Upload
buidat
View
218
Download
1
Embed Size (px)
Citation preview
American Bar Association
Forum on the Construction Industry
IMPLEMENTING DISPUTE RESOLUTION PROCEDURES
IN MULTI-PARTY CONSTRUCTION DISPUTES
Robert W. Wachsmuth, Esq. R. Daniel Douglass, Esq.
Glast, Phillips & Murray, P.C. Stites & Harbison, PLLC
219 East Houston Street 303 Peachtree Street, N.E.
Suite 400 2800 SunTrust Plaza
San Antonio, TX 78205 Atlanta, GA 30308
May 18-19, 2006
Paradise Point Resort - San Diego, CA
© 2006 American Bar Association
IMPLEMENTING DISPUTE RESOLUTION PROCEDURES
IN MULTI-PARTY CONSTRUCTION DISPUTES
Alternative Dispute Resolution (ADR) procedures are widely used as an efficient and
effective means of dealing with inevitable disputes in the construction industry. ADR
procedures are typically creatures of contract, relying upon the parties’ agreement for their
authority, applicability and enforceability. Most standard industry contract forms (e.g., AIA,
AGC, DBIA, EJCDC) include some form of proposed ADR procedures. Implementation of
contractual ADR procedures has been supported and facilitated by federal and state laws such
as the Federal Arbitration Act (FAA) and various enactments of the Uniform Arbitration Act
(UAA) and Uniform Mediation Act (UMA). Use of arbitration procedures is found in federal
government contracting as well as on private projects.
Over the years, some typical enforcement problems and issues have developed, such as refusal
to mediate, joinder of non-signatory parties in arbitration, forum and location disputes, and the
like. Awareness of these potential pitfalls can inform the drafting of better contract language
to minimize enforcement problems and maximize the benefits of ADR. Awareness of the
available remedies in the courts and under applicable laws and industry rules can also enhance
contract drafting and avoidance of enforcement problems.
A. Dispute Resolution Procedures Available
On private projects, the ADR options are limited only by the parties’ willingness to agree.
The options include informal negotiation, mediation, arbitration, Dispute Review Board
(DRB), and hybrids of the foregoing, including standard litigation. The standard industry
contracts forms have developed over the years to include several of these ADR options, both
in the design-bid-build delivery method and in the design-build approach.
ZZ997:99950:119424:1:ATLANTA 3
In the federal government contracting arena, the Alternative Dispute Resolution Act
establishes procedures for use of ADR to resolve claims against the government, but only with
the mutual agreement of the parties.1 While the typical procedure on appeal of a contracting
officer’s decision is an evidentiary hearing before an appointed hearing officer, mediation is
available if both parties agree. But the Court of Federal Claims will not force mediation or
other ADR procedures on the parties. In practice, Department of Justice attorneys have
seldom agreed to use ADR, although this may be changing in recent times.2 ADR procedures
are also available on international projects if included in the contract between the parties.
Arbitration is the long-standing common ADR mechanism for dispute resolution in
international transactions, but interest in western style mediation is being studied and
encouraged in Europe and China.
B. How Typically Addressed in Standard Contracts
The standard industry contract forms typically provide for resolution of disputes by mediation
and arbitration and sometimes include other procedures, such as architect’s decision or step
negotiations between the parties. For example, the 1997 AIA A201 General Conditions
provide for an initial decision by the architect, followed by mediation in accordance with the
AAA Construction Industry Mediation Rules, followed by binding arbitration in accordance
with the AAA Construction Industry Arbitration Rules.
The A201 document allows for, but also places limits on, consolidation or joinder. It
provides:
4.6.4 Limitation on Consolidation or Joinder. No arbitration
arising out of or relating to the Contract shall include, by
consolidation or joinder or in any other manner, the Architect,
the Architect’s employees or consultants, except by written
consent containing specific reference to the Agreement and
signed by the Architect, Owner, Contractor and any other person
or entity sought to be joined. No arbitration shall include, by
consolidation or joinder or in any other manner, parties other
than the Owner, Contractor, a separate contractor as described in
Article 6 and other persons substantially involved in a common
ZZ997:99950:119424:1:ATLANTA 4
question of fact or law whose presence is required if complete
relief is to be accorded in arbitration. No person or entity other
than the Owner, Contractor or a separate contractor as described
in Article 6 shall be included as an original third party or
additional third party to an arbitration whose interest or
responsibility is insubstantial. Consent to arbitration involving
an additional person or entity shall not constitute consent to
arbitration of a Claim not described therein or with a person or
entity not named or described therein. The foregoing agreement
to arbitrate and other agreements to arbitrate with an additional
person or entity duly consented to by parties to the Agreement
shall be specifically enforceable under applicable law in any
court having jurisdiction thereof.
This clause prevents joinder of the project architect without its consent. However, it permits
consolidation with or joinder of non-signatory parties that are substantially involved in the
dispute and necessary for complete relief. It also provides that consolidation or joinder is
specifically enforceable in any court having jurisdiction, facilitating liquidation agreements
and joinder provisions in subcontracts and purchase orders.
The 1997 AIA B141 Owner-Architect Agreement also provides for resolution of disputes by
mediation followed by arbitration, and expressly provides that no arbitration under the
Agreement shall include by consolidation or joinder of any person not a party to the
Agreement except by written consent of the Owner, Architect and other persons sought to be
joined. Thus, the AIA documents for a design-bid-build project contemplate possible joinder
of necessary parties and consolidation with other arbitration proceedings, but propose to
preclude joinder of the project architect without its written consent. The AIA documents
reference the AAA Construction Industry Arbitration Rules, Rule 7 of which provides for
consolidation or joinder if the parties’ agreement or the law provides for consolidation or
joinder.
The AGC Document No. 200 Owner-Contractor Agreement provides for step negotiations
between the parties, followed by mediation, and thereafter resolution by the method selected
ZZ997:99950:119424:1:ATLANTA 5
from a “Dispute Resolution Menu.” The AGC document also provides: “All parties
necessary to resolve a claim shall be parties to the same dispute resolution proceeding.
Appropriate provisions shall be included in all other contracts relating to the Work to provide
for the consolidation of such dispute resolution procedures.” Thus, the AGC document places
importance on the ability to join all necessary parties and recognizes the necessity of including
ADR and joinder provisions in other contracts on the project.
The EJCDC documents also include dispute resolution provisions, which are found in EJCDC
C-800 SC-16 Dispute Resolution. It provides six options for disputes resolution, including
various combinations of mediation, arbitration, litigation, step negotiation, and use of a third-
party neutral.3 Unlike the AIA documents, the EJCDC C-800 provides for joinder of the
design professional if necessary to resolve the dispute. It also provides for arbitration fees and
expenses to be shared equally by the parties.
The design-build delivery method has a different set of standard form contracts, which also
recognize the benefits of ADR procedures and the joinder of multiple parties or consolidation
of multiple proceedings. The 2004 AIA A141 Owner/Design-Builder Agreement provides for
initial resolution of disputes by a neutral jointly selected by the parties in the agreement, or by
the Owner if no neutral is selected. Thereafter, the dispute is referred to mediation followed
by binding arbitration. The A141 document also provides for consolidation with another
arbitration proceeding or joinder of other parties under certain circumstances. Joinder and
consolidation are limited to common issues of law or fact and persons or entities having a
direct contract with the Owner or Design-Builder which requires arbitration and does not
prohibit consolidation or joinder. The AIA B143 Design-Builder/Architect Agreement
similarly provides for mediation followed by binding arbitration and provides for
consolidation or joinder under similar circumstances.
ZZ997:99950:119424:1:ATLANTA 6
The DBIA Document No. 535 Owner/Design-Builder Agreement provides for step
negotiations between the parties to resolve disputes, followed by mediation and binding
arbitration. Mediation is conducted pursuant to the AAA Construction Industry Mediation
Rules, and arbitration is in accordance with the AAA Construction Industry Arbitration Rules.
The DBIA document also provides that any arbitration may be joined or consolidated with
another arbitration involving a person or entity necessary to resolve the dispute or
substantially involved in or affected by the dispute. It further provides that appropriate
provisions will be included in contracts with other parties on the project to require such
joinder or consolidation. The DBIA Document No. 540 Design-Builder/Designer Agreement
provides for resolution of disputes involving the Owner pursuant to the provisions of the
Owner/Design-Builder Agreement, and further provides that the design-builder and designer
will cooperate in the prosecution or defense of owner disputes and will accept the result of
such dispute resolution. For disputes not involving the Owner, the agreement provides for
step negotiations between the parties, followed by mediation and binding arbitration. The
arbitration agreement similarly provides for joinder or consolidation with other persons or
entities necessary to resolve the dispute or substantially involved in or affected by the dispute.
C. Typical Enforcement Problems
1. Refusal to Mediate
Mediation is often a prerequisite, and in many contracts a condition precedent to arbitration or
litigation of disputes. Since mediation is facilitated settlement negotiation, its success in
resolving a dispute depends upon the parties reaching agreement. There can be other benefits
from the mediation process, such as inexpensive exchange of information and enhanced
communication of positions, but the ultimate measure of success is resolution of the dispute.
If one party obstructs the process by refusing to attend or refusing to negotiate in good faith,
what remedies does the other party have? Is an action to compel mediation available, and
ZZ997:99950:119424:1:ATLANTA 7
would you want to use it? Is “good faith” enforceable or lack of “good faith” sanctionable?
Can a party’s refusal to attend or to negotiate in good faith provide grounds for waiver of
mediation as a condition precedent to arbitration or litigation? Finally, is it possible to join
other parties that are necessary to complete relief or that enhance the prospects for settlement
in the mediation process?
There appears to be a divergence among federal courts on whether to compel or waive
mediation as a condition precedent to arbitration in multi-step ADR clauses. In cases where
the court finds that the condition precedent of mediation or good faith negotiation has been
met, the court has compelled arbitration.4 If the condition precedent has not been met, the
courts have taken different approaches. Several courts have ordered the parties to submit the
dispute to mediation as a prerequisite to arbitration.5 Other courts have found a waiver of the
mediation requirement and compelled arbitration.6 In the Dimark Marketing case, when the
parties were unable to agree on a location for mediation, the court waived the mediation
requirement and compelled arbitration.
Two federal appellate courts have taken a different and more drastic approach, ruling that by
failing to request mediation in a multi-step ADR clause, the arbitration provision was never
triggered and the parties must continue in litigation.7 The surprising result of these decisions
is effectively a waiver of the contractually agreed multi-step ADR clause. In both cases, the
court observed that the FAA policy favoring arbitration does not override the stated wishes of
the contracting parties, which in both contracts provided for mediation prior to arbitration.
The language in the HIM Portland case was more specific in stating that mediation was a
“condition precedent to arbitration or the institution of legal or equitable proceedings by either
party.” The court in the Kemiron Atlantic case did not require such explicit language to find
that mediation was a condition precedent that had not been satisfied.
ZZ997:99950:119424:1:ATLANTA 8
It is arguable that the federal courts should not be wrestling with this issue at all. Rather, the
court should defer to an arbitrator on such questions of “procedural arbitrability” as whether a
condition precedent to arbitration, such as mediation, has been satisfied or waived.8
The United States Supreme Court has recognized a distinction between procedural
arbitrability issues and substantive arbitrability issues and has suggested that the former are
the province of arbitrators while the latter are proper for decision by the courts.9 The Wiley
decision has been recognized as a guide on handling procedural versus substantive
arbitrability issues, and federal courts have often ruled on substantive arbitrability issues while
deferring procedural arbitrability issues to the arbitrator.10
The Howsam decision referred to the Revised Uniform Arbitration Act of 2000 (RUAA),
which updated the Uniform Arbitration Act adopted by most states and which has been
approved by the American Bar Association, endorsed by the American Arbitration
Association and already adopted by several states.11
Section 6 of the RUAA codifies the
general rule in federal and state courts on arbitrability issues, providing that the court decides
whether an agreement to arbitrate exists or a controversy is subject to the agreement to
arbitrate, whereas the arbitrator decides whether a condition precedent to arbitrability has been
met and whether the contract containing the arbitration agreement is enforceable. The CPR
Institute for Dispute Resolution arbitration rules similarly grants the arbitrator authority to
decide procedural arbitrability issues.
The foregoing indicates that the question of whether to compel or waive mediation as a
condition precedent to arbitration should be left to the arbitrator and not decided by the court.
This approach would be consistent with the scenario in which one party delays or obstructs
mediation and the other party files an arbitration demand and attempts to proceed with
ZZ997:99950:119424:1:ATLANTA 9
arbitration. Under these circumstances, the mechanism is in place to appoint an arbitrator to
resolve any challenge based on failure to mediate, i.e., compel or waive mediation. However,
if the parties are in court because one party has filed a lawsuit and neither party has timely
pursued enforcement of the ADR clause, there is a distinct possibility that the court could find
a waiver of the ADR provisions. Obviously, the way to avoid this result is timely exercise of
the ADR rights in the contract.
While federal courts tend to follow the U.S. Supreme Court on procedural vs. substantive
arbitrability issues, the various state courts often decide procedural arbitrability issues such as
whether a party has waived arbitration, in the context of a motion to compel arbitration.12
One’s odds of getting a state court to defer to an arbitrator may be enhanced by filing an
arbitration demand before seeking to compel arbitration, so that there is an arbitrator
appointed or about to be appointed to whom the court can defer.
Another potential issue is the authority of the courts to compel mediation. The Federal
Arbitration Act (FAA) provides that a contract clause requiring the parties to “settle by
arbitration a controversy arising out of such contract … shall be valid, irrevocable, and
enforceable, save upon such grounds as exist at law or in equity for the revocation of any
contract.” 9 U.S.C. § 2. When presented with an issue covered by an arbitration agreement,
the courts are required to stay the litigation until arbitration has occurred on application of
either party. 9 U.S.C. § 3. The FAA does not expressly address “mediation.” But couldn’t a
court enforce performance of a condition precedent to achieve the purposes of the FAA?
Several federal courts have found that enforcement of a mediation clause or multi-step ADR
clause is within the scope of the FAA. In Fisher v. GE Medical Systems,13
the court found
that federal policy favors arbitration in a broad sense and mediation falls within that
preference for non-judicial dispute resolution. The court cited other federal court decisions
ZZ997:99950:119424:1:ATLANTA 10
for the proposition that the policy in favor of finality of arbitration is but one part of a broader
goal of encouraging informal dispute resolution, which is not limited to arbitration.14
Therefore, the FAA was broad enough to authorize enforcement of a mediation agreement.
Other courts have reached a similar result.15
As a practical matter, how much success is a party likely to have negotiating a settlement with
an unwilling counterpart? It has been argued that ordering a reluctant party to mediate
violates the first premise of mediation as a voluntary and consensual process.16
In court-
ordered mediation cases, most courts have found that good faith requires only a party’s
attendance, not meaningful participation, and sanctions have been imposed when a party
failed to attend without good cause.17
The more practical approach may be to minimize delay
by proceeding with an arbitration demand and letting the arbitrator decide whether to compel
mediation or deem the requirement waived.
Joinder can be an important issue in mediation, just as it is in arbitration (as discussed below).
One commentator has observed that the likelihood of a successful settlement of a construction
defect dispute is directly related to the involvement of all subcontrators and design
professionals who performed the work or provided the professional services that gave rise to
the defect claim, as well as their insurance carriers.18
It is a fact of life that disputes are
generally easier to settle when there are more pockets of money at the table. Since mediation
is subject to the agreement of the parties, it is wise to ensure that a consent to joinder or
consolidation in a construction contract applies to mediation as well as arbitration.
2. Joinder and Consolidation in Arbitration
Every construction lawyer knows that a dispute on a large construction project can involve
multiple parties, and a complete resolution can require joining multiple parties in a single
proceeding. A good example is water intrusion claims on a highrise condominium project.
ZZ997:99950:119424:1:ATLANTA 11
Water intrusion can involve roofing, glass and glazing, EIFS and other exterior enclosures,
and virtually every trade performing work on the project. The causes can involve defective
design, defective workmanship, or defective materials or products. As a result, the owner,
architect, general contractor, trade contractors and suppliers are potentially necessary parties
to dispute resolution. What begins as an owner-contractor dispute can involve nearly every
participant in the construction project.
The failure to join all potentially responsible parties in one proceeding can expose various
parties to the risks of duplicative expense and inconsistent results. If the owner litigates or
arbitrates with the architect in one forum and with the contractor in another, he is exposed to
the risk of the architect successfully defending based on poor workmanship and the contractor
prevailing based on design defects. The owner can be left holding the bag on remedial costs
when he may be the only blameless party in the process. Similarly, the general contractor will
be looking to pass through defective workmanship claims to subcontractors that performed the
work and defective material claims to the respective material suppliers. The inability to join
all necessary subcontractors and suppliers exposes the contractor to the same risk of
inconsistent results as the project owner.
Joinder and consolidation are related issues, but joinder is more problematic than
consolidation. Consolidation with another arbitration proceeding obviously presupposes that
all parties have signed arbitration agreements. Thus, the only question is whether those
arbitration agreements preclude, or should be presumed to preclude, consolidation with other
arbitrations involving other parties. Generally, the standard is whether there are common
issues of law or fact and the parties are necessary for complete relief. This standard is
reflected in the consolidation language found in standard industry form contracts.
ZZ997:99950:119424:1:ATLANTA 12
Joinder of other parties to an existing arbitration may involve parties that have not signed an
arbitration agreement. Since arbitration is a creature of contract, the presumption is that a
party cannot be compelled to join an arbitration proceeding if it is not a signatory to an
arbitration agreement with one of the parties. This is an important distinction between
arbitration and litigation, where the rules of civil procedure typically authorize a court to
compel joinder and consolidation under certain circumstances.19
Thus, a general contractor cannot compel a subcontractor to join its arbitration with the owner
or with another subcontractor if the subcontract does not contain an arbitration agreement.
Likewise, an owner cannot compel an architect to join an arbitration with the general
contractor if the architect’s agreement precludes joinder. Obviously, the most effective way to
ensure that all necessary parties can be joined is to ensure that all agreements on a
construction project provide for arbitration and for joinder or consolidation. The enforcement
problems arise in seeking consolidation where the contracts do not provide for consolidation,
and in seeking joinder of non-signatory parties.
3. Consolidation of Arbitrations
While a number of federal court decisions have recognized the courts’ power to consolidate
separate arbitration proceedings, more recent decisions have prohibited consolidation absent
consent. An example is United Kingdom, Ministry of Defense v. Boeing Co.,20
in which the
federal court was prohibited from ordering consolidation of arbitration proceedings arising
from separate agreements absent the parties’ agreement to consolidation despite the
proceedings involving similar questions of fact and law. The Second Circuit Court of Appeals
held that the “FAA does not authorize consolidation of arbitration proceedings unless doing so
would be in accordance with the terms of the agreement.”
ZZ997:99950:119424:1:ATLANTA 13
State courts have taken differing approaches to the issue. Some state courts have precluded
consolidation in the absence of express statutory authority or where the arbitration agreement
is silent on consolidation.21
Other state courts have recognized judicial authority to order
consolidation of arbitration proceedings, although it may be limited by the contract terms.22
Some states have enacted statutes expressly granting the courts authority to consolidate
arbitrations, while other states have enacted statutes granting arbitrators the authority to
consolidate arbitrations and join related parties.23
The revised Uniform Arbitration Act (RUAA) has proposed to address this issue by allowing
in section (10)(a) for application to a court to consolidate separate arbitration proceedings.
Under this provision, a court has discretion to order consolidation of separate arbitrations if
the claims arise from the same transactions, a common issue of law or fact creates the
possibility of conflicting decisions, and the prejudice from failure to consolidate outweighs the
risk of undue delay or prejudice to objecting parties.
Thus, without contractual language addressing the issue, a party is unlikely to compel
consolidation of separate arbitration proceedings in the federal courts and in certain state
courts, while the ability to obtain court ordered consolidation is enhanced in certain states.
These varying results highlight the importance of including appropriate contract language to
preserve the option of compelling consolidation of related arbitration proceedings.
4. Joinder of Non-Signatory Parties
Generally, a non-signatory party cannot be compelled to join an arbitration proceeding and
does not have standing to compel arbitration with a signatory party. However, some situations
have been recognized by the courts as justifying joinder of a non-signatory party in arbitration.
Theories supporting joinder of a non-signatory party include (1) incorporation by reference (2)
assumption, (3) agency, (4) veil piercing/alter ego, and (5) estoppel.24
ZZ997:99950:119424:1:ATLANTA 14
The “incorporation by reference” argument is often seen in two contexts. First, a “flow down”
clause in a subcontract may incorporate by reference the arbitration clause in the owner-
contractor agreement. For example, in JS&H Constr. Co. v. Richmond County Hosp.
Authority,25
a subcontract that incorporated by reference the general conditions of the prime
construction contract between general contractor and hospital authority made the
subcontractor subject to the arbitration provisions of the prime contract. Thus, one contract
drafting approach is to include a multi-party ADR provision in the owner-contractor
agreement and incorporate it by reference through a “flow down” clause in the architect and
subcontractor agreements.
Second, a surety performance bond that incorporates by reference the secured contract or
subcontract may render the non-signatory surety subject to an arbitration agreement in the
referenced contract or subcontract. For example, in Boys Club of San Fernando Valley, Inc. v.
Fidelity & Deposit Co.,26
a contractor’s performance bond surety was required to arbitrate
with the project owner under the terms of an arbitration clause in the owner-contractor
agreement, which was incorporated by reference into the bond. The court held that the
incorporation of the contract into the bond expressed the intention of the parties, including the
surety who was not a signatory to the contract, to arbitrate disputes.
On occasion, both of the foregoing examples of “incorporation by reference” can be found in
the same case. For example, in Exchange Mut. Ins. Co. v. Haskell Co.,27
a surety on a
performance bond was bound to arbitrate a dispute with a subcontractor when the bond
incorporated the subcontract by reference and the subcontract likewise incorporated the
general contract by reference, which included the arbitration clause. The owner contract
contained the following arbitration agreement:
ZZ997:99950:119424:1:ATLANTA 15
All the claims, disputes and other matters in question arising out
of, or relating to this contract or the breach thereof, except for
claims which have been waived by the making or acceptance of
final payment as provided by subparagraphs 8.6.5 and 8.6.6 and
which cannot be settled by negotiation between the Contractor
and the Owner, shall be decided in accordance with the
Construction Industry Arbitration Rules of the American
Arbitration Association. The award rendered by the arbitration
shall be final, and judgment may be entered upon it in
accordance with applicable laws to any court having jurisdiction
thereof.
The subcontract contained the following incorporation clause:
Subcontractor hereby assumes the same obligations and
responsibilities with respect to his performance under this
Subcontract, that Contractor assumes towards Owner with
respect to his performance on the General Contract. If the
General Contract, which is hereby incorporated by reference,
fails or conflicts with any provision of this Subcontract, or any
modification hereof, this Subcontract shall govern.
The performance bond provided by the subcontractor and its surety included the following
incorporation clause:
WHEREAS, the principal has entered into a written Subcontract
with The Haskell Company, dated 10/8/79 to perform as
Subcontractor, certain portions of the work in connection with
the said Prime Contract, consisting of … as stated in
Subcontract No. 4234-06 … which Subcontract is hereby
referred to and made a part hereof.
The court found that the performance bond incorporated by reference the subcontract, the
subcontract incorporated by reference the general contract and hence the duty to arbitration.
In the surety bond situation, the “incorporation by reference” argument is not always
available. In a dispute between a general contractor and subcontractor, the GC can likely
compel joinder of the sub’s surety because the sub’s bond will usually reference the
subcontract. However, the subcontractor may not be able to compel joinder of the GC’s
surety because the GC’s bond will reference the owner-contractor agreement, not the
ZZ997:99950:119424:1:ATLANTA 16
subcontract. Perhaps joinder could be achieved if the owner-contractor agreement contains an
arbitration clause that is incorporated by reference in the subcontract.
Turning the tables slightly, a non-signatory surety may have standing to compel arbitration on
the same theory. In Travelers Cas. & Surety Co. of America, Inc. v Long Bay Mgmt. Co.,28
a
general contractor’s performance bond surety had the right to compel arbitration of a claim
under the construction contract against the project owner, since the contract and its arbitration
clause were incorporated into the bond. The opposite result is also possible. In Hartford
Accident & Indem. Co. v. Scarlett Harbor Associates, Ltd. Partnership,29
the court found that
a surety could not compel arbitration of the obligee owner’s claim on the performance bond
based on an arbitration clause in the referenced owner-contractor agreement.
The “assumption” theory for joinder of a non-signatory party is relevant where one party has
been assigned or has assumed a contract containing an obligation to arbitrate disputes.
Generally, the non-signatory party must manifest an intention to be bound by the agreement
containing the arbitration clause.
The “veil piercing/alter ego” theory may be used to join a person or entity related to a
signatory entity in the arbitration. For example, if one company controls another as its alter
ego, or there are grounds for piercing the corporate veil to get to a principal or general partner,
the related non-signatory party may be joined in an arbitration with the signatory entity.
The “estoppel” theory for joinder of a non-signatory party can arise from the facts and the
parties’ conduct. In Dunn Constr. Co. v. Sugar Beach Condominium Assoc., Inc.,30
a
developer sued its contractor and surety for defective work and the dispute was referred to
arbitration pursuant to the language of the AIA form contract. The developer’s lender
foreclosed on part of the property and loaned funds to the condominium association to make
ZZ997:99950:119424:1:ATLANTA 17
repairs. The lender and association then intervened in the developer’s action against the
contractor and surety, claiming to be third party beneficiaries of the construction contract.
The contractor and surety demanded arbitration of the claims by the lender and association
and petitioned the federal court to compel arbitration under the FAA. The court found that the
lender and association were estopped from asserting that they were not bound to arbitrate
because they had characterized themselves as third party beneficiaries of the contract and
because the lender had occupied an integral position with respect to the construction contract
and was a named obligee on the surety bond.
In Sunkist Soft Drinks, Inc. v. Sunkist Growers, Inc.,31
a non-signatory party was permitted to
compel arbitration with a signatory party because the signatory party relied on the terms of the
agreement containing the arbitration clause in asserting its position. In McBro Planning &
Development Co. v. Triangle Electronic Constr. Co.,32
a non-signatory party was bound to
arbitrate claims that were so intertwined as to be “inherently inseparable” from arbitrated
claims the non-signatory had opted to pursue.
In In re Weekley Homes, L.P.,33
the daughter of the signatory owner of a home construction
contract was compelled to participate as a party to the arbitration required under her father’s
contract. The court found that the daughter’s negotiations with the builder for changes and
additions to and warranty work under the contract constituted her receipt of benefits under the
contract which estopped her from avoiding the arbitration provisions of the contract. The
court recognized what it termed the “federal law of ‘direct benefits estoppel,’” citing In re
Kellogg Brown & Root, Inc.34
The claimant daughter had pleaded tort injury from asthma
caused by dust from Weekley’s repairs of the home, thus not suing “based on the contract” or
seeking a direct benefit from the contract. Nevertheless, the Texas Supreme Court found
ZZ997:99950:119424:1:ATLANTA 18
ample evidence of her receipt of direct benefits under the contract sufficient to estop her from
avoiding the arbitration provision.
By use of liquidating or award/judgment sharing agreements, parties which lack privity can
effectively be joined as participants in any ADR process required by the governing contract.
The general contractor agrees to prosecute claims against the Owner, the Architect or other
separate contractors on behalf of his subcontractors and suppliers in consideration of their
agreement to look only to their respective shares of the final award or judgment for recovery
of their claims, waiving judgment against the general contractor.
Such agreements are usually entered after disputes and claims arise but may be contemplated
or required in subcontracts and purchase orders. They do, however, present their own unique
issues of enforceability, conflicts of interest, cost sharing and liability for counterclaims.
In Interstate Contracting Corp. v. City of Dallas,35
the Texas Supreme Court expressly
approves “pass-through claims”, recognizes them as valid in spite of Texas law insistence on
privity of contract, and sets out a thorough discussion of their history and recognition in other
jurisdictions. The opinion cites United States v. Blair36
as well as Severin v. United States,37
and other familiar decisions for the policy rationale for allowing pass-through claims pursuant
to a liquidation or consolidation-of-claims agreement included in the subcontract or by
separate agreement. The opinion also reviews the published opinions from nineteen states that
have addressed this issue, concluding that eighteen states “treat pass-through claims favorably,
and only Connecticut rejects them.”38
The language of the subcontract and pass-through agreement in the Interstate Contracting
case can be instructive for future contract drafting purposes. The subcontract provided:
ZZ997:99950:119424:1:ATLANTA 19
In the event SUBCONTRACTOR has a claim for which the
Owner may be responsible, the CONTRACTOR, in its sole
discretion, may initiate with the Owner, at the
SUBCONTRACTOR’S expense and which shall include
attorneys fees, any dispute or claim procedures provided for in
the Contract documents for the use and benefit of
SUBCONTRACTOR: otherwise SUBCONTRACTOR shall
have full responsibility for the preparation of its claims and shall
bear all expenses thereof, including attorneys fees.
CONTRACTOR shall be liable to SUBCONTRACTOR only to
the extent of the amount, if any, actually awarded as a result of
the disputes process: SUBCONTRACTOR shall be entitled
only to the amount, if any, actually awarded as a result of the
disputes process: and such amount when received by
CONTRACTOR from the Owner shall satisfy and discharge
CONTRACTOR from any and all liability to
SUBCONTRACTOR for or on account of the acts or omissions
of the Owner or its Architect or Engineer.
The parties also entered a pass-through agreement, which included the following terms:
1. MSI [the subcontractor] may pursue the Claim against the
city [the owner] in Interstate’s name. Interstate [the general
contractor] shall cooperate fully with MSI including, but not
limited to, passing on the Claim to the City and executing such
documents that may be required to further the Claim; and MSI
shall cooperate fully with Interstate. MSI shall have the
responsibility for the preparation of any claim, the presentation
and prosecution of any such claim, and the conduct of any
litigation.
3. MSI shall diligently pursue the Claim. The right to abandon,
settle, compromise or dismiss the Claim shall be shared by MSI
and Interstate. Interstate and MSI shall each not settle the Claim
without the others prior written approval.
4. All costs, fees and other expenses (including expert and
attorney fees) incurred by MSI in connection with the
preparation, prosecution and litigation of the Claim shall be paid
by MSI. MSI shall have no responsibility for any attorney fees
or expenses that Interstate may elect to incur.
6. From any amount paid in settlement of the Claim, Interstate
and MSI shall be paid first for their respective markup
(including profit and overhead).
. . .
ZZ997:99950:119424:1:ATLANTA 20
The remainder of the settlement fund shall be prorated and paid
between Interstate and MSI in the same percentage that each
party’s portion of the Claim (exclusive of the markup) is to the
total Claim (exclusive of markup) submitted to the City.
A theory of agency or similar relationship can sometimes provide grounds for arbitration with
a non-signatory party. In Wasserstein v. Kovatch,39
a homeowners’ lawsuit against principals
of a general contractor was consolidated with claims by other parties on the same project and
referred to arbitration. The homeowners’ claim against the principals of the general contractor
related to actions under the contract with the general contractor, which called for arbitration of
disputes. The court found, among other grounds, that the individual defendants were entitled
to arbitration as agents of the general contractor, even though they were not signatories to the
arbitration agreement.
The foregoing theories focus on compelling arbitration with all necessary parties, including
non-signatory parties to the arbitration agreement. In a creative twist, one possible solution
for joinder of all parties involves the court declining to enforce an arbitration agreement when
it would result in the inability to include all necessary parties in one forum. The Rules of
Civil Procedure could allow joinder or consolidation in the court system, while non-signatory
parties might not be joined in an arbitration proceeding. This approach is discussed below.
5. Waiver vs. Partial Arbitration
If you have all necessary parties in one lawsuit, but some have not signed arbitration
agreements and the foregoing joinder arguments do not apply, what can you do? Can you get
the court to waive arbitration and proceed in litigation with all parties? Do you want some
parties to go off and arbitrate while your client sits back and watches?
It is arguable that compelling arbitration by less than all parties (or of fewer than all disputes)
actually frustrates speedy and economical dispute resolution that is the prime objective of
ZZ997:99950:119424:1:ATLANTA 21
arbitration.40
On such a theory, some courts have declined to stay judicial proceedings and
compel arbitration where the proceedings were so intermingled that enforcing arbitration
between some parties would only increase the cost, length and complexity of dispute
resolution.41
Other decisions, however, interpret state arbitration statutes as requiring enforcement of an
arbitration agreement even if the result may be counterproductive.42
The weight of authority
under the FAA mandates enforcement of an arbitration agreement regardless of whether some
parties cannot be ordered to join the arbitration.43
In Moses H. Cone Memorial Hospital v. Mercury Construction Corp.,44
the U.S. Supreme
Court stated that the FAA “requires piecemeal resolution when necessary to give effect to an
arbitration agreement”, and enforcement of an arbitration agreement is required
“notwithstanding the presence of other persons who are parties to the underlying dispute but
not to the arbitration agreement.”45
Thus, the option of declining to enforce an arbitration
agreement would presumably be available only by the addition of express contract language
giving the parties or the court such authority.
6. Forum/Locale Battles
A forum selection clause, specifying the forum or location for any arbitration, can be
important in multi-party dispute resolution. If none is included, it is one more open issue for
dispute among the parties. If it is included, it can still lead to battles if one or more parties are
seriously disadvantaged by the forum selected. In addition, the forum selection clause offers a
potential advantage over federal or state civil procedure rules in litigation. While it may not
be possible to get all necessary parties in one venue under judicial rules, a contractual
agreement to one forum can overcome the problem.
ZZ997:99950:119424:1:ATLANTA 22
Several issues arise in considering what sort of forum selection clause to include in an ADR
provision. Is it enforceable and when can it be challenged? What is the result if no forum
selection clause is included?
Federal courts generally enforce contractual forum selection clauses. The U.S. Supreme
Court’s decision in The Bremen v. Zapata Off-Shore Co.,46
reversed a trend in federal courts
of hostility toward contractual forum selection clauses. The court declared that such clauses
are “prima facie valid and should be enforced unless enforcement is shown by the resisting
party to be “unreasonable” under the circumstances.” The court defined “unreasonable” as so
gravely difficult and inconvenient that the resisting party will be deprived of its day in court.
Following the Bremen decision, federal courts have generally and routinely enforced
contractual forum selection clauses. This general rule also applies to forum selection clauses
in arbitration provisions.47
Thus, the FAA generally mandates enforcement of arbitration
provisions, and Bremen and its progeny generally mandate enforcement of forum selection
clauses, including those contained in arbitration provisions.
A number of states have enacted statutes that place limitations on forum selection clauses.
North Carolina, for example, has provided by statute that a contract provision specifying a
forum other than North Carolina for resolution of disputes arising out of a North Carolina
project is void as against public policy. One would expect the state courts of North Carolina
(or other states having similar statutes) to refuse to enforce a forum selection clause if it
violates such a statute. However, the same is not true in the federal courts.
Federal courts generally follow the federal law of Bremen and its progeny and enforce forum
selection clauses as written despite contrary state law. In addition, many courts have held that
the FAA preempts state law restrictions on forum selection clauses in arbitration agreements.
ZZ997:99950:119424:1:ATLANTA 23
For example, in Doctor’s Assocs., Inc. v. Hamilton,48
the court held that state law restrictions
on forum selection clauses in an arbitration provision are preempted by the FAA. Other
courts have concluded that if state law imposes an absolute requirement of in-state arbitration
notwithstanding the parties’ agreement otherwise, the applicability of the state law would be
in serious doubt as a result of the preemptive effect of the FAA.49
Thus, if an action to compel
arbitration is brought in federal court rather than state court, or if the dispute involves
interstate commerce such that the FAA applies, then a forum selection clause is likely
enforceable as written despite state law to the contrary. In addition, the odds of enforcement
can be enhanced by including language such as: “Any disputes concerning the enforceability
or scope of the arbitration clause shall be resolved pursuant to the Federal Arbitration Act, 9
U.S.C. § 1 et seq., and the parties acknowledge that the FAA preempts any state law
restrictions on the enforcement of the arbitration clause in this agreement according to its
terms, including any restrictions on the site of the arbitration.”
Some forum selection clauses are drafted for the convenience of one party (usually the one
with most bargaining power at the time of contract) but bearing little or no relation to the
project site or location of witnesses, and perhaps creating serious hardship for the other party
or parties. When you represent one of these parties, it is good to know that there may be
exceptions to enforcement of such a forum selection clause and that the clause may be
severable so as not to invalidate the entire ADR provision. Under the Bremen line of cases,
there are exceptions to the presumed enforceability of a forum selection clause on grounds
such as unequal bargaining power, fraud or effective denial of access to a forum. The party
objecting to the forum selection clause has the burden of showing a “compelling and
countervailing reason” on one of these grounds to overcome the strong policy in favor of
enforcement.
ZZ997:99950:119424:1:ATLANTA 24
One example of refusal to enforce an unworkable forum selection clause in the international
arbitration context is the case of National Iranian Oil Co. v. Ashland Oil, Inc.50
In that case,
the relevant contract specified arbitration in Teheran, Iran, as well as arbitrator selection and
applicable law in accordance with Iranian guidelines. The dispute arose after the Iranian
Islamic Revolution, and the American party to the contract refused to arbitrate in Iran because
of the danger to Americans in that forum. The court refused to compel arbitration in the
chosen forum (Iran) or in another forum (United States), and instead allowed the case to go
forward in court, thereby negating the entire arbitration provision.
The foregoing result is arguably incorrect and undesirable. Courts have the option to enforce
the ADR provision as written, refuse to enforce the ADR provision at all, or invalidate and
sever the offending portion while enforcing the remaining clause. While a forum selection
clause is particularly important in international contracts, it is also important that an invalid
forum selection clause not defeat the entire ADR provision. An arbitration agreement is
severable from the contract that contains it.51
Other courts have severed and refused to
enforce an offending forum selection clause.52
Here is another opportunity to include contract
language that enhances the likelihood of the desired result, such as: “In the event that any
provision of this arbitration agreement is unenforceable, that provision is severable from the
remainder of the arbitration agreement, which shall remain in full force and effect.”
If an arbitration agreement does not include a forum selection clause, or includes an unfair or
unworkable forum selection clause, the proper forum for arbitration can be a subject of
dispute. This is only more likely in a case with multiple parties. Since this is a question of
procedural arbitrability, rather than substantive arbitrability, the question would normally be
decided by an arbitrator rather than a court. In guiding arbitrator determinations, the
ZZ997:99950:119424:1:ATLANTA 25
American Arbitration Association typically requests information from the parties on the
following nine factors:
1) location of parties
2) location of witnesses and documents
3) location of site or place or materials
4) consideration of relative costs to the parties
5) place of performance of contract
6) laws applicable to the contract
7) place of previous court actions
8) necessity of an on-site inspection of the project
9) any other reasonable arguments that might affect the locale
determination.
These factors are obviously aimed at a fair and practical determination based on circumstances
of the particular case. The determination is obviously made more difficult when an arbitration
involves numerous parties in differing geographic locations. This highlights the importance of
including appropriate contract language in project agreements, not only to ensure the joinder
of all necessary parties in one proceeding, but also to ensure that all necessary parties are
amenable to one venue.
The choice of where to file an action to compel arbitration can affect the forum of the
arbitration as well as the enforceability of the arbitration agreement.53
The FAA54
provides
that a party can enforce an arbitration agreement by action in a federal district court that has
an independent basis for jurisdiction, but also provides that the hearing and proceedings under
the arbitration agreement shall be within the district in which the petition is filed. Thus, where
the arbitration agreement does not specify a forum for the proceedings, the forum may be
determined by where an action to compel arbitration is filed. Where the arbitration agreement
in the contract includes a forum selection clause, the result of an action to compel under the
FAA can vary depending upon the court.
ZZ997:99950:119424:1:ATLANTA 26
The majority view is represented by the decision of the 10th Circuit Court of Appeals in Ansari
v. Qwest Communications Corp.55
The majority view is also followed by the Third, Sixth and
Seventh Circuits. Under this view, a district court may compel arbitration only within its
district and only if the arbitration agreement selects a forum within or encompassing its
district. Under this interpretation of the FAA, filing an action in a district court outside of the
forum selected in the arbitration agreement may defeat enforcement of a forum selection
clause or perhaps avoid arbitration entirely.
A minority view is represented by the Fifth Circuit decision in Dupuy-Busching Gen. Agency,
Inc. v. Ambassador Ins. Co.56
By this approach, a district court may compel arbitration in the
forum selected by the arbitration agreement, even if it is not within the court’s district. This
approach eliminates the “race to the courthouse” created by the majority view, but is
obviously inconsistent with the language of Section 4 of the FAA. A third view is represented
by the Ninth Circuit decision in Textile Unlimited, Inc. v. A. BMH & Co., Inc.57
Under the
Ninth Circuit approach, a district court may compel arbitration in its district and ignore the
forum selected by the parties in the arbitration agreement.
The inconsistent results among the federal courts once again highlights the importance of
careful contract drafting in order to avoid enforcement problems.
7. Unilateral Enforceability
An enforceability issue that has arisen over the last several years is the use of “unilateral” or
“discretionary” arbitration provisions. These are contract clauses that give one party the right
to choose whether to arbitrate or litigate disputes while purportedly leaving the other party no
option to choose or compel arbitration. Such provisions are found in owner-contractor
agreements and in general contractors’ form subcontracts. Are these clauses enforceable and
what effect do they have on multi-party disputes?
ZZ997:99950:119424:1:ATLANTA 27
When faced with such contract language, a court could conceivably enforce it as written, read
it as mutually enforceable by the parties, or declare it unenforceable. Both the Federal
Arbitration Act and Uniform Arbitration Act provide that a valid agreement to arbitrate is
enforceable “save upon such grounds as exist at law or in equity for the revocation of any
contract.” While some courts have refused to enforce “unilateral” or “discretionary”
arbitration provisions, most courts have apparently enforced the language as written.58
One argument against the enforceability of such provisions is that they are one-sided and
unreasonably favorable to the drafter to the point of being unconscionable.59
A unilateral
arbitration option has also been invalidated based on lack of mutuality and lack of
consideration.60
On the other hand, a subcontract provision that gave the general contractor
“at its sole option” the right to require the subcontractor to arbitrate disputes has been found
enforceable and not unconscionable.61
The impact of such clauses on multi-party disputes is that some parties can potentially compel
arbitration, and related joinder or consolidation, while other parties cannot. Such a regime can
start with the owner-contractor agreement and be incorporated by reference through lower tier
project agreements. The scenario leaves a subcontractor, for example, with little control or
predictability, and the decisions regarding arbitration or litigation can only flow downward. A
general contractor on the other hand, may see advantages in being able to control the
prospects of consolidation or joinder by controlling the choice of dispute resolution forum.
8. Dispute Review Boards
The Dispute Review Board (DRB) has been a useful tool for resolving disputes on some
construction projects. A typical example involves a three-member board appointed by the
owner and contractor to hear disputes arising during the project and issue non-binding
decisions that may become binding if not contested by either party. The American Arbitration
ZZ997:99950:119424:1:ATLANTA 28
Association posts a sample DRB agreement on its website, which contemplates a three-
member board conducting hearings and issuing a written report and recommendation on
disputes arising during a project. However, this dispute resolution tool is not without
enforcement problems.
In Los Angeles County Metropolitan Transp. Auth. v. Shea-Kiewit-Kenny,62
the California
courts dealt with a dispute between the owner and contractor over the owner’s removal of its
appointed representative on a DRB. The project involved construction of a tunnel segment of
the Los Angeles subway system. In accordance with the contract documents, the owner and
contractor each appointed one representative to the DRB and those appointees selected a third
member. The contract further provided that the DRB would consider disputes placed before
them by either party and provide written recommendations for settlement of the disputes.
Either party could reject the DRB’s recommendations by providing a timely notice of intent to
litigate the issues. All records and written recommendations of the DRB would be admissible
in subsequent litigation.
A dispute arose when the owner gave the contractor a termination notice based on the
discovery of a large sinkhole on Hollywood Boulevard. The contractor requested a DRB
hearing on the purported termination, and the owner claimed that the termination extinguished
the existence of the DRB. The DRB determined that it had authority to consider the dispute
and scheduled a hearing. The owner refused to attend and a hearing was held in the owner’s
absence, resulting in a decision that the termination was improper. The issue then went to
litigation.
The owner thereafter terminated for cause the DRB member that it had appointed. The
contractor objected and the owner filed a declaratory judgment action on the issue of whether
its removal for cause of its DRB appointee was proper. The trial court agreed with the owner
ZZ997:99950:119424:1:ATLANTA 29
and the contractor appealed. The appeal focused on what constitutes “cause” justifying
removal of a DRB member under the contract terms. The contractor argued that it must be the
same as the “cause” necessary to remove a judge. The court disagreed, finding that the DRB
was a creature of contract, not a constitutional or statutory entity. The court found that
“cause” meant a fair and honest reason in the exercise of good faith, and observed that
removal simply resulted in replacement with a new member, not destruction of the DRB.
Another consideration was whether the DRB appointee’s conduct would reasonably cause the
owner to lose confidence in its appointee, since confidence in the DRB members was essential
for the process to work. Thus, the court found that the owner had cause for removal of its
appointee based on the contractual prohibition against ex-parte communications, expression of
opinions during hearings and prejudging issues.
This case demonstrates potential enforcement issues with a DRB. A dispute as drastic as
termination may be beyond the scope of a contractual DRB to resolve. The irony is that the
parties wound up litigating over the entity they established to avoid litigation.
D. Contract Language to Avoid Enforcement Problems
There are numerous revisions and substitutions for typical dispute resolution clauses that can
address and perhaps avoid some of the typical enforcement problems discussed above. The
following revisions or substitutions to dispute resolution clauses are possible ways to address
problems such as refusal to mediate, consolidation of arbitration proceedings, joinder of non-
signatory parties, forum for mediation or arbitration, pre-hearing discovery, and similar issues.
1. Refusal to Mediate
The following alternate mediation clause can be used in Section 4.5 of the AIA A201
document to address timing, mediator section, location and delay:
Unless delay in initiating or prosecuting a Claim in litigation
would irrevocably prejudice the Owner or Contractor, any claim
ZZ997:99950:119424:1:ATLANTA 30
that is not resolved by direct discussions between the parties
shall be submitted to Mediation under the Construction Industry
Mediation Rules of the American Arbitration Association or
such other rules as the parties may promptly agree to employ. If
the Owner and Contractor cannot agree on the selection of a
mediator within ten (10) days of the request for Mediation,
either party may immediately request the appointment of a
mediator in accordance with the governing mediation rules.
Mediation shall occur at any location to which the parties and
mediator agree or, in the absence of agreement, at the location
of the Project.
The parties agree to conduct and conclude Mediation
proceedings under this paragraph within sixty (60) days from
the designation of the mediator. In the event that Mediation
proceedings do not resolve the claim within such period, either
party may initiate other means of dispute resolution with respect
to the claim.63
This clause helps to minimize disputes over mediation as a condition precedent, delay by an
obstructing party, and risk of waiver of the entire ADR process, by using time limits. If there
is no agreement on a mediator within 10 days, one is appointed. If the dispute is not resolved
by mediation in 60 days from appointment of a mediator, either party can proceed to the next
stage. A specification of forum or locale should probably be added to this clause.
Time limits can also be used in the “meet and confer” stage of dispute resolution. The
following clause may be used for this purpose:
Field Presentation’s Meeting: Within fifteen (15) days after a
dispute occurs, the Contractor’s senior project management
personnel shall meet with the Owner’s project representative in
a good faith attempt to resolve the dispute.
Management Representatives’ Meeting: If Contractor’s and
Owner’s project representatives fail to meet, or if they are
unable to resolve the dispute, a senior executive for Contractor
and for Owner, neither of which may have day-to-day Project
management responsibilities, shall meet, within thirty (30) days
after the commencement of the dispute, in an attempt to resolve
the dispute and any other identified disputes or any unresolved
issues that may lead to a dispute.
ZZ997:99950:119424:1:ATLANTA 31
If the senior executives of Contractor and Owner are unable to
resolve a dispute or if a senior management conference is not
held within the time provided herein, either party may make
written demand on the other party for mediation by an
independent mediator.64
2. Joinder and Consolidation in Arbitration
The following clause may be used in an owner-contractor agreement on design-bid-build or
design-build projects to provide for the right to join other parties in an arbitration or other
dispute resolution process:
At either party’s option, third parties may be joined in any of the
dispute resolution processes listed above, by consolidation,
joinder or otherwise, who are subject to a valid alternative
dispute resolution agreement with the party seeking joinder of
such third-party.65
An advantage of this clause is its applicability to all dispute resolution processes used in the
contract: mediation, arbitration or litigation. The reach of this clause could be extended to
subcontracts and sub-consultant agreements by use of the following “flow-down” clause:
Subcontractor agrees to be bound to the Contractor by all the
terms of the Agreement between the Contractor and Owner and
the Contract Documents thereto (except for the payment
provisions of the Owner-Contractor Agreement which are
specifically excluded from the scope of this Subcontract), and
assumes toward the Contractor and the Owner all the obligations
and responsibilities that the Contractor, by those instruments,
assumes toward the Owner.
Typical “flow-down” clauses are also found in the AIA A401 document (section 2.1) and the
AGC 650 document (section 3.1). The AIA A201 document (section 5.3.1) provides that the
contractor will include such a provision in its subcontracts.
Use of a “pass-through” clause in subcontracts is another method of joining necessary parties
in one dispute resolution process. The following clause may be used in subcontracts as a
ZZ997:99950:119424:1:ATLANTA 32
“pass-through” agreement requiring the contractor to pursue claims promptly on behalf of the
subcontractor against the owner:
Contractor shall, within ten (10) working days after receipt of
action from Owner on a claim containing Subcontractor’s Claim
give notice to Subcontractor. If Subcontractor does not agree
with Owner’s action, Subcontractor may direct Contractor to
pursue its Claim against Owner, in accordance with the Contract
Documents, and Contractor shall take said action if
Subcontractor agrees to be responsible for its pro rata share of
the costs associated with pursuing the Claim against Owner. If
Contractor complies with this provision, it shall not be
independently liable to Subcontractor for Subcontractor’s
claim.66
The following clause may be used for allocation of costs between contractor and subcontractor
in the joint presentation of claims:
When Contractor pursues a claim against the Owner or its
agents that incorporates any claim on behalf of Subcontractor,
each party shall pay the fees of any mediator or arbitrator and
the cost of the dispute resolution proceedings in proportion to
the amount of the party’s respective claim. If Contractor and
Subcontractor participate in a legal proceeding to resolve issues
between them that do not involve the owner, each party shall
share equally in paying the bills of mediators or arbitrators and
of any service administering the dispute process. As part of a
final award, the arbitrator may require the party it deems
unsuccessful to reimburse the costs and fees charged by
mediators and/or arbitrators. Each party will, however, remain
responsible for its owner attorneys’ fees and costs, if any, and
no award for a party’s costs and attorneys’ fees shall be made
unless provided for in the Contract Documents.67
The following alternate clauses may be used in Section 4.6 of the AIA A201 document to
address consolidation and joinder issues:
Consolidation. To the extent not prohibited by the Owner’s or
Contractor’s agreements with third parties, disputes or Claims
with third parties involving common questions of fact or law
shall be addressed in the same ADR proceeding.
ZZ997:99950:119424:1:ATLANTA 33
Joinder. The American Arbitration Association may join to any
arbitration under this Agreement an entity not a party to this
Agreement or other arbitrations involving this Project who has
consented to such joinder, if such joinder is necessary to a
complete resolution of any common issues of law or fact. The
award rendered by the arbitrators will be final and not subject to
appeal, and judgment may be entered upon it in any court
having jurisdiction thereof.68
The following alternate clause can be employed in Section 7.2 of the AIA B151 document
(Owner-Architect Agreement) to facilitate joinder:
The Architect waives all objections to joinder of the Architect as
a party to any mediation, arbitration or litigation related to this
Project in which the Owner is joined or is otherwise positioned
as a party and in which the Architect’s conduct or performance
of professional services is in any way relevant to the subject of a
dispute. The Architect also agrees to prepare or modify all
documents used or prepared by the Architect, including but not
limited to agreements between the Architect and his
Consultants, Agreements between the Owner and other parties,
and any General and Supplemental Conditions for Construction
for this Project, to reflect this waiver.69
The following alternate clauses could be used in Article 6 of the AIA A401 document
(Subcontract) to facilitate consolidation or joinder:
Any claim arising out of or related to this Subcontract or the
breach thereof, except claims as otherwise provided in
Subparagraph 4.1.5 and except those waived in this
Subcontract, shall be settled according to the dispute resolution
procedures in the Prime Contract.
For a dispute that involves the Subcontractor’s work, in whole
or in part, the Subcontractor shall be bound by the outcome of
the dispute resolution procedure.
The Contractor shall pay the Subcontractor the amount of the
proportionate share of any recovery due the Subcontractor on
the basis of the ratio of the Subcontractor’s claims to other
claims that are asserted, less the expenses and attorneys fees of
the procedures, provided the Subcontractor’s claims and other
claims are substantially similar and reasonably justified as to
merit and actual costs incurred as determined by the Contractor.
The Subcontractor shall pay the Contractor its proportionate
share of a recovery by the Owner against the Contractor
ZZ997:99950:119424:1:ATLANTA 34
involving the Subcontractor’s work or materials and pay the
Contractor its proportionate share of the expenses and attorneys
fees incurred in defending such Owner claim against the
Contractor.
All claims, disputes and other matters in question between the
Subcontractor and the Contractor arising out of or related to the
Subcontract or the breach thereof, except as specifically
governed by the foregoing provisions, and except for claims
that have been waived by the making and acceptance of final
payment, may be mediated by the parties in accordance with the
Construction Industry Mediation Rules of the American
Arbitration Association then in effect or decided by arbitration
in accordance with the Construction Industry Arbitration Rules
of the American Arbitration Association then in effect at the
sole option of the Contractor. If a request for mediation or
demand for arbitration is filed by the Subcontractor, the
Contractor will advise the Subcontractor within thirty (30) days
after the receipt of such a request for mediation or a demand for
arbitration if the Contractor exercises the option to mediate or
arbitrate or rejects mediation or arbitration or both; such
election, once made, shall be binding. The filing of a request
for mediation by the Contractor shall be deemed an election to
mediate and shall constitute the exercise of the option of the
Contractor to proceed with mediation. The filing of a demand
for arbitration by the Contractor shall be deemed an election to
arbitrate and shall constitute the exercise of the option of the
Contractor to proceed with arbitration. The Contractor may
join or consolidate mediation or arbitration with the Owner,
Architect, any other Subcontractor, surety, insurer or any other
party having an interest in the proceedings. The Subcontractor
hereby consents to such joinder or consolidation, which may be
ordered at the sole discretion or election of the Contractor. This
agreement to mediate or arbitrate shall be specifically
enforceable under applicable law in any court having
jurisdiction thereof. Any award rendered by arbitration shall be
final, and judgment may be entered upon it in accordance with
the applicable law in any court having jurisdiction thereof.70
The following alternate clause is similarly suitable for use in the AIA A401 Subcontract, but
is more from the subcontractor’s perspective:
The Contractor shall give the Subcontractor prompt written
notice of any demand received or made by the Contractor for
arbitration if the dispute involves or relates to the Work,
materials, equipment, rights or responsibilities of the
Subcontractor. The Contractor shall consent to inclusion of the
Subcontractor in the arbitration proceeding, whether by joinder,
consolidation or otherwise, if the Subcontractor requests in
ZZ997:99950:119424:1:ATLANTA 35
writing to be included within ten (10) days after receipt of the
Contractor’s notice.71
3. Forum/Locale Battles
An enforceable forum selection clause can help avoid venue disputes in multiparty dispute
resolution. The enforceability of a forum selection clause is generally enhanced by specifying
the location of the project. Parties are generally subject to jurisdiction, state law restrictions
are mollified, and an action to compel arbitration can likely be brought in that judicial district.
The following clauses may be used to reduce the likelihood of problems with enforceability
based on an objectionable or flawed venue provision:
Any disputes concerning the enforceability or scope of the
arbitration clause shall be resolved pursuant to the Federal
Arbitration Act, 9 U.S.C. § 1 et seq. (FAA), and the
[contractor/subcontractor] acknowledges that, notwithstanding
any contrary language in this Agreement, the FAA preempts any
state law restrictions on the enforcement of the arbitration clause
in this Agreement according to its terms, including any
restrictions on the site of the arbitration.
In the event that any provision of this arbitration agreement is
unenforceable, that provision is severable from the remainder of
this arbitration clause, and the balance of the arbitration
agreement shall remain in full force and effect. In addition, any
ruling invalidating any other portion of the Agreement shall not
affect the validity of this arbitration clause.72
4. Litigation, Discovery
Some practitioners avoid arbitration under certain circumstances. For example, the prospect
of expensive litigation can be seen as enhancing the success of negotiation or mediation. An
owner may prefer the court system for the prospect of summary judgment on contract terms,
such as waiver due to untimely notice. A contractor may have the same preference regarding
enforcement of subcontract terms. Opponents of arbitration may cite such “drawbacks” as
ZZ997:99950:119424:1:ATLANTA 36
failure of arbitrators to be sufficiently bound by facts or law, limited grounds for appellate
review, problems with joinder of necessary parties, ineffective subpoena power and limited
discovery.73
In such circumstances, the following clause can be used to provide for resolution of disputes
by litigation and to delete any reference to ADR:
Notwithstanding any other provision in the Contract
Documents, the parties agree that all disputes arising out of or
related to the Project shall be resolved through litigation. The
parties further agree that the sole and exclusive forum for such
litigation shall be [insert venue.] All references in the Contract
Documents to dispute resolution procedures other than litigation
are hereby deleted.74
Some objections to arbitration can be addressed by simply including additional language in
the ADR clause. For example, larger projects involving disputes of greater complexity and
dollar value may merit more extensive discovery, but also benefit from the expertise of
arbitrators familiar with the industry. The following clause may be used to provide for the
type and extent of discovery in arbitration:
Each party shall produce all documents relevant to the dispute
not less than thirty (30) days after the demand for arbitration has
been filed. The documents provided to the other party shall
include reports of any experts who may testify, in person or by
affidavit, at the arbitration proceedings. An expert’s report shall
set forth all opinions of the expert and the factual basis for the
opinions. Any document not provided to the other party in
compliance with this provision may not later be introduced in
the arbitration proceedings and any expert whose report is not
given to the other party, as provided herein, shall not be allowed
to testify in the arbitration proceedings.
Each party shall be entitled to depose no more than ___ (___)
fact witnesses for no longer than ___ (___) hours each. Each
party shall be entitled to depose any and all retained expert
opinion witnesses for no longer than ___ (___) hours each. All
discovery disputes shall be decided by the arbitrator(s). The
arbitrator(s) may modify these discovery limitations for good
cause shown.75
ZZ997:99950:119424:1:ATLANTA 37
The following alternate clause may be used in the AIA A201 document to address the issue of
pre-hearing discovery:
The parties shall be entitled to discover all documents and
information reasonably necessary for a full understanding of
any legitimate issue raised in the arbitration. Parties may use
all methods of discovery available under the Federal Rules of
Civil Procedure and shall be governed thereby. Prior to the
deposition of any expert witness, the party proposing to call
such a witness shall provide a full and complete report by the
expert, together with the expert’s calculations and other data by
which the expert reached any opinions concerning the subject
matter of the arbitration. The report shall be provided no more
than ten (10) days prior to the date set forth in the expert
witnesses’ deposition.76
5. Enforceability
The following alternate provision may be used in the AIA A201 document to address
enforceability of the arbitration clause:
This consent to arbitrate and any other agreement or consent to
arbitrate entered into in accordance herewith as provided in
Paragraph 4.6 will be specifically enforceable under the
prevailing arbitration law of any court having jurisdiction.77
1 Adrian Bastianelli, Litigating with the Federal Government, ABA Forum 2000 Annual Meeting (May
200); 5 U.S.C. §§ 571 et seq. 2 Id.
3 Daniel S. Brennan, et al. The Construction Contracts Book, Chap. 8 “Dispute Resolution”, p. 75
(American Bar Ass’n 2004). 4 Daye Nonferrous Metals Co. v. Trafigura Beheer, 1997 U.S. Dist. LEXIS 9661 (S.D. N.Y. 1997).
5 DeGroff v. Masco Tech Forming Technologies Fort Wayne, Inc., 179 F. Supp. 2d 896 (N.D. IN.
2001); Semco, LLC v. Ellicott Machine Corp, Int’l., 1999 WL 493278 (E.D. LA. 1999); Ponce
Roofing, Inc. v Roumel Corp., 190 F. Supp. 2d 264 (D. Puerto Rico 2002); Jenks v. Workman, 2000
WL 962821 (S.D. IN 2000). 6 Blue Cross & Blue Shield of Texas v. Dimark Marketing, Inc., 1997 WL 405169 (N.D. TX 1997);
Cumberland & York Distributors v. Coors Brewing Co., 2002 WL 193323 (D. ME, 2002); Welborn
Clinic v. Medquist, Inc., 301 F.3d 634 (7th
Cir. 2002). 7 HIM Portland, LLC v. DeVito Bldrs., 317 F.3d 41 (1
st Cir. 2003); Kemiron Atlantic v. Aguakem Int’l.,
Inc., 290 F.3d 1287 (11th
Cir. 2002). 8 See, Note & Comment: Should mediation trigger arbitration in multi-step alternative dispute
resolution clauses?, 15 Am. Rev. of Int’l. Arb. 162 (2004). 9 Howsam v. Dean Witter Reynolds, 537 U.S. 79 (2002); John Wiley & Sons, Inc. v David Livingston,
376 U.S. 543 (1964). 10
Thomas J. Stipanowich, Of Procedural Arbitrability: The Effect of Noncompliance With Contract
Claim Procedures, 40 S.C.L. Rev. 847, 860 (1989); AT&T Technologies, Inc. v. Communications
ZZ997:99950:119424:1:ATLANTA 38
Workers of America, 475 U.S. 643 (1986); Moses Cone Memorial Hosp. v. Mercury Constr. Corp.,
460 U.S. 1, 24-25 (1983); Stroh Container Co. v Delphi Indus., Inc., 783 F.2d 743 (8th
Cir. 1986). 11
The RUAA has been adopted by the following states as of August 31, 2005: Alaska, Colorado,
Hawaii, Nevada, New Jersey, New Mexico, North Dakota, Oklahoma, Oregon, Utah and Washington.
Legislation has been introduced or proposed for adoption of the RUAA in Arizona, Maryland,
Vermont, Connecticut, Indiana, Iowa, Massachusetts, West Virginia, and District of Columbia. For
other considerations in drafting arbitration clauses, including joinder, consolidation and enforcement
pursuant to the RUAA, see John C. Fleming, “A Few Things to Know about the Revised Uniform
Arbitration Act,” Commercial & Business Litigation, Vol. 7, No. 2 (Winter 2006). 12
See e.g., Federated Dept. Stores, Inc. v. Pavarini Constr. Co., 425 So.2d 1212 (Fla. 4th
DCA 1983;
Wise v. Tidal Constr Co., Inc., 261 Ga. App. 670, 583 S.E.2d 466 (2003). 13
276 F. Supp. 2d 891 (M.D. Tenn. 2003) 14
Id. at 893, citing Bakers Union Factory, #326 v. ITT Continental Banking Co., Inc., 749 F.2d 350,
353 (6th
Cir. 1984). 15
C.B. Richard Ellis, Inc. v. American Environmental Waste Mgmt, 1998 U.S. Dist. LEXIS 20064,
1998 WL 903495 (E.D. N.Y. 1998). 16
Symposium Article: Mediating in the Shadow of the Courts: A Survey of the Emerging Case Law,
54 Ark. L. Rev. 171 (2001); Dept. of Transp. v. City of Atlanta, 380 S.E.2d 265, 268 (Ga. 1989). 17
E.g., Avril v Civilmar, 605 S.2d 988 (Fla. DCA 1992); Texas Parks & Wild Life Dept. v. Davis, 988
S.W.2d 370 (Tex. App. 1999); but see, Texas D.O.T. v. Pirtle, 977 S.W.2d 657 (Tex. App. 1998). 18
John Bickerman, Don’t Get Caught Shorthanded: Include All Players in Construction Defect
Mediation, 13 Constr. 6 (Summer 2004). 19
See F.R.C.P. 18, 19, 20. 20
998 F.2d 68 (2nd
Cir. 1993). 21
Andrew Ness and David Peden, Arbitration Developments – Defects & Solutions, ABA Forum 2002
Annual Meeting (April 2002); Consolidated Pac. Eng’g, Inc. v. Greater Anchorage, 563 P.2d 252
(Alaska 1977); Louisiana Stadium & Exposition Dist. v. Huber, Hunt & Nichols, Inc., 349 So.2d 491
(La. Ct. App. 1977); Bay County Bldg. Auth. v. Spence Bros., 140 Mich. App. 182, 362 N.W.2d 739
(1984); Pueblo of Lagunna v. Cillessen & Son, Inc., 101 N.M. 341, 682 P.2d 197 (1984); Hjelle v.
Sornsin Constr. Co., 173 N.W.2d 431 (N.D. 1970); Ashland City Sch. Dist. Bd. of Educ. v. Ashland
City Teachers Ass’n, 1997 Ohio App. LEXIS 2337 (Ohio Ct. App. 1997); Balfour, Guthrie & Co. v.
Commercial Metals Co., 93 Wash. 2d 199, 607 P.2d 856 (1980); Bateman Constr, Inc. v. Haitsuka
Bros., Ltd., 77 Haw. 481 889 P.2d 58 (1995). 22
Litton Bionetics, Inc. v. Glen Constr. Co., 292 Md. 34, 437 A.2d 208 (1981); Grover-Dimond Assoc.
v. American Arb. Ass’n, 297 Minn. 324, 211 N.W.2d 787 (1973); Exber, Inc. v. Sletten Constr. Co., 92
Nev. 721, 558 P.2d 517 (1976); William Blanchard Co. v. Beach Concrete Co., 150 N.J. Super. 277,
375 A.2d 675(App. Div. 1977); County of Sullivan v. Nezelek, Inc., 42 N.Y.2d 123, 366 N.E.2d 72,
397 N.Y.S.2d 371 (1977); School Dist of Philadelphia v. Livingston-Rosenwinkel, P.C., 690 A.2d 1321
(Pa. Commw. Ct. 1977); Children’s Hosp. of Phila. v. American Arb Ass’n 231 Pa. Super. 230, 331
A.2d 848 (1974). 23
Cal. Civ. Proc. Code §§ 1281.3; Mass. Ann. Laws. ch. 251, § 2A; O.C.G.A. § 9-9-6; S.C. Code Ann.
§ 15-48-60; N.J. Stat. § 2A: 23B-10. 24
Merrill Lynch Inv. Managers v. Optibase, Ltd., 337 F.3d 125 (2nd
Cir. 2003). 25
473 F.2d 212 (5th
Cir. 1973). 26
6 Cal. App. 4th
1266, 8 Cal. Rptr. 2d 587 (2d Dist. 1992). 27
742 F.2d 274 (6th
Cir. 1984). 28
58 Mass. App. 786, 792 N.E.2d 1013 (2003). 29
346 Md. 122, 695 A.2d 153 (1997). 30
760 F.Supp. 1479 (S.D. Ala. 1991). 31
10 F.3d 753 (11th
Cir. 1993), cert. den. 513 U.S. 869 (1994). 32
741 F.2d 342 (11th
Cir. 1984). 33
176 S.W.3d 740 (Tex. 2005). 34
166 S.W.3d 732, 741. 35
135 S.W.3d 605 (Tex. 2004).
ZZ997:99950:119424:1:ATLANTA 39
36
321 U.S. 730, 737-38 (1944). 37
99 Ct. Cl. 435, 444 (1943). 38
Interstate Contracting, at 613-614. 39
261 N.J. Super. 277, 618 A.2d 886 (App. Div. 1993). 40
Thomas J. Stipanowich, Arbitration and the Multiparty Dispute: The Search for Workable
Solutions, 72 Iowa L. Rev. 473, 483-488 (March 1987). 41
See e.g., Ford Motor Co. Ltd. v. Gorthon, 397 F.Supp. 1332 (D. Md. 1975); J.F. Inc. v. Vicik, 99 Ill.
App. 3d 815, 426 N.E. 2d 257, 260 (1981); County of Jefferson v. Barton-Douglas Contractors, Inc.
282 N.W.2d 155, 158-59 (Iowa 1979); Prestressed Concrete, Inc. v. Adolfson & Peterson, Inc. 308
Minn. 20, 24, 240 N.W.2d 551, 553 (1976); Rosenthal v. Berman, 14 N.J. Super. 348, 352, 82 A.2d
455, 457 (App. Div. 1951); GAF Corp v. Werner, 106 A.D.2d 41, 46, 484 N.Y.S.2d 12, 16(1985) 42
Bowes v. International Pharmaken Laboratories, Inc., 111 Mich. App. 410, 314 N.W.2d 642 (1981);
Charles J. Frank, Inc. v. Associated Jewish Charities of Baltimore, 294 Md. 433, 450 A.2d 1304
(1982); Galt v. Libby-Owens-Ford Glass Co., 376 F.2d 711 (7th
Cir. 1967); Travel Consultants, Inc. v.
Travel Mgmt Corp., 367 F.2d 334 (D.C. Dir. 1966); Atlas Plastering, Inc. v. Superior Court, 72 Cal.
App. 3d 63, 140 Ca. Rptr. 59 (1977); Town of Danvers v. Wexler Constr. Co., 422 N.E.2d 782 (Mass.
App. Ct. 1981); Manchester Township Bd of Educ. v. Thomas P. Carney, Inc., 199 N.J. Super. 266,
589 A.2d 682 (App. Div. 1985); Stillwater Leased Housing Assocs. v. Kraus-Anderson Constr. Co.,
319 N.W.2d 424 (Minn. 1982). 43
Stipanowich, Arbitration and the Multiparty Dispute, 72 Iowa L. Rev. 473, 487 (March 1987). See,
e.g., McBro Planning & Dev. Co. v. Triangle Elec. Constr. Co., 741 F.2d 342, 349 (11th
Cir. 1984);
Hughes Masonry Co. v. Greater Clark County School Bldg. Corp., 659 F.2d 836, 838-39 (7th
Cir.
1981); IC. Itoh & Co. v. Jordan Int’l Co., 552 1228, 1231 (7th
Cir. 1977); Acevedo Maldonado v. PPG
Indus, 514 F.2d 614, 616 (1st Cir. 1975); Hamilton Life Ins. Co. v. Republic Nat’l Life Ins. Co., 408
F.2d 606, 609 (2d Cir. 1969); Hilti, Inc. v. Oldach 392, F.2d 368, 370-71 (1st Cir. 1968); Wilko v.
Swan, 201 F.2d 439, 445 (2d Cir.) rev’d on other grounds 346 U.S. 427 (1953); Martin K. Eby Constr.
Co. v City of Arvada, 599 F. Supp. 449, 450 (D. Colo. 1981); Schulman Inv. Co. v. Olin Corp. 458 F.
Supp. 186, 188 (S.D.N.Y 1978); Lawson Fabrics, Inc. v. Akzona, Inc., 355 F. Supp 1146, 1148
(S.D.N.Y. 1973). 44
460 U.S. 1 (1983). 45
460 U.S. at 20. 46
407 U.S. 1 (1972). 47
Mitsubishi Motors v. Solar Chrysler-Plymouth¸ 473 U.S. 614 (1985); Carnival Cruise Lines, Inc. v.
Shute, 499 U.S. 585 (1991). 48
150 F.3d 157 (2nd
Cir. 1998). 49
Management Recruiters Int’l., Inc. v. Bloor, 129 F.3d 851 (6th Cir. 1997); M.C. Constr. Corp. v.
Gray Co., 17 F. Supp. 2d 541 (W.D. VA 1998). 50
817 F.2d 326 (5th
Cir. 1987) cert. den. 108 S.Ct. 329 (1987). 51
Prima Paint Corp. v. Flood & Conklin, 388 U.S. 395 (1967). 52
E.g., Yoder v. Heinold Commodities, Inc., 630 F. Supp. 756 (E.D. Va. 1986). 53
Steven Welhouse and Paule Lurie, “Ansari: Problems with Forum Selection Arbitration Clauses”,
UNDER CONSTRUCTION, ABA Forum Newsletter (August 2005). 54
9 U.S.C. § 4. 55
2005 WL 1625225 (10th
Cir. 2005). 56
524 F.2d 1275 (5th
Cir. 1975). 57
240 F.3d 781 (9th
Cir. 2001). 58
Adam Nahmias, The Enforceability of Contract Clauses Giving One Party the Unilateral Right to
Choose between Arbitration and Litigation, 21 Constr. Lawyer 36 (Summer 2001); Barker v Gulf USA,
Inc., 154 F.3d 788 (8th
Cir. 1998); Doctors Assocs., Inc. v. Distajo, 66 F.3d 438 (2nd
Cir. 1995). 59
Iwen v. U.S. West District, 977 P.2d 989 (Mont. 1999). 60
Stevens/Leinweber/Sullens, Inc. v. Holm Dev. & Mgmt., Inc., 795 P.2d 1308 (Ariz. Ct. App. 1990). 61
Willis Flooring, Inc. v. Howard S. Lease Constr. Co., 656 P.2d 1184 (Ak. 1983). 62
59 Cal. App. 4th
676, 69 Cal. Rptr. 2d 431 (1997). 63
Glower W. Jones, Alternate Clauses to Standard Construction Contracts, p. 403 (2d Ed. 1988).
ZZ997:99950:119424:1:ATLANTA 40
64
Brennan, The Construction Contracts Book, Chap. 8 “Dispute Resolution”, p. 80 (American Bar
Ass’n 2004). 65
Brennan, et al., The Construction Contracts Book. Chap. 8 “Dispute Resolution”, p. 81 (American
Bar Ass’n 2004). 66
Brennan, et al., The Construction Contracts Book, Chap. 8 “Dispute Resolution”, p. 79-80
(American Bar Ass’n 2004). 67
Brennan, et al., The Construction Contracts Book, Chap. 8 “Dispute Resolution”, p. 80-81
(American Bar Ass’n 2004). 68
Jones, Alternate Clauses to Standard Construction Contracts, pp 288, 405 (2d Ed. 1988) 69
Id. at 92. 70
Id. at 636-638. 71
Id. at 770. 72
Kevin Kennedy “Drafting an Enforceable Franchise Agreement Arbitration Clause”, 22 Franchise
L.J. 122 (Fall 2002). 73
Brennan, et al., The Construction Contracts Book, Chap. 8 “Dispute Resolution”, p. 67 (American
Bar Ass’n 2004). 74
Brennan, et al., The Construction Contracts Book, Chap. 8 “Dispute Resolution”, p. 82 (American
Bar Ass’n 2004). 75
Id. at 81. 76
Jones, Alternate Clauses to Standard Construction Contracts, p. 289 (2d Ed. 1988). 77
Id. at 287.