APS/SRP Stakeholder MeetingFor Transmission Planning
FERC Order 890APS Attachment ESRP Attachment K
APS Transmission PlanningSRP Transmission PlanningPhoenix, ArizonaJune 28, 2012
• Welcome
• Introductions
• Meeting Overview
APS/SRP Joint Stakeholder Meeting 6/28/2012
2
Agenda1. Welcome, Introductions and Meeting Overview
2. Status of Action Items - 12/16/11 Joint APS/SRP 4th Quarter Meeting
3. APS Planninga. APS Planning Calendar & Methodologyb. Review APS filed Ten-Year Plan c. 2012 Study Assumptionsd. Interconnection Requests and APS Generator Queue Status updatee. Transmission Service Requestsf. Requests Received for Economic Planning Studies g. Stakeholders invited to submit requests for additional transmission studiesh. Comments/questions
4. SRP Planninga. SRP Planning Calendar and Methodologyb. 2012 Study Assumptionsc. Review SRP filed Ten- Year Plan d. Interconnection Requests and SRP Generator Queue Status updatee. Transmission Service Requestsf. Requests received for economic planning studiesg. Stakeholders invited to submit requests for additional transmission studiesh. Comments/questions
5. Stakeholder Questions/Comments
6. Action Items
APS/SRP Joint Stakeholder Meeting 6/28/2012
3
2. Status of Action Items
• A/I: SRP and APS will post LeeAnn’s Order 1000 presentation at OASIS websites.
APS/SRP Joint Stakeholder Meeting 6/28/2012
4
3.a. APS Planning Calendar & Methodology
• WECC/TEPPC/WestConnect Planning Calendar
• APS Planning Calendar• Planning Process/Methodology
APS/SRP Joint Stakeholder Meeting 6/28/2012
5
APS/SRP Joint Stakeholder Meeting 6/28/2012
6
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
10yr Plan – Filed with ACC by Jan. 31 10yr. Plans filed by others
APS Corporate Load Forecast
Stakeholder Input
APS Corporate Load Forecast – Post Summer
Sep. 1 – Network Transmission Customers and all other Transmission Customers Load &
Resource Forecast
10yr. Plan – New load forecast sensitivity
WestConnect Coordinated base case
development
Develop 10yr base cases from AZ seed cases
10yr. Plan study effort – Determination of projects, timings, and scope
4th Quarter Stakeholder Meeting – Review draft of current 10yr plan, discussion Economic Study
requests, receive stakeholder input
Planning Calendar for Ten-Year Planning CycleAPS Transmission Planning – 10 Yr
Plan
Arizona Utilities coordinated seed case development – from WestConnect cases
2nd Quarter Stakeholder Meeting – Stakeholder input on studies, request study alternatives,
updates on current projects
Other Subregional Coordination
Activities Throughout the Year
• APS/SRP Coordination Meeting
• APS/WAPA Coordination Meeting
• WestConnect Meetings
• SWAT Meetingso CATSo CRTo New Mexicoo SATSo El Dorado Valleyo Transmission
Corridoro Advisoryo Short-circuit
Oct. 31 – Deadline to submit Economic Study Requests for 4th Quarter Meeting review
APS/SRP Joint Stakeholder Meeting 6/28/2012
7
What Type of Study?1
Does Transmission Provider’s system
meetNERC/WECC
criteria?
No
Does Transmission Provider’s system meet local reliability criteria?
Yes
Transmission Provider determines facilities
needed with Stakeholder input
No
Transmission Provider coordinates with Sub-
Regional Planning Group
Yes
Economic Reliability
Transmission Provider
Evaluation
Regional
TEPPC evaluates with Stakeholder
input
Transmission Provider Economic
Study
Customer Choice of Study at Customer’s
expense
Local2
TEPPC determines high priority, performs
study
High priority
Not high priority
TEPPC determines not
high priority
Study results documented in a report and reviewed
by Customer and Transmission Provider
Transmission Provider determines facilities
needed with Stakeholder input
1. Generator Interconnection Request studies are performed pursuant to the Large Generator Interconnection Procedure contained in the Transmission Provider’s Open Access Transmission Tariff (OATT). Transmission Service Requests are also performed pursuant to OATT procedures.
2. All requests for economic planning studies received by the Transmission Provider are forwarded to TEPPC for inclusion in the TEPPC Master List. TEPPC will evaluate only those requests that have regional impacts.
Transmission Planning Process
Exhibit 1 – APS Attachment E
3.b. APS Ten Year Plan Projects 2012-2021
Transmission PlanFiled on Jan. 31, 2012
APS/SRP Joint Stakeholder Meeting 6/28/2012
8
2011 (In-Service):• Hoodoo Wash 500kV
switchyard• Cedar Mountain 500kv
switchyard2012:• Youngs Canyon 345/69kV
substation2013:• Delaney-Palo Verde 500kV line2014:• D. Basin-Pinal Central 230kV
line• Pinal Central-Sundance 230kV
line• Bagdad 115kV relocation2015:• Delaney-Sun Valley 500kV line• Hassayampa-N.Gila 500kV line• Mazatzal 345/69kV substation2016:• Morgan-Sun Valley 500kV line2021:• TS12 230/69kV substation
APS/SRP Joint Stakeholder Meeting 6/28/2012
9
APS/SRP Joint Stakeholder Meeting 6/28/2012
10
APS/SRP Joint Stakeholder Meeting 6/28/2012
11
2015: Sun Valley-Trilby
Wash 230kV line Trilby Wash-Palm
Valley 230kV line
2021: Scatter Wash
230/69kV substation
APS/SRP Joint Stakeholder Meeting 6/28/2012
12
APS/SRP Joint Stakeholder Meeting 6/28/2012
13
2015: Palo Verde Hub-North Gila
500kV #2 line North Gila-TS8 230kV line
Bulk Transformer Additions/Replacements
APS/SRP Joint Stakeholder Meeting 6/28/2012
14
Description Year
Kyrene 500/230kV Transformer #3 (in-service) 2012
Pinnacle Peak 230/69kV Transformer #4 (in-service) 2011
Black Peak 161/69kV Transformer Replacement 2013
Buckeye 230/69kV Transformer #2 Replacement 2016
Raceway 230/69kV Transformer #2 2018
Palm Valley 230/69kV Transformer #2 2019
Yavapai 230/69kV Transformer #2 2021
In-Service Date Changes
APS/SRP Joint Stakeholder Meeting 6/28/2012
15
Project Name Previous in-service date
New in-service date
Saguaro (TS12): Relocate the 230kV yard and install a 230/69kV transformer (Scope change)
2012 2021
Scatter Wash loop-in of Pinnacle Peak-Raceway 230kV line
2013 2021
Delaney-Sun Valley 500kV line 2014 2015
Sun Valley-Trilby Wash 230kV line 2014 2015
Mazatzal loop-in of Cholla-Pinnacle Peak 345kV line
2014 2015
Palo Verde Hub-North Gila 500kV #2 line 2014 2015
North Gila-TS8 230kV line 2014 2015Note: The in-service dates shown in this table are based on load projections, not potential interconnections. New generation interconnections may accelerate the in-service date.
3.c. 2011 NERC/WECC Reliability Studies• Summer Peak cases
– TPL-001 & TPL-002• Thermal analysis (All 10 years)• Post-Transient (All 10 years)• Transient Stability (2014 & 2021)
– TPL-003 & TPL-004 (2012 & 2020)• Maximum Load Serving Capability for Phx
& Yuma (All 10 years)– TPL-001 & TPL-002 Thermal and Post Transient
• Low Load Assessment– 2012 Heavy Winter & 2016 Light Autumn– Thermal, Transient Stability, & Post Transient– TPL-001 thru TPL-004
APS/SRP Joint Stakeholder Meeting 6/28/2012
16
2011 NERC Compliance Studies
APS/SRP Joint Stakeholder Meeting 6/28/2012
17
Peak Load Assessment - SummerNERC STANDARD STUDIES COMPLETED
TPL -001(n-0) Thermal Transient Stability Post Transient2012 SIL X2012 PEAK X2020 SIL X2020 PEAK X
TPL-002 (n-1)2012 SIL (Lines, xfmrs, gens) X X2012 PEAK (Lines, xfmrs, gens) X X X2012 MLSC (Lines, xfmrs, gens) X X2020 SIL (Lines, xfmrs, gens) X X2020 PEAK (Lines, xfmrs, gens) X X X2020 MLSC (Lines, xfmrs, gens) X X
TPL-003 (n-2)2012 Stuck Breaker/Breaker Failure X X X2012 N-1-1 X X X2012 Bus Section X X X2020 Stuck Breaker/Breaker Failure X X X2020 N-1-1 X X X2020 Bus Section X X X
TPL-004 (n-xx)2012 Major Substations With/Without Generation X X X2012 Stuck Breaker/Breaker Failure X X X2012 Common Corridor X X X2020 Major Substations With/Without Generation X X X2020 Stuck Breaker/Breaker Failure X X X2020 Common Corridor X X X
2011 NERC Compliance Studies
APS/SRP Joint Stakeholder Meeting 6/28/2012
18
Low Load AssessmentNERC STANDARD STUDIES COMPLETED
TPL -001(n-0) Thermal Transient Stability Post Transient2012 Heavy Winter Case X2016 Light Autumn Case X
TPL-002 (n-1)2012 TRANSMISSION LINE X X X2012 XFMR X X2012 GENERATION X X2012 REACTORS X X2016 TRANSMISSION LINE X X X2016 XFMR X X2016 GENERATION X X2016 REACTORS X X
TPL-003 (n-2)2014 Stuck Breaker X X X2014 N-1-1 X X X2016 Stuck Breaker X X X2016 N-1-1 X X X
TPL-004 (n-xx)2014 Loss of All Generation Units at a Station X X X2014 Common Corridor X X X2016 Loss of All Generation Units at a Station X X X2016 Common Corridor X X X
3.c. 2012 Study Assumptions
• Coordinated Base Cases (Seed Cases)– 2014 - WECC 2014hs3sa case– 2021 - WECC 2021hs1a case– Same cases as 2011 – updated for 2012
• 69kV transmission models incorporated• Most up-to-date forecasts for peak
summer loads
APS/SRP Joint Stakeholder Meeting 6/28/2012
19
3.c. 2012 NERC/WECC Reliability Studies• Summer Peak cases
– TPL-001 & TPL-002• Thermal analysis (All 10 years)• Post-Transient (All 10 years)• Transient Stability (2014 & 2021)
– TPL-003 & TPL-004 (2014 & 2017)• Maximum Load Serving Capability for Phx
& Yuma (All 10 years)– TPL-001 & TPL-002 Thermal and Post Transient
• Low Load Assessment– 2013 & 2017 Heavy Winter– Thermal, Transient Stability, & Post Transient– TPL-001 thru TPL-004
APS/SRP Joint Stakeholder Meeting 6/28/2012
20
3.d. Generation Interconnection Requests
• Generation Interconnection requests– APS OASIS contains Generation
Interconnection Queue• http://www.oatioasis.com/azps/index.html• 74 Solar projects - 5677 MW• 9 Wind projects - 3378.8 MW• 1 natural gas project - 320 MW
Note: Generator Queue information as of 6/14/12
APS/SRP Joint Stakeholder Meeting 6/28/2012
21
APS/SRP Joint Stakeholder Meeting 6/28/2012
22
A - Delaney/Sun Valley• 4 projects• 2120 MWB - HAA-NG 500kV line• 8 projects• 2098 MWC - Gila Bend/Buckeye• 41 projects• 1232 MWD - Yuma• 5 projects• 154 MWE - La Paz• 2 projects• 40 MWF - Cholla/Showlow• 8 projects• 933 MWG - Northern AZ• 9 projects• 2254 MWH- Pinal County• 2 projects• 31 MWI - Cochise County• 1 projects• 20 MW
Note 1: Generator Queue information as of 6/14/12Note 2: Figures displayed do not represent complete queue
CD
E
G
I
APS/SRP Joint Stakeholder Meeting 6/28/2012
23
A - Delaney/Sun Valley• 4 projects• 2120 MWB - HAA-NG 500kV line• 8 projects• 2098 MWC - Gila Bend/Buckeye• 41 projects• 1232 MWD - Yuma• 5 projects• 154 MWE - La Paz• 2 projects• 40 MWF - Cholla/Showlow• 8 projects• 933 MWG - Northern AZ• 9 projects• 2254 MWH- Pinal County• 2 projects• 31 MWI - Cochise County• 1 projects• 20 MW
Note 1: Generator Queue information as of 6/14/12Note 2: Figures displayed do not represent complete queue
CD
E
G
I
APS 2011 System Peak = 7087 MWCurrently in Generation Queue ≈ 8,800 MW
3.e&f. Transmission Interconnection & Study Requests
• 1 Wires to Wires Interconnection Requests
• 42 Transmission Service Requests• All requests based on Four Corners transaction
• Currently no Economic Study Requests
APS/SRP Joint Stakeholder Meeting 6/28/2012
24
3.g. Stakeholder Study Requests
• Study requests can be made at any time to:– [email protected]
APS/SRP Joint Stakeholder Meeting 6/28/2012
25
3.h. Comments & Question
• Comments…
• Questions???
APS/SRP Joint Stakeholder Meeting 6/28/2012
26
27APS/SRP Joint Stakeholder Meeting June 28, 2012
4.a. SRP Planning Calendar & Methodology
• SRP Planning Calendar• SRP Planning Process/Methodology
APS/SRP Joint Stakeholder Meeting June 28, 2012
28
What Type of Study?1
Does Transmission Provider’s system
meetNERC/WECC
criteria?
No
Does Transmission Provider’s system meet local reliability criteria?
Yes
Transmission Provider determines facilities
needed with Stakeholder input
No
Transmission Provider coordinates with Sub-
Regional Planning Group
Yes
Economic Reliability
Transmission Provider
Evaluation
Regional
TEPPC evaluates with Stakeholder
input
Transmission Provider Economic
Study
Customer Choice of Study at Customer’s
expense
Local2
TEPPC determines high priority, performs
study
High priority
Not high priority
TEPPC determines not
high priority
Study results documented in a report and reviewed
by Customer and Transmission Provider
Transmission Provider determines facilities
needed with Stakeholder input
1. Generator Interconnection Request studies are performed pursuant to the Large Generator Interconnection Procedure contained in the Transmission Provider’s Open Access Transmission Tariff (OATT). Transmission Service Requests are also performed pursuant to OATT procedures.
2. All requests for economic planning studies received by the Transmission Provider are forwarded to TEPPC for inclusion in the TEPPC Master List. TEPPC will evaluate only those requests that have regional impacts.
Transmission Planning Process
Exhibit 1 – SRP Attachment K
APS/SRP Joint Stakeholder Meeting June 28, 2012
29
30APS/SRP Joint Stakeholder Meeting June 28, 2012
4.b. 2012 NERC Compliance Study Methodology
• Coordinated Base Cases (Seed Cases)• NERC Compliance Studies
– 2014 – APS/SRP 2014 coordinated case– 2018 – APS/SRP 2018 coordinated case
• 69kV transmission models incorporated• Most up-to-date forecasts for peak
summer loads
31APS/SRP Joint Stakeholder Meeting June 28, 2012
4.b. 2012 NERC Compliance Study Methodology
NERC Compliance Studies Cases• 2014 & 2018 Summer Peak & Off-peak Cases• 2014 & 2018 Off-peak Cases are Low Load
(winter conditions) and High Import (shoulder cases with low generation in the Phoenix Metro Area).
• Following analysis are conducted:– Thermal analysis– Post-Transient– Transient Stability
32APS/SRP Joint Stakeholder Meeting June 28, 2012
NERC Compliance StudiesNERC STANDARD Type of Studies Completed
TPL-001 (N-0) Thermal Transient Stability Post-transient
2014 Peak X
2014 Low Load X
2014 High Import X
2018 Peak X
2018 Low Load X
2018 High Import X
2018 All-in X
TPL-002 (N-1) Thermal Transient Stability Post-transient
2014 Peak X X X
2014 Low Load X X X
2014 High Import X X X
2018 Peak X X X
2018 Low Load X X X
2018 High Import X X X
33APS/SRP Joint Stakeholder Meeting June 28, 2012
NERC Compliance StudiesNERC STANDARD Type of Studies Completed
TPL-003 (N-2) Thermal Transient Stability Post-transient
2014 Bus outages X X X
2014 Contingency of towers X X X
2014 Stuck breaker X X X
2014 Common Corridor X X X
2014 N-1-1 X X X
2018 Bus outages X X X
2018 Contingency of towers X X X
2018 Stuck breaker X X X
2018 Common Corridor X X X
2018 N-1-1 X X X
TPL-004 (N-X) Thermal Transient Stability Post-transient
2014 Substations with generation X X
2014 Common Corridor/Substationwithout generation
X X
Note: TPL-003 studies were performed on Peak, Low Load & High Import cases
34APS/SRP Joint Stakeholder Meeting June 28, 2012
4.b 2012-2021 Ten Year Plan Methodology
• Coordinated Base Cases (Seed Cases)– 2014 WECC 2014hs3sa case– 2021 WECC 2021hs1a case
• 69kV transmission models incorporated• 2012-2021 cases built from the seed
cases• Most up-to-date forecasts for peak
summer loads
35APS/SRP Joint Stakeholder Meeting June 28, 2012
4.b 2012-2021 Ten Year Plan Methodology
2012-2021 SRP Ten-Year Plan• TPL-001 & TPL-002 Studies Conducted for
all ten years• Studies conducted using Summer Peak
Cases
36APS/SRP Joint Stakeholder Meeting June 28, 2012
4.c SRP Ten Year Plan 2012-2021
37APS/SRP Joint Stakeholder Meeting June 28, 2012
SRP’s 500kV System
CEDAR MTN (APS)
38APS/SRP Joint Stakeholder Meeting June 28, 2012
SRP’s 230kV System
39APS/SRP Joint Stakeholder Meeting June 28, 2012
SRP’s 230kV System –East
40APS/SRP Joint Stakeholder Meeting June 28, 2012
SRP’s 230kV System - West
41APS/SRP Joint Stakeholder Meeting June 28, 2012
SRP’s 115kV System
42APS/SRP Joint Stakeholder Meeting June 28, 2012
Electric System Additions/Upgrades
Equipment Year
Reactive Devices
Pinal Central (possible) tbd
Transformers
Kyrene 3rd 500/230kV transformer 2012
Schrader 3rd 230/69kV transformer 2013
Pinal Central 1st & 2nd 500/230kV transformers 2014
Rudd 1st 230/69kV transformer 2017-2018
Pfister (RS-24) 1st 230/69kV transformer 2021
Reconductor
Rogers-Thunderstone (possible) 2014
43APS/SRP Joint Stakeholder Meeting June 28, 2012
SRP Changes from 2011 to 2012Projects Placed in Service in 2011
– Dinosaur-Abel-Randolph 230kV line– Abel 230kV yard– Abel 230/69kV transformer– Randolph 230kV yard
Revised Project and Substation Names– Santa Rosa 500kV station has been re-named “Duke”
Revised In-Service Dates– Pfister 230kV Substation was 2019, now 2021– SunZia Southwest Transmission Project was 2015/16,
now 2016– Rudd 230/69kV was 2013, now 2017 or 2018– Schrader 230/69kV was 2014, now 2013– Rogers-Santan was TBD, now 2016
44APS/SRP Joint Stakeholder Meeting June 28, 2012
• Generation Interconnection Requests• Transmission Interconnection Requests• Transmission Service Requests• Economic Study Requests
SRP Planning - Study Requests
45APS/SRP Joint Stakeholder Meeting June 28, 2012
• Currently there are no Transmission Interconnection Requests under study
4.d. SRP Planning –Interconnection Requests (Transmission)
The joint interconnection requests are listed on SRP OASIS website @ http://www.oatioasis.com/SRP/index.html 46
47APS/SRP Joint Stakeholder Meeting June 28, 2012
Generation Interconnection Requests listed at this slide are for SRP solely owned transmission..
A. EAST VALLEY• 2 Natural Gas Projects –
819MW• 1 Solar Project – 20MW
B. EMA 115kV AREA• 1 Solar Project – 45MW
C. PINAL CENTRAL • 1 Natural Gas Project –
540MW
SRP Planning –Interconnection Requests (Generation)
BA
C
48APS/SRP Joint Stakeholder Meeting June 28, 2012
• Currently there are no Transmission Service Requests under study
4.e. SRP Planning - Transmission Service Requests
4.f. SRP Planning – Economic Study Requests
• Currently there are no Economic Study Requests
49APS/SRP Joint Stakeholder Meeting June 28, 2012
• SRP invites Stakeholders to submit request for additional transmission studies
4.g. Stakeholders Requests
50APS/SRP Joint Stakeholder Meeting June 28, 2012
4.h. SRP Planning – Comments & Questions
• Stakeholder comments/questions on 2011 Study Results or 2012 Study Requests
• Requests can be made at any time to:– [email protected]
5. Stakeholder Questions and Comments
Open discussion
Reference Material• WestConnect –
http://www.westconnect.com/documents.php• APS OASIS –
http://www.oatioasis.com/azps/index.html• SRP OASIS –
http://www.oatioasis.com/srp/index.html
APS/SRP Joint Stakeholder Meeting 6/28/2012
51
6. Action Items
• Review any action items identified for follow up
• Information addressing action items to be posted on APS and/or SRP OASIS and WestConnect website
APS/SRP Joint Stakeholder Meeting 6/28/2012
52