Upload
catherine-weaver
View
213
Download
0
Tags:
Embed Size (px)
Citation preview
APS/SRP 2nd Quarter Stakeholder Meeting for Transmission Planning
FERC Order 890 SRP Attachment K APS Attachment E
APS Deer Valley FacilityPhoenix, ArizonaJune 18, 20159 AM -12 PM
Agenda
1. Welcome, Introductions, and Stakeholder Meeting Overview
2. Status of Action Items - 12/18/2014 Joint APS/SRP 4th Quarter Public Planning Meeting
3. Purpose of Today’s meeting – APS Planning
4. Purpose of Today’s meeting – SRP Planning 5. Stakeholder Questions/Comments
6. Action Items
2
2. Status of Action Items
• There were no action items captured at the 4th Quarter Stakeholder meeting held on 12/18/2014
3
3. Purpose of Today’s meeting
• Per APS’s OATT, APS conducts the 2nd quarter public planning meeting to– A) review its current transmission study plan– B) provide an opportunity for transmission customers to
update their loads, resources and other data that were submitted by September 1, 2014
– C) provide an opportunity for stakeholder input on any aspect of the study plan
– D) review any stakeholder proposals previously submitted to APS for study plan alternatives
– E) invite submittal of additional stakeholder study plan proposals for review and discussion
– F) provide updates on APS’s planned transmission projects
4
3.A. APS’s Study Plan
• APS has two distinct, but related, transmission study processes– NERC Compliance– APS’s Annual Planning
• The difference between the two plans:– NERC Compliance:
• Minimum 2 seasons, 2 discrete years (near and long term); all cases examine P0-P7 (formerly Category A – D)
– APS’s annual planning: 1 season, 10 consecutive years; N-0 and N-1
– Annual plan is used as starting point for NERC Compliance
• Working on combining TPL assessment and Annual Planning for future years
5
3.A. 2014 NERC Compliance StudiesPeak Load Assessment – Summer
NERC STANDARD STUDIES PERFORMED
TPL -001(n-0) Thermal Transient Stability Post Transient
2019 PEAK X
2019 MLSC X
2024 PEAK X
2024 MLSC X
TPL-002 (n-1)
2019 PEAK (Lines, xfmrs, gens) X X X
2019 MLSC (Lines, xfmrs, gens) X X
2024 PEAK (Lines, xfmrs, gens) X X X
2024 MLSC (Lines, xfmrs, gens) X X
TPL-003 (n-2)
2019 Stuck Breaker/Breaker Failure X X X
2019 N-1-1 X X X
2019 Bus Section X X X
2024 Stuck Breaker/Breaker Failure X X X
2024 N-1-1 X X X
2024 Bus Section X X X
TPL-004 (n-xx)
2019 Major Substations With/Without Generation X X X
2019 Stuck Breaker/Breaker Failure X X X
2019 Common Corridor X X X
2024 Major Substations With/Without Generation X X X
2024 Stuck Breaker/Breaker Failure X X X
2024 Common Corridor X X X
6
3.A. 2014 NERC Compliance StudiesLow Load Assessment
NERC STANDARD STUDIES PERFORMED
TPL -001(n-0) Thermal Transient Stability Post Transient
Near-Term TO BE DETERMINED X
Long-Term TO BE DETERMINED X
TPL-002 (n-1) Near-Term TRANSMISSION LINE X X XNear-Term XFMR X X XNear-Term GENERATION X X XNear-Term REACTORS X XLong-Term TRANSMISSION LINE X X XLong-Term XFMR X X XLong-Term GENERATION X X XLong-Term REACTORS X X
TPL-003 (n-2) Near-Term Stuck Breaker X X XNear-Term N-1-1 X X XLong-Term Stuck Breaker X X XLong-Term N-1-1 X X X
TPL-004 (n-xx) Near-Term Loss of All Generation Units at a Station X X XNear-Term Common Corridor X X XLong-Term Loss of All Generation Units at a Station X X XLong-Term Common Corridor X X X
7
3.A. NERC Compliance Results?
• 2014 Results?– APS is fully compliant with NERC Transmission
Planning Standards
• 2015 Progress?– Case building complete– DYD files being finalized– Perform study work starting in July/August
8
3.A. 2015 NERC Compliance Study Methodology
NERC Compliance Studies Cases• 2016, 2020 & 2024 Summer Peak Cases• Off-peak Case is Low Load and High Import (shoulder case with
low generation in the Phoenix Metro Area)– 2017 Light Spring case; one case in the near-term– High ratio of renewable generation to overall generation on-line
• Following analyses are conducted:– Thermal– Post-Transient– Short-Circuit– Transient Stability
9
3.A. 2015 NERC Compliance Studies
• TPL-001-4 combined previous TPL-001 through TPL-004– No longer Category A, B, C, & D– Now P0 through P7
• Covers all scenarios from N-0 to N-1-1• Also includes Multiple Contingencies due to relay or
breaker failures
– Requires more cases/scenarios– Includes short-circuit analysis
10
3.A. APS TPL Plan for 2015 Study
Near-Term Long-TermYear 1
(2016)2
(2017)3 4 5
(2020)6 7 8 9
(2024)10
Steady State
Peak Load (Summer) X X X
Peak load sensitivity X X
Off-Peak (Spring) X
Off-Peak sensitivity X
Stability
Peak Load (Summer) X ?
Peak load sensitivity X
Off-Peak (Spring) X
Off-Peak sensitivity X
11
3.A. 2016-2025 Ten-Year Plan Methodology
• Coordinated Base Cases– 2015HS – SASG/AZ coordinated case used to build heavy
summer 2016-2019– 2020HS – AZ coordinated case used to build heavy summer
2021-2023– 2024HS – SWAT/AZ coordinated case used to build heavy
summer 2025 (same SWAT updated case submitted to WestConnect)
– The intermediate cases are APS/SRP coordinated
• 69kV transmission models incorporated• Most up-to-date forecasts for peak summer loads• N-0 and N-1 analysis conducted for all ten years
12
Note: AZ coordinated cases also included IID
3.A. 2016-2025 Ten-Year Plan Status
• AZ Seed cases are complete (2016HS, 2020HS, 2024HS)
• Intermediate cases are in development• Ten-Year plan studies will be performed in the
summer/fall• Draft results typically available during 4th
Quarter Stakeholder meeting• Ten-Year Plan filed by the end of January• BTA Studies will also be completed and filed
– 10th Year Snapshot & Extreme Contingency– RMR study needs are being evaluated
13
3.B. Customer Load/Resource Updates
• APS has all load/resource data from Network Customers and has incorporated them into the base cases
• Should you like to provide information for the future APS planning cycles, please see critical dates on the next slide
14
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
10yr Plan – Filed with ACC by Jan. 31 10yr. Plans filed by others
APS Corporate Load Forecast
Stakeholder Input
APS Corporate Load Forecast – Post Summer
Sep. 1st – Network Transmission Customers and all other Transmission Customers Load & Resource Forecast
10yr Plan – New load forecast sensitivity
Develop 10yr base cases from AZ seed cases
10yr Plan study effort – Determination of projects, timings, and scope
4th Quarter Stakeholder Meeting – Review draft of current 10yr plan, discuss Economic Study requests, receive
stakeholder input
Planning Calendar for Ten-Year Planning CycleAPS Transmission
Planning – 10 Yr Plan
Arizona Utilities coordinated seed case development
2nd Quarter Stakeholder Meeting – Stakeholder input on studies, request study
alternatives, updates on current projects
Other Coordination Activities Throughout
the Year
· APS/SRP Coordination Meeting
· APS/WAPA Coordination Meeting
· WestConnect Meetings
· SWAT Meetingso AZTSo New Mexicoo Eldorado Valleyo Transmission Corridoro Short-circuit
Oct. 31st – Deadline to submit Economic Study Requests for 4th Quarter Meeting
review
15
3.B. Feedback on the Plan?
• Feedback on the Plan or methodologies– NERC Reliability– Ten Year Plan
• See next slide to see how APS would evaluate plan submittals or alternatives.
16
What Type of Study?1
Does Transmission Provider’s system
meetNERC/WECC
criteria?
No
Does Transmission Provider’s system meet local reliability criteria?
Yes
Transmission Provider determines facilities
needed with Stakeholder input
No
Transmission Provider coordinates with Sub-
Regional Planning Group
Yes
Economic Reliability
Transmission Provider
Evaluation
Regional
TEPPC evaluates with Stakeholder
input
Transmission Provider Economic
Study
Customer Choice of Study at Customer’s
expense
Local2
TEPPC determines high priority, performs
study
High priority
Not high priority
TEPPC determines not
high priority
Study results documented in a report and reviewed
by Customer and Transmission Provider
Transmission Provider determines facilities
needed with Stakeholder input
1. Generator Interconnection Request studies are performed pursuant to the Large Generator Interconnection Procedure contained in the Transmission Provider’s Open Access Transmission Tariff (OATT). Transmission Service Requests are also performed pursuant to OATT procedures.
2. All requests for economic planning studies received by the Transmission Provider are forwarded to TEPPC for inclusion in the TEPPC Master List . TEPPC will evaluate only those requests that have regional impacts.
Transmission Planning Process
Exhibit 1 – APS Attachment E
17
3.B. Review Stakeholder proposals previously submitted
• APS received no stakeholder proposals in 2014 or prior to this meeting.
18
3.B. Submittal of additional study plan proposals
• If you have study ideas for APS to consider, please send a detailed message to: [email protected]
• Please include (at a minimum)– Your Name/Company/contact info (e-mail/phone #)– What the purpose of the study request is? And how will
the results be used?• E.g. Determine how much load the system can accommodate without
new generation/transmission? Results will be used to inform developers where there may be opportunities for additional commercial development without transmission/generation investment.
– What year(s) and season(s) is of interest?– What type of study – reliability (power flow only?)
economic?
19
3.B. APS Ten-Year Plan Projects 2015-2024
Transmission PlanFiled on Jan. 30, 2015
20
3.B. Changes since 2015 Plan was filed
• Two projects completed– Hassayampa-North Gila #2 500kV line
• Energized May, 2015• New Path 49 (EOR) rating of 10,100 MW
– Palm Valley-Trilby Wash 230kV line• Energized April, 2015• Trilby Wash now providing new source for northwestern part of valley
• Actively under construction– Palo Verde-Delaney-Sun Valley 500kV– Sun Valley-Trilby Wash 230kV– Bagdad 115kV Relocation
21
In-Service: Hassayampa-North Gila 500kV #2
Line2016: Delaney-Palo Verde 500kV Line Delaney-Sun Valley 500kV Line2017: Bagdad 115kV Line Relocation Mazatzal 345/69kV Substation2018: Morgan-Sun Valley 500kV Line Ocotillo Modernization Project
22
23
In-service: Palm Valley-Trilby
Wash 230kV Line2016: Sun Valley-Trilby Wash
230kV Line2018: Ocotillo Modernization
Project2026: Morgan-Sun Valley
230kV Line
24
In-service: Hassayampa-North Gila
500kV #2 Line2018: North Gila-Orchard
230kV Line
Bulk Transformer Additions/Replacements
Description Year
Two 100MVAR Reactors at Four Corners 230kV 2015/2016
Trilby Wash 230/69kV Transformer (in-service) 2015
Sun Valley 500/230kV Transformer 2016
Mazatzal 345/69kV Transformer 2017
Prescott 230/115kV Transformer #3 2017
North Gila 500/230kV Transformer 2018
Orchard 230/69kV Transformer 2018
Orchard 230/69kV Transformer #2 2018
Saguaro 230/69kV Transformer 2021
25
APS Planning - Study Requests
• Generation Interconnection Requests• Transmission Interconnection Requests• Transmission Service Requests• Economic Study Requests
26
3.C. Generation Interconnections
• Active Generation Interconnection requests– APS OASIS contains Generation Interconnection
Queue• http://www.oatioasis.com/azps/index.html• 2 Solar projects - 220 MW• 1 Wind projects - 1000 MW• 1 Wind/Solar project – 101 MW wind/60 MW solar• 3 Natural Gas projects – 2429 MW
Note: Generator Queue information as of 4/23/15
27
A - HAA-NG 500kV line 1 projects 200 MWB - Gila Bend/Buckeye 2 projects 654 MWC – Metro Phx 1 projects 595 MWD - FC 1 projects 1200 MWE - Northern AZ 2 projects 1161 MW
Note 1: Generator Queue information as of 4/23/15Note 2: Figures displayed may not represent complete queue
A B
C
E
D
28
3.D. Transmission Service Requests
• 1 Wires to Wires Interconnection Requests
• 42 Transmission Service Requests
29
3.E. Economic Study Requests
• Currently no Economic Study Requests
30
3.F. APS Planning – Comments & Questions
• Stakeholder comments/questions on 2014 Study Results or 2015 Study Requests
• Requests can be made at any time to:– [email protected]
31
4. Purpose of Today’s Meeting
• Per SRP’s OATT, SRP conducts the 2nd quarter public planning meeting to:A) Review its current transmission study plan
– provide an opportunity for transmission customers to update their loads, resources and other data – review any stakeholder proposals previously submitted to
SRP for study plan alternativesB) Provide updates on SRP’s transmission projects (Ten Year Plan) C) Provide updates on the generation study requestsD) Provide updates on the transmission study requestsE) Provide updates on the economic study requestsF) Invite stakeholders to submit additional study proposals
3212/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.A. – SRP’s Study Plan
• SRP has two distinct, but related, transmission study plans– NERC Compliance– SRP’s budgetary planning
• The difference between the two plans:– NERC Compliance: 3 seasons/scenarios, 2 discrete years (near
and long term)– SRP’s annual planning: 1 season, 10 consecutive years (first 6
years are for budget, remaining 4 for compliance purposes)
• The similarities between the two plans:– Similar load forecasts, demand response– They are reliability studies
3312/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.A. 2015 NERC Compliance Study Methodology
• Coordinated Base Cases (Seed Cases)– 2016 – AZ coordinated case used to build 2016-2019– 2020 – AZ coordinated case used to build 2020-2024– 2024 – AZ coordinated case used to build 2025– The intermediate cases are APS/SRP coordinated– SRP NERC Compliance cases– 2017 and 2021
• 69kV transmission models incorporated• Most up-to-date forecasts for peak summer loads
3412/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.A. 2015 NERC Compliance Study Methodology
NERC Compliance Studies Cases• 2017 & 2021 Summer Peak & Off-peak Cases• 2017 & 2021 Off-peak Cases are Low Load (spring/winter
conditions) and High Import (shoulder cases with low generation in the Phoenix Metro Area)
• Following analyses are conducted:– Thermal analysis– Post-Transient– Transient Stability
3512/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.A. NERC Compliance Studies
NERC STANDARD Type of Studies Completed
TPL-001 (N-0) Thermal Transient Stability Post-transient
2017 Peak X
2017 Low Load X
2017 High Import X
2021 Peak X
2021 Low Load X
2021 High Import X
TPL-002 (N-1) Thermal Transient Stability Post-transient
2017 Peak X X X
2017 Low Load X X X
2017 High Import X X X
2021 Peak X X X
2021 Low Load X X X
2021 High Import X X X
3612/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.A. NERC Compliance StudiesNERC STANDARD Type of Studies Completed
TPL-003 (N-2) Thermal Transient Stability Post-transient
2017 Bus outages X X X
2017 Contingency of towers X X X
2017 Stuck breaker & protection system failure (SLG fault) X X X
2017 Common Corridor X X X
2017 N-1-1 X X X
2021 Bus outages X X X
2021 Contingency of towers X X X
2021 Stuck breaker & protection system failure (SLG fault) X X X
2021 Common Corridor X X X
2021 N-1-1 X X X
TPL-004 (N-X) Thermal Transient Stability Post-transient
2017 Substations with generation X X
2017 Common Corridor/Substation without generation X X
2017 Stuck breaker & protection system failure (3PHG fault) X X
Note: TPL-003 Studies performed on Peak, Low Load & High Import cases
3712/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.A. NERC Compliance Results
• 2014 Results– 2014 NERC Compliance Studies were finalized by beginning
of November of 2014
• 2015 Progress– Case building under way– TPL-001-4 effective 1/1/2016– SRP will perform the studies for TPL-001-4 in order to
compliant after 1/1/2016– Besides nomenclature differences, major addition is
requirement for short circuit studies
3812/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.A.– Stakeholder Proposals
• SRP received no stakeholder proposals in 2014 or prior to this meeting
4.A. – Customer Load/Resource Updates
• No customers provided load/resource data in September 2014
• SRP received no stakeholder proposals in 2014 or prior to this meeting.
• If you like to provide information for the future SRP planning cycles, please see critical dates on the next slide
4012/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4112/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.B. SRP Ten Year Plan 2015-2024
• SRP has Filed its Ten Year Plan as of January 30, 2015
4212/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.B. 2016-2025 Ten Year Plan Methodology
• Coordinated Base Cases
– See NERC Compliance Methodology slide #6
• 69kV transmission models incorporated
• Most up-to-date forecasts for peak summer loads
• TPL-001 & TPL-002 Studies Conducted for all ten years
4312/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
EXISTING LINES
FUTURE LINESFUTURE 500kV SUBSTATION
EXISTING 500kV SUBSTATION
NEVADA
WESTWING
KYRENE
SILVERKING
CORONADO
CHOLLA(APS)
MEADMcCULLOUGH
MARKETPLACE
BROWNING
HASSAYAMPA
RUDDPALO VERDE
PINAL WEST
JOJOBA
DUKE
NAVAJO GS
SUGARLOAF
MOENKOPI(APS)
YAVAPAI(APS)
PINNACLE PEAK (APS)
PINALCENTRAL
SUNZIA (SWPG)
2018
CentralNew Mexico
SPRINGERVILLE(TEP)
DUGAS(APS)
500kV System
345kV
MORGAN(APS)
2015-2024
CEDAR MT(APS)
2016
ELDORADO
MOHAVE
230kV
PERKINS
All Changes since January 2014 Ten Year Plan shown in red
2024
4412/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
Price Road Corridor Project
BRANDOW
WARD
CORBELL
ALEXANDER
WESTWING
KYRENEANDERSON
WHITETANKS
ORME
SRPPINNACLE PEAK
PAPAGO
LIBERTY(W.A.P.A.)
AGUAFRIA
DEERVALLEY
(APS)
ROGERS
TO APSOCOTILLO
TOAPS
PINNACLE PEAK
TOW.A.P.A.
PINNACLE PEAK
W.A.P.A.
W.A.P.A.
W.A.P.A.
KNOX
SCHRADER
RUDD
230kV System
SANTAN
THUNDERSTONE
BROWNING
EXISTING 230kV SUBSTATIONS
FUTURE 230kV CIRCUIT
EXISTING 230kV CIRCUIT
FUTURE 230kV SUBSTATIONS
GENERATING STATION
DOUBLE CIRCUIT, PHASE TIED LINE
GOLDFIELD
ABEL
DINOSAUR
2021
DESERTBASIN
PINALCENTRAL
RANDOLPH
2021PFISTER
TBD
2015-2024
ToSilver King
RS-28(2017)
2017
TBD
RS-27(TBD)
TO SANTAROSA(APS)
TO CASAGRANDE
(APS)
All Changes since January 2014 Ten Year Plan shown in red 4512/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
115kV
MIAMI
PINAL
SUPERIOR
SPURLOCK
MOONSHINE
ELLISON
FRAZIER
RAYMORRIS
KEARNY
HAYDEN
STEWARTMOUNTAIN
MORMONFLAT
HORSEMESA
GOLDFIELD230kV
OAKFLAT
PINTOVALLEY
KNOLL
TO APACHE(AEPCO)
TOTHUNDERSTONE
COOLIDGE(W.A.P.A.)
TOSILVER KING
500kV
SILVERKING230
ASARCO
GENERATING STATION
EXISTING LINE
FUTURE LINE
EXISTING SUBSTATION
FUTURE SUBSTATION
EasternMining Area
CARREL
BONNEYBROOK(APS)
TRASK
CARLOTA
ROOSEVELT
RS-30 115KV(2019)
230kV(2019)
2015-2024
TRANSFORMER
RS-29 230kV(2019)
2019
All Changes since January 2014 Ten Year Plan shown in red 4612/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.B. SRP changes since 2014 Plan• Completed Projects
– Pinal West – Duke – Pinal Central 500kV line– Pinal Central – Browning 500kV line– Pinal Central – Randolph 230kV line– Desert Basin – Pinal Central 230kV line– Pinal Central 500kV and 230kV Substation– Duke 500kV Substation– Browning – Rogers 230kV line
• New Projects– Hassayampa – Pinal West 500kV Jojoba line loop in 2016– Browning – Corbell and Santan – Rogers 230kV line in 2020– Hassayampa – Pinal West 500kV #2 in 2024
• Delayed Projects– Superior-Silver King 115kV re-route was 2015, now 2017– Schrader-RS28 230kV line was 2016, now 2017
4712/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.B. SRP changes since 2014 Plan• Delayed Projects
– RS28 230kV substation was 2016, now 2017– Eastern Mining Expansion was 2018, now 2019– Sun Zia was 2017, now 2018– Silver King-RS29 230kV was 2018, now 2019– RS29 230kV substation was 2018, now 2019– RS29-RS30 115kV was 2018, now 2019– RS30 115kV substation was 2018, now 2019– Ellsworth Technology Corridor was 2019, now TBD– New Superior-New Oak Flat 230kV was 2021, now TBD– New Oak Flat-Silver King 230kV was 2021, now TBD– Abel 500kV Substation was 2020, now TBD
• Removed Projects– None
4812/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.C. – 4.E. Transmission Planning Study Process SRP evaluates plan submittals or alternatives according to the following flowchart.
What Type of Study?1
Does Transmission Provider’s system
meetNERC/WECC
criteria?
No
Does Transmission Provider’s system meet local reliability criteria?
Yes
Transmission Provider determines facilities
needed with Stakeholder input
No
Transmission Provider coordinates with Sub-
Regional Planning Group
Yes
Economic Reliability
Transmission Provider
Evaluation
Regional
TEPPC evaluates with Stakeholder
input
Transmission Provider Economic
Study
Customer Choice of Study at Customer’s
expense
Local2
TEPPC determines high priority, performs
study
High priority
Not high priority
TEPPC determines not
high priority
Study results documented in a report and reviewed
by Customer and Transmission Provider
Transmission Provider determines facilities
needed with Stakeholder input
1. Generator Interconnection Request studies are performed pursuant to the Large Generator Interconnection Procedure contained in the Transmission Provider’s Open Access Transmission Tariff (OATT). Transmission Service Requests are also performed pursuant to OATT procedures.
2. All requests for economic planning studies received by the Transmission Provider are forwarded to TEPPC for inclusion in the TEPPC Master List. TEPPC will evaluate only those requests that have regional impacts.
Transmission Planning Process
Exhibit 1 – SRP Attachment K
4912/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.C.-E. SRP Planning - Study Requests
• Generation Interconnection Requests
• Transmission Interconnection Requests
• Transmission Service Requests
• Economic Study Requests
5012/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.C. SRP Planning –Interconnection Requests (Transmission)
• Currently there are no Transmission Interconnection Requests under study
5112/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.C. Interconnection Requests (Generation)
A. EAST VALLEY2- Solar Projects 100MW
B. EMA 115kV AREA3- Solar Projects 105MW
Generation Interconnection Requests listed on this slide are for SRP solely owned transmission
5212/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
BA
4.D.-E. SRP - Transmission Service and Economic Study Requests
• SRP received one Transmission Service Request• There are no Economic Study Requests
5312/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.F. Submittal of Additional Study Plan Proposals
• If you have study ideas for SRP to consider, please send a detailed message to: [email protected]
• Please include (at a minimum):– Your Name/Company/contact info (e-mail/phone #)– What the purpose of the study request is? And how
will the results be used?– What year(s) and season(s) is of interest?– What type of study – reliability (power flow only?),
economic?
5412/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
4.G. SRP Planning – Comments & Questions
• Stakeholder comments/questions on 2015 Study Results
5512/18/2014 APS/SRP Stakeholder Meeting for Transmission Planning
5. Stakeholder Questions & Comments
• Open discussion
• WestConnect –– http://www.westconnect.com/documents.php
• APS OASIS –– http://www.oatioasis.com/azps/index.html
• SRP OASIS –– http://www.oatioasis.com/srp/index.html
56
6. Action Items
• Review any action items, assignments, and due dates
57