Althea Wilkinson Radio Net Project Manager University of Manchester Jodrell Bank Observatory. Mid-Term Review Management Aspects Grenoble April 2007. Outline. Collaboration and Interaction - LGurvits Administrative Financial Current status Comparison with original planning - PowerPoint PPT Presentation
Citation preview
Althea WilkinsonRadioNet Project Manager
University of Manchester Jodrell Bank Observatory
Mid-Term ReviewManagement AspectsGrenoble April 2007
Outline
• Collaboration and Interaction - LGurvits• Administrative• Financial
– Current status– Comparison with original planning– Situation for rest of FP6 project– Recommendations for FP7
Finance workshops
• Finance workshop – October 2005 – – Aimed at administrative staff supporting
RadioNet around Europe– Best practice for Form C, Justification of
costs, audits etc.• Finance workshop for SKADS coordinators
administration at their start-up, Dec 2005– Best practice, pitfalls, etc
RadioNet Management Structure
RadioNet Board
Project Scientist Project Manager
Executive Committee
Administrative Assistant Project Officer
Joint Research Activities Networking Transnational Access
Management - administration• RadioNet has worked well – achieved goal of improving
European contact and collaboration
• Scientific and Technical management– By JRA Leaders, NA leaders and TNA contacts
• Administrative and financial management– Shared administrative responsibility between JBO and JIVE – Contract amendment – Co-ordination of reporting – technical and financial– Distribution of EC finance – Co-ordination of audits
Communication within RadioNet• 2 Board meetings/year – different functions & sizes• Sub-committees (eg FP7) - telecons
• Communication via RMT (about every 6 weeks) and Exec telecons (~ every 3 months)
• WIKI – temporary document exchange, meetings in formation, minutes, etc.
• Permanent RadioNet Document Archive – storage of all documents, plans, minutes, etc.
Administration (4)
• Issues– Role of JIVE as separate banker –
mechanism needs to be streamlined for FP7– Sanctions on feedback difficult to enforce– Look at more use of videoconferencing
• JBO Management team produced 582kg of CO2 in flights for this meeting
Finance - Overall statusY1 Y2 Y3 Total Left
2,759,164 2,994,062 2,841,528 8,594,754 3,802,236
Total spend, actual versus original budget
0.00
500,000.00
1,000,000.00
1,500,000.00
2,000,000.00
2,500,000.00
3,000,000.00
3,500,000.00
4,000,000.00
M1-M12 M13-M24 M25-M36 M37-M48 M49-M60
Reporting period, month x to month y
€
Original
Actual
Predicted for 2007
Finance – TNA status
TNAs actual spend to end Dec 2006 vs. original budget
0
200000
400000
600000
800000
1000000
1200000
1400000
JBO
IRAMINAF
PPARCEVN
TNA trav
el
MPIfR
ASTRON
CHALMERSUMK
Facility/Institute
€
ActualOriginal budget
TNAs
• 135% claimed in Y1 – hence 65% in Y5• Hours of access lower in Y3 – engineering
works – still 1.9 x minimum• Re-allocations – to create contingency
– So far 2.5%– By end of Y5 – 3%– Enables outreach, workshops and training
meetings, Hands on Universe, SKA office contribution, calendars, etc…
TNA reallocations
Re-allocations compared to original budget
0
200000
400000
600000
800000
1000000
1200000
1400000
JBO
IRAMINAF
PPARCJIV
E
JIVE tr
avel
MPIfR
ASTRON
CHALMERSUMK
Institute
€
RealloactionsOriginal budget
TNA issues
• Publications – Y2 – 5– Y3 – 63 – increasing satisfactorily– Acknowledgement of RadioNet
• User feedback– Feedback forms not uniformly returned
• AI from Board meeting to re-circulate TNA operators with guidelines, and on operators to ensure acknowledgment and feedback achieved
JRAs - ALBUSALBUS actual versus projected spend to end Dec
2006
0
100000
200000
300000
400000
500000
600000
JIVE JBO MPIfR ASTRON
Institute
€ ActualProjected
Funded activity will continue to end of FP6 RadioNet
JRAs - PHAROSPHAROS actual vs projected spend to end Dec 2006
050000
100000150000200000250000300000350000400000450000500000
ASTRON JBO INAF UMK UBIR MECSA
Institute
€
ActualProjected
JBO development (beam former) delayed – continues to end 2007
On-telescope testing – reduced programme to test only on Lovell telescope proposed
AI on further €50K funding for ASTRON
JRAs - AMSTARAMSTAR actual vs. original budget to end Dec 2006
0
50000
100000
150000
200000
250000
300000
350000
400000
450000
IRAM CHALMERS CCLRC-RAL SRON OBSPM KOSMA FG-IGN TuD
Institute
€
ActualOriginal budget
Several institutes now finished work – all complete by Dec 2007
Projected over-run of €20K – re-allocation approved by Board
Management – N1JBO Management, actual versus original budget
0
100000
200000
300000
400000
500000
600000
Y1 Y2 Y3 3Y total
€
Actual
Original
JIVE mangement, actual vs. original budget
0
50000
100000
150000
200000
250000
300000
350000
Y1 Y2 Y3 3Y total
€
Actual
Original
Travel actual
Travel original
Management staff/other costs
Still sufficient total budget
JIVE overrunning – still positive overall
JIVE originally planned only for 4 years
Management travel
Formally over-running
Result of more activity than expected – support for Board members travel to Board meetings
Can still be accommodated within overall costs
Monitor closely
Networking – N2N2 Synergy
0
50000
100000
150000
200000
Year 1 Year2 Year3 3Y total 5Y total
€
Staff actualStaff originalTravel actualTravel original
With re-allocations
Originally planned for 2 years
Will run into 2007 with meetings and residual staff support
Networking – N3
Over-run every year
With reallocations, can run at same rate until mid 2008
N3 Science Workshops
0
50000
100000
150000
200000
250000
Year 1 Year2 Year3 3Y total 5Y total
€
Actual
Original
Current
With re-allocations
NA3 Meetings - 2007Meeting
EVN2015
Location
Dwingeloo
Date
01-02/03/07
Cost €
2500LOFAR Science Dwingeloo 23-27/04/07 9000II EPTAM Cagliari 16-18/05/07 2500ERIS Bonn 10-15/09/07 16000
YERAC Bordeaux 16000Massive stars Heidelberg 10-14/09/07 3500Modern Radio
Universe Manchester 01-05/10/07 15000
Total 64500
Networking – N4 & N6N4 Engineering Forum, actual spend vs original budget
0
20000
40000
60000
80000
100000
120000
Year 1 Year2 Year3 3Y total 5Y total
€
Actual
Original
N6 ALMA Forum
0
20000
40000
60000
80000
100000
Year 1 Year2 Year3 3Y total 5Y total
€
Actual
Original
Taken together – situation similar
Both within budget
Both started slowly
Both should complete without problems
Small re-allocations towards N3
5K from N4
10K from N6
Still to be cleared with NA chairs
Networking – N5N5 Software Forum
0100002000030000400005000060000700008000090000
Year 1 Year2 Year3 3Y total 5Y total
€
Actual
Original
Minimal activity – terminated by agreement with Board and NA5 chairs
Funds reallocated to JRAs and NAs
Re-allocation of remaining N5 funding
Left on closure on N5 65205
ALBUS for taking on remaining N5 work 13000
PHAROS, funding for Torun to attend meetings 10000
ALMA forum 10000
To NA3 32205
Networking N7N7 Astronomy Across Europe: actual spend vs
original budget
0
50000
100000
150000
200000
250000
300000
Year 1 Year2 Year3 3Y total 5Y total
€
Actual
Original
Current
With re-allocations
Has expanded significantly beyond original plan
Covers all outreach activities
Where most of re-allocated funds have been used
(TNA travel 30K, TNA re-allocation, 5Y,180K)
Networking – N8
N8 Spectrum Management
0
20000
40000
60000
80000
100000
120000
Year 1 Year2 Year3 3Y total 5Y total
€
Actual
Original
Well under control
Should complete with no problems
Projection to end 2008
Estimated Two Year Requirements
1.65 years TNA after re-allocations at 2006 rate 1 921 912
JRAs including reallocations 954 816
NAs at requested rate for 18 months 547 619
plus estimate at same rate for last 6 182 540
Total 3 606 887
Still left, in bank and with EC 3 802 236
Remaining after all projected payments 195 349
18 months Implementation Plan – 2007 to June 2008
Current request is € 3 181 352.11
EC have pointed out this is close to the maximum we can request, and have queried whether this is what we really want
We can only get 80% of unaudited EC contribution before end of project
At present, only audited up to end of Y2
Also still only get 75% of request minus what remains of previous pre-financing.
Current request will give us pre-financing of € 1 746 636.31
Implementation Plan (2)
Left to claim at start 2008 - € 87 471.80
Left to claim at start of 2009 - € 1 328 752.78
Strategy discussed at Board meeting yesterday for the
financing of the end of FP6 RadioNet
Alternatives presented were:
• Have another audit at the end of 2007
• Claim everything now
• Spread claim evenly over last two years
Strategy for financing last two years of FP6 RadioNet
• All institutes will be asked to accept an additional audit of Y4 and Y5 at the end of 2007
• The current IP will be modified slightly to increase the current request to the maximum allowable
• Only request next year will be for prefinancing freed by 2007 audit
Finance – suggestions for FP7• Bear in mind funding of:
– Contingency– Outreach– Board Meetings
• Larger fraction for management• Consider how travel should be funded
Collaboration and Interaction• Within RadioNet
– NAs and JRAs by definition are collaborative projects
– NA events facilitate collaboration on European (eg YERAC, ERIS) and worldwide (eg ALMA) scale outside RadioNet community
– Active European collaboration has grown from this experience – has worked well and we know each other better
Interactions outside RadioNet• Board meetings foster contacts at high level through “at
large” members from other I3s (ILIAS, Opticon, EuroPlanet, Astronet – now on Road Map panels )– Represented at each others Board meetings– Joint meeting with ILIAS planned for 2008
• With other major projects (ALMA,SKA etc)– Board Representatives– Plan FP7 JRAs connected with these projects
• With observatories/institutions worldwide– Outreach activities (calendars, brochures, HOU project,IAU
etc)• Attendance at EAS, IAU, I3-Net and JENAM meetings