50
Team Logo Here CanSat 2016 CDR: Team 8008 AGH Skydivers 1 CanSat 2016 Post Flight Review (PFR) Version 1.0 Team 8008 AGH Skydivers

AGH University of Science and Technology PFR

  • Upload
    vuhanh

  • View
    235

  • Download
    9

Embed Size (px)

Citation preview

Page 1: AGH University of Science and Technology PFR

Team Logo

Here

CanSat 2016 CDR: Team 8008 AGH Skydivers 1

CanSat 2016

Post Flight Review (PFR)Version 1.0

Team 8008

AGH Skydivers

Page 2: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

2

Presentation Outline

Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

Page no. Contents Presenter

3 Introduction Weronika Mrozińska

5 Systems Overview Weronika Mrozińska

18 Concept of Operations and Sequence of Events Weronika Mrozińska

23 Flight data analysis Jakub Rachucki

39 Failure alalysis Jakub Rachucki

44 Lessons Learned Jakub Rachucki

Page 3: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

3

Team Organization

Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 4: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

4

Team Organization

Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

From left: Bartosz Moczała (Ground Station Crew), Jakub Rachucki (Ground Station Crew),

Weronika Mrozińska (Mission Control Officer), Zbigniew Kostka (Recovery Crew), Tomasz Strzałka (Recovery Crew).

Page 5: AGH University of Science and Technology PFR

Team Logo

Here

5

Systems Overview

Weronika Mrozińska

CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 6: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Mission Summary

6Presenter: Weronika Mrozińska

Mission Objectives

Safely release the glider (SV) from the re – entry Container

Descent gliding in circular pattern of no more than 1000m in diameter and as closely to the 3.3m/s rate as possible

Collect telemetry data during flight and transmit them to the Ground Station in real time

Take pictures while requested

Land and process to the recovery mode

Bonus Objectives

Transmit image to ground station after each picture is taken.

Telemetry must still be sent during image transmission at the

1 Hz rate using the same XBee radio.

Rationale: comparing to the second possible bonus

objective, this selectable objective does not require any

additional mechanical components, therefore it does not

increase the mass of the CanSat, which is limited.

External Objectives

Our personal objective is to measure acceleration, rotational speed and magnetic field to simulate trajectory and orientation of

the glider.

CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 7: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) CanSat overview - container

7Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

Container – made of GFRP ( Glass Fiber ReinforcedPolymer with Balsa wood)

Parachute.

Dummy mass.

Page 8: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) CanSat overview - payload

8Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

Camera coverPitot tube module cover On-board computer cover

Buzzer Antenna

Carbon telescopic rods3d printed plane of attack

Carbon CanSat ribbing.

Page 9: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) CanSat overview - payload

9Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

Slider

Rubber band

Camera Module3d printed structure parts

Nylon kite

Pitot tube

Page 10: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

10

Components Summary & CanSat

Overall Cost – Hardware

Presenter: Weronika Mrozińska

Part Description Quantity Price[$] Total[$]

Sensors Subsystem

ORG1218 GPS receiver 1 35.07 35.07

BMP180 Pressure sensor 1 4.95 4.95

Eagle Tree Airspeed Micro SensorPitot tube+ pitot tube

sensor1 42.99 42.99

DS18B20 Temperature Sensor 1 3.09 3.09

LIS331 Accelerometer 1 5.65 5.65

HMC5883LSMD Magnetometer 1 5.98 5.98

LSM9DS0 IMU 1 7.89 7.89

TEPT4400 Light Sensor 3 0.58 1.74

uCamII Camera module 1 49.00 49.00

CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 11: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

11

Components Summary & CanSat

Overall Cost – Hardware

Presenter: Weronika Mrozińska

Part Description Quantity Price[$] Total[$]

Structure

PLA 3D printing material 80g 0,035[$/g] 2.8

Carbon rods Rotation shafts. 0.9m 1,97[$/m] 1.77

CanSAT container SV is stored in container 1 20 20

Weights Container load N/A 2 2

Carbon tubes Kite holder 1.2m 4,7[$/m] 5.64

Ripstop Nylon Kite Material 0,126m2 25,91 [$/m2] 3.26

Rubber Wings opening mechanism 1 packet 1 1

Parachute Container recovery system 1 14,53 14.53

Swivel Container recovery system 1 3 3

Other PartsScrews for mounting

components, kite strings etc.N/A 10 10

CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 12: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

12

Components Summary & CanSat

Overall Cost – Hardware

Presenter: Weronika Mrozińska

Part Description Quantity Price[$] Total[$]

CDH subsystem

ATXMEGA256A3BU CPU 1 8.47 8.47

Swissbit SFSD2048NgBW1MT-t-ME-1x1-STD

MicroSD card for industry 1 32.7 32.7

XBee Pro 50mW U.FL - Series 2B Radio module 1 38.77 38.77

2.4GHz Antenna Radio antenna 1 4.95 4.95

Buzzers Payload recovery - indicator 2 1 2

Other Parts Resistors, capacitors etc. 1 5 5

Electrical Power Subsystem

TrustFire Rechargeable Li-Ion 10440 AAA 3.7V 600mAh Battery

Main power source 1 8 8

FC0V474ZFTBR24 SUPERcapacitor

Backup source of power 1 2.72 2.72

317EMP Voltage regulator 1 0.48 0.48

LTC4065 Battery charger 1 1.31 1.31

Other Parts Resistors, capacitors etc. 1 5 5

Total cost of hardware $298.37

CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 13: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

13

CanSat Overall Cost – Hardware

Presenter: Weronika Mrozińska

Budget summary

CanSat $298.37

Shipping $50.00

SUM: $348.37

Exchange rates used

£1,0000 $1.4200

€ 1,0000 $1.0800

CHF 1,0000 $0.9800

PLN 1,00 $0.2400

CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 14: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

14

CanSat Overall Cost – Other Costs

Presenter: Weronika Mrozińska

Part Description Quantity Price[$] Total[$]

Ground Control System

XBee Pro 63mW RPSMA - Series 2B Radio module 1 42,55 42,55

Panel antenna IP-G14-F2425-HV Antenna for radio module 1 24,5 24,5

RP-SMA male to N male antenna cable.

Radio module 1,5 m 6 6

USB XBee Adapter Radio adapter 1 24,95 24,95

Testing & prototyping

PrototypingPrinting of components, making prototypes, etc.

N/A 300 300

TestingRenovating of old rocket, conducting rocket tests

N/A 3000 3000

Spare partsReplacing malfunctioning

partsN/A 200 200

CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 15: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

15

CanSat Overall Cost – Other Costs

Presenter: Weronika Mrozińska

Part Description Quantity Price[$] Total[$]

Competition

Competition Fee N/A 1 100 100

Flights N/A 5 1029,08 5145.4

Meals N/A 72 12 864

Accommodation N/A 5 125 625

Renting a car N/A 1 520 520

Total $9284

Budget summary

Income (external sponsors)

+$11100

Own funds +$500

CanSat Budget – Hardware -$348.37

CanSat Budget – Other Costs

-$ 10852.40

Balance +$399.33

CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 16: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Componets Summary

16

Electronics Mechanics GS

GPS receiver Main power source 3D printed Parts Radio module

Pressure sensor Backup source of power Rotation shafts.Antenna for

radio module

Pitot tube+ pitot tube sensor Voltage regulator Container Radio module

Temperature Sensor Battery charger Container load Radio adapter

Accelerometer Resistors, capacitors etc. CanSat Carbon ribbing

Magnetometer Radio antenna Kite Material

IMU Buzzer Wings opening mechanism

Light Sensor Container recovery system

Camera module Rubber bands

CPU Environmental protection elements

MicroSD card Nylon strings

Radio module Screws

Telecopic carbon tubes

Neodymium magnets

Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 17: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Physical layout

17Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 18: AGH University of Science and Technology PFR

Team Logo

Here

18

Concept of Operations and Sequence

of Events

Weronika Mrozińska

CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 19: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Comparison of planned and actual Con-Ops

19Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

Activitiy Execution

Launch Pass

Deploy CanSat from the rocket Pass

Collecting and sending data Pass

Open Parachute Pass

Separation Pass

Separate SV from the container Failed

Acquire picture Pass

Landing Pass/Failed

Data post-processing in GS Pass

Page 20: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Release Logic

20Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

Ligth sensors detect deployment from rocket

Altitude less then 450m

Nichrome wire for cutting string switched on for 14s

Redundancy:Possible to release the glider from container by using remote command

Page 21: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Comparison of planned and actual SOE

21Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

Stage Responsibilities Assigned person

Ca

nS

at

Pre

pa

rati

on

an

d

as

se

mb

ly

Arrive at launch site.

Whole Team

Preparation of the CanSat for turning in.

Checklist

• Communication test

• Structure check.

• Check battery level and on-board computer state.

• Check recovery system (unfolding of the kite)

CanSat assembly.

Final Check (checklist once again)

Turn in CanSat at the check-in table by noon.

Pre

flig

ht

Collect CanSat CanSat Crew

Load CanSat to rocket CanSat Crew

Verify the communication Ground station Crew

Take a rocket and the ground station to the launch pad GS Crew + CanSat Crew

Setting up the ground station GS Crew

Executing of launch procedures Mission control officer

Ground station Crew performing all required flight operation. (sending remote

commands etcGS crew

Page 22: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Comparison of planned and actual SOE

22Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

Stage Responsibilities Assigned person

Mis

sio

n

CanSat is launched

Mission control officer

CanSat deployment from the rocket.

Container parachute flight

Separation at 400m +/- 10m

Deplyment from container

Glider flight

Touchdown

• Buzzer on

• Telemetry off.

Ground station Crew performing all required flight operation. (sending

remote commands etc.GS crew

Re

co

ve

ry

After all CanSat launched recovery crew head out for CanSat recovery. Recovery Crew

Clearing out the ground station to make it available for the rest of the tames. GS Crew

Turning in the thumb drive with saved telemetry in CSV format. GSCrew

Recovery crew comeback with the CanSat for PFR analysis. Recovery Crew

An

aly

sis

Collecting data obtain from sensors.

Whole TeamIn case of telemetry fail recover data from the on-board computer.

Analysis of obtained data.

Mission assessment and preparation for the presentation.

Page 23: AGH University of Science and Technology PFR

Team Logo

Here

23

Flight Data Analysis

Jakub Rachucki

CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 24: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Payload Separation Altitude

24Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

407,6m

There is signal lag in

the GPS signal-

which is normal for

high velocities.

Altitude which is

coming form

pressure sensor is

relative to the

ground.

GPS altitude is

relative to sea level.

Page 25: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Payload Separation Altitude

25Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

407,6m

There was no

deplyment due to the

structure faliure.

Separation module

started working when

altitude dropped below

450m

Page 26: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Payload Separation Altitude

26Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

After separation, SV was stuck in the container. Nevertheless separation was conducted.

Page 27: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Payload Separation Altitude

27Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Separation was conducted on altitude 407,6 m.

Page 28: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) CanSat Altitude

28Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Altitude based on GPS data, ploted on the map.

Page 29: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Descent Rate Before Separation

29Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Descent rate before separation was equal to the one calculated and tested – approx. 8m/s

Page 30: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Payload descent rate below separation

30Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Time elapsed from the moment of separation until touchdown was approx. 50sThe calculated and tested descent time was 125 +/- 15s

Page 31: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Images

31Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 32: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Images

32Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Part of the field was localized using „googlemaps”.

Photo confirms that there was no deployment. Part of the container can be seen in the picture.

Picture shows part of the field.

Page 33: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

Payload Telemetry – SV Pressure

Sensor Data

33Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Not even single frame was lost during mission

Page 34: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

Payload Telemetry – SV Temperature

Data

34Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 35: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

Payload Telemetry – SV Battery

Voltage Data

35Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 36: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Selectable Objective Data

36Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Acquiring photo via Xbee

Photo shows part of the field.

The same Xbee was used to send telemetry data and picture.

Picture transmission didn’t disturb telemetry

Picture transmission was 17 s long.

Photo command was send when CanSat was on the 218m. Due to very late time of the photo command a part of the photo was not received, CanSat was stillsending photo after touchdown.

Full Xbee frequency transmission possibilities were used in order to send this photo

Page 37: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Personal Objective

37Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Measure acceleration, rotational speed and magnetic field to simulate trajectory and orientation of the glider

Page 38: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Personal Objective

38Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 39: AGH University of Science and Technology PFR

Team Logo

Here

39

Failure Analysis

Jakub Rachucki

CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 40: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

Identification of failures, root causes,

and corrective actions

40Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Failures:

Gliders stuck in the container

Root causes

Spare container was used as we forgot dedicated one

Glider stuck due to the fact that the foil got sticky under high temperature

Investigation:

Altitude and velocity plot shows movement

String was cut

Voltage plot shows drop of the voltage value after crossing 450 meters, which was defined altitude for separation.

Reason of the failure visible after recovery

Page 41: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

Identification of failures, root causes,

and corrective actions

41Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Altitude plot shows drop of altitude after separation time

Page 42: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

42Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Identification of failures, root causes,

and corrective actions

Vertical velocity plot show „velocity value pick” during separation which indicates glider movement

Page 43: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

43Presenter: Jakub Rachucki CanSat 2016 CDR: Team 8008 AGH Skydivers

Identification of failures, root causes,

and corrective actions

Corrective actions:

Use dedicated container

Perform whole mission once again in Poland using„Beta” Rocket, made by AGH Space Systems

Page 44: AGH University of Science and Technology PFR

Team Logo

Here

44

Lessons Learned

Jakub Rachucki

CanSat 2016 CDR: Team 8008 AGH Skydivers

Page 45: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

Discussion of what worked and

what didn't

45Presenter: Weronika Mrozińska

ID Requirement

1 Total mass of the CanSat (container and payload) shall be 500 grams +/- 10 grams.

2 The glider shall be completely contained in the container. No part of the glider may extend beyond the container.

3Container shall fit in a cylindrical envelope of 125 mm diameter x 310 mm length including the container passive descent control system.

Tolerances are to be included to facilitate container deployment from the rocket fairing.

4The container shall use a passive descent control system. It cannot free fall. A parachute is allowed and highly recommended. Include a spill

hole to reduce swaying.

5 The container shall not have any sharp edges to cause it to get stuck in the rocket payload section.

6 The container shall be a florescent color, pink or orange.

7 The rocket airframe shall not be used to restrain any deployable parts of the CanSat.

8 The rocket airframe shall not be used as part of the CanSat operations.

9 The CanSat (container and glider) shall deploy from the rocket payload section.

10 The glider must be released from the container at 400 meters +/- 10 m.

11The glider shall not be remotely steered or autonomously steered. It must be fixed to glide in a preset circular pattern of no greater than

1000 meter diameter. No active control surfaces are allowed.

12 All descent control device attachment components shall survive 30 Gs of shock.

13 All descent control devices shall survive 30 Gs of shock.

CanSat 2016 PDR: Team 8008 AGH Skydivers

Page 46: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

Discussion of what worked and

what didn't

46Presenter: Weronika Mrozińska

ID Requirement

14 All electronic components shall be enclosed and shielded from the environment with the exception of sensors.

15 All structures shall be built to survive 15 Gs acceleration.

16 All structures shall be built to survive 30 Gs of shock.

17 All electronics shall be hard mounted using proper mounts such as standoffs, screws, or high performance adhesives.

18 All mechanisms shall be capable of maintaining their configuration or states under all forces.

19 Mechanisms shall not use pyrotechnics or chemicals.

20Mechanisms that use heat (e.g., nichrome wire) shall not be exposed to the outside environment to reduce potential risk of setting vegetation

on fire.

21 During descent, the glider shall collect air pressure, outside air temperature, and battery voltage once per second.

22 During descent, the glider shall transmit all telemetry at a 1 Hz rate.

23Telemetry shall include mission time with one second or better resolution, which begins when the glider is powered on. Mission time shall be

maintained in the event of a processor reset during the launch and mission.

24 XBEE radios shall be used for telemetry. 2.4 GHz Series 1 and 2 radios are allowed. 900 MHz XBEE Pro radios are also allowed.

25 XBEE radios shall have their NETID/PANID set to their team number.

26 XBEE radios shall not use broadcast mode.

CanSat 2016 PDR: Team 8008 AGH Skydivers

Page 47: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

Discussion of what worked and

what didn't

47Presenter: Weronika Mrozińska

ID Requirement

27 The glider shall have an imaging camera installed and pointing toward the ground.

28 The resolution of the camera shall be a minimum of 640x480 pixels in color.

29 Cost of the CanSat shall be under $1000. Ground support and analysis tools are not included in the cost.

30 Each team shall develop their own ground station.

31 All telemetry shall be displayed in real time during descent.

32 All telemetry shall be displayed in engineering units (meters, meters/sec, Celsius, etc.)

33 Teams shall plot data in real time during flight.

34 The ground station shall include one laptop computer with a minimum of two hours of battery operation, xbee radio and a hand held antenna.

35The ground station must be portable so the team can be positioned at the ground station operation site along the flight line. AC power will

not be available at the ground station operation site.

36 Both the container and glider shall be labeled with team contact information including email address.

37The flight software shall maintain a count of packets transmitted, which shall increment with each packet transmission throughout the

mission. The value shall be maintained through processor resets.

38 No lasers allowed.

39The glider must include an easily accessible power switch which does not require removal from the container for access. Access hole or

panel in the container is allowed.

CanSat 2016 PDR: Team 8008 AGH Skydivers

Page 48: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

Discussion of what worked and

what didn't

48Presenter: Weronika Mrozińska

ID Requirement

40 The glider must include a battery that is well secured to power the glider.

41 Lithium polymer cells are not allowed due to being a fire hazard.

42 Alkaline, Ni-MH, lithium ion built with a metal case, and Ni-Cad cells are allowed. Other types must be approved before use.

43 The glider shall receive a command to capture an image of the ground and store the image on board for later retrieval.

44 The telemetry shall indicate the time the last imaging command was received and the number of commands received.

45The glider vehicle shall incorporate a pitot tube and measure the speed independent of GPS. The speed shall be compared with GPS

speed.

46 The glide duration shall be as close to 2 minutes as possible.

47 The CanSat shall have a payload release override command to force the release of the payload in case the autonomous release fails.

48 A buzzer must be included that turns on after landing to aid in location.

49 Glider shall be a fixed wing glider. No parachutes, no parasails, no autogyro, no propellers.

CanSat 2016 PDR: Team 8008 AGH Skydivers

Page 49: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want)

Discussion of what worked and what

didn't

49Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

Container descent control system worked. Descent was stable and within assumed speed limit

CanSat structure survived touchdown without any damage

System of wings unfolding worked- telescopic carbon rods were extended

Buzzer worked and helped to easily recover the CanSat

Autonomous fly state detection worked. Fly software was able to detect: rocket fly, descent, deployment from the rocket, touchdown, separation and camera state

Sensor worked perfectly

Sending of photo didn’t disturbed telemetry transmission

Photo was sent using same Xbee as for telemetry

Separation mechanism worked - string was cut on altitude of 407,6m

GS application worked perfectly. Data was plotted in real time and fly software states were displayed on the front panel

Telemetry worked flawlessly, not even single package was lost

Antenna gun-like holder help to maintain successful communication

Professional short coaxial antenna cable ensure small power loss during communication

None of the environmental protection elements was damaged

SV release from the container

Page 50: AGH University of Science and Technology PFR

Team Logo

Here

(If You Want) Conclusions

50Presenter: Weronika Mrozińska CanSat 2016 CDR: Team 8008 AGH Skydivers

All of the subsystems and mechanisms worked

Dedicated container should be used

The CanSat is able to be launched agained

Thank you for the great competition!