Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
This article outlines the main points to check during installation of load cells to control tensions while installing and service life, applied on bar and cable ground anchors as well as prestressing and post tensioning tendons. It is only a practical guide based on experience and is not intended
to replace any Engineers’ design.
However simple they may appear, load cell installations pose unexpected questions. These challenges include load range, alignment, positioning and diameter consistency, as well as
temperature effects, all of which will have significant impacts on the outcome.
No one load cell installation is the same and careful planning of each project should be carried to ensure a successful installation.
Anchor Load Cells Installation - considerations
Load cells are the preferred system to monitor anchor behaviour. The more complex the engineering
design laying behind the more meticulous and precise installation must be.
The main considerations are:
Type of structure to anchor
Expected anchor loads
Anchor head: dimensions and terminology
Anchor: bar and cable dimensions
Unexpected readings
NOTE: There are outstanding issues to be considered when installing load cells.
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
2
Item Considerations Possible solutions
Structural concrete elements
Compressive forces can be applied
to concrete elements either before
concrete casting, i.e. pre tensioning
at the precast concrete plant, or
once the concrete is casted, i.e.
post tensioning usually onsite.
Pre and post tensioning multi strand
anchor blocks are designed specifically
to the number of tendons / strands.
Load cells are used regularly to control
tensions applied to the tendons at the
precast concrete plant. In this use, the
difference between Outer (OD) and Inner
Diameters (ID) is usually small so the
available circular crown section is thin.
Ensure the dimensions of the load
cell will effectively fit to the anchor
block.
Frequency of load cell calibration
must be kept to once every six
months or higher when used in
production at the precast concrete
plant.
Ground Engineering structures
Tension load is used to stabilize
and to retain ground deformation
using bar or cable / strand anchors,
i.e. support and retaining walls,
slopes or embankments, bridge
abutments, slabs subjected to
under pressure, etc.
It is a priority to learn:
type of anchor that will be in
place, i.e. bar or cable anchor,
passive or active, above or below
groundwater level;
loads the anchoring element will
bear.
Temporary ground anchors are those
with a service life of up to two years.
Permanent ground anchors have a
service life longer than two years.
Chosen load cell type and
dimensions are a function of the type
of anchor and its service load.
Protection at the anchor head is
mandatory for service lifespans in
excess of two years.
Automatic data acquisition is of great
help for those spots difficult to
access or located in remote sites.
Strut monitoring
Loads in (excavation) struts can be
monitored using a load cell,
measuring the full load on the full
section of the strut.
It takes a lot of expertise to install a load
cell to monitor a strut.
Placing a load cell in a strut may alter
the loading conditions both in the strut
and in the cell.
Monitoring outcome from load cells
installed in a strut easily correlates to
measurements obtained using strain
gauges.
Strain gauges properly installed on a
strut give an idea about moments in
the element –flexion, compression,
torsion-, additionally to load.
TYPE OF STRUCTURE TO ANCHOR
NOTE: The kind of structure to anchor and the kind of anchoring element determine the
definitive design for the load cells.
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
3
Item Considerations
Type of anchor load cells
There are three types of load cells provided by
Geosense:
Hydraulic load cells;
Strain gauge load cells;
Vibrating Wire (VW) load cells.
The factors to take into account when deciding which load
cell type to use are:
Duration of monitoring;
Accuracy required;
Data logging requirement;
Robustness.
Possible solutions
Hydraulic load cells
These are low cost but they are the least accurate as they are significantly affected by temperature. Hydraulic load
cells are useful for monitoring anchors on long term projects where any changes in load are likely to be significant.
They can be upgraded to be data logged by attaching a Vibrating Wire (VW) or analogue pressure sensors. When
fitted with a Bourdon gauge they offer quick and simple readings.
Standard output from hydraulic load cells: manometer for pressure indication.
Strain gauge load cells
Should be used if dynamic monitoring is required. This is because they give a constant output and do not have to be
polled for information. Strain gauge load cells are very accurate over the short term but may be prone to drift in the
long term. This is due to glue drift of the attached sensors but also down to electrical drift of the sensors and other
electronic components. They can be easily and cheaply data logged and are, arguably, the easiest and cheapest to
use for wireless monitoring applications.
Output signal from strain gauge load cells: mV/V; Ω for thermistor if in place.
Vibrating wire (VW) load cells
These are the highest in cost. VW load cells are also the most robust and suitable for civil engineering applications.
Bearing this in mind, VW load cells certainly are our choice for loads of 1000 kN and bigger. Sensors used are
electromechanical, mechanically attached in the sensor, so they are very stable over the long term. Due to the fact
that each load cell has either three or six gauges, individually read, eccentric loading is also easily spotted. In terms of
accuracy, VW load cells are the equal of strain gauge load cells. VW load cells cannot be dynamically monitored.
Output signal from VW load cells: Hz or Digits; Ω for thermistor if in place.
TYPE OF STRUCTURE TO ANCHOR
NOTE: Service duration, precision needed, type of readings output, and robustness are
factors to consider when choosing a type of load cell.
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
4
NOTE: In case a load cell is installed, the anchor becomes a measurement anchor.
An anchor is an installation capable of transmitting an applied tensile load to a load
bearing structure or to the ground.
ground
retaining
structure
anchor head
load cell
load bearing
plates
TYPE OF STRUCTURE TO ANCHOR
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
5
NOTE: Ensure expected load range is fully understood and proper unloaded base readings
are taken right before installation.
Item Considerations Possible solutions
Capacity of the load cell
It is crucial to know the service
and maximum expected loads
at the anchoring element.
It is recommended that the chosen load
cell should work within 50% to 80% of
the calibrated range of the load cell.
In case it is found that the percentage
of the calibrated load to the design
load is over 100%, the load cell with the
next highest load range must be
chosen.
Base readings
In addition to the base reading
showing on the calibration
certificate the unloaded, onsite
base values must be known and
taken as base reference.
Onsite unloaded reading is the reference
value any future reading will be
subtracted to in order to get the actual
load. Both load and temperature must be
recorded.
Take several unloaded base readings
(load, temperature) right before
installation. With no significant
environment and temperature changes,
these base readings should all be within
±0.25% Full Scale F.S.
Test loads
Investigation test: a load test to
establish the ultimate load
resistance of an anchor.
Suitability test: a load test to
confirm that a particular anchor
design will be adequate in
particular ground conditions.
Acceptance test: a load test to
confirm that each anchor
conforms with the acceptance
criteria.
During all testing the load shall be
applied and released smoothly. Loading
velocity is a key factor to control during
stressing and destressing and will
certainly affect anchors’ behaviour.
Over range capacity for Geosense load
cells is +20% Full Scale F.S.
Always follow onsite written test
procedures approved by Client’s
Technical Representative.
Load cells should not be over loaded by
more than +50% F.S.
Anchor load cells’ readings –load and
temperature- and their times, strands’
displacements and any significant data
must be carefully recorded during
tensioning operations.
Linear versus polynomial
calculation
Depending on the kind of
output signal obtained from the
anchor load cell, values can be
calculated using a linear or a
polynomial conversion.
Due to environmental factors that may
affect the reading of a load cell, site base
readings should always be used as the
reference starting value, including load
(Hz/Digits, mV/V) and temperature.
Readings from the readout unit directly
display the average reading for the
vibrating wire or strain gauges active in
the load cell.
At the lower range of loading 1%↔10%
F.S., some anchor load cells appear to be
less precise compared to the same load
cell working in its mid load range.
Whenever beginning a new project, it is
interesting to use both linear and
polynomial calculations to compare the
values obtained, if possible.
If some extra degree of accuracy is
required, polynomial conversion shall
be used.
Conversion formulae and factors are
available in the calibration certificates
and in the corresponding manuals.
EXPECTED ANCHOR LOADS
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
6
NOTE: Check that design of anchor loading and anchor tests together with dimensions for
the hydraulic jack, load cell and load bearing plates are correct.
Item Considerations Possible solutions
Sizing
It is essential to choose the
right diameters for the load
cells before putting forward a
Purchase Order.
The important information for deciding
your load cell size is the outer diameter
OD of the bolt or cable anchor being
measured and the expected load at the
anchoring element.
Different manufacturers may have
different cell sizes for equivalent loads.
If the diameter of the bolt or cable
anchor is x, it is recommended that the
smallest load cell inner diameter ID be
IDmin = x + 5 mm .
Load distribution plates
To ensure load is applied
equally over the annular loading
surface of the cell.
Uneven or deformed load bearing plates
will affect the readings in the load cell.
For loads up to 4500kN, load bearing
plates should be 1”½ ↔ 2” thick.
Different types of load cells may need
one or two load bearing plates.
Hydraulic jack↔load cell
reading
Anchors are loaded using a
hydraulic jack. It is common
practice to make straight
comparisons between load
values showing on the jack to
loads measured by the load cell.
Outside diameters for multi strand
hydraulic jack and load cell should be the
same.
Ø jack < Ø load cell ≡ higher load values
Ø jack = Ø load cell ≡ true load values
Ø jack > Ø load cell ≡ lower load values
A fully comprehensive document is
needed onsite showing all the
dimensions and technical features for
the hydraulic jack.
Before used onsite, both the hydraulic
jack and the load cell should come with
their up-to-date Calibration Certificates.
Eccentric loading
Load is not applied at the axis
of the anchor + load cell
setting.
Eccentric loading will affect the readings
in the load cell as the load cell is under
higher loads in one portion with respect
to the other.
Effects are minimised by having several
sensors within the load cell and
averaging, the use of load bearing
plates and proper installation
procedures.
ANCHOR HEAD: DIMENSIONS
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
7
NOTE: Load cells are the stethoscopes for anchors.
ANCHOR HEAD: TERMINOLOGY
Anchor load cell and load bearing plates.
load cell
load distribution plates
anchor load bearing
plate / abutment plate
wedge plate
wedges
strands
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
8
NOTE: Expected loads and anchor dimensions must be understood to choose the right load
cell.
Terminology for a ground bar anchor.
Ground bar anchor terminology.
ANCHOR HEAD: TERMINOLOGY
bar anchor VW load cell
thread bar
anchor load bearing / abutment plate
load distribution plates
bearing plate
anchor nut
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
9
NOTE: To install a load cell on a cable anchor may take a little bit more than to install it on
a bar anchor.
Cable / strand ground anchor terminology.
ANCHOR HEAD: TERMINOLOGY
anchor nut
anchor load bearing / abutment plate
load distribution
plates
cables /
strands
bearing plate
cable anchor VW load cell
wedge plate
wedges
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
10
NOTE: It is advisable to double check any technical documents before ordering a load cell.
ANCHOR: BAR AND STRAND DIMENSIONS
load distribution
plates
cables /
strands
Item Considerations Possible solutions
Different sizes for bar and cable
anchors
Different bar and cable anchor
manufacturers have different sizes
for their anchoring elements.
Anchoring elements are manufactured
using different steels and overall designs.
It is advisable to double check anchor
bar, cable and head dimensions
before deciding for any load cell. All
technical documents must be at hand
when ordering anchor load cells.
The figures below are for information purposes only, not to be taken for granted or for calculation. Please check
manufacturer’s specifications and Project Technical requirements when going through design of anchors and / or
choosing a load cell.
BAR Ø
DSI Prestressing Steel GEWI Steel bar GEWI Plus Steel bar
Ø OD Yield Force Ø OD Yield Force Ø OD Yield Force
mm kN mm kN mm kN
15 159 16 100 18 170
20 283 20 157 22 255
26.5 523 25 245 25 329
28 308 28 413
32 764 32 402 30 474
36 967 35 645
40 1194 40 630 43 973
47 1648 50 980 57.5 1740
63.5 1758 63.5 2122
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
11
NOTE: It is advisable to double check technical specifications before ordering a load cell.
ANCHOR: BAR AND STRAND DIMENSIONS
load distribution
plates
cables /
strands
The figures below are for information purposes only, not to be taken for granted or for calculation. Please check
manufacturer’s specifications and Project Technical requirements when going through design of anchors and / or
choosing a load cell.
BAR Ø
Ischebeck hollow CTS/Titan Williams Form Eng. 150 KSI Williams Form Eng. B7X
Ø OD Yield Force Ø OD Min. Ultimate Str. Ø OD Yield Force
mm kN mm kN mm kN
30 471 - 583 26 567 32 210
40 592 - 597 32 834 32 294
52 546 36 1054 38 404
73 500 - 594 46 1734 51 677
103 500 - 572 57 2727
127 603 65 3457
130 550 75 4568 76 1466
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
12
NOTE: It is advisable to make sure load cell match Project Technical Requirements.
ANCHOR: BAR AND STRAND DIMENSIONS
cables /
strands
The figures below are for information purposes only, not to be taken for granted or for calculation. Please check
manufacturer’s specifications and Project Technical requirements when going through design of anchors and / or
choosing a load cell.
STRAND Ø 0.5" (13 mm) diam. - 7 wires per strand
0.6" (15 mm) diam. - 7 wires per strand
DSI Williams Form Eng.
# Strands Ultimate Str. Ø Wedge Plate # Strands Ultimate Load Ø Wedge Plate
kN mm kN mm
1 261 120 1 261 108
2 521 120 2 522 108
3 782 120 3 783 108
4 1043 120 4 1044 127
5 1303 143 5 1305 127
6 1564 143 6 1566 127
7 1825 143 7 1827 127
8 2085 141 8 2088 187
9 2346 161 9 2349 187
10 2610 187
11 2871 187
12 3128 161 12 3132 187
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
13
NOTE: Check points have to be allowed for onsite to make sure the system “anchor + load
cell” works properly.
Item Considerations Possible solutions
Unsynchronized readings
The reading on the jack is taken at
a different time from that taken on
the load cell. The strands are
tensioned using the jack, the
wedges are put in place and the
load locked.
The load applied by the jack diminishes
during the load wedge locking process.
In case the load is applied too fast, some
accommodation time is needed for all
the load to be distributed along the
anchoring element.
It is recommended to carry out Lift
Off Testing for load cell reading
versus hydraulic jack reading to
identify any loss of load transfer.
Hydraulic jack longer than the
load cell setting
This is prone to inaccurate load
measurement due to eccentric
loading, resulting in bending and
causing some friction between the
ram and the seal, i.e. binding of the
seal of the jack –see Anchor Head
Dimensions-.
The load is over registered by the jack,
often taken as under registering in the
load cell.
Load cells come calibrated from the
factory before use onsite. The
hydraulic jack ram has been used to
install many anchors after its
calibration, so it must be assumed
that the calibration certificate
corresponding to the load cell is
more up-to-date than the calibration
certificate for the hydraulic jack.
Hydraulic jack ram different
from load cell diameter
The ram size varies from the load
cell size –see Anchor Head
Dimensions-.
This causes bending of the distribution
plate which in turn causes over or under
measurement of load depending on the
ratio load cell / jack areas.
Match the load cell and the hydraulic
jack ram diameters. Usually, this is
not easy to achieve as we will have to
bear with the means available onsite.
Suitable, thick load distribution plates
must be used to distribute the load
as even as possible to the load cell –
Uniformly Distributed Load UDL-.
Temperature effects
Changes in environment
temperature will have several
effects on the readings registered
by the load cell.
Thermal influences are complex to
discern because it is not only the load
cell that is affected but any structural
elements surrounding the load cell, i.e.
brick, concrete or steel structures.
One way to understand the effects of
temperature changes is to record the
installed load cell readings together
with both ambient and cell
temperatures when no other changes
are taking place.
An option is to take the readings
always at the same time of the day,
preferably early morning right before
sunrise.
UNEXPECTED READINGS
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
14
NOTE: Eccentric loading must be avoided when installing load cells in anchors.
UNEXPECTED READINGS
Centred load cell in an anchor installation.
Eccentric load cell in an anchor installation.
Avoid eccentric loading!
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
15
NOTE: Changes in environment conditions will have several effects on the readings
registered by the load cell.
Item Considerations Possible solutions
Load cell is giving unstable
readings
Are the readings alright with a different
readout?
If yes then suspect low battery.
Are the load readings outside the range
of the load cell?
Make sure the expected loads and
the load cell range match.
Is there a source of electrical noise
nearby, such as a generator or a motor?
Have any electrical noise source
removed away.
Is there any significant temperature
effect?
See “Temperature effects” in this
document.
VW load cell: unstable readings Is the correct swept frequency being
used?
Check swept frequency coming from
readout and / or datalogger.
Strain gauge load cell: unstable
readings
Is the load cell part of an unexpected
electrical loop?
Check insulation resistance between
the cell body and any cable. The
reading should be >500 MΩ.
Manometer
Were manometer fitted check for
damage?
Check the needle return to zero with
no load.
Check for leaks on the cell.
Hydraulic load cell: unstable
readings
Vibrating Wire VW
Is the correct swept frequency being
used?
Check swept frequency coming from
readout and / or datalogger.
UNEXPECTED READINGS
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
16
NOTE: It is crucial to foresee convenient onsite conditions before installing load cells.
LOAD CELLS’ APPLICATIONS
Single strand hydraulic jacks tensioning an active, multi-stage ground anchor.
Multi strand hydraulic jack tensioning an active ground anchor with a load cell.
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
17
NOTE: Clean and tidy installations favour reliable readings.
LOAD CELLS’ APPLICATIONS
Strain gauge anchor load cell to monitor
a passive ground bar anchor.
Vibrating wire VW load cell installed to control an
active, multi-stage strand ground anchor (2/2).
Vibrating wire VW anchor load cell installation in
an active, multi-stage strand ground anchor (1/2).
Vibrating wire VW bar anchor load cell load to
monitor a ground bar anchor.
KNOWLEDGE ARTICLE MC, GC, TL 31/05/2017 V0.0
18
TYPE OF STRUCTURE Structure Ensure design for the anchor block and the load cell elements are
the same -OD & ID, load-.
Type of load cell Chose your load cell bearing in mind service load, kind of anchor
and lifespan.
ANCHOR LOADS Base reading Take a series of unloaded base readings right before onsite instal-
lation.
Load Follow approved onsite testing and loading procedures.
Loads below 10% F.S. may result in imprecise readings.
Load cells should not be overloaded by more than +50% F.S.
Linear ↔ polynomial cal-
culation Agree with the Client which one to use.
ANCHOR HEAD DIMEN-
SIONS Jack ↔ load cell reading ODs for jack and load cell should be the same.
Load bearing plates Bearing plate thickness should be 1”½ ↔ 2”.
Eccentric loading Always avoid eccentric loading. Having several sensors fitted in the
load cell and averaging minimises the effects of eccentric loading.
Bar and strand anchor Bar and cable anchor manufacturers produce anchoring elements
in different sizes.
UNEXPECTED READINGS Dimensions Anchor, load cell and hydraulic jack diameters must be consistent.
Temperature effects Take readings from anchor load cell always at the same time of the
day, preferably right before sunrise.
Types of sensors Load cells including a thermistor allow for more accurate tempera-
ture compensations.
Troubleshooting Check for easy to understand subjects when a load cell is giving
unstable readings.
NOTE: Positive installations need planning and good care onsite.
SUMMARY