Annexure-A
Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
1 Details of Project
a. Name of the Project(s) : Proposed expansion of Bulk Drug and
Bulk Drug Intermediates in existing
Manufacturing Unit
b. Name of the Company / Organisation : M/s. Anmol Antioxidants Pvt. Ltd.
c. Registered Address : Survey No. 35 & 36, Behind HGI
Foundary, Vill. Baska, Tal. Halol, Dist.
Panchmahal, Gujarat-389350.
d. Legal Status of the Company : -
e. Joint Venture (Yes / No) : No
If Yes,
(i) No. of JV Partners (Multiple Entries
Allowed)
: NA
Name of the JV
Partner
Share of the JV
Partner
Address of the JV
Partner
Email Id of JV
Partner
Mobile No. of
JV Partner
2 Address for the correspondence :
a. Name of the applicant : Mr. Ramesh D. Chodvadia
b. Designation (Owner / Partner / CEO) Director
c. Address 2208/1, GIDC Residence area, GIDC
Ankleshwar, Dist: Bharuch, Gujarat
d. Pin code 393002
e. e-mail [email protected]
f. Telephone No. +919825205460
g. Fax No. -
3 Category of the Project/Activity as per Schedule of EIA Notification, 2006
a. Project / Activity
[1(a)(i) / 1(a)(ii) / 1(b) / 1(c) / 1(d) / 1 (e) / 2(a)
/ 2(b) / 3(a) / 3(b) / 4(a) /4(b)(i)/ 4(b) (ii) / 4(c) /
4(d) / 4(e) / 4(f) / 5(a) / 5(b) / 5(c) / 5(d) / 5(e) /
5(f) / 5(g) / 5(h) / 5(i) / 5(j) / 6(a) / 6(b) / 7(a) /
7(b)/ 7 (c) / 7 (d) / 7 (da) / 7 (e) / 7 (f) / 7 (g) / 7
(h) / 7 (i) / 8 (a) / 8 (b)]
5 (f)
b. Category (A/B1/B2) A
If B1 or B2
Reason for application at Central Level / State
Level (in case of B2 projects)
NA
If others NA
c. Please Specify : NA
d. EAC concerned (for category A Projects only)
EAC concerned (for category A Projects only)
(Coal Mining / Non-coal Mining / Thermal /
River Valley & Hydro / Industry- I / Industry-II
/ Infrastructure-I / Infrastructure-II / Nuclear
&Defence / CRZ
: Industry-II
e. New / Expansion /Modernization / One Time
Capacity expansion (only for Coal Mining) /
Expansion under Para 7(ii) / Modernization
under Para 7(ii) / Change of Product Mix under
Para 7(ii))
: Expansion
4 Location of the Project
a. Plot / Survey / Khasra No. : Survey No. 35 & 36, Behind HGI
Foundary
b. Village : Baska
Page 2 of 75
c. Tehsil : Halol
d. District : Panchmahal
e. State : Gujarat
f. Pin Code 389350
g. Bounded Latitudes (North)
From : 22°28'13.43"N
To : 22°28'16.80"N
h. Bounded Longitudes(East)
From : 73°27'23.42"E
To : 73°27'26.72"E
i. Survey of India Topo Sheet No. : F43H7
j. Upload Topo Sheet File (Upload pdf only) : Attached Separately as Annexure - 1
k. Maximum Elevation Above Means Sea
Level(AMSL)
: 105m
l. Upload (kml) File (Upload kml only) : Attached Separately as Annexure - 2
m. Distance of Nearest HFL from the project
boundary within the study area
: --
n. Seismic Zone (Zone: 1 / 2 / 3 / 4 / 5) : Seismic Zone-III
5. Whether project is executed in multiple States (Yes /
No)
No
If Yes
a. Number of States in which Project will be
Executed
(e.g. 1,2,3,4,5,6)
: NA
b. Main State of the Project : NA
c. Other State (Multiple Entries Allowed)
(If the project to be executed, does not belong
to any state, then state category could be
selected as 'Other')
: NA
State District Tehsil Village
6 Details of Terms of Reference (ToR)
a. Whether ToR is mandatory for submitting
application (Yes / No)?
Yes
If Yes
b. Date of issue of ToR / Standard ToR : 16/10/2017
c. MoEFCC / SEIAA File No. : IA-J-11011/432/2017-IA-II(I)
d. Upload ToR Letter (PDF only) : Attached Separately as Annexure - 3
7 Details of Public Consultation
a. Whether the Project Exempted from Public
Hearing (Yes / No)?
: No.
If Yes
Reason NA
b. Supporting Document (upload pdf only) : Attached Separately as Annexure-4
c. Whether details of Public Hearing available
(Yes / No)?
: Yes
If No,
d. Reason thereof No
Supporting Documents (upload pdf only) :
e. Date of Advertisement of Public Hearing 10/05/2018
f. Copy of advertisement in English (Upload PDF
only)
Attached Separately as Annexure-5
g. Whether Public hearing was presided over by
an officer of the rank of Additional District
Magistrate or above (Yes / No)
Yes
If yes
h. Designation of Presiding Officer (District
Magistrate / District Collector / Deputy
Shri M L Nalvaya (Resident Additional
Collector and Additional District
Page 3 of 75
Commissioner / Other – please specify) Magistrate, Panchmahal, Godhra)
i. Copy of duly signed Proceeding of Public
Hearing in English (Upload pdf only)
Attached Separately as Annexure-4
j. Date of Public Hearing 11/06/2018
k. Venue of Public Hearing at Project site M/s. Anmol Antioxidants
Private Limited, Survey No. 35 & 36,
B/H. HGI Foundry,
Village Baska
Tehsil Halol
District Panchmahal
State Gujarat
l. Distance of Public Hearing Venue from the
Proposed Project (km)
at Project site M/s. Anmol Antioxidants
Private Limited
m. No. of people attended 56
n. If the multiple public hearing conducted NA
Pl give the details of each PH as per (e) to (o)
above
8 Details of Project Configuration / Product (Multiple
Entries Allowed)
a. Whether the project is New (Yes / No)? No
If yes,
b. Project Configuration
Plant / Equipment / Facility Configuration Remarks if any
c. Product
Product / Activity (Capacity
/ Area
Quantity Unit Mode of Transport
/ Transmission of
Product
Existing
1 Ethisterone 0.2 MT/Month Truck by Road
2 Nandrolone 0.1 MT/Month Truck by Road
3 Betamethasone valerate 0.05 MT/Month Truck by Road
4 Budesonide 0.03 MT/Month Truck by Road
5 Mometasone Furoate 0.03 MT/Month Truck by Road
6 Triamcinolone 0.03 MT/Month Truck by Road
7 Betamethasone Dipropionate 0.05 MT/Month Truck by Road
8 Clobetasol propionate 0.07 MT/Month Truck by Road
9 Triamainolone Acetonide 0.07 MT/Month Truck by Road
10
Sulphonated Melamine
Formaldehyde condensate
Solution
16 MT/Month Truck by Road
11 Halobetasole propionate 0.03 MT/Month Truck by Road
12 Dexamethasone Sodium
Phosphate
0.05 MT/Month Truck by Road
13 Clobetasol Butyrate 0.03 MT/Month Truck by Road
14 Beclomethasone
Dipropionate
0.03 MT/Month Truck by Road
15 Prednisolone sodium
phosphate
0.03 MT/Month Truck by Road
16 Betamethasone Sodium
phosphate
0.05 MT/Month Truck by Road
17 N (3-bromo propyl pthalide) 5 MT/Month Truck by Road
18 Prednisolone Acetate 0.03 MT/Month Truck by Road
Additional Products
Group A
19 Acebrofylline
30 MT/Month Truck by Road
20 Ambroxol Hydrchloride
21 Amlodipine Besylate
Page 4 of 75
22 Bupropion Hydrochloride
23 Celecoxib
24 Doxofylline
25 Drotaverine Hydrochloride
Group-B
26 Etoricoxib
30 MT/Month Truck by Road
27 Flurbiprofen
28 Glibenclamide
29 Phenazopyridine
Hydrochloride
30 Phenyl Ephrine
31 Quetiapine fumarate
32 Telmisartan
33 Valsartan
Group-C
34 Bisoprolol Fumarate
10 MT/Month Truck by Road
35 Brimonidine Tartrate
36 Capacitabine
37 Cinacalcet Hydrochloride
38 Donepezil Hydrochloride
39 Gemcitabine Hydrochloride
40 Glimepiride
41 Ivabridine
42 Nevivolol Hydrochloride
43 Pirfenidone
44 Sofosbuvir
45 Terbinafine Hydrochloride
46 Ursodeoxycholic acid
Group-D
47 2 Amino Phenyl phenyl
Sulfide
40 MT/Month Truck by Road
48 2 Amino 3,5 Di bromo
benzaldehyde
49 Dibenzo[b,f][1,4]Thiazepin-
11(10H)-One
50 4 Methyl Acetophenone
51
2-Chloro-1,3 bis
(dimentylamino)
trimethinium hexafluoro
phosphate
52 2,3-Dibenzoyl-D-Tartaric acid
53 Ethyl Trifluoro Acetate
54 m Phenoxy benzyl alcohol
55 p Methoxy Phenyl Acetonirile
56 Phthaloyl Amlodipine
57 Sulfanilamide
58 3-Trifluoromethyl Cinnamic
Acid
Group-E
59 Glipizide
10 MT/Month Truck by Road
60 Modafinil
61 Mycophenolate Mofetil
62 Tadalafil
63 Tranexamic Acid
64 5-(1-Carboxyethyl)-2-
Phenylthio-Phenylacetic Acid
65 Zaltoprofen
Page 5 of 75
Total 141.88 MT/Month
- Unit:- (Ton per Annum (TPA), Mega Watt (MW), Hectares (ha), Kilo Liter per Day (KLD), Ton
Crushed per Day (TCD), Cubic Meter per Day, Kilometers (Km), Million Liters per Day (MLD),
Others)
- Mode of Transport/Transmission of Product (Road, Rail, Conveyor Belt, Pipe Conveyor, Arial
Ropeway, combination of two or three modes, Others)
9 If Expansion / Modernisation / One Time Capacity expansion (Only for Coal Mining) / Expansion under
Clause 7 (ii) / Modernisation under Clause 7 (ii) / Change of Product Mix under Clause 7 (ii))
a. Details of environmental clearance granted
earlier
No EC earlier. Unit have CCA before
14-09-2006.
(i) Date of issue of environmental
clearance
NA
(ii) MoEFCC / SEIAA File Number NA
(iii) Upload EC Letter NA
b. Details of certified report on compliance of
earlier environmental clearance conditions
Not applicable as company has not
Environmental Clearance for existing unit.
(i) Details of Regional Office of
MoEFCC / Zonal Office of CPCB /
SPCB / UTPCC from which certified
report on compliance of earlier
environmental clearance conditions
obtained
NA
(ii) Letter No NA
(iii) Status of Compliance NA
(iv) Certified report on compliance of
earlier environmental clearance
conditions (Including Monitoring
Report) (Upload pdf only)
NA
(v) Date of site visit NA
c. Details of Consent of Operate
(i) Whether Consent of Operate is
obtained (Yes / No)?
Yes
if yes,
(ii) Upload Copies of all Consent to
Operate obtained since inception
(Upload pdf only)
Attached Separately as Annexure - 6
(iii) Date of issue 23/04/2014
(iv) Valid up to 13/03/2019
(v) File No AWH - 61842
(vi) Application No.
(viii) Upload Copy of Consent to operate
valid as on date (Upload pdf only)
Attached Separately as Annexure - 6
d. Details of Capacity Expansion (Multiple
Entries Allowed)
Product / Activity
(Capacity/Area)
Quantity From Quantity To Unit Mode of Transport /
Transmission of
Product
1 Ethisterone 0.2 0.2 MT/Month Truck by Road
2 Nandrolone 0.1 0.1 MT/Month Truck by Road
3
Betamethasone
valerate
0.05 0.05 MT/Month Truck by Road
4 Budesonide 0.03 0.03 MT/Month Truck by Road
5
Mometasone
Furoate
0.03 0.03 MT/Month Truck by Road
6 Triamcinolone 0.03 0.03 MT/Month Truck by Road
7
Betamethasone
Dipropionate
0.05 0.05 MT/Month Truck by Road
8
Clobetasol
propionate
0.07 0.07 MT/Month Truck by Road
Page 6 of 75
9
Triamainolone
Acetonide
0.07 0.07 MT/Month Truck by Road
10
Sulphonated
Melamine
Formaldehyde
condensate
Solution
16 16 MT/Month Truck by Road
11
Halobetasole
propionate
0.03 0.03 MT/Month Truck by Road
12
Dexamethasone
Sodium Phosphate
0.05 0.05 MT/Month Truck by Road
13 Clobetasol Butyrate 0.03 0.03 MT/Month Truck by Road
14
Beclomethasone
Dipropionate
0.03 0.03 MT/Month Truck by Road
15
Prednisolone
sodium phosphate
0.03 0.03 MT/Month Truck by Road
16
Betamethasone
Sodium phosphate
0.05 0.05 MT/Month Truck by Road
17
N (3-bromo propyl
pthalide)
5 5 MT/Month Truck by Road
18
Prednisolone
Acetate
0.03 0.03 MT/Month Truck by Road
19 Acebrofylline
-- 30 MT/Month Truck by Road
20
Ambroxol
Hydrchloride
21
Amlodipine
Besylate
22
Bupropion
Hydrochloride
23 Celecoxib
24 Doxofylline
25 Drotaverine
Hydrochloride
26 Etoricoxib
-- 30 MT/Month Truck by Road
27 Flurbiprofen
28 Glibenclamide
29 Phenazopyridine
Hydrochloride
30 Phenyl Ephrine
31 Quetiapine
fumarate
32 Telmisartan
33 Valsartan
34 Bisoprolol
Fumarate
-- 10 MT/Month Truck by Road
35 Brimonidine
Tartrate
36 Capacitabine
37 Cinacalcet
Hydrochloride
38 Donepezil
Hydrochloride
39 Gemcitabine
Hydrochloride
40 Glimepiride
41 Ivabridine
42 Nevivolol
Hydrochloride
Page 7 of 75
43 Pirfenidone
44 Sofosbuvir
45 Terbinafine
Hydrochloride
46 Ursodeoxycholic
acid
47 2 Amino Phenyl
phenyl Sulfide
-- 40 MT/Month Truck by Road
48 2 Amino 3,5 Di
bromo
benzaldehyde
49 Dibenzo[b,f][1,4]T
hiazepin-11(10H)-
One
50 4 Methyl
Acetophenone
51 2-Chloro-1,3 bis
(dimentylamino)
trimethinium
hexafluoro
phosphate
52 2,3-Dibenzoyl-D-
Tartaric acid
53 Ethyl Trifluoro
Acetate
54 m Phenoxy benzyl
alcohol
55 p Methoxy Phenyl
Acetonirile
56 Phthaloyl
Amlodipine
57 Sulfanilamide
58 3-Trifluoromethyl
Cinnamic Acid
59 Glipizide
-- 10 MT/Month Truck by Road
60 Modafinil
61 Mycophenolate
Mofetil
62 Tadalafil
63 Tranexamic Acid
64 5-(1-
Carboxyethyl)-2-
Phenylthio-
Phenylacetic Acid
65 Zaltoprofen
Total 1389
- Unit:- (Ton per Annum (TPA), Mega Watt (MW), Hectares (ha), Kilo Liter per Day
(KLD), Ton Crushed per Day (TCD), Cubic Meter per Day, Kilometers (Km), Million
Liters per Day (MLD), Others)
- Mode of Transport/Transmission of Product (Road, Rail, Conveyor Belt, Pipe Conveyor,
Arial Ropeway, combination of two or three modes, Others)
10 Project Cost
a. Total Cost of the Project at current price level
(in Lakhs)
Rs. 1000 Lakhs
b. Fund Allocated for Environment Management
(Capital) (in Lakhs)
Rs. 140 Lakhs
c. Fund Allocated Towards ESC (Entrepreneur
Social Responsibility) (in Lakhs)
Rs. 25 Lakhs (next 5 years)
d. Fund Allocation for Environment Management Rs. 10 Lakhs/Annum
Page 8 of 75
Plan (EMP) (Recurring per Annum) (in Lakhs)
11 Whether project attract the General Condition
specified in the Schedule of EIA Notification (Yes /
No)? [provide name of WL/CPA/ESA/Inter-state
boundary / International boundary and distance from
the project]
No
If Yes
a. Protect Area Notified Under the Wild Life
(Protection) Act, 1972
NA
b. Critically Polluted Areas as identified by the
Central Pollution Control Board from Time to
Time
NA
c. Notified Eco-Sensitive Area NA
d. Inter-State Boundaries and International
Boundaries
NA
12 Whether projects attract the Specific Condition
specified in the Schedule of EIA Notification
(Yes/No)?
No
If Yes
a. If any Industrial Estate/Complex / Export
processing Zones / Special Economic Zones /
Biotech Parks / Leather Complex with
homogeneous type of industries such as Items
4(d), 4(f), 5(e), 5(f), or those Industrial estates
with pre-defined set of activities (not
necessarily homogeneous, obtains prior
environmental clearance, individual industries
including proposed industrial housing within
such estates /complexes will not be required to
take prior environmental clearance, so long as
the Terms and Conditions for the industrial
estate/complex are complied with (Such
estates/complexes must have a clearly
identified management with the legal
responsibility of ensuring adherence to the
Terms and Conditions of prior environmental
clearance, who may be held responsible for
violation of the same throughout the life of the
complex/estate
NA
13 Raw Material / Fuel Requirement (Multiple Entries
Allowed)
Attached Separately as Annexure - 7
a. Details of Raw Material / Fuel Requirement
Sr.
No. Name of Product Raw Material
Consumption
Quantity
(MT/Month)
CAS No.
In case of expansion proposals, total requirement of raw material / fuel shall be given
- Unit:- (Ton per Annum (TPA), Mega Watt (MW), Hectares (ha), Kilo Liter per Day (KLD), Ton
Crushed per Day (TCD), Cubic Meter per Day, Kilometers (Km), Million Liters per Day (MLD),
Others)
- Mode of Transport/Transmission of Product (Road, Rail, Conveyor Belt, Pipe Conveyor, Arial
Ropeway, combination of two or three modes, Others)
b. Upload copy of Linkage / Fuel Supply
Agreement / e-auction / Memorandum of
Understanding / Letter of Allocation / Captive
source / others.
Company has not done any MOU to
purchase fuel. Company purchases the
fuel from local supplier as per
requirement.
14. Baseline Data (Air / Water / Noise / Soil / Ground Water table / Others)
a. Period of Base Line Data Collection
From (DD/MM/YYYY) 01 March 2017
To (DD/MM/YYYY) 31 May 2017
Page 9 of 75
b. Season (Summer / Pre-monsoon/Post-
monsoon/Winter)
Pre-Monsoon
c. No. of Ambient Air Quality (AAQ) Monitoring
Locations
12
d. Details of AAQ Monitoring (Multiple Entries
Allowed)
Criteria
Pollutants
Unit Maximum
Value
Minimum
Value
98 Percentile
Value
Prescribed
Standards
PM10 µg/m3 80.85 70.65 80 100
PM2.5 µg/m3 52.15 41.96 52 60
NOx µg/m3 18.23 10.23 18 80
SO2 µg/m3 21.73 12.16 21 80
O3 µg/m3 11.12 10.37 11 100
Pb µg/m3 BDL BDL - 1
NH3 µg/m3 7.38 2.16 7 400
CO mg/m3 1.29 1.19 - 2
C6H6 µg/m3 BDL BDL - 5
BaP mg/m3 BDL BDL - 1
As mg/m3 BDL BDL - 6
Ni mg/m3 BDL BDL - 20
HCl µg/m3 BDL BDL - -
Cl2 µg/m3 BDL BDL - -
HC ppm BDL BDL - -
VOC ppm 0.8 0.3 - -
- Criteria Pollutants:- (PM10, PM2.5, SO2, NOx, Others parameters specific to sector)
- Unit:- (Microgram per Meter Cube, Nano Gram per Meter Cube, Mili Gram per Meter Cube
NA)
e. No. of Ground Water Monitoring Locations
(Multiple Entries Allowed)
12
f. Details of Ground Water Monitoring
Criteria
Pollutants
Unit Maximum
Value
Minimum
Value
98 Percentile
Value
Prescribed
Standards
pH - 7.92 7.51 - -
Turbidity NTU BDL 3.7 - -
TDS mg/L 1996 472 - -
TSS mg/L 32 2 - -
DO mg/L 5.92 5.27 - -
COD mg/L 10.88 2.56 - -
BOD3 mg/L BDL BDL - -
Total hardness
(as CaCO3)
mg/L 876.9 208 - -
Calcium
hardness (as
CaCO3)
mg/L 272.1 44.3 - -
Total Alkalinity mg/L 525 260 - -
Chlorides mg/L 939.3 19.7 - -
Sulphates mg/L 134.8 1.3 - -
Copper mg/L BDL BDL - -
Sodium mg/L 634.8 16.13 - -
Potassium mg/L 8.11 0.28 - -
Criteria Pollutant:- (pH, TSS, TDS, Total Hardness, Chlorides, Fluoride, Heavy Metals, Other parameters
specific to sector)
- Unit:- (mg/l, NA)
g. No. of Surface Water Monitoring Locations 1
h. Details of Surface Water Monitoring (Multiple
Entries Allowed)
Criteria
Pollutants
Unit Maximum
Value
Minimum
Value
98 Percentile
Value
Prescribed
Standards
Page 10 of 75
pH - 7.88 - - -
Turbidity NTU 1.3 - - -
TDS mg/L 262 - - -
TSS mg/L 6 - - -
DO mg/L 6.85 - - -
COD mg/L 12.8 - - -
BOD3 mg/L BDL - - -
Total hardness
(as CaCO3)
mg/L 96.76 - - -
Calcium
hardness (as
CaCO3)
mg/L 58.4 - - -
Total Alkalinity mg/L 125 - - -
Chlorides mg/L 7.8 - - -
Sulphates mg/L 1.8 - - -
Copper mg/L BDL - - -
Sodium mg/L 67.95 - - -
Potassium mg/L 1.7 - - -
- Parameter:- (pH, DO, BOD, COD, Others parameters specific to the sector)
- Unit:- (mg/l, NA)
i. No. of Ambient Noise Monitoring Locations 9
j. Details of Noise Monitoring (Multiple Entries
Allowed)
Parameter Unit Maximum
Value
Minimum
Value
98 Percentile
Value
Prescribed
Standards
Industrial dBA 71 (Day)
68 (Night)
66 (Day)
61 (Night)
- Day – Night
75 - 70
Residential dBA 53 (Day)
44 (Night)
45 (Day)
34 (Night)
- Day – Night
55 - 45
- Parameter:- (Leq (Day), Leq (Night)
- Unit:- (A-weighted decibels (dB(A))
k. No. of Soil Monitoring Location (Multiple
Entries Allowed)
12
Parameter Unit Maximum
Value
Minimum
Value
98 Percentile
Value
pH - 7.84 7.03 -
Water Holding
Capacity
(WHC)
% 67.69 22.60 -
Bulk Density gm/cm3
1.25 1.09 -
Sulphates mg/kg 695.1 112.6 -
Chlorides mg/kg 582.7 154.2 -
Total Hardness mg/kg 1142 317 -
Calcium mg/kg 320 104 -
Sodium mg/kg 2592 210 -
Iron mg/kg 90.82 18.12 -
Potassium mg/kg 2941 413 -
Copper mg/kg BDL BDL -
- Parameter:- (pH, N(Nitrogen), P(Phosphorous), K(Potassium), Electric Conductivity)
- Unit:- (Millisiemens per Centimeter, Milligram per Litre, Percent, Centimeter per Second,
Milliequivalents per 100 Gram, Milligram per Kilogram, Parts per Million, Kilogram per
hectare, Others)
l. Ground Water Table -
i. Range of Water Table Pre-Monsoon Season
(Meters Below Ground Level (m bgl))
From 100 m
To 200 m
ii. Range of Water Table Post-Monsoon (Meters
Page 11 of 75
Below Ground Level (m bgl))
From 50 m
To 100 m
iii. Whether Ground Water Intersection will be
there (Yes / No)?
No
If Yes,
(i) Upload Copy of Central Ground Water
Authority Letter (Upload pdf only)
(ii) Letter No.
(iii) Date of issue
15 Details of Water Requirement (During Operation)
(Multiple Entries Allowed)
a. Details
Source Quantity in
KLD
Method of water
withdrawal
Method of Transport
Process 26.95
Bore well Pipeline
Cooling Tower
Make-up
42
Boiler 32
Washing 10.1
Scrubbing 10
Domestic 12.6
Gardening 20
Other 10
Total 163.65
- Source: Surface / Ground Water / Sea / Others
- Mode of Transportation: Pipeline / Canal / Others
- Method of water withdrawal: Bore well
b. Upload Copy of Permission from Competent
Authority (Upload pdf only)
Attached Separately as Annexure - 8
c. Letter No. 21-4/2356/GJ/IND/2017
d. Date of issue 03/06/2017
e. Permitted quantity --
f. Whether Desalination is proposed (Yes / No) No
If Yes,
(i) Desaliation capacity (KLD)
(ii) Quality of Brine (KLD)
(iii) Mode of Disposal of brine
16 Waste Water Management (During Operation) --
Type /
Source
Quantity
of Waste
Water
Generate
d (Kilo
Litre per
Day)
Treatment
Capacity (Kilo
Litre per Day)
Treatment Method Mode of
Disposal
Quantity
of
Treated
Water
Used in
Recyclin
g / Reuse
(Kilo
Litre per
Day)
Quantity
of
Discharg
ed Water
(Kilo
Litre per
Day)
Process 45.55 ETP consist of
primary
treatment
(59.1 KLD),
RO Plant
(42.69 KLD),
MEE 25 KLD)
Low COD/TDS
Stream (59.1 KLD)
will be treated in
ETP, out of which
16.41 KLD of
effluent will be send
to CETP of NIA for
further treatment and
42.69 KLD of
Only
16.41
KLD of
Low
COD/TD
S Stream
will be
send to
NIA for
61.69
KLD of
effluent
will be
reused
Only
16.41
KLD of
Low
COD/T
DS
Stream
will be
send to
Cooling
Tower
Make-up
4.225
Boiler 3.225
Washing 10.1
Other 6
Scrubbing 10
Page 12 of 75
effluent will be send
to RO (37.69 KLD of
RO Permeate will be
reuse and 5 KL/Day
of RO reject will be
send to MEE).
High COD/TDS
Stream (20 KLD) +
RO reject (5 KLD)
will be send to MEE
and MEE condensate
will be reuse.
further
treatmet
and
disposal.
All other
effluent
will be
recycled.
NIA for
further
treatmet
and
disposal.
Domestic 12.6 -- -- Domestic
waste
water
will be
treated &
disposed
of
through
septic
tank &
soak pit.
-- --
Gardenin
g
00 -- -- -- -- --
Total 79.1
a. Total Waste Generation 91.7 KL/Day (Industrial: 79.1 KL/Day +
Domestic: 12.6 KL/Day)
b. Total Discharge Water 16.41
c. Total Reused Water 61.69
17 Solid Waste Generation Management (Multiple Entries Allowed)
Item Quantity per
Month
Unit Mode of
Transport
Mode of Disposal
Used Oil 240
Liter Truck by
Road
Collection, Storage, Transportation and
Disposal by selling to registered re-
refiners
Spent Carbon 6.9 MT Truck by
Road
Collection, Storage,
Transportation and sent to cement
industries for co-processing or
incineration at CHWIF.
ETP Sludge 10.0 MT Truck by
Road
Collection, Storage, Transportation and
Disposal at TSDF site of NECL
Nandesari.
Discarded
Bags/
Containers/
barrels/
Liners
700
950
Nos. Truck by
Road
Collection, Storage & reused after
decontamination for filling ETP Sludge.
Residue &
Waste
0.83
MT Truck by
Road
Collection, Storage, Transportation and
sent to cement industries for co-
processing or incineration at CHWIF.
Inorganic
Acids
0.9
MT Truck by
Road
Collection, Storage & Reused back in
process after Decontamination.
Organic
Residue
12.71
MT Truck by
Road
Collection, Storage, Transportation and
sent to cement industries for co-
processing or incineration at CHWIF.
MEE Salt 30 MT Truck by
Road
Collection, Storage, Transportation and
Disposal at TSDF site of NECL
Page 13 of 75
Nandesari.
Sodium
Bromide
solution
10 MT Truck by
Road
Collection, Storage, Transportation and
Treated in ETP and then send to CETP
of NIA for Further Treatment.
HBr solution 107.5 MT Truck by
Road
Collection, Storage, Transportation and
Treated in ETP and then send to CETP
of NIA for Further Treatment.
KBr Solution 30 MT Truck by
Road
Collection, Storage, Transportation and
Treated in ETP and then send to CETP
of NIA for Further Treatment.
Dilute HCl 20 MT Truck by
Road
Collection, Storage, Transportation and
Treated in ETP and then send to CETP
of NIA for Further Treatment.
- Item:- (Industrial Waste, Municipal Solid Waste, Fly Ash, Bottom Ash, Hazardous Waste
(as per Hazardous and Other Waste Management Rules, 2016), E Waste, Bio – Medical
waste, Construction & Demolition waste, plastic waste, Others)
- Unit:- (Tons, Kiloliter)
- Mode of Disposal:- (Treatment, Storage and Disposal Facility (TSDF), Authorized Re –
Cyclers, Landfills, Sanitary Landfills, Others)
18 Air Quality Impact Prediction (Multiple Entries
Allowed)
Criteria
Pollutants
Unit Baseline
Concentration
Minimum
Value
Incremental
Concentration
Total
GLC
Prescribed
Standard
SPM µg/m3 121.8 114.3 0.03 121.83 200
SO2 µg/m3 21.73 12.16 0.002 21.732 80
Nox µg/m3 18.23 10.23 0.000 18.23 80
HCl µg/m3 BDL BDL 0.002 BDL 200
Br2 µg/m3 BDL BDL 0.000 BDL 100
NH3 µg/m3 7.38 2.16 0.005 7.385 400
- Parameter:- (PM10, PM2.5, SO2, NOx, Other parameters specific to the sector)
- Unit:- (Microgram per Meter Cube, NA)
19 Power Requirement
a. Quantity (Kilo Volt Amps (KVA)) 1500 KVA (Total Proposed)
b. Source MGVCL (GEB)
c. Upload Copy of Agreement (Upload pdf only)
d. Standby Arrangement (Details of DG Sets) 250 KVA (shall be used in emergency
only)
e. Stack Height (in m) 11 m
20 Land Ownership Pattern (Prior to the project
proposal) in Ha
NA
a. Forest Land
b. Private Land -
c. Government Land
d. Revenue Land
e. Other Land
Total Land
21 Present Land Use breakup in Ha Unit in KM
a. Water Bodies 4.14
b. Open/Barren Land 27.38
c. Agriculture 124.18
d. Fallow Land 108.78
e. Degraded Vegetation 14.28
f. Vegetation Medium Density 9.05
g. Vegetation High Density 7.08
h. Scrub 2.49
i. Marshy Land 2.49
j. Settlement 9.09
Page 14 of 75
Miscellaneous 4.88
Total 313.84
22 Land requirement for various activities (Multiple
entries allowed) in Ha
Description of Activity / Facility / Plant /
Others
Land requirement (m2) Remarks
Process Area 4,207
Utility Area 1,526
Labor Room & Toilet 328
Raw Material & Product Storage Area 1,098
Office/Lab 345
Road 1,432
Workshop 486
ETP Area 418
Cooling Plant 328
Open Area & Parking Area 11,997
Green Belt 10,916
Total 33,081
- Activity / Facility / Plant / Others include: Main Plant, Township, Greenbelt, Ash pond, Quarry
area, OB dump Area, Safety zone, Tailing pond, Landfill, Water reservoir, Desalination plant,
Area for solid waste management, Built-up area, others
23 Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; ANP-Notified
Protected Area; ESAs-ECO Sensitive Areas; ESZs- Eco Sensitive Zones)
a. Details of Ecological Sensitivity NA
Details of Ecological Sensitivity Name Distance from
the Project (Kms)
Remarks
- Details of Ecological Sensitivity:- (Critically Polluted Area, WLS, NPA, ESAs, ESZs,
Corridors, Wildlife Corridors)
b. Whether NBWL recommendation is required
(Yes / No)?
No
If Yes,
Upload NBWL recommendation in PDF
c. Details of Environmental Sensitivity NA
Details of Ecological Sensitivity Name Distance from
the Project (Kms)
Remarks
- Details of Environmental Sensitivity:- (Forest, Archaeological Sites, Defence Installation,
Others)
d. Whether NoC / Permission from the competent
authority is required (Yes / No)?
NA
If Yes,
Upload NoC / Permission from the competent
authority in PDF
NA
24 Forest Land
1 Whether any Forest Land involved (Yes / No)? No
If Yes
a. Forest Clearance Status (In-Principle (Stage-1)
Approval Obtained / Final (Stage-II) Approval
Obtained / Forest Clearance Under Process
(Stage-I) / Forest Clearance Under Process
(Stage-II) / Application for Forest Clearance
yet to be Submitted)
NA
If In-Principle (Stage-I) Approval Obtained,
(i) MoEFCC file number NA
Page 15 of 75
(ii) Date of InPrinciple (Stag-I)
approval
NA
(iii) Area diverted NA
(iv) Upload FC Letter (Upload pdf
only and attach it an
Annexure-FC letter)
NA
If Final (Stage-II) Approval Obtained, NA
(i) MoEFCC file number NA
(ii) Date of Final Approval NA
(iii) Date of In-Principle Approval NA
(iv) Area diverted NA
(v) Upload FC Letter (Upload pdf
only and attach it as Annexure-
FC letter)
NA
If Forest Clearance under process (Stage-I)
(i) MoEFCC file number NA
(ii) Area applied NA
If Forest Clearance under Process (Stage-II)
(i) MoEFCC file number NA
(ii) Area Applied NA
b. Legal Status of Forest Land (Reserve,
Protected, Private, Village, Others)
NA
if Others,
Please Specify Others NA
25 Tree Cutting, if any
a. Acquired Land NA
b. Details of Tree Cutting and Planting of Trees
(Upload pdf Only)
NA
26 Land Acquisition Status
a. Acquired Land Land is acquired.
b. Land yet to be acquired -
c. Status of Land acquisition if not acquired -
27 Rehabilitation and Resettlement (R&R)
a. No. of Villages NA
b. No. of Households NA
c. No. of PDFs (Project Displaced Families) NA
d. No. of PAFs (Project Affected Families) NA
e. Funds Allocated for R & R NA
f. Status of R & R (Completed / In-progress / Yet
to start)
NA
28 Whether there is Presence of Schedule-I Species
(Yes/No)?
No
If yes,
a. Details of Schedule-I Species NA
b. Whether conservation plan for Schedule-I
Species has been prepared (Yes / No)?
NA
If Yes,
(i) Upload conservation plan (Upload
only PDF)
NA
(ii) Fund Provision made NA
(iii) Period of Implementation NA
c. Whether conservation plan for Schedule-I
Species has been approved by competent
authority (Yes / No)?
NA
(i) Upload copy of approval (Upload PDF
Only)
NA
(ii) Letter No. NA
(iii) Date of issue NA
Page 16 of 75
(iv) Recommendation if any NA
29 Whether there is Presence of Water Bodies in Core
Area (Yes / No)?
No
If yes,
a. Details of Water Bodies in Core Area NA
b. Whether there is Diversion required (Yes /
No)?
NA
If yes, NA
c. Details of diversion required NA
d. Details of study conducted NA
e. Whether permission has been obtained from
competent authority (Yes / No)?
NA
(i) Upload copy of permission
(Upload PDF only)
NA
(ii) Letter No. NA
(iii) Date of issue NA
(iv) Recommendation if any NA
30 Whether there is Presence of Water Bodies in Buffer
Area (Yes / No)?
NA
If Yes NA
a. Details of Water Bodies in Buffer Area NA
b. Direction of Water Bodies in Buffer Area
(North, South, East, West, North East, North
West , South East, South West)
NA
c. Distance of Water Bodies in Buffer Area (kilo
meters)
NA
31 Manpower Requirement
a. Permanent employment during construction
b. Permanent employment during operation 55 Nos.
c. Temporary employment during construction
d. Temporary employment during operation
e. No. of Working days 365
f. Total manpower 24
32 Green Belt in Ha
a. In case of new projects NA
i. Total Area of Green Belt NA
ii. percentage of Total Project Area NA
iii. No. of Plants to be Planted NA
iv. Funds Allocated for Plantation NA
v. Upload Green Belt Plan (Upload PDF Only) NA
b. In case of expansion / modernisation / change
in product mix etc.
i. Description Existing Proposed Total
Total Area of Green Belt 0 10,916 10,916
Percentage of Total Project
Area
0 33% 33%
No. of Plants 0 2200 2200
Funds Allocated 0 30,00,000 30,00,000
ii. Upload Green Belt Plan (Upload PDF Only) As per above mentioned data of Para
32 (i).
33 Project Benefit (Multiple entry allowed)
Type of Project Benefits Details of Project Benefit
Social & Environment • The demand for products intended to be
manufacture is increasing in the country. M/s.
Niranjan Chemicals will be able to meet the
demand of various products locally.
• The project will save forex as certain
products import will be reduced.
Page 17 of 75
• This will also generate direct and indirect
employment opportunity for various levels of
people.
(Project benefits shall be include environmental, social and others)
34 Whether the Project / Activity attracts the provision of
CRZ (Yes / No)?
No
If Yes,
1 Project Details
a. CRZ Classification (CRZ I(A), CRZ I
(B), CRZ II, CRZ III, CRZ IV (A), CRZ
IV (B))
NA
b. Location type: (Non-Eroding Coast,
Low and Medium Eroding Coast, High
Eroding Coast)
NA
c. Details of Mangroves Land Involved, if
any
NA
d. Area of Mangroves Land (Hectare) NA
e. EIA (Terrestrial) Studies: (Carried Out,
Not Carried Out)
NA
If Carried Out,
1) Summary of Details of EIA
(Terrestrial) Studies
NA
2) Upload Recommendation made
in EIAs (Upload pdf only)
NA
3) Period of Study from (EIA
Terrestrial)
NA
4) Period of Study to (EIA
Terrestrial)
NA
If Not Carried out
Give Reason NA
f. EIA (Marine) Studies: (Carried Out, Not
Carried Out)
NA
If Carried Out
1) Summary Details of EIA
(Marine) Studies
NA
2) Upload Recommendation made
in EIAs
NA
3) Period of Study from (EIA
Marine)
NA
4) Period of Study To (EIA
Marine)
NA
If Not Carried Out
Give Reason NA
g. Disaster Management Plant/National
Oil Spill Disaster Contingency Plan (if
applicable)
NA
2 Description of the Project Under Consideration
a. Type of Project: (Resort/Buildings/civic
amenities, Coastal Roads/Roads on stilt,
Pipelines from Thermal power Blow
Down, Marine Disposal of Treated
Effluent, Facility for Storage of Goods /
Chemicals, Off Shore structures,
Desalination Plant, Mining of Rare
Earth / Atomic Minerals, Sewage
Treatment Plants, Lighthouse, Wind
Mills, Others)
NA
If Resort / Buildings / civic amenities,
1) Agency Name for Preparing CRZ Maps NA
Page 18 of 75
2) Total Area/Buit-up Area (hectare) NA
3) Height of Structure NA
4) FSI Ratio NA
5) The governing Town Planning
Rules/Regulations
NA
6) Details of Provision of Car Parking
Area
NA
If Coastal Roads/Roads on stilt,
1) Agency Name for Preparing CRZ Maps NA
2) Area of Land Reclamation NA
3) Estimated Quantity of Muck/Earth for
Reclamation
NA
4) Carrying Capacity of Traffic NA
If Pipelines from Thermal Power Blow Down.
1) Agency Name for Preparing CRZ Maps NA
2) Length of Pipeline NA
3) Length of Traversing CRZ Area NA
4) Depth of Excavation NA
5) Width of Excavation NA
6) Length of Pipeline from Seashore to
Deep Sea
NA
7) Depth of Outfall Point from Surface to
Sea Water
NA
8) Temperature of effluent above Ambient
at Disposal Point
NA
If Marine Disposal of Treated Effluent
1) Agency Name for Preparing CRZ Maps NA
2) Location of Intake/Outfall NA
3) Depth of Outfall Point NA
4) Length of Pipeline NA
5) Length of Traversing CRZ Area NA
6) Depth of Excavation NA
7) width of Excavation NA
8) Length of Pipeline from Seashore to
Deep Sea/Creek
NA
9) Depth of Outfall Point from Surface to
Sea Water
NA
10) Depth of Water at Disposal Point NA
11) Type of Disposal NA
If Facility for Storage of Goods/Chemicals.
1) Agency Name for Preparing CRZ Maps NA
2) Name and Type of Chemical NA
3) End use of the Chemical NA
4) No. of Tanks for Storage NA
5) Capacity of Tanks NA
If offshore structures,
1) Agency Name for Preparing CRZ Maps NA
2) Exploration or Development NA
3) Depth of Sea Bed NA
4) No. of Rigs/Platform NA
5) Details of Group Gathering Stations NA
If Desalination Plant,
1) Agency Name for Preparing CRZ Maps NA
2) Capacity of Desalination NA
3) Total Brine Generation NA
4) Temperature of Effluent above ambient
at Disposal Point
NA
5) Ambient Salinity NA
Page 19 of 75
6) Disposal Point NA
If Mining or Rare Earth/Atomic Minerals,
1) Agency Name for Preparing CRZ Maps NA
2) Capacity of Mining NA
3) Volume/Area to be mined NA
4) Type of Mineral to be Extracted NA
5) End use of the Mineral NA
If Sewage Treatment Plants,
1) Agency Name for Preparing CRZ Maps NA
2) Capacity NA
3) Total Area of Construction NA
4) Compliance of effluent parameters as
laid down by CPCB/SPCB/other
authorised agency
NA
5) Whether discharge is in sea
water/creek?
If yes,
NA
Distance of Marine Outfall Point from
Shore/from the tidal river bank
NA
Depth of Outfall Point from Sea Water
Surface
NA
Depth of Sea at Outfall Point NA
If lighthouse,
1) Agency Name for Preparing CRZ Maps NA
2) Total Area of Construction NA
3) Height of the Structure NA
If Wind Mills,
1) Agency Name for Preparing CRZ Maps NA
2) Capacity (MW) NA
3) Transmission Lines: (Overhead,
Underground)
NA
4) Diameter of Windmill NA
5) Length of Blade NA
6) Speed of Rotation NA
7) Height of the Structure NA
If others,
1) Agency Name for Preparing CRZ Maps NA
2) Please specify with salient features NA
3) Upload relevant Document (Upload pdf
only)
NA
3. Distance of Project (In Meters) from LTL/HTL
to be Stated
a. Clause of CRZ Notification Under
which the project is
Permissible/Regulated Activity
NA
b. Whether CRZ Map Indicating HTL,
LTL Demarcation in 1:4000 Scales
Prepared? (Yes / No)?
NA
If yes,
1) Distance of Project (in meters)
from HTL to be stated
NA
2) Upload Map (kml File) NA
3) Distance of Project (in meters)
from LTL to be stated
NA
4 Upload Map (kml File) NA
c. Whether Project Layout Superimposed on
CRZ Map 1:4000 Scales (Yes / No)?
NA
If Yes,
Page 20 of 75
1) Upload Map (kml File) NA
d. Whether CRZ Map 1:25000 Covering 7
km Radius Around Project Site Prepared
(Yes / No)?
NA
If Yes,
1) Upload Map (kml File) NA
e. Whether CRZ Map Indicating CRZ-I, II,
III and IV including other Notified ESAs
Prepared (Yes / No)?
NA
If Yes,
1) Upload Map (kml File) NA
f. NOC from State Pollution Control Board
Obtained (Yes / No)?
NA
If Yes
1) Upload Copy of NOC (Upload
pdf only)
NA
g. Details of Rain Water Harvesting System NA
4. Recommendation of State Coastal Zone
Management Authority
NA
a. Upload Copy of CZMA (Upload pdf only) NA
b. State the Conditions Imposed NA
c. Social and Environmental Issues and
Mitigations Measures Suggested
Including but not Limited to R&R, Water,
Air, Hazardous Wastes, Ecological
aspects, etc. (Brief Details to be Provided)
NA
35 Sector Specific Details
I Whether the proposal is mining of minerals (coal / non –
coal) project (Yes / No)?
No
If Yes,
1 No. of Mineral to be Mined (Multiple Entries
Allowed)
NA
Mineral to be Mined Major or Minor Mineral
2 Mine Capacity in ROM (Run of Mine) NA
3 Upload 500 meters Cluster Certificate from State
Mines and Geology in case of minor minerals
(upload pdf only)
NA
4 Mining Area NA
a. Approval Letter No. NA
b. Date of Approval NA
c. Upload Approved Letter (Upload pdf
only)
NA
d. Approved by State Mines & Geology
Department / Indian Bureau of Mines /
Ministry of Coal /Ministry of Mines /State
Government /Atomic Mineral Directorate
/ Others)
NA
e. If Others, NA
Please specify
f. Approved Mining Lease Area NA
g. Approved Capacity NA
5 Technical Details
a. Total Geological Reserves (Million Ton) NA
b. Mineable Reserve (Million Ton) NA
c. Extractable Reserves (Million Ton) NA
d. Percent of Extraction (%) NA
f. Stripping Ratio NA
Page 21 of 75
g. Category of Gaseousness (Only for Coal
Mining, Others may write Not applicable)
NA
h. Average Gradient (Degree) NA
i. Maximum Thickness of Seams (meters)
(Only for Coal Mining, Others may write
Not applicable
NA
j. Mining Method (Opencast / Underground
/ Mixed (Opencast + Underground) / Adit
NA
k. Life of Mine (Years) NA
6 Details of beneficiation (including crushing /
screening / others)
a. Whether it is proposed to install crusher
within the mining lease area (Yes / No)?
NA
b. No. of Crushers NA
c. Details of crushers (Multiple entries
allowed)
NA
Crusher ID Capacity (in TPH) Remarks
d. Whether it is proposed to install
beneficiation plant / Coal washery within
the mining lease area (Yes / No)?
NA
If Yes,
e. Beneficiation / washing Technology NA
f. Capacity NA
7 Details of Seams if applicable
a. No. of seams NA
b. Thickness of seams to be worked on NA
c. Maximum Thickness of Seams (meters) (if
not applicable, may write NA)
NA
8 Details of Mining Lease
a. Details of Mining Lease NA
b. Upload Letter of Intent (Upload pdf only) NA
c. Date of Execution of Mining Lease with
Reference Number
NA
d. Validity of Mining Lease NA
e. Upload Copy of Executed Lease deed valid
as on Date (Upload pdf only)
NA
f. Earlier Renewals (Multiple entries
allowed0
NA
Uploaded Copy of Earlier Lease Date of Renewal
9 OB (Over Burden) Management (Only if Mining
Method: Opencast)
a. Details of External Dumps NA
i) No. of OB Dumps NA
ii) Total Area (in Hectare) NA
iii) Height (in meter) NA
iv) Quantity (in Million Cubic meter) NA
v) No. of year back fill up NA
b. Details of Internal Dump
i) No. of Internal Dumps NA
ii) Total Area (in Hectare) NA
iii) Height (in meter) NA
iv) Quantity (in Million Cubic meter) NA
10 Details of Topsoil Management
a. Quantity of Topsoil excavation during the
entire life of the mine (in Million Cubic
NA
Page 22 of 75
meter)
b. Quantity of Topsoil proposed for utilization
for reclamation during the entire life of the
mine (in Million Cubic meter)
NA
c. Quantity of Topsoil proposed for utilisation
for other activities during the entire life of
mine (in Million Cubic meter)
NA
11 Details of Final Mine Void (Only if Mining Method:
Opencast)
a. Area (in Hectare) NA
b. Depth (in meter) NA
c. Volume (in Million Cubic meter) NA
12 Details of Quarry (Only if Mining Method:
Opencast)
a. Final Void of (hectare) NA
b. At a Depth of (meter which is proposed to
be converted into a Water Body.)
NA
c. Total Quarry Area (ha) NA
13 Details of Transportation
a. In Pit/Underground to Surface NA
b. Surface to Siding/Loading NA
c. Transportation / Conveyor Details NA
14 Details of Land Usage (Pre-Mining)
Land Use Within
ML Area
(Hectare)
Outside ML
Area
(Hectare)
Total
Agriculture Land
Forest Land
Waste Land
Grazing Land
Surface Water Bodies
Settlements
Others (Specify)
15 Details of Transportation
a. In Pit/Underground to Surface NA
b. Surface to Siding/Loading NA
c. Transportation / Conveyor Details NA
16 Details of Land Usage (Pre-Mining)
Land Use Within ML
Area
(Hectare)
Outside ML
Area
(Hectare)
Total
Agriculture Land
Forest Land
Waste Land
Grazing Land
Surface Water Bodies
Settlements
Others (Specify)
17 Details of Land Usage (Post-Mining) NA
Land Use Plantation Water Body Public Use Others
Excavation/Quarry
Top Soil Storage
External OB dumps
Internal OB dumps
Roads
Built Up Area
(Colony/Office)
Green Belt
Page 23 of 75
Virgin Area
Other
Total
18 Details of Reclamation (Only if Mining Method:
Opencast) Total Afforestation Plan shall be
Implemented Covering of Mining. This will include:
NA
a. External OB Dump (in hectare) NA
b. Internal OB Dump (in hectare) NA
c. Quarry (in hectare) NA
d. Safety Zone (in hectare) NA
e. Final Void of (in hectare) NA
f. At a Depth of (meter which is proposed to be
converted into a Water Body.)
NA
g. Density of Tree Plantation per ha (in no.) NA
h. Other in ha (such as Excavation Area along
ML Boundary, along Roads and
Infrastructure, Embankment Area and in
Township Located outside the Lease etc.)
NA
i. Total afforestation plant (in hectare) NA
19 Status of Progressive Mining Closure Plan (For
Expansion Project only)
NA
a. Implementation of Various Activities as per
Approved Progressive Mine Closure Plan (in
Bar Chart) (pdf) (upload pdf only)
NA
b. Any Deviation from the Approved
Progressive Mine Closure Plan
NA
c. Total Area Excavated (in hectare) NA
d. Total Area Backfilled after Excavation (in
hectare)
NA
e. Total Area Reclaimed (in hectare) NA
20 Actual Coal/Ore Production vis-à-vis sanctioned
capacity Since inception (Multiple Entries Allowed)
NA
Financial year Sanctioned
Capacity as
per EC
(MTPA)
Sanctioned
capacity as per
CTO
Sanctioned
capacity as
per
approved
Mining
Plan
Actual
Production
Excess
Production
Beyond the
EC/CTO/Mining
plan Sanctioned
Capacity
(MTPA)
II Whether proposal is for Thermal Project (including captive
power plant and Waste Hear Recovery Plant) (Yes / No)?
No
If yes,
1 Specific of the Plant
a. Technology proposed (Supercritical, Sub-
Critical, CFBC, AFCB, PFBC, IGCC,
Incineration, Pyrolysis, Gasification, Bio –
methanation, others)
NA
b. Plant Load Factor (%) NA
c. Station Heat Rate (Kcal/Kwh) NA
d. Steam Rate / Flow Rate NA
e. Boiler Temperature NA
f. Boiler Pressure NA
g. Type of Stack (Single flue / Bi-flue / Tri-flue) NA
h. No. of Stacks NA
Stack ID Stack
height (m)
Stack
Diameter at
exit (m)
Exit
Velocity of
stack gas
(m/s)
Exit
temperature
of stack gas
(° C)
Page 24 of 75
2 Details of fuel linkage (please specify if multiple
linkage are involved)
NA
a. Type of linkage (Linkage / Fuel Supply
Agreement / e-auction / MoU / LOA /
Captive / Open market / Others)
NA
b. Quantity of linkage granted NA
c. Date of Linkage NA
d. Duration of linkage NA
3 Details of Transportation of fuel
Details / Mode Distance (km) Quantity (TPA)
Rail
Road
Pipeline
Conveyor
Other mode (please specify)
4 Details of Fuel Characteristics
a. Gross Calorific Value (Kcal/Kg) NA
b. Ash content (%) NA
c. Sulphur Content (%) NA
d. Moisture (%) NA
e. Mercury (mg/kg) NA
f. Fixed Carbon (%) NA
g. Volatile Matter (%) NA
5 Details of Cooling System
a. Type of cooling system: Air cooled/water
cooled
NA
b. Type of draft: Natural draft/Forced draft NA
c. Type of air circulation: Parallel flow/counter
flow
NA
d. Cycles of Cooling (COC) NA
e. Water requirement for cooling (m3/day) NA
f. Boiler blow down temperature NA
II
I
Whether proposal is for River Valley & Hydroelectric
Project (Yes / No)?
No
If yes,
1 Sub Sector: (Multipurpose Project / Hydroelectric
Project / Irrigation Project)
NA
2 Name of River NA
3 Whether Cumulative Impact Assessment and
Carrying Capacity Study of River Basin Carried Out?
(Yes / No)
No
If yes,
a. Status of Cumulative Impact Assessment and
Carrying Capacity Study of River Basin:
(Recommended / Not Recommended)
NA
If Recommended NA
b. Details of Cumulative Impact Assessment and
Carrying Capacity Study of River Basin
NA
c. Upload Relevant Documents (Upload pdf
only)
NA
4 Type of Project: (Construction of Dam Barrage / Run
of the River / Lift Irrigation Scheme)
NA
5 Dam Height (meter) if applicable NA
6 Dam Length (meter) if applicable NA
7 Total Submergence Area (hectare) NA
8 Details of Gross Command Area (GCA) (hectare) NA
9 Details of Irrigation Command Area (ICA) (hectare) NA
Page 25 of 75
10 Details of Culturable Command Area (CCA)
(hectare)
NA
11 Total Command Area (hectare) NA
12 Powerhouse Installed Capacity NA
a. Type of Powerhouse: (Underground /
Surface)
NA
b. Capacity (megawatts) NA
c. No. of Tunnels NA
d. No. of Units NA
e. Bank of River: (Left / Right / Both) NA
13 Generation of Electricity Annually
a. Quantity of Generation of Electricity
Annually (in Giga Watt Hours (GWh)
NA
b. Water availability at various percentages NA
Percentage Water availability
(Cusecs)
Dependable year Remarks
At 50%
At 75%
At 90%
c. Machine Availability (%) NA
d. Cost of Electricity Generation (in INR) NA
e. Internal Rate of Return (%) NA
f. Year of achievement of Internal Rate of
Return
NA
14 Catchment Area Treatment Plan (Upload PDF) NA
15 Muck Management Plan
a. Upload Muck Management Plan in PDF NA
b. Total Excavation Muck (Cubic Meter) NA
c. Utilized for Construction (Cubic Meter) NA
d. No. of Muck Disposal sites NA
e. Total Muck Disposal Area (Ha) NA
16 Fishery Development and Management Plan
a. Upload Fishery Development and
Management Plan in PDF
NA
b. No. of Fingerlings NA
c. No. of Fish Species NA
d. Name of the umbrella Fish Species (Scientific
Name)
NA
17 Status of Environmental Flow
Season Average Inflow (in
Million Cubic meter)
Percent of Flow
Lean
Non – Lean
Monsoon
Non - Monsoon
18 Free Flow Stretch (km) NA
19 Approval of Central Water Commission
a. Approval Reference No. NA
b. Date of Approval NA
c. Upload Copy of Approval (Upload pdf only) NA
20 Approval of Central Electricity Authority
a. Approval Reference No. NA
b. Date of Approval NA
c. Upload Copy of Approval (Upload pdf only) NA
21 Details of Coffer Dam (upstream ) if applicable
a. Quantity of the material (m3) NA
b. Length of the dam (m) NA
c. Quantity of muck to be used (m3) NA
Page 26 of 75
d. Quantity of borrow material to be used (m3) NA
e. Decommissioning plan (upload in PDF) NA
22 Details of Coffer Dam (downstream) if applicable
a. Quantity of the material (m3) NA
b. Length of the dam (m) NA
c. Quantity of muck to be used (m3) NA
d. Quantity of borrow material to be used (m3) NA
e. Decommissioning plan (upload in PDF) NA
IV Whether the proposal is Infrastructure project (Yes / No)? No
If Yes
1 Details of Building Construction
a. Maximum Height of the Building (Meters) NA
b. Total No. of Flats to be Build NA
c. No. of Buildings NA
d. Total plot area (sqm) NA
e. Total Built up area (sqm) NA
2 Foreshore Facilities And/or Marine Disposal
a. Whether Project Involves Foreshore
Activities and/or marine Disposal (Yes / No)?
No
If Yes,
b. Upload Shoreline Study (Upload pdf only) NA
c. Type of Cargo NA
d. Quantity of Cargo NA
e. Control Measures of Cargo NA
f. Dust Control Measures NA
g. Quantum NA
h. Quantity of Dredging (Cubic meter per day) NA
i. Type of Dredging Material NA
j. Disposal of Dredge Material NA
k. Details of Outfall Diffusers NA
l. No. of Dilution Expected NA
m. Distance at which the outlet will Reach
Ambient Parameters
NA
n. Details of Monitoring at outfall NA
o. Copy of NoC from PCB in case of Marine
Disposal (Upload pdf only)
NA
3. Rain Water Harvesting
a. No. of Storage NA
b. Capacity NA
c. No. of Recharge Pits NA
d. Capacity NA
4. Parking
a. Details of 4-Wheeler/2-Wheeler Parking NA
5. Energy Saving Measures
a. Source/Mode NA
b. Percentage NA
c. Quantity NA
6. Other Details
a. Details of impact on Water Bodies and
Drainage patters of catchment area, if any
NA
b. Details of Traffic Density Impact Assessment
and Modelling Study (Upload pdf only)
NA
c. In case of Underground Tunnel projects
below the Forest Land Subsidence Impact
Study report (Upload pdf only)
NA
7. Type of Industries to be established with Industrial
Estate as per their category A/B
Sl. No. Type of Industry No. of Units Category A/B
Page 27 of 75
8. Length of the alignment in case of highway projects NA
9. Details Bridges/ROB/Interchanges, Flyovers, Vehicle
Underpass and Pedestrian Underpass (in case of
Highway Projects)
NA
a. Total No. of Bridges NA
b. Total No. of ROB NA
c. Total No. of Interchanges NA
d. Total No. of Flyovers NA
e. Total No. of Vehicle Underpass NA
f. Total No. of Pedestrian Underpass NA
g. Details of other utilities rail and road
corridors
NA
36 Details of Court Cases if any
a. Whether there is any Court Cases pending against the
project and/or land in which the project is proposed
to be set up (Yes / No)?
No
If Yes,
b. Name of the Court (District Court / High Court /
NGT / Tribunals / Supreme Court of India)
NA
If name of Court: (Districts Courts, High Courts,
NGT, Tribunals)
c. Name of the Sub-Court NA
d. Case No. NA
e. Orders/Directions of the court, if any and its
relevance with the proposed project
NA
f. Case Details NA
g. Upload Court Order if any (Upload pdf Only) NA
37 Details of direction issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)
Act / Water (Prevention & Control of Pollution Act
a. Whether any direction issued under Environment
(Protection) Act / Air (Prevention & Control of
Pollution) Act / Water (Prevention & Control of
Pollution) Act (Yes / No)?
No
If Yes,
b. Details of directions issued under Environment
(Protection) Act / Air (Prevention & Control of
Pollution) Act / Water (Prevention & Control of
Pollution) Act
NA
c. Upload copy of direction issued under Environment
(Protection) Act / Air (Prevention & Control of
Pollution) Act / Water (Prevention & Control of
Pollution) Act
NA
d. Compliance status of directions
36 Details of EIA Consultant
a. Have you hired Consultant for preparing documents
(Yes / No)?
Yes
If No.
(i) Reason for not engaging the Consultant NA
If Yes,
(i) Accreditation No.
(ii) Name of the EIA Consultant M/s. Aqua-Air Environmental Engineers
Pvt. Ltd
(iii) Address 403, Centre Point, Nr. Kadiwala School,
Ring Road, Surat - 395002
(iv) Mobile No. 99044 33995
(v) Landline No. 0261 2460854/3048586/2461241
(vi) E-mail Id [email protected]
Page 28 of 75
(vii) Category of Accreditation (Eligible for
Category A / Eligible for Category B)
Stay Order from High Court
(viii
)
Sector of Accreditation -
(ix) Validity of Accreditation -
(x) Upload Certificate of Accreditation certified
by QCI / NABET (Upload pdf Only)
-
39 Documents to be attached
I If Project type is New / Expansion / Modernization / one-
time capacity expansion for coal mining:
No
a. Upload Copy of EIA / EMP Report NA
b. Upload Copy of Risk Assessment Report NA
c. Upload Copy of Feasibility Report / Detailed Project
Report (DPR) / Detailed Engineering Report /
Detailed Conceptual Plan / Approved Mining Plan
(in case of Mining proposals) (Upload pdf only)
NA
d. Upload Copy of Final Layout Plan (Upload pdf only) NA
e. Upload Cover Letter (Upload pdf only and attach it
as Annexure-document of Cover Letter)
NA
f. Upload a copy of documents in support of the
competence/authority of the person making this
application to make application on behalf of the User
Agency (Upload pdf only and attach it as Annexure-
authorization)
NA
g. Upload copy of District Survey Report (for mining of
minor minerals only)
NA
Upload copy of Replenishment Study Report &
Baseline Survey data (for river sand mining
proposals only)
NA
h. Upload Additional File, if any (Upload pdf only) NA
II If Project Type is other than New / Expansion /
Modernization / one-time capacity expansion for coal
mining: -
No
a. Upload Copy of Feasibility Report/ Detailed Project
Report(DPR) /Detailed Engineering Report /Detailed
Conceptual Plan (Upload pdf only)
NA
b. Upload Copy of Final Layout Plan (Upload pdf only) NA
c. Upload Cover Letter(Upload pdf only and attach it as
Annexure-document of Cover letter)
NA
d. Upload a copy of documents in support of the
competence/authority of the person making this
application to make application on behalf of the User
Agency (Upload pdf only and attach it as Annexure-
authorization)
NA
e. Upload Additional File, if any (Upload pdf only) NA
f. Upload Updated Form1 (Upload pdf only) NA
40 Undertaking
a. I hereby give undertaking that the data and
information given in the application and enclosures
are true to be best of my knowledge and belief and I
am aware that if any part of the data and information
found to be false or misleading at any stage, the
project will be rejected and clearance given, if any to
the project will be revoked at our risk and cost. In
addition to above, I hereby give undertaking that no
activity / construction / expansion has since been
taken up
Complied
b. Name Mr. Ramesh D. Chodvadia
c. Designation Director
Page 29 of 75
d. Company M/s. Anmol Antioxidants Pvt. Ltd.
e. Address Survey No. 35 & 36, Behind HGI
Foundary, Village: Baska-389350, Tal:
Halol, Dist: Panchmahal, Gujarat
*****
Page 30 of 75
Annexure – 1
Toposheet
Page 31 of 75
Annexure – 2
KML FILE
Annexure-GPS FILE.kml
Page 32 of 75
Annexure – 3
TOR Letter
Page 33 of 75
Page 34 of 75
Page 35 of 75
Page 36 of 75
Page 37 of 75
Page 38 of 75
Page 39 of 75
Page 40 of 75
Page 41 of 75
Annexure-4
Minutes of Public Hearing
Page 42 of 75
Page 43 of 75
Page 44 of 75
Page 45 of 75
Page 46 of 75
Page 47 of 75
Page 48 of 75
Page 49 of 75
Page 50 of 75
Page 51 of 75
Page 52 of 75
Page 53 of 75
Page 54 of 75
Page 55 of 75
Page 56 of 75
Page 57 of 75
Page 58 of 75
Page 59 of 75
Page 60 of 75
Page 61 of 75
Annexure-5
Advertisement of Public Hearing
Time of India Dated 10/05/2018
Page 62 of 75
Annexure – 6
Consent to Operate
Page 63 of 75
Page 64 of 75
Page 65 of 75
Page 66 of 75
Page 67 of 75
Annexure-7
List of Raw Material
Existing
SR.
NO. Name of Raw Materials
CAPACITY
(KGS/Month)
1. Betamethasone 42
2. 1,3 dibromo propene 1231
3. 1,4 dioxane 621
4. 16 Hydroxy prednisolone 33
5. 19 hydroxy-4-androst-3,17-dione 179
6. 5 tr(Tetraene Acetate) 103
7. 8 dm (16 alphamethyl 17,21 dihydroxy 9,11 epoxy Pregna 1,4 diene 3,20
dione) 24
8. Acetic Acid 26
9. Acetic Anhydrate 31
10. Acetone 894
11. Acetylene gas 91
12. Androstenedione 212
13. Bep (betamethasone-17-propionate) 52
14. Betamethasone 192
15. Butyaldehyde 13
16. Charcoal 64
17. Chloroform 469
18. Comium trioxide 61
19. Cromic Acid 9
20. db 11(16alphamethyl 17,21 dihydroxy 9,11 epoxy Pregna 1,4 diene 3,20 dione) 29
21. Dexamethasone 42
22. Diflorasone 32
23. Dimethyl foramide 1230
24. Ethyl acetate 7
25. Formaldehyde 4681
26. Furoyl chloride 11
27. HCl (Hydrochloric Acid) 1826
28. Hexane 35
29. hf acid (Hydrofluoric Acid) 351
30. hyflow 76
31. Isopropyl alcohol 85
32. Isopropyl ether 56
33. K2CO3 (Potassium carbonate) 267
34. Lithium chloride 137
35. Mdc (Methylene Dichloride) 842
36. Melamine 2416
37. Methanol 1436
38. Mibk (methyl isobutyl ketone) 225
39. MSC (Methane Sulfonyl chloride) 109
40. Pet. Ether 81
41. Potassium carbonate 4406
42. Potassium hydroxide 1040
43. Ppc (Pyrophosphoryl Chloride) 109
44. Prednisolone 59
45. Propionic anhydride 83
46. Pthalamide 3846
47. Ptsc (p-Toluene Sulphonic Acid) 26
48. Pyridine 324
49. Sodium borohydrate 22
50. Sodium hydroxide 271
51. Sodium metabisulphide 2265
52. Sulfuric Acid 398
Page 68 of 75
Proposed
53. TEA (Tri ethyl Amine) 43
54. TEOF (Triethyl ortho fromate) 129
55. Tetrahydrofuran 260
56. Tmop (Trimethyl Orthopropionate) 56
57. Triethyl orthopropionate 86
58. Triethyl orthobutyrate 25
SR.
NO. Name of Raw Materials
CAPACITY
(MT/Month)
Proposed
GROUP-A
1. Acebrofylline
1. Acefylline 11.85
2. Toluene 70.50
3. Ambroxol base 18.90
4. DMF 30.00
2. Ambroxol Hydrochloride
1. Toluene 72.00
2. 2 Amino 3,5 dibromo benzaldehyde 22.20
3. Trans-4-Amino cyclohexanol 9.00
4. Methanol 72.00
5. Sodium Borohydride 3.60
6. Activated Carbon 1.20
7. Methanolic HCl 12.90
3. Amlodipine Besylate
1. Phthaloyl Amlodipine 32.63
2. Mono Methyl Amine 50.25
3. Methanol 131.25
4. Ethyl Acetate 92.63
5. Benzene Sulfonic Acid 11.25
6. Carbon 2.25
4. Bupropion Hydrochloride
1. Toluene 75.00
2. 3-Chloro-2’-Bromo Propiophenone 30.00
3. tert butyl amine 10.50
4. 20% Methanolic HCl 24.30
5. Iso Propyl Alcohol 60.00
6. Carbon 0.90
5. Celecoxib
1. 4 SPH 21.00
2. Dione Derivative 19.50
3. Toluene 84.00
4. Carbon 1.50
6. Doxofylline
1. Theofylline 26.10
2. 2-Bromomethyl-1,3-dioxolane 24.30
3. Sodium Carbonate 8.40
4. Dimethyl Formamide (DMF) 72.00
5. Carbon 0.30
7. Drotaverine Hydrochloride
1. 3,4-Diethoxy phenylacetic acid 16.50
2. 3,4-Diethoxy phenyl ethyl amine 15.00
3. Toluene 90.00
4. Sodium Hydroxide 1.50
5. Phosphorous oxychloride 13.80
6. IPA 45.00
GROUP-B
Page 69 of 75
8. Etoricoxib
1. Ketosulfone 25.50
2. DMF 75.00
3. CDT Salt 27.90
4. Potassium tert Butoxide 12.90
5. Toluene 60.00
6. Acetic Acid 9.00
7. IPA 45.00
8. Carbon 0.90
9. Flubiprofen
1. 2,4-Difluoronitrobenzene 26.40
2. Diethyl methyl malonate 28.50
3. Sodium Hydroxide 23.70
4. Dimethylformamide 29.40
5. Toluene 161.40
6. Palladium Catalyst 0.60
7. Hydrogen 1.50
8. Methanol 86.40
9. Benzene 19.80
10. Copper Powder 4.50
11. Sodium Nitrite 14.70
12. Acetic Acid 13.50
13. Conc HCl 80.40
14. Carbon 0.30
10. Glibenclamide
1. Sulfonamide Derivative 24.30
2. Ammonia 37.50
3. Cyclo Hexyl Isocyanate 8.40
4. Acetone 243.90
5. Sodium Hydroxide 3.90
6. Conc HCl 13.20
7. Carbon 1.50
11. Phenazopyridine Hydrochloride
1. Aniline 12.38
2. Conc HCl 19.50
3. Sodium Nitrite 9.38
4. 2,6 Diamino Pyridine 13.88
5. Acetone 75.00
6. HCl gas 5.10
12. Phenyl Ephrine Hydrochloride
1. m Hydroxy Acetophenone 33.90
2. Ethyl Acetate 49.50
3. Bromine 42.00
4. Toluene 169.50
5. N Methyl benzyl Amine 54.90
6. IPA.HCl 31.50
7. Palladium carbon 1.20
8. Methanol 100.50
9. Liq Ammonia 60.00
10. L Tartaric Acid 33.90
11. IPA 69.90
12. Acetic Anhydride 33.00
13. Sulfuric Acid 7.20
14. Methanolic HCl 30.00
15. Carbon 0.90
13. Quetiapine Fumarate
1. Dibenzo-1,4-thiazepine one 17.40
2. Thionyl chloride 15.00
Page 70 of 75
3. Toluene 75.00
4. Piperazin ethoxy ethanol 13.80
5. Ethanol 90.00
6. Fumaric Acid 4.50
7. Acetic Acid 3.00
14. Telmisartan
1. 1,7'-Dimethyl-2'-propyl-2,5'-bibenzimidazole 19.50
2. Methyl 4'-(bromomethyl) biphenyl-2-carboxylate 19.80
3. Sodium carbonate 9.60
4. DMF 120.00
5. Methanol 99.00
6. Sodium hydroxide 3.60
7. Conc HCl 11.40
8. Carbon 0.60
15. Valsartan
1. Bromo OTBN 22.50
2. L Valine 10.50
3. Methanol 60.00
4. Thionyl Chloride 12.45
5. Ethyl Acetate 75.00
6. Conc HCl 17.25
7. Acetone 90.00
8. Valeryl Chloride 10.88
9. MDC 75.00
10. Sodium Azide 9.75
11. Caustic lye 3.75
12. Carbon 1.50
GROUP-C
16. Bisoprolol Fumarate
1. 4-hydroxy benzyl alcohol 3.75
2. 2- Isopropoxy ethanol 3.50
3. Amberlyst-15 1.25
4. Sodium Carbonate 3.50
5. Sodium Hydroxide 1.50
6. Epichlorohydrin 2.88
7. Toluene 27.50
8. Sodium borohydride 0.38
9. Methanol 31.25
10. Isopropyl amine 2.75
11. MDC 21.25
12. Acetone 40.00
13. Fumaric Acid 3.25
14. Carbon 0.30
17. Brimonidine Tartrate
1. Chorobenzene 80.00
2. 5-Bromo-6-thiouredo quinoxaline 8.00
3. Ethylene diamine 5.00
4. Isopropyl alcohol 20.00
5. Conc HCl 25.00
6. Caustic Lye dilute 40.00
7. Methanol 90.00
8. L Tartaric Acid 5.50
9. Carbon 1.00
18. Capacitabine
1. 5 Fluoro Cytosine 5.00
2. MDC 75.00
3. 5-Methyltetrahydrofuran-2,3,4-triyl triacetate 10.75
4. Methanol 90.00
Page 71 of 75
5. n Pentyl Chloroformate 11.25
6. Conc HCl 8.00
7. Caustic lye 5.00
8. Carbon 0.50
9. Ethyl acetate 62.50
10. n Heptane 2.50
19. Cinacalcet Hydrochloride
1. Trifluoro methyl Cinnamic acid 7.50
2. Methanol 30.00
3. Raney Nickel 1.30
4. Toluene 15.00
5. Boric Acid 0.30
6. Naphthyl ethyl amine 5.80
7. Sodium Borohydride 1.80
8. MDC 7.50
9. Conc HCl 12.50
10. Carbon 0.80
20. Donepezil Hydrochloride
1. 2-[(1-Benzyl-4-piperidyl)methyl]-5,6-dimethoxy inden-1-one 10.75
2. Methanol 55.00
3. Palladium Carbon 0.55
4. Hydrogen 2500 M3
5. Toluene 37.50
6. IPA 20.00
7. Carbon 0.25
8. IPA HCl 9.15
21. Gemcitabin Hydrochloride
1. Dibenzoyl Lactum 32.50
2. Ethyl Acetate 125.00
3. Sodium bis(2-methoxyethoxy)- aluminumhydride 17.50
4. Tri ethyl amine 5.00
5. Methane Sulfonyl Chloride 32.50
6. Acetyl Cytosine 13.30
7. Trimethylsilyl chloride 2.30
8. Toluene 82.50
9. Liq Ammonia 17.50
10. Conc HCl 33.80
11. Acetone 25.00
12. Carbon 0.50
22. Glimepiride
1. Sulfonamide Derivative 10.00
2. Trans Iso Cyanate 6.00
3. Acetone 100.00
4. Potassium Carbonate 7.50
5. Methanol 40.00
6. Conc HCl 16.30
7. Carbon 2.50
23. Ivabradine Hydrochloride
1. Potassium Carbonate 2.40
2. Acetone 20.00
3. IDDB 9.00
4. MBC.HCl 6.00
5. Toluene 30.00
6. Palladium on Carbon 0.80
7. IPA 12.00
8. Conc HCl 15.00
9. Methanol 60.00
10. Carbon 1.00
Page 72 of 75
24. Nebivolol Hydrochloride
1. 6-Fluoro-2-(oxiran-2-yl)-3,4-dihydro-2H-chromene 10.00
2. Benzyl amine 3.25
3. TBAB 1.00
4. Toluene 30.00
5. IPA 37.50
6. Palladium on Carbon 0.25
7. Methanol 40.00
8. Carbon 0.50
9. HCl Gas 1.75
25. Pirfenidone
1. Di methyl formamide 22.50
2. Bromo benzene 10.80
3. Potassium Carbonate 5.50
4. 5-Methyl-1H-pyridin-2-one 1.90
5. Copper Oxide 7.00
6. Toluene 16.00
7. Sodium Hydroxide 3.00
8. Conc HCl 9.00
26. Sofosbuvir
1. Phenyl Phosphorodichloridate 5.25
2. (S)-Isopropyl 2-Amino propanoate hydrochloride 4.50
3. Potassium carbonate 4.25
4. DMF 20.00
5. TBAB 0.50
6. Ethyl Acetate 30.00
7. 1-((2R,3R,4R,5R)-3-fluoro-4-hydroxy-5-(hydroxymethyl)-3-ethyltetrahydro-
furan-2-yl)pyrimidine-2,4(1H,3H)-dione 6.25
8. Methanol 25.00
9. Carbon 0.50
27. Terbinafine Hydrochloride
1. Naphthyl methyl chloride 6.25
2. Methyl amine 4.00
3. Toluene 30.00
4. 1 Chloro 6,6 Dimethylhept-2-en-4-yne 5.75
5. Potassium Carbonate 3.50
6. DMF 37.50
7. IPA 20.00
8. HCl gas 2.25
9. Carbon 0.50
28. Ursodeoxycholic acid
1. 3-hydroxy-7-ketocholanic acid 10.80
2. Butanol 22.50
3. Sodium metal 1.50
4. Phosphoric acid 85% 9.30
5. Imidazole 2.30
6. Methanol 47.50
7. Sodium Hydroxide 1.50
8. Conc HCl 10.50
GROUP-D
29. 2 Amino Phenyl phenyl Sulfide
1. Thio Phenol 25.60
2. 2 Nitro Chloro Benzene 34.40
3. Caustic Flakes 11.20
4. Raney Nickel 0.80
5. Methanol 160.00
30. 2-Amino-3,5-dibromobenzaldehyde
1. Methyl Anthranilate 24.00
Page 73 of 75
2. Methanol 216.00
3. Bromine 25.60
4. THF 68.00
5. Sodium Borohydride 4.80
6. Toluene 96.00
7. Manganese dioxide 23.20
31. Dibenzo[b,f][1,4]Thiazepin-11(10H)-One
1. 2 Amino phenyl phenyl sulfide 38.00
2. Poly Phosphoric Acid PPA 120.00
3. Ethyl Chloro formate 25.20
32. 4 Methyl Acetophenone
1. Acetyl Chloride 26.00
2. Toluene 48.00
3. Aluminum Chloride 64.00
4. Conc HCl 28.00
33. 2-Chloro-1,3-bis(dimentylamino)trimethinium hexafluorophosphate
1. Dimethylformamide 14.40
2. Chloroacetyl chloride 16.00
3. Phosphorus Oxychloride 22.00
4. Caustic Flakes 26.40
5. Hexafluoro phosphoric acid 36.00
34. 2,3-Dibenzoyl-D-Tartaric acid (DBDT)
1. Benzoyl Chloride 35.60
2. D Tartaric Acid 21.20
3. Toluene 60.00
35. Ethyl Trifluoro Acetate
1. Trifluoro Acetic Acid 34.40
2. Ethanol 20.00
3. Sodium Carbonate 1.60
4. Sulfuric Acid 4.80
36. m Phenoxy benzyl alcohol
1. m Phenoxy Benzaldehyde 39.92
2. Nickel Catalyst 0.20
37. p Methoxy Phenyl Acetonirile
1. 4 Methoxy Benzaldehyde 41.60
2. Nickel Catalyst 0.80
3. Hydrogen gas 11200 M3
4. Nitrogen 800 M3
5. Conc HCl 96.00
6. Toluene 80.00
7. Sodium Cyanide 14.40
8. Sodium Chloride 4.80
38. Phthaloyl Amlodipine
1. Ethyl-4-(2-phthalimido) ethoxy acetoacetate 28.00
2. o Chloro Benzaldehyde 13.20
3. Acetic Acid 4.00
4. Methyl 3 Amino Crotonate 11.20
5. Methanol 120.00
39. Sulfanilamide
1. Acetanilide 36.00
2. Chloro Sulfonic Acid 62.40
3. Ammonia Solution 116.00
4. Conc HCl 48.00
5. Soda Ash 22.40
4. 3-Trifluoromethyl Cinnamic Acid
1. 3 Trifluoromethyl Aniline 32.00
2. Conc HCl 53.20
3. Sodium Nitrite 16.00
Page 74 of 75
4. Acrylonitrile 11.60
5. Caustic Flakes 10.00
6. Conc Sulfuric Acid 14.00
GROUP-E
41. Glipizide
1. Sulfonamide Derivative 8.00
2. Cyclo Hexyl Iso Cyanate 3.50
3. Potassium Carbonate 6.00
4. Acetone 80.00
5. Methanol 60.00
6. Carbon 0.25
7. Conc HCl 16.00
42. Modafinil
1. 2-[(Diphenyl methyl)sulfanyl] acetamide 12.00
2. Acetic Acid 16.25
3. Hydrogen Peroxide 6.75
4. Methanol 37.50
43. Mycophenolate Mofetil
1. Mycophenolic acid 7.63
2. 2 Morpholinoethanol 5.75
3. PTSA 0.38
4. Ethanol 37.50
44. Tadalafil
1. Carboxylate Intermediate 11.38
2. Methanol 50.00
3. Methyl Amine 14.75
45. Tranexamic Acid
1. Benzoate derivative 14.50
2. Sodium Methoxide 4.13
3. Methanol 45.00
4. Ruthenium 0.25
5. Hydrogen gas 7500 M3
6. Nitrogen 750 M3
7. Potassium hydroxide 5.25
8. Conc HCl 16.25
9. Carbon 0.50
46. 5-(1-Carboxyethyl)-2-Phenylthio-Phenylacetic Acid
1. 2 Phenylthio 5 Propionyl Phenyl Acetic Acid 10.70
2. Toluene 40.00
3. TriethylFormate 7.70
4. Zinc Dust 1.00
5. Bromine 7.50
6. Carbon 0.30
47. Zaltoprofen
1 5(1-Carboxyethyl)-2-Phenylthio-phenylacetic Acid 11.67
2 Poly Phosphoric Acid 30.00
3 EDC 23.33
4 Carbon 0.67
Page 75 of 75
Annexure-8
Application for Permission to Abstract Ground Water