Anderson Point Project Schedule

Embed Size (px)

Citation preview

  • 8/10/2019 Anderson Point Project Schedule

    1/3

    ID TaskMode

    Task Name Duration Start Finish

    1 Anderson Point ParkEmbankment Repair

    46 days Wed 10/1/14 Wed 12/3/14

    2 Submitalls 17 days Thu 10/2/14 Fri 10/24/14

    3 Project Schedule 1 day Thu 10/9/14 Thu 10/9/14

    4 Schedule of Values 1 day Fri 10/10/14 Fri 10/10/14

    5 Emergency Contact List 1 day Fri 10/10/14 Fri 10/10/14

    6 Damages Claim Form 1 day Fri 10/10/14 Fri 10/10/14

    7 TESC 1 day Fri 10/10/14 Fri 10/10/14

    8 SPCCP 1 day Fri 10/10/14 Fri 10/10/14

    9 Mater ial submit tal s 17 days Thu 10/2/14 Fr i 10/24/14

    10 Pre-Construction Meeting 1 day Wed 10/1/14 Wed 10/1/14

    11 On site meeting 1 day Wed 10/1/14 Wed 10/1/14

    12 Notice to Proceed 1 day Mon 10/27/14 Mon 10/27/14

    13 Notice to Proceed 1 day Mon 10/27/14 Mon 10/27/14

    14 Mobilize 2 days Tue 10/28/14 Wed 10/29/14

    T T S M W F S T T S M W F S T T S M W F S T T S M 28, '14 Oct 5, '14 Oct 12, '14 Oct 19, '14 Oct 26, '14 Nov 2, '14 Nov 9, '14 Nov 16, '14

    Task

    Split

    Milestone

    SummaryProject Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual TaskDuration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-onlyExternal Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 1

    Project: Anderson Point ProjectDate: Wed 10/22/14

  • 8/10/2019 Anderson Point Project Schedule

    2/3

  • 8/10/2019 Anderson Point Project Schedule

    3/3

    ID TaskMode

    Task Name Duration Start Finish

    29 Wall Construction 20 days Thu 10/30/14 Wed 11/26/14

    30 Excavate for wall 3 days Thu 10/30/14 Mon 11/3/14

    31 Stockpile reuasablematerial from wallexcavation on site

    3 days Thu 10/30/14 Mon 11/3/14

    32 Construct Wall 18 days Mon 11/3/14 Wed 11/26/14

    33 Substantial Completion 6 days Wed 11/26/14 Wed 12/3/14

    34 Substantial Completion 1 day Wed 11/26/14 Wed 11/26/14

    35 Demobilization 3 days Mon 12/1/14 Wed 12/3/14

    36 Clean up 3 days Mon 12/1/14 Wed 12/3/14

    37 Demobilization ofequipment

    3 days Mon 12/1/14 Wed 12/3/14

    T T S M W F S T T S M W F S T T S M W F S T T S M 28, '14 Oct 5, '14 Oct 12, '14 Oct 19, '14 Oct 26, '14 Nov 2, '14 Nov 9, '14 Nov 16, '14

    Task

    Split

    Milestone

    SummaryProject Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual TaskDuration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-onlyExternal Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 3

    Project: Anderson Point ProjectDate: Wed 10/22/14