147
BEFORE THE HONBLE MEGHALAYA STATE ELECTRICITY REGULATORY COMMISSION, SHILLONG PETITION FOR APPROVAL OF FINAL TRUED-UP OF ANNUAL REVENUE REQUIREMENT FOR FY 2009-10 FILED BY MEGHALAYA POWER DISTRIBUTION CORPORATION LTD. LumJingshai, Short Round Road, Shillong - 793 001

APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

BBEEFFOORREE

TTHHEE HHOONN’’BBLLEE

MMEEGGHHAALLAAYYAA SSTTAATTEE EELLEECCTTRRIICCIITTYY RREEGGUULLAATTOORRYY CCOOMMMMIISSSSIIOONN,, SSHHIILLLLOONNGG

PPEETTIITTIIOONN

FFOORR

AAPPPPRROOVVAALL OOFF FFIINNAALL TTRRUUEEDD--UUPP

OOFF

AANNNNUUAALL RREEVVEENNUUEE RREEQQUUIIRREEMMEENNTT

FFOORR

FFYY 22000099--1100

FILED BY

MEGHALAYA POWER DISTRIBUTION CORPORATION LTD.

LumJingshai, Short Round Road, Shillong - 793 001

Page 2: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

BEFORE THE HON’BLE MEGHALAYA STATE ELECTRICITY REGULATORY

COMMISSION

FILE / PETITION NO………

IN THE MATTER OF

TRUING-UP OF THE ANNUAL REVENUE REQUIREMENT (ARR) FOR THE YEAR 2009-10

AND IN THE MATTER OF

MEGHALAYA POWER DISTRIBUTION CORPORATION LIMITED, LUMJINGSHAI,

SHILLONG – 793001, MEGHALAYA

PETITIONER

The Petitioner respectfully submits as under:

1. The Power Supply Industry in Meghalaya had been under the control of the erstwhile

Meghalaya State Electricity Board (MeSEB) with effect from 21st January 1975. The

Government of Meghalaya (GoM or State Government) unbundled and restructured the

Meghalaya State Electricity Board with effect from 31st March 2010. The Generation,

Transmission and Distribution businesses of the erstwhile Meghalaya State Electricity Board

were transferred to four successor companies. The State Government issued a Notification “The

Meghalaya Power Sector Reforms Transfer Scheme 2010” thereby giving effect to the transfer

of assets, properties, rights, liabilities, obligations, proceedings and personnel of the erstwhile

MeSEB. On 31st March 2012, Government of Meghalaya issued further amendment to the

above mentioned transfer scheme, to transfer Assets and Liabilities including all rights,

obligations and contingencies with effect from 31st March 2012 to namely :

Generation: Meghalaya Power Generation Corporation Ltd. (MePGCL)

Transmission: Meghalaya Power Transmission Corporation Ltd. (MePTCL)

Distribution: Meghalaya Power Distribution Corporation Ltd. (MePDCL)

Meghalaya Energy Corporation Limited (MeECL), a Holding company.

2. The Meghalaya State Electricity Regulatory Commission (hereinafter referred to as “MSERC”

or “the Hon’ble Commission”) is an independent statutory body constituted under the

provisions of the Electricity Act (EA), 2003. The Hon’ble Commission is vested with the

authority of regulating the power sector in the State inter alia including determination of tariff

for electricity consumers.

Provisions of Law

3. The Hon’ble Commission has notified the Meghalaya State Electricity Regulatory Commission

Page 3: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

(Terms and Conditions for Determination of Tariff) Regulations, 2011 on 10th February 2011.

This Regulation provides the framework under which the licensees shall operate. Accordingly,

the key provisions of the said Regulation are reproduced below for reference.

15. Review and Truing-Up

(1) ……...

(2) After Audited accounts of a year are made available, the Commission shall undertake

similar exercise as above with reference to the final actual figures as per the Audited

accounts. This exercise with reference to Audited accounts shall be called ‘truing-Up’.

(3) The generating company or the licensee, as the case may be, shall make an application

before the Commission, for ‘truing up’ of ARR of the previous year by 30th September of the

following year, on the basis of Audited statement of accounts and the Audit Report, thereon.

The generating company or the licensee shall get their accounts Audited within a specified

time frame, either by the Comptroller & Auditor General of India or by a Statutory Auditor

drawn from the panel of Statutory Auditors approved by the Comptroller & Auditor

General of India, from time to time, to enable them to file the application for ‘truing up’

within the specified date, that is 30th September of the following year.

4. Section 61 & Section 62(c) & (d) of Electricity Act 2003 empowers the Hon’ble Commission to

determine tariff for wheeling and retail sale of electricity for the Licensee. Accordingly, this

petition is submitted according to the aforementioned provisions of the Tariff Regulations and

on the basis of actual performance.

5. It is submitted that this Petition for Final True up for FY 2009-10 is hereby filed, based on

Annual Audited Accounts of erstwhile MeSEB and in pursuant to the Orders below, namely,

(i) Order dated 5th August 2010 passed by the Hon’ble Commission in “Remand Proceedings

No. 1 of 2010” in the matter of “Remand Order dated 19.04.2010 passed by the Hon’ble

Appellate Tribunal for Electricity in Appeal No. 67 of 2010 read with I.A.No.86 of 2010”

(A copy of Order dated 05.08.2010 is enclosed as Annexure I), and

(ii) Order dated 19th November 2010 passed by the Hon’ble Commission in the matter of

“Application seeking modification, recall and / or review of certain observations and

findings in the Order dated 05.08.2010 passed by the Commission in Remand Proceedings

No. 1 of 2010”, (A copy of Order dated 19.11.2010 is enclosed as Annexure II),

6. The Comptroller & Auditor General of India (CAG) have Audited the Balance Sheet of

Page 4: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

Meghalaya State Electricity Board as on 31st March 2010, Net Revenue and Appropriation

Account for the year ended on that date under Rule 14 of the Electricity (Supply) Annual

Accounts Rules, 1985 read with Section 172 (a) and 185 (2) (d) of the Electricity Act 2003 and

submitted the Separate Audit Report of GAC on 1st July 2011 which is attached as Annexure

III.

Final Truing Up for FY 2009-10

7. The following sections outline the deviations in actual expenses for FY 2009-10 based on the

Audited Accounts of erstwhile MeSEB in comparison with the expenditure provisionally

assessed by the Hon’ble Commission vide Order dated 5th August 2010.

Category wise Sales and Revenue

8. Comparison of category wise audited sales and revenue and provisionally assessed sales and

revenue for FY 2009-10 is shown in the following Table :-

Table 1 : Category wise Sales and Revenue

Category

FY 2009-10 Provisionally assessed by MSERC

vide Order dated 5.8.2010 Audited

Sales (MUs)

Revenue (Rs. Crs)

Sales (MUs)

Revenue (Rs. Crs)

Domestic

71.60 232.27 70.99 Commercial 27.02 52.24 31.35 Industrial 224.45 468.63 235.25 Public Lighting 0.99 1.49 0.98 Irrigation & Agriculture 0.11 0.63 0.11 Public Water Works 12.31 31.58 12.31 Bulk Supply to Others 29.94 60.91 30.01 Misc/General Purpose 6.17 48.64 1.06 Construction Project H.T. 2.01 1.35 Inter-State Sale 13.16 4.96 UI Sale 26.97 67.29 22.51 Wheeling Charges 0.45 Other Recovery 4.41 Total 896.09 399.56 978.85 415.74

It is submitted that the revenue of RS 415.74 crore from sale of power included an amount of

Rs 231.82 crores billed to HT & EHT Industrial Consumers as per tariff determined in the

Hon’ble Commission’s Tariff Order dated 30th September, 2008 (applicable for the period of 8

months in FY 2009-10) and Tariff Order dated 30th November, 2009 (applicable for 4 months in

FY 2009-10).

Page 5: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

9. It is submitted that the Hon’ble Supreme Court, in its Order dated 28.08.2012, has held that the

tariff rates passed by Tariff Order dated 10.09.2009 of this Hon’ble Commission shall be

deemed to have come into effect from 01.10.08. A copy of the Hon’ble Supreme Court’s Order

is enclosed as Annexure IV.

10. Pursuant to the Order dated 28.08.2012 of the Hon’ble Supreme Court, the MeECL petitioned

the Hon’ble Commission to consider the following:-

a) Revision of bills as per Tariff Order dated 10.09.2009 with retrospective effect, only for

IHT and IEHT categories.

b) The benefit of tariff rate revision for categories other than IHT and IEHT may be passed in

2013-14.

c) To revise the trued-up ARR 2008-09 in view of the revision of bills as per Tariff Order

dated 10.09.2009 with retrospective effect for IHT and IEHT categories.

However, this Hon’ble Commission, vide Order dated 14.12.2012, dismissed the petition as not

being maintainable. A copy of this Hon’ble Commission’s Order is enclosed as Annexure V.

11. In the circumstances, the MePDCL proceeded to revise the bills as petitioned before this

Hon’ble Commission. The revised bills were served to the IHT and IEHT consumers in March

2013. In view of the above revision in bills of Industrial Consumers, revenue from sale of

power of HT & EHT Industrial Consumers for FY 2009-10 has reduced from Rs 231.82 crore

by Rs 54.57 crore to Rs 177.25 Crores. Therefore, this has resulted in reduction in total revenue

from sale of power from Rs 415.74 crore to Rs 361.17 Crores. It is submitted before the

Hon’ble Commission to kindly approve Revenue from sale of power at Rs 361.17 Crores for

FY 2009-10.

12. It is submitted before the Hon’ble Commission that by revising only the bills of IHT and IEHT

consumers, it raises the issue of discrimination in tariff and showing undue preference to IHT

and IEHT consumers. Therefore, to avoid any discrimination, the tariff for other categories

other than IHT and IEHT may be adjusted in subsequent tariff orders as detailed below :-

a). The difference in average rate for each category is calculated as shown in ANNEXURE VI.

b). The actual sales for the period from April 2009 to October 2009 for FY 2009-10 and the

amount to be adjusted against each category is calculated as shown in ANNEXURE VII.

Page 6: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

Power Purchase Expenses

13. It is submitted that apart from own generation, power was purchased power from NEEPCO,

NHPC, NTPC, IPPs, Traders, and other sources. A comparison of power purchase expenses as

per the Audited Accounts and as provisionally assessed by Hon’ble Commission for FY 2009-

10 is shown in the following Table below.

Table 2: Power Purchase Expenses for FY 2009-10

Particulars Provisionally assessed by MSERC vide Order dated

5.8.2010

FY 2009-10 (Audited) Deviation

Power Purchase Cost 223.74 222.63 (1.11) Add understated Amount* - 1.28 1.28 Total Power Purchase Cost 223.74 223.91 0.17

* Audit Objection of understatement of Expense pertaining to amount payable to PTCIL & PGCIL as shown in serial no 8 in page 3 of Statement of accounts for FY 09-10

It is submitted that the Hon’ble Commission had provisionally assessed Power Purchase Cost at

Rs.223.74 Crs. However, as per audited Annual Accounts for the FY 2009-10, the power

purchase cost amounts to Rs.223.91 Crs. It is submitted before the Hon’ble Commission to

kindly true up the power purchase expenses at Rs 223.91 crore.

Fixed Costs for FY 2009-10

14. Based on the Capital Cost and the consequent Capitalized Expenditure, Equity Component and

Normative Debt, the fixed cost for FY 2009-10 has been determined in accordance with the

MSERC Tariff Regulations 2011 outlined thereof. As outlined under the regulations, the fixed

cost has been determined under the following major heads:

o Operation and Maintenance Expenses

o Depreciation

o Interest and Finance Charges

o Income Tax

o Return on Equity

O&M Expenses

15. Operations and Maintenance (O&M) Expenses of the Company consists of the following

elements:

o Repairs and Maintenance Costs

o Employee Expenses

Page 7: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

o Administrative and General Expenses

Repairs and Maintenance Expenses go towards the day to day upkeep of the assets of MeECL

and form an integral part of the Company’s efforts towards reliable and quality power supply as

also in the reduction of losses in the system.

Employee expenses comprise of salaries, dearness allowance, bonus, terminal benefits in the

form of pension & gratuity, leave encashment and staff welfare expenses.

Administrative expenses mainly comprise of rents, telephone and other communication

expenses, professional charges, conveyance and travelling allowances and other debits.

16. Repairs and Maintenance Expenses

Except for Stage I power station, which was renovated in 2001-02, the power stations are

between 20 to 50 years old. These power stations require more expenses to maintain the

scheduled generation. In addition, Meghalaya being the hilly terrain state demands a

comparatively more expenses in maintaining the transmission and distributions network. Repair

and Maintenance expenditure is dependent on various factors. The assets of MeECL are old and

require regular maintenance to ensure uninterrupted operations. MeECL has been trying its best

to ensure uninterrupted operations of the system and accordingly has been undertaking

necessary expenditure for R&M activities. The summary of the comparison of the actual R&M

expenses for FY 2009-10 vis-à-vis the expenses provisionally assessed by the Hon’ble

Commission has been given in the table below:

Table 3: R&M expenses for FY 2009-10 (Rs Crores)

Particulars Provisionally assessed by MSERC vide Order dated 5.8.2010

FY 2009-10 (Audited) Deviation

R & M Expenses 20.26 20.09 (0.17)

It is submitted that R&M expenses cannot be considered as a controllable expenditure as it is

necessary to incur as and when required to supply quality power to its consumers on

continuously. Hence R&M expenses are genuine and legitimate expenditure which may kindly

be approved are as per Audited Accounts.

17. Employee Expenses

The employee expenses comprise the following broad sub-heads of expenditure:

Basic Salary

Dearness Allowance

Overtime

Other Allowances

Page 8: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

Earned Leave Encashment

Staff Welfare and Other Expenses

Medical Expenses Reimbursements

Terminal Benefits

o Provident fund contribution

o Gratuity payments

o Pension Payments

o Provision for PF Fund

o Leave encashment on retirement

A significant component of the employee cost has been the salary and terminal benefit which is

being met from the revenue earning on year to year basis. In other words, the actual pension

outflow for the retired personnel is being managed from the revenue earned in the year. Also

new employees are being recruited to meet the shortage of man power due to gradual retirement

of employees. The summary of the comparison of the actual employee expenses for FY 2009-

10 vis-à-vis the expenses provisionally assessed by the Hon’ble Commission has been given in

the table below:

Table 4: Employee Expenses for FY 2009-10 (Rs Crores)

Particulars Provisionally assessed by MSERC vide Order dated 5.8.2010

FY 2009-10 (Audited) Deviation

Employee Expenses 111.03 114.92 3.89

It is submitted that the deviation in Employee Cost is mainly due to increase of D.A., Medical

Allowance and Terminal benefits which are genuine and legitimate expenditure which may

kindly be approved per Audited Accounts certified by the Auditors.

18. Administration and General Expenses

The Administrative and general expenses comprise of following broad sub heads of

expenditure.

Rent, Rates and Taxes

Insurance

Telephone and Postage Charges

Conveyance and Traveling

Audit Fees

Training Expenses

Page 9: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

Electricity Charges

Other Expenses including water charges, Printing and Stationary expenses, Legal,

professional and consultancy fees, advertisement, vehicle running, office expenses

and other miscellaneous expenses.

The summary of the comparison of the actual A&G expenses for FY 2009-10 vis-à-vis the

expenses provisionally assessed by the Hon’ble Commission has been given in the Table

below:

Table 5: A&G Expenses for FY 2009-10 (Rs Crores)

Particulars Provisionally assessed by MSERC vide Order

dated 5.8.2010

FY 2009-10 (Audited) Deviation

Administration & General Expenses 8.71 10.01 1.30

The A&G expenses are also increasing gradually due to expansion of the power sector in the

state and also to keep pace with the inflation. As there is increase in the activities of the

Licensee, the A&G expenses have also been increased. Moreover, there was inflationary trend

in the market. Further in the FY 2009-10 Rs 2.74 Cr is spent towards consultancy services

availed for various projects, which has lead to the deviation from the provisionally assessed

figure. It is submitted that A&G expenses are the legitimate expenses incurred and are directly

related to the day to day administration and general operation. It is further submitted before the

Hon’ble Commission to kindly consider the number of employees, size and number of offices,

geographical spread while approving the A&G expenses. A&G expenses are genuine and

legitimate expenditure and hence may kindly be approved as per Audited Accounts certified by

the Auditors.

19. Depreciation

Following table shows the summary of the comparison of the actual depreciation for FY 2009-

10 vis-à-vis the depreciation provisionally assessed by the Hon’ble Commission.

Table 6: Depreciation for FY 2009-10 (Rs Crores)

Particulars Provisionally assessed by MSERC vide Order dated 5.8.2010

FY 2009-10 (Audited) Deviation

Depreciation 17.08 25.94 8.86

The deviation in total depreciation is due to capitalization of Sonapani and revision of

Page 10: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

depreciation rates for fixed asset by CERC. The depreciation rate has been considered as per the

CERC Regulations, 2009 (Notification No.L-7/145(160)/2008-CERC dated 19th January,

2009) and calculated the depreciation on fixed assets for FY2009-10. Therefore, it is submitted

before the Hon’ble Commission to consider the parameters impacting depreciation as

uncontrollable and approve the entire amount of depreciation as per Audited Accounts.

20. Interest and Financial Charges

The interest expenditure on account of long-term loans depends on the outstanding loan,

repayments, and prevailing interest rates on the outstanding loans. Further, the projected capital

expenditure and the funding of the same also have a major bearing on the long-term interest

expenditure. Details of source-wise Interest expenses as well as other interest & finance charges

including cost of raising finance have been furnished in the following table.

Table 7: Total Interest and Finance Charges for FY 2009-10

Particulars Amounts (Rs. Crs) Interest on State Govt. Loan 19.91 Interest on Bonds 21.08 Interest on PFC Loan 6.17 Interest on Loan from CSS 0.98 Interest on REC Loan 26.30 Interest on Loan from Bank 13.82 Interest on Loan from HUDCO 2.96 Interest on Loan (Federal Bank) 1.31 Interest on Loan (OECF Japan) 1.56 Interest on Loan (JBIC Japan) 0.17 Penal Interest 3.86 Discount to Consumers for timely payment 0.01 Cost on Raising Finance 0.83 Other Charges 4.45 Total Interest and Finance Charges 103.40

It is submitted that the interest & finance charges also include the Interest on State Govt. Loan

of Rs. 19.91 Crs. Hence, the claimed on Interest and Finance Charges are excluding the Interest

on State Government Loan. The following table shows the summary of the comparison of the

actual interest and finance charges for FY 2009-10 vis-à-vis the interest and finance charges

provisionally assessed by the Hon’ble Commission.

Table 8: Interest & Finance Charges for FY 2009-10

Particulars Provisionally assessed by MSERC vide Order dated 5.8.2010

FY 2009-10 (Audited) Deviation

Interest & Finance Charges 72.70 83.49 10.79

Page 11: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

It is submitted that Interest & finance charges are genuine and legitimate expenditure and the

Hon’ble Commission may kindly approve the entire interest & finance charges as per Audited

Accounts.

21. Expenses Capitalized

A summary of the comparison of the actual expenses capitalized for FY 2009-10 vis-à-vis the

expenses capitalized provisionally assessed by the Hon’ble Commission has been given in the

table below:

Table 9: Expenses Capitalised for FY 2009-10 (Rs Crores)

Particulars Provisionally assessed by MSERC vide Order

dated 5.8.2010

FY 2009-10

(Audited) Deviation

Interest & Finance Charges Capitalised 58.65 63.85 5.20 Employee Expenses Capitalised 9.31 9.98 0.67 Administration & General Expenses Capitalised - 0.13 0.13 Total Expenses Capitalised 67.96 73.96 6.00

It is submitted that the Hon’ble Commission may kindly approve the entire expenses capitalized as

per Audited Accounts.

22. Other Debits (including provision for Bad Debts)

A summary of the comparison of the actual other Debits (including provision for Bad Debts)

for FY 2009-10 vis-à-vis the other Debits (including provision for Bad Debts) provisionally

assessed by the Hon’ble Commission has been given in the table below:

Table 10: Other Debits (including provision for Bad Debts) for FY 2009-10 (Rs Crores)

Particulars Provisionally assessed by MSERC vide Order

dated 5.8.2010

FY 2009-10

(Audited) Deviation

Other Debits (including provision for Bad Debts) 10.00 14.24 4.24

The deviation in other debits is mainly due to written off of Nangalbibra Thermal Power station. It

is submitted before the Hon’ble Commission to kindly approve the entire Other Debits (including

provision for Bad Debts) as per Audited Accounts.

23. Income Tax

A summary of the comparison of the income tax as per Audited Accounts of erstwhile MeSEB

Page 12: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

for FY 2009-10 vis-à-vis the income tax provisionally assessed by the Hon’ble Commission

has been given in the table below:

Table 11: Income Tax for FY 2009-10 (Rs Crores)

Particulars Provisionally assessed by MSERC vide Order dated 5.8.2010

FY 2009-10 (Audited) Deviation

Income Tax 4.94 - (4.94)

24. Prior Period Credits/Charges

It is submitted that the Accounting Standard 5 (AS 5) issued by Institute of Chartered Accounts

of India deals with the Net Profit/Loss for the Period, Prior Period Items and Changes in

Accounting Policies. As per the AS 5, all items of income and expense, which are recognized in

a period, should be included in determination of net profit or loss for the period unless an

accounting standard requires or permits otherwise. Prior period items’ are material charges or

credits which arise in the current period as a result of errors or omissions in the preparation of

the financial statements of one or more prior periods. The following Table provides the details

of the prior period credits/ (charges) for FY 2009-10.

Table 12: Net prior period credits / (charges) for FY 2009-10 (Rs Crores)

Particulars FY 2009-10 (Audited) Income relating to Previous Year Excess Provision for Depreciation 0.00 Excess Provision for Interest and Fincance Charges 0.00 Other Excess Provision 1.03 Other Income 0.31 SUB TOTAL 1.34 Expenses / Losses relating to Previous Year Purchase of Power relating to prior period 11.72 Operating Expenses Employees Costs relating to prior period 4.47 Depreciation under provided in prior period 4.24 Interest and Other Charges relating to prior period 81.33 Administration Expenses relating to prior period 0.00 Wheeling Charges relating to prior period 4.99 Other Expenses relating to prior period 0.03 SUB TOTAL 106.78 NET PRIOR PERIOD CREDITS/(CHARGES) (105.44)

The disclosure of prior period items is in line with Accounting Standard (AS)-5 on Prior Period

and Extraordinary Items, which emphasizes that Prior period items should be separately

disclosed in the current statement of profit and loss together with their nature and amount; and

in a manner that their impact on current profit or loss can be perceived. Therefore prior period

Page 13: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

items which are necessary for smooth functioning of the company are pertaining to the previous

financial year but recognized during current year and hence are of uncontrollable nature.

25. The Hon’ble Commission, in its Order dated 5.8.2010 had not allowed the provisional

expenditure of Rs 13.28 crore against prior period. It is submitted that prior period expenses or

revenue are by definition, “items which arise in the current period as a result of errors or

omissions in the preparation of the financial statements of one or more prior periods” and

hence such items are uncontrollable in nature.

26. It is submitted that employee costs relating to prior period, short provision for Income tax in

prior period and administrative expenses relating to prior period are all uncontrollable.

Employee expenses are purely on the basis of the guidelines issued by competent authorities

like the State Government and hence any variation is purely beyond the control of the Licensee.

Similarly, income tax expenses are statutory expenses and cannot be projected. Hence such

legitimate expenses may kindly be allowed.

27. Interest and Other Charges relating to prior period are purely uncontrollable in nature. These

are mainly due to audit objection and reconciliation of loan payable to financial institutions.

The breakup of Interest and other charges related to prior period is mentioned below:

Reconciliation of REC Loan- Rs 68.7 Crs

Audit Objection and understatement of loan in prior period- Rs 12.3 Cr

It is submitted before the Hon’ble Commission to kindly allow total prior period expenses of Rs

102.51 Crs.

Table 13: Uncontrollable Prior Period (Expenses) /Income

Particulars Amounts (Rs. Crs) Purchase of Power relating to prior period 11.72 Employees Costs relating to prior period 4.47 Interest and Other Charges relating to prior period 81.33 Wheeling Charges relating to prior period 4.99 Total Uncontrollable Prior Period (Expenses) /Income 102.51

28. Return on Equity

It is submitted that the return on equity for FY 2009-10 as provisionally assessed by the Hon’ble

Commission vide Order dated 5.8.2010 may kindly be retained.

Page 14: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

Aggregate Technical & Commercial (AT & C) Losses.

29. It is submitted that the AT&C loss for FY 2009-10 is 28.60 %, as can be seen from the

calculation shown in Table below:

Table 14: AT&C Losses for FY 2009-10

Particulars Formula Units

Provisionally assessed by MSERC vide Order dated 5.8.2010

Audited

Generation (own as well as any other connected generation net after deducting auxiliary consumption) within area of supply of DISCOMS

A MU 532.31

534.79

Input energy (metered import) received at interface points of DISCOM network.

B MU 819.61

819.61

Input energy (metered Export) by the DISCOM at interface points of DISCOM network.

C MU 13.16

13.16

Total energy available for sale within the licensed area to the consumers of the DISCOM

D=A+B-C MU 1338.76

1341.24

Energy billed to metered consumers within the licensed area of the DISCOM

E MU

896.09

898.40 Energy billed to un-metered consumers within the licensed area of the DISCOM

F MU

Total energy billed G=E+F MU 896.09 898.40

Amount billed to consumers within the licensed area of the DISCOM H Rs.

Crs

393.90

333.69 Amount realized by the DISCOM out of the amount billed at H

Revenue from sale of power Rs.

Crs

340.51

343.40

RE subsidy 12.31

12.31

Total I Rs. Crs

352.82

355.71

Collection Efficiency (%) J=(I/H) x 100 % 89.57

106.60

Energy realized by the DISCOM K=J x G MU 802.64

957.67

Distribution Loss (%) L={(D-G) ÷D}X100 %

33.07

33.02

AT&C Loss (%) M={(D-K) ÷D}X100 %

40.05

28.60

Page 15: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

It is submitted that the AT&C loss as provisionally assessed by the Hon’ble Commission vide

Order dated 5.8.2010 may kindly be revised to 28.60 %.

Penalty/ (Incentive) for AT&C Losses for FY 2009-10

30. In the Order dated 05.08.2010 in Remand Proceedings No. 1 of 2010, Hon’ble Commission has

observed , inter alia, held as under:-

“19. The Commission carefully considered the submissions contained in the Affidavit dated

30.07.2010 filed by MeECL and noted with concern that MeSEB / MeECL had sought to

justify the increased level of AT&C losses of 40.05 percent during 2009-10, as against

33.79 percent during 2008-09, by stating that “the collection efficiency during FY 2009-

10 was adversely affected due to part payment of the current bills by the members of the

Byrnihat Industries Association (BIA). It may be informed that the amount paid by the

industries for the period April to November 2009 was Rs.121.34 crores against a demand

of Rs.159.12 crores (as per Tariff Order dated 30th September 2008), and thereby

outstanding amount is Rs.37.78 crores)”. The justification offered by MeSEB / MeECL is

wholly misconceived and untenable. The Commissions Tariff (D) Order dated 30.09.2008

was revised vide Commission’s Tariff(D) Order dated 10.09.2009. The tariff rates were

thereby revised downwards by an average of over 20 percent, with effect from 01.10.2008.

The Commission’s Tariff (D) Order dated 10.09.2009 has not been stayed or set aside by

any Competent Authority. The MeSEB / MeECL were required to comply with the said

Tariff (D) Order dated 10.09.2009 and to implement the directions contained therein. By

continuing to raise / realize electricity bills from consumers, for the period 01.10.2008 to

30.11.2009, as per rates fixed by Tariff(D) Order dated 30.09.2008, as indicated by them

in their said Affidavit dated 30.07.2010, the MeSEB / MeECL have violated the

Commission’s Tariff Order dated 10.09.2009, and are liable to be proceeded against and

penalized as per provisions of Section 142 of the Electricity Act of 2003.

20. Considering the critical level of increasing AT&C losses (provisional) during the year

2009-10, as reported by MeECL, the Commission hereby decides to discourage such

inefficiency, and to impose a penalty for MeSEB / MeECL’s failure to reduce the AT&C

loss by the mandated level of 3 percent from the previous year (2008-09) level of 33.79

percent. The penalty is accordingly assessed at Rs.55.27 Crores, as per detailed

calculation shown at Schedule-I Below-

SCHEDULE-I

CALCULATION OF PENALTY FOR FAILURE TO CAUSE A MINIMUM OF 3%

REDUCTION IN AGGREGATE TECHNICAL & COMMERCIAL (AT&C) LOSSES DURING

Page 16: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

2009-10

1. AT & C Losses during 2008-09 as reported by MeSEB vide their letter No. MESEB/SE(RA)33/43 dt.14.10.2009. = 33.79%

2 Mandated minimum reduction of AT&C Losses for Entities having AT&C Losses in excess of 30%.

= 3.00%

3.

Maximum permissible AT&C Loss for MeSEB during 2009-10 after reduction of such loss by a minimum of 3% from the previous year’s level.

= 30.79%

4.

Actual AT&C Losses during 2009-10 as reported by MeSEB vide their Affidavit dated 30.07.2010 under cover of their Letter No.MESEB/SE(RA)43/55, dt.30.07.2009.

= 40.05%

5.

Shortfall in minimum reduction of AT&C Losses by MeSEB during 2009-10 = (40.05-30.79%).

= 9.26%

6. Shortfall in minimum reduction of AT&C Losses by MeSEB during 2009-10 in Million Units = (9.26% of 1338.76 Mu’s ).

= 123.9692 MUs

7.

Average aggregate Unit Rate for sale of power by MeSEB during 2009-10 = Revenue income from sale of power during 2009-10 = Rs.399.57 Cr Total Energy billed 896.09 MU (Based on data submitted by MeECL vide their Affidavit dated 30.07.2010 under cover of their Letter No. MESEB/SE(RA)43/55, dt.30.07.2009)

Rs.4.4590

8. Penalty for failure to reduce AT&C Losses by 3% during 2009-10 = 123.9692 MU x Rs.4.4590

= 55.2778 Cr

= Say Rs.55.27 Cr …..”

31. It is submitted that the Hon’ble commission vide its order dated 19th November 2010 held that:

“(b) The observations and findings of the Commission in its order dated 05.08.2010 in

Review Petition No.1 of 2010, as well as its direction to penalizing the Applicant with

regard to AT&C Losses, were made on the basis of level of AT&C reported by the

Petitioner. The circumstances under which in the instant proceedings, could be

appropriately raised by the Petitioner for consideration of the Commission, while truing

up the ARR for the year 2009-10.

(c) Considering the facts and circumstances of the instance case, Commission directs the

Petitioner to submit their proposal for truing-up of their Annual Revenue Requirement for

the year 2009-10 along with the Audited Statement of Accounts for that year and the

Commission to more fully address the issue related to AT&C losses, raised in the instant

Petition.”

32. It is submitted that the above calculation of penalty by Hon’ble Commission was based on

Page 17: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

revenue demand at tariff determined by Hon’ble Commission vide its Order dated 30th

September 2009. However, pursuant to Hon’ble Supreme Court’s Order dated 28th August 2012

and subsequent revision of bills for industrial HT & EHT consumers, the revenue demand for

the FY 2009-10 has reduced by Rs 54.57 crores and based on revised revenue demand,

collection efficiency for the FY 2009-10 has also improved, leading to a AT & C loss of 28.60

%.

Table 15 Calculation of Penalty/ (Incentive) for AT&C Losses for FY 2009-10

Particulars Unit Amount AT&C losses approved by Hon'ble Commission in FY 2007-08 % 31.62 Mandated minimum reduction of AT&C Losses for entities having AT&C Losses in excess of 30%. % 3.00

AT & C Loss target to be achieved in FY 2008-09 % 28.62 Mandated minimum reduction of AT&C Losses for entities having AT&C Losses below 30%. % 1.50

AT & C Loss target to be achieved in FY 2009-10 % 27.12 Actual AT&C losses during 2009-10 after implementation of Hon'ble Supreme Court's Order dated 28.08.12.

% 28.60

Shortfall % due to less AT&C Losses during 2009-10 % (1.38) Shortfall in minimum reduction of AT&C losses during 2008-09 in Millions Units = 1.38 % of 978.86 MU MU 13.51

Average aggregate Unit Rate for sale of power during 2009-10 Rs./Unit 3.69 Penalty for AT&C Losses non-achievement 2009-10 Rs. Crs 4.98

Other Income

33. It is submitted that this Hon’ble Commission had provisionally assessed vide Order dated

5.8.2010, the “Other Income”, which includes Delayed Payment Surcharge, at Rs.22.67 Crores.

As per the Audited Accounts 2009-10, other income was Rs 58.50 crore. However, due to

revision in bills of industrial HT & EHT consumers, Delayed Payment Surcharge has also

reduced from Rs 48.59 crore by Rs 15.56 crore to Rs 33.03 crore. Therefore, the MePDCL

humbly prays before the Hon’ble Commission to kindly reduce Other Income from Rs 58.50

crore by Rs 15.56 crore to Rs 42.93 crore, as shown below :

Table 16 Calculation of Penalty/ (Incentive) for AT&C Losses for FY 2009-10

Sl. No. PARTICULARS

Provisionally assessed by MSERC vide Order dated 5.8.2010

FY 2009-10

(Audited)

Truing up after implementation of Hon'ble Supreme Court's Order dated 28.8.12,vide this petition

1 Interest on Staff Loans and Advances

226700000 108907 108907

2 Income from Investment 53211511 53211511 3 Interest on Loans and

Page 18: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

Advances to licensee

4 Delayed payment charges from consumers 485921283 330306162

5 Discount/Rebates from suppliers/contractors 31455996 31455996

6 Interest from Bank (other than fixed deposit) 277208 277208

7 Income from Trading 3123628 3123628

8 Income from staff welfare activities

9 Miscellaneous Receipts 10912332 10912332 10 Total 226700000 585010865 429395744

Aggregate Revenue Requirement and Revenue Gap/Surplus for FY 2009-10

34. It is submitted that due to changes in Revenue from Sale of Power, AT&C losses and Other

Income, the Annual Revenue Requirement for FY 2009-10 will also change. The table below

summarizes the Revised Aggregate Revenue Requirement and Revenue Gap/Surplus for FY

2009-10.

Table 17: Aggregate Revenue requirement and Revenue Gap/Surplus for FY 2009-10

Particulars

FY 2009-10 Provisionally

assessed by MSERC vide

Order dated 5.8.2010

(Actual) Deviation

Power Purchase Cost including Transmission Charges 223.74 223.91 0.17 Repair & Maintenance Expenses 20.26 20.09 (0.17) Employee Expenses 111.03 114.92 3.89 Administration & General Expenses 8.71 10.01 1.30 Depreciation 17.08 25.94 8.86 Interest & Finance Charges 72.70 83.49 10.79

Other Debits (Incl Provisions for Bad Debts) 10.00 14.24 4.24

Income Tax 4.94 - (4.94) Prior Period Charges /(Credits) 102.51 102.51 Revenue Expenditure 468.46 595.10 126.64 Less: Expenses Capitalised Interest & Finance Charges Capitalised 58.65 63.85 5.20 Employee Expenses Capitalised 9.31 9.98 0.67 Administration & General Expenses Capitalised 0.13 0.13 Net Revenue Expenditure 400.50 521.15 120.65 Return on Equity Capital 28.28 28.28 -

Page 19: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

Aggregate Revenue Requirement 428.78 549.43 120.65 Less: Non Tariff Income Other Income 22.67 42.94 20.27 R.E.Subsidy 13.68 12.31 (1.37) Fiscal Loss for failure to cause 3% reduction of AT&C loss 55.27 4.98 (50.29) Net Aggregate Revenue Requirement 337.16 489.20 152.04 Revenue from Sale of Power 399.56 361.17 (38.39) Net Gap/ (Surplus) (62.40) 128.03 190.43

Prayer

In view of new facts, circumstances and submissions made in this petition, the Petitioner prays that

this Hon’ble Commission may be pleased to consider the submissions made in this petition and :

(a) Approve the ARR of Rs 489.20 Crores against the provisionally assessed vide Order dated

5.8.2010 of Rs 337.16 Crores.

(b) Approve the revised Revenue of Rs 361.167 Crores against provisionally assessed vide Order

dated 5.8.2010 at Rs 399.57 Crores.

(c) Allow the deficit of Rs 128.03 crores for FY 2009-10 to be adjusted in the subsequent year.

(d) Allow that the tariff for other categories other than IHT and IEHT may be adjusted in

subsequent tariff orders.

(e) Pass such orders, as Hon’ble Commission may deem fit and proper and necessary in view of

the facts and circumstances of the case.

(f) Condone any inadvertent omissions, errors & shortcomings and permit the applicant to

add/change/modify/alter this filing and make further submissions as required.

Petitioner

S.B. Umdor

Superintending Engineer (R-O)

For & on behalf of Meghalaya Power Distribution Corporation Limited

Page 20: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 21: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 22: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 23: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 24: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 25: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 26: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 27: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 28: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 29: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 30: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 31: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 32: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 33: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 34: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 35: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 36: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 37: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 38: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 39: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 40: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 41: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 42: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 43: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 44: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 45: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 46: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 47: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 48: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 49: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 50: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 51: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 52: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 53: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 54: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 55: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 56: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 57: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 58: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 59: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 60: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 61: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 62: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 63: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 64: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 65: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 66: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 67: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 68: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 69: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 70: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 71: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 72: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 73: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 74: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 75: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 76: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 77: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 78: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 79: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 80: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 81: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 82: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 83: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 84: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 85: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 86: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 87: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 88: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 89: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 90: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 91: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 92: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 93: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 94: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 95: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 96: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 97: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 98: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 99: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 100: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 101: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 102: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 103: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 104: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 105: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 106: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 107: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 108: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 109: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 110: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 111: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 112: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 113: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 114: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 115: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 116: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 117: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 118: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 119: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 120: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 121: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 122: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 123: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 124: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 125: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 126: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 127: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 128: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 129: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 130: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 131: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 132: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

ITEM NO.4 COURT NO.12 SECTION XVII

S U P R E M E C O U R T O F I N D I A

RECORD OF PROCEEDINGS

CIVIL APPEAL NOS. 1237-1238 OF 2011

BYRNIHAT INDUSTRIES ASSN. Appellant(s)

VERSUS

MEGHALAYA STATE ELCT.REG.COMMN. & ANR. Respondent(s)

(With appln(s) for stay and office report)

(FOR FINAL DISPOSAL)

Date: 28/08/2012 These Appeals were called on for hearing today.

CORAM :

HON'BLE MR. JUSTICE SURINDER SINGH NIJJAR

HON'BLE MR. JUSTICE H.L. GOKHALE

For Appellant(s) Mr. C.A. Sundaram,Sr.Adv.

Mr. M.G. Ramachandran,Adv.

Mr. K.V. Mohan,Adv.

Mr. Anand K. Ganesan,Adv.

Ms. Swapna Sheshadri,Adv.

For Respondent(s) Mr. P.S. Narsimha,Sr.Adv.

Mr. Vishal Anand,Adv.

Mr. Pukhrambam Ramesh Kumar,Adv.

Mr. A.V. Rangam,Adv.

UPON hearing counsel the Court made the following

O R D E R

The appeals are dismissed as having become infructuous in terms of the signed order.

(A.S. BISHT) (INDU BALA KAPUR)

COURT MASTER COURT MASTER

(Signed order is placed on the file)

Page 133: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NOS. 1237-1238 OF 2011

BYRNIHAT INDUSTRIES ASSOCIATION Appellant(s)

VERSUS

MEGHALAYA STATE ELCTRICITY REGULATORY COMMISSION

AND ANR. Respondent(s)

O R D E R

By order dated 10.9.2009 passed by the Meghalaya State Electricity Regulatory Commission, the unit rates of demand charges/energy charges were revised and fixed in the manner specified in Column (3) of Table VII attached with the aforesaid order. The said orders states that these rates shall be deemed to have come into effect from 1st October, 2008 and shall remain valid till the Tariff (D) is next revised by the Commission. On the basis of the tariff now fixed by the Commission, the amount due from the appellants was Rs.358.31 crores for the fiscal year 2008-09. The appellants had actually paid Rs.371 crores although the original claim by the respondents was Rs.465.73 crores.

In our considered opinion, since the final amount due has been fixed at Rs.358.31 crores, the present appeals have been rendered infructuous. The appeals are accordingly dismissed as having become infructuous.

However, any surplus amount which may have accrued to the appellants shall be adjusted against the future bills in accordance with law.

.....................J

(SURINDER SINGH NIJJAR)

.....................J

(H.L. GOKHALE)

New Delhi;

August 28, 2012.

Page 134: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 135: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

ANNEXURE VI

Difference in average rate against each category between Tariff Order Dated 30.09.2008 and Tariff Order dated 10.09.2009.

LT Category Sale in

MU

Rate as per Tariff Order Dated 30.09.2008 Rate as per Tariff Order Dated 10.09.2009

Difference of Average

Rate Connected Load (KW)

Demand Charge (Rs per

KW)

Total Demand Amount

Slab of Units Rates

(paisa per unit)

Amount in each

slab (Lakhs)

Total Revenue (Rs. In Cr)

Average rate (Rs per unit)

Demand Charge (Rs per

KW)

Total Demand Amount

Rates (paisa

per unit)

Amount in each

slab (Lakhs)

Total Revenue (Rs. In Cr)

Average rate (Rs per unit)

Domestic (DLT) 192.11 218307 25 654.92

First 100 Units 235 2528.13

58.83 3.06 25 654.92

225 2420

56.29 2.93 0.13 Next 100 Units 275 1426.42 264 1369

Above 200 Units 390 1273.74 363 1185

Commercial (CLT) 30.63 42910 70 360.44

First 100 Units 400 428.80

17.58 5.74 70 360.44

400 429

17.57 5.74 0.00 Next 100 Units 475 509.20 475 509

Above 200 Units 500 459.50 500 459

Industrial(ILT) 4.68 10771 100 129.25

First 500 Units 400 18.80

3.57 7.63 100 129.25

400 19

3.56 7.61 0.02 Next 500 Units 480 33.60 478 33

Above 1000 Units 500 175.50 500 175

Public Lighting (PL) 1.49 323 70 2.71 All Units 500 74.50 0.77 5.18 70 2.71 490 73 0.76 5.08 0.10 Public Water Supply (WSLT)

6.43 4206 60 30.28 All Units 390 250.77 2.81 4.37 60 30.28 400 257 2.87 4.47 -0.10

Agriculture (AP) 0.61 476 30 1.71 All Units 150 9.15 0.11 1.78 30 1.71 132 8 0.10 1.59 0.18

General Purpose (GP)

8.95 8911 50 53.47

First 100 Units 440 86.68

4.87 5.44 50 53.47

440 87

4.86 5.44 0.00 Next 100 Units 475 93.57 475 93

Above 200 Units 505 253.00 505 253

Kutir Jyoti metered (KJ)

2.70

Rs. 50/-

15.39 0.15 0.56

Rs. 50/-

15.39 0.15 0.56 0.00 Kutir Jyoti unmetered (KJ)

Rs. 60/- Rs. 60/-

Office employees 45.00 10 45.00 0.45 0.100 44 44 0.44 0.098 0.002

HT Category Contract Demand

(KVA)

Rate (Rs per Kva)

Rate (Rs per Kva)

Domestic HT

79.16 61909 300 1671.55 All Units 300 2374.8 40.46 5.11 225 1253 225 1781 30.34 3.83 1.28 Public Service (Bulk supply)

Commercial (CHT) 6.15 6492 280 163.60 All Units 350 215.25 3.79 6.16 242 141 286 176 3.17 5.15 1.01 Public Water Works (WSHT)

19.52 7458 170 114.12 All Units 280 546.56 6.61 3.38 170 114 280 546 6.60 3.38 0.00

Page 136: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition

ANNEXURE VII

Actual Sale in MU and amount (Rs) for the period from April 2009 to December 2009

Sl. No. LT Category

Difference of Average

Rate (Rs per unit)

Actual Sale in MU for the period from April

2009 to December 2009

Amount (Rs in crore)

1 Domestic (DLT) 0.13 149.61 1.94

2 Commercial (CLT) 0.00 28.71 0.00

3 Industrial(ILT) 0.02 4.16 0.01

4 Public Lighting (PL) 0.10 1.12 0.01

5 Public Water Supply (WSLT) -0.10 4.67 -0.05

6 Agriculture (AP) 0.18 0.44 0.01

7 General Purpose (GP) 0.00 8.15 0.00

8 Kutir Jyoti metered (KJ) 0.00 3.56 0.00

9 Office employees 0.002 27.59 0.01

HT Category

1 Domestic HT 1.28 12.95 1.66

2 Public Service (Bulk supply) 1.28 41.93 5.37

3 Commercial (CHT) 1.01 8.65 0.87

4 Public Water Works (WSHT) 0.00 18.54 0.00

Page 137: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 138: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 139: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 140: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 141: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 142: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 143: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 144: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 145: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 146: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition
Page 147: APPROVAL OF FINAL TRUED-UP ANNUAL REVENUE …meecl.nic.in/tariffs/MePDCL/True_up_Petitions... · before the hon’ble meghalaya state electricity regulatory commission, shillong petition