Upload
ibrahim
View
217
Download
0
Embed Size (px)
Citation preview
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
1/16
AHS MRW00 DAM-MS101
COMMENTS :
Sign.N.
Sign.N.
Sign.N.
C Sign.N.G. FOUCAULT C. DELAGE J. BINDELE 07 October
2004
OPTION 1 : 90.DAM.001.AC ADDITIONAL DOORUPDATING SUB-CONTRACTOR DESIGNATION
PREL
BSign.N. G. FOUCAULT C. DELAGE J. BINDELE
30 September 2004
UPDATING OF SCOPE OF SERVICES PREL
ASign.N. G. FOUCAULT C. DELAGE J. BINDELE
20 August2004
FIRST ISSUE PREL
R E V
ETABLI
ESTABLISHED
VERIFIECHECKED
APPROUVE APPROVED
DATE MODIFICATIONS STAT
Approved Approved as noted Returned for correction For information
Date : ………………………….. Signature : …………………………….
LAHMEYER INTERNATIONAL
GOVERNMENT OF THE REPUBLIC OF THE SUDANMINISTRY OF IRRIGATION AND WATER RESOURCES
MEROWE DAM PROJECT IMPLEMENTATION UNIT
MEROWE DAM PROJECT
10 x 140MVACONTRACTS 3A, 3B, 3C, 3E
ENGINEER: SUB-CONTRACTOR:
TECHNICAL SPECIFICATION
ELEVATORS
SCALE1/1
Sub-contractor :
M1144-A40182 REV
C SH/SHEND
1/16
N of SH
16
INTERNAL USE
Ce document propriété de ALSTOM ne doit pas être utilisé, copié ou communiqué à des tiers sans son autorisation
This document is the exclusive property of ALSTOM and shall not be used, copied or communicated to third parties without their prior authorization
Power EnvironmentHydro
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
2/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 2/16
TABLE DES MODIFICATIONS / MODIFICATIONS TABLE
REVETABLI
ESTABLISHED
VERIFIE
CHECKED
APPROUVE
APPROVED DATE MODIFICATIONS STAT.
A G. FOUCAULT C. DELAGE J. BINDELE20
August2004
FIRST ISSUE PRE
B G. FOUCAULT C. DELAGE J. BINDELE30
SeptembUPDATING OF SCOPE OF SERVICES PRE
C G. FOUCAULT C. DELAGE J. BINDELE07 OPTION 1 : 90.DAM.001.AC ADDITIONAL DOOR
UPDATING SUB-CONTRACTOR DESIGNATIONPRE
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
3/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 3/16
TABLE OF CONTENTS
TABLE OF CONTENTS ...................................................................................................................................................3
1 INTRODUCTION..................................................................................................................................................................4
2 REFERENCES DOCUMENTS............................................................................................................................................4
3 FUNCTIONAL REQUIRMENT..........................................................................................................................................5
4 TECHNICAL REQUIRMENT.............................................................................................................................................6
4.1 GENERAL TECHNICAL CONDITIONS .......................................................... ........................................................... 6 4.1.1 Environment conditions ...................................................... ............................................................. ...........................6 4.1.2 Electrical network conditions ........................................................ ............................................................ .................6 4.1.3 Country’s and international standards.......................................................................................................................6
4.2 DESIGN CRITERIA.......................................................................................................................................................7 4.2.1 Elevator standard ............................................................ ...................................................... .....................................7 4.2.2 Design, material and workmanship general requirement................................... ....................................................... 7 4.2.3 Safety...........................................................................................................................................................................7 4.2.4 Civil work tolerance....................................................................................................................................................7 4.2.5 Embedded parts minimum thickness ....................................................... ............................................................. .......7 4.2.6 Earthing ................................................... ....................................................... ............................................................ 8 4.2.7 Electrical enclosure ........................................................ ................................................................. ...........................8 4.2.8 Cubicle and electrical components ....................................................... ..................................................... .................8
4.2.9 Motors.................................................... ............................................................ ......................................................... 8 4.2.10 Fixed access ladder .................................................. ........................................................ ......................................9 4.2.11 Identification plate...................................................... ................................................................. ...........................9 4.2.12 Corrosion protection ..................................................... .............................................................. ...........................9 4.2.13 Accessories .......................................................... .............................................................. ...................................10
5 SCOPE OF SUPPLY ............................................................. ........................................................... ...................................11
5.1 CONSTRUCTION..............................................................................................................................................................11 5.1.1 Hoisting gear consisting of ................................................ .............................................................. .........................12 5.1.2 Cabin of elevator consisting of :...............................................................................................................................12 5.1.3 Elevator shaft consisting of......... ............................................................ ......................................................... .........12 5.1.4 Entrance for elevator ................................................................. ..................................................... ..........................12 5.1.5 Control and monitoring of elevator .......................................... .............................................. ..................................12
5.1.6 Float switches ............................................................. ........................................................... ...................................13 5.2 SPECIFIC WARRANTIES OF EQUIPMENTS ............................................................................. .............................13 5.3 PENALTIES FOR SPECIFIC WARRANTIES ................................................... ......................................................... 13
6 DEFINITION OF TECHNICAL SERVICES...................................................................................................................14
6.1 TECHNICAL DESIGN EXECUTION.........................................................................................................................14 6.2 LIST OF TECHNICAL DOCUMENTS TO BE ISSUED BY THE SUB-CONTRACTOR ..........................................14 6.3 TECHNICAL PROGRESS REPORT...........................................................................................................................15 6.4 TECHNICAL LABELLING.........................................................................................................................................16
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
4/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 4/16
1 INTRODUCTION
These technical specification defines the applicable conditions for MEROWE project :- Final customer : MDPIU (MEROWE Dam Project Implementation Unit)- Country : REPUBLIC OF THE SUDAN- Site : MEROWE
These specification is applicable for the supply of :
PASSENGERS AND FREIGHT ELEVATORS
2 REFERENCES DOCUMENTS
The General Painting Specification INS-MRW-00-WOG-MS-102The General Technical Specification AHS-MRW-00-WIG-MS-100
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
5/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 5/16
3 FUNCTIONAL REQUIRMENT
ITEM 30.DAM.001.AC 70.DAM.001.AC 90.DAM.001.AC 90.DAM.002.AC
Contractual designation Freight elevator
for non-overflowconcrete dam
Passenger elevator
for GIS building
Freight elevator for
service building
Passenger
elevator forservice building
Type Freight Passenger Freight Passenger
Lifting capacity 2 000 kg 630 kg 2 000 kg 630 kg
Hoisting speed 0.5 m/s 1.0 m/s 0.5 m/s 1.0m/s
Number of access 5 5 11 11
Number of cabin door 1 1 2
(OPTION 1)
1
Height of elevator entrance 2.20 2.10 2.20 2.10
Height of elevator cabin 2.20 2.10 2.20 2.10
Section of elevator cabin 2.0 x 2.5 1.1 x 1.4 2.0 x 2.5 1.1 x 1.4
Level of motor room 306.5 292.0 283.7 283.7Level of floor access 238.0 260.00 241.5 241.5
260.0 276.20 247.2 247.2
272.0 279.50 253.8 253.8
299.4 282.80 257.10 257.10
303.0 286.10 260.40(OPTION 1)
260.40
263.70 263.70
267.00 267.00
270.30 270.30
273.6 273.6
276.9 276.9
280.3 280.3
Civil work dimension
Shaft width 3 370 1 950 3 370 1 950
Shaft length 3 250 2 100 3 000 2 100
Shaft pit height 2 200 1 500 2 200 1 500
Access door width 3 200 1 600 3 200 1 600
Access door height 2 600 2 315 2 600 2 315
Electric hoist load (mini) 1 000 daN 500 daN 1 000 daN 500 daN
IMPORTANT REMARK : The final levels shall be confirmed by ALSTOM General Arrangement and Civil-Work drawings during detailed design.
OPTION 1 : The access level at 260.4 shall be defined with two side access. This should be quoted separatelyas an option.
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
6/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 6/16
4 TECHNICAL REQUIRMENT
4.1 GENERAL TECHNICAL CONDITIONS
4.1.1 Environment conditions
The electrical and control equipment will be designed according to the following conditions:- Altitude ....................................................................................... 260m above sea level
Ambient site temperature (and relative humidity):- Minimum indoor.......................................................................... 4 °C- Maximum indoor ......................................................................... 35 °C- Design temperature...................................................................... 48 °C- Relative humidity (average per month) ...................................... 29,1 % (at 20 °C)
Earthquake withstand ability :
- Horizontal acceleration ............................................................... > 0,2 g
- Vertical acceleration ................................................................... > 0,1 g
- Safety factor ................................................................................ ≥ 2,0
Equipment installed in power plant to be capable of withstanding an ambient temperature of+ 48°C without damage, under normal conditions of operation.
4.1.2 Electrical network conditions
AC Auxiliary Supply for motors- Rated Voltage : 400/230V- Distribution type : 3 phases, 4 wires- Voltage variations at consumers terminals : +10% -15% (-20% during motors starting)- Frequency : 50Hz- Frequency variations : Normal : ± 0.5Hz – Transient : -3Hz, +2Hz
- Neutral System : TNS
AC Auxiliary supply for lighting and space heaters- Rated Voltage : 230V- Distribution type : 1 ph + N- Voltage variations at consumers terminals : +10% -15%- Frequency : 50Hz
- Frequency variations : Normal : ± 0.5Hz – Transient : -3Hz, +2Hz- Neutral System : TNS
DC Auxiliary supply for control and measurements
- Rated Voltage : 220V
- Voltage variations at consumers terminals : +10% -15%
- Earthling System : Both poles isolated from earth
4.1.3 Country’s and international standards
Certain specification issued by national or other widely recognised bodies are referred to in thiscontract. Such specification shall be defined and referred to hereinafter as standard specificationsand shall be the latest editions at the time of issue of the order. The following standards shall beused:EN European normIEC International Electro technical commissionANSI American National standard institute
FEM Federation Europeenne de la Manutention, FranceBS British standard
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
7/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 7/16
4.2 DESIGN CRITERIA
4.2.1 Elevator standard
Elevators built according EN81
Dynamic load : 110% of rated load
Static test load : 150% of rated load
4.2.2 Design, material and workmanship general requirement
All parts of the equipment shall be designed and manufactured in the best and fully suitable mannerwith materials best suited to their purpose and in accordance with recognized standard to good practice and latest technology.
Wherever practicable, the design and shaping of important component shall be such as to facilitatefull non-destructive examination.
In the design, due regard shall be paid to the accessibility of parts which require maintenance. The
lubrication points shall be clearly marked and arranged in an orderly and clearly visible manner.Tooth gears in the vicinity of accessible places shall be enclosed. All screws, bolts and nuts shall belocked so that it is impossible for them to become loose in operation.
The parts shall be usable without adjustment. The brakes shall be dimensioned to hold fast the test
load.
The sub-contractor is required to pay attention to the reduction of sound, noise and vibration and isrequired to provide and install all necessary sound and vibration-reducing materials. Any noises
made by the cabin in its normal passage through the hoist ways shall be eliminated as far as possible.
Sheaves and wheels for load ropes shall have a pitch diameter not less than 40 times the diameter ofthe rope used therewith.
The cabin speed downwards with rated load under normal operating conditions with power supplyon or off shall not exceed 125% of rated speed.
The elevator shall be equipped for manual operation in case of motor or power failure.
4.2.3 Safety
The design of the equipment shall provide all reasonable precautions for the security of the personnel engaged in operation and maintenance and shall meet the relevant safety regulations andstandards specified in employer’s requirements, General technical specification.
All live, moving and rotating parts shall be adequately secured in order to avoid danger to theoperating staff.
4.2.4 Civil work tolerance
IMPORTANT REMARK : To meet the project deadline, a preliminary study has already defined the bottom of the elevator shafts as here above. The sub-contractor will confirm his agreement and willsupply all equipments and fittings accessories accordingly.
For building measures as well as for placing first-stage concrete anchors, an accuracy of +-30mm
shall be taken into account
4.2.5 Embedded parts minimum thickness
Minimum thickness of steel, without regard to stress, shall be as follows unless otherwise specified :
- Gate skin plate : 15mm- Plate thickness of any structural part except webs of rolled shapes : 10mm
- Embedded metal with exposed surfaces : 12mm
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
8/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 8/16
- Completely embedded metal : 10mm- Corrosion resistant steel cladding after final machining : 6mm- Diameter of bolts or screws on gate structures : 16mm- Diameter of adjusting bolt between frame or embedded part and welding pad 20mm
4.2.6 Earthing
All metal parts shall be electrically earthed.
4.2.7 Electrical enclosure
Electrical equipment enclosure for electrical equipment shall comply with IEC79, IEC298, IEC529and IEC947-1.
Minimum enclosure classification for non-rotating electrical equipment shall be :
Indoors only in totally enclosed rooms with provision for limiting ingress of dust IP31
Indoors, except as noted otherwise IP54
The enclosure protection class of outdoor installed equipment IP64
The enclosure classification of main and auxiliary cables boxes with the cable terminated shall not be less than that of the associated equipment, subject to a minimum classification of IP54
4.2.8 Cubicle and electrical components
The design, manufacture and testing of all equipment and installations shall comply with the latestelectrical standards IEC and ISO.
Equipment installed in power plant to be capable of withstanding an ambient temperature of
+ 48°C without damage, under normal conditions of operation.
The electrical equipment shall be arranged such that it is easily accessible.
Each switchboard, cubicle, panel, etc.. shall incorporate electric heaters fed from LV single phasecapable of providing movement of sufficient heated air to avoid condensation.
The local control panels shall be manufactured from sheet steel of 2 mm thickness.
Main electrical component shall include a safety margin of 10% under consideration of the worstcase to be meet in service.
In case the sub-contractor needs a voltage different from those available, the necessary transformershave to be supplied by himself.
Each equipment must be provided with a dedicated earthing according to the sub-contractorstandard.
Labeling principles to be in accordance with applicable regulations and sub-contractor standards.
Each electric equipment of the electrical material list must be physically labeled the same way.
Cables terminals are included in the sub-contractor scope of supply.
All equipment to be connected must be provided with dedicated connection devices and cables penetrations (with some spare penetrations). It is the sub-contractor’s responsibility to supply anysupporting for electrical equipment.
4.2.9 Motors
All motors shall comply to IEC standard motor dimensions.
AC motors shall have squirrel cage type rotors.
All motors shall be of totally enclosed fan-cooled type, protection class IP44 according IErecommendation 144.
No light metal alloy casings will be accepted for motors above the size of 10kW.
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
9/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 9/16
Motors installed in power plant to be capable of withstanding an ambient temperature of+48°C without damage, under normal conditions of operation.
Motor rating service factor :Up to 5kW Minimum 120 % of power demand
More than 5kW Minimum 110% of power demand
AC motor shall be designed for direct on line starting.
Under all operation conditions the noise level of motors shall not exceed 85dB(A)
All the cables junction boxes will be fitted with cable glands suitable to the cable diameter.
4.2.10 Fixed access ladder
Ladder shall comply with BS4211. The minimum width of ladders shall be 500mm.
Handrails and protective barrier shall be provided wherever necessary to protect operation ormaintenance personnel from hazard and shall comply with BS6180
Double hand railing shall be provided unless otherwise specified. Each length shall be joined byinternal ferrules and all joints shall be neatly finished by the removal of all burns. The top rail shall
be not less than 30mm diameter and a height of not less than 1100mm from platform level. Theintermediate rail shall be not less than 25mm diameter rand at a height of not less than 535 from the platform level.
Toe plates extending to a height of not less than 100mm above the platform or gallery level and ofthickness not less than 6mmshall be supplied.
The open grid floor panels shall be not less than 25mm in depth and shall be and approvedmanufacturer and generally in accordance with BS4592
4.2.11 Identification plate
Each main and auxiliary equipment shall have, permanently attached to it in a conspicuous position,
a rating plate of non corrosive material upon which is to be engraved :- the manufacturer’s name and address,
- the equipment type, serial number and date of manufacture,
- main design data
Labels shall be made of gravoply or similar, with a black engraving on white background, with letter
size 4 mm mini. All labels shall be in English.
4.2.12 Corrosion protection
The equipment shall be protected according :
General Painting Specification AHS-MRW-00-WOG-MS-101
In addition to :
- For surfaces of steel structures : Thorough cleaning by sandblasting until the surface ismetallically clean; removal of dust; hot-dip galvanizing by complete immersion.
- Steel plates for doors, cabin, for the control building passenger elevator in the workshop surfaceshall be painted
– Light metal : oxidized colorless
– Safety catch and governor ropes : stainless steel – Bolt material : galvanized finish
– Machine and bright parts : All machined and bright parts shall be treated for transport with a
suitable protective coat insoluble in water, durable for at least 12 months – For on site weld zones and defect areas, the same paint schedule as indicated above shall apply..
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
10/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 10/16
4.2.13 Accessories
- Systems will be equipped with all the accessories required for their good operation.- Special tools for removing the various pieces of the apparatuses if needed to be supplied.- If lifting of equipment/packages require a lifting beam, it is inside the sub-contractor's scope of
supply.
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
11/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 11/16
5 SCOPE OF SUPPLY
The definition of the scope of technical supply, which is given by the order and its appendices, is not of an
exhaustive nature. It is the duty of the sub-contractor to deliver equipment which is complete and fulfils thecontractual requirements and characteristics and the purpose for which it is intended.
2 (two) passenger elevators, including cabin, hoisting gear, guide rails for cabin and counterweight, entrances,control and monitoring equipment, main circuit breaker in machine room and float switch;
2 (two) freight elevators, including cabin, hoisting gear, guide rails for cabin and counterweight, entrances,control and monitoring equipment, main circuit breaker in machine room and float switch;
2 (two) electric hoists 1.0t mini in freight elevator hoisting mechanism room and monorail track of electrichoist;
2 (two) electric hoist, 0.5t mini in passenger elevator hoisting mechanism room and monorail track of electrichoist;
1 (one) set of minor accessories including all ladders, guards and handrail necessary to obtain easy and safeaccess to the elevator machines.
1 (one) set of general spare parts : The required general spare parts as specified in employer’s requirements,General Technical Specification, shall be included in the tender for the equipment specified in this part.
1 (one) set of special spare parts : The special spare parts listed below shall be included in the tender for theequipment specified in this part :
- 1 set of load ropes- 1 set of brake linings- 1 brake coil- 1 set of traveling cables- 1 set of machine bearing- 1 set of guide shoes for cabin- 1 set of counterweight guide shoes- 1 set of floor relay coils- 2 sets of push buttons- 2 set of indication lamps- 1 set of indication lamp holders- 1 set of complete control panel relays, brushes, safety switches, fuses, condensers, rectifiers,
resistors, transformers- 1 set of cabin limit switches- 1 set of governor safety switches
1 (one) set of special tools : The scope of work shall include all normal customary tools as well as all toolsand devices, which are specially made and/or required for complete assembling, dismantling, adjustment, andmaintenance of all equipment specified in this part. The stipulation stated in employer’s requirement,General technical specification. All tools and devices have to be handed over the employer in unused
condition.1 (one) set of oil and grease : The sub-contractor shall supply oil and greases in accordance withrequirements employer’s requirements, General technical specification. Supply shall include an extra 100%of total oil quantity, in sealed, non returnable containment;
1 (one) set of all consumables used for erection, start-up and first operation period are inside of sub-contractor's scope of supply (touch up paint, anchoring bolts …)
5.1 CONSTRUCTION
The specific requirements indicated hereunder are in addition to and in completion of those notmentioned specifically, as arising from the sub-contractor’s obligation to supply complete workand designs suitable to fulfill the performance and the requirements of the complete supplycovered by this section.
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
12/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 12/16
5.1.1 Hoisting gear consisting of
- Driving motor with two speeds for automatic stop and inspection drive- Worm gear running in an oil bath in a closed casing.- All bearing points shall be provided with ball bearings- Hoisting brake, mounted directly on the motor- Gearing and driving sheave mounted on a steel bed plate
- The sheave shaft shall be equipped with ball or roller bearings- Sheaves and wheels for load ropes- Elevator steel wire ropes
- Counterweight of cast iron for counterbalance- Buffers installed under the cabin and counterweight on in the pit.- The counterweight shall compensate the cabin weight plus 50% of loading capacity.
5.1.2 Cabin of elevator consisting of :
- Welded rigid construction with wear-resisting and gliding guide shoes- Access from one side moving doors, except one double access level of ITEM 90-DAM-001-AC
OPTION 1)
- Telephone niche, with a separate communication suspension cable with three double conductors.The cable shall be wired to a separate terminal box in the machine room.
- Emergency exit in the cabin roof.
- Safety catch- Illumination in the centre of the cabin roof, moisture-resistant
- Floor and wall facing ‘One meter from the floor); of a aluminum nipple plate, and the floor shall be lined with PVC.
- The cabin shall be equipped with exhaust fan;- The cabin shall be equipped with an additional cabin lining for provisional use during the
installation period of the power house equipment.- The elevator cabin shall be well lighted and ventilated- A storage cabinet for two battery lamps and a 5kg fire-extinguisher shall be arranged in the cabin.
The door of the cabinet shall be glazed and provided with a key lock. In case of emergency theglass pane shall serve as emergency exit (will have to be smashed)
- An over speed actuated safety brake of the wedge type with 4 adjustable guide shoes shall bearranged at the cabin. The safety brake shall stop the cabin in case of hoist brake failure or ropedamage.
5.1.3 Elevator shaft consisting of
- Guide rails for the elevator cabin and counterweight, with guide shoes of steel profile and with allnecessary fasteners.
5.1.4 Entrance for elevator
- Automatic sliding doors shall be located on the same side of the elevator including all necessaryfoundation plates and fixing bolts.
5.1.5 Control and monitoring of elevator
- The stipulations states in employer’s requirements, General technical specifications, shall beobserved accordingly.
- - The control system shall be automatic with push-button control, passenger-operated, completewith all necessary control buttons, busy lamps and one up and one down arrow on all landing boards, and with floor indicator board above the ground floor entrances
- The cabin board shall also be equipped with an electric alarm including an additional operated
emergency supply system, with cut-cut switch for safety stop, and with optical indicator for
overload limit stop.- Instead of floor indicator in the cabin, the inside of the doors shall ne lettered with the
corresponding floor numbers.
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
13/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 13/16
- The equipment shall include all necessary contactors, switches, motor starters, thermal overload protection for the motor, and speed governor for release of the safety catch.
- The control system shall be the “collective-selective type” and the cabin shall be equipped with afloor indicator.
5.1.6 Float switches
The elevator shall additionally be equipped with a float switch located at the bottom of the elevatorshaft pit, monitoring the water level in case of flooding and initiating the blocking of the cabin in
the ground-floor position or at the floor above the flooding elevation with optical indicator in thecabin.
5.2 SPECIFIC WARRANTIES OF EQUIPMENTS
The sub-contractor covers his equipment against fault in design, sizing, material, manufacture and assembly,as well as their conformity to the use for which they are intended and more specifically :
- The equipments provide safety working conditions.
- The sub-contractor guarantees the specified lifting capacities, and the maximum stopping
difference of the elevator cabin under rated load shall not be more than +/- 10mm.
- Static load test will be 150% of the design load.
5.3 PENALTIES FOR SPECIFIC WARRANTIES
In case the technical warranties were not obtained, the sub-contractor should owe part of the totalamount of the purchase order. This penalty is defined in commercial terms.
Payment of the penalties does not release the sub-contractor from his obligations to finish the equipmentor the works, nor from other contractual obligations.
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
14/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 14/16
6 DEFINITION OF TECHNICAL SERVICES
6.1 TECHNICAL DESIGN EXECUTION
The sub-contractor undertakes to implement procedures and all necessary means to verify the
Documents/Drawings issued by him, and their coherency among themselves, before transmission to theSub-contractor.
All units of measure shall be designated in SI system. In drawings and other technical materials withother units of measure their values shall be added in SI.
The sizes of documents will be A1, A2, A3 and A4 according to international standard ISO 5457.
All documents have to be produced in English language. The translation costs are payable by the sub-contractor.
All document shall be produced in accordance with the sub-contractor’s general numbering andcodification standards. The electronic format of the documents will be in accordance with the sub-
contractor graphic charter. All required document shall respect ALSTOM forms and issued with
Autocad 2002, MS Word or MS Excel.
6.2 LIST OF TECHNICAL DOCUMENTS TO BE ISSUED BY THE SUB-CONTRACTOR
When placing the purchase order, we provide a preliminary list. It is not a comprehensive one and might
be completed during the progress of the project.
The lead-times are to be understood for document handed in our office, in their final form and checked by the sub-contractor.
Printing for approval : Each document will be submitted in 3 PAPER COPIES, 1 electronic copy withtransmittal form
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
15/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 15/16
TECHNICAL DOCUMENTS LIST DELIVERY
FIRST SET OF DOCUMENTS
Studying, procurement and manufacturing timetable C + 2 weeks
Preliminary list of technical documents to be supplied C + 2 weeks
Preliminary general arrangement drawing, per ITEM, including :
- Civil work outline dimension- Machine room loads detail- Machine room hoist detail- Shaft load and fixing detail
- Location of electrical components
C + 3 weeks
Preliminary list of consumers C + 4 weeks
SECOND SET OF DOCUMENTS
Final general arrangement including :
- All detail required for maintenance or erection- List of components
C + 6 weeks
List of consumers C + 6 weeks
Preliminary electrical cubicle drawing C + 6 weeks
List of sub-contractors C + 6 weeks
Lubrication chart C + 6 weeks
Equipment Data sheet C + 8 weeks
Motor data sheet
THIRD SET OF DOCUMENTS
Final electrical cubicle drawing C + 16 weeks
Cable list and wiring diagram C + 16 weeks
Workshop control report C + 18 weeks
Supply list C + 20 weeks
Motor factory test C + 10 weeks
Paint factory test C + 10 weeks
Electrical cubicle factory testFactory acceptance inspection C + 20 weeks
Certificate of conformity C + 20 weeks
Certificate of origin C + 20 weeks
Erection booklet C + 20 weeks
Maintenance booklet C + 20 weeks
Packing list C + 20 weeks
Disposal available C + 22 weeks
NOTA : C is date of order
NOTA : All the documents must be prepared on ALSTOM FORMS
6.3 TECHNICAL PROGRESS REPORT
During the different phases of the project respectively design, manufacturing and commissioning, thesub-contractor will have to issue progress report. The format of the report will be agreed between the
sub-contractor and the sub-contractor during the kick-off meeting.
This progress report will be submitted to the sub-contractor on a monthly basis during design andmanufacturing and on a weekly basis during commissioning period.The content of this report should cover as a minimum the following items :
- The principal operations carried out and the difficulties encountered during the month,
- An estimation of progress task by task (in percentage),- The revision of the end dates, and, if necessary, the analysis of causes of deviations and
consequences on the remaining works,
8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators
16/16
AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 16/16
- The manpower resources implemented.
- Technical issues: description, corrective action plan
During the commissioning period, the sub-contractor will have to report on a daily basis to thecommissioning manager.
6.4 TECHNICAL LABELLINGEach ITEM shall be packed separately for erection reasons.
Each PART or sub-assembly must bear a metal label showing the ITEM number, the number ofALSTOM order, possibly the assembly and identification plan number or any designation appearing inthe order or likely to identify this part. If the conditions of labeling are not respected, the cost ofidentifying the equipment shall be deducted from the payments due to the sub-contractor.