Alaska LNG Concept Information
Alaska LNG
Overview
October
December 3, 2013
Alaska LNG Concept Information Project Overview
Project Team • BP, ConocoPhillips, ExxonMobil and TransCanada are
working together to progress an Alaska LNG project: − 300+ people involved in project planning and design work − Multiple third-party contractors engaged, including
Alaskans − Leveraging Denali, APP, and related material ($700M past
work)
Project Description • Concept selection work to date:
− Gas treatment plant located on the North Slope − An 800-mile, 42-inch diameter pipeline − Up to 8 compression stations − At least 5 off-take points for in-state gas delivery − Liquefaction plant and marine export terminal located in
south-central region − Lead site is Nikiski
− Preliminary capital investment: $45-$65B
- 1 -
Alaska LNG Concept Information LNG Plant and Marine Terminal Site Selection
• Lead Site – After evaluating more than 20 locations, the Project Team has identified a primarily industrial area near Nikiski.
• The Team has performed considerable technical work for both the location of the plant as well as the viability of Nikiski for LNG tanker operations.
• A Nikiski LNG plant site takes into consideration a pipeline route that provides access to natural gas for: – Fairbanks – Mat-Su Valley – Anchorage – Kenai Peninsula
• Alaska LNG wants to be a good neighbor. • Our goal is to lessen impacts and enhance
benefits to the businesses and residents in the area.
Alaska LNG Plant Conceptual Layout
- 2 -
Alaska LNG Concept Information Land Access
• Access to land is part of project development. • Access to land allows further engineering and feasibility studies, including
environmental, geotechnical, soils, groundwater and other research as necessary to confirm the LNG plant and terminal site selection.
• The exact parcels that we want to access are confidential. We do not have a specific timetable for completing the process.
• We hope that we will be able to reach an arrangement with the landowners in the areas we are interested in accessing.
- 3 -
Mark Jennings
Alaska LNG Concept Information
Field Studies • 2013 Summer Field work completed September 2013:
– Cultural Resources: >6,500 acres – Hydrology / Lakes / Fisheries studied: 27 / 17 / 20 – Subsistence and Health Impact Assessments starting
this winter (2013/14) – 150 people involved in field studies (60% Alaskans)
• Alaska LNG is now working to answer key technical questions to reduce uncertainty and continue advancing the project.
• The multi-year field work effort is now underway. • We are working to complete the 2013 program and are
planning for the 2014 season. • The primary scope of field work is to analyze existing
environmental conditions along project footprint – Planning, logistics, and permitting to support
survey work
– Public and agency engagement to support survey work and ongoing project planning
Previous and Current Work Key project design accomplishments • Confirmed ability to integrate into existing
operations • Completed project design concept, announced
Feb 2013 • Finalized LNG Lead Site
- 4 -
Alaska LNG Concept Information Benefits for Alaskans
• A successful Alaska LNG project would provide a host of economic benefits to Alaskans including:
– State revenues – Short and long-term job opportunities – Business and industrial opportunities
• Commercializing North Slope natural gas through the Alaska LNG Project will provide Alaskans access to a cleaner burning and dependable energy source to supply ongoing in-state energy demand via five off-take points along the pipeline route.
• The off-take points would be decided following consultation with State officials and local utilities
- 5 -
Alaska LNG Concept Information Key Issues, Timing and Next Steps
Key Issues − “Mega-project” challenges (labor, resources, equipment, schedule, etc.) − Uncertainty related to permit timing and scope
Next steps − Completing field studies in preparation for regulatory submissions
− Winter Field Season 2013/14 − Summer Field Season 2014
− More detailed engineering and design work for an LNG plant, marine export terminal, LNG tanker fleet, a pipeline and a gas treatment plant
Project timing − Preliminary engineering and environmental studies within a 3-5 year timeframe (depending on
regulatory approvals) − After regulatory approvals are received and funding is secured, final engineering, design,
procurement and construction may be completed in 5-6 years
- 6 -
Alaska LNG Concept Information Contact Us
• If you have questions or concerns, please call our Alaska toll-free number
• We will respond to you and put your name and address in our stakeholder database, which will give you the option to automatically receive project updates
- 7 -
Mark Jennings
Alaska LNG
Kenai Peninsula Office 120 Trading Bay Road Suites 310, 320 Kenai, AK 99611
Toll-free number: 855-550-5445
Alaska LNG Concept Information
Additional Information
Alaska LNG
Alaska LNG – Integrated Team
Producing Fields Lead: BP
Pipelines Lead: APP
LNG Plant Lead: ConocoPhillips
ERL Team Lead: ExxonMobil
Commercial Team Lead: BP
Concept Team Lead: ExxonMobil
Management Committee
Technical Committee
Multimillion Dollar, Four-Company Effort – 125+ Employees, 100+ Contractors •Joint work commenced March 31, 2012 after completion of the Pt. Thomson Settlement / joint work agreements •Cooperative effort among the leading North Slope producers and a leading North American pipeline company •Identified potentially viable LNG project options to monetize ANS natural gas •Used company strengths, shared information / expertise; built upon past efforts, sought out new ideas
Integration Team Lead: ExxonMobil
Alaska LNG – Project Concept Description
Gas Treating •Located at North Slope or Southcentral LNG site •Remove CO2 and other gases and dispose / use •Footprint: 150 - 250 acres •Peak Workforce: 500 - 2,000 people •Required Steel: 250,000 - 300,000 tons •Among largest in world
Liquefaction Plant • Capacity: 15 – 18 million tonnes per annum (MTA)
3 trains (5-6 MTA / train) • Potential areas: 22 sites assessed in Cook Inlet, Prince
William Sound and other Southcentral sites • Footprint: 400 - 500 acres • Peak Workforce: 3,500 - 5,000 people • Required Steel: 100,000-150,000 tons
Storage / Loading • LNG Storage Tanks, Terminal • Dock; 1 - 2 Jetties • Design based on 15– 20 tankers • Peak Workforce: 1,000-1,500 people
Estimated Total Cost: $45 – $65+ Billion Peak Construction Workforce: 9,000 – 15,000 jobs Operations Workforce: ~1000 jobs in Alaska
Descriptions and costs are preliminary in nature and subject to change. Cost range excludes inflation.
Pipeline • Large diameter: 42”- 48” operating at >2,000 psi •Capacity: 3 - 3.5 billion cubic feet per day •Length: ~800 miles (similar to TAPS) •Peak Workforce: 3,500 - 5,000 people •Required Steel: 600,000 - 1,200,000 tons •State off-take: ~5 points, 300-350 million cubic feet per day, based on demand
Producing Fields •~35 TCF discovered North Slope resource •Additional exploration potential •Anchored by Prudhoe Bay and Pt. Thomson with ~20 years supply available
•Use of existing and new North Slope facilities •Confirmed range of gas blends from PBU/PTU can generate marketable LNG product
•Peak Workforce: 500 – 1,500 people
GO
LNG
Pro
ject
O
pera
tions
Execute: • Final engineering • Financing • Procurement • Fabricate / Logistics / Construct • Prepare for Operations
Complete Gov’t / Reg. Issues: • Secure remaining construction
/ operating permits • Stakeholder engagement Implement business structure & agreements
Commission / start-up
Alaska LNG – Work Plans / Key Decision Points
Evaluate: • Range of technically viable
options for major project components
• Business Structure • In-state gas / export LNG demand
Screen commercial viability
Viable Technical Option(s) Identified Government Support Permits / Land Use Achievable Potential Commercial Viability
Requirements to Take Next Step:
Progress: • Preliminary engineering to
refine concept • Business structure • Financing plan
Start individual gas / LNG sales / shipping efforts Assess commercial viability
Viable technical option Government Support Permits / Land Use Underway Potential Commercial Viability
Activ
ities
Complete: • Front-end engineering & design • Major contract preparation • Business structure • Financing arrangements
Solicit Interest of Others Advance Gov’t / Reg. Issues: • Key permit / land use approvals • Stakeholder engagement • Secure DOE Export License
Execute individual gas / LNG sales / shipping agreements Confirm commercial viability
Secure Permits / Land Use / Financing / Key Commercial Agreements
Confirm Commercial Viability Execute EPC contracts
Peak Staffing: ~300 400 - 500 500 – 1,500 9,000 – 15,000
Cost ($): Tens of Millions Hundreds of Millions Billions Tens of Billions
Est. Engineering / Technical Duration*: 12 - 18 Months 2 - 3 Years 5 - 6 Years
Concept Selection
Pre- FEED
FEED (Front-End
Engineering & Design)
EPC (Engineering,
Procurement & Construction)
Decision to Build the
Project Decision Decision
(Today)
PTU Settlement, Joint Work
Agreements
* NOTE: Duration of various phases may be extended by protracted resolution of fiscal terms, permitting and regulatory delays, legal challenges, changes in commodity market outlook, time to secure long-term LNG contracts, labor shortages, material & equipment availability, weather, etc.
GO GO GO
Solicit Interest of Others Establish Government Support and Advance Regulatory Issues:
• Competitive oil tax environment; predictable / durable LNG project fiscal terms; AGIA Issues
• Assure ability to secure regulatory approvals / permits / land use • Environmental activities / Technical data collection • Stakeholder engagement • File DOE Export License