André Augustinus 16 June 2003DCS Workshop 3 Acknowledgements and apologies Thanks to all detector groups that provided me with input for this overview Apologies for the very short notice
Citation preview
DCS Workshop
André Augustinus16 June 2003
Detector DCS status
Overview and news
16 June 2003DCS Workshop 2André Augustinus
Overview Status of URD’s Hardware and layout
• Overview of the detectors sub systems• Cabling overview
Operational aspects• Control Hierarchy• Error situations and interlocks
Future• Prototyping in detectors and planning• Plans in central team
Other news Detector presentations
16 June 2003DCS Workshop 3André Augustinus
Acknowledgementsand apologies
Thanks to all detector groups that provided me with input for this overview
Apologies for the very short notice
16 June 2003DCS Workshop 4André Augustinus
Overview Status of URD’s Hardware and layout
• Overview of the detectors sub systems• Cabling overview
Operational aspects• Control Hierarchy• Error situations and interlocks
Future• Prototyping in detectors and planning• Plans in central team
Other news Detector presentations
16 June 2003DCS Workshop 5André Augustinus
User Requirements Status of the URDs and other sources of information
URD
ITS-pixel Recent URD; regular information exchange
ITS-drift Basic URD, no recent update
ITS-strip Basic URD, no recent update. No recent news
TPC Regular information exchange
TRD Recent URD; regular information exchange
TOF Some information, lack of written information
HMPID Regular information exchange
16 June 2003DCS Workshop 6André Augustinus
User Requirements Status of the URDs and other sources of information
URD
PHOS Incomplete URD
PHOS-CPV Basic URD
Muon-Trk Recent URD; regular information exchange
Muon-Trg Regular information exchange
FMD No URD (yet), but information exchange
T0 No URD (yet), some information since last WS
V0 No URD (yet), good contact since last WS
16 June 2003DCS Workshop 7André Augustinus
User Requirements Status of the URDs and other sources of information
URD
PMD No URD, very limited contact
ZDC No URD, very limited contact
ACORDE Early stage, limited contact
EMC Early stage, regular contact
Infrastructure Basic URD, central team
16 June 2003DCS Workshop 8André Augustinus
Overview Status of URD’s Hardware and layout
• Overview of the detectors sub systems• Cabling overview
Operational aspects• Control Hierarchy• Error situations and interlocks
Future• Prototyping in detectors and planning• Plans in central team
Other news Detector presentations
16 June 2003DCS Workshop 9André Augustinus
Overview ofdetector sub-systems
Will try to go quickly, concentrate on things that might need clarification
Will use overview drawings as last meeting Included all drawings for reference
AndréAugustinus
Cavern
Inside magnet
Counting room
10DCS Workshop 16 June 2003Detector
CAEN
CAEN OPCserver
PVSS II PVSS II
Detector
Wiener
PCI-CANWiener OPCserver
Ethernet
User interface
Database(s)
OPCclient
DIMclient
20
120
1..4
PVSS II
CoolingPlant
PLC
SchneiderOPCserver
1
1
4
High Voltage Low Voltage Detector Cooling
PVSS IIOPC client
PVSS IIOPC client
ITS-pixel
E C
HV LV
E
[FSM?]C
ontro
l roo
m
(AC
R)
Detector
10
PCI-VMEDIMserver
FEE
On-detectorelectronics
VME(wiener?)
2
PCI-VME
Optics
PCI-CANWiener OPCserver
PVSS IIOPC client
C1 or 2
360
Crate Control
DDL
16/06/03
VR board(12 VR each)
240
LV20
JTAG
20?
Number of CAN busses will depend on performance
[to be tested]
AndréAugustinus
Cavern
Inside magnet
Counting room
11DCS Workshop 16 June 2003Detector
CAEN
CAEN OPCserver
PVSS II PVSS II
Detector
AREM
DIM or OPCserver
Ethernet
User interface
Database(s)
OPCclient
DIMclient
288520
PVSS II
CoolingPlant
PLC
SchneiderOPCserver
1
6 6
High Voltage Low Voltage Detector Cooling
PVSS IIOPC client
PVSS IIOPC client (?)
ITS-drift
E
HV LV
E
[FSM?]C
ontro
l roo
m
(AC
R)
Detector
?
DIMserver
FEE
On-detectorelectronics
72*12
10/03/03
E
PCI-CANWiener OPCserver
PVSS IIOPC client
C
VME(wiener?)
2..4
DDL
Optics
VR
?
CAEN can be moved to CR; at the cost of longer HV cables [cost issue]
Where does these twisted pair go?
To VME?
Crate Control
AndréAugustinus
Cavern
Inside magnet
Counting room
12DCS Workshop 16 June 2003Detector
CAEN
CAEN OPCserver
PVSS II PVSS II
Detector
CAEN(?)
CAEN OPCserver
Ethernet
User interface
Database(s)
OPCclient
DIMclient
450144
PVSS II
CoolingPlant
PLC
SchneiderOPCserver
11 5
High Voltage Low Voltage Detector Cooling
PVSS IIOPC client
PVSS IIOPC client
ITS-strip
E E
HV LV
E
[FSM?]C
ontro
l roo
m
(AC
R)
Detector
?
?DIMserver
FEE
On-detectorelectronics
PCI-CANWiener OPCserver
PVSS IIOPC client
C?
?
Crate Control
FEROM(VME? wiener?)
8+
?? OPCserver
PVSS IIOPC client
I/O device(PLC,Wago,ELMB?)
Detector
Temp. monitoring
??
DDL
28/02/03
No commentsso farCan these CAEN be moved to CR?Can these CAEN be moved to CR?
LV: Is Arem-Pro still an option?
AndréAugustinus
Cavern
Inside magnet
Counting room
13DCS Workshop 16 June 2003Chambers
ISEG
PCI-CANISEG OPCserver
PVSS II PVSS II
Chambers
Wiener
PCI-CANWiener OPCserver
Ethernet
User interface
Database(s)
RCU
DIMserver
OPCclient
DIMclient
108288
1..3 1..22 ?
PVSS II
Chambers,detector
ELMB
1..18
~400?
PVSS IIRS232
HVrod
Heinzinger
4?
1
CoolingPlant (ch)
PLC
SchneiderOPCserver
1?
18?
3
22
1
216
High Voltage Low Voltage FEETemp. Monitor Chamber Cooling Very High Voltage
PVSS IIOPC client
PVSS IIOPC client
PCI-CANELMB OPCserver
PVSS IIOPC client
TPC(1)
C C
HV LV
EC E
HV
S
[FSM?]C
ontro
l roo
m
(AC
R)
108?
Chambers,detector
44
DD
L
16/06/03
EthernetSwitch
EthernetSwitch
?
?
E
E
ProfiBus is still a possible alternative
Controls interface under study
AndréAugustinus
Cavern
Inside magnet
Counting room
14DCS Workshop 16 June 2003
Ethernet
HVrod
“box”
?DIMserver (?)
?
12?
4
VHV Curr. Monitor
TPC(2)
CoolingPlant (rods)
PLC
Schneider/SiemensOPCserver
1
VHV rod Cooling
ThermalScreen(s)
PLC
18
Schneider/SiemensOPCserver
1?
Thermal Screen(s)
?DIMserver (?)
?
Laser calibr. syst.
PCI-ProfibusOPCserver (?)
2?
Pulser system
PS Laser
Mirrors,cameras
?
SchneiderOPCserver
Gas system
PLC
ELMBGas
E E E
CP
HVrod
4
CoolingPlant (TS)
Detector
P
Chambers
Gatingpulser
72?
Calibrationpulser
16/06/03
216
URD is being written
AndréAugustinus
Cavern
Inside magnet
Counting room
15DCS Workshop 16 June 2003Detector
ISEG
PCI-CANISEG OPCserver
PVSS II PVSS II
Detector
Wiener
PCI-CANWiener OPCserver
Ethernet
User interface
Database(s)
DCS board
DIMserver
OPCclient
DIMclient
18*(12+18)1080
1..10 1..50 1
PVSS II
10
50
540
High Voltage Low Voltage FEE
PVSS IIOPC client
PVSS IIOPC client
EthernetSwitch
540
EthernetSwitch
x
SchneiderOPCserver
Gas system
PLC
ELMBGas
[FSM?]
C C E E
E
EHV LV
TRDC
ontro
l roo
m
(AC
R)
CoolingPlant
PLC
SchneiderOPCserver
1?
Detector Cooling
E
Detector
?
Detector
?
DA
TA 2*540
16/06/03
Distribution Box
x
Network topology still under study
What kind of distribution box is this?
AndréAugustinus
Cavern
Inside magnet
Counting room
16DCS Workshop 16 June 2003Detector
CAEN
CAEN OPCserver
PVSS II PVSS II
Detector
CAEN(?)
Ethernet
Database(s)
OPCclient
DIMclient
360?
3600
18
4
?
High Voltage Low Voltage
PVSS IIOPC client
User interface
PVSS II
SchneiderOPCserver
Gas system
PLC
ELMBGas
E
CP
E E
HV
LV
TOFC
ontro
l roo
m
(AC
R)
[FSM?]
distribution180
HV 180
CAEN OPCserver
PVSS IIOPC client
DC-DC
LV
360
DIMserver
FEE
DRM
CoolingPlant
PLC
SchneiderOPCserver
1?
Detector Cooling
?
E
Detector
?
Detector
?
E
72?
PCI-CANWiener OPCserver
PVSS IIOPC client
C
VME(wiener?)
Crate Control
?
?
DDL
28/02/03
No realcomments so far
TOF presentationin a moment
AndréAugustinus
Cavern
Inside magnet
Counting room
17DCS Workshop 16 June 2003Detector
CAEN
CAEN OPCserver
PVSS II PVSS II
Detector
Wiener
PCI-CANWiener OPCserver
Ethernet
Database(s)
LiquidCirculation
OPCclient
DIMclient
12649
?
On-detectorelectronics
70
1 17
High Voltage Low Voltage Liquid Circulation Temp. Monitor
PVSS IIOPC client
PVSS IIOPC client
?? OPCserver
PVSS IIOPC client
SiemensOPCserver
PLC1
?
User interface
PVSS II
SchneiderOPCserver
Gas system
PLC
ELMBGas
E
CP
EE C
HV LV
HMPIDC
ontro
l roo
m
(AC
R)
[FSM?]
I/O device(PLC,Wago,ELMB?)
?
CoolingPlant
PLC
SchneiderOPCserver
1?
Detector Cooling
E
Detector
?
Detector
?
Detector
?
10/03/03
VME+NIM
PCI-CANWiener OPCserver
?
1+1
Crate Control
PVSS IIOPC client
C
?
Can these CAEN be moved to CR?
(were originally projected in CR)
AndréAugustinus
Cavern
Inside magnet
Counting room
18DCS Workshop 16 June 2003Detector
CAEN(?)
CAEN OPCserver
PVSS II PVSS II
Detector
Wiener(?)
PCI-CANWiener OPCserver
Ethernet
Database(s)
OPCclient
DIMclient
??
?
On-detectorelectronics
?
? ?
High Voltage Low Voltage Temp. Monitor
PVSS IIOPC client
PVSS IIOPC client
?? OPCserver
PVSS IIOPC client
User interface
PVSS II
E C
HV LV
PHOSC
ontro
l roo
m
(AC
R)
[FSM?]
I/O device(PLC,Wago,ELMB?)
?
CoolingPlant
PLC(?)
OPC/DIMserver (?)
?
Detector Cooling
?
E
Detector
?
RCU
PCI-ProfibusDIMserver
?
10-20
FEE
E
DD
L
28/02/03
?
Can these CAEN be moved to CR?
Following activities in TPC
AndréAugustinus
Cavern
Inside magnet
Counting room
19DCS Workshop 16 June 2003Detector
CAEN
CAEN OPCserver
PVSS II PVSS II
Detector
Wiener
PCI-CANWiener OPCserver
Ethernet
Database(s)
OPCclient
DIMclient
4016?
?
On-detectorelectronics
?
1 5?
High Voltage Low Voltage Temp. Monitor
PVSS IIOPC client
PVSS IIOPC client
?? OPCserver
PVSS IIOPC client
User interface
PVSS II
SchneiderOPCserver
Gas system
PLC
ELMBGas
E
CP
E C
HV LV
PHOS-CPVC
ontro
l roo
m
(AC
R)
[FSM?]
I/O device(PLC,Wago,ELMB?)
?
Detector
?
28/02/03
?
Can this CAEN be moved to CR?
AndréAugustinus
Cavern
Counting room
20DCS Workshop 16 June 2003Detector
CAEN
PVSS II PVSS II
Detector
Wiener
PCI-CANWiener OPCserver
Ethernet
Database(s)
OPCclient
DIMclient
328
?
?
Detector
?
28
High Voltage Low Voltage Environment monitor
PVSS IIOPC client
PVSS IIOPC client
?? OPCserver
PVSS IIOPC client
User interface
PVSS II
SchneiderOPCserver
Gas system
PLC
ELMBGas
E
CP
E C
HV
LV
Muon-TrkC
ontro
l roo
m
(AC
R)
[FSM?]
I/O device(PLC,Wago,ELMB?)
?
PCI-CANWiener OPCserver
PVSS IIOPC client
C
VME(wiener)
1
Crate Control
1
Geometrymonitor
DIMserver (?)
? ?
Geometry
Air/Watercooling
PLC(?)
OPC/DIMServer (?)
?
Detector Cooling
E
Detector
?
Detector
?
16/06/03
?
PCI-CAN
CAEN OPC
Switch
192
HV
C
?1
140
Crocus(on-detector crates)
DD
L20
repeater3
C48
Purpose build HV switch.Need a closer look!
AndréAugustinus
Cavern
Counting room
21DCS Workshop 16 June 2003Detector
CAEN
CAEN OPCserver
PVSS II PVSS II
Detector
Wiener
PCI-CANWiener OPCserver
Ethernet
Database(s)
OPCclient
DIMclient
16100
?
Detector
?
2 2
High Voltage Low Voltage Environment monitor
PVSS IIOPC client
PVSS IIOPC client
?? OPCserver
PVSS IIOPC client
User interface
PVSS II
SchneiderOPCserver
Gas system
PLC
ELMBGas
E
CP
E C
HV LV
Muon-TrgC
ontro
l roo
m
(AC
R)
[FSM?]
I/O device(PLC,Wago,ELMB?)
?
Crate Control
Efficiencysystem
Detector
?
PCI-CANWiener OPCserver
PVSS IIOPC client
C
VME(wiener)
17
?
10/03/03
Can be moved to CR if really needed
AndréAugustinus
Cavern
Inside magnet
Counting room
22DCS Workshop 16 June 2003Detector
CAEN ?
PVSS II PVSS II
Pre-amps
CAEN ?
Ethernet
Database(s)
OPCclient
DIMclient
14070
1 1
High Voltage Low Voltage
User interface
PVSS II
HV
LV
FMDC
ontro
l roo
m
(AC
R)
[FSM?]
Crate Control
CAEN OPCserver
PVSS IIOPC client
CAEN OPCserver
PVSS IIOPC client
FEE
Digitizers
10
Air cooling
?
Detector Cooling
Detector
?
PCI-CANWiener OPCserver
PVSS IIOPC client
C
VME(wiener?)
?
10/03/03
10
FMD-RCUPCI? VME?
E E
PCI-ProfibusDIMserver
?E
20lvl0
E?
300?
DD
L
TTC
2
Following activities in TPC
?
Can this CAEN be moved to CR?
AndréAugustinus
Cavern
Inside magnet
Counting room
23DCS Workshop 16 June 2003
Detector(PMT)
CAEN(?)
PVSS II PVSS II
Detector(shoe box)
?
Ethernet
Database(s)
OPCclient
DIMclient
?24
? ?
High Voltage Low Voltage
User interface
PVSS II
HV LV
T0C
ontro
l roo
m
(AC
R)
[FSM?]
PCI-CANWiener OPCserver
PVSS IIOPC client
Crate Control
??
PVSS II?
??
PVSS II?
DIMserver
FEE
On-detectorelectronics
?
Laser system
?
Laser calibr. syst.
Detector
?
C
VME(wiener?)
?
?
10/03/03
Can be shared with V0
Following activities in TOF
AndréAugustinus
Cavern
Inside magnet
Counting room
24DCS Workshop 16 June 2003Detector
CAEN
PVSS II PVSS II
Ethernet
Database(s)
OPCclient
DIMclient
144+12
1
High Voltage
User interface
PVSS II
HV
V0C
ontro
l roo
m
(AC
R)
[FSM?]10/03/03
Crate Control
DIMserver
FEE
?
PCI-CANWiener OPCserver
PVSS IIOPC client
C
VME(wiener?)
4?
?
CAEN OPCserver
PVSS IIOPC client
E
PMT
Opticalfibers
Front-Endelectronics
Maybe shared with T0
AndréAugustinus
Cavern
Inside magnet
Counting room
25DCS Workshop 16 June 2003Detector
?
PVSS II PVSS II
Detector
?
Ethernet
Database(s)
OPCclient
DIMclient
5252
? ?
High Voltage Low Voltage
User interface
PVSS II
HV LV
PMDC
ontro
l roo
m
(AC
R)
[FSM?]
Crate Control
??
PVSS II?
??
PVSS II?
On-detectorelectronics
52
Temp. Monitor
?? OPCserver
PVSS IIOPC client
I/O device(PLC,Wago,ELMB?)
?
SchneiderOPCserver
Gas system
PLC
ELMBGas
E
CP
CoolingPlant
PLC
?
?
Detector Cooling
E
Detector
?
Detector
?
PCI-CANWiener OPCserver
PVSS IIOPC client
C
VME(wiener?)
?
?
28/02/03
No commentsso far
AndréAugustinus
Cavern
Counting room
26DCS Workshop 16 June 2003Detector
?
PVSS II PVSS II
Ethernet
Database(s)
OPCclient
DIMclient
50
?
High Voltage
User interface
PVSS II
HV
ZDCC
ontro
l roo
m
(AC
R)
[FSM?]
Crate Control
??
PVSS II?
PCI-CANWiener OPCserver
PVSS IIOPC client
C
VME(wiener?)
?
?
16/06/03
No commentsso far
AndréAugustinus
Cavern
Counting room
27DCS Workshop 16 June 2003Detector
?
PVSS II PVSS II
Detector
?
Ethernet
Database(s)
OPCclient
DIMclient
?128?
? ?
High Voltage Low Voltage
User interface
PVSS II
HV LV
Cosmics(ACORDE)
Con
trol r
oom
(A
CR
)[FSM?]
Crate Control
??
PVSS II?
??
PVSS II?
PCI-CANWiener OPCserver
PVSS IIOPC client
C
VME(wiener?)
?
?
28/02/03
No commentsso far
16 June 2003DCS Workshop 28André Augustinus
Summary For many detectors we have more or less
detailed information For a few detectors we are lacking even very
basic information
16 June 2003DCS Workshop 29André Augustinus
CablingBackground: End of the year the RB26 doors will be closed Need to know what cables will go through
• TPC, TRD, TOF Started an effort to capture cabling
information, based on what we know• Inspired by pixel cabling overview last meeting
16 June 2003DCS Workshop 30André Augustinus
Cabling I will present examples for a few sub-systems
Question: Do we think this is a useful activity and should
be continued?
31DCS Workshop 16 June 2003
PC
ISEG ECH238
3
EHQ F 020p18
MagnetDoor
UXRack xxx
Detector
C 1..3
? m
Device
TPC; high voltage 10/03/2003
? m
1..3 CANBus[16 lines per cable, CERN standard. Scem xxx ]
18
E
ControlPC
1 Ethernet
? m
18 cables
CR xRack xxx
Should be some patch panel somewhere…
32DCS Workshop 16 June 2003
PC
Wiener PL500F
3
2..7V / 115A?
MagnetDoor
UXRack xxx
Detector
C 1..22
? m
Device
TPC; low voltage 10/03/2003
? m
1..22 CANBus[under discussion ]
72
E
ControlPC
1 Ethernet
? m
CR xRack xxx
Should be some patch panel somewhere…
[under discussion ]
72?
72 bus bars
72(?) sense wires
33DCS Workshop 16 June 2003
PC
Wiener PL500
4
5V / 50A20
MagnetDoor
UXRack xxx
30 m
TPCend
Detector
C 1..4
? m
Device
VR
board
120
60
6 x
ITS-pixel; low voltage 10/03/2003
Internalpatch panel
6 m 3 m 1 m
1..4 CANBus
240 sense wires
180 T signal cables
[s = 6 mm2]
[s = 1 mm2]
[s = 25 mm2] [shared withHigh Voltage andtemperature monitoring]
20
E
ControlPC
1 Ethernet
? m
60 MCM extenders20 cables 120 cables (Vdd, gnd)
120 cables (Vmcm, gnd)
CR xRack xxx
Vdd, gnd, 2 senseVmcm, gnd, 2 sense3 T_mcm
120240
180
180 T signal cables?
180
20
20
JTAG
20 JTAG control cables?
16 June 2003DCS Workshop 34André Augustinus
Cabling Can this be useful? A repository of (DCS related) cabling
• Can be used as input to the installation team Needs input from the detectors ‘Later’ detectors can be inspired by ‘earlier’
detectors
16 June 2003DCS Workshop 35André Augustinus
CablingSpecial case: Ethernet at detector level Some detectors envisage Ethernet on/in the
detector: • TPC, TRD, TOF, PHOS, FMD, T0• More detail in Peter’s talk
Technical issues• Must work in magnetic field and radiation• What will be the best topology
16 June 2003DCS Workshop 36André Augustinus
Cabling “Managerial” issues
• How to interface with rest of network• Who is responsible for what
Many efforts going on in this field to tackle technical aspects• When things become more clear we should get IT
division involved• choice of equipment, managerial aspects
16 June 2003DCS Workshop 37André Augustinus
Overview Status of URD’s Hardware and layout
• Overview of the detectors sub systems• Cabling overview
Operational aspects• Control Hierarchy• Error situations and interlocks
Future• Prototyping in detectors and planning• Plans in central team
Other news Detector presentations
16 June 2003DCS Workshop 38André Augustinus
Controls HierarchyECS
DCS DAQ Trig
ITS TPC TRD …
SPD SDD SSD HV LV Cool
RB24 RB26
Sec1Sec2
Sec3
“Node”
=“Control Unit”
in FSM
16 June 2003DCS Workshop 39André Augustinus
Controls hierarchy Reflects the operation of your detector Each “node” can be operated independently
• Should define a “node” for each entity that has to be the ability to be operated independently (e.g. in the case of a calibration run)
A “node” contains the logic of interaction between its children
16 June 2003DCS Workshop 40André Augustinus
Controls HierarchyECS
DCS DAQ Trig
ITS TPC TRD …
SPD SDD SSD HV LV Cool
RB24 RB26
Sec1Sec2
Sec3
Will there be a reason to operate the ITS as one single entity?
and/orIs there a ‘strong’ interaction between the ITS detectors?
thenthis ITS node should be defined
16 June 2003DCS Workshop 41André Augustinus
Controls hierarchy The lowest node reflects the smallest part of
your detector that logically could be operated independently• Note that we talk operation here; this is not the
smallest part of the detector you can switch off (e.g. in case of a problem); that will always be possible on the channel level !
16 June 2003DCS Workshop 42André Augustinus
Controls HierarchyECS
DCS DAQ Trig
ITS TPC TRD …
SPD SDD SSD HV LV Cool
RB24 RB26
Sec1Sec2
Sec3
Does it make sense to operate a single TPC sector; or does one only operate one half of the TPC at the same time?
16 June 2003DCS Workshop 43André Augustinus
Controls hierarchy One should try to match the ‘smallest
operable part’ of your detector for all sub systems, especially if they have to be operated simultanously
Chamber
HV1a HV1b
LV1
If all HV has to be on to operate the chamber; or if LV can only be switched on if both HV is on, it makes no sense to define both HV as individual nodesBetter to define all HV as one node
16 June 2003DCS Workshop 44André Augustinus
Controls hierarchy For operation it would be very convenient to
have the same subdivision for DCS and DAQ• So that one can ‘partition’ part of your detector
and run in stand alone (e.g. for calibration); both DCS and DAQ
• It is not logical to be able to operate one half of your detector while in DAQ you can only read out the whole detector
• Or, if the DAQ can run one sector in stand-alone while the DCS is only able to operate half of the detector
16 June 2003DCS Workshop 45André Augustinus
Controls hierarchy You can define as many intermediate levels in
your hierarchy as you need For each node you will have to define
• the states it can have,• the commands it can accept, • the logical behaviour it should have
Giacinto will talk in more detail on Finite State Machines
16 June 2003DCS Workshop 46André Augustinus
Error situationsand Interlocks
Various levels of protection of your equipment Inside your equipment (hardware)
• E.g. a current exceeding a given value will result in switching off that channel (trip)
In the DCS system (software)
Program an action on any set of readings (within a sub system or across sub systems)• E.g. if HV on one part of a chamber goes off, switch off the
rest of the chamber• E.g. if a rise of temperature is measured, switch off LV
16 June 2003DCS Workshop 47André Augustinus
Error situationsand Interlocks
Interlock (hardware)
Can be inside or across sub systems, or even from outside the detector• A trip on one channel, force also other channels
to trip• If the gas system fails, switch off the HV• If the cooling system fails, switch of the LV• An alarm system can switch off all your systems
16 June 2003DCS Workshop 48André Augustinus
Error situationsand Interlocks
Software actions give high flexibility in their implementation (delay’s, special ramp down, can act on the channel level)• But: are intrinsically less reliable
Hardware action are less flexible and usually act in a more ‘crude’ way• But: are highly reliable
Difficult to get good things of both…
16 June 2003DCS Workshop 49André Augustinus
Error situationsand Interlocks
This means work for you… For each event analyse what is the impact on
your detector and equipment Define what action needs to be taken and
evaluate the risk if the action is not taken This gives an indication how the action could
be implemented (hardware or software)
16 June 2003DCS Workshop 50André Augustinus
Overview Status of URD’s Hardware and layout
• Overview of the detectors sub systems• Cabling overview
Operational aspects• Control Hierarchy• Error situations and interlocks
Future• Prototyping in detectors and planning• Plans in central team
Other news Detector presentations
16 June 2003DCS Workshop 51André Augustinus
Prototyping HV and LV
• Less than half of the detectors have ‘final hardware’ and started prototyping
• only few with Framework/PVSS Gas and Cooling
• Outsourced to CERN groups (except PHOS cooling)
• Various stages of progress• Some in production, others in design
16 June 2003DCS Workshop 52André Augustinus
Prototyping Other systems
• Various stages of progress• Concentrating mainly on functionality rather than
controls aspects• To be followed case by case
As always:• Let us know what you are doing, and any remarks
you have !
16 June 2003DCS Workshop 53André Augustinus
Detector (DCS) planning Some information on beam tests etc. Pre-installation information in central planning Very little information on DCS needs at the
various stages Please let us know your needs in controls for
your beam tests, lab tests, pre-installation etc.• So that we can plan our work and your support
16 June 2003DCS Workshop 54André Augustinus
Central team Good news: We finally got (temporary…) lab space
• We will set up all ‘common solutions’• These set-up’s can be used as demonstration and
for debugging purposes Involved in TPC tests Major ‘proof of concept’ during pre-installation
of TPC in 2004
16 June 2003DCS Workshop 55André Augustinus
More news An effort started to redesign the Framework
• Simplify the internals (easier maintenance)• Simplify for the users (panels etc.)• Further integration of FSM
Ready by the end of the year• Coincides with a new version of PVSS (version 3)
If you use the framework, it is now to let us know your comments and remarks !!!
16 June 2003DCS Workshop 56André Augustinus
More news Current framework can still be used
• Your own created panels will need to be adapted to the new Framework
For FSM, if you can, wait for new Framework• It’s configuration and use will be simplified
16 June 2003DCS Workshop 57André Augustinus
Overview Status of URD’s Hardware and layout
• Overview of the detectors sub systems• Cabling overview
Operational aspects• Control Hierarchy• Error situations and interlocks
Future• Prototyping in detectors and planning• Plans in central team
Other news Detector presentations