1
Asbestos Management
2020 EIC Training
2
Asbestos Management
Trainer
Jonathan Bass, Environmental Specialist
Office of Construction
3
Standard Specifications Section 210
Removal and Disposal of Asbestos-Containing Materials (Buildings, Bridges & Highways)
✓ Buildings – Thermal Insulations, Siding, Roofing, Caulks, Sealers,
Flooring, Plasters, Ceiling Tile, etc.
✓ Bridges/Culverts – Bond Breakers, Joint Fillers, Caulks, Suspended
& Encased Utilities, Steel Coatings, Masonry Coatings, etc.
✓ Highways – Buried Utilties, Sidewalk Joint Filler, etc.
4
Thermal System Insulation
5
Thermal System Pipe Insulation
6
Transite Siding
7
Asbestos Roofing
8
Asbestos Floor Tile & Mastic
9
Asbestos Ceiling Tile
10
BEARING PADS
11
Suspended Transite Pipes
12
Suspended Coated Utility
13
Steel Coating – Up Close
14
Steel Coatings – Outside Bays
15
Masonry Coating
16
Route 30 Mine Kill Masonry Coating Abatement
17
Mazur Furniture – I287 Westchester Masonry Coating
18
Railbed Curbing
19
Railbed Curbing – Close up
20
Defunct Residency – Copper Salvage
21
Sheetpacking
22
Transite Expansion Joint Housing
23
Joint Filler
24
Culvert Coatings
25
NYSDOT Blanket Variance 14
• Statewide Application to Bridges and Highways
• Applies to Non-friable Asbestos-Containing Materials (ACMs) on
Bridges and Highways (no application to buildings).
• Applicable to NYSDOT, Thruway, Canal Corp. and County Highway
Projects (can also be used by private sector or municipal utility
companies working within listed agency, authority or county right-of-
way)
• Cities, Townships and Villages Can Use as Model for Site Specific
Variance Applications
• Requires Renewal by Department Every Three Years
26
Project/Air Monitoring
• Provided through Asbestos Term Agreement Consultant Forces
• Three (3) Zonal Agreements (Upstate East, Upstate West & Downstate)
• Managed by Main Office Consultant Management Bureau
• Acts as EIC Inspection Staff for All Asbestos Abatement Work
• Request for Use Made by Regional Construction Environmental
Coordinator or Regional Environmental Unit
27
Section 210-3 Construction Details
“The Contractor shall schedule a coordination meeting
between the Asbestos Subcontractor and the
Department Contracted Asbestos Project Monitor to be
held at least two (2) weeks before the start of any
asbestos abatement work.”
28
Recordkeeping
• Project Record Documentation is Generated by Both the Asbestos
Abatement Contractor and Project Monitoring Firms
• Following Completion of Asbestos Abatement Work, Copies of All
Asbestos Abatement Documentation is Retained by the Department
for Project Record
• Asbestos Bridge Abatement Project Records are Particularly
Important Because of Future Rehabilitation and Demolition Work
29
Waste Disposal
• All Friable Asbestos Waste Must Be Transported Under a Waste
Shipment Record and Disposed of at a Waste Disposal Facility
Permitted to Accept Friable Asbestos Waste (NYSDEC maintains
a current list of permitted NYS facilities)
• Friable Asbestos Waste Transport Also Requires a NYSDEC
Permitted Hauler
• Non-Friable Asbestos Waste May Be Disposed of at Sites
Approved to Accept Construction & Demolition (C&D) Debris
• Non-Friable Asbestos Waste Does Not Require A Waste
Shipment Record or a NYSDEC Permitted Hauler for Transport.
However, recent Part 360 revision does now require registration
and tracking for C&D
• C&D Disposal Receipts are Required
30
EB 16-048 – Section 210 CIM
II. Procedure (Project Monitor Responsibilities)
1. Reviewing & Approving Asbestos Contractor Pre-Abatement Submittals
2. Maintaining Daily Asbestos Abatement Project Documentation for the EIC
3. Ensuring Regulatory and Contractual Compliance by the Asbestos Contractor
4. Conducting Any Necessary Compliance Air Monitoring & Lab Analysis
5. Conducting Any Necessary Additional Bulk Sampling & Lab Analysis
6. Performing All Final Clearance Inspections (authorizing 75% item payment)
7. Verifying and Documenting All Removal Quantities for the EIC
8. Reviewing & Approving Asbestos Contractor Post-Abatement Submittals
9. Compiling All Asbestos Project Documentation for EIC Into Electronic File
(includes waste disposal documentation and authorizing final 25% item
payment)
31
EB 16-048 – Section 210 CIM
III. Documentation Retention
• Retain All Interim Daily Asbestos Abatement Project Documentation as
Attachments to Corresponding DWRs. Together With Approved Pre-
Abatement Submittals, This Represents the Project Record.
• Final Electronic Asbestos Abatement Close-Out File(s) Received From
the Project Monitor Shall be Retained for Long-Term Storage on
Corresponding Project-Wise Folders. Construction Environmental
Coordinator (CEC) Responsibility.
32
33
34
35
I81 State Street Demo
36
I81 State Street Demo
37
Region 7 Masonry Coating Abatement
38
Region 7 Masonry Coating Abatement
39
Region 9 Route 17 Steel Coating Abatement
40
Masonry Coating Shrouded Tool Abatement
41
Steel Coating Shrouded Tool Abatement
42
More Steel Coating Shrouded Tool Abatement
43
Cross Westchester Transite Pipe Abatement
44
Cross Westchester Transite Pipe Abatement
45
Cross Westchester Transite Pipe Abatement
46
North-South Arterial
Controlled Demolition
47
North South Arterial Controlled Demolition
48
North South Arterial Controlled Demolition
49
Questions???
50
Poll Question #1
NYSDOT Blanket Variance 14 is not applicable to
Asbestos Abatement for which Government Entity(s)?
1. NYSDOT
2. NYS Thruway
3. NYS Canal Corp.
4. County Highways
5. City, Town & Villages
51
#1 Answer
5. City, Town & Villages
* Mention NYC Asbestos Regulations & NYSDOT Applicability (Region 11 and NYC Watershed)
52
Poll Question #2
According to Standard Specification 210, the Contractor
is responsible for coordinating an asbestos abatement
start-up meeting between the Asbestos sub-contractor
and the Department Project Monitor a minimum of how
many weeks prior to the start of abatement work?
1. One
2. Two
3. Three
4. Four
53
#2 Answer
2. Two Weeks
54
Poll Question #3
Non-Friable Asbestos Waste Transport and Disposal
Requires NYSDEC Permitted Haulers and Waste
Shipment Records.
TRUE OR FALSE?
55
#3 Answer
FALSE
56
Poll Question #4
The Department-Contracted Asbestos Project Monitor
Acts as Separate Inspection Staff for the EIC and is
Responsible for the Following:
1. Pre-abatement Submittal Review & Approval
2. Regulatory and Contractual Compliance by the
Asbestos Abatement Sub-contractor
3. Verification/Documentation of All Removed Asbestos
Material Quantities
4. Final Asbestos Close-out Reporting
5. All of the Above
57
#4 Answer
5. All of the Above
58
Poll Question #5
Long Term Retention of Asbestos Abatement
Documentation in Project Wise is the Responsibility of
Who?
1. EIC
2. Project Monitor
3. Asbestos Abatement Sub-contractor
4. Construction Environmental Coordinator (CEC)
5. None of the Above
59
#5 Answer
4. Construction Environmental Coordinator