Upload
trinhduong
View
214
Download
1
Embed Size (px)
Citation preview
Amir Sweater & Apparels Ltd.Sattar Bhaban, Bogabari Bazar
Baipan, Ashulia, Savar,23.937512N, 90.274135E
2nd April 2014
1
4
Outline calculations indicate high stresses in columns shown circled.
Detail Engineering Assessment required for building.
Factory Building
6
2,000 l
2,000 l 1,000 l
2 no. 2,000 litre and one 1,000 litre tanks mounted on 160mm thick flat slab at roof level.
Building Engineer to verify that the slab has been adequately designed to carry loading due to water tanks
Stair core
8
Level 4400mm high floor build-up in toilet area on flat slab
Building Engineer to check that the flat slab has been adequately designed to carry floor build-up loads
10
Building engineer to evaluate if the column has been designed for vehicle impact load, or provide adequate protection to column due to impact loading.
Double height column at risk of being accidentally struck by a vehicle.
Damage on the column observed suggest numerous incidents of the column being struck
12
Timber and bamboo rafters & purlins.
Building engineer to review roof design, particularly regarding stability in high wind conditions, and propose remedial measures as necessary.
14
Column arrangement varies between permit and survey drawings
Building permit drawing Survey drawing
18
Problems Observed
1 Column Stresses2 Water tanks on roof slab and slab build-up in toilet areas3 Columns at entrance exposed to impact from vehicles4 Stability of lightweight roof over stair core under high wind conditions5 Storage of materials on stairs is hindering escape route
19
Item No. Observation Recommended Action Plan Recommended Timeline
1 Column stressesFactory Engineer to review design, loads and column stresses in factory building
Immediate - Now
2 Column stressesVerify insitu concrete stresses by cores or existing cylinder strengths for ground floor columns or take 100mm dia. Cores from min. 4 no. columns
Immediate - Now
3 Column stressesA Detail Engineering Assessment of factory to be commenced immediately - see attached scope.
Immediate - Now
4 Column stressesProduce and actively manage a loading plan for all floor plates within the factory giving consideration to floor capacity and column capacity.
6-weeks
5 Column stresses Detail Engineering Assessment to be completed 6-weeks
6 Column stresses Produce accurate structural drawings for the building. 6-months
7Water tanks at roof level and slab build-up in toilet areas
Detail Engineering Assessment (see Item 1) to include assessment of tank loads on flat slab and slab build-up in toilet areas
Immediate - Now
8Water tanks at roof level and slab build-up in toilet areas
Detail Engineering Assessment to be completed. Tanks to be moved if required.
6-weeks
9Water tanks at roof level and slab build-up in toilet areas
Implement actions arising from Detail Engineering Assessment.
6-months
20
This Schedule develops a minimum level of information, Analysis and testing expected as part of a Detail Engineering Assessment.The Building(s) have been visually assessed and it is deemed necessary that a detailed engineering assessment be carried out by a competent Engineering Team employed by the factory Owner. This Request should be read in conjunction with the BUET developed Tripartite Guideline document for Assessment of Structural Integrity of Existing RMG Factory Buildings in Bangladesh (Tripartite Document), the latest version of this document should be referenced. T his document also gives guidance on required competency of Engineering Team.
We expect that the following will be carried out:1. Development of Full Engineering As-Built Drawings showing Structure, loading, elements, dimensions , levels, foundations and framing on Plan,
Section and Elevational drawings .2. The Engineering team are to carry out supporting calculations with a model based design check to assess the safety and serviceability of the building
against loading as set out in BNBC-2006, Lower rate provisions can be applied in accordance with the Tripartite Guidelines following international engineering practice, justification for these lower rate provisions must be made.
3. A geotechnical Report describing ground conditions and commenting on foundation systems used/proposed.4. A report on Engineering tests carried out to justify material strengths and reinforcement content in all key elements studied.5. Detailed load plans shall be prepared for each level showing current and potential future loading with all key equipment items shown with associated
loads.6. The Engineering team will prepare an assessment report that covers the following:
• As-Built drawings including• Plans at each level calling up and dimensioning all structural components • Cross sectional drawings showing structural beams, slabs, floor to floor heights, roof build-ups and Basic design information of the
structure• Highlight any variation between As-built compared to the designed structure• Results of testing for strength and materials• Results of geotechnical assessment and testing/investigation• Details of loading, inputs and results of computer modelling• Commentary on adequacy/inadequacy of elements of the structure• Schedule of any required retrofitting required for safety or performance of Structure
Any proposals for Retrofitting to follow guidance developed in the Tripartite Document
Detail Engineering Assessment
21
Item No. Observation Recommended Action Plan Recommended Timeline
10Column at entrance exposed
to impact from vehicles
As part of Detail Engineering Assessment (see Item 1), evaluate if column at entrance has been designed to withstand vehicular impact loading.
Immediate - Now
11Column at entrance exposed
to impact from vehiclesProvide permanent adequate protection to column as required following assessment.
6-weeks
12Column at entrance exposed
to impact from vehiclesEnsure that protection to column is maintained. 6-months
13Lightweight roof over stair
core
Building engineer to review design of roof over stair core, particularly in terms of stability under high wind conditions, and propose remedial measures as necessary.
6-weeks
14Lightweight roof over stair
coreImplement remedial works. 6-months
15 Storage of materials on stairsAll material storage on stairs to be removed immediately, in order to maintain a clear escape route.
Immediate - Now
16 Storage of materials on stairs Continue to ensure stairs are kept clear. 6-weeks
17 Storage of materials on stairs Continue to ensure stairs are kept clear. 6-months