Upload
sergioparma
View
228
Download
0
Embed Size (px)
Citation preview
8/3/2019 Aisc - Office Buildings
1/16
MEETING THE
CHALLENGES OF
THE 21ST CENTURY
S T E E L - F R A M E D F F I C E B U I L D I N G S
O
There's always a solution in steel!
stru
ctur
alsteel
8/3/2019 Aisc - Office Buildings
2/16
stru
cturalsteel
A B N A M R O B A N KChicago, IL
OWNER: ABN AMRO Bank of North America
PROGRAM MANAGER: Hines
ARCHITECT: DeStefano and Partners, LTD.
STRUCTURAL ENGINEER: Thornton Thomasetti Engineers
GENERAL CONTRACTOR: Turner Construction Co.
STEEL FABRICATOR: Zalk Josephs Fabricators, LLC.
STEEL ERECTOR: Area Erectors, Inc.
8/3/2019 Aisc - Office Buildings
3/16
Cost, Speed, Quality, and Marketability are important considerations thatdrive the decision owners and developers make for new office building construction. Who
isnt worried about budgets or schedules and if their new facility will meet their quality
expectations within budget? And who doesnt worry about how marketable the building will
be in order to attract and retain tenants that will ensure profits through the expected life of the
building?
The selection of the structural steel framing system is the first step in meeting those
considerations. And it has been the first step for countless office structures in the United States
dating back to 1885 when steel was used for the first time in the 10-story Home Insurance
Building located in Chicago, IL. Steel is the material of choice of project decision makers that
have learned steel-framed office buildings are unsurpassed in:
Cost-effective construction
Accelerated project schedules
Early occupancy
Reduced life-cycle costs
Future adaptability to changing tenant requirements
Meeting security, fire protection, blast and progressive collapse demands
Ease of integration with other building systems
Increased schedule control due to all-weather erection capabilities
Quality assurance due to offsite fabrication in controlled environments
Column-free space maximizing space usage and office layout flexibility
Enhanced flexibility and comfort to attract and retain potential tenants
Maximized resale value and minimized demolition costs
I N T R O D U C T I O N
8/3/2019 Aisc - Office Buildings
4/16
2
In addition, new emerging technologies and systems are increasing the positive impact that steel has on
projects today. Some of those innovations have been driven by the new imperatives of building design
and construction in the 21st century: the ability to withstand terrorist acts, higher standards for seismic
safety and fire safety at reasonable cost, increased need to layout flexibility, energy efficiency, and
sustainable design.
What follows is a journey across the country looking at nine examples of steel-framed offices, each one
illustrating one or more ways of meeting owners and developers demands for better facilities that are
faster to build and at the lowest total cost.
Congress Center: A Chicago, IL, mid-rise office where the developer saved over $500,000 byminimizing floor depth to reduce the cost of cladding and mechanical services and ended up with
over 33,000 sq ft of column-free space per floor, gaining a competitive advantage in the office market.
General Services Administration: A low-rise build-to-suit office in Atlanta, GA, whose fast-track design
and construction resists progressive collapse in the event of a terrorist attack and is easily adaptableto future changes.
New York State Department of Environmental Conservation: A built-to-suit mid-rise office in Albany,
NY, where the owner, foreseeing winter construction, chose steel, which aided in satisfying the rigid
environmental standards of LEED certification by the U.S. Green Building Council.
ADC Telecommunications: A low-rise build-to-suit office campus in Eden Prairie, MN, where spray-on
fire protection was in large part eliminated on the exposed structural steel to accomplish the owners
aesthetic requirements without compromising the highest standards of life safety and property
protection.
Bureau of Indian Affairs: A low-rise office in Albuquerque, NM, where weeks were cut out of the
design and construction schedule through the use of new software that allows movement of
information from design to detailing to automated fabrication electronically while still satisfying the
owners design requirements against progressive collapse from terrorist acts.
JPMorgan Chase: A San Francisco investment high-rise signature office where the developer saved
$1,250,000 in the overall cost of cladding and mechanical services by minimizing floor and ceiling
thickness. The office, which required large column-free areas, also had to meet stringent new seismic
requirements cost-effectively.
CNF Transportation, Inc.: A mid-rise build-to-suit office in Portland, OR, with column-free working
areas where the owner cut operating costs by 25-30% by integrating HVAC with the structural
system.
U.S. Navy Pacific Command Center: A military command center in Oahu, HI, where the owner was
able to get the project back in budget and on schedule with a unique and economical structural
system to resist earthquakes, hurricanes and progressive collapse from terrorist acts.
Summit Place: A constructive reuse where a vintage heavy manufacturing plant near Milwaukee,
WI, was converted into offices affording the developer a competitive advantage in the office market.
Virtually all the original steel structure was reused.
8/3/2019 Aisc - Office Buildings
5/16
OWNER: Development Resources, Inc.
ARCHITECT: OWP/P
STRUCTURAL ENGINEER: OWP/P Structures
MECHANICAL ENGINEER: Environmental Systems Design
GENERAL CONTRACTOR: Power Construction Company
STEEL ERECTOR: Gatwood Steel Erection
CHALLENGE:Provide a structure that accommodates
changing tenant needs.
SOLUTION 1:Take advantage of structural steel span
capabilities by eliminating interior columns located
between the core and exterior of the building.
The ability to economically achieve spans up to 46 ft
created an open floor area exceeding 33,000 sq ft
per floor. This appeals to a greater number of poten-
tial tenants who want maximum freedom for space
planning as well as comfort for their employees. And
advanced design methodologies are allowing longer
spans and maximizing comfort with the elimination of
perceptible vibrations.
SOLUTION 2:Take advantage of the ease of
modification inherent with a structural steel system.
Building owners and managers are always faced
with changing requirements and a compositesteel frame can easily be modified to satisfy exist-
ing or new tenant changing requirements such as
increased floor loads for storage and equipment,
new openings for mechanical equipment and verti-
cal shafts or floor-to-floor staircases. Within the four
years since its opening in 2001, Congress Center
has required several dozen structural modifications
in order to meet changing tenant requirements.
www.aisc.org/office_projects
CHALLENGE:Minimize construction costs.
SOLUTION 1:Integrate structural steel with
mechanical services to reduce floor-to-floor heights.
Structural and mechanical designers working closelytogether coordinated structural and mechanical
requirements so that shop-fabricated web penetra-
tions could be used for the passage of fire protection,
mechanical, electrical and plumbing systems within
the depth of the girders. This resulted in a savings of
at least 1 ft in floor depth while providing tenants 9-ft
ceiling heights. This drove down associated costs of
enclosure systems, partition and vertical building sys-
tems by more than $30,000 per foot or nearly half a
million dollars for the whole building.
SOLUTION 2:Maximize spans between structural floor
elements to reduce construction time.
A 51/4-in. composite metal floor deck increased
spacing of structural beams to 16 ft on-center. By
increasing the span of the composite floor system,
fewer structural beams were required which reduced
fabrication as well as erection time. The building was
completed quicker and a positive revenue stream was
generated earlier giving the developer a higher return
on investment.
Structural steel offers developer maximum cost savings and office layout flexibility
to gain a competitive advantage in the local office market.
Located in Chicagos West Loop, this new 16-story, 529,000-sq-ft office building was built to meet the demand
for new Class-A office space in the central business district. Because it was an investment property, the archi-
tects had to work to a limited budget while still creating a building that would be a worthy addition to an area of
the city enjoying rejuvenation.
C O N G R E S S C E N T E R
Ducts and cable
trays throughwebs for reducedfloor/ceiling depth
46-ft clear span:
core-to-perimeter
9-ft ceiling height
8/3/2019 Aisc - Office Buildings
6/16
G E N E R A L S E R V I C E S A D M I N I S T R A T I O N
4
In fact, even before design was finished, the GSA
issued extensive modifications that required signifi-
cant increases in floor loads and the addition of acolumn-free space for an auditorium. Principle bays
now required a span in excess of 45 ft. Structural steel
with a composite metal deck proved most economical
with the use of W21 beams spanning 46 ft 2 in. on 10-
ft centers and a composite deck comprised of a 3-in.
metal deck and 31/4 in. of lightweight concrete topping.
Girders spanned 30 ft between columns with some
spans, at the exterior bays, spanning 40 ft 10 in.
CHALLENGE:Meet a tight budget and schedule.
SOLUTION: Structural steels ease of design, construc-
tion speed and compatibility with other building sys-
tems helps project meet schedule and budget goals.The project team worked out an aggressive schedule
to design, construct, fit up and occupy the build-
ing within the time frame demanded by the GSA.
The team took advantage of sophisticated structural
design software that facilitated 3-D modeling of
changing design requirements and helped minimize
the time to incorporate design changes. In spite of the
mid-stream design changes, the structural steel and
composite metal deck system provided the developer
the only means to complete the project on time. It was
completed on time and $100,000 below budget!
CHALLENGE:Find an economical solution to prevent
progressive collapse.
SOLUTION:Rely on structural steels ductility to designa resilient and redundant structure.
The building was to be used exclusively for administra-
tive purposes and the perimeter was secure so the
design criterion required only that elimination of any
first-floor perimeter column would not cause even
a partial collapse. A structural steel solution was
both elegant and simple. The building was girdled
between the first and second floors with W33 x 118
beams spanning the 30-ft interior bays and 40-ft 10-in.
end bays. These are attached to the perimeter col-
umns with fully welded moment connections designed
for the full plastic moment of the beams. To handle
the scenario of a corner column being destroyed,a perimeter column was placed within 10 ft of the
corners to eliminate the potential for a cantilever in
excess of 40 ft.
CHALLENGE:Provide a structure that can be easily
modified to meet changing tenant requirements even
during the middle of the design.
SOLUTION:Use structural steel framing and composite
metal deck to meet changing tenant requirements.
The client foresaw the possibility of needing to make
future modifications to both the structure and deck.
Structural steel satisfies blast and progressive collapse criteria and offers owner
maximum ability to adapt to future changes.
This four-story 107,000-sq-ft Class-A office building located in Atlanta, GA, was developed and leased exclusive-
ly to the General Services Administration and occupied by the Center for Disease Control. The urgent need of
the GSA was a building that would easily accommodate future changes in use and layout at an aggressive rental
rate. Challenging the project even further, a blast-resistant/anti-progressive collapse design criterion was added
midway in the design process, due to the September 11 attack.
OWNER: General Services Administration
DEVELOPER: Highwood Properties
ARCHITECT: Cooper Carry, Inc.
STRUCTURAL ENGINEER: Uzun & Case Engineers
GENERAL CONTRACTOR: Brasfield & Gorrie
STEEL FABRICATOR: Stein Steel
STEEL ERECTOR: Composite Construction Services, Inc.
Heavy beams (W33 x 118) forminganti-blast girdle around perimeter
Fully welded moment connections
8/3/2019 Aisc - Office Buildings
7/16
N E W Y O R K S TAT E
D E P A R T M E N T O F E N V I R O N M E N T A L C O N S E R V A T I O N
CHALLENGE:Earn a LEED
Silver Rating from the U.S.
Green Building Council.
SOLUTION:Take advantage of the green features
of structural steel.The architect collaborated closely with the owner and
mechanical engineer to integrate many green features
into the design and construction of the building.
A LEED consultant was also brought on board to help
shepherd the project through the certification process
by making a list of sustainable features that would
contribute to the LEED credits required for certifica-
tion. The LEED consultants recommendation to use
structural steel contributed significantly and easily
toward three LEED credits, including: use of materials
with recycled content, local/regional use of materials
and the reduction of construction waste. First, all struc-tural steel produced in the United States contains a
minimum of 95 percent recycled content with an aver-
age of 65 percent of post-consumer recycled content.
Second, structural steel was fabricated and supplied
by a fabricator located less than one hour from the
project site, well within the 500-mile radius required
under LEED 2.0. Finally, scrap structural steel is too
valuable to be thrown into a landfill and virtually 100
percent is recycled into new steel products.
www.aisc.org/office_projects
CHALLENGE:Meet a fast-track delivery schedule.
SOLUTION:Capitalize on all-weather construction with
structural steel.
The construction of the structural frame is often on thecritical path of a project schedule. On this project it
was evident the structure would have to be construct-
ed during the winter months, increasing the poten-
tial for weather related delays. Structural steel was
selected to minimize this risk. In fact, the steel fabri-
cator expedited the steel delivery, started fabrication
early in October and steel erection proceeded swiftly
late November through completion of the structure in
mid-April. Structural steel was fabricated off-site in a
controlled environment by a skilled labor force unaf-
fected by changing weather conditions where quality
and tolerance achievement was assured resulting in
fewer field erection problems. The ability to be erect-
ed year-round also benefited the project schedule.
All-weather construction capabilities and sustainability advantages of structural
steel help owner meet tight construction schedule and obtain LEED
Silver Rating.
When considering its new headquarters, the New York State Department of Environmental Conservation in
Albany, NY, wanted it to be a model of environmental responsibility in design, construction and operation.
As such, this 13-story, 500,000-sq-ft office satisfies the sustainable design standards to achieve a LEED
(Leadership in Energy and Environmental Design) Silver Rating by the U.S. Green Building Council.
OWNER: Picotte Companies
LESSEE: NYS Department of Environmental Conservation
ARCHITECT: Woodward Connor Gillies & Seleman Architects
LEED CONSULTANT: Steven Winter and Associates
STRUCTURAL ENGINEER: Selnick Harwood Engineers
MECHANICAL ENGINEER: Quantum Engineering
GENERAL CONTRACTOR: Beltrone Construction
STEEL FABRICATOR/ERECTOR: Schenectady Steel, Inc.
8/3/2019 Aisc - Office Buildings
8/16
A D C T E L E C O M M U N I C AT I O N S
6
CHALLENGE:Eliminate passive fire protection on
building structure to help achieve owner demands for
an architectural statement.SOLUTION:Bring in a fire-engineering consultant
to develop alternatives to traditional fire protection
methods.
Under the Minnesota State Building Code at the time
(amended 1997 Uniform Building Code) the construc-
tion type would have dictated passive fire protection
on the exposed structural framing and composite floor
assemblies. A fire-engineering consultant was brought
in to conduct a performance-based fire protection
analysis. Life safety, property protection and continu-
ity of operation goals were established and translated
into performance criteria. The consultant evaluated
various fire protection design alternatives and ulti-mately proposed an overall system that included
an enhanced quick response sprinkler system that
washes the primary framing, a total coverage smoke
detection and control system as well as a fire alarm
system. The proposed systems eliminated the need for
fire separation walls between buildings and spray-on
fire protection on approximately 80% of the structure.
While the original intent for eliminating the spray-on
fire-proofing was for aesthetics, adding spray-on pro-
tection could have meant as much as $500,000 to the
owner.
Fire-engineering and early steel fabricator involvement help owner make architectural
statement with architecturally exposed structural steel at an economical cost.
This world headquarters for a high-tech telecommunications company provides 500,000 sq ft of space on a 90-
acre campus in Eden Prairie, MN. The three-story complex is comprised of buildings arranged in an irregular
pattern, creating diversion and interest. The owner wanted to expose the steel structure, both inside and out, as
a reflection of the high-tech nature of the companys work. The exposed structure thus is the major architectural
statement of the complex.
OWNER: ADC Telecommunications
ARCHITECT/ENGINEER: Hammel Green & Abrahamson
FIRE ENGINEER: MountainStar Group
GENERAL CONTRACTOR: Kraus-Anderson Construction Co.
STEEL FABRICATOR: LeJeune Steel Co.
STEEL ERECTOR: Amerect, Inc.
Sprinkler coverage of space
Sprinkler washing of primary framing
CHALLENGE:Make maximum use of architecturally
exposed structural steel while avoiding
unnecessary costs.SOLUTION:Bring a steel fabricator on board early and
integrate the fabricator with the design team during
the design phase of the project.
Getting a qualified steel fabricator on board during the
early phases of the design and integrating him with
the design team always results in a more economical
structure. ADC Telecommunications proved to be no
exception. A steel fabricator was brought on board at
the beginning of the design process to work closely
with the architect and engineer. Fabricator integration
into the design team helped to keep the visions of the
designers more in line with fabrication and erection
practicalities resulting in many thousands of dollarssaved for the owner. For example, the fabricator had
the time to manufacture and submit models, to clearly
show that for some 700 trusses (14 ft in the air) it was
not necessary to grind welds for appearance sake and
that the structural strength of the welds was adequate.
Further, they were able to show that expensive welded
connections could be replaced with standard bolted
truss-to-column connections and still meet the high
aesthetic standards set by the architect. Finally, the
fabricator worked with the structural engineer on vari-
ous connections and other details to ensure more
economical fabrication and erection costs while still
achieving structural requirements.
8/3/2019 Aisc - Office Buildings
9/16
Continuous beamfor support of floors
Continuous beamfor support of floors
Break awaycolumn for blast
B U R E A U O F I N D I A N A F F A I R S
CHALLENGE:Provide a facility that would resist
blast and progressive collapse.
SOLUTION:Capitalize on steels ductility and design a
redundant structure.
Structural steel with its superior ductility, strength andability to accommodate blast load induced deforma-
tion reversals proved to meet all owner design expec-
tations. In addition, steels high strength-to-weight
ratio provided the added bonus of a lighter more eco-
nomical foundation.
The owner had two specific security requirements.
First, any perimeter column over the three floors could
be removed and allow the collapse of a single bay up
through the three floors. However, horizontal progres-
sion was permitted. The structural engineer oversized
the connections on the inboard side of the interior col-
umns so if the beam in the exterior bay pulled away,the interior would remain intact. Second, if any ground
floor column were removed in the lobby area, the floor
and structure above would remain intact. Using elas-
tic analysis the engineers applied a load factor taking
into account impact loads from the reversal of the
floor above after the blast. Beam-to-column moment
connections were developed to the full capacity of
the beams.
www.aisc.org/office_projects
CHALLENGE:Meet a fast-track schedule.
SOLUTION:Work with a steel specialty contractor that
assumes total responsibility for the structural steel
scope and uses new interoperable software.
The design-build contractor worked closely with asteel specialty contractor that assumed total respon-
sibility for the scope of the structural steel package.
The steel team, including a structural engineer, detail-
er, steel fabricator and erector under its umbrella,
worked closely together to shave two months from
the overall project schedule. Helping to drive this
significant schedule reduction was the use of interop-
erable design, detailing and fabrication software that
facilitated seamless transfer of a 3-D structural model
into detailing software and ultimately into automated
CNC fabrication equipment. Use of the software pro-
vided the general contractor with more timely budgets
and schedule information and ultimately cut the time
required to convert the final design into fabricated
components.
Steel specialty contractor, using new interoperable software, eliminates two months
from the construction schedule to help owner occupy building sooner.
The new regional headquarters for the Bureau of Indian Affairs (BIA) is a three-story 140,000-sq-ft building
located in Albuquerque, NM. The owner had expiring leases in diverse locations and desired to consolidate their
activities in a new office as quickly as possible and within strict budgetary limitations.
OWNER: Bureau of Indian Affairs
DESIGN-BUILD CONTRACTOR: OPUS West Construction Corp.
ARCHITECT: DCSW Architects, Inc.
STEEL TEAM
STRUCTURAL ENGINEER: Chaves-Grieves Consulting Engineers. Inc.
STEEL FABRICATOR/ERECTOR: AmFab, Incorporated
8/3/2019 Aisc - Office Buildings
10/16
J P M O R G A N C H A S E & C O .
8
CHALLENGE:Satisfy the heightened California
seismic requirements.
SOLUTION:Use a proven and redundant system
with reduced beam section moment connections.
In order to resist Zone 4 seismic forces, a lateral loadresisting system was provided in both directions. Along
the short direction, two 3-bay frames consisting of
33-in.-deep ductile outrigger beams with moment
connections to interior and exterior columns and four
braced frames between the core columns were pro-
vided. In the long direction, two 3-bay ductile moment
frames along exterior sides and two braced frames
along core walls were provided. All beam-to-column
moment connections used the reduced beam section
or dog-bone, which had been tested and pre-qualified
for the maximum beam size used.
CHALLENGE:Provide a maximum of column-free spacefor layout flexibility.
SOLUTION:Use sloping columns and composite steel
floor system.The developer wanted to be able to
offer tenants complete freedom for space planning.
By sloping the columns to make up for the setbacks
in the exterior walls the lateral load resisting system
could be accommodated within the perimeter framing.
Furthermore, this avoided the interference of transfer
girders. That and the floor system of a 51/4-in. compos-
ite slab on metal deck spanning 10 ft between com-
posite steel beams, which in turn span 43 ft, mean
that there are no columns between the office core andthe exterior walls.
CHALLENGE:Keep floor depth to a minimum as a way
of reducing cost.
SOLUTION:Notch the floor beams.
The developer was looking for ways to control
costs. Close coordination between the structural and
mechanical designers led to notching the 33-in.-deep
outrigger beams near mid-span for the passage of
main ducts. This reduced the floor-to-floor height by
more than a foot. When considering the cost of curtain
wall, structural steel, vertical shafts and mechanical
services, each vertical foot was worth approximately
$45,000 or $1,250,000 net savings for the whole proj-
ect.
CHALLENGE:Meet unique structural challenges posed
by the architecture.
SOLUTION:Utilize sloping exterior columns to create
the building setbacks as desired.
The building of rectangular shape, has two setbacks
on long sides one at level 8 and another at level
28. The normal way of supporting setback columns
on transfer girders is not desirable in high seismic
areas. This challenge was met by sloping the col-
umns to make up for the offsets. These columns
result in horizontal elements at levels 6, 8, 27 and 28.
These beams are connected to the columns with pins
thereby eliminating any uncertainty of behavior at the
beam-to-column joints. The sloping columns at the
two outrigger frames are of box shape common to
frames in both directions.
Structural steel lowers floor-to-floor heights saving developer $1,250,000.
Built by a prominent developer, designed by a world-renown architect and located in the heart of San Francisco
this 31-story Class-A building houses the West Coast headquarters of JPMorgan Chase & Co. Its almost 670,000
sq ft include two levels of underground parking and are complemented by a large ground level plaza and urban
park. The design is modern and complements the skyline with classical elegance. The exterior wall design is a
delicately proportioned tower of glass with a lush green aluminum frame.
OWNER: JPMorgan Chase & Co.
DEVELOPER: Hines
ARCHITECT OF RECORD: Cesar Pelli and Associates
PRODUCTION ARCHITECT: Kendall-Heaton Associates
STRUCTURAL ENGINEER: CBM Engineers
GENERAL CONTRACTOR: Turner Construction
STEEL FABRICATOR/ERECTOR: Strocal, Inc.
Sloped columns avoidingtransfer girders/trusses
Pre-approved dog-bonehigh seismic section
Notched and reinforcedbeams for reducedfloor-to-floor height
8/3/2019 Aisc - Office Buildings
11/16
C N F T R A N S P O R T AT I O N , I N C .
floor heights were reduced as much as 18 in. due to
elimination of the traditional HVAC plenum that typi-
cally runs below the beams. With the more traditional
approaches, the additional material cost of steel col-umns, masonry, glazing and vertical shafts could eas-
ily have added $200,000 to the cost of construction.
An additional savings was realized due to the unique
mechanical design that resulted in less expensive
equipment as well as the minimization of horizontal
ductwork.
CHALLENGE:Minimize cost of future changes in office
layout.
SOLUTION:Use structural steel framing with a raised
access floor.
As work teams change, and departments grow and
shrink, the under-floor system minimizes the disruptionand cost of demolition and construction to move wiring
and cabling. In addition, the steel structure can easily
be modified to accommodate changes in floor loads,
and the addition of floor openings among other things.
The unique cellular beam design, with web openings
running along the length will facilitate ease of installing
new MEP systems as needed in the future.
www.aisc.org/office_projects
CHALLENGE:Create an office that reduces (energy)
operating costs.
SOLUTION:Integrate structural and mechanical
systems for maximum efficiency.Close cooperation between the structural engineer,
mechanical engineer and the steel contractor led to
a unique mechanical system that took advantage of
the steel structure itself. A raised access floor act-
ing as both a space for power, voice and data whips
and under-floor air path was combined with a cellular
beam structure/ceiling assembly that created a return
air plenum. The web openings in the cellular beams
allowed for the free flow of used air to ceiling-mount-
ed water-source heat pumps. This mechanical/struc-
tural integration in combination with a southern build-
ing orientation and high efficiency glazing reduced
energy consumption by 30 percent less than required
by the State of Oregon Energy Code or approximately
$64,000 in savings per year.
CHALLENGE:Minimize construction costs.
SOLUTION:Use cellular beams to reduce floor-to-floor
heights to cut cladding and vertical MEP costs.
Use of cellular beams allowed for economical long
spans as well as facilitated free airflow and the pas-
sage of miscellaneous other mechanicals such as
sprinkler pipes through the web openings that ran
continuously along the member lengths. Floor-to-
Innovative integration of structural and HVAC systems contributes to approximately
$64,000 in annual energy savings as well as over $200,000 during construction.
The 250,000-sq-ft center is a five-story headquarters of an international transportation and logistics conglomer-
ate located in Portland, OR. As the world headquarters and nerve center, the facility is open 24/7 and back-up
systems are designed to allow operations to continue even under a loss of city or first phase back-up power. The
progressive and image-conscious owner wanted a facility that was functional yet environmentally sensitive.
Raised access floor
Space for under-floorair path
Cellular beams allow-ing for mechanical passthroughs and easy
circulation of air
Cellular beams clear spancore to perimeter
OWNER: CNF Transportation
ARCHITECT: GBD Architects
STRUCTURAL ENGINEER: KPFF Engineers
MECHANICAL ENGINEER: Glumac International
GENERAL CONTRACTOR: Hoffman Construction
STEEL CONTRACTOR: R.F. Stearns, Inc.
8/3/2019 Aisc - Office Buildings
12/16
U. S. N A V Y PA C I F I C C O M M A N D C E N T E R
10
CHALLENGE:Further reduce cost while satisfying addi-
tional Department of Defenses blast and
progressive collapse requirements.
SOLUTION:Use SidePlateTM
connection technology
to reduce structure and foundation costs, resist windand seismic loads and prevent progressive collapse.
The team with the structural steel proposal went back
to the drawing boards. The AT/FP progressive col-
lapse criteria, most simply stated, specified that any
single column in any location could be removed
and the surrounding structure had to remain intact.
To meet new requirements, a novel and cost-effec-
tive type of connection was proposed for the Pacific
Command Center. An innovative moment connection,
by SidePlateTM
Systems, Incorporated, strategically
placed throughout the structure, provided an all-steel
system with enhanced redundancy and ductility that
exceeded wind and seismic requirement and met
all the Navys security requirements as well. The
proposed system cut nearly $4 million dollars off the
steel package and resulted in budget and schedule
requirements being achieved.
CHALLENGE:Bring a critical project back into
budget and schedule.
SOLUTION:Use design-build project delivery with struc-
tural steel.
The U.S. Navy, in order to get a new facility designedand built as quickly as possible, issued a Request
for Proposal (RFP) from several design-build teams.
Working with an architect, they issued bridging docu-
ments that included a mix of cast-in-place and pre-
cast concrete with a pre-stressed concrete floor slab.
Teams could submit other solutions as long as they
met the Navys performance criteria including a blast-
resistant faade. Teams were allowed three months to
respond.
Structural steel is inherently more ductile than con-
crete and that material property can be used to
advantage in resisting blast loadings. Designing duc-tility into the structural frame can give it a significant
advantage in handling the load reversals that are
characteristic of a bomb blast. In addition, a structural
frame is lighter which saves foundation costs and is
very cost-effective in meeting seismic design provi-
sions.
One of the design-build teams took advantage of this
and proposed a structural steel system that saved
several million dollars over the concrete design but
fell short of meeting budget goal. At this point, the
U.S. Navy added Anti-terrorism/Force Protection (AT/
FP) blast and progressive collapse requirements andasked for revised proposals.
Design-build and unique steel connection system eliminates over $4,500,000
in costs and meets stringent design criteria for earthquake, wind, blast and
progressive collapse.
This six-story 320,000-sq-ft building, located in Oahu, HI, is the headquarters for the U.S. Navy Pacific
Command. As originally designed in concrete, the project was significantly over budget.
OWNER: Department of the Navy
BRIDGING ARCHITECT: Wimberly Allison Tong and Goo
DESIGN-BUILD TEAM
DESIGN-BUILD CONTRACTOR: Dick Pacific Construction Co.
ARCHITECT/ENGINEER OF RECORD: Atkins/Benham Group
ASSOC. STRUCTURAL ENGINEER: Baldridge & Associates Structural Engineering,
BLAST CONSULTANT: Weidlinger AssociatesSTEEL FABRICATOR: Brooklyn Iron Works, Inc.
STEEL ERECTOR: Swanson Steel Company, Inc.
SidePlateTM
connection
8/3/2019 Aisc - Office Buildings
13/16
S U M M I T P L A C E
In the open high bays up to three additional floors
were inserted. These bays formerly contained 300-ton
capacity bridge cranes. The crane rails were removed
and sold and the remaining crane beams were relo-
cated onto new haunches to support new insert
floors. While structural steel can be easily reinforced
to handle higher loads, office loads were so much
lower than the original industrial load requirements
that the structure did not have to be reinforced in any
way. To accommodate new mechanical ductwork,
web openings in existing girders were field fabricated
and reinforced. Existing roof framing was left exposed
as a clear expression of the buildings bones.
Existing skylights were also repaired and upgradedto provide lots of natural light and increase office pro-
ductivity.
CHALLENGE:Create a dramatic modern gateway
to the existing buildings.
SOLUTION:Add a four-story addition to the front
of the manufacturing buildings.
The addition and its atrium comprise 44,000 sq ft of
Class-A space. This created a grand and modern
entrance and served as a transition to the remodeled
industrial buildings behind.
www.aisc.org/office_projects
CHALLENGE:Convert three abandoned manufacturing
buildings into modern offices.
SOLUTION:Rely on the adaptability of the steel struc-
ture to reuse it completely.
The reuse of the existing buildings was less costly
than building new on a green field site. Doing so
benefits the environment by eliminating resources
required to tear down the building and transport the
non-steel material to a scrap yard or to produce and
transport new material to the job site. Furthermore,
one avoids the waste of abandoning an old site as
well as the energy and materials required to develop
a new site.
Working closely with the architect and structural
engineer, the developer looked at the palette of avail-
able features; solid brick walls, ceiling heights from
9 ft to over 26 ft, up to 17-ft-high windows, 500-ft-long
skylights, up to 83,000-sq-ft floor plates combined
with large column-free spaces and exposed structural
framing. Combining these features with the addition of
new windows, electrical power, modern HVAC, eleva-
tors and escalators readily brought the project up to
modern day standards.
Structural steel frames in three 70 year-old industrial buildings form the backbone
of a cost-effective conversion into an office complex with Class-A amenities.
The creation of a company over 100 years ago gave rise to the town of West Allis near Milwaukee, WI that
became a center for heavy manufacturing in Milwaukee. The demise of the company, Allis-Chalmers, in the
late 1980s meant the loss of over 15,000 jobs and the shuttering of nearly two million sq ft of historic industrial
buildings. Slightly more than half of the floor area was demolished (with many materials being land-filled and
steel being recycled into other steel products) leaving approximately 900,000 sq ft standing. In 2002 a former
employee turned developer decided there might be new life for those old bones that could spark a renaissance
of West Allis as a newly invigorated community.
DEVELOPER: Whitnall Summit, LLC
ARCHITECT: Renner Architects
STRUCTURAL ENGINEER: SRI Design
GENERAL CONTRACTOR: Selzer-Ornst
STEEL FABRICATOR: Ace Iron & Steel Corp.
STEEL ERECTOR: Dannys Construction Company, Inc.
STEEL FABRICATOR/ERECTOR: Construction Supply & Erection, Inc.
8/3/2019 Aisc - Office Buildings
14/16
12
The demands of the 21st century present new challenges to every office building owner, developer,
designer and construction professional. Challenges demand ingenuity, creativity and innovative solu-
tions. This brochure introduced you to many of those 21st century challenges and how some of them
were addressed through innovative uses of structural steel. In doing so, office structures were built more
economically and quickly while still maintaining quality and future flexibility to ensure profitability.
Since the beginning of modern steel construction in the 1880s structural steel has grown to be the
material of choice in office construction. Not only are the benefits of Cost, Speed, Qualityand Marketability available to every owner, but new and innovative approaches to the design chal-lenges of the 21st century abound with steel.
The possibilities for economical and technically sound solutions in steel are many. And the good news is
there is an easy way to find them. The AISC Steel Solutions Center, staffed with engineers experienced
in all phases and types of construction, is available to assist you to determine what the best structural
system is, how much will it cost and how long will it take to build. This assistance is provided for you free
of cost for all types of buildings including: offices, parking structures, hospitals, apartments, as well as
hotels. The Steel Solutions Center is there to make structural steel easier for you to use so do not hesi-
tate to call for any issue related to structural steel including: material specifications, coatings, fire protec-
tion, vibration, seismic design, blast-resistant design, connections, or construction feasibility. If you are a
designer, there are even free tools available to make your job easier and better.
Help is but a few keystrokes or a short phone call away at the AISC Steel Solutions Center:
1-866-ASK-AISC (866-275-2472)
or
Congress CenterPage 3
8/3/2019 Aisc - Office Buildings
15/16
stru
ctur
alste
el
JPMorgan Chase & Co.
Page 8
Summit Place
Page 11
8/3/2019 Aisc - Office Buildings
16/16
There's always a solution in steel!
AISC Marketing, LLC.One East Wacker Drive, Suite 700Chicago, Illinois 60601-1802
866.ASK.AISC www.aisc.org
Interested in knowing more about why a structural steel frame is the
best option for your next office building?
Please visit our web site www.aisc.org/office_projects for a
detailed look at the projects and topics highlighted in this brochure.
You are also invited to contact the AISC Steel Solutions Center at
866.ASK.AISC or [email protected] to discuss how these
solutions can be applied to capture the benefits of structural steel on
your next project.
Item F044-06(2/05:15M:ADV)