AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

  • Upload
    ibrahim

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    1/16

     

    AHS MRW00 DAM-MS101

    COMMENTS :

    Sign.N.

    Sign.N.

    Sign.N.

    C Sign.N.G. FOUCAULT C. DELAGE J. BINDELE 07 October

    2004

    OPTION 1 : 90.DAM.001.AC ADDITIONAL DOORUPDATING SUB-CONTRACTOR DESIGNATION

    PREL

    BSign.N. G. FOUCAULT C. DELAGE J. BINDELE

    30 September 2004

    UPDATING OF SCOPE OF SERVICES PREL

     ASign.N. G. FOUCAULT C. DELAGE J. BINDELE

    20 August2004

    FIRST ISSUE PREL

       R   E   V

     ETABLI

    ESTABLISHED

     VERIFIECHECKED

     APPROUVE APPROVED

    DATE MODIFICATIONS STAT

     Approved Approved as noted Returned for correction For information

    Date : ………………………….. Signature : …………………………….

    LAHMEYER INTERNATIONAL

    GOVERNMENT OF THE REPUBLIC OF THE SUDANMINISTRY OF IRRIGATION AND WATER RESOURCES

    MEROWE DAM PROJECT IMPLEMENTATION UNIT 

    MEROWE DAM PROJECT

    10 x 140MVACONTRACTS 3A, 3B, 3C, 3E

    ENGINEER: SUB-CONTRACTOR: 

    TECHNICAL SPECIFICATION

    ELEVATORS

    SCALE1/1

    Sub-contractor :

    M1144-A40182 REV

    C SH/SHEND

    1/16 

    N of SH

    16 

    INTERNAL USE

    Ce document propriété de ALSTOM ne doit pas être utilisé, copié ou communiqué à des tiers sans son autorisation

    This document is the exclusive property of ALSTOM and shall not be used, copied or communicated to third parties without their prior authorization 

    Power EnvironmentHydro

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    2/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 2/16 

    TABLE DES MODIFICATIONS / MODIFICATIONS TABLE  

    REVETABLI

    ESTABLISHED 

    VERIFIE

    CHECKED 

     APPROUVE

     APPROVED DATE MODIFICATIONS STAT.

     A G. FOUCAULT C. DELAGE J. BINDELE20

     August2004

    FIRST ISSUE PRE

    B G. FOUCAULT  C. DELAGE J. BINDELE30

    SeptembUPDATING OF SCOPE OF SERVICES PRE

    C G. FOUCAULT C. DELAGE J. BINDELE07 OPTION 1 : 90.DAM.001.AC ADDITIONAL DOOR

    UPDATING SUB-CONTRACTOR DESIGNATIONPRE

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    3/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 3/16 

    TABLE OF CONTENTS

    TABLE OF CONTENTS ...................................................................................................................................................3  

    1  INTRODUCTION..................................................................................................................................................................4  

    2  REFERENCES DOCUMENTS............................................................................................................................................4 

    3  FUNCTIONAL REQUIRMENT..........................................................................................................................................5 

    4  TECHNICAL REQUIRMENT.............................................................................................................................................6 

    4.1  GENERAL TECHNICAL CONDITIONS .......................................................... ........................................................... 6 4.1.1   Environment conditions ...................................................... ............................................................. ...........................6  4.1.2   Electrical network conditions ........................................................ ............................................................ .................6  4.1.3  Country’s and international standards.......................................................................................................................6  

    4.2  DESIGN CRITERIA.......................................................................................................................................................7 4.2.1   Elevator standard ............................................................ ...................................................... .....................................7  4.2.2   Design, material and workmanship general requirement................................... ....................................................... 7  4.2.3  Safety...........................................................................................................................................................................7  4.2.4  Civil work tolerance....................................................................................................................................................7  4.2.5   Embedded parts minimum thickness ....................................................... ............................................................. .......7  4.2.6    Earthing ................................................... ....................................................... ............................................................ 8 4.2.7    Electrical enclosure ........................................................ ................................................................. ...........................8 4.2.8  Cubicle and electrical components ....................................................... ..................................................... .................8 

    4.2.9   Motors.................................................... ............................................................ ......................................................... 8 4.2.10   Fixed access ladder .................................................. ........................................................ ......................................9 4.2.11   Identification plate...................................................... ................................................................. ...........................9 4.2.12  Corrosion protection ..................................................... .............................................................. ...........................9 4.2.13   Accessories .......................................................... .............................................................. ...................................10 

    5  SCOPE OF SUPPLY ............................................................. ........................................................... ...................................11 

    5.1  CONSTRUCTION..............................................................................................................................................................11  5.1.1   Hoisting gear consisting of ................................................ .............................................................. .........................12 5.1.2  Cabin of elevator consisting of :...............................................................................................................................12 5.1.3   Elevator shaft consisting of......... ............................................................ ......................................................... .........12 5.1.4   Entrance for elevator ................................................................. ..................................................... ..........................12 5.1.5  Control and monitoring of elevator .......................................... .............................................. ..................................12 

    5.1.6    Float switches ............................................................. ........................................................... ...................................13 5.2  SPECIFIC WARRANTIES OF EQUIPMENTS ............................................................................. .............................13 5.3  PENALTIES FOR SPECIFIC WARRANTIES ................................................... ......................................................... 13 

    6  DEFINITION OF TECHNICAL SERVICES...................................................................................................................14 

    6.1  TECHNICAL DESIGN EXECUTION.........................................................................................................................14 6.2  LIST OF TECHNICAL DOCUMENTS TO BE ISSUED BY THE SUB-CONTRACTOR ..........................................14 6.3  TECHNICAL PROGRESS REPORT...........................................................................................................................15 6.4  TECHNICAL LABELLING.........................................................................................................................................16 

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    4/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 4/16 

    1 INTRODUCTION

    These technical specification defines the applicable conditions for MEROWE project :- Final customer : MDPIU (MEROWE Dam Project Implementation Unit)- Country : REPUBLIC OF THE SUDAN- Site : MEROWE

    These specification is applicable for the supply of :

    PASSENGERS AND FREIGHT ELEVATORS

    2 REFERENCES DOCUMENTS

    The General Painting Specification INS-MRW-00-WOG-MS-102The General Technical Specification AHS-MRW-00-WIG-MS-100

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    5/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 5/16 

    3 FUNCTIONAL REQUIRMENT

    ITEM 30.DAM.001.AC 70.DAM.001.AC 90.DAM.001.AC 90.DAM.002.AC

    Contractual designation Freight elevator

    for non-overflowconcrete dam

    Passenger elevator

    for GIS building

    Freight elevator for

    service building

    Passenger

    elevator forservice building

    Type Freight Passenger Freight Passenger

    Lifting capacity 2 000 kg 630 kg 2 000 kg 630 kg

    Hoisting speed 0.5 m/s 1.0 m/s 0.5 m/s 1.0m/s

     Number of access 5 5 11 11

     Number of cabin door 1 1 2

    (OPTION 1)

    1

    Height of elevator entrance 2.20 2.10 2.20 2.10

    Height of elevator cabin 2.20 2.10 2.20 2.10

    Section of elevator cabin 2.0 x 2.5 1.1 x 1.4 2.0 x 2.5 1.1 x 1.4

    Level of motor room 306.5 292.0 283.7 283.7Level of floor access 238.0 260.00 241.5 241.5

    260.0 276.20 247.2 247.2

    272.0 279.50 253.8 253.8

    299.4 282.80 257.10 257.10

    303.0 286.10 260.40(OPTION 1)

    260.40

    263.70 263.70

    267.00 267.00

    270.30 270.30

    273.6 273.6

    276.9 276.9

    280.3 280.3

    Civil work dimension

    Shaft width 3 370 1 950 3 370 1 950

    Shaft length 3 250 2 100 3 000 2 100

    Shaft pit height 2 200 1 500 2 200 1 500

    Access door width 3 200 1 600 3 200 1 600

    Access door height 2 600 2 315 2 600 2 315

    Electric hoist load (mini) 1 000 daN 500 daN 1 000 daN 500 daN

    IMPORTANT REMARK : The final levels shall be confirmed by ALSTOM General Arrangement and Civil-Work drawings during detailed design.

    OPTION 1 : The access level at 260.4 shall be defined with two side access. This should be quoted separatelyas an option.

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    6/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 6/16 

    4 TECHNICAL REQUIRMENT

    4.1 GENERAL TECHNICAL CONDITIONS

    4.1.1 Environment conditions

    The electrical and control equipment will be designed according to the following conditions:- Altitude ....................................................................................... 260m above sea level

    Ambient site temperature (and relative humidity):- Minimum indoor.......................................................................... 4 °C- Maximum indoor ......................................................................... 35 °C- Design temperature...................................................................... 48 °C- Relative humidity (average per month) ...................................... 29,1 % (at 20 °C)

    Earthquake withstand ability :

    - Horizontal acceleration ............................................................... > 0,2 g

    - Vertical acceleration ................................................................... > 0,1 g

    - Safety factor ................................................................................ ≥ 2,0

    Equipment installed in power plant to be capable of withstanding an ambient temperature of+ 48°C without damage, under normal conditions of operation.

    4.1.2 Electrical network conditions

    AC Auxiliary Supply for motors- Rated Voltage : 400/230V- Distribution type : 3 phases, 4 wires- Voltage variations at consumers terminals : +10% -15% (-20% during motors starting)- Frequency : 50Hz- Frequency variations : Normal : ± 0.5Hz – Transient : -3Hz, +2Hz

    - Neutral System : TNS

    AC Auxiliary supply for lighting and space heaters- Rated Voltage : 230V- Distribution type : 1 ph + N- Voltage variations at consumers terminals : +10% -15%- Frequency : 50Hz

    - Frequency variations : Normal : ± 0.5Hz – Transient : -3Hz, +2Hz- Neutral System : TNS

    DC Auxiliary supply for control and measurements

    - Rated Voltage : 220V

    - Voltage variations at consumers terminals : +10% -15%

    - Earthling System : Both poles isolated from earth 

    4.1.3 Country’s and international standards

    Certain specification issued by national or other widely recognised bodies are referred to in thiscontract. Such specification shall be defined and referred to hereinafter as standard specificationsand shall be the latest editions at the time of issue of the order. The following standards shall beused:EN European normIEC International Electro technical commissionANSI American National standard institute

    FEM Federation Europeenne de la Manutention, FranceBS British standard

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    7/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 7/16 

    4.2 DESIGN CRITERIA

    4.2.1 Elevator standard

    Elevators built according EN81

    Dynamic load : 110% of rated load

    Static test load : 150% of rated load

    4.2.2 Design, material and workmanship general requirement

    All parts of the equipment shall be designed and manufactured in the best and fully suitable mannerwith materials best suited to their purpose and in accordance with recognized standard to good practice and latest technology.

    Wherever practicable, the design and shaping of important component shall be such as to facilitatefull non-destructive examination.

    In the design, due regard shall be paid to the accessibility of parts which require maintenance. The

    lubrication points shall be clearly marked and arranged in an orderly and clearly visible manner.Tooth gears in the vicinity of accessible places shall be enclosed. All screws, bolts and nuts shall belocked so that it is impossible for them to become loose in operation.

    The parts shall be usable without adjustment. The brakes shall be dimensioned to hold fast the test

    load.

    The sub-contractor is required to pay attention to the reduction of sound, noise and vibration and isrequired to provide and install all necessary sound and vibration-reducing materials. Any noises

    made by the cabin in its normal passage through the hoist ways shall be eliminated as far as possible.

    Sheaves and wheels for load ropes shall have a pitch diameter not less than 40 times the diameter ofthe rope used therewith.

    The cabin speed downwards with rated load under normal operating conditions with power supplyon or off shall not exceed 125% of rated speed.

    The elevator shall be equipped for manual operation in case of motor or power failure. 

    4.2.3 Safety

    The design of the equipment shall provide all reasonable precautions for the security of the personnel engaged in operation and maintenance and shall meet the relevant safety regulations andstandards specified in employer’s requirements, General technical specification.

    All live, moving and rotating parts shall be adequately secured in order to avoid danger to theoperating staff.

    4.2.4 Civil work tolerance

    IMPORTANT REMARK : To meet the project deadline, a preliminary study has already defined the bottom of the elevator shafts as here above. The sub-contractor will confirm his agreement and willsupply all equipments and fittings accessories accordingly.

    For building measures as well as for placing first-stage concrete anchors, an accuracy of +-30mm

    shall be taken into account

    4.2.5 Embedded parts minimum thickness

    Minimum thickness of steel, without regard to stress, shall be as follows unless otherwise specified :

    - Gate skin plate : 15mm- Plate thickness of any structural part except webs of rolled shapes : 10mm

    - Embedded metal with exposed surfaces : 12mm

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    8/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 8/16 

    - Completely embedded metal : 10mm- Corrosion resistant steel cladding after final machining : 6mm- Diameter of bolts or screws on gate structures : 16mm- Diameter of adjusting bolt between frame or embedded part and welding pad 20mm

    4.2.6 Earthing

    All metal parts shall be electrically earthed.

    4.2.7 Electrical enclosure

    Electrical equipment enclosure for electrical equipment shall comply with IEC79, IEC298, IEC529and IEC947-1.

    Minimum enclosure classification for non-rotating electrical equipment shall be :

    Indoors only in totally enclosed rooms with provision for limiting ingress of dust IP31

    Indoors, except as noted otherwise IP54

    The enclosure protection class of outdoor installed equipment IP64

    The enclosure classification of main and auxiliary cables boxes with the cable terminated shall not be less than that of the associated equipment, subject to a minimum classification of IP54

    4.2.8 Cubicle and electrical components

    The design, manufacture and testing of all equipment and installations shall comply with the latestelectrical standards IEC and ISO.

    Equipment installed in power plant to be capable of withstanding an ambient temperature of

    + 48°C without damage, under normal conditions of operation.

    The electrical equipment shall be arranged such that it is easily accessible.

    Each switchboard, cubicle, panel, etc.. shall incorporate electric heaters fed from LV single phasecapable of providing movement of sufficient heated air to avoid condensation.

    The local control panels shall be manufactured from sheet steel of 2 mm thickness.

    Main electrical component shall include a safety margin of 10% under consideration of the worstcase to be meet in service.

    In case the sub-contractor needs a voltage different from those available, the necessary transformershave to be supplied by himself.

    Each equipment must be provided with a dedicated earthing according to the sub-contractorstandard.

    Labeling principles to be in accordance with applicable regulations and sub-contractor standards.

    Each electric equipment of the electrical material list must be physically labeled the same way.

    Cables terminals are included in the sub-contractor scope of supply.

    All equipment to be connected must be provided with dedicated connection devices and cables penetrations (with some spare penetrations). It is the sub-contractor’s responsibility to supply anysupporting for electrical equipment.

    4.2.9 Motors

    All motors shall comply to IEC standard motor dimensions.

    AC motors shall have squirrel cage type rotors.

    All motors shall be of totally enclosed fan-cooled type, protection class IP44 according IErecommendation 144.

     No light metal alloy casings will be accepted for motors above the size of 10kW.

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    9/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 9/16 

    Motors installed in power plant to be capable of withstanding an ambient temperature of+48°C without damage, under normal conditions of operation.

    Motor rating service factor :Up to 5kW Minimum 120 % of power demand

    More than 5kW Minimum 110% of power demand

    AC motor shall be designed for direct on line starting.

    Under all operation conditions the noise level of motors shall not exceed 85dB(A)

    All the cables junction boxes will be fitted with cable glands suitable to the cable diameter.

    4.2.10 Fixed access ladder

    Ladder shall comply with BS4211. The minimum width of ladders shall be 500mm.

    Handrails and protective barrier shall be provided wherever necessary to protect operation ormaintenance personnel from hazard and shall comply with BS6180

    Double hand railing shall be provided unless otherwise specified. Each length shall be joined byinternal ferrules and all joints shall be neatly finished by the removal of all burns. The top rail shall

     be not less than 30mm diameter and a height of not less than 1100mm from platform level. Theintermediate rail shall be not less than 25mm diameter rand at a height of not less than 535 from the platform level.

    Toe plates extending to a height of not less than 100mm above the platform or gallery level and ofthickness not less than 6mmshall be supplied.

    The open grid floor panels shall be not less than 25mm in depth and shall be and approvedmanufacturer and generally in accordance with BS4592

    4.2.11 Identification plate

    Each main and auxiliary equipment shall have, permanently attached to it in a conspicuous position,

    a rating plate of non corrosive material upon which is to be engraved :- the manufacturer’s name and address,

    - the equipment type, serial number and date of manufacture,

    - main design data

    Labels shall be made of gravoply or similar, with a black engraving on white background, with letter

    size 4 mm mini. All labels shall be in English.

    4.2.12 Corrosion protection

    The equipment shall be protected according :

    General Painting Specification AHS-MRW-00-WOG-MS-101

    In addition to :

    - For surfaces of steel structures : Thorough cleaning by sandblasting until the surface ismetallically clean; removal of dust; hot-dip galvanizing by complete immersion.

    - Steel plates for doors, cabin, for the control building passenger elevator in the workshop surfaceshall be painted

     – Light metal : oxidized colorless

     – Safety catch and governor ropes : stainless steel – Bolt material : galvanized finish

     – Machine and bright parts : All machined and bright parts shall be treated for transport with a

    suitable protective coat insoluble in water, durable for at least 12 months – For on site weld zones and defect areas, the same paint schedule as indicated above shall apply..

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    10/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 10/16 

    4.2.13 Accessories

    - Systems will be equipped with all the accessories required for their good operation.- Special tools for removing the various pieces of the apparatuses if needed to be supplied.- If lifting of equipment/packages require a lifting beam, it is inside the sub-contractor's scope of

    supply.

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    11/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 11/16 

    5 SCOPE OF SUPPLY

    The definition of the scope of technical supply, which is given by the order and its appendices, is not of an

    exhaustive nature. It is the duty of the sub-contractor to deliver equipment which is complete and fulfils thecontractual requirements and characteristics and the purpose for which it is intended.

    2 (two) passenger elevators, including cabin, hoisting gear, guide rails for cabin and counterweight, entrances,control and monitoring equipment, main circuit breaker in machine room and float switch;

    2 (two) freight elevators, including cabin, hoisting gear, guide rails for cabin and counterweight, entrances,control and monitoring equipment, main circuit breaker in machine room and float switch;

    2 (two) electric hoists 1.0t mini in freight elevator hoisting mechanism room and monorail track of electrichoist;

    2 (two) electric hoist, 0.5t mini in passenger elevator hoisting mechanism room and monorail track of electrichoist;

    1 (one) set of minor accessories including all ladders, guards and handrail necessary to obtain easy and safeaccess to the elevator machines.

    1 (one) set of general spare parts : The required general spare parts as specified in employer’s requirements,General Technical Specification, shall be included in the tender for the equipment specified in this part.

    1 (one) set of special spare parts : The special spare parts listed below shall be included in the tender for theequipment specified in this part :

    - 1 set of load ropes- 1 set of brake linings- 1 brake coil- 1 set of traveling cables- 1 set of machine bearing- 1 set of guide shoes for cabin- 1 set of counterweight guide shoes- 1 set of floor relay coils- 2 sets of push buttons- 2 set of indication lamps- 1 set of indication lamp holders- 1 set of complete control panel relays, brushes, safety switches, fuses, condensers, rectifiers,

    resistors, transformers- 1 set of cabin limit switches- 1 set of governor safety switches

    1 (one) set of special tools : The scope of work shall include all normal customary tools as well as all toolsand devices, which are specially made and/or required for complete assembling, dismantling, adjustment, andmaintenance of all equipment specified in this part. The stipulation stated in employer’s requirement,General technical specification. All tools and devices have to be handed over the employer in unused

    condition.1 (one) set of oil and grease : The sub-contractor shall supply oil and greases in accordance withrequirements employer’s requirements, General technical specification. Supply shall include an extra 100%of total oil quantity, in sealed, non returnable containment;

    1 (one) set of all consumables used for erection, start-up and first operation period are inside of sub-contractor's scope of supply (touch up paint, anchoring bolts …)

    5.1 CONSTRUCTION

    The specific requirements indicated hereunder are in addition to and in completion of those notmentioned specifically, as arising from the sub-contractor’s obligation to supply complete workand designs suitable to fulfill the performance and the requirements of the complete supplycovered by this section.

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    12/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 12/16 

    5.1.1 Hoisting gear consisting of

    - Driving motor with two speeds for automatic stop and inspection drive- Worm gear running in an oil bath in a closed casing.- All bearing points shall be provided with ball bearings- Hoisting brake, mounted directly on the motor- Gearing and driving sheave mounted on a steel bed plate

    - The sheave shaft shall be equipped with ball or roller bearings- Sheaves and wheels for load ropes- Elevator steel wire ropes

    - Counterweight of cast iron for counterbalance- Buffers installed under the cabin and counterweight on in the pit.- The counterweight shall compensate the cabin weight plus 50% of loading capacity.

    5.1.2 Cabin of elevator consisting of :

    - Welded rigid construction with wear-resisting and gliding guide shoes- Access from one side moving doors, except one double access level of ITEM 90-DAM-001-AC

    OPTION 1)

    - Telephone niche, with a separate communication suspension cable with three double conductors.The cable shall be wired to a separate terminal box in the machine room.

    - Emergency exit in the cabin roof.

    - Safety catch- Illumination in the centre of the cabin roof, moisture-resistant

    - Floor and wall facing ‘One meter from the floor); of a aluminum nipple plate, and the floor shall be lined with PVC.

    - The cabin shall be equipped with exhaust fan;- The cabin shall be equipped with an additional cabin lining for provisional use during the

    installation period of the power house equipment.- The elevator cabin shall be well lighted and ventilated- A storage cabinet for two battery lamps and a 5kg fire-extinguisher shall be arranged in the cabin.

    The door of the cabinet shall be glazed and provided with a key lock. In case of emergency theglass pane shall serve as emergency exit (will have to be smashed)

    - An over speed actuated safety brake of the wedge type with 4 adjustable guide shoes shall bearranged at the cabin. The safety brake shall stop the cabin in case of hoist brake failure or ropedamage.

    5.1.3 Elevator shaft consisting of

    - Guide rails for the elevator cabin and counterweight, with guide shoes of steel profile and with allnecessary fasteners.

    5.1.4 Entrance for elevator

    - Automatic sliding doors shall be located on the same side of the elevator including all necessaryfoundation plates and fixing bolts.

    5.1.5 Control and monitoring of elevator

    - The stipulations states in employer’s requirements, General technical specifications, shall beobserved accordingly.

    - - The control system shall be automatic with push-button control, passenger-operated, completewith all necessary control buttons, busy lamps and one up and one down arrow on all landing boards, and with floor indicator board above the ground floor entrances

    - The cabin board shall also be equipped with an electric alarm including an additional operated

    emergency supply system, with cut-cut switch for safety stop, and with optical indicator for

    overload limit stop.- Instead of floor indicator in the cabin, the inside of the doors shall ne lettered with the

    corresponding floor numbers.

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    13/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 13/16 

    - The equipment shall include all necessary contactors, switches, motor starters, thermal overload protection for the motor, and speed governor for release of the safety catch.

    - The control system shall be the “collective-selective type” and the cabin shall be equipped with afloor indicator.

    5.1.6 Float switches

    The elevator shall additionally be equipped with a float switch located at the bottom of the elevatorshaft pit, monitoring the water level in case of flooding and initiating the blocking of the cabin in

    the ground-floor position or at the floor above the flooding elevation with optical indicator in thecabin.

    5.2 SPECIFIC WARRANTIES OF EQUIPMENTS

    The sub-contractor covers his equipment against fault in design, sizing, material, manufacture and assembly,as well as their conformity to the use for which they are intended and more specifically :

    - The equipments provide safety working conditions.

    - The sub-contractor guarantees the specified lifting capacities, and the maximum stopping

    difference of the elevator cabin under rated load shall not be more than +/- 10mm.

    - Static load test will be 150% of the design load.

    5.3 PENALTIES FOR SPECIFIC WARRANTIES

    In case the technical warranties were not obtained, the sub-contractor should owe part of the totalamount of the purchase order. This penalty is defined in commercial terms.

    Payment of the penalties does not release the sub-contractor from his obligations to finish the equipmentor the works, nor from other contractual obligations.

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    14/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 14/16 

    6 DEFINITION OF TECHNICAL SERVICES

    6.1 TECHNICAL DESIGN EXECUTION

    The sub-contractor undertakes to implement procedures and all necessary means to verify the

    Documents/Drawings issued by him, and their coherency among themselves, before transmission to theSub-contractor.

    All units of measure shall be designated in SI system. In drawings and other technical materials withother units of measure their values shall be added in SI.

    The sizes of documents will be A1, A2, A3 and A4 according to international standard ISO 5457.

    All documents have to be produced in English language. The translation costs are payable by the sub-contractor.

    All document shall be produced in accordance with the sub-contractor’s general numbering andcodification standards. The electronic format of the documents will be in accordance with the sub-

    contractor graphic charter. All required document shall respect ALSTOM forms and issued with

    Autocad 2002, MS Word or MS Excel.

    6.2 LIST OF TECHNICAL DOCUMENTS TO BE ISSUED BY THE SUB-CONTRACTOR

    When placing the purchase order, we provide a preliminary list. It is not a comprehensive one and might

     be completed during the progress of the project.

    The lead-times are to be understood for document handed in our office, in their final form and checked by the sub-contractor.

    Printing for approval : Each document will be submitted in 3 PAPER COPIES, 1 electronic copy withtransmittal form

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    15/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 15/16 

    TECHNICAL DOCUMENTS LIST DELIVERY

    FIRST SET OF DOCUMENTS

    Studying, procurement and manufacturing timetable C + 2 weeks

    Preliminary list of technical documents to be supplied C + 2 weeks

    Preliminary general arrangement drawing, per ITEM, including :

    - Civil work outline dimension- Machine room loads detail- Machine room hoist detail- Shaft load and fixing detail

    - Location of electrical components

    C + 3 weeks

    Preliminary list of consumers C + 4 weeks

    SECOND SET OF DOCUMENTS

    Final general arrangement including :

    - All detail required for maintenance or erection- List of components

    C + 6 weeks

    List of consumers C + 6 weeks

    Preliminary electrical cubicle drawing C + 6 weeks

    List of sub-contractors C + 6 weeks

    Lubrication chart C + 6 weeks

    Equipment Data sheet C + 8 weeks

    Motor data sheet

    THIRD SET OF DOCUMENTS

    Final electrical cubicle drawing C + 16 weeks

    Cable list and wiring diagram C + 16 weeks

    Workshop control report C + 18 weeks

    Supply list C + 20 weeks

    Motor factory test C + 10 weeks

    Paint factory test C + 10 weeks

    Electrical cubicle factory testFactory acceptance inspection C + 20 weeks

    Certificate of conformity C + 20 weeks

    Certificate of origin C + 20 weeks

    Erection booklet C + 20 weeks

    Maintenance booklet C + 20 weeks

    Packing list C + 20 weeks

    Disposal available C + 22 weeks

     NOTA : C is date of order

     NOTA : All the documents must be prepared on ALSTOM FORMS

    6.3 TECHNICAL PROGRESS REPORT

    During the different phases of the project respectively design, manufacturing and commissioning, thesub-contractor will have to issue progress report. The format of the report will be agreed between the

    sub-contractor and the sub-contractor during the kick-off meeting.

    This progress report will be submitted to the sub-contractor on a monthly basis during design andmanufacturing and on a weekly basis during commissioning period.The content of this report should cover as a minimum the following items :

    - The principal operations carried out and the difficulties encountered during the month,

    - An estimation of progress task by task (in percentage),- The revision of the end dates, and, if necessary, the analysis of causes of deviations and

    consequences on the remaining works,

  • 8/18/2019 AHS-MRW-00-DAM-TS-001 Rev C Consultation Elevators

    16/16

     

     AHS-MRW-00-DAM-TS-001 rev C Consultation elevators.doc 16/16 

    - The manpower resources implemented.

    - Technical issues: description, corrective action plan

    During the commissioning period, the sub-contractor will have to report on a daily basis to thecommissioning manager.

    6.4 TECHNICAL LABELLINGEach ITEM shall be packed separately for erection reasons.

    Each PART or sub-assembly must bear a metal label showing the ITEM number, the number ofALSTOM order, possibly the assembly and identification plan number or any designation appearing inthe order or likely to identify this part. If the conditions of labeling are not respected, the cost ofidentifying the equipment shall be deducted from the payments due to the sub-contractor.