Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
APPLICATION FOR WORKS APPROVAL
Limestone Crushing and Screening Premises Lot 8 Wattle Avenue, Nowergup
Prepared by:
RPS
38 Station Street, SUBIACO WA 6008
PO Box 465, SUBIACO WA 6904
T: 618 9211 1111
F: 618 9211 1122
W: www.rpsgroup.com.au
Report No: 3780
Version/Date: FinalA
Prepared for:
URBAN RESOURCES PTY LTD
Unit 4, 127 Melville Parade, COMO WA 6152
RPS Environment and Planning Pty Ltd (ABN 45 108 680 977)
Limestone Crushing and Screening Premises, Lot 8 Wattle Ave Nowergup
3780, FinalA DOCUMENT STATUS / DISCLAIMER
Document Status
Version Purpose of Document Orig Review Review Date
Format Review
RPS Release Approval
Issue Date
Draft A Draft for Client Review SV Client 18.05.11
FinalA Final for Issue SV MZ 24.05.11 25.05.11 25.05.11 25.05.11
Disclaimer
This document is and shall remain the property of RPS. The document may only be used for the purposes for which it was
commissioned and in accordance with the Terms of Engagement for the commission. Unauthorised copying or use of this
document in any form whatsoever is prohibited.
Limestone Crushing and Screening Premises, Lot 8 Wattle Ave Nowergup
3780, FinalA Page 1
TABLE OF CONTENTS Page
1.0 INTRODUCTION ....................................................................................... 2
2.0 SUBJECT SITE ............................................................................................. 3
2.1 Location and Ownership ....................................................................................... 3
2.2 Current Approvals ................................................................................................. 3
2.3 Surrounding Land Uses and Sensitive Receptors ............................................... 3
3.0 DESCRIPTION OF PROPOSED PREMISES ............................................ 4
3.1 Machinery/Equipment ........................................................................................... 4
3.2 Throughput Volumes ............................................................................................ 4
3.3 Prescribed Categories ........................................................................................... 5
3.4 Hours of Operation ............................................................................................... 5
4.0 IDENTIFICATION AND MANAGEMENT OF POTENTIAL
ENVIRONMENTAL IMPACTS .................................................................. 6
4.1 Noise ....................................................................................................................... 6
4.2 Dust ......................................................................................................................... 6
5.0 CONCLUSION ............................................................................................ 8
APPENDICES
APPENDIX 1 Certificate of Title
APPENDIX 2 Proof of Lease Arrangement
APPENDIX 3 Current Planning and Environmental Approvals
APPENDIX 4 Equipment Diagram
APPENDIX 5 Noise Impact Assessment
APPENDIX 6 Dust Management Plan and Incident Report Form
Limestone Crushing and Screening Premises, Lot 8 Wattle Ave Nowergup
3780, FinalA Page 2
1.0 INTRODUCTION
On behalf of our client, Urban Resources Pty Ltd, RPS is seeking a Works Approval from the
Department of Environment and Conservation for a limestone crushing and screening premises
on Lot 8 Wattle Avenue, Nowergup. This application is submitted further to an Application
Enquiry lodged with the DEC in February 2011 and a subsequent Scoping Meeting held with DEC
Officers at their Booragoon Office on 21 March 2011.
City of Wanneroo and WA Planning Commission planning approvals, along with a local Extractive
Industries Licence, have previously been obtained for the site, and our client has been advised that
a works approval is now required for the proposed crushing and screening operation. The
proposed operation is understood to fall within Category 12 of Prescribed Premises Schedule 1 of
the Environmental Protection Regulations 1987.
The following report provides information on the following matters in support of the works
approval application (as requested by DEC officers at the recent Scoping Meeting):
A description of the site, its location, ownership and operational arrangements.
Background information on previously obtained approvals and licences.
A description of the proposed premises, including equipment details, throughput volumes,
hours of operation, and potential environmental impacts.
Management measures in place to minimise/mitigate any potential off-site impacts.
Limestone Crushing and Screening Premises, Lot 8 Wattle Ave Nowergup
3780, FinalA Page 3
2.0 SUBJECT SITE
2.1 Location and Ownership
The location of the proposed crushing and screening premises is within the current DEC clearing
permit area of Lot 8 (No. 259) Wattle Ave, Nowergup (refer Figure 1 over the page). The
proposed premises location comprises an active quarry area of approximately 10ha located in the
northernmost section of Lot 8 Wattle Avenue. This application does not apply to any other part
of Lot 8 Wattle Avenue, which is subject to separate environmental (clearing) approvals prior to
any additional quarrying activity.
The subject land is a portion of the land formally described Lot 8 on Diagram 53380, depicted on
Volume 2132, Folio 850 – a Certificate of Title is provided at Appendix 1. Urban Resources Pty
Ltd are the operator of the existing quarry operation under lease agreement with the landowner,
Oakford Land Company Pty Ltd. Proof of the lease arrangement is provided at Appendix 2.
Urban Resources Pty Ltd is a privately owned, local business. The company commenced trading
in August 2006 and its main business is the mining of sand and limestone for use in the Perth
metropolitan construction industry. Their products service a range of companies from large
entities to distributors to the home building industry for sand products. Filling sand is also
supplied to contracting companies in residential developments or directly to developers. Stephen
Elliot is the sole director of Urban Resources.
2.2 Current Approvals
City of Wanneroo and WA Planning Commission planning approvals, a DEC Clearing Permit and
a local Extractive Industries Licence have previously been obtained for the site (with the
Extractive Industries Licence currently in the process of being renewed by the City of
Wanneroo). The mobile equipment to be used for crushing and screening operations has
previously been granted an Environmental Protection Act 1986 Licence valid to August 2012.
Copies of all relevant documentation/approvals are provided at Appendix 3.
2.3 Surrounding Land Uses and Sensitive Receptors
Lot 8 Wattle Avenue is bounded to the west by market garden and quarry activities, to the south
by zoned but vacant MRS Industrial land (immediately across Wattle Avenue), to the east by
quarrying and portions of a Bush Forever site and to the north east by an existing Water
Corporation reserve that will contain a water storage tank in the future. There are many other
existing and exhausted limestone quarries in the vicinity. A bush forever site is located in the
south eastern corner of Lot 8 Wattle Avenue (approximately 500-600m away).
The closest sensitive receptor (i.e. a land use that is potentially sensitive to the operation of
prescribed premises such as a quarry) is a residential dwelling located at Lot 2 Wattle
Avenue/Dayrell Road, approximately 650-700m directly west of the quarry site (refer Figure 1).
Another residential dwelling is also located on Lot 2, approximately 700-750m to the south west
of the quarry site. It is important to note, however, that these dwellings are only 450m and 150m
away (respectively) from an existing limestone quarry located within Lot 2, which is much closer
than the quarry on Lot 8.
21
1
5
4
23
22
121
6
2 5204
10
8
7
0
NO
RT
H
not permitted. Please contact the author.
Unauthorised reproduction or amendment
+61 8 9211 1111
+61 8 9211 1122
Subiaco WA 6008
38 Station Street
ACN 108 680 977
ABN 45 108 680 977
T
F
W
RPS Environment and Planning Pty Ltd
rpsgroup.com.au
' COPYRIGHT PROTECTS THIS PLAN
PO Box 465 Subiaco WA 6904
Subject Site
CHECKED
DRAWN
PLANNER
REVISION
PLAN No
DATE
SCALE
CLIENT
:
:
:
:
:
:
:
:
LEGEND
WATTLE
ROAD
AVENUE
DAYRELL
50 100 150 200 250m
only and are subject to detailed engineering design.
All carriageways are shown for illustrative purposes
Areas and dimensions shown are subject to final survey calculations.
Accuracy +/- 4m. Projection MGA Zone 50.
Aerial Photography dated January 2010.
Base data supplied by Landgate.
PROPOSED PREMISES LOCATION
Lot 8 Wattle Avenue, NOWERGUP
FI
GU
RE 1
-
L.W.
S.V.
-
3780-5-001.dgn
17 May 2011
1:5,000@A3
Urban Resources Pty. Ltd.
Location of Proposed Premises
Closest sensitive receptors
Closest sensitive receptors
Limestone Crushing and Screening Premises, Lot 8 Wattle Ave Nowergup
3780, FinalA Page 4
3.0 DESCRIPTION OF PROPOSED PREMISES
3.1 Machinery/Equipment
The proposed works approval is for the operation of a crushing and screening plant for limestone
products including, but not limited to, 75mm road base, 25mm, 19mm, 14mm aggregate and -
5mm aglime. The crushing and screening process is generally described as follows:
Limestone raw feed (excavated from the quarry site) is fed into the feed hopper of the
jaw crusher.
The resulting product fed to the screening plant where oversize materials are recycled
through the Pegson impact crusher, then fed back over the screening plant.
This product is then stockpiled via the conveyor and further manual stockpiling is carried
out by the second front end loader.
All material fed into the process is eventually ground to the required size, therefore no
waste material is generated by the process.
In simple terms, process inputs comprise of limestone raw feed, with process outputs being
crushed limestone products of variable size/grain.
The plant is track mounted and portable, and it is envisaged that it will work at a range of sites
within and around the Perth metropolitan area (with the appropriate works approvals/licences
where required). The plant consists of the following items:
Striker JM11-80 Jaw Crusher.
Pegson 428 Impact Crusher.
Finlay 694 Screening Plant.
Striker 18M stockpiling conveyor.
The plants are all diesel driven but are fuelled by way of a mobile tanker (mini tankers) so there is
no fuel stored on site. A diagram illustrating the general arrangement of the plant equipment is
provided at Appendix 4.
No water license/bore is required for the crushing and screening works. The only water required
on site is delivered via water carts (and other bores in the area by agreement if required) for dust
suppression purposes – this is already being carried out as part of existing quarry operations.
3.2 Throughput Volumes
The plant has a throughput rate of 100 and 250 tonnes per hour depending on the fineness of the
product being made, and therefore likely to exceed 50,000 tonnes per annum.
As previously noted, the plant is mobile and is utilised elsewhere when not being used at Wattle
Avenue (subject to DEC Works Approvals where required). It is expected that the plant will be
Limestone Crushing and Screening Premises, Lot 8 Wattle Ave Nowergup
3780, FinalA Page 5
on site for around the 162 days (approximately 60%) of the year. This will be mainly April
through to November as the operator has other commitments with the machinery in the summer
months.
Table 1: Crushing and Screening Throughputs for Lot 8 Wattle Avenue Limestone Quarry
Product Throughput
(Tonnes/hr)
Estimated Volume
(Tonnes)
Period on Site
(in days)
75 mm Limestone 250 70,000 35
20mm limestone 175 80,000 57
Ag Lime 90 50,000 69
TOTAL
200,000 162
3.3 Prescribed Categories
Given the anticipated throughput rates as outlined above, it is understood that the proposed
limestone crushing and screening premises falls within Category 12 of Prescribed Premises
Schedule 1 of the Environmental Protection Regulations 1987. On this basis, and as confirmed at
the recent Scoping Meeting, a DEC works approval is therefore required for the premises.
3.4 Hours of Operation
Quarry operations are limited by condition of the City of Wanneroo Extractive Industries Licence
to the following hours:
06:30 – 18:00 Monday to Friday (except Public Holidays).
07:00 – 17:00 Saturday.
No work permitted on Sunday or Public Holidays.
Given the ancillary nature of the proposed premises, and accounting for operational start up and
shut down times, the proposed limestone crushing and screening premises will be limited to a
smaller operating window than the quarry itself.
Limestone Crushing and Screening Premises, Lot 8 Wattle Ave Nowergup
3780, FinalA Page 6
4.0 IDENTIFICATION AND MANAGEMENT OF POTENTIAL
ENVIRONMENTAL IMPACTS
If not adequately managed, dust and noise have the potential to impact on sensitive environmental
and social receptors, including nearby residents. There are no other potential off-site
environmental impacts associated with the proposed premises.
It is also important to note that the crushing and screening premises are incidental to the
approved quarry operation, which is subject to detailed consideration of all operational quarry
matters and potential impacts (including noise and dust). Public consultation was also carried out
as part of local approvals processes. A detailed site management plan is in place for the quarry
site, and sets out a range of management actions to mitigate environmental impacts.
The following provides a summary of potential environmental impacts associated with the
proposed premises and proposed management measures to be implemented.
4.1 Noise
Site noise associated with the existing quarry operation is actively managed in accordance with
the approved Excavation and Rehabilitation Management Plan for the site, primarily by way of
maintaining adequate buffers, screens and the location of noise generating equipment on the pit
floor below natural ground level (once at suitable depth). All machinery is to be maintained in
good condition with efficient mufflers and noise shielding.
With regard to the proposed limestone crushing and screening premises, specialist acoustic
consultants were engaged (as recommended by DEC officers in the recent Scoping Meeting) to
assess premises noise levels against the prescribed standards of the Environmental Protection (Noise)
Regulations 1997. The full Noise Impact Assessment report is provided at Appendix 5, and
concludes that compliance with the daytime LA10 assigned noise level under the regulations is
achieved at all nearby residential receivers.
4.2 Dust
Dust generation is a potential effect of limestone quarrying and crushing/screening operations, and
if left unmanaged can create significant nuisance problems for local residents and businesses. Both
the site owner and operator are aware of the need to control and minimise dust emissions, and
are committed to pro-active and ongoing management actions to minimise any potential
disturbances.
Site operations are being carried out in accordance with a comprehensive dust management
regime as approved by the City of Wanneroo as part of the local planning and licensing process
(refer Appendix 6). Dust is primarily controlled by way of site watering and the application of
hydromulch and gluon to stabilise exposed areas. Access roads are also treated with Dustex to
minimise dust generated by vehicle/machinery movements.
The quarry operator has set up a register of dust complaints (see attached Dust Incident Form
included in Appendix 6) and has actively responded to (and addressed) previous complaints
directed through the City of Wanneroo. The register is kept at the operator’s main office rather
Limestone Crushing and Screening Premises, Lot 8 Wattle Ave Nowergup
3780, FinalA Page 7
than on-site given that complaints have previously been received by phone and email, rather than
directly to operators on site.
Following the receipt of dust complaints in January/February 2011, the following dust management
regime has been imposed, in addition to those actions already committed to in the Site
Rehabilitation and Management Plan:
a) All open areas of the site have been either hydromulched or treated with gluon to
stabilize the unworked areas of the site.
b) The unsealed access road has been extensively treated with Dustex and all watering of
the road now contains supplementary amounts of Dustex to keep the roads from creating
further dust.
c) The gluon is reapplied on a regular basis to stockpiles during the summer months to
prevent a reoccurrence of the previous complaints.
d) The working faces are being sprayed with water prior to crushing or screening to
minimize dust from the actual mining process.
e) Dust control has been reinforced as a priority with the operators and work will cease if
the actual operation is causing dust (consistent with the dust management actions set out
in the Site Management Plan). Watering of the road access and open areas has also been
prioritized with the operator and supervisor.
f) It is anticipated that by the end of the 2012 all operations and major stockpiles will be
located on the quarry floor (progressively being mined) rather than as now stockpiled on
the top of the site. It is not possible to do this until the quarry is sufficiently established.
g) The site operator has also endeavored to get the adjoining landowner to contact them
directly if there are dust issues, as this will help to speed up the response time to any
problems. However, at this stage it appears that the adjoining landowner prefers to send
complaints via the Shire, which often results in a delay before the operator is contacted.
The site operator has, however, responded actively to those complaints received and
believes the situation is now under control.
h) The site is being actively monitored for any signs of dust nuisance since these additional
actions have been taken.
i) There have been no complaints since the introduction of these measures.
This dust management regime will continue to be enforced and actively monitored throughout the
operation of the limestone crushing and screening premises. Furthermore, as previously noted,
the crushing and screening equipment will only be located on site between the months of April
and November, as the operator has other commitments with the machinery in the summer
months. Given the location of the nearest sensitive receptors to the west/southwest of the site,
and that easterly breezes are generally limited to summer months, it is unlikely that any additional
dust issues will be created by the proposed crushing and screening premises.
Limestone Crushing and Screening Premises, Lot 8 Wattle Ave Nowergup
3780, FinalA Page 8
5.0 CONCLUSION
This report has been submitted on behalf of our client, Urban Resources Pty Ltd, in support of an
application for a DEC Works Approval for a limestone crushing and screening premises at Lot 8
Wattle Avenue, Nowergup. It provides detailed information on the proposed premises and
potential environmental impacts, along with details of management actions to minimise any
potential disturbance to local sensitive receptors.
The proposed crushing and screening operation is ancillary to the existing quarry operation
already present on site, and it has been demonstrated to present no significant additional risk to
the locality in terms of potential noise and dust generation impacts. In light of these findings, it is
respectfully requested that the DEC grant a Works Approval for the premises at the earliest
opportunity.
rp 3780 works approval application 260511
APPENDIX 1
Certificate of Title
APPENDIX 2
Proof of Lease Arrangement
APPENDIX 3
Current Planning and
Environmental Approvals
APPENDIX 4
Equipment Diagram
APPENDIX 5
Noise Impact Assessment
Noise Impact Assessment
Prepared For
Urban Resources Pty Ltd
May 2011
Reference: 11041826-01b
Lot 8 Wattle Avenue, Nowergup Limestone Crushing Operations
GEORGE
LLOYD
Acoustics
Report: 11041826-01b
Lloyd George Acoustics Pty Ltd ABN: 79 125 812 544
PO Box 717 Hillarys WA 6923
Offices: Ocean Reef Padbury Scarborough Waterford
Phone: Fax:
Email: Mobile:
9300 4188 9300 4199 [email protected]
0439 032 844
9401 7770 9401 7770 [email protected]
0400 414 197
9245 3223 9300 4199 [email protected]
0438 201 071
9313 3655 9300 4199 [email protected]
0427 388 876
Member of the Association of Australian Acoustical Consultants – (AAAC)
Approved for Issue: Rebecca Donovan
Position: Project Director
Verified Terry George
Date: 26 May 2011
This report has been prepared in accordance with the scope of services described in the contract or agreement between Lloyd George Acoustics Pty Ltd and the Client. The report relies upon data, surveys, measurements and results taken at or under the particular times and conditions specified herein. Any findings, conclusions or recommendations only apply to the aforementioned
circumstances and no greater reliance should be assumed or drawn by the Client. Furthermore, the report has been prepared solely for use by the Client, and Lloyd George Acoustics Pty Ltd accepts no responsibility for its use by other parties.
Lloyd George Acoustics
CONTENTS
1 INTRODUCTION ................................................................................................................ 1
2 CRITERIA ........................................................................................................................... 2
3 METHODOLOGY ............................................................................................................... 3
3.1 Site Measurements ..................................................................................................... 3
3.2 Noise Modelling ........................................................................................................... 3
3.2.1 Meteorological Information .................................................................................. 4
3.2.2 Topographical Data.............................................................................................. 4
3.2.3 Ground Absorption ............................................................................................... 4
3.2.4 Source Sound Levels ........................................................................................... 5
3.2.5 Modelling Scenario .............................................................................................. 5
4 RESULTS ........................................................................................................................... 5
5 DISCUSSION...................................................................................................................... 7
6 CONCLUSION .................................................................................................................... 8
APPENDICES
A Terminology
Lloyd George Acoustics
Reference: 11041826-01b Page 1
1 INTRODUCTION
RPS on behalf of Urban Resources Pty Ltd commissioned Lloyd George Acoustics to complete a noise impact assessment of a proposed quarry site located at Lot 8 Wattle Avenue, Nowergup. The site is located approximately 700m to the nearest residential premises. The City of Wanneroo have requested that this assessment be conducted in accordance with the Environmental Protection (Noise) Regulations 1997, to determine if the activities are compliant during all hours of operation. The site locality and surrounding premises are shown in Figure 1.1.
Figure 1.1: Site Locality and Surroundings
Plant to be used on the site is relatively new and well maintained, and comprises:
Striker Jaw Crusher;
Pegson 428 Impact Crusher;
Finlay Screening Plant; and
Striker Stockpiling Conveyor.
The general site operation is as follows:
Raw limestone is fed into the jaw crusher;
The product is then fed into the screening plant where any oversized material is recycled through the Pegson impact crusher, then re-fed into the screening plant.
R1
R2
R3
R4
R5
R6
Assumed Plant Location
Lloyd George Acoustics
Reference: 11041826-01b Page 2
The product is then stockpiled via the conveyor and further manual stockpiling occurs.
The hours of operation have been assumed to be 7.00am to 6:00pm Monday to Saturday. It is understood that quarrying has already commenced on the site. The purpose of this report is to assess the impact of the crushing and screening plant only.
Appendix A contains a description of some of the terminology used throughout this report.
2 CRITERIA
Environmental noise in Western Australia is governed by the Environmental Protection Act 1986, through the Environmental Protection (Noise) Regulations 1997 (the Regulations).
Regulation 7 defines the prescribed standard for noise emissions as follows:
“7. (1) Noise emitted from any premises or public place when received at other premises –
(a) Must not cause or significantly contribute to, a level of noise which exceeds the assigned level in respect of noise received at premises of that kind; and
(b) Must be free of –
i. Tonality;
ii. Impulsiveness; and
iii. Modulation”.
A “…noise emission is taken to significantly contribute to a level of noise if the noise emission exceeds a value which is 5dB below the assigned level…”
Tonality, impulsiveness and modulation are defined in Regulation 9. Noise is to be taken to be free of these characteristics if:
(a) The characteristics cannot be reasonably and practicably removed by techniques other than attenuating the overall level of noise emission; and
(b) The noise emission complies with the standard after the adjustments of Table 2.1 are made to the noise emission as measured at the point of reception.
Table 2.1 – Adjustments For Intrusive Characteristics
Tonality Modulation Impulsiveness
+ 5dB + 5dB + 10dB
Note: The above are cumulative to a maximum of 15dB.
The assigned levels including the influencing factor (prescribed standards) are specified in Regulation 8 and are shown below in Table 2.2. Six assessment locations have been
Lloyd George Acoustics
Reference: 11041826-01b Page 3
selected as shown on Figure 1.1. The influencing factor has been determined to be zero at all six nearby residences.
Table 2.2 –Assigned Noise Levels
Premises Receiving Noise Time Of Day
Assigned Level (dB)
LA10 LA1 LAmax
Noise Sensitive
0700 to 1900 hours Monday to Saturday (Day) 45 55 65
0900 to 1900 hours Sunday and public holidays (Sunday) 40 50 65
1900 to 2200 hours all days (Evening) 40 50 55
2200 hours on any day to 0700 hours Monday to Saturday and 0900 hours Sunday and public holidays (Night)
35 45 55
3 METHODOLOGY
3.1 Site Measurements Under the Regulations, there are certain requirements that must be satisfied when undertaking measurements and are defined in Regulations 19, 20, 22 and 23 and Schedule 4. In undertaking the measurements, these have been satisfied, specifically noting the following:
The sound level meter used was a Rion NA 28 (S/N: 01270693), which holds current laboratory certificates of calibration available upon request and was field calibrated before and after the measurements and found to be within +/- 0.5 dB. This meter simultaneously records the slow and fast time weighted sound levels allowing relevant data to be collected. The microphone was fitted with a standard wind screen with winds being less than 5m/s;
The microphone was at least 1.2 metres above ground level and at least 3.0 metres from reflecting facades (other than the ground plane) and as such no adjustments have been applied for reflected noise;
Measurements of individual sources were recorded on 27 April 2011 between 12pm and 2pm.
3.2 Noise Modelling To determine the noise emissions from the subject site, the computer modelling programme SoundPlan 7.0 has been utilised. The programme was selected to use the CONCAWE algorithms, which requires the following input data:
Lloyd George Acoustics
Reference: 11041826-01b Page 4
Meteorological Information;
Topographical data;
Ground Absorption; and
Source sound power levels.
3.2.1 Meteorological Information
Meteorological information utilised is based on that specified in EPA Guidance for the Assessment of Environmental Factors No.8 Environmental Noise draft, and are shown below in Table 3.1.
Table 3.1 –Modelling Meteorological Conditions
Parameter Day (0700-1900)
Temperature (oC) 20
Humidity (%) 50
Wind Speed (m/s) 4
Wind Direction All & Prevailing
Pasquil Stability Factor E
Note that the above conditions approximate the typical worst-case for enhancement of sound propagation. The EPA policy is that compliance with the assigned noise levels needs to be demonstrated for 98% of the time, during the day and night periods, for the month of the year in which the worst-case weather conditions prevail. In most cases, the above conditions occur for more than 2% of the time and therefore must be satisfied.
At wind speeds greater than those shown above, sound propagation may be further enhanced, however background noise from the wind itself and from local vegetation is likely to be elevated and dominate the ambient noise levels.
3.2.2 Topographical Data
Topographical data was provided by RPS and is at 5-metre intervals.
3.2.3 Ground Absorption
Ground absorption varies from a value of 0 to 1, with 0 being for an acoustically reflective ground (e.g. water or bitumen) and 1 for acoustically absorbent ground (e.g. grass). In this instance, a value of 0.80 has been used for the surroundings, and 0.20 has been used for the quarry.
Lloyd George Acoustics
Reference: 11041826-01b Page 5
3.2.4 Source Sound Levels
Table 3.2 shows the sound power levels used in the modelling. These have been determined based on the onsite measurements of each item of plant. The front end loader operation currently has not been considered in this assessment as it already operates on the site.
Table 3.2 – Source Sound Power Levels, dB
Description Octave Band Centre Frequency (Hz) Overall
dB(A) 63 125 250 500 1k 2k 4k 8k
Impact Crusher 112 111 115
106 108 111
104 105 107
105 104 104
102 102 102
100 99 97
97 95 91
89 87 82
112
Jaw Crusher 90 95 95
102 93 94
96 87 88
92 92 89
89 88 90
87 86 84
82 81 79
76 76 73
98
Screening Plant 89 92 92
98 92 90
90 84 84
89 90 87
87 85 85
85 85 85
84 83 81
79 76 73
97
3.2.5 Modelling Scenario
To represent a worst case scenario, the modelling has assumed that the plant is operating in the north western portion of the site, as shown on Figure 1.1. Owing to the nature of the noise associated with the plant it is considered to be present for more than 10% of the time; hence, it is the LA10 criteria that must be satisfied. The assumed noise source height is 2 metres above the ground level as provided by RPS.
4 RESULTS
The predicted noise levels, including source noise ranking and compliance with noise limit are presented in Tables 4.1 and 4.2. Two scenarios have been modelled, Scenario 1, shown in Table 4.1, predicts the noise associated with the site at the pre-quarrying ground heights. Quarrying works have already commenced on the site, therefore the pre-quarrying ground height used in the modelling has been completed to provide an absolute worst case scenario. The existing ground height is currently lower than the pre-quarrying height, but is not yet at the finished ground height. Scenario 2, shown in Table 4.2, predicts the noise at the finished ground heights based on the plans provided by RPS.
Lloyd George Acoustics
Reference: 11041826-01b Page 6
Table 4.1: Scenario 1 Predicted Noise Levels and Noise Source Ranking at Pre-Quarrying Ground Heights
Receiver Predicted
Noise Level LA10 dB
Noise Source Ranking Adjustments (Table 2.1)
Adjusted Noise Level
LA10 dB Comment
RL1 42 Impact crusher = 42 dB(A) Screening plant = 24 dB(A) Jaw crusher = 20 dB(A)
5 47 Exceeds daytime assigned level by 2 dB.
RL2 36 Impact crusher = 36 dB(A) Screening plant = 14 dB(A) Jaw crusher = 10 dB(A)
5 41 Complies with daytime assigned level.
RL3 41 Impact crusher = 41 dB(A) Screening plant = 25 dB(A) Jaw crusher = 20 dB(A)
5 46 Exceeds daytime assigned level by 1 dB.
RL4 39 Impact crusher = 39 dB(A) Screening plant = 22 dB(A) Jaw crusher = 18 dB(A)
5 44 Complies with daytime assigned level.
RL5 37 Impact crusher = 37 dB(A) Screening plant = 19 dB(A) Jaw crusher = 15 dB(A)
5 42 Complies with daytime assigned level.
RL6 38 Impact crusher = 38 dB(A) Screening plant = 20 dB(A) Jaw crusher = 16 dB(A)
5 43 Complies with daytime assigned level.
The predicted operations based on the pre-quarrying ground heights across the site may exceed the assigned noise level under worst case weather conditions by up to 2 dB at the existing residential location (RL1) to the west of the site. This 2dB exceedance is manageable by stockpiling within 20 metres of the crushing and screening area, so that the equipment is located on the east side of the stockpile.
Note that a 2 dB exceedance is considered fairly negligible given that the calculations assume downwind conditions, include all equipment operating simultaneously and include the tonality adjustment.
Lloyd George Acoustics
Reference: 11041826-01b Page 7
Table 4.2: Predicted Noise Levels and Noise Source Ranking at Finished Ground Heights
Receiver Predicted
Noise Level LA10 dB
Noise Source Ranking Adjustments (Table 2.1)
Adjusted Noise Level
LA10 dB Comment
RL1 37 Impact crusher = 37 dB(A) Screening plant = 24 dB(A) Jaw crusher = 18 dB(A)
5 42 Complies with daytime assigned level.
RL2 26 Impact crusher = 25 dB(A) Screening plant = 14 dB(A) Jaw crusher = 10 dB(A)
5 31 Complies with daytime assigned level.
RL3 29 Impact crusher = 28 dB(A) Screening plant = 14 dB(A) Jaw crusher = 13 dB(A)
5 34 Complies with daytime assigned level.
RL4 32 Impact crusher = 32 dB(A) Screening plant = 16 dB(A) Jaw crusher = 10 dB(A)
5 37 Complies with daytime assigned level.
RL5 28 Impact crusher = 27 dB(A) Screening plant = 11 dB(A) Jaw crusher = 6 dB(A)
5 33 Complies with daytime assigned level.
RL6 29 Impact crusher = 29 dB(A) Screening plant = 12 dB(A) Jaw crusher = 7 dB(A)
5 34 Complies with daytime assigned level.
5 DISCUSSION
The methodology of the modelling was such that the equipment was located toward the north western portion of the site, considered to represent a worst-case scenario. The predictions were divided into two scenarios, Scenario 1 being at the pre-quarrying ground heights, while Scenario 2 represented the finished ground heights of the proposed quarry. The results presented in Tables 4.1 and 4.2 are considered generally representative of the noise emissions from the site.
The results show that the Regulations are exceeded at two locations for Scenario 1. As discussed, the ground heights across the site are already significantly lower than the pre-quarrying heights, therefore it is considered that the exceedance of 2dB(A) is negligible, however, it is recommended that the following noise management techniques be adhered to:
Working hours to be restricted to 7.00am to 6.00pm Monday to Saturday.
Ensure roads within the site are well maintained; and
Stockpile within 20 metres of the plant facing the residents wherever practicable.
The results show that the predicted noise levels comply with the daytime assigned levels at all residential receivers at the finished ground heights.
Lloyd George Acoustics
Reference: 11041826-01b Page 8
6 CONCLUSION
The results of the noise predictions show that the crushing and screening plant complies with the daytime LA10 assigned level under the Environmental Protection (Noise) Regulations 1997 at finished ground heights.
With the inclusion of the noise management techniques, detailed in Section 4 and summarised in Section 5, compliance with the Regulations can be achieved at all ground heights.
Lloyd George Acoustics
APPENDIX A
Terminology
Lloyd George Acoustics
Reference: 11041826-01b Page A1
The following is an explanation of the terminology used throughout this report.
Decibel (dB)
The decibel is the unit that describes the sound pressure and sound power levels of a noise source. It is a logarithmic scale referenced to the threshold of hearing.
A-Weighting
An A-weighted noise level has been filtered in such a way as to represent the way in which the human ear perceives sound. This weighting reflects the fact that the human ear is not as sensitive to lower frequencies as it is to higher frequencies. An A-weighted sound level is described as LA dB.
Sound Power Level (Lw) Under normal conditions, a given sound source will radiate the same amount of energy, irrespective of its surroundings, being the sound power level. This is similar to a 1kW electric heater always radiating 1kW of heat. The sound power level of a noise source cannot be directly measured using a sound level meter but is calculated based on measured sound pressure levels at known distances. Noise modelling incorporates source sound power levels as part of the input data.
Sound Pressure Level (Lp) The sound pressure level of a noise source is dependent upon its surroundings, being influenced by distance, ground absorption, topography, meteorological conditions etc and is what the human ear actually hears. Using the electric heater analogy above, the heat will vary depending upon where the heater is located, just as the sound pressure level will vary depending on the surroundings. Noise modelling predicts the sound pressure level from the sound power levels taking into account ground absorption, barrier effects, distance etc.
LASlow This is the noise level in decibels, obtained using the A frequency weighting and the S time weighting as specified in AS1259.1-1990. Unless assessing modulation, all measurements use the slow time weighting characteristic.
LAFast This is the noise level in decibels, obtained using the A frequency weighting and the F time weighting as specified in AS1259.1-1990. This is used when assessing the presence of modulation only.
LAPeak This is the maximum reading in decibels using the A frequency weighting and P time weighting AS1259.1-1990.
LAmax An LAmax level is the maximum A-weighted noise level during a particular measurement.
LA1
An LA1 level is the A-weighted noise level which is exceeded for one percent of the measurement period and is considered to represent the average of the maximum noise levels measured.
Lloyd George Acoustics
Reference: 11041826-01b Page A2
LA10 An LA10 level is the A-weighted noise level which is exceeded for 10 percent of the measurement period and is considered to represent the “intrusive” noise level.
LAeq The equivalent steady state A-weighted sound level (“equal energy”) in decibels which, in a specified time period, contains the same acoustic energy as the time-varying level during the same period. It is considered to represent the “average” noise level.
LA90 An LA90 level is the A-weighted noise level which is exceeded for 90 percent of the measurement period and is considered to represent the “background” noise level.
One-Third-Octave Band Means a band of frequencies spanning one-third of an octave and having a centre frequency between 25 Hz and 20 000 Hz inclusive.
LAmax assigned level Means an assigned level which, measured as a LA Slow value, is not to be exceeded at any time. LA1 assigned level Means an assigned level which, measured as a LA Slow value, is not to be exceeded for more than 1% of the representative assessment period.
LA10 assigned level Means an assigned level which, measured as a LA Slow value, is not to be exceeded for more than 10% of the representative assessment period.
Tonal Noise A tonal noise source can be described as a source that has a distinctive noise emission in one or more frequencies. An example would be whining or droning. The quantitative definition of tonality is:
the presence in the noise emission of tonal characteristics where the difference between —
(a) the A-weighted sound pressure level in any one-third octave band; and
(b) the arithmetic average of the A-weighted sound pressure levels in the 2 adjacent one-third octave bands,
is greater than 3 dB when the sound pressure levels are determined as LAeq,T levels where the time period T is greater than 10% of the representative assessment period, or greater than 8 dB at any time when the sound pressure levels are determined as LA Slow levels.
This is relatively common in most noise sources.
Lloyd George Acoustics
Reference: 11041826-01b Page A3
Modulating Noise A modulating source is regular, cyclic and audible and is present for at least 10% of the measurement period. The quantitative definition of tonality is:
a variation in the emission of noise that —
(a) is more than 3 dB LA Fast or is more than 3 dB LA Fast in any one-third octave band;
(b) is present for at least 10% of the representative
Impulsive Noise An impulsive noise source has a short-term banging, clunking or explosive sound. The quantitative definition of tonality is:
a variation in the emission of a noise where the difference between LA peak and LA Max slow is more than 15 dB when determined for a single representative event;
Major Road
Is a road with an estimated average daily traffic count of more than 15,000 vehicles.
Secondary / Minor Road
Is a road with an estimated average daily traffic count of between 6,000 and 15,000 vehicles.
Influencing factor
( ) ( )
100m within roadmajor each for 6450m within roadmajor each for 2
100m within roadsecondary each for 2 dB) 6 of (maximumFactor Traffic
noise thereceiving premises theof radius 450m a within land commercial of percentage the%TypeB
noise thereceiving premises theof radius a100m within land commercial of percentage theB Type %
noise thereceiving premises theof radius 450m a within land industrial of percentage the%TypeA
noise thereceiving premises theof radius a100m withinland industrial of percentage theA Type %
:
B Type %B Type %201A Type %A Type %
101
450
100
450
100
450100450100
===+
=
=
=
=
+++=
where
Representative Assessment Period
Means a period of time not less than 15 minutes, and not exceeding four hours, determined by an inspector or authorised person to be appropriate for the assessment of a noise emission, having regard to the type and nature of the noise emission.
Lloyd George Acoustics
Reference: 11041826-01b Page A4
Background Noise Background noise or residual noise is the noise level from sources other than the source of concern. When measuring environmental noise, residual sound is often a problem. One reason is that regulations often require that the noise from different types of sources be dealt with separately. This separation, e.g. of traffic noise from industrial noise, is often difficult to accomplish in practice. Another reason is that the measurements are normally carried out outdoors. Wind-induced noise, directly on the microphone and indirectly on trees, buildings, etc., may also affect the result. The character of these noise sources can make it difficult or even impossible to carry out any corrections.
Ambient Noise Means the level of noise from all sources, including background noise from near and far and the source of interest.
Specific Noise Relates to the component of the ambient noise that is of interest. This can be referred to as the noise of concern or the noise of interest.
Satisfactory Design Sound Level The level of noise that has been found to be acceptable by most people for the environment in question and also to be not intrusive.
Maximum Design Sound Level The level of noise above which most people occupying the space start to become dissatisfied with the level of noise.
Reverberation Time Of an enclosure, for a sound of a given frequency or frequency band, the time that would be required for the reverberantly decaying sound pressure level in the enclosure to decrease by 60 decibels.
RMS The root mean square level. This is used to represent the average level of a wave form such as vibration.
Vibration Velocity Level The RMS velocity of a vibration source over a specified time period. Units are mm/s.
Peak Velocity Level of vibration velocity measured as a non root mean square (r.m.s.) quantity in millimetres per second (mm/s).
Lloyd George Acoustics
Reference: 11041826-01b Page A5
Chart of Noise Level Descriptors
Typical Noise Levels
APPENDIX 6
Dust Management Plan and
Incident Report Form
URB-Form-03-13 Issue 1 April 2011
DUST INCIDENT REPORT FORM Date:__________________ Time:_____________ Received by:________________________
Complaint Received From:
Name:_________________________________ Tel No:_______________________________
Address:_____________________________________________________________________
Area/Suburb:__________________________ Municipality:____________________________
Name of Developer/Operator:____________________________________________________
Address of Developer/Operator:__________________________________________________
Address of Development/Operation:_______________________________________________
Type of complaint (odour, dust, smoke, noise, other)__________________________________
____________________________________________________________________________
Details of Incident Received (effect/frequency)_______________________________________
____________________________________________________________________________
Referred to:____________________________ Date:__________________________________
Action Taken/Advice Given/Matter Referred to:____________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
Recorded by:________________________________ Date:______________________________