12
Page 1 of 12 AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF THE TENDER FOR SUPPLY OF LIQUID MEDICAL OXYGEN ON RATE CONTRACT BASIS AND SUPPPLY, INSTALLATION AND COMMISSIONING OF LIQUID MEDICAL OXYGEN STORAGE SYSTEM AT THREE MEDICAL COLLEGES Bid Ref. No.: OSMCL/2018-19/EQP-SLMO/29 Queries and necessary amendment to Techno-Commercial terms conditions 1. Queries: Pg.11, Section-IV, Clause no. 4.1 a) We recommend Storage vessel capacity (VIE Tank) should be 20 kL each for both MKCG Medical College and Hospital, Berhampur and Vimsar, Burla respectively in order to ensure smooth and uninterrupted supply of Liquid Medical Oxygen and one additional 6kL tank at SCB Medical College-Cuttack for requirement of Pulmonary Medicine department. b) OSMCL needs to clarify whether up-gradation of the existing Manifold system for all the three Institutions (Cuttack, Berhampur and Burla) is required or not. Accordingly cost against the same shall be incorporated in the Price Bid. Or Scope need to get redefined and get limited to LMO system with hook up only. Since this tender had been asked for Supply, Installation and commissioning LMO storage vessel and Supply of LMO. Original Tender Clause: Sl. Name of the institution LMO Storage Vessel Capacity (VIE Tank) 1 SCB Medical College and Hospital, Cuttack Main Unit: 20KL: 1no. Additional Units: 10KL: 1no., 6KL:1no. 2 MKCG Medical College and Hospital, Berhampur One Unit: 10KL 3 VIMSAR, Burla One Unit: 10KL Amendment: a) The required LMO storage vessel capacity for both MKCG Medical College and Hospital, Berhampur and VIMSAR, Burla is amended to single unit of 20KL from 10KL keeping in view of future expansion of the medical colleges. No additional tank required for Pulmonary Medicine department at SCB Medical College-Cuttack and should be connected with copper pipeline from available LMO storage vessel. Sl. Name of the institution LMO Storage Vessel Capacity (VIE Tank) 1 SCB Medical College and Hospital, Cuttack Main Unit: 20KL: 1no. Additional Units: 10KL: 1no., 6KL:1no. 2 MKCG Medical College and Hospital, Berhampur One Unit: 20KL 3 VIMSAR, Burla One Unit: 20KL b) It is amended that up-gradation of each existing manifold system has to be done at all three medial colleges to semi-automatic manifold system (8X8 with both main and backup oxygen cylinder bank system). The cost of the upgradation of existing manifold system to semi-automatic manifold system shall have to be quoted separately in price bid format (Format-B).

AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF …osmcl.nic.in/sites/default/files/AmendmentUploadLMO.pdf · 2019. 4. 10. · Page 2 of 12 2. Queries: Pg.12, Section-IV, Clause

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF …osmcl.nic.in/sites/default/files/AmendmentUploadLMO.pdf · 2019. 4. 10. · Page 2 of 12 2. Queries: Pg.12, Section-IV, Clause

Page 1 of 12

AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF THE TENDER

FOR SUPPLY OF LIQUID MEDICAL OXYGEN ON RATE CONTRACT BASIS AND

SUPPPLY, INSTALLATION AND COMMISSIONING OF LIQUID MEDICAL

OXYGEN STORAGE SYSTEM AT THREE MEDICAL COLLEGES

Bid Ref. No.: OSMCL/2018-19/EQP-SLMO/29

Queries and necessary amendment to Techno-Commercial terms conditions

1. Queries:

Pg.11, Section-IV, Clause no. 4.1

a) We recommend Storage vessel capacity (VIE Tank) should be 20 kL each for

both MKCG Medical College and Hospital, Berhampur and Vimsar, Burla

respectively in order to ensure smooth and uninterrupted supply of Liquid

Medical Oxygen and one additional 6kL tank at SCB Medical College-Cuttack for

requirement of Pulmonary Medicine department.

b) OSMCL needs to clarify whether up-gradation of the existing Manifold system

for all the three Institutions (Cuttack, Berhampur and Burla) is required or not.

Accordingly cost against the same shall be incorporated in the Price Bid.

Or

Scope need to get redefined and get limited to LMO system with hook up only.

Since this tender had been asked for Supply, Installation and commissioning

LMO storage vessel and Supply of LMO.

Original Tender Clause:

Sl. Name of the institution LMO Storage Vessel Capacity

(VIE Tank)

1 SCB Medical College and

Hospital, Cuttack

Main Unit: 20KL: 1no.

Additional Units: 10KL: 1no., 6KL:1no.

2 MKCG Medical College and

Hospital, Berhampur One Unit: 10KL

3 VIMSAR, Burla One Unit: 10KL

Amendment:

a) The required LMO storage vessel capacity for both MKCG Medical College and

Hospital, Berhampur and VIMSAR, Burla is amended to single unit of 20KL

from 10KL keeping in view of future expansion of the medical colleges. No

additional tank required for Pulmonary Medicine department at SCB Medical

College-Cuttack and should be connected with copper pipeline from available

LMO storage vessel.

Sl. Name of the institution LMO Storage Vessel Capacity

(VIE Tank)

1 SCB Medical College and

Hospital, Cuttack

Main Unit: 20KL: 1no.

Additional Units: 10KL: 1no., 6KL:1no.

2 MKCG Medical College and

Hospital, Berhampur One Unit: 20KL

3 VIMSAR, Burla One Unit: 20KL

b) It is amended that up-gradation of each existing manifold system has to

be done at all three medial colleges to semi-automatic manifold system

(8X8 with both main and backup oxygen cylinder bank system). The cost

of the upgradation of existing manifold system to semi-automatic manifold

system shall have to be quoted separately in price bid format (Format-B).

Page 2: AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF …osmcl.nic.in/sites/default/files/AmendmentUploadLMO.pdf · 2019. 4. 10. · Page 2 of 12 2. Queries: Pg.12, Section-IV, Clause

Page 2 of 12

2. Queries:

Pg.12, Section-IV, Clause no. 4.3

a) Sl No: 7: Provision of Fire Safety major shall be covered under SMPV Rule 16.

Or

Compliance will be achieved as SMPV Rule, 2016 under PESO. Purchaser need

to offer the location for LMO storage tank job that meets the Fire safety rules.

b) Sl No: 9: Provision of emergency back-up for Medical Oxygen supply in

cylinders shall be in the scope of the Buyer and any cost associated in refilling

of cylinders with Medical Oxygen gas shall be borne by the Buyer.

Or

Compressed Medical Oxygen in cylinders supply should be out of preview. Also

No Price format attached in Tender documents.

c) Sl No: 10: No Electrical safety test is required for this installation

Or

Electrical safety tests - Not applicable, since no electricity is required for Liquid

Medical oxygen storage tanks

Original Tender Clause:

a) Sl No: 7: Provision of required Fire Safety major as per latest fire safety rules

b) Sl No: 9: Provision of emergency backup for medical oxygen supply by supplying

required number of jumbo cylinders to the individual manifold room.

c) Sl No: 10: The successful bidder shall provide factory test certificates for the

materials used and also supply complete set of design lay outs, safety manuals,

standard operating manuals for the whole systems and subsystems to be

supplied. The detailed site plan and system layout plan including civil/ electrical

works or other related works shall be prepared by the successful bidder and

shall be handed over to the users after the commissioning of the projects. Final

electrical safety tests, fire safety test, System commissioning tests and any

quality check required shall be done by an authorized third party

agency/personnel after the handover of the project.

Amendment:

a) Pt. No. 7: Provision of required Fire Safety major as per SMPV Rule, 2016.

b) Pt. No.9: The supplier shall have responsibility of provision of emergency

backup for medical oxygen supply by refilling of the existing jumbo cylinders

available in hospital to the individual manifold room during the execution of the

project. However the hospital authority shall bear the cost of the refilling

inclusive of transportation in the approved rate only for a period of 48 hours

only from time of interruption of service of the LMO system caused due

to breakdown of the system or shutdown of the system for schedule

maintenance or exhaust of the liquid gas of the storage vessel due to not timely

filling of the LMO gas due to any mishap happens during transportation of the

transport vehicle or any other possible reason. The supplier has to bear the

cost of refilling of cylinders and shall have the responsibility to provide

backup services to each manifold systems after the first 48 hours

without any extra cost. The rate of refilling of medical oxygen cylinders

inclusive of transportation shall have to be quoted under Format-B of price bid

in PDF file.

c) Pt. No. 10: The successful bidder shall provide factory test certificates for the

materials used and also supply complete set of design lay outs, safety manuals,

Page 3: AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF …osmcl.nic.in/sites/default/files/AmendmentUploadLMO.pdf · 2019. 4. 10. · Page 2 of 12 2. Queries: Pg.12, Section-IV, Clause

Page 3 of 12

standard operating manuals for the whole systems and subsystems to be

supplied. The detailed site plan and system layout plan including civil/ electrical

works or other related works shall be prepared by the successful bidder and

shall be handed over to the users after the commissioning of the projects. The

electrical safety test is required in case of any electrical components of more

than 1000V of in use inside the LMO system.

3. Queries:

Pg.13, Section-IV, Clause no. 4.4

a) Sl.No. c: We will maintain uninterrupted supply of LMO. However during any

shutdown period or to keep manifold in good conditions- emergency back of

Bulk Cylinders reqd. Which can continue with local vendors.

b) Sl No: e: Exact quantity of LMO being supplied by the Supplier shall be

measured by weighment basis.

Or

Supply quantification need to be done based on weighment or Flow meter wise.

Content gauge is old method which is used only as reference for % stock

available in the tank.

c) Sl No: f: All supplies of LMO shall accompany with Purity certificate to be

provided by the Supplier and hence cost of testing and transportation

associated in terms of sending the gases supplied for quality test to a Govt.

approved Lab from time to time shall be in scope of the Buyer.

d) Sl No. i,j,k: We can supply as order on customer or Schedule customer through

Telemetry system installed along with LMO vessel for 0 failure in uninterrupted

supply of Oxygen and manual intervention.

e) Sl No: l: The supplier should pay Rental/Facility Charge other than cost of gases

considering investment being done on the procurement of tanks and associated

accessories.

Or

Will maintenance of the equipment for first 5 years + 5 years further will be the

responsibility of the supplier. However a Facility Charge on monthly basis

should be included as part of the price schedule for as maintenance charge due

high cost of spares & high initial investment of the equipment, as the size and

quantity of equipment varies from each hospital.

Original Tender Clause:

a) Sl.No. c: The bidders should be able to maintain uninterrupted supply of LMO

and medical gases even in emergencies. The bidders shall give undertakings to

the Hospitals and make alternate arrangement for the supply of gases at their

risk and responsibility.

b) Sl. No: e: The Supplier shall ensure that exact quantity of LMO is being supplied

by proper measurement (volume of LMO through properly calibrated content

gauge), which shall be arranged by him, failing which, the supply shall have to

be replaced by the supplier on his own cost.

c) Sl. No: f: The gases supplied will be sent for quality test to a Govt. approved

Lab from time to time and the cost of testing & Transportation or any other

incidental charges will be borne by the supplier.

d) Sl. No. i,j,k: i) Failure or delay in supply of life saving medical gases shall result

in financial penalty and any other levy as decided by the Tender inviting

authority. j) The bidders shall give undertakings that if they fail to maintain

Page 4: AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF …osmcl.nic.in/sites/default/files/AmendmentUploadLMO.pdf · 2019. 4. 10. · Page 2 of 12 2. Queries: Pg.12, Section-IV, Clause

Page 4 of 12

standards of tank and cylinders, gases and if some mishap occurs, they shall be

responsible for the same. k) The bidders shall give undertakings to the

hospitals that they will provide uninterrupted supplies as per demand of the

hospitals.

e) Sl. No: l: The supplier shall not be paid any rental/facility charges other than

cost of gases.

Amendment:

a) Pt. no. c: The bidders should be able to maintain uninterrupted supply of LMO

and medical gases even in emergencies. The bidders shall give undertakings to

the Hospitals regarding the same and make alternate arrangement for the

supply of gases at their risk and responsibility after first 48 hours of

interrupted service of the LMO system for the reasons mentioned

above.

b) Pt. no. e: The Supplier shall ensure that exact quantity of LMO is being supplied

by proper measurement through either properly calibrated volume gauge of

LMO or Flow meter or content gauge) which shall be arranged by the

supplier failing which necessary penalty shall be levied on the supplier as

decided by the hospital authority.

c) Pt. No. f: The gases supplied may be sent for quality test to any Govt. approved

Lab from time to time for ensuring the quality of the delivered product and the

cost towards the testing or any other incidental charges will be borne by the

hospital authority. However the transportation of the test sample shall

have to be done by the supplier.

d) Pt. no. i, j, k: The clauses shall remain unchanged. However it is clarified that

the daily monitoring of the status of the LMO tank storage shall be undertaken

by supplier through remote monitoring system or daily routine contact to the

operator or through scheduled period delivery process based on consumption.

e) Pt. No. l: The supplier shall be paid with only facility charges of the LMO

system other than the cost of gas as approved in the tender. The cost

towards the facility charge per tank per month for entire 10 years of

duration shall have to be quoted under Format-B of other price bid format

in PDF file and which shall be taken into account of price evaluation for

derivation of lowest quoted bid. The revised Format-B of price bid is attached at

Appendix-A.

4. Queries:

Pg.15, Section-V, Clause no. 5.1

a) Clause No: 5.1.1: Regret our inability to accept Supply, installation and

Commissioning period within 90 days from the date of issue of Work Order and

Site handover. We request the same to be within 180 days from the date of

issue of Work Order and Site handover.

Or

Supply, Installation, commissioning period should be considered 135 days from

the date of written site clearance from Purchaser or original consignee and

same shall be applicable for Clause no. 6.29.1.

b) Clause No: 5.1.4: Regret our inability to accept Validity of rate as 10 years from

the date of approval. Supplier should be entitled for a revision in price of the

Product as well as for the Monthly Facility Charges for Tank (VIE) usage on the

basis of Power, Fuel and WPI variation

Page 5: AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF …osmcl.nic.in/sites/default/files/AmendmentUploadLMO.pdf · 2019. 4. 10. · Page 2 of 12 2. Queries: Pg.12, Section-IV, Clause

Page 5 of 12

Or

Fixing a 10 years, Liquid Medical Oxygen will be high variable driven product

with key component Power , Diesel and Consumer/ Wholesale price Index is

regularly changing on increasing trend, along with the cost of capital equipment

used each institutions. A yearly fixed escalation should be included during the

contract period, with clear definition on the applicability during the 5 YEAR and

post extension period.

c) Clause no. 5.1.8: Oxygen should be provided 24 x7 x 365 days. No uptime is

applicable.

Original Tender Clause:

a) Clause No: 5.1.1: Supply, Installation & Commissioning period: Within 90 days

from the date of issue of Work Order and Site handover

b) Clause No: 5.1.4: Validity of Rate : 10 years from date of approval

c) Clause no. 5.1.8: Uptime in a year: 95%

Amendment:

a) Clause no. 5.1.1: Supply, installation and commissioning period shall be within

120 days from date of issue of work order and site handover whichever is later

and is also applicable for Clause no. 6.29.1. (Another 30 days from the tender

schedule of 90 days is felt sufficient to execute the project and also to avoid

further delay for functioning of the project)

b) Clause no. 5.1.4: The approved price of liquid gas and facility charges shall have

an escalation of 3% per year on the approved base rate subject to

production of Govt. notification on hike in price/service/taxes.

c) Clause no. 5.1.8: Uptime is not applicable. Hence deleted from tender as

already period of back up service and scope of supply has been defined earlier.

5. Queries:

Pg.15, Section-V, Pre-qualification of the bidder

a) Clause No: 1.2.2: Manufacturing Unit of the supplier shall be within 750 km and

not 500 km distance from the concerned institution for convenience and

avoiding delay in emergencies.

Or

Should retain the clause of having manufacturing plant within 500km distance

from the concerned institution for maintaining uninterrupted and reliable supply

avoiding cross state product movements.

b) Clause No: 1.2.6: Turnkey word may please be omitted for setting up Liquid

Medical Oxygen Storage Vessel and supply to at least 5 nos. of Govt./Corporate

Hospitals/Private Hospitals/Medical Colleges each with bed capacity of at 500

beds and not 750 beds during last three financial years.

Or

Should be there for better experience and management of this scale and size of

the Govt. hospital project.

c) Clause no. 1.2.7: Should be at least 500 Crs. as LMO supply of three MCH is

part of tender. As supplier has to have large ASU, along with sufficient tanker

and working capital for enabling services required for the Healthcare Institution

under Govt.

Original Tender Clause:

a) Clause No: 1.2.2: The bidder must have at least two manufacturing units of

Liquid Medical Oxygen in India, out of which, at least one manufacturing unit

Page 6: AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF …osmcl.nic.in/sites/default/files/AmendmentUploadLMO.pdf · 2019. 4. 10. · Page 2 of 12 2. Queries: Pg.12, Section-IV, Clause

Page 6 of 12

must be within 500km. distance from the concerned institution for convenience

and avoiding delay in emergencies.

b) Clause No: 1.2.6: The bidder must have executed the turnkey job of Setting up

of Liquid Medical Oxygen Storage Vessel and on supply process of Liquid

Medical Oxygen in India in at least 5 nos. of Govt./Corporate Hospitals/Medical

Colleges each with bed capacity of at least 750 beds during the last three

financial years i.e. 2015-16, 2016-17 & 2017-18. Project completion and

commissioning certificates shall have to be furnished as proof of supply, failing

which the bid shall be liable to be rejected.

c) Clause no. 1.2.7: The bidder must have a minimum average annual turnover of

Rs.10 Crores in the last three financial years i.e. 2015-16, 2016-17 & 2017-18,

to be certified by a Chartered Accountant in Format T8.

Amendment:

a) Clause no. 1.2.1: The bidder must have atleast two manufacturing units of

Liquid Medical Oxygen in India, out of which, at least one manufacturing

unit must be within 750km. distance from the concerned institution for

convenience and avoiding delay in emergencies.

b) Clause no. 1.2.6: The bidder must have executed the job of setting up of Liquid

Medical Oxygen Storage Vessel on turnkey and on supply process of Liquid

Medical Oxygen in India in at least 5 nos. of Govt. hospitals/ Corporate

Hospitals/Medical College hospitals each with bed capacity of atleast

500 beds during the last three financial years i.e. 2015-16, 2016-17 &

2017-18. Project completion and commissioning certificates shall have to be

furnished as proof of supply, failing which the bid shall be liable to be rejected.

c) Clause no. 1.2.7: No Change

6. Queries:

Pg.38, Clause no. 6.30

a) Clause No: 6.30.1: Regret our inability to accept with no advance terms

b) Clause No: 6.30.2: Our agreed payment terms shall be as under:

i) 40% advance along with Work Order

ii) 30% within 7 days from the date of receipt of material supply at site duly

certified by the buyer through Stock entry certificate

iii) 20% within 7 days against civil construction and installation of the tanks at

all the sites

iv) 10% against successful training and commissioning of the tanks at all the

sites

Or

LMO project will have two parts: one turnkey work i.e. civil & pipeline and regular

payment of LMO supply bills: 1. Supply bills should be payable within 30 days. 2.

Turnkey projects payment bill will be payable just after hand over certification with

stock entry certificate etc. i.e. as per NIT.

c) Payment against LMO shall be within 30 days from the date of receipt of

material at your Hospital sites

d) It may further be noted that cost of statutory requirements/statutory fees along

with shall be borne by the Buyer directly.

Or

Directly payable by consignee/ Individual Hospital, as License charge payable to

Govt.as per statutory requirement.

Page 7: AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF …osmcl.nic.in/sites/default/files/AmendmentUploadLMO.pdf · 2019. 4. 10. · Page 2 of 12 2. Queries: Pg.12, Section-IV, Clause

Page 7 of 12

e) The Buyer shall provide tested and certified crane, of appropriate capacity as

specified by supplier at Buyer’s own cost for unloading of the tanks at all the

Hospital sites and loading the same on the foundation. However, total

supervision shall be done by supplier and supplier site in charge designated for

this job.

f) Clause No: 6.32.5 and 6.32.9 may kindly be withdrawn.

g) Regret our inability to accept Clause No: 6.43.5 against Liquidated Damages

h) Regret our inability to accept Clause no: 6.44 (Termination of contract) which

needs revision as under:

This Agreement shall be terminable:

a) By either party giving not less than 60 (sixty) days’ notice in writing to the other

party for breach by the other Party of any of the terms and conditions of this

Agreement save as otherwise stated in clause 12.1c below and provided such

breach shall not have been rectified by the end of the said notice period.

b) By either party forthwith by giving notice in writing to the other, in the event of the

other going into liquidation compulsorily or voluntarily, being declared insolvent or

in the event of the other consenting to amalgamation, merger or take-over.

c) Notwithstanding anything contained hereinabove, timely payment of the equipment

usage charges and price for the products supplied is the essence of this Agreement

and a breach of this obligation by Buyer is a breach of terms of this Agreement and

notwithstanding any other remedy stated hereinabove, shall entitle Seller at its

discretion to suspend supplies of Product or terminate this Agreement forthwith. In

either case, the Buyer shall be solely liable and responsible for all consequences

thereof, including any death or injury to any of the patients consuming the Product

at the hospitals where the Product is being supplied hereunder.

In the event of termination of this Agreement:

a) Buyer shall pay for the supplies already made by Seller and the Equipment usage

charges as long as the Equipment remains in the custody of Buyer in terms of this

Agreement.

b) Buyer shall forthwith return to Seller, the Equipment and every part thereof and

any other equipment or assets of Seller, which may be in or under Buyer’s control,

without demur or protest and without making any claims or demands whatsoever.

c) Seller shall remove the Equipment within three (3) months of termination of this

Agreement.

d) It is expressly agreed between the parties that in the event of termination of this

Agreement Buyer shall pay to Seller all the expenses incurred by Seller, towards

decommissioning & transportation of the Equipment. However in the event of

earlier termination of Agreement due to breach of any of the terms of the

Agreement by Buyer, Buyer shall bear twice the expenses incurred by Seller,

towards decommissioning and transportation of the Equipment.

Or

Clause no: 6.44.1 and 6.44.5: The clause should be extended to Suppliers also

(Reciprocal), with a clear notice to be given to the individual institutions to have a

common approach on termination of contract.

Original Tender Clause:

a) Clause No: 6.30.1: No advance payment shall be made to the supplier.

b) Clause no. 6.30.2: 90% of the cost towards civil construction/ modification/

development work, Cost of expansion of copper pipeline system/ up-gradation of

Page 8: AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF …osmcl.nic.in/sites/default/files/AmendmentUploadLMO.pdf · 2019. 4. 10. · Page 2 of 12 2. Queries: Pg.12, Section-IV, Clause

Page 8 of 12

gas manifold system (excluding CMC Cost) + 100% of the liquid medical gas

filled in the tank, Cost of Statutory requirement/statutory fees and installation

cost if any + 100% tax shall be paid to the supplier on receipt of the stock entry

certificate, installation and demonstration/ training of the item from the

consignee.

c) Clause no. 6.32.5: The prospective bidder, who are manufacturers, shall submit

an undertaking in the Format T6 & T7 from the Original Equipment

Manufacturers (OEM) that they are willing to provide spare parts for the period

of warranty as mentioned and also during the additional CMC period, if awarded.

The OEM shall also assure continuity of service to their product, in the event of

change in dealership or the bidders – their existing dealers - couldn’t provide

service during the warranty / CMC period.

d) Clause no. 6.32.9: Complaints should be attended properly, maximum within

the time mentioned in clause 5.1.9. In case, the repair/fault duration is likely to

exceed 72 hours, the period of warranty or CMC period shall be extended for

2days for every 1day delay maximum up to 15 working days. On exceeding the

15 working days, the performance security of the successful bidder shall be

forfeited and deemed action shall be initiated as per the procurement guideline.

e) Clause no. 6.43.5: Liquidated Damage

f) Clause no. 6.44: Termination of Contract with sub clauses as mentioned in

tender document

Amendment:

a) Clause No: 6.30.1: No Change in clause, Advance payment shall not be made

to the supplier.

b) Clause no. 6.30.2: No Change, Payment schedule shall remain same as

specified in the clause.

c) No payment shall be made for only delivery or receipt of the goods.

d) Cost towards statutory requirements/statutory fees/Licensing fees shall be

paid to the supplier as per the Govt. approved rate. No additional

consultancy fee/ liaising fee/Supervising fee shall be paid to the supplier.

e) As a part of the installation & commissioning work, all kind of heavy duty

machineries such as Cranes/excavator/hydra required during project shall have

to arrange and cost towards necessary job shall have to borne by the supplier.

f) Clause no. 6.32.5: The prospective bidder, who are manufacturer of the liquid

medical oxygen shall have to submit an undertaking in the Format T6 only. Rest

of the point under the clause is not applicable.

g) Clause no. 6.32.9: The clause is deleted as warranty and CMC costs are not

applicable.

h) Clause no. 6.43.5: No Change

i) Clause no. 6.44: No Change

7. Queries:

Pg.9, Section-III, Clause no. 3.1.5

The liquid oxygen system will be built, owned & maintained by the supplier.

Customer have also demanded for Performance security deposit. So here warranty

of the equipment should not be applicable, since the point had got covered in the

above 2 points.

Original Tender Clause:

Page 9: AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF …osmcl.nic.in/sites/default/files/AmendmentUploadLMO.pdf · 2019. 4. 10. · Page 2 of 12 2. Queries: Pg.12, Section-IV, Clause

Page 9 of 12

The successful bidder shall furnish a performance security in the shape of a

Demand Draft/Bank Guarantee issued by a Nationalized Bank in favour of Tender

Inviting Authority for an amount of 10% of the annual contract value. The annual

contract value shall be the cost of liquid gas for a year i.e. Approved Rate per Cubic

meter (M3)×50,000 (Cubic meter per month)×12 (months)×3 Units (assuming

consumption of 50,000 m3 per month).

Amendment:

Performance security of specified amount shall have to be submitted as

part of the tender clause. However warranty and CMC is not applicable.

CORRIGENDUM

The typographical error in value of cubic meter at Pg. no. 11, under importance

notes, the pt. no. 1 is corrected as follows,

1. The bidders shall have to quote the price of liquid medical oxygen per cubic

meter for each medical college in the respective row of BOQ (attached as

excel file) in the e-tender portal. However, for evaluation purpose, total cost for

1,00,000 cubic meter unit for SCBMCH-Cuttack, 60,000 cubic meter unit for

MKCGMCH-Berhampur and 50,000 cubic meter unit for VIMSAR-Burla will

be taken into consideration based on the quoted rate per institution.

Queries relating to Technical Specification (Section VII)

Sl.

Item/

Particulars

Name in the

Specification

Queries raised by

the prospective

bidders

Original Technical

Specification

Clarifications/

Amendments in

response to the

queries.

1

Pg. no. 53,

Pt.no.5:

Liquid

Medical

Oxygen

Tank

Change over from

Main supply (Liquid

Medical Oxygen) to

back up supply will

occur on pressure

difference, provided

the backup manifold

is connected with

sufficient full cylinder

and kept in ready to

use condition.

The vessel shall be

supplied as a

functional whole with

all materials of

construction & the

cleaning regime

suitable for medical

grade liquid oxygen.

In case of failure in

liquid oxygen supply,

it should

automatically switch

over to an

emergency oxygen

manifold.

Clarified that

In case of failure in

liquid oxygen supply, it

should automatically

switch over to an

emergency oxygen

manifold system

connected with existing

jumbo cylinders with

filled oxygen. The

supplier shall have to

monitor and inform the

system in-charge timely

for the status of back

up cylinders for smooth

operation of the

system.

2

Pg. no. 54,

Accessories

B)

Submittals

Original Quality Test

Certificates are

retained by PESO, so

only the copy of the

certificates can be

The Liquid Medical

oxygen tank shall

accompany the

Original Quality Test

Certificate

Amended

During project

handover, quality test

certificates in duplicate

or photo copy certified

Page 10: AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF …osmcl.nic.in/sites/default/files/AmendmentUploadLMO.pdf · 2019. 4. 10. · Page 2 of 12 2. Queries: Pg.12, Section-IV, Clause

Page 10 of 12

handed over by PESO should be

furnished.

3

Pg. no. 55,

Accessories

B)

Submittals

Pt. no. 6

Change over from

Main supply (Liquid

Medical Oxygen) to

back up supply will

occur on pressure

difference, provided

the backup manifold

is connected with

sufficient full cylinder

and kept in ready to

use condition.

Automatic change over

should be provided

between the LMO Tank

and existing oxygen

manifold in Entire

campus of Medical

College Hospital.

Clarified that

In case of failure in

liquid oxygen supply, it

should automatically

switch over to an

emergency oxygen

manifold system

connected with existing

jumbo cylinders with

filled oxygen. The

supplier shall have to

monitor and inform the

system in-charge timely

for the status of back

up cylinders for smooth

operation of the

system.

4

Pg. no. 55,

Accessories

B) Safety

Pt. no. 6

Annunciation panel

will show if there is

any deviation from

the set parameters.

Automatic

changeover to

manifolds with

control panel

Amended

Automatic changeover

to manifolds with

annunciation panel

showing change in set

parameters.

5

Pg. no. 55,

Accessories

B) Safety

Pt. no. 6

It should be same as

presently maintained

by individual user /

Manifold

Manifold control

panel should be kept

outside scope.

Alarm on indicating

manifold in use in

case the vessel is not

in use and

Alarm on low

pressure back-up

manifold cylinders

Amended

Alarm on indicating in

case the vessel is not in

use.

Alarm on low pressure

back-up manifold

cylinders should be

displayed in the semi-

automatic manifold

system, which shall be

supplied by the

supplier.

6 Copper

Pipeline

We request you to

include Copper+ SS

pipe as it will be

more durable and

easy to handle in

Public area of

Hospital and less

chance of theft.

Only Copper pipeline

has been specified.

No Change, Clarified

that only Copper pipe

certified by Lloyd shall

have to be supplied.

7 Ground

Trenching

We request for

underground trench/

Only ground

trenching has been

Amended

For distribution of

Page 11: AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF …osmcl.nic.in/sites/default/files/AmendmentUploadLMO.pdf · 2019. 4. 10. · Page 2 of 12 2. Queries: Pg.12, Section-IV, Clause

Page 11 of 12

Overhead structure

depending on safety

of pipeline routing.

specified. copper pipeline from

LMO Tank to individual

manifold, either

underground trenching

of atleast 2 feet with

concrete lining and

cover lid or overhead

structure of sufficient

height shall have to be

made for safety of

pipeline routing. Proper

labelling/indication/caut

ion shall have to be

executed at the

distribution site of the

copper pipeline.

Page 12: AMENDMENT TO PRE-BID MEETING HELD ON DT.12.03.2019 OF …osmcl.nic.in/sites/default/files/AmendmentUploadLMO.pdf · 2019. 4. 10. · Page 2 of 12 2. Queries: Pg.12, Section-IV, Clause

Page 12 of 12

The amended format-B of price bid format is as follows, Appendix-A

FORMAT-B

(Shall be considered for financial evaluation)

Nature of Work: Towards expansion of copper pipeline from LMO Storage Vessel to manifold

system and Upgradtion of the manifold system (Hospital wise and Vessel Capacity Wise)

Name of Institution: <Mention the name of the institution>

Vessel Capacity (20KL/10KL/6KL) <Mention the Vessel Capacity>

Sl. No.

NAME OF PARTICULAR WORK WITH DESCRIPTION (As per the standard length of 500 meter)

<Payment shall be made based on as per actual basis after the post commissioning calculation and

inspection>

Quantity (Approx.)

Unit (Mtr./No.

/Pc.)

Rate (in Rs.)

Amount (in Rs.)

1 Expansion of copper pipeline from LMO Storage Vessel to manifold system.

500 Mtr.

2 Cost towards upgradation of existing manifold to semi-automatic manifold system (8x8) cylinder bank configuration

As Required

per Vessel

3 Cost towards refilling of existing jumbo cylinders for backup supply at manifold system inclusive of transportation.

1no.

4 Facility Charges of the LMO Storage System per 20KL vessel capacity per month for entire 10 years

Lump sum

5 Facility Charges of the LMO Storage System per 10KL vessel capacity per month for entire 10 years

Lump sum

6 Facility Charges of the LMO Storage System per 6KL vessel capacity per month for entire 10 years

Lump sum

7 <Any other work may be defined>

.

TOTAL (in Rs.)

(Both in Figure and Word)

Note: The above format shall have to be prepared for each of the vessel capacity of

the individual medial colleges separately. The total price of the each of the format

(Format-B) along with civil cost quoted in Format-A for each location of LMO vessel

and cost of LMO quoted in excel price bid format for each medical colleges shall be

added together for evaluation of lowest quoted bidder.

N.B:

1. The amendments mentioned above are to be treated as amendments in the

technical specification(s) and term(s) and condition(s) of the above tender reference.

All other technical specifications and terms conditions remain unchanged.

2. Since any text in the price BOQ can’t be changed in the e-tender portal, the

amendments mentioned in the specifications above are to be treated as amendments

in the price bid/ BOQ also.

Sd/

Managing Director, OSMC