Alpha p Harm

Embed Size (px)

Citation preview

  • 7/30/2019 Alpha p Harm

    1/3

    ID Task Name % Complete Duration Predecessors

    1 Alphapharm Project Planning 0% 54 days

    2 Initiate Stage 0% 2 days

    3 Conduct project kick off 0% 1 day

    4 Order services 0% 0 days

    5 Develop the project schedule 0% 1 day 3

    6 Initiate Stage complete 0% 0 days 5,4

    7

    8 Execute Stage 0% 54 days

    9 Network Solution 0% 54 days

    10 Network Design Stage 0% 5 days

    11 Conduct network design meeting 0% 1 day 3FS+1 day

    12 Produce the network diagram 0% 1 day 11

    13 Customer review and approval of ND 0% 3 days 12

    14 Plan the site priorities and staging 0% 1 day 12

    15 Design Stage complete 0% 0 days 14

    16

    17 60 Mica St Carole Pk 5M wireless upgrade 0% 24 days

    18 Customer provide installation authorisations 0% 5 days

    19 Provision the wireless link 0% 15 days 18

    20 Provision the network 0% 3 days 19

    21 Customer cutover activity 0% 1 day 20

    22 Completed wireless link - Service Ready 0% 0 days 21

    23 Cancel the Optus Broadlink access 0% 0 days 22

    24

    25

    26 32 Mica St Carole Pk 5M backup upgrade 0% 24 days

    27 Customer provide installation authorisations 0% 5 days

    28 Provision the wireless link 0% 15 days 18

    29 Provision the network 0% 3 days 19

    30 Customer cutover activity 0% 1 day 20

    31 Completed wireless link - Service Ready 0% 0 days 21

    32 Cancel the BDSL access 0% 0 days 31

    33

    34 Garnett St Carole Pk 20M new backup 0% 24 days

    35 Customer provide installation authorisations 0% 5 days

    36 Provision the wireless link 0% 15 days 35

    37 Provision the network 0% 3 days 36

    16/05

    17/05

    22/05

    18/06

    18/06

    18/06

    18/06

    Apr May Jun JulQtr 2, 2013 Qtr 3, 2013

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    Page 1

    Project: Infrastructure upgrade project

    Date: Thu 23/05/13

  • 7/30/2019 Alpha p Harm

    2/3

    ID Task Name % Complete Duration Predecessors

    38 Customer cutover activity 0% 1 day 37

    39 Completed wireless link - Service Ready 0% 0 days 38

    40

    41 Millers Point Internet Service 0% 29 days

    42 Upgrade Primary 0% 29 days

    43 Provision the 30M AAPT access 0% 25 days 4

    44 Provision the network 0% 3 days 43

    45 Cutover activity 0% 1 day 44

    46 Implemet Backup 0% 29 days

    47 Provision the 30M Telstra access 0% 25 days 4

    48 Provision the network 0% 3 days 47

    49 Cutover activity 0% 1 day 48

    50 Cancel Testra access 0% 0 days

    51 Cancel the 4M Telstra access 0% 0 days 45

    52

    53 Millers Point MPLS upgrade 0% 29 days

    54 Primary Service 0% 16 days

    55 Provision Q in Q to exisitng access 0% 15 days

    56 Cutover activity 0% 1 day 55

    57 Backup Service 0% 29 days

    58 Provision the 10M Optus access 0% 25 days

    59 Provision the network 0% 3 days 58

    60 Cutover activity 0% 1 day 59

    61 20M Wireless Service 0% 24 days

    62 Customer provide installation authorisations 0% 5 days

    63 Provision the wireless link 0% 15 days 62

    64 Provision the network 0% 3 days 63

    65 Customer cutover activity 0% 1 day 64

    66

    67 SIP implementation 0% 54 days

    68 Port validation activities(dependant on requirements) 0% 20 days

    69 Provision the SIP trunk 0% 5 days 60

    70 Customer SIP testing 0% 10 days 69

    71 Customer ready for porting 0% 0 days 70

    72 ISDN number porting 0% 10 days 71

    73

    74 Close Stage 0% 2 days

    18/06

    25/06

    25/06

    16/07

    Apr May Jun JulQtr 2, 2013 Qtr 3, 2013

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    Page 2

    Project: Infrastructure upgrade project

    Date: Thu 23/05/13

  • 7/30/2019 Alpha p Harm

    3/3

    ID Task Name % Complete Duration Predecessors

    77

    78 Manage Stage 0% 46 days

    79 Project Progress Meetings 0% 46 days

    80 Project Progress Meeting 1 0% 1 hr

    81 Project Progress Meeting 2 0% 1 hr

    82 Project Progress Meeting 3 0% 1 hr

    83 Project Progress Meeting 4 0% 1 hr

    84 Project Progress Meeting 5 0% 1 hr

    85 Project Progress Meeting 6 0% 1 hr

    86 Project Progress Meeting 7 0% 1 hr

    87 Project Progress Meeting 8 0% 1 hr

    88 Project Progress Meetings 9 0% 1 day

    89 Project Progress Meetings 10 0% 1 day

    90

    91 Project Highlight reports 0% 46 days

    92 Develop and release Highlight reports 1 0% 1 hr

    93 Develop and release Highlight reports 2 0% 1 hr

    94 Develop and release Highlight reports 3 0% 1 hr

    95 Develop and release Highlight reports 4 0% 1 hr

    96 Develop and release Highlight reports 5 0% 1 hr

    97 Develop and release Highlight reports 6 0% 1 hr

    98 Develop and release Highlight reports 7 0% 1 hr

    99 Develop and release Highlight reports 8 0% 1 hr

    100 Project Highlight reports 9 0% 1 day

    101 Project Highlight reports 10 0% 1 day

    Apr May Jun JulQtr 2, 2013 Qtr 3, 2013

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    Page 3

    Project: Infrastructure upgrade project

    Date: Thu 23/05/13