7/30/2019 Alpha p Harm
1/3
ID Task Name % Complete Duration Predecessors
1 Alphapharm Project Planning 0% 54 days
2 Initiate Stage 0% 2 days
3 Conduct project kick off 0% 1 day
4 Order services 0% 0 days
5 Develop the project schedule 0% 1 day 3
6 Initiate Stage complete 0% 0 days 5,4
7
8 Execute Stage 0% 54 days
9 Network Solution 0% 54 days
10 Network Design Stage 0% 5 days
11 Conduct network design meeting 0% 1 day 3FS+1 day
12 Produce the network diagram 0% 1 day 11
13 Customer review and approval of ND 0% 3 days 12
14 Plan the site priorities and staging 0% 1 day 12
15 Design Stage complete 0% 0 days 14
16
17 60 Mica St Carole Pk 5M wireless upgrade 0% 24 days
18 Customer provide installation authorisations 0% 5 days
19 Provision the wireless link 0% 15 days 18
20 Provision the network 0% 3 days 19
21 Customer cutover activity 0% 1 day 20
22 Completed wireless link - Service Ready 0% 0 days 21
23 Cancel the Optus Broadlink access 0% 0 days 22
24
25
26 32 Mica St Carole Pk 5M backup upgrade 0% 24 days
27 Customer provide installation authorisations 0% 5 days
28 Provision the wireless link 0% 15 days 18
29 Provision the network 0% 3 days 19
30 Customer cutover activity 0% 1 day 20
31 Completed wireless link - Service Ready 0% 0 days 21
32 Cancel the BDSL access 0% 0 days 31
33
34 Garnett St Carole Pk 20M new backup 0% 24 days
35 Customer provide installation authorisations 0% 5 days
36 Provision the wireless link 0% 15 days 35
37 Provision the network 0% 3 days 36
16/05
17/05
22/05
18/06
18/06
18/06
18/06
Apr May Jun JulQtr 2, 2013 Qtr 3, 2013
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
Project: Infrastructure upgrade project
Date: Thu 23/05/13
7/30/2019 Alpha p Harm
2/3
ID Task Name % Complete Duration Predecessors
38 Customer cutover activity 0% 1 day 37
39 Completed wireless link - Service Ready 0% 0 days 38
40
41 Millers Point Internet Service 0% 29 days
42 Upgrade Primary 0% 29 days
43 Provision the 30M AAPT access 0% 25 days 4
44 Provision the network 0% 3 days 43
45 Cutover activity 0% 1 day 44
46 Implemet Backup 0% 29 days
47 Provision the 30M Telstra access 0% 25 days 4
48 Provision the network 0% 3 days 47
49 Cutover activity 0% 1 day 48
50 Cancel Testra access 0% 0 days
51 Cancel the 4M Telstra access 0% 0 days 45
52
53 Millers Point MPLS upgrade 0% 29 days
54 Primary Service 0% 16 days
55 Provision Q in Q to exisitng access 0% 15 days
56 Cutover activity 0% 1 day 55
57 Backup Service 0% 29 days
58 Provision the 10M Optus access 0% 25 days
59 Provision the network 0% 3 days 58
60 Cutover activity 0% 1 day 59
61 20M Wireless Service 0% 24 days
62 Customer provide installation authorisations 0% 5 days
63 Provision the wireless link 0% 15 days 62
64 Provision the network 0% 3 days 63
65 Customer cutover activity 0% 1 day 64
66
67 SIP implementation 0% 54 days
68 Port validation activities(dependant on requirements) 0% 20 days
69 Provision the SIP trunk 0% 5 days 60
70 Customer SIP testing 0% 10 days 69
71 Customer ready for porting 0% 0 days 70
72 ISDN number porting 0% 10 days 71
73
74 Close Stage 0% 2 days
18/06
25/06
25/06
16/07
Apr May Jun JulQtr 2, 2013 Qtr 3, 2013
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 2
Project: Infrastructure upgrade project
Date: Thu 23/05/13
7/30/2019 Alpha p Harm
3/3
ID Task Name % Complete Duration Predecessors
77
78 Manage Stage 0% 46 days
79 Project Progress Meetings 0% 46 days
80 Project Progress Meeting 1 0% 1 hr
81 Project Progress Meeting 2 0% 1 hr
82 Project Progress Meeting 3 0% 1 hr
83 Project Progress Meeting 4 0% 1 hr
84 Project Progress Meeting 5 0% 1 hr
85 Project Progress Meeting 6 0% 1 hr
86 Project Progress Meeting 7 0% 1 hr
87 Project Progress Meeting 8 0% 1 hr
88 Project Progress Meetings 9 0% 1 day
89 Project Progress Meetings 10 0% 1 day
90
91 Project Highlight reports 0% 46 days
92 Develop and release Highlight reports 1 0% 1 hr
93 Develop and release Highlight reports 2 0% 1 hr
94 Develop and release Highlight reports 3 0% 1 hr
95 Develop and release Highlight reports 4 0% 1 hr
96 Develop and release Highlight reports 5 0% 1 hr
97 Develop and release Highlight reports 6 0% 1 hr
98 Develop and release Highlight reports 7 0% 1 hr
99 Develop and release Highlight reports 8 0% 1 hr
100 Project Highlight reports 9 0% 1 day
101 Project Highlight reports 10 0% 1 day
Apr May Jun JulQtr 2, 2013 Qtr 3, 2013
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 3
Project: Infrastructure upgrade project
Date: Thu 23/05/13