26
PRODUCTION REQUIREMENTS Standard lot size (in units) 1,000 Direct labor employees 2 PROCESS TIME Average Cycle time (in seconds) 80 20 60 110 Start Lot Load materials into hopper 1.00 0.050 0.900 1.100 Enter machine parameters 0.15 0.005 0.140 0.160 Prepare documentation 0.15 0.015 0.120 0.180 Setup machine 0.50 0.025 0.350 0.600 Subtotal start lot 1.80 0.095 1.510 2.040 End Lot Reset machine parameters 0.08 0.008 0.070 0.090 Count units 0.75 0.150 0.500 1.000 Verify count 0.50 0.050 0.450 0.550 Document output produced 0.25 0.025 0.230 0.270 Clean area 0.17 0.025 0.140 0.200 Subtotal end lot 1.75 0.258 1.390 2.110 Total setup time* 3.55 0.353 2.900 4.150 Machine Time Run production 22.22 Total Processing Time 25.77 Net available time in hours 120 Number of lots per week 5.00 Standard Deviation Minimum Value Maximum Value *Total setup time = SStart Lot Activities + S End Lot Activities

Appendix c

Embed Size (px)

DESCRIPTION

Appendix C

Citation preview

Page 1: Appendix c

PRODUCTION REQUIREMENTSStandard lot size (in units) 1,000 Direct labor employees 2

PROCESS TIME Average

Cycle time (in seconds) 80 20 60 110

Start LotLoad materials into hopper 1.00 0.050 0.900 1.100Enter machine parameters 0.15 0.005 0.140 0.160Prepare documentation 0.15 0.015 0.120 0.180Setup machine 0.50 0.025 0.350 0.600Subtotal start lot 1.80 0.095 1.510 2.040

End LotReset machine parameters 0.08 0.008 0.070 0.090Count units 0.75 0.150 0.500 1.000Verify count 0.50 0.050 0.450 0.550Document output produced 0.25 0.025 0.230 0.270Clean area 0.17 0.025 0.140 0.200Subtotal end lot 1.75 0.258 1.390 2.110

Total setup time* 3.55 0.353 2.900 4.150

Machine TimeRun production 22.22

Total Processing Time 25.77

Net available time in hours 120

Number of lots per week 5.00

Standard Deviation

Minimum Value

Maximum Value

*Total setup time = SStart Lot Activities + S End Lot Activities

Page 2: Appendix c

Materials Each 500.00 $ 1.00 $ 500

Setup labor Hours 7.10 $ 15.00 107 Labor Hours 44.44 $ 15.00 667 Subtotal labor 774

Setup machine Hours 3.55 $ 50.00 178 Overhead Hours 22.22 $ 50.00 1,111 Total overhead costs 1,289 Total costs per lot (1) $ 2,563

Cost per unit (2) $ 2.56

Sales price $ 3.25 Gross Margin 27%

(1) Sum of labor, materials and overhead costs(2) Total costs ÷ standard lot size

Unit of Measure

Quantity per Lot

Cost per Unit of

Measure

Total Costs

Page 3: Appendix c

PRODUCTION REQUIREMENTSStandard lot size (in units) 1,000 Direct labor employees 2

PROCESS TIME Average

Cycle time (in seconds) 80 20 60 110

Start LotLoad materials into hopper 1.00 0.050 0.900 1.100Enter machine parameters 0.15 0.005 0.140 0.160Prepare documentation 0.15 0.015 0.120 0.180Setup machine 0.50 0.025 0.350 0.600Subtotal start lot 1.800 0.095 1.510 2.040

End LotReset machine parameters 0.08 0.008 0.070 0.090Count units 0.75 0.150 0.500 1.000Verify count 0.50 0.050 0.450 0.550Document output produced 0.25 0.025 0.230 0.270Clean area 0.17 0.025 0.140 0.200Subtotal end lot 1.75 0.258 1.390 2.110

Total setup time* 3.550 0.353 2.900 4.150

Machine TimeRun production 22.22

Total Processing Time 25.77

Net available time in hours 120

Number of lots per week 5.00

Standard Deviation

Minimum Value

Maximum Value

*Total setup time = SStart Lot Activities + S End Lot Activities

Page 4: Appendix c

Materials Each 500 $ 1.00 $ 500

Setup labor Hours 7.10 $ 15.00 107 Labor Hours 44.44 $ 15.00 667 Subtotal labor 774

Setup machine Hours 3.55 $ 50.00 178 Overhead Hours 22.22 $ 50.00 1,111 Total overhead costs 1,289 Total costs per lot (1) $ 2,562

Cost per unit (2) $ 2.56

Sales price $ 3.25 Gross Margin 27%

(1) Sum of labor, materials and overhead costs(2) Total costs ÷ standard lot size

Unit of Measure

Quantity per Lot

Cost per Unit of

Measure

Total Costs

Page 5: Appendix c

Page

Crystal Ball ReportSimulation started on 12/22/03 at 7:11:41Simulation stopped on 12/22/03 at 7:11:44

Assumptions

Assumption: Cycle time (in seconds) Cell: B6

Triangular distribution with parameters:Minimum 60.00Likeliest 80.00Maximum 110.00

Selected range is from 60.00 to 110.00

Assumption: Load materials into hopper Cell: B9

Uniform distribution with parameters:Minimum 0.90Maximum 1.10

Assumption: Count units Cell: B17

Uniform distribution with parameters:Minimum 0.50Maximum 1.00

End of Assumptions

Mean = 83.33

60.00 72.50 85.00 97.50 110.00

Cycle time (in seconds)

Mean = 1.00

0.90 0.95 1.00 1.05 1.10

Load materials into hopper

Mean = 0.75

0.50 0.63 0.75 0.88 1.00

Count units

Page 6: Appendix c

Page

Crystal Ball ReportSimulation started on 12/22/03 at 7:11:41Simulation stopped on 12/22/03 at 7:11:44

Forecast: Total Processing Time [AppendixC.xls]Monte Carlo Time - Cell: B28

Percentiles:

Percentile Hours0% 20.57

10% 23.1120% 24.1930% 25.0040% 25.7550% 26.3960% 27.1070% 28.0380% 29.1790% 30.40

100% 33.91

End of Forecast

Frequency Chart

Certainty is 95.00% from 21.72 to 32.21 Hours

Mean = 26.60.000

.006

.012

.018

.024

0

6

12

18

24

20.67 23.97 27.27 30.57 33.87

1,000 Trials 997 Displayed

Forecast: Total Processing Time

Page 7: Appendix c

Page

Forecast: Number of lots per week [AppendixC.xls]Monte Carlo Time - Cell: B32

Percentiles:

Percentile lots0% 4.00

10% 4.0020% 4.0030% 4.0040% 4.0050% 5.0060% 5.0070% 5.0080% 5.0090% 5.00

100% 6.00

End of Forecast

Cumulative Chart

lots

Mean = 4.58.000

.250

.500

.750

1.000

0

250

500

750

1000

4.00 5.25 6.50 7.75 9.00

1,000 Trials 1,000 Displayed

Forecast: Number of lots per week

Page 8: Appendix c

Page

Forecast: Cost per Unit [AppendixC.xls]Monte Carlo Cost - Cell: E13

Percentiles:

Percentile Dollars0% $2.15

10% $2.35 20% $2.44 30% $2.50 40% $2.56 50% $2.61 60% $2.67 70% $2.74 80% $2.83 90% $2.93

100% $3.21

End of Forecast

Frequency Chart

Certainty is 95.00% from $2.24 to $3.08 Dollars

Mean = $2.63.000

.006

.012

.018

.024

0

6

12

18

24

$2.15 $2.42 $2.68 $2.95 $3.21

1,000 Trials 997 Displayed

Forecast: Cost per Unit

Page 9: Appendix c

Page

Forecast: Gross Margin [AppendixC.xls]Monte Carlo Cost - Cell: E16

Percentiles:

Percentile Percent0% 1%

10% 11%20% 15%30% 18%40% 22%50% 24%60% 27%70% 30%80% 33%90% 38%

100% 51%

End of Forecast

Frequency Chart

Certainty is 95.00% from 5% to 45% Percent

Mean = 25%.000

.006

.013

.019

.025

0

6.25

12.5

18.75

25

1% 14% 26% 38% 51%

1,000 Trials 998 Displayed

Forecast: Gross Margin

Page 10: Appendix c

Page

Crystal Ball ReportSimulation started on 12/22/03 at 7:11:41Simulation stopped on 12/22/03 at 7:11:44

Target Forecast: Cost per Unit

Cycle time (in seconds) 99.6%

Load materials into hopper 0.3%

Count units 0.1%

100% 50% 0% 50% 100%

Measured by Contribution to Variance

Sensitiv ity Chart

Page 11: Appendix c

Page

Crystal Ball ReportSimulation started on 12/22/03 at 7:51:03Simulation stopped on 12/22/03 at 7:51:07

Forecast: Total Processing Time [AppendixC.xls]Monte Carlo Time - Cell: B28

Percentiles:

Percentile Hours0% 23.01

10% 24.1620% 24.6530% 25.1440% 25.4550% 25.7360% 26.0770% 26.3880% 26.7590% 27.26

100% 28.72

End of Forecast

Frequency Chart

Certainty is 95.00% from 23.57 to 27.98 Hours

Mean = 25.75.000

.006

.013

.019

.025

0

6.25

12.5

18.75

25

23.06 24.44 25.83 27.21 28.60

1,000 Trials 998 Displayed

Forecast: Total Processing Time

Page 12: Appendix c

Page

Forecast: Number of lots per week [AppendixC.xls]Monte Carlo Time - Cell: B32

Percentiles:

Percentile lots0% 4.00

10% 4.0020% 4.0030% 5.0040% 5.0050% 5.0060% 5.0070% 5.0080% 5.0090% 5.00

100% 5.00

End of Forecast

Cumulative Chart

lots

Mean = 4.78.000

.250

.500

.750

1.000

0

250

500

750

1000

4.00 5.25 6.50 7.75 9.00

1,000 Trials 1,000 Displayed

Forecast: Number of lots per week

Page 13: Appendix c

Page

Forecast: Cost per Unit [AppendixC.xls]Monte Carlo Cost - Cell: E13

Percentiles:

Percentile Dollars0% $2.34

10% $2.43 20% $2.47 30% $2.51 40% $2.54 50% $2.56 60% $2.59 70% $2.61 80% $2.64 90% $2.68

100% $2.80

End of Forecast

Frequency Chart

Certainty is 95.00% from $2.39 to $2.74 Dollars

Mean = $2.56.000

.006

.013

.019

.025

0

6.25

12.5

18.75

25

$2.35 $2.46 $2.57 $2.68 $2.79

1,000 Trials 998 Displayed

Forecast: Cost per Unit

Page 14: Appendix c

Page

Forecast: Gross Margin [AppendixC.xls]Monte Carlo Cost - Cell: E16

Percentiles:

Percentile Percent0% 16%

10% 21%20% 23%30% 24%40% 26%50% 27%60% 28%70% 29%80% 31%90% 34%

100% 39%

End of Forecast

Frequency Chart

Certainty is 95.00% from 19% to 36% Percent

Mean = 27%.000

.007

.013

.020

.026

0

6.5

13

19.5

26

17% 22% 28% 33% 39%

1,000 Trials 997 Displayed

Forecast: Gross Margin

Page 15: Appendix c

Page

Assumptions

Assumption: Cycle time (in seconds) Cell: B6

Triangular distribution with parameters:Minimum 70.00Likeliest 80.00Maximum 90.00

Selected range is from 70.00 to 90.00

Assumption: Load materials into hopper Cell: B9

Uniform distribution with parameters:Minimum 0.90Maximum 1.10

Assumption: Count units Cell: B17

Uniform distribution with parameters:Minimum 0.50Maximum 1.00

End of Assumptions

Mean = 80.00

70.00 75.00 80.00 85.00 90.00

Cycle time (in seconds)

Mean = 1.00

0.90 0.95 1.00 1.05 1.10

Load materials into hopper

Mean = 0.75

0.50 0.63 0.75 0.88 1.00

Count units