA final argument, paragraph 487. 587 Exhibit 22742-X0722, CCA final argument, paragraph 489. 588 Exhibit 22742-X0722, CCA final argument, paragraph 489. 589 Exhibit 22742-X0725, AET final argument, paragraph 347. 590 Exhibit 22742-X0725, AET final argument, paragraph 348. 591 Exhibit 22742-X0725, AET final argument, paragraph 347. 592 Exhibit 22742-X0722, CCA final argument, paragraph 575.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 144
opportunity to recover “any other prudent costs and expenses that the Commission considers
appropriate, including a fair allocation of the owner’s costs and expenses that relate to any or all
of the owner’s electric utilities.” To the extent that the Commission determines they are not, the
shareholder and not the ratepayer is responsible for those costs.
640. In determining just and reasonable rates, the UCA argued that the stand-alone principle
should be foremost in determining reasonable rental costs. Applying this principle, the
Commission should approve costs only if they can be found to be prudent as measured against a
notional separate stand-alone utility. In other words, was it reasonable or would it be prudent, for
a stand-alone utility carrying out AET’s business to incur these costs when they were incurred?
The UCA submitted that the relationship of AET to its parent, or to its parent’s parent must be
ignored. Further, the costs should not be artificially made lower or higher as a result of these
corporate relationships, than would be the case if AET were acting as a stand-alone entity.593 The
UCA asserted that AET, acting prudently as a stand-alone entity would not have made the
decision and commitment so early, and that the Commission can take the downturn into
account.594
641. The UCA noted Mr. Palladino’s admission to Commission counsel that “so the lease
space was a –was driven by ATCO, not ATCO Electric Transmission.”595 The UCA argued that
the parent took over the management of AET in this instance, and must assume management’s
responsibilities to ratepayers. The UCA further reminded the Commission that AET’s move was
not supported by a business case.596
642. The UCA stated that the relevant question to be determined by the Commission is
whether the allocation to AET of head office rental costs based on a decision made by ATCO
Ltd. in 2013 would represent market value measured at the time it would have been prudent or
necessary for AET (as a stand-alone entity) to relocate from its former location to ATCO Park.
The UCA’s answer to this question was that it would not. In its view, the year 2013 was far too
early to serve as the relevant benchmark for FMV.
643. The UCA argued that while it may or may not have made sense for ATCO Ltd. to
commit in 2013 to the future construction of ATCO Park, the question for the Commission to
determine is whether the allocation to AET of head office rental costs based on market rates in
2013 represents FMV for regulated utility rate-making purposes in 2018-2019. According to the
UCA, the Commission, in relying on the standalone principle to set just and reasonable rates for
AET, should measure the FMV of commercial office rental rates at the time it would have been
prudent or necessary for AET, as a standalone entity, to incur (that is, to legally commit itself to
paying) office space leasing costs at its new head office location. In the UCA’s view, that time
would not have been 2013 but several years later.
644. In reply argument, the UCA noted that both it and the CCA agree that, because AET is
not a party to the ATCO Park lease, the lease itself has no legal significance for AET.597 AET has
593 Exhibit 22742-X0724, UCA final argument, paragraph 73. 594 Exhibit 22742-X0724, UCA final argument, paragraph 86. 595 Transcript, Volume 6, page 896, lines 2-4. 596 Exhibit 22742-X0724, UCA final argument, paragraph 70. 597 Exhibit 22742-X0724, UCA final argument, paragraph 81; Exhibit 22742-X0722, paragraph 527; and
Transcript, Volume 6, page 1044, lines 15 to 23.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 145
claimed that the lease provides documentary evidence to support the quantum of rental costs.598
The UCA questioned whether it was prudent or reasonable to commit to a rental rate four years
prior to when the office space would become available.599
645. In reply argument, AET stated that the uncontroverted evidence in this proceeding is that
in 2013, the ATCO group of companies, including AET, were running out of space for their
growing number of office employees in the downtown Calgary area and needed a permanent
solution to their growing workforce requirements. Therefore, in 2013, a decision and
commitment were made to build ATCO Park taking into consideration the current and future
needs of the entire organization, including forecasts of future requirements based on information,
economic conditions, commercial real estate rental rates and vacancy rates known at that time.600
According to AET, the evidence also demonstrated that the rental rate in the ATCO Park lease
was in alignment with the FMV for comparable suburban Class A buildings at the time the
commitment to proceed with ATCO Park was made by ATCO Ltd.601
646. AET submitted that as the head office rent costs were consistent with FMV at the time
the commitment was made to proceed with the building, including those costs in AET's revenue
requirement is reasonable.
647. AET maintained that the Supreme Court of Canada602 has been clear that, whether or not
it is reasonable to assess a particular cost using hindsight, turns on the circumstances of that cost.
AET stated that a “no-hindsight assessment” of the head office rental costs included in AET's
forecast revenue requirement is a “reasonable means of striking the balance of fairness between
consumers and utilities.” AET took issue with the CCA's suggestion that because the costs in this
instance are “operating costs,” they should be assessed on “an annual basis for reasonability.”603
It noted, for example, that the Supreme Court of Canada was clear in Ontario (Energy Board) v
Ontario Power Generation Inc. (OEB decision) that a no-hindsight prudence analysis may
equally be applied to operating costs:
A no-hindsight prudence review has most frequently been applied in the context of
capital costs, but Enbridge and Nova Scotia Power (both 2005 and 2012) provide
examples of its application to decisions regarding operating costs as well. I see no reason
in principle why a regulatory board should be barred from applying the prudence test to
operating costs.604
648. AET submitted that just because head office rental costs are operating costs is not
determinative of whether a hindsight analysis should be used. Many contracts for the acquisition
of goods and services can extend beyond a single test year; and the reasonableness of the
associated operating costs is judged based on the circumstances that existed at the time the
commitment was made. The subject lease was no different.605
598 Exhibit 22742-X0725, AET final argument, paragraph 350. 599 Exhibit 22742-X0724, UCA final argument, PDF pages 29-30, paragraph 84. 600 Exhibit 22742-X0618, AET rebuttal evidence, Part 7.1, PDF pages 122-128; AET rebuttal evidence,
paragraphs 334-337. 601 Exhibit 22742-X0618, AET rebuttal evidence, Table 13. 602 Ontario (Energy Board) v Ontario Power Generation Inc., [2015] 3 SCR 147. 603 Exhibit 22742-X0722, CCA final argument, paragraph 485. 604 OEB, paragraph 102. 605 Exhibit 22742-X0727, AET reply argument, pages 81-82.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 146
649. There is one other preliminary matter the Commission wishes to address before turning to
its findings in this part of the decision. That is, it remains somewhat unclear to the Commission
whether AET is seeking approval of only the real estate rental costs allocated to it by ATCO Ltd.
for the 2018 and 2019 test years, or whether AET is seeking a blanket approval from the
Commission of the full schedule of rental charges set out in ATCO Ltd.’s 10 year lease,
including all 10 annual escalation charges. The Commission, notes, however, that in its reply
argument, AET stated that:
…the evidence on the record establishes that neither the term of the lease commitment,
being 10 years, nor the escalation included in the ATCO Park Lease, detract from the
reasonableness of the ATCO Park Lease rental rates...the Commission should not assess
the reasonableness of the rental forecast to be included in head office costs allocated to
AET with “hindsight.” Therefore, material changes in market rates for comparable real
estate after the point in time when the commitment was made to proceed with ATCO
Park are not relevant to the Commission's determination of fair market value of the
subject rental rates. Given that a hindsight analysis is not appropriate, the benefit or risk
of material change in the rental market does not render the ATCO Park Lease rates
unreasonable or imprudent. As such, the Commission should not penalize the shareholder
as a result of market downturns during the term of a lease, just as it would be
inappropriate to impose additional costs associated with market rental increases on
customers during the term of a lease. Both sides should be expected to honour the terms
of the agreement they have entered into, and the Commission should approve the
inclusion of the associated costs, as long as it is shown that [they] were reasonable, as is
the case here, at the time the commitment was made.606 [emphasis added]
650. Based on this detailed explanation of AET's position, the Commission will treat AET as
having applied for approval of the schedule of direct head office rental costs for the full term of
the lease, and not just those for the two years of the current test period.
Commission findings
651. AET, the CCA and the UCA all agree that head office rent will be determined by the
Commission based on its authority to set just and reasonable rates pursuant to Section 121(2)(a)
of the Electric Utilities Act. The Commission determines rates, in accordance with its legislative
mandate, which requires it to render decisions in the public interest.607 The Commission tests
rates given the Commission’s rate-setting function and recognizing its role as a specialized and
expert tribunal.608
652. The burden of proof to show that a tariff is just and reasonable lies with the party seeking
approval of the tariff.609 Section 122(1)(h) states:
606 Exhibit 22742-X0727, AET reply argument, page 80 607 Section 6(1)(a) of the Alberta Utilities Commission Act provides that Commission members “shall act honestly,
in good faith and in the public interest.” 608 ATCO Gas and Pipelines Ltd v Alberta (Utilities Commission), 2014 ABCA 397, paragraph 17, where the Court
commented, “The Commission is a specialized body with a high level of expertise in a wide range of areas:
ATCO Gas and Pipelines Ltd v Alberta (Utilities Commission), 2014 ABCA 28 at para, 26. These include:
utility regulatory reform, competition policy, strategic planning and development, wholesale markets, service
quality and compliance standards, performance-based and incentive regulation, capital structure of regulated
utilities, debt and equity markets, utility assets dispositions, utility deregulation and, of course, rate-related
regulation – along with the policy considerations involved in each.” 609 Section 121 of the Electric Utilities Act.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 147
When considering a tariff application, the Commission must have regard for the principle
that a tariff approved by it must provide the owner of an electric utility with a reasonable
opportunity to recover
…
(h) any other prudent costs and expenses that the Commission considers appropriate,
including a fair allocation of the owner’s costs and expenses that relate to any or all of the
owner’s electric utilities.
653. AET is an “owner” of a transmission facility as defined in Section 1(1)(jj) of the Electric
Utilities Act.
654. AET submitted that the Commission’s consideration of whether the allocated head office
rent costs constitute just and reasonable rates for head office rent during the 2018-2019 test
period should be based on whether these rent costs were consistent with FMV in 2013, that is, at
the time ATCO Ltd. made a commitment on behalf of the ATCO group of companies to proceed
with ATCO Park.610 In AET’s submission, if the Commission finds that the rental costs being
allocated to AET by ATCO Ltd. are consistent with FMV in 2013, then recovering these costs
through AET’s 2018-2019 revenue requirement is reasonable. Earlier in the proceeding,
including the hearing itself, AET had suggested that in order for the Commission to be able to
make such a determination, it must first conduct a prudency assessment of ATCO Ltd.’s decision
to build a new head office at ATCO Park for the ATCO group of companies. In AET’s
submission, were the Commission to find that ATCO Ltd.’s 2013 decision was prudent, and that
the costs of giving effect to this decision were likewise prudently incurred, based on what was or
should have been known to ATCO Ltd. at that time about conditions in the downtown and
suburban Calgary commercial property market, then the Commission must conclude that the
head office rent costs being allocated to AET by ATCO Ltd., including the increases in rent costs
during the test period, constitute FMV and, hence, are just and reasonable.611
655. As the Commission in questioning pointed out several times during the hearing, however,
the Commission's task is to set just and reasonable rates for AET, not its unregulated parent
company. Thus, whether ATCO Ltd., was prudent or imprudent in deciding in 2013 to build new
head office space for the ATCO group of companies, and whether the costs it subsequently
incurred in doing so were prudent or imprudent, has no bearing on whether the head office rental
costs that AET is seeking to recover from customers during the 2018-2019 test period are just
and reasonable.
656. AET conceded this point during argument and reply argument, acknowledging that “As
noted by the Commission, the Commission is not testing the corporate decision of ATCO Ltd. to
proceed with ATCO Park in this proceeding.”612 In the latter stages of this proceeding, therefore,
AET stepped away from its earlier request that the Commission conduct a prudency review to
satisfy itself of the reasonableness of ATCO Ltd.’s decision to proceed with the construction of a
new head office at ATCO Park. Instead, AET narrowed its focus to the evidence it submitted on
overcrowding at its then head office in the 2013-2014 period and the market-based rental rate
610 Exhibit 22742-X0727, AET reply argument, page 75. 611 Exhibit 22742-X0727, AET reply argument, paragraph 248. 612 Exhibit 22742-X0727, AET reply argument, paragraph 221.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 148
comparison it compiled in 2013 for commercial real estate comparable to what ATCO Ltd. had
decided to build to meet its needs in future years.
657. All parties agree that the concept of FMV can be of considerable assistance in
ascertaining whether a proposed rate for the rental of commercial real estate is just and
reasonable. Section 2.1(n) of ATCO's Affiliate Code of Conduct defines FMV as “the price
reached in an open and unrestricted market between informed and prudent parties, acting at
arm’s length and under no compulsion to act.” Similar definitions can be found in various other
dictionaries. For example, Black’s Law Dictionary613 defines FMV as “the price that a seller is
willing to accept and a buyer is willing to pay on the open market and in an arm’s length
transaction; the point at which supply and demand intersect.” The Dictionary of Legal Terms,614
meanwhile, defines market value as “the price that property would bring in a market of willing
buyers and willing sellers, in the ordinary course of trade. Market value is generally established,
if possible, on the basis of sales of similar property in the same locality. Market value is
generally synonymous with actual value, cash value, and fair market value.” A similar definition
of FMV can be found in Duhaime’s Law Dictionary: “The hypothetical most probable price that
could be obtained for a property by average, informed purchasers.”615
658. The Commission finds that there is little dispute among the parties to this proceeding on
how FMV should be defined. Far more contentious, however, is when FMV should be measured
in order to provide a benchmark or proxy for just and reasonable rates during the current test
years. In particular, should the FMV of comparable commercial real estate be measured (1) as of
2013; (2) the date the ATCO Ltd. lease was signed; (3) the time period when a stand-alone
regulated entity contemplating a head office move might have reasonably committed to a long
term rental lease; or perhaps (4) closer to the date the leased premises actually became available
for occupancy? According to AET, the FMV of head office rental costs, at least in the case of
ATCO Park, must be determined not at the time the rates are to be charged to AET (that is, the
2018-2019 test period), but at the time the decision was initially made by AET’s parent, ATCO
Ltd., to build ATCO Park. In other words, AET claims that the correct time to ascertain FMV for
its head office rental costs is four to five years before the new rates are to be charged to AET,
notwithstanding the significant and widespread collapse in real estate rental rates in the Calgary
commercial property market during the intervening years.616 As noted above, interveners were of
the view that FMV should be determined much closer to the start of the current test period.
659. The Commission does not accept AET’s submissions on the ATCO Park lease costs. It
finds that AET has failed to meet its onus to establish, on the balance of probabilities, that the
relevant time period to assess the reasonableness of AET’s proposed office space rental rates for
the 2018-2019 test period (and beyond for the remainder of ATCO Ltd.’s lease term) is in 2013
when ATCO Ltd. made an irreversible commitment to build ATCO Park. Notwithstanding
AET’s view that basing AET’s 2018-2019 revenue requirements on the FMV of comparable
commercial real estate in 2013 is just and reasonable, there is insufficient evidence before the
Commission in this proceeding to substantiate these claims.
660. In particular, no business case for the construction of ATCO Park was ever filed for
Commission approval, nor would the Commission have ever accepted an ATCO Ltd. business
613 10th ed., Bryan A. Garner ed., Thomson Reuters, 2009. 614 3rd ed., Steven H Gifis, Barron’s Educational Services Inc., 1998. 615 http://www.duhaime.org/LegalDictionary/F.aspx 616 Exhibit 22742-X0618, AET rebuttal evidence, page 122.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 149
case for such a review had one been filed. This is because the Commission regulates AET and
not ATCO Ltd. and AET had very little, if anything, to do with the decision to build ATCO Park
and relocate there. Moreover, AET provided the Commission no evidence of other alternatives to
committing in 2013 to a new office build and future relocation that it may have put forward for
its parent companies’ consideration. For example, there was no evidence of AET or any of its
affiliates even considering temporary office space to deal with immediate overcrowding while
the “big build” took its expected course. The only alternative discussed in this proceeding was
the all or nothing option described by AET as ATCO Ltd.’s “go/no go” decision. The
Commission notes, in this regard that, according to AET, ATCO Ltd.’s decision to build 200,000
sq. ft. of office space to accommodate 600 employees plus an allowance for future expansion and
workforce growth was “irreversible.”617 Yet, sometime after ATCO Ltd.’s “go/no go” and
“irreversible” decision the ultimate square footage of ATCO Park was reduced to 155,000 sq.
ft.618 In addition, there was no documentary evidence of a legal or commercial nature to support
AET’s claim that its parent made an “irreversible” decision to proceed with ATCO Park at
anytime in 2013.
661. Likewise, there was nothing preventing AET from presenting the Commission with its
own assessment of the alternatives it faced in 2013, its ranking of those alternatives, and how
AET addressed its most pressing future needs for office space with its parent companies,
especially in terms of the type, square footage and rental cost of office space it believed it could
reasonably justify and recover in Commission-approved rates on a going forward basis. In this
regard, AET could also have signed its own lease with ATCO Investments Ltd. on terms it
believed were just and reasonable from a regulatory perspective and at a time that it considered
was equally advantageous to customers as it was fair to its ultimate shareholders. In the absence
of such additional documentation, however, the Commission finds itself with insufficient
evidence to support AET’s position that the head office rent costs its unregulated parent, ATCO
Ltd., wants AET to recover through its rates in 2018 and 2019 (and beyond), are just and
reasonable. At the same time, the Commission reiterates that it has no jurisdiction to assess the
prudence of ATCO Ltd.’s 2013 decision to build ATCO Park and the costs it incurred as a result.
662. The Commission further notes, in this regard, that there was no witness on the AET
hearing panel who was able to provide any first-hand evidence on the deliberations undertaken
and factors considered by AET’s parent companies at the time the commitment was made to
build ATCO Park. Nor was anyone on the AET panel able to testify on how AET’s parent
companies decided what to build, how much to build, and where to build it.619 For example, in
response to Commission questions on how AET communicated to its parent companies its needs
for office space, Mr. Goguen confirmed that while there may have been some discussions, no
one on the panel was involved in any of them:
617 Exhibit 22742-X0618, AET rebuttal evidence, page 123. 618 Exhibit 22742-X0572, page 24. 619 Transcript, Volume 6, page 887, Mr. Palladino confirmed that AET was not part of the negotiation process with
respect to terms or lease rates; page 1035, Mr. Palladino stated that engagement on space requirements were at
the CEO level and Board of Directors level and that the engagement would have occurred at the more senior
level within the ATCO group of companies. Mr. Palladino confirmed he was not engaged in those discussions;
page 1035, the office space requirements were based on an open-office concept and from that perspective, the
conversation would have happened “at the ATCO level”; page 1042, Mr. Goguen confirms that he was not
involved in the signing of the lease; and page 1070, Mr. Palladino confirmed that he was not aware of the
circumstances as to why the lease was signed in 2017.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 150
Q. So presumably no one -- did anyone on this witness panel get involved in the
discussions regarding AET's needs for space?
A. MR. GOGUEN: So perhaps I'll weigh in. So, firstly, to your question, no, nobody on
the panel. I was in a different role at that point in time. And perhaps just to correct
Mr. Palladino’s statement just slightly, he used the term “managing director.” Managing
directors came into the fold as part of our corporate reorg in 2015. Prior to that we had
presidents of the company. And I'm surmising that the presidents would have had -- made
representations of expectations of growth, et cetera, so that there's an overall common
understanding as to where the company’s going. And that would have been part of the
dialogue, I guess, from a corporate perspective in determining what the right approach
would have been.620 [emphasis added]
663. In addition, the Commission agrees with Mr. Madsen’s testimony that there is not a full
understanding of the decisions made in the 2013 timeframe, including those relating to the long-
term lease arrangement between certain ATCO companies (not including AET) that was only
signed in 2017:
Like my first point would be that I don't think we have a fulsome understanding of all the
considerations and factors that were -- that went into informing that decision, because we
did not have an ATCO witness, nor did we have an ATCO business case. As far as
simply because they made the decision to incur rental costs for a period of ten years at a
point in time and they believed that that decision was reasonable at that point in time,
again, I would turn back to the fact that these are operating costs. The Commission
assesses the reasonableness of a forecast operating cost in each period. Decisions that
occurred in the past which, may be prudent in the past, does not define those operating
costs as being prudent in the current period from a forecast perspective, in my opinion.
I think that they still need to be assessed for reasonableness in the current period.621
664. Because AET did not have input into or direct knowledge of the decision-making process
of the parent, and in the absence of clear insight into that process, there is also very little
evidence upon which the Commission can make a finding on the justness and reasonableness of
the actual amount, nature and quality of head office space being allocated to AET by its parent
and the rental rates being charged to AET for this space. AET has failed to meet its onus to
demonstrate that the head office rent costs it is seeking to recover in rates during the 2018-2019
test period (and beyond), including the allocation of space to AET underpinning those costs, are
just and reasonable.
665. This leaves the Commission in the position of having to decide how head office rental
rates for AET should be determined as there is insufficient evidence that prevailing market rental
rates for comparable commercial properties in Calgary during the 2013 time period provide a
reasonable basis for setting rates in 2018 and 2019 (and beyond). Although Mr. Palladino stated
it would take more than 12 to 24 months622 for AET to plan a head office move, in the
circumstances of this case, there is insufficient evidence to support what a reasonable time period
would be to plan an office relocation and then lease rental space for AET. The Commission does
not have the benefit of an AET lease or sublease and AET did not provide a business case to
justify its rental costs as a stand-alone entity as part of its 2018-2019 GTA.
620 Transcript, Volume 6, page 1036, lines 4-20. 621 Transcript, Volume 7, page 1192, line 18 to page 1193 line 9. 622 Transcript, Volume 6, page 895, lines 16 to 19.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 151
666. Absent other material and relevant information, such as an independent, standalone
assessment by AET of the head office rent that should be attributable to the regulated business,
or the existence of a formal AET lease or sublease, the best information available to the
Commission to set the appropriate time for determining the FMV of head office rent is the
ATCO Ltd. lease, which took effect on August 1, 2017. The lease is the only legal document that
provides a starting date for the legal obligations associated with the office space in ATCO Park.
It is also the only legal document that describes the term of the rights and obligations associated
with the leased premises and the head office rental costs that are allocated to and ultimately
included in AET’s head office rent.
667. In its argument, the CCA suggested that the Commission impute a lease rate of $20 per
sq. ft., that being the current rate at ATCO Centre, along with an operating cost allowance of
$16.50 per sq. ft.623 The UCA supported the recommendations of the CCA.624
668. In considering the evidence on the record with respect to the lease rate to be allowed for
the test period, the Commission concurs with the CCA that allowing a lease rate of $20.00 per
sq. ft. for both test years is reasonable. The Commission also considers that an operating cost
allowance of $16.00 per sq. ft. for 2018 is reasonable with an allowance of $16.50 per sq. ft. for
the 2019 test year. The $16.00 per sq. ft. approved for 2018 allows for a reasonable inflationary
increase over what AET states is the current estimate at ATCO Centre of $15.27 per sq. ft.625 The
$16.50 per sq. ft. approved for 2019 allows for an inflationary increase over 2018. AET is
directed to use these amounts in its compliance filing for purposes of determining its revenue
requirement.
669. For purposes of determining lease rates, AET is directed to provide, in its compliance
filing, evidence with respect to escalation rates that might be present in 10 year leases at the time
the ATCO Ltd. lease was signed in August 2017, and the Commission will consider whether the
approval of an escalator is warranted. The Commission’s determinations with respect to the
operating cost portion of the rental costs apply only to the current test period.
670. Turning to the calculations underlying AET's forecast head office costs, the Commission
notes that the increase in head office rent costs associated with ATCO Park is the result of two
primary drivers. The first driver is an increase in rented space from approximately 85,000 sq. ft.
in the ATCO Centre in downtown Calgary to 155,000 sq. ft. in ATCO Park in southwest
Calgary. The second driver is the increase in the office rental rate from $20 per sq. ft. to $32 per
sq. ft. at ATCO Park.626 The Commission will determine whether these drivers, or inputs to the
calculation of head office rent, are reasonable.
671. AET has stated that the forecast amount of head office rent allocated to it for the office
space occupied by corporate staff providing services to AET was $1.8 million for each of the test
years. A breakdown was provided in a response to a CCA IR,627 which demonstrated that the
majority of this forecast cost, $1.6 million for each test year, related to ATCO Park and was the
623 Exhibit 22742-X0722, CCA final argument, page 173. 624 Exhibit 22742-X0724, UCA final argument, page 25. 625 Exhibit 22742-X0572, page 24. 626 Exhibit 22742-X0557.01, AET-AUC-20180CT04-011(a), PDF page 154. 627 Exhibit 22742-X0572, page 24, AET-CCA-20180CT05-013(e), Attachment 1.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 152
reason for the significant increase in allocated corporate office rent. The table is reproduced
below:
Table 42. Forecast head office rent628
Description
Actual 2015
Actual 2016
Actual 2017
Forecast 2018
Forecast 2019
($ million)
Office rent per Sch 25-9 (total) 3.6 3.6 4.2 8.6 8.6
Comprised of:
ATCO Centre I 2.4 2.4 2.8 - -
ATCO Park - - - 7.8 7.8
ATCO Centre Edmonton 0.5 0.5 0.7 0.6 0.6
Other 0.7 0.7 0.7 0.2 0.2
3.6 3.6 4.2 8.6 8.6
AET allocation 18.0% 19.8% 19.9% 21.0% 21.0%
Office rent per Sch 25-9 (AET share) 0.6 0.7 0.8 1.8 1.8
Comprised of:
ATCO Centre I 0.4 0.5 0.6 - -
ATCO Park - - - 1.6 1.6
ATCO Centre Edmonton 0.1 0.1 0.1 0.1 0.1
Other 0.1 0.1 0.1 0.1 0.1
0.6 0.7 0.8 1.8 1.8
672. In the Commission’s view, affiliates appear to be charged twice for the same square
footage in the calculation of the total office rent. The calculation shows AET being allocated a
portion of 100 per cent of the cost of ATCO Park rather than the portion occupied by corporate
staff. This is verified by the calculation of ATCO Park costs as $7.8 million in the 2018 and 2019
forecasts ((which was derived based on $32 per sq. ft. rent + $18 per sq. ft. operating cost)629
times 155,000 sq. ft.). AET is being charged 21 per cent630 of this amount, which comes to
$1.6 million in each year.
673. AET was clear in its argument, however, that the portion of corporate space occupied by
direct AET employees was charged through the first category of office costs, head office rent.
AET stated:631
…with respect to the first category of costs, rent for AET leased space for AET
employees, these lease costs are forecast in USA 931.1 (Ex. X0001.02, Schedule 25-3,
628 Exhibit 22742-X0572, IR response to CCA-2018OCT05-013(e), page 24. 629 Exhibit 22742-X0572, page 24. 630 Exhibit 22742-X0572.02, page 24. The percentage of corporate costs that AET is allocated per the allocation
formula. Exhibit 22742-X0002, Schedule 28-8-1 shows the calculations. 631 Exhibit 22742-X0725, AET final argument, page 100.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 153
line 106). USA 931.1 captures the costs of AET's leased spaced costs, including ATCO
Park.
674. Given the above statement, it is clear to the Commission that the only portion of ATCO
Park costs to be allocated to AET through Corporate office rent account, USA 930.2, is AET’s
portion of corporate staff occupying space. From the response to Undertaking 52632 there were
459 employees at ATCO Park but only 237 were related to corporate functions – 177 head office
and 60 shared service employees. In the Commission’s view, it is only the pro rata share of these
employees’ costs at ATCO Park that should be charged to AET through corporate office rent
USA 930.2. That is, 21 per cent of the costs related to the 237 corporate employees.
675. In addition, to determine AET's reasonable share of corporate rent costs, the Commission
considers it necessary to examine the total capacity at ATCO Park. As noted in AET’s rebuttal
evidence, the occupancy at ATCO Centre was 90 per cent at the end of 2013 and was forecast to
rise to 98 per cent by the end of 2014. According to AET, the ATCO group of companies
considered the space at ATCO Centre inadequate and described the situation as follows:
During the years leading up to 2013, to cope with the capacity issues, ATCO reduced the
size of cubicles, increased the number of bullpen-type spaces, and placed up to four
people in offices intended for one employee. While this provides a workable solution for
the short-term, a long-term solution was required that would also allow for leasing rate
predictability.633
676. The Commission accepts this evidence as demonstrating that the ATCO group of
companies were facing space constraints at ATCO Centre by 2013 heading into 2014. In rebuttal
evidence, AET stated that when the move to ATCO Park was initially decided, it was expected
that 200,000 sq. ft. would be needed to accommodate 600 employees, plus an allowance for
future expansion and workforce growth.634
677. The actual space in the lease for ATCO Park is 155,000 sq. ft.635 During the hearing,
Commission counsel asked AET whether there was any industry benchmark relied upon to
determine the square footage requirements. Mr. Palladino responded:
I'm not aware of an industry benchmark that they may have looked at other than the
requirements they had at the time to facilitate the growing FTE requirements that they
were forecasting.636
678. AET did not identify benchmarks for office space square footage. There is a significant
increase in total square footage at ATCO Park, 155,000 sq. ft., over that available at ATCO
Centre, 85,000 sq. ft.637 As stated in AET’s rebuttal evidence, when ATCO Group initially
planned ATCO Park it considered it would need a space of 200,000 sq. ft. to accommodate 600
employees, plus an allowance for future expansion and workforce growth. The Commission
considers that the workforce reductions within the ATCO Group and AET since 2015 offset the
need for an allocation for future growth, which was identified in the initial planning by the
632 Exhibit 22742-X0696. 633 Exhibit 22742-X0618, AET rebuttal evidence, page 123. 634 Exhibit 22742-X0618, AET rebuttal evidence, page 123. 635 Exhibit-22742-X0572, page 24. 636 Transcript, Volume 6, page 882, lines 11-14. 637 Exhibit 22742-X0618, AET rebuttal evidence, page 121.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 154
ATCO Group. The Commission considers the actual space per sq. ft. at ATCO Park should be
sufficient to accommodate the 600 employees identified as the initial baseline need.638 Based on
600 employees and using 155,000 sq. ft., this equates to approximately 260 sq. ft./employee.
679. The Commission notes that the actual occupancy of ATCO Park is only 459
employees.639 AET has indicated that it targets a vacancy rate of seven per cent with respect to
office space.640 Applying this factor to the actual number of employees currently housed at
ATCO Park indicates that ATCO Ltd. only requires sufficient space for approximately 500
employees,641 not the 600 capacity of ATCO Park. The Commission has concerns with respect to
this excess capacity for 100 staff. Consequently, the Commission considers that ratepayers
should not be charged for a building, meeting rooms, or other common spaces that are excess
capacity i.e., capacity that is beyond what is reasonably required for office space for current
employees and for common space.
680. Therefore, to adjust the number of employees used in the allocation of corporate staff,
and to ensure AET's regulated customers are not charged for the capacity of 100 staff identified
above, AET is directed to compute the square footage in its allocation of corporate rent for
ATCO Park on the basis of (260/600)642 x 21 per cent. The numerator is the sum of head office
employees and shared services employees identified in Undertaking 52, adjusted for the seven
per cent vacancy factor. The denominator of 600 is the total employee capacity of ATCO Park.643
The use of the total employee capacity as the denominator will ensure that AET is not charged
for the excess capacity that exists at ATCO Park and would otherwise be charged if the actual
occupancy of 459 were used.
681. The above adjustment corrects the charges to USA 930.2 for AET’s portion of corporate
head office lease costs. The Commission also notes that a similar adjustment should be made to
USA 931.1 to correct the charges to AET for the 21 direct AET employees, plus the adjustment
for the seven per cent building vacancy rate, in ATCO Park. AET is directed to make this
adjustment in its compliance filing.
682. The Commission notes that IR response AET-CCA-2018OCT05-013(e)644 indicates that
AET is also charged for space occupied by corporate staff at other locations. In its compliance
filing, AET is directed to provide the calculations supporting these charges to enable the
Commission to verify that charges for corporate staff at other locations are reasonable.
683. Separate and apart from head office rental costs, the lease costs for the amount charged in
USA 931.1, for AET employees directly occupying corporate office space, are forecast to be
$1.5 million in each of the test years. While AET has identified that $1.4 million of this is
payable to Canadian Utilities Limited645 no breakdown has been provided as to the facilities
rented or how the forecast rent expense has been calculated. To ensure that the Commission has
a thorough understanding of how the forecast has been determined, AET is directed in its
638 Exhibit 22742-X0618, AET rebuttal evidence, page 123. 639 Exhibit 22742-X0696, Undertaking 52. 640 Exhibit 22742-X0288, AET-CCA-2017AUG30-048, page 165. 641 Calculated as: 459 employees x 1.07 = 491 actual capacity needed, will be rounded up to 500. 642 Calculated as: 237 employees x 1.07 = 254. The number of corporate staff for which housing would be required
for with the vacancy factor. Rounded up to 260. 643 Exhibit 22742-X0618, AET rebuttal evidence, page 121. 644 Exhibit 22742-X0572, page 24. 645 Exhibit 22742-X0002.04, Schedule 30-8.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 155
compliance filing to identify the facilities leased and to provide the calculations showing how the
forecast of $1.5 million has been derived, and the Commission will test these costs further in the
compliance filing.
15.5 Reserve for injuries and damages
684. AET discussed the reserve for injuries and damages (RID) in Section 29.2 of the
application.646 For the test years, AET forecast charges to the reserve account of $700,000 in
2018 and $200,000 in 2019, noting that the decrease in charges from past years is due to lower
actual claims experienced. For 2018 and 2019, AET included a provision of $0 to move the
account towards a target balance of zero by the end of 2019. AET applied for approval to
continue to annually settle any differences between the approved amounts and actual amounts
within this reserve account as part of its Transmission Deferral Account and Annual Filing for
Adjustment Balances Application, similar to the treatment approved in Decision 20272-D01-
2016.647
685. For GTA test periods, AET includes a provision in the RID account for uninsured claims.
The provision is an estimate and does not identify specific claims made by the utility. Actual
claims regarding the RID, and draws against the reserve are reviewed as part of AET’s
application for disposition of deferral accounts and annual filing for adjustment balances
proceedings. However, for this proceeding, AET provided actual claims for the 2015-2017
period.
686. In argument, AET submitted that due to the timing of Decision 20272-D01-2016 and the
timing of the 2018-2019 GTA, actual RID claims for the 2015-2017 period were included in its
revised application. The impact of any differences between actual and approved RID claims for
2015 through 2017 is incorporated into the 2018-2019 GTA RID forecast, which ultimately
settles the balances reflected in this account. Going forward, AET requested in its 2018-2019
GTA the continuation of the ability to settle the reserve balance annually. It is AET’s intention to
true up RID amounts tied to future years in future deferral applications.648
687. The CCA took no position with respect to AET’s request for approval of amounts to be
funded within the RID.
Commission findings
688. There were no objections by interveners to AET’s forecast or its request to settle the RID
on an annual basis. The Commission notes the extended period required to process this
application and the availability of actual amounts for RID claims for the 2015-2017 period. The
Commission has reviewed the RID claims included in attachments 29.2.1 to 29.2.3 to AET’s
revised application, and finds the amounts to be reasonable. The Commission accepts and
approves AET’s forecast amounts of uninsured losses, with the exception of those costs in
respect of the Fort McMurray wildfire as noted in paragraph 3 of this decision. The Commission
accepts AET’s proposal to settle the RID account annually on a go-forward basis. AET is
directed to reflect these changes in its compliance filing to this application.
646 Exhibit 22742-X0001.02, updated application, starting at paragraph 598. 647 Exhibit 22742-X0001.02, updated application, paragraph 599. 648 Exhibit 22742-X0725, AET final argument, paragraph 326.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 156
16 Financing and credit metrics
689. AET’s forecast capital program over the test years is much smaller than that for the
period 2011-2014, which required temporary credit relief measures to address potential negative
impacts on AET's credit metrics. These relief measures comprised: including transmission direct
assigned capital construction work-in-progress (CWIP) balances in rate base, recovery of the
capital portion of pension costs on a cash basis, and recovery of federal future income taxes
(FIT).
690. The Commission, in Decision 20272-D01-2016, directed AET to discontinue CWIP-in-
rate base and the recovery of the capital portion of pension costs on a cash basis effective
January 1, 2017. AET continued to collect FIT in its revenue requirement as its sole credit relief
measure for 2017.
16.1 Credit metrics
691. In its application, AET sought the continued collection of federal FIT for the test period
given the following:
…it results in forecast credit metrics which are in line with those from AET’s 2016 and
2017 GTA as well as the FFO/Debt credit metric range of 9-13% for an “A” rated utility
based on S&P’s low volatility scale which originates from the 2016 Generic Cost of
Capital Proceeding and was continued in the 2018 Generic Cost of Capital Decision
(22570-D01-2018).”649 [footnotes omitted]
692. AET submitted that the continued collection of federal FIT will help maintain credit
metrics at a level that will sustain an “A” rating and minimize the risk of a credit rating
downgrade that would result in higher AET costs for new debt issues.
693. To support its credit metrics during the test period, “AET is targeting the middle to upper
part of the 9-13% FFO/Debt range.”650 AET included the following table in its application:
Table 43. Credit metrics scenarios with and without federal FIT
2018 Scenarios
Federal FIT No relief
FFO/Debt 11.4% 10.5%
FFO interest coverage 3.49 3.29
Interest coverage 2.26 2.26
2019 Scenarios
Federal FIT No relief
FFO/Debt 11.4% 10.7%
FFO interest coverage 3.48 3.32
Interest coverage 2.30 2.30
Source: Exhibit 22742-X0001.02, application, paragraph 576.
649 Exhibit 22742-X0001.02, updated application, paragraph 573. 650 Exhibit 22742-X0001.02, updated application, paragraph 577.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 157
694. Mr. Bell presented evidence, on behalf of the UCA, showing the credit metrics levels
with and without federal FIT.651 The following tables reflect credit metrics which include federal
FIT credit relief:
Table 44. Credit metrics scenarios which include federal FIT
2018 With refund of CWIP Without refund of CWIP
FFO/Debt 12.0% 11.4%
FFO interest coverage 3.60 3.49
Interest coverage 2.26 2.26
2019 With refund of CWIP Without refund of CWIP
FFO/Debt 11.8% 11.4%
FFO interest coverage 3.58 3.48
Interest coverage 2.30 2.30
Source: Exhibit 22742-X0599, Mr. Bell evidence on behalf of the UCA, paragraph A22, PDF page 14.
695. The following tables reflect credit metrics which exclude federal FIT credit relief:
Table 45. Credit metrics scenarios which exclude federal FIT
2018 With refund of CWIP Without refund of CWIP
FFO/Debt 10.5% 10.5%
FFO interest coverage 3.29 3.29
Interest coverage 2.26 2.26
2019 With refund of CWIP Without refund of CWIP
FFO/Debt 10.6% 10.7%
FFO interest coverage 3.32 3.32
Interest coverage 2.30 2.30
Source: Exhibit 22742-X0599, Mr. Bell evidence on behalf of the UCA, paragraph A22, PDF page 14.
696. Mr. Bell observed that AET's credit metrics, as shown in the tables above, are well within
the Commission-prescribed ranges of 9 to 13 per cent652 established in the 2018 Generic Cost of
Capital decision,653 even with the refund of CWIP-in-rate base balances and excluding federal
FIT. Mr. Bell added, “The FFO to Debt percentages of 10.5% and 10.6% for 2018 and 2019
respectively are well above the AUC floor of 9%, and even above 10%. Further I note that the
ratios increase from 2018 to 2019.”654
697. Mr. Bell submitted655 that credit ratings agencies consider:
…the regulated utilities as low risk ventures, and any risk faced by shareholders is
largely derived from other business ventures. In fact, it is entirely possible that, on a
standalone basis, the credit ratings of the other non-regulated ATCO entities would be
much lower were it not for the support provided by the regulated ATCO entities.
651 Exhibit 22742-X0599, Mr. Bell evidence on behalf of the UCA, paragraph A22, PDF page 14. 652 Decision 22570-D01-2018, paragraph 700. 653 Decision 22570-D01-2018, paragraphs 775-776. 654 Exhibit 22742-X0599, Mr. Bell evidence on behalf of the UCA, paragraph A23, PDF page 15. 655 Exhibit 22742-X0599, Mr. Bell evidence on behalf of the UCA, paragraph A24, PDF page 16.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 158
698. For the above reasons, Mr. Bell recommended that the collection of federal FIT be
removed from the 2018 and 2019 revenue requirements, resulting in reductions of $29.2 million
and $23.8 million for 2018 and 2019, respectively.656
699. In its argument, the UCA submitted:
…the evidence suggests that it is not AET and its regulated activities that are responsible
for the factors that credit agencies consider to be creating pressure upon ATCO Ltd.’s
credit rating. Again, the credit rating agencies routinely view AET’s regulated activities
as posing less of a risk to credit metrics than unregulated activities do. Ultimately, AET
ratepayers should not be responsible for supporting CU Inc.’s credit ratings, to counteract
pressures placed upon them by unregulated affiliates. In the circumstances, the available
rate relief should be provided.657
700. AET challenged Mr. Bell’s position that an acceptable FFO-to-debt ratio above the
Commission floor of nine per cent or even 10 per cent is not supported.658 It argued that targeting
the middle to upper part of the Commission's approved nine to 13 per cent FFO-to-debt range is
prudent because AET and ultimately CU Inc.’s credit metrics need to remain well supported to
minimize the risk of a further credit rating downgrade.
701. In addition, AET stated:
… AET’s current forecast FFO to Debt ratio of 11.4% for each of the 2018 and 2019 Test
Periods is in-line with the AUC’s calculated 11.1% FFO to Debt ratio from the 2018
GCOC Decision. Further, the forecast 2018 and 2019 FFO to Debt ratio of 11.4% is very
close to AET’s 2017 GTA approved forecast for FFO to Debt of 11.2% which is an
appropriate comparison to AET’s 2018-2019 forecast given Federal FIT was approved by
the AUC as the sole credit relief measure for AET’s 2017 Test Period …659
[footnotes omitted]
702. Further, AET submitted that Mr. Bell had mischaracterized statements taken from S&P
credit rating reports by suggesting that the rating downgrade was directly due to unregulated
projects, such as the West Fort McMurray Transmission project.
Mr. Bell appears to use these misleading statements in an attempt to place an increased
weighting on S&P’s consideration of non-regulated projects on its determination of
ATCO Ltd.’s credit rating and imply AET’s request for credit relief of Federal FIT is
required as subsidization for ATCO Ltd. which AET submits is simply not the case.660
703. AET stated that federal FIT amounts collected through the approved revenue requirement
receive no cost capital treatment. This means that customers are compensated at AET's weighted
cost of capital for this no cost capital amount, which is treated as an offset to the return on rate
base that AET earns.
656 Exhibit 22742-X0599, Mr. Bell evidence on behalf of the UCA, paragraph A26, PDF page 17. 657 Exhibit 22742-X0724, UCA final argument, paragraph 100. 658 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 204. 659 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 204. 660 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 205.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 159
Commission findings
704. The Commission’s view on targeting a credit rating in the “A range” has not changed
from the 2016 GCOC or 2018 GCOC, each of which was premised upon maintaining AET's
FFO-to-debt ratio in the range of nine to 13 per cent. In the previous AET GTA, interveners
proposed an FFO-to-debt ratio of 11 per cent, while AET proposed a ratio of at least 14 per cent.
705. In the current GTA, the CCA recommends an FFO-to-debt ratio of between nine per cent
and 10 per cent, while AET requested 11.4 per cent for each of its test years, stating that it was
targeting the middle to upper part of the Commission’s accepted FFO-to-debt range to minimize
the risk of a further credit rating downgrade.
706. The Commission considers that the level of credit metrics should conform to the ranges
and minimums reviewed and established as part of the GCOC proceedings, and that the level of
support required is that which is needed to maintain a stable “A range” rating, which influences
the cost of debt available to the utility.
707. The Commission observes that AET wishes to continue the sole credit relief mechanism
approved in the last GTA for 2017, being the collection of federal FIT. For the 2018 test year,
which has now passed, CU Inc. did not experience a credit rating downgrade. Neither has this
occurred for the first half of 2019 which has now passed as well.
708. The Commission finds that the FFO-to-debt ratio currently requested by AET is close to
the midpoint of the current Commission acceptable range. Further, this level of FFO-to-debt,
which has not resulted in a credit downgrade, is reasonable and contributes to a stable credit
rating from which customers benefit through stable rates for the cost of debt.
709. The FFO-to-debt ratio level proposed by the CCA, which is based upon discontinuing
federal FIT, lies at the lower end of the range generally accepted by the Commission. The FFO-
to-debt range requested by AET, meanwhile, approximates the level approved by the
Commission during the previous GTA.
710. For the reasons above, the Commission has determined that AET may continue to collect
federal FIT for the test years, as its sole credit relief measure.
16.2 Cost of debt
711. AET’s external financing requirements, and those of ATCO Gas and Pipelines Ltd.
(operating as ATCO Gas for gas distribution and ATCO Pipelines for gas transmission), are
obtained through CU Inc.661
712. In its updated application, AET is forecasting the following long term debt issues during
the test years:
661 Exhibit 22742-X0001.02, updated application, paragraph 568.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 160
Table 46. Forecast long-term debt issues during test period
Issue Rate Amount ($ million) Maturity
2018 4.13% 90 2048
2019 4.43% 60 2049
Source: Based on Exhibit 22742-X0001.02, updated application, Table 28.2 Forecast Long Term Debt Issues, paragraph 579.
713. Debt issues would be mirrored down to AET through CU Inc. and are forecast to have a
30 year term to maturity. Forecast debenture rates of 4.13 per cent and 4.43 per cent for 2018 and
2019, respectively, which represent “the mid-year forecast [that] is determined using the average
of year-end forecasts from Consensus Forecasts. This methodology differs from the previous
method undertaken in the AET 2015-2017 GTA, but it provides a more stable forecast as the
Consensus report provides a larger set of data points.”662
714. AET provided the following tables to summarize the forecast debenture rates:663
Table 47. Forecast 2018 long-term debt rate
%
Consensus forecast,10-year GOC
November 2018 2.50
2018 10-year GOC proxy 2.50 2.50
10-30 year GOC bond yield differential 0.18
30-year credit spread 1.45
2018 forecast 30-year debt rate 4.13
Source: Exhibit 22742-X0001.02, updated application, paragraphs 582-583.
Table 48. Forecast 2019 long-term debt rate
%
Consensus forecast,10-year GOC
August 2019 2.80
2019 mid-year 10-year GOC proxy 2.80 2.80
10-30 year GOC bond yield differential 0.18
30-year credit spread 1.45
2019 forecast 30-year debt rate 4.43
Source: Exhibit 22742-X0001.02, Application, paragraphs 582 - 583, PDF pages 596-597.
715. AET sought to discontinue the debt rate deferral account, which had been established by
the Commission in Decision 2013-358.664 It submitted that the decline in the size of its capital
program and the significantly lower forecast of debenture issues in the current application have
reduced the risk of a material difference from forecast occurring.
716. The CCA observed that the forecast debt rate for 2018 was 4.42 per cent in AET’s
original application. Subsequently, the September 2018 application update showed a revised
forecast rate for 2018 of 4.13 per cent, while the actual debt issue by CU Inc. in late November
had an interest rate of 3.95 per cent. The CCA submitted that the actual debt issue rate of
3.95 per cent should be used, and the 2018 revenue requirement should be adjusted accordingly.
662 Exhibit 22742-X0001.02, updated application, paragraph 582. 663 Exhibit 22742-X0001.02, updated application, paragraphs 582-583. 664 Decision 2013-358, paragraphs 923-925.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 161
717. In its argument, the CCA presented the following table displaying a history of AET’s
debt forecasts and subsequent 30-year bond forecasts:665
Table 49. AET 2019 forecast, 2018 actual debt issue and current 30-year bond rates
AET forecast 17/06/16
AET forecast 17/11/10
AET forecast 18/09/04
Actual debt issue
late Nov. 2018
2019 forward rate 19/01/24
Current rate
19/03/12
(%)
Forecast/Actual AET debt rate
4.60 4.72 4.43 3.95
Less: credit spread 1.45 1.45 1.45 1.45
Implied/Actual 30-year bond rate
3.15 3.27 2.98 2.50 2.17 2.02
Source: Exhibit 22742-X0001, PDF page 526; Exhibit 22742-X0001.02, PDF page 622; Transcript, Volume 3, pages 429-430; and Bank of Canada V39056.
718. The CCA argued that its table demonstrates that AET’s forecasts consistently overstate
the actual interest rates that would be paid, and the table shows a falling trend in interest rates
from the original forecast 30-year Canada rate of 3.15 per cent to the current rate of 2.02 per
cent.
719. For 2019, the CCA recommended that the Commission select either the current rate of
2.02 per cent, or the forward rate of 2.17 per cent or, alternately, the average of the current and
forward rate, being 2.1 per cent, if the Commission wished to rely on more than one rate.
720. The CCA submitted that its proposed bond rates are close to the 2.3 per cent rate
established in the 2018 Generic Cost of Capital decision.666 The CCA, however, did not
recommend use of the 2.3 per cent rate given that interest rates appear to have fallen 12 to 30
basis points since the GCOC decision was issued.
721. The CCA argued that AET’s forecasts have been consistently high as they are based on
the Consensus Forecasts. Since AET is forecasting a 30-year bond rate of 2.98 per cent instead
of the current actual rate of 2.02 per cent, the CCA submitted that costs are over-estimated by
$0.4 million for 2019. The CCA’s recommendations with respect to bond rates would result in
2019 debt rates being in the range of 3.47 per cent to 3.62 per cent.
722. The CCA opposed AET’s proposal to eliminate the interest rate deferral account, instead
recommending that it be retained “out of an abundance of caution.”667 The CCA submitted that
should the Commission decide to eliminate the deferral account, the approved rate should be set
no higher than 3.62 per cent for 2019.
723. In argument, AET submitted that the 2018 actual CU Inc. debt issuance of $90 million at
a coupon rate of 3.95 per cent was in line with its 2018 forecast, and that the variance from the
665 Exhibit 22742-X0722, CCA final argument, paragraph 746, PDF page 217. 666 Exhibit 22742-X0722, CCA final argument, paragraph 751-752. 667 Exhibit 22742-X0722, CCA final argument, paragraph 761.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 162
forecast rate of 4.13 per cent had an immaterial impact on revenue requirement of approximately
$0.1 million and $0.2 million for 2018 and 2019, respectively.668
724. In reply argument, AET submitted that the CCA inappropriately introduced new evidence
in its argument about the 2019 debt rate based on information current as of March 12, 2019. AET
argued that it has had no opportunity to test or respond to such evidence and submitted that this
new evidence be struck from the record and be disregarded by the Commission.669
725. In response to the CCA proposal to use the Bloomberg forward curve forecast, AET
argued that the forward curve is not a forecast of what rates will be in the future. Instead, it is an
indication of rates that can be locked-in today for settlement at some point in the future. For this
reason, the forward curve is better suited for coordinating hedging contracts.
726. Lastly, with respect to the debt deferral account, AET submitted that as it no longer meets
the criteria for deferral account treatment, it should be removed.670
Commission findings
727. In Decision 2010-189,671 the Commission considered the following criteria when
evaluating the need for a deferral account:
materiality of the forecast amounts,
uncertainty regarding the accuracy and ability to forecast the amounts,
whether or not the factors affecting the forecasts are beyond a utility’s control and,
whether or not the utility is typically at risk with respect to the forecast amounts672
728. The Commission has also considered a symmetry factor, as described below:
In another Board decision, also referenced in Decision 2003-100, the Board, when
examining the merits of an application for a deferral account on the facts of that
proceeding, took the view that "deferral accounts should not be for the sole benefit of
either the company or the customers." Deferral accounts, rather, should “provide a degree
of protection to both the Company and the customers from circumstances beyond their
control,” and hence “[s]ymmetry must exist between costs and benefits for both the
Company and its customers." The Board also noted that it expected that "the individual
mechanisms involved in the use of each deferral account should be applied in a consistent
and fair manner in both test years and non-test years.673
729. In addition, the Commission’s predecessor, the Alberta Energy and Utilities Board, found
that it did “not consider there to be a definitive Board policy regarding the use of deferral
accounts. Rather, the board’s practice [has] been to evaluate the use of a deferral account on a
case-by-case basis, on its own merit.”674
668 Exhibit 22742-X0725, AET final argument, paragraph 406. 669 Exhibit 22742-X0725, AET final argument, paragraph 292. 670 Exhibit 22742-X0725, AET final argument, paragraph 295. 671 Decision 2010-189. 672 Decision 2010-189, paragraph 72. 673 Decision 2010-189, paragraph 73. 674 Decision 2003-100: ATCO Pipelines, 2003/2004 General Rate Application – Phase I, Application 1292783-1,
December 2, 2003, page 116.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 163
730. AET sought to have the debt rate deferral account discontinued, due to its smaller capital
program and correspondingly lower forecast debt issues, resulting in reduced risk of material
forecast differences. The CCA, however, recommended maintaining the deferral account given
AET’s forecast history, which consistently overstated the actual interest rates that would be paid.
731. The Commission observes that while the capital program in the current application has
moderated, there has been little change in the size of forecast long-term debt issues in 2016
($120 million) and 2017 ($55 million) relative to the size of forecast debt issues in the current
test period.
732. For the 2018 test year, AET forecast a long-term debt issue of $90 million using a
forecast debt rate of 4.13 per cent, which has subsequently been replaced with an actual rate of
3.95 per cent. For 2019, AET has forecast a long term debt issue of $60 million at an interest rate
of 4.43 per cent, while the CCA has recommended debt rates in the range of 3.47 per cent to
3.62 per cent. While AET’s debt rate forecasts in its application show an increasing trend, the
CCA argued that there was, instead, a falling trend in actual interest rates.
733. These debt rate forecast variances for 2019 fall between the level of three quarters to one
per cent, which the Commission considers material based upon the forecast debt issue amount of
$60 million. Further, the Commission finds that the continued use of deferral account treatment
provides a balance of protection for the utility and customers, as required by the symmetry
factor.
734. For these reasons, the Commission considers that the debt rate deferral account should
continue to be used, but in this case, only for the 2019 test year. For 2018, the Commission
directs that the actual cost of debt be used. The amount to be recorded in the 2019 deferral
account is to be determined by updating the approved “Schedule of Debt Capital Employed and
Embedded Cost” (Schedule 28-2) for 2019 to reflect the actual weighted debenture rate for 2018;
and updating the same schedule for 2019 to reflect the actual weighted debenture rates for each
of 2018 and 2019. The resulting embedded cost of debt for the applicable year will then be used
to update the “Schedule of Capital Structure and Average Cost of Capital” (Schedule 28-1) for
that year. This will result in an updated return on long-term debt for that year. The difference
between the updated return on debt and the approved return on debt for that year will be the
resulting balance in the debenture rate deferral account for that year.
735. Given the approval for the continued use of the debt rate deferral account for 2019, the
Commission needs to determine a reasonable forecast for the cost of debt to be used for the
second test year. As the actual cost of debt and the issue amount for AET’s 2018 debt issuance is
known, the Commission directs AET, in the compliance filing, to update its application in all
aspects to reflect the 2018 actual cost of debt resulting from the actual 2018 long-term debt
issues.
736. The CCA recommended three options for the 2019 debt rate: basing the debt rate on the
current Government of Canada bond rate of 2.02 per cent, the forward Government of Canada
bond rate of 2.17 per cent, or the average of these two rates, being 2.1 per cent. AET challenged
the CCA's submissions on this point because they were based on improperly adduced new
evidence, namely, the current 30-year Canada bond rate as of March 12, 2019. The Commission
agrees with AET's submission that the CCA improperly introduced new evidence in its argument
and, accordingly, will disregard the 2019 information provided in the CCA’s argument.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 164
737. While not in agreement with the CCA's proposed debt rate, the Commission finds AET's
forecast debt rate of 4.43 per cent to be high, particularly in light of its recent bond tender at 3.95
per cent. The Commission directs AET to use 3.95 per cent as a forecast rate for 2019 long-term
debt, especially since this forecast 2019 debt rate will be afforded deferral account treatment.
The Commission, therefore, approves a forecast 2019 debt rate of 3.95 per cent and directs AET,
in its compliance filing, to update its application in all aspects to reflect the forecast long-term
debt cost rates of 3.95 per cent for 2018 and 2019.
17 Revenue offsets and recoveries from affiliates
738. Revenue offsets that form part of revenue requirement include amounts related to facility
charges, affiliate revenues, services to outside parties and other revenue. Facility charges serve to
recover costs incurred by AET when constructing and operating facilities on sites having an
industrial system designation. Affiliate revenue results from AET personnel providing services to
AET affiliates, and the revenue includes “recovery of the direct cost of the service as well as
overhead charges in accordance with the Inter-Affiliate Code of Conduct. Affiliate revenues are
offset by affiliate cost of goods sold which are included in operations costs.”675 Services to
outside parties are performed by AET staff at the request of external parties for projects such as
road moves or work for the AESO.676
739. The table below provides a breakdown of revenue offsets by component:
Table 50. Revenue offset forecasts by component for test years
2018 2019
($ million)
Facility charges 0.5 0.5
Affiliate revenues 6.7 6.7
Services to outside parties 0.3 0.3
Revenue from leasing telemark tower to ATCO Gas 0.7 0.7
Total revenue offsets 8.2 8.1
Source Exhibit 22742-X0002.04, GTA schedules, Transmission Revenue Offsets, Schedule 8-1.
740. Bema presented evidence, on behalf of the CCA, showing that AET’s forecasting
accuracy for revenue offsets was very low. Bema suggested that much of the variance appeared
to be due to AET’s practice of not forecasting contracted services provided to AET affiliates. It
therefore recommended that the following adjustments be made to revenue offsets to align the
test year forecasts with AET’s historical actuals:677
(a) For Alberta PowerLine a $1.2 million and $1.3 million increase in 2018 and 2019,
respectively;
(b) For ATCO Power a $0.6 million increase in each of 2018 and 2019;
(c) For Northland Utilities (Yellowknife) a $0.1 million increase in both 2018 and
2019; and
675 Exhibit 22742-X0001.02, updated application, paragraph 270, PDF page 295. 676 Exhibit 22742-X0001.02, updated application, paragraph 275, PDF page 298. 677 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 649, PDF page 204.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 165
(d) For ATCO Electric Yukon a $0.1 million increase in each of 2018 and 2019.
741. Bema further explained that:678
Bema is not recommending any adjustment to AET’s base operating costs for these
offsets and Bema expects there to be enough staff and resources within AET to provide
this increased level of service to its affiliates. This is supported by the observed declines
in prior years for AET’s operating costs despite steadily increasing revenue offsets to
affiliates.
742. The CCA challenged AET’s continued reliance on an activity-based approach to forecast
revenue offsets, stating “it provides for a consistent and repeated understatement of AET’s
revenue offsets year-after-year.”679
743. The CCA pointed to AET’s need to correct an “inadvertent” error (related to Alberta
PowerLine revenue offsets) as identified by AET in its rebuttal evidence as further proof that the
revenue offsets were not well supported.680
744. In reply argument, the CCA expressed concerns681 over the potential variance between
forecast and actual internal labour allocated to O&M activities that can arise due to changes in
the amount of internal labour actually needed to provide services to affiliates. When less internal
labour than forecast is used for O&M activities because more internal labour is being used to
provide services to affiliates, then ratepayers are likely paying too much based on the O&M
forecasts included in revenue requirement.
745. AET challenged Bema’s characterization of AET’s accuracy in forecasting revenue
offsets as misleading and inaccurate. AET explained that a large portion of the variance is due to
contracted services being provided to AET affiliates. AET explained that it “…does not forecast
these expenses as they are flow-throughs and have no impact on overall revenue requirement.”682
746. In response to the adjustments proposed by the CCA, AET stated:683
There is no evidence on the record that the services AET will provide during the test
period will remain at historical levels or that AET would be able to provide a higher
volume of services than it has forecast without retaining additional staff. AET has
developed its revenue offset forecast, as well as the corresponding Cost of Goods Sold
forecast, based on the best available information on the services that will be provided in
the test period and the resources that will be required to provide these services.
747. With respect to the forecast update for Alberta PowerLine, which AET had not included
in its September 4, 2018 application update, AET explained that given the stage of the
proceeding, “[AET] will flow the related impacts through 2018 and 2019 revenue requirement in
its GTA compliance filing.”684 AET stated that forecast revenue offsets for Alberta PowerLine of
678 Exhibit 22742-X0592, CCA - Evidence of Bema Enterprises, paragraph 650, PDF page 204. 679 Exhibit 22742-X0722, CCA final argument, paragraph 709, PDF page 205. 680 Exhibit 22742-X0722, CCA final argument, paragraph 711, PDF page 206. 681 Exhibit 22742-X0726, CCA reply argument, paragraphs 116-117, PDF pages 28-29. 682 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 177. 683 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 179. 684 Exhibit 22742-X0618, AET rebuttal evidence, PDF page 181.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 166
$2.6 million and $2.4 million for 2018 and 2019, respectively, will be updated to $4.1 million
and $4.6 million, respectively.
748. In argument, AET reiterated that the ATCO Group Inter-Affiliate Code of Conduct
allows provision of services to affiliates on a cost recovery basis, which includes the fully
burdened costs incurred by AET. AET added that “customers are kept neutral on both a forecast
and actual basis due to offsetting entries on the Costs of Goods Sold (‘COGS’) line and the
revenue offset line which yields zero cost to customers.”685
749. In response to Direction 47 of Decision 20272-D01-2016, AET performed a review of the
affiliate overhead burden rate. While the methodology used to calculate the overhead rate has not
changed, AET removed certain costs from the overhead rate calculation because they are
specifically linked and attributed to the function of AET’s utility assets and are not required to
support labour charged to affiliate projects. Further, some costs previously identified as support,
or overhead type costs for providing services to affiliates were removed from the overhead rate
calculation because these costs are being directly charged to affiliate projects by the groups
involved. AET added that:
The result of AET's affiliate overhead rate review is the calculation of a 23% overhead
rate, which has been applied in AET's forecast costs for affiliate services in 2018 and
2019. The former affiliate overhead rate applied prior to this review was calculated as
30% for O&M affiliate work, with an additional 30% burden for capital affiliate work
(for a total of 60% burden on capital affiliate work). The revenue requirement impact of
updating the overhead rate from the previous rate to 23% is approximately $0.1 million
for each of 2018 and 2019.686
750. AET further submitted that its forecast of affiliate work is not related to its forecast of
required O&M work. For this reason, if more or less affiliate work is required, this does not
increase or decrease the O&M activity level. AET stated that even if it does more affiliate work
than it has forecast over the test period, it will be required to complete its forecast O&M work
using other resources, such as capital employees or contractors.687
751. AET confirmed that it did not forecast flow-through costs as part of revenue offsets
because these costs vary widely from month to month and have no impact on overall revenue
requirement. Flow-through costs primarily comprise payments to landowners for land access,
third party contractors (mostly land agents), hearing costs, and legal fees.688
Commission findings
752. The Commission has prepared the following table that provides a historical comparison
of the forecast accuracy for affiliate revenues, which are part of the revenue offsets included in
revenue requirement:
685 Exhibit 22742-X0725, AET final argument, paragraphs 169-170, PDF pages 57-58. 686 Exhibit 22742-X0725, AET final argument, paragraphs 182, PDF pages 61. 687 Exhibit 22742-X0725, AET final argument, paragraphs 171-173, PDF pages 58-59. 688 Exhibit 22742-X0725, AET final argument, paragraphs 177-178, PDF pages 59-60.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 167
Table 51. Historical comparison of forecast and actual affiliate revenues
Description
2015 2016 2017 Test period
approved actual approved actual approved actual 2018 2019
Affiliate revenue ($ million)
Alberta PowerLine 5.1 9.9 10.2 13.8 11.3 19.8 2.6 2.4
ATCO Power 10.5 9.8 2.9 10.8 0.4 7.6 2.2 2.4
ATCO Energy Solutions 9.7 7.9 0.4 0.9 0.4 0.4 0.0 0.0
ATCO Structures & Logistics 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.0
ATCO Electric Distribution 2.7 1.4 2.7 1.2 2.7 1.2 1.3 1.3
ATCO Gas 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
ATCO Electric Yukon 0.0 0.1 0.1 0.0 0.0 0.3 0.2 0.2
Northland Utilities (NWT) 0.1 0.0 0.1 0.1 0.1 0.1 0.1 0.1
Northland Utilities (Yellowknife)
0.0 0.1 0.0 0.0 0.0 0.2 0.1 0.1
Other 0.0 0.0 0.0 0.0 0.0 0.4 0.0 0.0
Total affiliate revenue 28.1 29.3 16.5 27.1 15.0 30.7 6.7 6.7
Source: Based on Proceeding 20272, exhibits 20272-X1101 and 22742-X0002.04 Schedule 8-1 Transmission Revenue Offsets, and Exhibit 22742-X0288, IR response AET-CCA-2017AUG30-060, Attachment 1.
753. While the CCA argued that forecast accuracy of affiliate revenue was low and required
adjustments to approach historical levels, AET countered that adjusting these forecasts to
historical levels was not supported. In addition, AET confirmed that a large part of the variance
between forecast and actual affiliate services is due to contracted services, which are not
forecast.
754. The Commission observes that not only do the forecast and actual service levels provided
to affiliates vary significantly, but a comparison of year-over-year actuals shows that revenues
associated with the services provided by AET to a particular affiliate can also vary significantly.
For this reason, the Commission considers that the adjustments proposed by the CCA based on
historical levels are unsupported. The Commission, therefore, rejects the CCA’s recommended
adjustments to affiliate revenue.
755. In its rebuttal evidence, AET identified an update related to forecast affiliate services for
Alberta PowerLine which had been missed in its September 4, 2018 application update. It
proposed to incorporate forecast updates of revenue offsets for Alberta PowerLine increasing
from $2.6 million and $2.4 million, to $4.1 million and $4.6 million, in 2018 and 2019,
respectively, as part of the GTA compliance filing.
756. The Commission finds AET’s proposal to incorporate the Alberta PowerLine forecast
update as part of the GTA compliance filing to be reasonable. The Commission directs AET to
reflect all impacts related to the Alberta PowerLine forecast update in the GTA compliance filing
arising from the determinations in this decision. The Commission understands that this update
will include charges based upon the new 23 per cent overhead rate. In light of the Commission
findings below regarding overhead rates, AET is directed to treat these updates as placeholders
and to submit forecasts of Alberta PowerLine’s affiliate services with the historical overhead rate
of 30 per cent for O&M and 60 per cent for construction projects in its compliance filing to this
decision.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 168
757. The Commission acknowledges the concern raised by the CCA that changes between
forecast and actual levels of affiliate services provided by AET could change the allocations of
internal labour required to provide those services. If AET forecasts O&M activities based on a
higher level of internal labour than is actually required or used, because those O&M labour
dollars are redirected to provide a higher level of affiliate services than were forecast, the
revenue requirement includes forecast labour dollars paid by AET ratepayers but potentially
without the AET O&M work being completed. In such case, the unused O&M labour dollars
flow to utility earnings. Further, if the O&M work included in the revenue requirement forecast
is not completed in the year forecast, it would not be fair to AET ratepayers to have some portion
of this work forecast in subsequent test years, because ratepayers would then be paying for the
same work twice.
758. AET argued that forecast affiliate work is not related to forecast O&M work, so changes
to the level of required affiliate work would not change the level of O&M activity. In addition,
AET stated it would complete the forecast O&M work using other resources, including capital
employees or contractors. In the Commission's view, this is not a complete answer to the concern
being raised. The issue remains that when the level of services that AET provides to affiliates is
higher than forecast, AET labour is displaced. This, in turn, affects the utility rather than the
affiliate receiving the services. The Commission considers that AET’s claim that there is no cost
to customers from providing affiliate services is only accurate to the extent one disregards
secondary effects (such as what happens to forecast AET work that is not completed because
labour resources had to be drawn from elsewhere to backfill AET’s internal labour that has been
re-assigned to provide higher than forecast services to affiliates). To some extent, AET’s
workforce expands or contracts based on increasing levels of service provided to its affiliates,
but if a shortfall of internal labour arises for AET when providing those services, it appears that
it is AET that must redirect capital employee resources to O&M activities, or hire external
contractors rather than the affiliate or affiliates in question having to do so for themselves.
759. The Commission requires additional information to evaluate the impacts on AET’s O&M
and capital that result from AET providing fluctuating levels of services to its affiliates. If the
affiliates engaged external contractors to provide the services currently provided by AET, the
impact on AET would be limited to the availability of contractors for AET work, or potentially
higher cost O&M activities, if the resources used to backfill are not at the same cost as internal
labour.
760. For this reason, the Commission directs AET to provide the following information as part
of all future GTAs where there is a variance of $0.5 million or more between forecast and actual
affiliate revenues, for any affiliate receiving services from AET:
(a) The forecast, actual and variance amounts for affiliate revenues, broken down by:
(i) AET internal labour
(ii) Fringe benefits on internal labour
(iii) Overhead loading on AET labour-related costs
(iv) Flow-through costs
(b) For the variance in AET internal labour taken from part (a) above, identify each
group that contributed to the internal labour variance, whether the variance amount
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 169
was for O&M or capital-related activities, and, for each variance amount, the dollar
amount and number of FTEs involved.
(c) For each group identified in part (b) above, confirm whether the work related to the
observed variance was backfilled, and provide an explanation of how and when this
was done.
761. Further, the ATCO Inter-Affiliate Code of Conduct requires the charging of “fully
burdened costs of such personnel for the time period they are used by the Affiliate, including
salary, benefits, vacation, materials, disbursements and all applicable overheads”689 for affiliate
services provided on a “cost recovery basis.”
762. In its application, AET provided its review of the affiliate overhead burden rate, in
response to Direction 47 of Decision 20272-D01-2016. The Commission finds that AET has
sufficiently responded to the direction by providing its review, however, as shown in the table
below, a comparison of overhead rates from historical actuals through the successive updates
filed in the current proceeding shows significant change, even during the course of this
proceeding.
Table 52. Historical comparison of overhead recovery rates for affiliate services
2015
actual 2016
actual 2017
forecast
2018 and 2019 test years original
2018 and 2019 test years revised
(%)
Overhead rate 40 30 30 30 23
Additional overhead rate on construction projects
30 30 30 30 0
Total overhead rate on construction projects
70 60 60 60 23
Source: Based on exhibits 22742-X0001 and 22742-X0001.02, Section 31 Affiliate Overhead Rate Review.
763. None of the intervening parties provided argument on overhead recovery for affiliates.
764. The Commission observes that the most recent update to AET’s response to Direction 47
proposes a significant change to the affiliate overhead rate. The Commission needs to satisfy
itself that the cost recovery required by the Affiliate Code of Conduct is fully met. The
Commission notes that the information filed by AET in its review of the affiliate overhead rate
includes limited supporting detail.
765. In an IR response, AET provided the following explanation for the change in the
overhead rate from 30 per cent/60 per cent to 23 per cent:690
As part of an overall review of the components within the overhead calculation, costs that
have been previously identified as support or an overhead cost, mainly salaries and wages
for groups such as engineering, construction, planning and operations were removed from
the calculation of the overhead rate. The reason for the removal of the costs is that any
involvement from these types of groups to provide services to a third-party or affiliate is
689 Decision 2003-040: ATCO Group, Affiliate Transactions and Code of Conduct Proceeding, Part B: Code of
Conduct, Application 1237673-1, May 22, 2003, Definitions, page 3. 690 Exhibit 22742-X0570, AET-CCA-2018OCT05-009, PDF pages 60-61.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 170
directly charged and is thus not also appropriately included again as a support or indirect
cost, that the overhead rate captures. For example, an engineer working on an affiliate
project directly charges one hour of labour to this project. On this hour of direct charged
engineering labour, fringe benefits are applied at a rate of 24% and overhead is applied at
a rate of 23%. From this simple example, it is clear that it is not necessary to include
engineering as a component of the overhead charge because engineering labour has been
directly charged to the project.
To be clear, the methodology employed to calculate the overhead rate has not changed,
rather the review focused on the components within the overhead calculation. The
overall revenue requirement impact is forecast to be approximately $0.1 million for 2018
and 2019, respectively.
766. The Commission notes that in the same IR response, AET stated that it has been applying
the 23 per cent affiliate overhead rate since January 1, 2018. The Commission considers that
AET’s use of its proposed affiliate overhead rate prior to approval for the test years is premature.
For this reason, the proposed affiliate overhead rate of 23 per cent used for 2018 and 2019 shall
be considered as a placeholder until the Commission renders its determination on the matter in
the compliance filing to this decision.
767. The Commission requires additional information to determine whether the significant
reduction to the affiliate overhead rate, along with the direct charging of costs by groups
providing services to AET affiliates, will result in the recovery of fully burdened costs for
personnel involved.
768. For this reason, the Commission directs AET, as part of its compliance filing, to provide
the following information:
(a) An expanded affiliate overhead schedule which adds columns to the current
information shown on the Transmission Overhead Rate schedule691 for each of the
2017 forecast, 2018 actuals, and 2018 and 2019 forecasts taken from the original
GTA application in this proceeding to facilitate comparison.
(b) A schedule that provides a detailed analysis of the affiliate overhead recovery
which compares the increased direct charging and the lower affiliate overhead rate
compared to the use of the previous overhead recovery rate. This comparison shall
identify individually each of the groups involved, and list each of the services that
each group is providing.
769. AET’s accounting policy for provision of services to or receipt of services from affiliates,
states that the overhead rate to be applied to labour charges is as follows:
For non-construction projects an Overhead rate of 30% will be applied to labour charges,
including payroll burden where applicable as defined above. An additional Overhead
rate of 30% will be applied to the labour charges including payroll burden for
construction projects.692
691 Exhibit 22742-X0001.02, updated application, Section 31, Transmission Overhead Rate, Attachment 31.6,
PDF page 1336. 692 Exhibit 22742-X0001.02, updated application, Section 31, Attachment 31.2, PDF page 1193.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 171
770. The Commission directs AET to provide an updated accounting policy for provision of
services to or receipt of services from affiliates that reflects the outcome of the Commission’s
decision on overhead rates in its compliance filing to this decision.
18 Order
771. It is hereby ordered that:
(1) ATCO Electric Ltd. shall file its 2018-2019 transmission general tariff application
compliance filing by August 8, 2019, to reflect the findings, conclusions and
directions in this decision.
Dated on July 4, 2019.
Alberta Utilities Commission
(original signed by)
Bohdan (Don) Romaniuk
Acting Commission Member
(original signed by)
Kristi Sebalj
Commission Member
(original signed by)
Bill Lyttle
Acting Commission Member
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 172
Appendix 1 – Proceeding participants
Name of organization (abbreviation) Company name of counsel or representative
ATCO Electric Ltd. – Transmission (AET)
Bennett Jones LLP
AltaLink Management Ltd. (AltaLink or AML)
Office of the Utilities Consumer Advocate (UCA)
Brownlee LLP Consumers’ Coalition Of Alberta (CCA)
Industrial Power Consumers Association of Alberta (IPCAA)
Alberta Direct Connect Consumers Association (ADC)
Direct Energy Marketing Limited
Alberta Utilities Commission Commission panel B. Romaniuk, Acting Commission Member K. Sebalj, Commission Member B. Lyttle, Acting Commission Member Commission staff
A. Sabo (Commission counsel) D. Cherniwchan L. Mullen C. Strasser J. Cameron D. Ward A. Starkov
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 173
Appendix 2 – Oral hearing – registered appearances
Name of organization (abbreviation) Name of counsel or representative
Witnesses
ATCO Electric Ltd. – Transmission (AET)
L. Keough D. Sheehan
Main panel: P. Goguen P. Bothwell H. Goode D. Hoshowski R. Itiveh K. Moledina N. Palladino Compensation panel: P. Goguen K. Yung N. Palladino
Consumers’ Coalition of Alberta (CCA)
J. Wachowich, QC R. Lee
D. Madsen D. Levson
Office of the Utilities Consumer Advocate (UCA)
T. Marriott, QC K. Rutherford
R. Bell
Alberta Utilities Commission Commission panel B. Romaniuk, Acting Commission Member K. Sebalj, Commission Member B. Lyttle, Acting Commission Member Commission staff
A. Sabo (Commission counsel) J. Graham (Commission counsel) D. Cherniwchan L. Mullen C. Strasser J. Cameron D. Ward
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 174
Appendix 3 – Summary of rulings and procedural requests
(return to text)
The following is a summary of rulings and procedural requests addressed during the proceeding:
1. August 2, 2017: The Commission granted the CCA’s request for AET to update certain
placeholders in its GTA, such as common group allocators and pension cost-of-living
allowances, to reflect the Commission’s determinations in other decisions. The Commission
directed AET to submit an omissions and updates (O&U) filing to reflect the CCA’s requested
updates, responses to IRs and any other new information that was available. The Commission
also granted the UCA’s request for an extension of the deadline for filing IRs. Exhibit 22742-
X0187.
2. September 22, 2017: The Commission granted AET’s request for an extension of the
deadline for filing responses to IRs, and the submission of its O&U filing, both of which were
due on the same day. Exhibit 22742-X0198.
3. October 20, 2017: The Commission granted, in part, AET’s motion requesting that the
Commission not require AET to respond to certain IRs. The Commission granted full or partial
relief requested for certain IRs related to O&M balances, organization information by employee
position, vegetation management and monthly depreciation data. Exhibits 22742-X0225 and
22742-X0226.
4. October 30, 2017: The Commission granted AET’s request for an extension of the
deadline for filing responses to IRs and for the submission of its O&U filing, both of which were
due on the same day. Exhibit 22742-X0228.
5. February 2, 2018: The Commission granted AET’s request for confidential treatment of
certain responses to IRs. Exhibit 22742-X0355.
6. May 2, 2018: The Commission granted, in part, a CCA motion to compel AET to provide
full and complete IR responses to a number of CCA IRs. Exhibits 22742-X0385 and 22742-
X0386.
7. June 11, 2018: The Commission granted AET’s request for confidential treatment of
additional responses to certain IRs. Exhibits 22742-X0414 and 22742-X0415.
8. June 11, 2018: The Commission ruled on the CCA’s request for a schedule adjustment
and a revised process schedule. The Commission granted a one-week delay and updated the
proceeding schedule accordingly. Exhibit 22742-X0416.
9. July 31, 2018: The Commission granted, in part, a CCA and UCA motion to compel AET
to provide full and complete IR responses to a number of IRs. Furthermore, the Commission
directed AET to provide full and complete responses to some of the Commission’s IRs.
Exhibits 22742-X0500, 22742-X0501 and 22742-X0502.
10. September 14, 2018: The Commission granted the CCA and the UCA requests for a third
round of IRs on AET’s September 2018 application update. Exhibit 22742-X0542.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 175
11. October 22, 2018: The Commission granted AET’s request for an extension of the
deadline for filing responses to IRs. Exhibit 22742-X0552.
12. November 8, 2018: The Commission issued a temporary suspension of the process
schedule pending a ruling on AET’s motion requesting that the Commission not require AET to
respond to certain IRs. Exhibit 22742-X0584.
13. November 14, 2018: The Commission granted, in part, AET’s motion requesting that the
Commission not require it to respond to Round 3 IRs. The Commission did not require AET to
respond to three IRs, required it to respond to three IRs, and required it to provide alternative
information to five IRs. The Commission denied the CCA’s request for the Commission to
require AET to provide further updates to the September 2018 application update.
Exhibits 22742-X0585 and 22742-X0586.
14. November 30, 2018: The Commission granted the CCA’s request for an extension of the
deadline for filing of intervener evidence and for filing IRs on intervener evidence.
Exhibit 22742-X0590.
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 176
Appendix 4 – Summary of Commission directions addressed in application
(return to text)
This section is provided for the convenience of readers and outlines the directions from Decision
20272-D01-2016 (ATCO Electric Ltd. 2015-2017 Transmission GTA) that the Commission
finds have been satisfied. Directions not in this appendix are either set out in the following
Appendix 5 as outstanding or have been maintained as new directions. In the event of any
difference between the directions in this section and those in the main body of Decision 20272-
D01-2016, the wording in the main body of Decision 20272-D01-2016 shall prevail.
47. For the above reasons, the Commission considers that affiliate overhead rates should be
examined as part of the next GTA proceeding to determine whether they are adequate.
The Commission directs ATCO Electric to provide a detailed assessment of affiliate
overhead burden rates comparing the current rates applied and their supporting basis, to
the forecast effective rate that results from forecast overhead costs and related forecast
activity levels. An examination of five years of historical information shall be
incorporated for comparison purposes. .......................................................... Paragraph 713
71. Given the lack of business case support provided by the utility in its application, the
Commission is not prepared to approve any of the expenditures forecast for the double
circuit project in the test period and directs ATCO Electric to remove the expenditures
from its current forecast. ATCO Electric is directed to submit a business case with the
requested level of detail in its next GTA. .................................................... Paragraph 1112
73. Given ATCO Electric’s description of asset management in the business case for project
82660 and how it should integrate with MAXIMO, CROW, Oracle, MOPS and GIS
information systems, the Commission is of the view that a comprehensive business case
treating all these components as a single project is required. This business case should
itemize all the work required, including any necessary enhancements or upgrades to the
various IT systems on an historical and go-forward basis. This business case should also
provide a cost/benefit analysis with a clear description of future cost requirements
including as much of the life cycle as can reasonably be anticipated. ATCO Electric is
directed to provide such a business case in its next GTA. ........................... Paragraph 1156
84. For the above reasons, the Commission directs ATCO Electric to prepare and file an
updated comprehensive lead/lag study as part of its next GTA application.
...................................................................................................................... Paragraph 1231
97 For these reasons, the Commission is not persuaded that the RPG’s request is reasonable
in the circumstances. However, it directs ATCO Electric to provide the following
information as part of all future GTA proceedings:
Complete descriptions of all sales or transfers of ATCO Electric transmission
assets occurring in the period covering actual information filed for comparison
use to the test years. Information regarding identified transactions must include a
description of the assets involved, a statement of the transaction value including
confirmation of whether and (if applicable) how fair market value pricing was
determined (including copies of all valuation reports relied upon).
Identification of all asset transactions between ATCO Electric and an affiliate, for
each comparison year of actuals or any portion thereof. For example, in the
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 177
current 2015-2017 proceeding, 2012 through 2014 actuals were provided for
comparative purposes. In addition, the 2015 test year forecast included a portion
of 2015 YTD actuals. For this example, information should be provided for 2012
through 2015 YTD actuals. ............................................................. Paragraph 1385
Other Matters:
9. …The Commission, however, is concerned that certain information is excluded because a
project’s capital expenditures in the test period are less than $5.0 million. The
Commission considers that the $5.0 million threshold should apply to the estimated total
project cost, not the forecast costs in the test period, and that this guideline be strictly
adhered to in all subsequent submissions. ..................................................... Paragraph 851
This section is provided for the convenience of readers and outlines the direction from Decision
21206-D01-2017 (ATCO Electric 2013 and 2014 Transmission Deferral Accounts and Annual
Filings) that the Commission finds has been satisfied. Directions not in this appendix are either
set out in the following Appendix 5 as outstanding or have been maintained as new directions. In
the event of any difference between the direction in this section and that in the main body of
Decision 21206-D01-2017, the wording in the main body of Decision 21206-D01-2017 shall
prevail.
16. However, the Commission is concerned that there may be second order impacts to the tax
method used by ATCO Electric. ATCO Electric’s rebuttal evidence shows an entry at
line 50 that is not clear as to whether there is a second order impact on future income
taxes. Therefore, the Commission directs that this issue be addressed in ATCO Electric’s
next GTA, specifically Proceeding 22742. .................................................... Paragraph 470
This section is provided for the convenience of readers and outlines the direction from Decision
22860-D01-2018 (ATCO Electric 2015-2017 Transmission GTA Second Compliance Filing)
that the Commission finds has been satisfied. Directions not in this appendix are either set out in
the following Appendix 5 as outstanding or have been maintained as new directions. In the event
of any difference between the direction in this section and that in the main body of Decision
22860-D01-2018, the wording in the main body of Decision 22860-D01-2018 shall prevail.
1. It appears to the Commission that the average base salary (total labour dollar per FTE)
method used by ATCO Electric to adjust O&M labour dollars, as a result of changes in
O&M FTEs, differs from how ATCO Electric may be forecasting labour dollars for
O&M FTEs in its GTA. As shown in Table 3, the amounts for labour dollar per O&M
FTE and total labour dollar per FTE are not the same. Therefore, to ensure that neither
ATCO Electric nor its customers are unjustly advantaged or disadvantaged by any
variance between the forecasted labour dollar for an O&M FTE and the use of the
average base salary when O&M FTE adjustments are required, ATCO Electric is directed
in all future applications to use the amounts included in its GTA forecast for each FTE
position when calculating the dollar impacts to FTE adjustments, unless specifically
directed otherwise by the Commission. .........................................................Paragraph 25
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 178
This section is provided for the convenience of readers and outlines the direction from Decision
22859-D01-2018 (ATCO Electric Transmission Common Group Compliance Filing) that the
Commission finds has been satisfied. Directions not in this appendix are either set out in the
following Appendix 5 as outstanding or have been maintained as new directions. In the event of
any difference between the direction in this section and that in the main body of Decision 22859-
D01-2018, the wording in the main body of Decision 22859-D01-2018 shall prevail.
1. As noted above, the Commission did not find credible ATCO Electric - Transmission’s
explanation that it could not reconcile its updated placeholder amounts to the requested
common group compliance filing amounts. In this regard, ATCO Electric has not met its
onus. The limited information detailing the substantive adjustments that occurred in
creating and supporting the entire pool of “common group” FTEs and costs is inadequate
in justifying the portion of costs allocated to ATCO Electric’s transmission function. The
Commission acknowledges that ATCO Electric - Distribution is under performance-
based regulation (PBR) and is only subject to minimum filing requirement (MFR)
schedules. However, further information about common costs is required in future GTAs
to support the costs allocated to ATCO Electric - Transmission. ATCO Electric Ltd. is
directed, on a go-forward basis, to provide all cost-information for every ATCO affiliate,
comprising the total costs and supporting detail, that substantiate and justify the costs
allocated to, or from, ATCO Electric’s transmission function. ....................... Paragraph 49
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 179
Appendix 5 – Summary of Commission directions to be addressed in future applications
(return to text)
This section is provided for the convenience of readers and outlines the directions from
Decision 20272-D01-2016 that the Commission considers remain outstanding. Directions not
listed in this appendix are either listed in the preceding Appendix 4 as completed or maintained
as new directions. In the event of any difference between the directions in this section and those
in the main body of Decision 20272-D01-2016, the wording in the main body of the relevant
decision shall prevail.
Decision 20272-D01-2016
18. On the basis of the foregoing, the Commission denies ATCO Electric’s proposed use of
forecast information in its actuarial database for the purpose of developing depreciation
parameters and directs ATCO Electric in its next depreciation study to revert to its
currently approved methodology which provides for the use of forecast capital additions
solely for the purpose of determining depreciation rates. .............................. Paragraph 400
21. On that basis, ATCO Electric is directed to identify and create a subaccount category for
any USA account that now includes, and in the future will include, assets constructed to
comply with ISO Rule 502.2, including any assets or capital projects constructed before
the ISO rule came into effect, where projects have been constructed under the assumption
that ISO Rule 502.2 would be adopted. ATCO Electric is directed to comply with this
finding at the time of its next depreciation study. .......................................... Paragraph 424
27. At the same time, the Commission wishes to obtain a better understanding of why ATCO
Electric’s costs of retirement for this account appear to significantly exceed that of
industry peers and considers it would be in the public interest and of considerable benefit
to the Commission for ATCO Electric to include a detailed explanation for this in its next
depreciation study. ATCO Electric is directed to provide the noted explanation in its next
depreciation study. ......................................................................................... Paragraph 551
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 180
Appendix 6 – Transcript, Volume 2, 2019-01-22 - Ruling on CCA request to mark two
exhibits
(return to text)
Appendix 6 -
Transcript Volume 2 2019-01-22 Ruling on CCA request to mark two exhibits
(consists of 7 pages)
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 181
Appendix 7 – Summary of Commission directions
This section is provided for the convenience of readers. In the event of any difference between
the directions in this section and those in the main body of the decision, the wording in the main
body of the decision shall prevail.
1. For the above reasons, the Commission finds that AET has failed to justify its requested
FTEs and associated dollar amounts in the test years. Based on the past FTE forecasts
noted above and the inability of AET to accurately track FTEs by cost centre through
various organizational changes, including the new shared services initiative, the
Commission cannot reasonably rely on the FTE forecasts filed by AET. The
Commission, therefore, directs AET to use its 2018 actual FTEs as the approved FTE
complement for 2018. The 2018 FTEs are approved as the opening 2019 FTE
complement. The Commission notes that the direction for 2018 is consistent with AET’s
Rule 005 reporting, which reflected 716.1 FTEs in 2018. ............................... paragraph 53
2. For the purposes of this decision and the compliance filing to follow, the Commission
directs AET not to offset the impacts of the reduction to capital FTEs with an increase in
contractor costs. ............................................................................................... paragraph 54
3. Given that the Commission’s direction to reduce AET’s FTE forecast in 2019 is not a
reduction to specific identifiable positions, AET is directed to calculate the impact of its
O&M FTE reductions using the average O&M salary per FTE and its capital FTE
reductions using the average capital salary per FTE. ...................................... paragraph 56
4. In its compliance filing to this decision, AET is directed to confirm, for the positions it
has forecast to eliminate in 2019, that they have been removed in accordance with the
findings and directions in this section, using the mid-year convention. .......... paragraph 58
5. For the above reasons, AET is directed to provide in its compliance filing a recalculation
of its 2018 severance costs based on the proportion of years of service each severed
position provided to the transmission function, as identified in Exhibit 22742-X0698.
.......................................................................................................................... paragraph 90
6. For the above reasons, AET is directed to incorporate out-of-scope inflation rates of
2.65 per cent for 2018 and 2.0 per cent for 2019 in its compliance filing to this decision.
........................................................................................................................ paragraph 120
7. For confirmation purposes, AET is directed to demonstrate in its compliance filing, with
calculations, that it has prorated its out-of-scope labour inflation to reflect increases
awarded on April 1 of each year. ................................................................... paragraph 122
8. In light of the evidence and testimony on the record, AET’s VPP forecasts are approved
at 80 per cent of the eligible employee payout amounts. This determination is consistent
with the Commission’s previous VPP approval in Decision 20272-D01-2016. In its
compliance filing to this decision, AET is directed to reflect the Commission’s findings
and directions regarding VPP, including those findings with respect to FTEs and labour
inflation rates, which affect eligible employee payout amounts. In implementing this
direction, AET is to take into account the mechanics of the reserve account detailed in
Section 5.2.2.3 Treatment of VPP reserve account balance below. ............. paragraph 156
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 182
9. The Commission has denied AET’s request to amend the mechanics of the VPP reserve
account to be symmetrical in nature, as detailed above. The Commission also agrees with
the CCA that the VPP reserve account balance should be targeted to be as close to zero
by the end of the GTA test periods as possible. The Commission notes in this regard, that
there is no benefit to AET shareholders, ratepayers or employees in maintaining a
positive balance in the VPP reserve account as any positive balance is designated as zero
cost capital. On the other hand, requiring ratepayers to provide VPP funds projected to be
spent, but that may not be spent not only for a period of one or more years after those
VPP funds are collected, but for one or more successive test periods, is prima facie
harmful to customers. In its compliance filing AET is directed to provide options on how
it could best operate the VPP reserve account to avoid an increasing accumulated balance
i.e., the VPP reserve account balance should trend as close to zero as possible ..................
........................................................................................................................ paragraph 160
10. However, the Commission notes that the Alberta provincial government repealed the
carbon tax effective June 4, 2019. The Commission takes notice of this repeal and directs
AET, in its compliance filing to this decision, to remove the effects of the repeal of the
carbon tax from its fuel cost forecast for the months in 2019 that are affected by this
legislative change. The Commission accepts AET’s 2018 fuel cost forecast, as filed in its
updated application. ....................................................................................... paragraph 176
11. Given the uncertainty with SRB costs, the Commission denies AET’s request to
discontinue the existing deferral account for annual structure payments. AET is directed
to reflect, in its compliance filing to this decision, the $200,000 reduction for the 2018
test year. The Commission also accepts the CCA arguments regarding the 2019 forecast
and directs AET to reduce the 2019 forecast by $200,000. ........................... paragraph 205
12. The Commission directs AET to maintain its reserve for vegetation management. As
noted by the CCA, the variance for 2015 was limited because the Commission accepted
actual results rather than forecasts for that year. ............................................ paragraph 209
13. AET’s statement shows that the vegetation management reserve account has supported
stability and AET’s management of its forecast costs. As a result, there is merit in
maintaining this reserve account. The Commission finds that the reserve account should
be continued and therefore directs AET to maintain the use of the vegetation management
reserve account............................................................................................... paragraph 211
14. The Commission shares some of the concerns expressed by the CCA regarding the level
of vegetation management costs. However, the Commission does not agree with the CCA
that a 25 per cent reduction in 2018-2019 vegetation management expenditures is
reasonable. For 2018, the Commission accepts the evidence of AET that 2018 actual
expenditures were tracking close to forecast and approves AET’s 2018 forecast. For
2019, the Commission agrees with the CCA that a reduction is warranted because there is
insufficient support that the forecast work for vegetation management must be completed
in 2019. Accordingly, the Commission directs that AET reduce the forecast vegetation
management costs for 2019 by 10 per cent in its compliance filing to this decision.
........................................................................................................................ paragraph 217
15. Further, the Commission directs AET to provide, in its next GTA, a detailed breakdown
of the savings and lower forecast expenses realized as a result of the transition by AET
from a primarily mechanically based vegetation management program to one that is
primarily based on the application of herbicides. .......................................... paragraph 218
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 183
16. The Commission accepts the submission of AET that its forecast for expenses in this
account reflects a reduced number of IT users. However, the Commission directs AET to
adjust its forecast for this account based on the Commission’s determinations regarding
forecast FTEs in Section 5.1.1 of this decision. ............................................. paragraph 222
17. Further, on June 5, 2019, the Commission issued Decision 20514-D02-2019 regarding
the ATCO Utilities IT common matters proceeding. AET is directed to reflect any
changes arising from the directions in that decision in its compliance filing to this
decision. AET is further directed to provide schedules detailing how the determinations
from Decision 20514-D02-2019 are reflected in its compliance filing. ........ paragraph 223
18. The Commission has examined parties’ evidence with respect to the salvage
methodologies used by EPCOR and APL. While the Commission will make no change to
AET’s depreciation methodology or depreciation rates in this proceeding, the
Commission directs AET, as part of its next depreciation study, to compare AET’s
average service lives and net salvage percentages for its five largest plant accounts (on a
dollar amount basis) to those of other electric transmission utilities in the province.
........................................................................................................................ paragraph 231
19. In its forecast, AET used a 15 per cent tax rate for federal income taxes and a 12 per cent
tax rate for provincial income taxes for both 2018 and 2019. The Commission approves
the 2018 applied-for tax rate of 15 per cent for federal income tax and 12 per cent for
provincial income tax. The Alberta government, in Bill 3: Job Creation Tax Cut (Alberta
Corporate Tax Amendment) Act, reduced the general provincial corporate tax rate from
12 per cent to 11 per cent. Bill 3 came into force on June 28, 2019 and amends sections
21 and 22 of the Alberta Corporate Tax Act, changing the provincial tax rate as of July 1,
2019. The Commission takes notice of the Legislative Assembly of Alberta’s passing of
Bill 3 and directs AET, in its compliance filing, to adjust for any changes in its provincial
tax rate. .......................................................................................................... paragraph 264
20. In the CCA’s reply argument, it acknowledged that it had not reviewed AET’s method
for calculating AFUDC in its income taxes, and recommended that the Commission
allow for further review of AET’s accounting of AFUDC in its income taxes in the
compliance filing. The Commission sees merit in the CCA’s request. AET is directed to
demonstrate in its compliance filing to this decision, using the information that is
currently available on the record of this proceeding, that its treatment of AFUDC in its
calculation of income tax expense does not involve either of the two potential errors
described in paragraph 267 above.................................................................. paragraph 278
21. In its argument, AET stated that it has treated AFUDC similarly in the past. AET is
directed, in its compliance filing to this decision, to provide a proposal to correct any
prior AFUDC-related errors in its calculation of income taxes, which were subsequently
collected through revenue requirement in prior years. .................................. paragraph 279
22. The Commission, however, remains interested in a specific scenario raised by the Bema
witness during the oral hearing. The scenario deals with when an asset is placed into
utility service and the corresponding impact to the asset valuation used for property tax
purposes. Accordingly, AET is directed to explore the timing of the capitalization of its
assets as an acceptable method to potentially reduce the amount of property taxes it
would otherwise be required to pay, and to report, at the time of its next GTA, whether
such timing can or should be taken into account on a go-forward basis. ...... paragraph 317
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 184
23. In its next GTA, however, AET is directed to file variance analyses reflecting the actual
expenditures, explanations for variance from forecast and the current status of projects
not completed. As previously directed in Decision 20272-D01-2016, AET is also
directed to file business cases, at the time of filing its next GTA, for projects with a
forecast value greater than $500,000 that are planned to be completed in the test period
but not forecast in the current application. ..................................................... paragraph 346
24. The Commission and interveners submitted numerous information requests to AET with
respect to these programs as well as the other forecast expenditures. The Commission
finds the evidence filed regarding AET’s forecast GP&E expenditures to be reasonable
and sufficient, and the proposed programs necessary. They are approved as filed. In its
next GTA, AET is directed to file variance analyses reflecting the actual capital
expenditures, explanations for variance from forecast and the current status of projects
not completed. ................................................................................................ paragraph 367
25. The Commission approves the necessary working capital test period forecasts as filed
subject to any adjustments that may be required based on the direction above. The
Commission directs AET, in the compliance filing, to reflect all findings and
determinations in this decision that affect the necessary working capital calculations.
........................................................................................................................ paragraph 520
26. The Commission notes that AET’s application relies on operating cost forecasts based on
the existing activity-based forecasting methodology. The shared services initiative has
not been fully implemented nor has AET requested that the Commission approve the new
methodology in the current proceeding. The Commission considers that further review of
the shared services initiative should be deferred to a future proceeding where it can be
thoroughly examined. The shared services initiative and approval of a new shared
services methodology was a live issue in the ATCO Pipelines’ proceeding (Proceeding
23793). In Decision 23793-D01-2019 issued on June 25, 2019, the Commission directed
ATCO Pipelines to coordinate with AET to ensure consistent information on the shared
services initiative in each of their next GRA and GTA, respectively. The Commission
went on to enumerate the nature of the information required, including the filing of cost
information for all ATCO affiliates to substantiate the costs allocated to all regulated
ATCO entities. The Commission in the current proceeding similarly directs AET to
coordinate with ATCO Pipelines to ensure that both utilities provide the same or
substantially similar information in the same format in support of the shared services in
their next respective GRA and GTA, preferably filing common documents wherever
possible. The information should include evidence supporting the functions created,
justifying total FTEs and costs before allocation to the participating ATCO companies
(AET and all other regulated and non-regulated ATCO entities), and include any analysis,
studies and calculations that explain and support the reasonableness and accuracy of the
allocation methodologies. The Commission finds that it would also be beneficial to show
all calculations that demonstrate the split between O&M and capital under the shared
services initiative in the next GRA and GTA. This common information will allow for a
proper testing of the shared services and for the provision of company specific
information to support shared services costs included in the proposed revenue
requirements. Accordingly, the Commission directs AET to provide the evidence,
analyses, studies and calculations noted above as well as any underlying assumptions for
the split between O&M and capital in its next GTA. ................................... paragraph 540
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 185
27. The Commission acknowledges that of the ATCO companies, AED and ATCO Gas are
under performance-based regulation and are subject only to minimum filing requirement
schedules. However, further information about common costs are required to support the
costs allocated to AET. As such, AET is directed, on a go-forward basis, to provide all
cost information for every ATCO affiliate, comprising the total costs and supporting
detail that substantiate and justify the costs allocated to AET relative to the other
regulated and non-regulated ATCO companies under the shared services initiative.
........................................................................................................................ paragraph 541
28. The Commission finds the arguments of the CCA to be more persuasive. The
Commission considers that it would be more consistent if deferral revenues were
included in the determination of the allocation factor and with AET’s treatment of
deferral revenues in Rule 005. In the Commission’s view, these deferral revenues can still
affect the revenue requirement of the entity, and the deferral revenues of direct assigned
capital are a function of, and reflect, the actual capital invested. Therefore, AET is
directed to include deferral account revenues in calculating net revenue for purposes of
the common cost group allocation methodology. .......................................... paragraph 569
29. On the question of whether CWIP should be included in PP&E for the purpose of
determining cost allocation, the Commission finds the arguments of AET to be more
persuasive. In the Commission’s view, including CWIP in PP&E more accurately reflects
the actual capital invested. The Commission also accepts that it is consistent with prior
practice. Therefore, AET is directed to continue to include CWIP in the net PP&E
allocator.......................................................................................................... paragraph 570
30. The Commission accepts AET’s explanation for the increase in fringe benefits given the
inflationary pressures on the specific cost items of CPP and employee benefit premiums.
With respect to the other employee benefits identified, however, it is not clear to the
Commission how a proposed increase of $0.7 million per year is justified, given that
FTEs are declining. For these reasons, the Commission approves a marginal increase of
$0.1 million and AET is directed to reduce its forecast spending on fringe and benefit
costs by $0.6 million for each of the test years and to reflect this reduction in its
compliance filing to this decision. ................................................................. paragraph 583
31. The Commission finds that the CCA’s proposed reduction for the general-other cost
category is excessive. The Commission, however, agrees with the CCA’s comments that
AET failed to justify or explain its proposed increases and some reduction is warranted.
As such, AET is directed to reduce its forecast general-other expenses by $0.4 million for
each of the test years and to reflect this reduction in its compliance filing. Bema
calculated the historical annual average cost for general-other expenses from 2013 to
2016 to be $0.4 million, and the Commission accepts that this calculation shows that
historical trend of $0.4 million per year provides a more reasonable forecast for general-
other expenses in the test years. ..................................................................... paragraph 584
32. The Commission accepts AET’s submission that its forecast expenses for this account
reflect fewer users and increased IT application expenses due to the move to a cloud-
based Oracle E-Business IT solution. However, the Commission directs AET to adjust its
forecast expenses for this account based on the Commission’s reduction in forecast FTEs
found elsewhere in this decision. ................................................................... paragraph 594
33. Further, on June 5, 2019, the Commission issued Decision 20514-D02-2019 in the ATCO
Utilities IT common matters proceeding. With respect to USA 934, AET is directed to
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 186
reflect any changes arising from the directions in that decision in its compliance filing to
this decision. AET is further directed to provide schedules detailing how the
determinations in Decision 20514-D02-2019 are reflected in the compliance filing to this
decision. ......................................................................................................... paragraph 595
34. The Commission is not convinced that the unique circumstances of Alberta PowerLine
require an adjustment to the allocation formula which has been consistently used in
AET’s GTAs. The use of the second year audited data in the allocation formula promotes
consistency, data reliability and avoids forecasting error. For these reasons, the
Commission directs that head office cost allocations continue to be calculated based on
the actual, audited financial data of the second year preceding the first test year of the
GTA. .............................................................................................................. paragraph 616
35. With respect to the second question, the development of a proxy for direct labour, the
Commission considers that some amount should be attributed to Alberta PowerLine. The
Commission considers it unreasonable that Alberta PowerLine should be able to avoid an
allocation of costs based on this factor solely because its labour billings from AET are
recorded as contractor costs. Alberta PowerLine clearly requires labour and that labour is
being supplied by AET. AET is therefore directed to propose, in its compliance filing, a
proxy for labour, including its rationale and calculations, that will be used in the head
office cost allocation calculation to account for Alberta PowerLine. ............ paragraph 617
36. In considering the evidence on the record with respect to the lease rate to be allowed for
the test period, the Commission concurs with the CCA that allowing a lease rate of
$20.00 per sq. ft. for both test years is reasonable. The Commission also considers that an
operating cost allowance of $16.00 per sq. ft. for 2018 is reasonable with an allowance of
$16.50 per sq. ft. for the 2019 test year. The $16.00 per sq. ft. approved for 2018 allows
for a reasonable inflationary increase over what AET states is the current estimate at
ATCO Centre of $15.27 per sq. ft. The $16.50 per sq. ft. approved for 2019 allows for an
inflationary increase over 2018. AET is directed to use these amounts in its compliance
filing for purposes of determining its revenue requirement. .......................... paragraph 668
37. For purposes of determining lease rates, AET is directed to provide, in its compliance
filing, evidence with respect to escalation rates that might be present in 10 year leases at
the time the ATCO Ltd. lease was signed in August 2017, and the Commission will
consider whether the approval of an escalator is warranted. The Commission’s
determinations with respect to the operating cost portion of the rental costs apply only to
the current test period..................................................................................... paragraph 669
38. Therefore, to adjust the number of employees used in the allocation of corporate staff,
and to ensure AET's regulated customers are not charged for the capacity of 100 staff
identified above, AET is directed to compute the square footage in its allocation of
corporate rent for ATCO Park on the basis of (260/600) x 21 per cent. The numerator is
the sum of head office employees and shared services employees identified in
Undertaking 52, adjusted for the seven per cent vacancy factor. The denominator of 600
is the total employee capacity of ATCO Park. The use of the total employee capacity as
the denominator will ensure that AET is not charged for the excess capacity that exists at
ATCO Park and would otherwise be charged if the actual occupancy of 459 were used.
........................................................................................................................ paragraph 680
39. The above adjustment corrects the charges to USA 930.2 for AET’s portion of corporate
head office lease costs. The Commission also notes that a similar adjustment should be
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 187
made to USA 931.1 to correct the charges to AET for the 21 direct AET employees, plus
the adjustment for the seven per cent building vacancy rate, in ATCO Park. AET is
directed to make this adjustment in its compliance filing. ............................. paragraph 681
40. The Commission notes that IR response AET-CCA-2018OCT05-013(e) indicates that
AET is also charged for space occupied by corporate staff at other locations. In its
compliance filing, AET is directed to provide the calculations supporting these charges to
enable the Commission to verify that charges for corporate staff at other locations are
reasonable. ..................................................................................................... paragraph 682
41. Separate and apart from head office rental costs, the lease costs for the amount charged in
USA 931.1, for AET employees directly occupying corporate office space, are forecast to
be $1.5 million in each of the test years. While AET has identified that $1.4 million of
this is payable to Canadian Utilities Limited no breakdown has been provided as to the
facilities rented or how the forecast rent expense has been calculated. To ensure that the
Commission has a thorough understanding of how the forecast has been determined, AET
is directed in its compliance filing to identify the facilities leased and to provide the
calculations showing how the forecast of $1.5 million has been derived, and the
Commission will test these costs further in the compliance filing. ............... paragraph 683
42. There were no objections by interveners to AET’s forecast or its request to settle the RID
on an annual basis. The Commission notes the extended period required to process this
application and the availability of actual amounts for RID claims for the 2015-2017
period. The Commission has reviewed the RID claims included in attachments 29.2.1 to
29.2.3 to AET’s revised application, and finds the amounts to be reasonable. The
Commission accepts and approves AET’s forecast amounts of uninsured losses, with the
exception of those costs in respect of the Fort McMurray wildfire as noted in paragraph 3
of this decision. The Commission accepts AET’s proposal to settle the RID account
annually on a go-forward basis. AET is directed to reflect these changes in its compliance
filing to this application. ................................................................................ paragraph 688
43. For these reasons, the Commission considers that the debt rate deferral account should
continue to be used, but in this case, only for the 2019 test year. For 2018, the
Commission directs that the actual cost of debt be used. The amount to be recorded in the
2019 deferral account is to be determined by updating the approved “Schedule of Debt
Capital Employed and Embedded Cost” (Schedule 28-2) for 2019 to reflect the actual
weighted debenture rate for 2018; and updating the same schedule for 2019 to reflect the
actual weighted debenture rates for each of 2018 and 2019. The resulting embedded cost
of debt for the applicable year will then be used to update the “Schedule of Capital
Structure and Average Cost of Capital” (Schedule 28-1) for that year. This will result in
an updated return on long-term debt for that year. The difference between the updated
return on debt and the approved return on debt for that year will be the resulting balance
in the debenture rate deferral account for that year. ...................................... paragraph 734
44. Given the approval for the continued use of the debt rate deferral account for 2019, the
Commission needs to determine a reasonable forecast for the cost of debt to be used for
the second test year. As the actual cost of debt and the issue amount for AET’s 2018 debt
issuance is known, the Commission directs AET, in the compliance filing, to update its
application in all aspects to reflect the 2018 actual cost of debt resulting from the actual
2018 long-term debt issues. ........................................................................... paragraph 735
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 188
45. While not in agreement with the CCA's proposed debt rate, the Commission finds AET's
forecast debt rate of 4.43 per cent to be high, particularly in light of its recent bond tender
at 3.95 per cent. The Commission directs AET to use 3.95 per cent as a forecast rate for
2019 long-term debt, especially since this forecast 2019 debt rate will be afforded
deferral account treatment. The Commission, therefore, approves a forecast 2019 debt
rate of 3.95 per cent and directs AET, in its compliance filing, to update its application in
all aspects to reflect the forecast long-term debt cost rates of 3.95 per cent for 2018 and
2019. .............................................................................................................. paragraph 737
46. The Commission finds AET’s proposal to incorporate the Alberta PowerLine forecast
update as part of the GTA compliance filing to be reasonable. The Commission directs
AET to reflect all impacts related to the Alberta PowerLine forecast update in the GTA
compliance filing arising from the determinations in this decision. The Commission
understands that this update will include charges based upon the new 23 per cent
overhead rate. In light of the Commission findings below regarding overhead rates, AET
is directed to treat these updates as placeholders and to submit forecasts of Alberta
PowerLine’s affiliate services with the historical overhead rate of 30 per cent for O&M
and 60 per cent for construction projects in its compliance filing to this decision.
........................................................................................................................ paragraph 756
47. For this reason, the Commission directs AET to provide the following information as part
of all future GTAs where there is a variance of $0.5 million or more between forecast and
actual affiliate revenues, for any affiliate receiving services from AET:
(a) The forecast, actual and variance amounts for affiliate revenues, broken down by:
(i) AET internal labour
(ii) Fringe benefits on internal labour
(iii) Overhead loading on AET labour-related costs
(iv) Flow-through costs
(b) For the variance in AET internal labour taken from part (a) above, identify each
group that contributed to the internal labour variance, whether the variance amount
was for O&M or capital-related activities, and, for each variance amount, the dollar
amount and number of FTEs involved.
(c) For each group identified in part (b) above, confirm whether the work related to the
observed variance was backfilled, and provide an explanation of how and when this
was done. ...............................................................................................paragraph 760
48. For this reason, the Commission directs AET, as part of its compliance filing, to provide
the following information:
(a) An expanded affiliate overhead schedule which adds columns to the current
information shown on the Transmission Overhead Rate schedule for each of the
2017 forecast, 2018 actuals, and 2018 and 2019 forecasts taken from the original
GTA application in this proceeding to facilitate comparison.
(b) A schedule that provides a detailed analysis of the affiliate overhead recovery
which compares the increased direct charging and the lower affiliate overhead rate
compared to the use of the previous overhead recovery rate. This comparison shall
identify individually each of the groups involved, and list each of the services that
each group is providing. ........................................................................paragraph 768
2018-2019 Transmission General Tariff Application ATCO Electric Ltd.
Decision 22742-D01-2019 (July 4, 2019) 189
49. The Commission directs AET to provide an updated accounting policy for provision of
services to or receipt of services from affiliates that reflects the outcome of the
Commission’s decision on overhead rates in its compliance filing to this decision.
........................................................................................................................ paragraph 770
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
09:33
11:17
218
THE CHAIR: Sorry?
MR. WACHOWICH: Baseball start time was always
five minutes --
THE CHAIR: That's right. Good point.
MS. SABO: My apologies. Just one
announcement. Our staff is working on the webcast
issue. Our internet is down, and our Calgary office is
trying to reconcile that.
We hope it's back up, but if anyone has any
further issues, just let us know at baseball time
10:05.
THE CHAIR: Thanks, Ms. Sabo. We'll see
everybody in 30 minutes.
(ADJOURNMENT)
THE CHAIR: Our apologies for the delay. It
took a little longer than we had hoped or anticipated
to complete our ruling. Unless there are any
preliminary matters to be dealt with prior to our
ruling, I think I'll just proceed with reading into the
record our ruling on the dispute between the parties as
to the admissibility of CCA's first two aids to
cross-examination as exhibits. That's the issue,
whether they should be admitted as exhibits.
Here with the ruling. Yesterday the CCA requested
that three aids to cross-examination be added as
ATCO Electric Ltd.Appendix 6 - Transcript, Volume 2, 2019-01-22 - Ruling on CCA request to mark two exhibits
Page 1 of 7
Decision 22742-D01-2019 (July 4, 2019)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
11:19
11:19
219
exhibits on the record of this proceeding. The first
two of these aids to cross-examination are at issue
here. They are articles found on the internet relating
to variable pay. The first is titled "Make Way for
Variable Pay," and the second is titled "Employers
Offer Variable Pay and Benefits to Retain Employees."
ATCO Electric opposed the CCA's request for
several reasons and provided a January 29th, 2010,
ruling in Proceeding 226 for the ATCO Utilities pension
common matters application as support for its position.
ATCO submitted that the 2010 ruling demonstrated
that an aid to cross-examination put to a witness does
not become evidence to be marked on the record.
Rather, only witness responses to the aid to
cross-examination are evidence.
In response to ATCO Electric's objection to the
two aids to cross-examination, the CCA requested that
it be provided the opportunity to submit other rulings
that address the use of aids to cross-examination.
This morning the CCA has provided excerpts from
two transcripts: The first from Proceeding 22542,
AltaLink 2014-2015 DACDA proceeding, Volume 1,
September 13th, 2018, pages 181 to 184; the second from
Proceeding 22570, the 2018 GCOC proceeding, Volume 1,
March 12, 2018, pages 61 to 76.
ATCO Electric Ltd.Appendix 6 - Transcript, Volume 2, 2019-01-22 - Ruling on CCA request to mark two exhibits
Page 2 of 7
Decision 22742-D01-2019 (July 4, 2019)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
11:21
11:22
220
ATCO Electric also has provided the Panel with two
rulings, the first from the 2018 GCOC decision, being
Decision 22570-D01-2018, issued August 2, 2018, and the
second from Proceeding 22570, the 2018 GCOC proceeding,
Volume 1. And I think that's the Transcript Volume 1,
March 12, 2018, pages 101 to 104.
The test of admissibility of an aid to
cross-examination was adopted by the Commission in its
January 29th, 2010, proceeding -- sorry, was adopted by
the Commission on January 29th, 2010, in Proceeding 226
and can be summarized as follows.
An aid to cross-examination is a document that a
party may use or refer to while questioning a witness
about their evidence. An aid to cross-examination is
most effective if the witness being questioned has
contributed to its preparation, is familiar with its
contents, or can quickly verify the accuracy of the
contents.
Unless an aid to cross-examination is drawn
directly from the witness's direct evidence or
testimony, or prepared by that witness in another
context, or provides updated or supplementary
information to the witness's evidence, it is unfair to
require the witness to verify a substantial portion or
the entirety of the information contained in the aid.
ATCO Electric Ltd.Appendix 6 - Transcript, Volume 2, 2019-01-22 - Ruling on CCA request to mark two exhibits
Page 3 of 7
Decision 22742-D01-2019 (July 4, 2019)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
11:23
11:24
221
This test of admissibility is not intended to
exclude from consideration every potential aid to
cross-examination that does not fall squarely within
its four corners. For example, there's a difference
between being asked to, quote, "verify" close quote,
the content of an aid and being asked to comment on
that content or to adopt that content in whole or in
part as aligning with the witness's own views,
et cetera.
In addition, the Commission, being the master of
its own process, always retains the discretion to
include or exclude from the record of any proceeding
any disputed aid to cross-examination. As stated by
Sopinka, J, writing for the majority in Prassad v.
Canada (Minister of Employment and Immigration), held
as follows -- and I believe this is from paragraph 16
of the decision: (as read)
"We are dealing here with the powers of
an administrative tribunal in relation
to its procedures. As a general rule,
these tribunals are considered to be
masters in their own house. In the
absence of specific rules laid down by
statute or regulation, they control
their own procedures subject to the
ATCO Electric Ltd.Appendix 6 - Transcript, Volume 2, 2019-01-22 - Ruling on CCA request to mark two exhibits
Page 4 of 7
Decision 22742-D01-2019 (July 4, 2019)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
11:25
11:26
222
proviso that they comply with the rules
of fairness and where they exercise
judicial or quasi-judicial functions,
the rules of natural justice."
I'll omit the detailed citation here.
In the Commission's view, the principles governing
the admissibility of an aid to cross-examination are
relevance, probative value, and fairness.
In order for an aid to cross-examination to be
properly accepted on the record, counsel must be able to
demonstrate that: one, the document is relevant to the
matters at hand; two, the document is of probative value
to the decisions before the Commission; and three, the
manner in which the document is put to the witnesses is
fair.
Having said this, however, it is generally
preferable that, wherever possible, questions be put to
the witness or witnesses directly without using an aid
to cross-examination.
The Commission Panel's task here is to exercise its
discretion and evaluate ATCO's objections to the
disputed aids to cross-examination on the basis of their
relevance, probative value, and the fairness with which
they were put to the witnesses.
The Commission is also mindful of the timing issue
ATCO Electric Ltd.Appendix 6 - Transcript, Volume 2, 2019-01-22 - Ruling on CCA request to mark two exhibits
Page 5 of 7
Decision 22742-D01-2019 (July 4, 2019)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
11:27
11:27
223
related to late and extensive rebuttal evidence, which
is not the case in this proceeding, but that
circumstances could lead it to a more permissive
acceptance of aids in the interests of efficiency in
some instances.
The Commission has heard the witness's testimony in
respect of the two disputed aids to cross-examination.
The aids to cross-examination were provided at least 24
hours in advance in accordance with Section 39.1 of the
AUC Rules of Practice, and there was sufficient notice
to ATCO that each aid would be put to the witnesses.
This practice afforded fairness to the witnesses in
reviewing the documents.
The Commission reminds parties of the last passage
of paragraph 861 of the 2018 GCOC decision,
Decision 22570-D01-2018, and I quote: (as read)
"We strongly encourage parties to
revisit their planned use of aids to
cross in light of the guidance provided
and otherwise work amongst themselves
and have all the parties work amongst
themselves in an attempt to resolve some
of these matters."
The Panel notes in this regard that counsel for the CCA
provided ATCO Electric's counsel with sufficient notice
ATCO Electric Ltd.Appendix 6 - Transcript, Volume 2, 2019-01-22 - Ruling on CCA request to mark two exhibits
Page 6 of 7
Decision 22742-D01-2019 (July 4, 2019)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
11:29
11:29
224
for the parties to have identified and potentially
resolved questions regarding the admissibility of the
contested aids. Hearing time is limited and must be
used efficiently in both utility and ratepayer
interests.
With respect to the contested aids themselves, the
Commission observes that none of the witnesses authored
or contributed to the articles. The ATCO witnesses'
response to questions with respect to the first aid to
cross-examination related only very generally to
ATCO Electric's experience with its own VPP program.
With respect to the second document, only a single
paragraph of that document, the fifth paragraph, was
proffered to the witness for comment, and that same
paragraph was read into the record at Transcript
Volume 1, page 90, lines 10 to 20.
As such, the Commission does not consider there to
be probative value with respect to these two documents
beyond the witness testimony already provided on the
record. Therefore, the first two aids to
cross-examination will not be entered into the record as
exhibits.
That concludes this ruling.
MR. WACHOWICH: Thank you, Mr. Chairman.
Sir, the only remaining housekeeping matter I have
ATCO Electric Ltd.Appendix 6 - Transcript, Volume 2, 2019-01-22 - Ruling on CCA request to mark two exhibits
Page 7 of 7
Decision 22742-D01-2019 (July 4, 2019)