Republic of the PhilippinesENERGY REGULATORY COMMISSION
San Miguel Avenue, Pasig City
IN THE MATTER OF THE APPLICATIONFOR APPROVAL OF REGULATED ENTITIES CAPITAL EXPEDITURE PROJECTS DUE TOFORCE MAJEURE,
ERC CASE NO.______RC
FIRST LAGUNA ELECTIRC COOPERATIVE,INC. (FLECO),
Applicant.X---------------------------------------------------------X
APPLICATION
COMES NOW , applicant First Laguna Electric Cooperative, Inc. (FLECO,
for short), through the undersigned counsel, and unto this Honorable
Commission, most respectfully states:
1. That applicant is an electric cooperative duly organized and existing under
and by virtue of the laws of the Philippines, with the principal office at
Barangay Lewin, Lumban, Laguna, where it may be served with summons
and other legal processes, represented in this instance by its Project
Supervisor, Acting general Manager, EVANGELITO S. ESTACA, of legal
age, Filipino, and with office address also at FLECO office;
2. That herein applicant is the exclusive franchise holder issued by the
national electrification Administration (NEA) to operate an electric light and
power services in the municipalities of the province of Laguna, namely:
Pagsanjan, Cavinti, Lumban, Kalayaan, Paete, Pakil, Pangil, Siniloan,
Famy, Mabitac, and Sta. Maria;
7/27/2019 Application CAPEX Force Majeure
2/5
3. That on July 13, 2011, Typhoon Basyang hit the Luzon area, including
the province of Laguna. As a consequence, the distribution lines of
FLECO were partially damaged, which caused brownout in its entire
coverage area, as shown in the attached pictures duly marked as
Annexes A to A -6;
4. That the details of capital expenditures of FLECO had actually incurred as
of the date of the force Majeure (Typhoon Basyang) was One Million Six
Hundred Thirty Four Thousand Four hundred Forty Three Pesos and
Eighty Seven Centavos (P1,634,443.87), as evidenced by the attachedmaterials damaged by Typhoon Basyang and duly marked a Annexes B
to B -3;
5. That the increase in costs of the damaged distribution lines is
P1,640,563.99 considering that the expenses incurred in the repair of the
damaged due to force Majeure was P3,275,007.86, the details of which is
shown in the attached Materials Used for FLECOs Distribution Lines
damaged by Typhoon Basyan g and duly marked as Annexes C to C -1,
and such costs are reasonable and occur as a sole consequences of the
aforesaid typhoon;
6. That for purposes of and in connection with this application, FLECO
hereby attached hereto the following documents in compliance with the
requirements pertinent there to:
a) Project Description;
b) Justification or Benefits to be delivered;
c) Estimated Project Costs
d) Project schedule
7. That the above projects are consistent with the Distribution development
Plan (PDC), the Philippine Grid code (PGC), the Philippine Distribution
Code (PDC) and other relevant government issuances; and in accordance
7/27/2019 Application CAPEX Force Majeure
3/5
with ERC Resolution No. 26. Series of 2009, Resolution Amending the
Rule for Approval of Regulated Entities Capital Expenditure P rojects;
8. That the source of fund for the aforementioned capital projects was taken
from Members Contribution for CAPEX (MCC);
9. That in compliance with the pre-filing requirements, we are submitting the
following:
a) Certification from the Presiding Officer or secretary of the
Legislative Body (and not the office of the Mayor) of the
municipality where it principally operates, that a copy of theapplication, with all its annexes accompanying documents attesting
to be fact that applicant has furnished the said legislative body of
the aforesaid application. If such principal place of operation is a
component city or municipality and secure the same certification
from the Sangguniang Panlalawigan of Laguna, or their duly
authorized representatives; and
b) Affidavit of Publication and Newspaper issue containing the
published Application in its entirety in a newspaper of general
circulation in Laguna;
10. That the approval of the capital expenditure projects due to Force Majeure
is needed to maintain efficient, reliable, and safety delivery of power to
FLECOs existing and future consumers, and will redound to the benefits
of the consuming public.
PRAYER
WHEREFORE, view from the foregoing, it is respectfully of this Honorable
Commission that, after due notice and hearing and consideration, this application
be approved.
7/27/2019 Application CAPEX Force Majeure
4/5
Other relief/s just and equitable under the premises are likewise prayed
for.
Cainta, Rizal for Pasig City, March 1, 2011.
ARNIDO O. INUMERABLECounsel for the applicant405 Elisa Street, U.E. Village, Cainta, RizalPTR No.4610303, 1-7-11, Q.C.IBP No. 857319, 3-1-11, Pasig CityRoll of Attorneys No. 28764MCLE Compliance III-0015335, 5-5-10
EXPLANATION
Filing and service of the foregoing application were done by registeredmail instead of personal service due to manpower constraint.
ARNIDO O. INUMERABLE
7/27/2019 Application CAPEX Force Majeure
5/5
Republic of the Philippines) ______________________) S.S
VERIFICATION/TION/CERTIFICATION
I, EVANGELITO S. ESTACA, of legal age, Filipino, with office address atBarangayn Lewin, Lumban, Laguna, Philippines, after having been sworn to inaccordance with law, here by depose and state:
1. That I am the Acting General Manager of First Laguna electric Cooperative,Inc. (FLECO), the applicant in this case;
2. That I have caused the preparation and filing of the this application for Approval of Regulated Entities Capital Expenditure Projects Due to force
majeure before the Energy Regulatory Commission;
3. That I have read and know the contents of the said application as true andcorrect to the best of my knowledge;
4. That I hereby certify that I have not therefore commenced any other action or proceeding involving the same in the Supreme court of Appeals or any other tribunal or agency;
5. That to the best of my knowledge, no such action or proceeding is pending in
the Supreme Court, the Court of Appeals or any other tribunal or agency;
6. That if there is such action or proceeding which is either pending or may have been terminated, I must state the status there of;
7. That should I thereafter learn that a similar action or proceeding has been filedor pending before the Supreme court, the Court of appeals or any other tribunal or agency, I will undertake to report that fact within five (5) daystherefore to the Court or agency wherein the original pleading has been filed.
IN WITNESS WHEREOF, I have here unto set my hand this 16 th day of June,2011at Marikina City, Philippines.
EVANGELITO S. ESTACA
AffiantCTC No.13472387Issued on Feb. 24, 2011Issued at Famy, Laguna
SUBCRIBED AND SWORN to before me this 16th
day of June, 2011 in MarikinaCity, Philippines, affiant exhibited to me his community Tax Certificate as shown above.
Doc. No.______;Page No.______;Book No.______;Series of 20____.