Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
AFRICAN DEVELOPMENT BANK
SWAZILAND
LOWER USUTHU SMALLHOLDERS IRRIGATION PROJECT II – (LUSIP II)
APPRAISAL REPORT
OSAN DEPARTMENT
April 2016
Publi
c D
iscl
osu
re A
uth
ori
zed
Publi
c D
iscl
osu
re A
uth
ori
zed
Auth
ori
ezd
Auth
ori
zed
TABLE OF CONTENTS
I – STRATEGIC THRUST & RATIONALE ........................................................................... 1
1.1 Project linkages with country strategy and objectives ......................................................... 1
1.2. Rationale for Bank’s involvement ...................................................................................... 2
1.3. Donor coordination ............................................................................................................. 2
II – PROJECT DESCRIPTION ................................................................................................. 3
2.1. Project components ............................................................................................................. 3
2.2. Technical solution retained and other alternatives explored…………………………… 3
2.3. Project Type ……………………………………………………………………………...4
2.4. Project cost and financing arrangements………………………………………………….4
2.5. Project’s target area and population ................................................................................... 5
2.6. Participatory process for project identification, design and implementation……………..6
2.7. Bank Group experience, lessons reflected in project design .............................................. 6
2.8. Key performance indicators ................................................................................................ 8
III – PROJECT FEASIBILITY ................................................................................................. 8
3.1. Economic and financial performance ................................................................................. 8
3.2. Environmental and Social impacts ..................................................................................... 9
IV – IMPLEMENTATION ..................................................................................................... 13
4.1. Implementation arrangements .......................................................................................... 13
4.2. Monitoring ........................................................................................................................ 14
4.3. Governance ....................................................................................................................... 15
4.4. Sustainability .................................................................................................................... 16
4.5. Risk management .............................................................................................................. 16
4.6. Knowledge building .......................................................................................................... 17
V - LEGAL INSTRUMENTS AND AUTHORITY…………………………………………17
5.1. Legal instrument ............................................................................................................... 17
5.2. Conditions associated with Bank’s intervention ............................................................... 17
5.3. Compliance with Bank Policies ........................................................................................ 18
VI – RECOMMENDATION ................................................................................................... 18
Appendix I: Map of the Project Area……………………………………………………….. I
Appendix II. Swaziland’s Socio-Economic Indicators………………………………………..II
Appendix III: AfDB Portfolio in Swaziland (March 2015).......................................................III
Appendix IV: SWADE Organogram………………………………………………………………….......IV
Currency Equivalents
As of November 2015
1 UA = 1.39687 USD
1 UA = 19.2806 ZAR (SZL)
1 USD = 13.80272 ZAR (SZL)
Fiscal Year
1 April – 31 March
Weights and Measures
1metric tonne = 2204 pounds (lbs)
1 kilogramme (kg) = 2.200 lbs
1 metre (m) = 3.28 feet (ft)
1 millimetre (mm) = 0.03937 inch (“)
1 kilometre (km) = 0.62 mile
1 hectare (ha) = 2.471 acres
i
Acronyms and Abbreviations
ACMS Aid Coordination and Management Section in Ministry of Econ. Planning
AfDB African Development Bank
ADEMU Agricultural Development and Environmental Management Unit (LUSIP 1)
EIB European Investment Bank
EIRR Economic Internal Rate of Return
ESIA Environmental and Social Impact Assessment
EU European Union
FAO Food and Agricultural Organization
FA Farmers' Association
GoS Government of Swaziland
IFAD International Fund for Agricultural Development
IRR Internal Rate of Return
ITF Individual Tenure Farms
KDDP Komati Downstream Development Project
LUSIP Lower Usuthu Smallholder Irrigation Project
MCM Million cubic meters
MDG Millennium Development Goal
MNRE Ministry of Natural Resources and Energy
MOA Ministry of Agriculture
NASWG National Agriculture Sector Working Group
NGO Non-Governmental Organization
NLP National Land Policy
NDS National Development Strategy
NEPAD New Partnership for Africa’s Development
PRSAP Poverty Reduction Strategy and Action Plan
SADC Southern African Development Community
SARC Southern Africa Resource Center
SEA Swaziland Environment Authority
SNC Swaziland National Council
SNL Swazi Nation Land
SSA Swazi Sugar Association
SWADE Swaziland Water & Agricultural Enterprise Ltd.
WUA Water Users Association
ii
Loan Information
Client’s information
BORROWER: Kingdom of Swaziland
EXECUTING AGENCY: Swaziland Water and Agriculture Development Enterprise
(SWADE)
Financing plan
Source Amount
(ZAR’000)
Amount
(UA’000)
Instrument
ADB 855,131
44,353
Loan
EIB 498,958 25,880 Loan
BADEA, KF 437,560 22,695 Loan
Government 216,330 11,220 Counterpart
TOTAL COST 2,007,979 104,148
ADB’s key financing information
Loan Currency South African Rand (ZAR)
Loan Type Fully Flexible Loan
Interest Rate Base Rate +Funding Cost Margin+ Lending
Margin + Maturity Premium Base Rate
Floating Base Rate based on 3-month JIBAR
Funding Cost Margin1 Refer to footnote
Lending Margin 60 basis points (0.6%)
Maturity Premium2
Fees None
Tenor Up to 24 years inclusive of Grace Period
Grace period 5 years
Average Loan Maturity 14.75 years
EIRR (base case) 10.6%
1 The six months adjusted average of the difference between: (i) the refinancing rate of the Bank as to the borrowings linked to the Floating
Base Rate and allocated to all its floating interest loans denominated in the Loan Currency and (ii) the Floating Base Rate for each semester
ending on 30 June and on 31 December. This spread shall apply to the Floating Base Rate which resets on 1 February and on 1
August. The Funding Cost Margin shall be determined twice per year on 1 January for the semester ending on 31 December and on 1 July
for the semester ending on 30 June.
2 The Maturity Premium is based on the Average Loan Maturity, which is defined as the weighted average time to repay a loan, calculated as
the average number of years until each principal repayment amount of the loan is due, weighted by the principal repayment amounts. Loans
with – an Average Loan Maturity less than or equal to 12.75 years will incur no (Nil) Maturity Premium; an Average Loan Maturity greater
than 12.75 years and up to 15 years will incur 10 bps (0.10%) Maturity Premium; an Average Loan Maturity greater than 15 years and up to
17 years will incur 20 bps (0.20%) Maturity Premium.
iii
Timeframe - Main Milestones (expected)
Concept Note approval 30 October, 2015
Project approval 4 May, 2016
Loan Signature 30 July 2016
Effectiveness 30 October , 2016
Closing Date 31 December, 2021
Completion 30 September, 2021
Last repayment 30 December, 2036
iv
Project Summary
1. Project Overview
1.1 The Swaziland- Lower Usuthu Smallholder Irrigation Project Phase II (LUSIP-II), is a follow-up
project to the LUSIP-I which was approved on 27 November 2003 (and completed in 2010) as a response
to the Government’s recognition that the natural resources potential of the Lower Usuthu River Basin
provided an excellent opportunity for effective integration of poor smallholder farmers on Swazi Nation
Land into the commercial agriculture sub-sector. The plan for the entire LUSIP is to divert part of the
peak flow of the Usuthu River into a 155 million m³ capacity off-river storage reservoir to be used to
irrigate 11,500 ha (in two phases) of downstream land to grow sugarcane. The overall objective of the
LUSIP project is to increase household income, enhance food security and improve access to social and
health infrastructure for the rural population by creating the conditions for the transformation of
subsistence level smallholder farmers into small-scale commercial farmers. The second phase of the
project (LUSIP-II) has four main components: (1) Main Conveyance System; (2) Secondary System; (3)
On Farm Infrastructure Development (New Area) – LUSIP II; and (4) Project Management and
Engineering Supervision.
1.2 The overall benefits of the project will include an increase in the agricultural production, improved
production infrastructure, environmental and natural resources conservation and capacity building of
beneficiaries in various aspects of agricultural production, environment and natural resources
management and entrepreneurship. The project will contribute to poverty reduction in the project target
region. Indeed, increased production will lead to higher incomes for producers and improve their social
and economic well-being. It will also contribute to raising agricultural productivity and growth in the
agriculture sector, and significantly increase the food and nutritional security and incomes of the 2,259 (at
least 50% women) additional rural households. The project will transform about 5217 hectares of land
from its present use of semi-subsistence level farming into diversified commercial cash and food
cropping.
2. Cost and Financing
The total cost of LUSIP II is estimated at ZAR 2.01 billion (UA104.15 million), to be financed by
the African Development Bank (AfDB) - ZAR 855.131 million (UA44.35 million); European Investment
Bank -ZAR 498.958 million (UA25.88 million); Kuwait Fund and BADEA – ZAR 437.56 million (UA
22.69 million); and the Government of Swaziland – ZAR 216.33 million (UA 11.22 million). AfDB will
finance the Main Conveyance System (Component 1) of the project.
3. Implementation
The Project will be implemented by the Swaziland Water and Agricultural Development
Enterprise (SWADE), a parastatal established by the Government of Swaziland in 1999 to facilitate the
planning and implementation of the Komati Downstream development Project (KDDP) and Lower
Usuthu Smallholder Irrigation Project (LUSIP), and any other large water and agricultural development
project that the Government may assign. It has successfully implemented the KDDP and the LUSIP-I. It
will be responsible for the design and technical supervision of the project activities in addition to the
procurement, financial management and Monitoring and Evaluation (M&E) of the project. The Project
will be implemented in five years (2016 – 2021).
v
4. Bank’s Added Value
The Bank’s intervention in this project will add significant value to the investments made by the
Government of Swaziland and other development partners under LUSIP 1. LUSIP 2 is thus critical to the
country in order to efficiently utilize these investments for the purpose of intensifying agriculture under
irrigation. The project will substantially address the agricultural production constraints and development
challenges faced by the rural communities identified in the 2014 AfDB’s Swaziland Country Strategy
Paper which include: (1) limited irrigation-related infrastructure that is holding back agricultural sector’s
growth and crop diversification; (2) sources of water from some major rivers located outside the country
which necessitate the country to negotiate its water rights with other countries especially South Africa;
and (3) limited diversification of exports which substantially relies on sugar export and to a lesser extent
on the textiles and clothing industry. In line with the Bank’s Ten Year Strategy, 2013-2022, the Bank’s
intervention will have the multiplier effect of economic development through infrastructure development.
By introducing bananas, maize, and beans into crops mix, in addition to the sugar production, the project
will contribute directly to meeting four major components of the “High 5” (feed Africa, industrialize
Africa, integrate Africa (through regional sugar exports) and improve the quality of life of the African
people through increased cash incomes from sugar sales.
5. Knowledge Management
The knowledge gained through the implementation of several projects and studies in the sector in
Swaziland has been duly applied in designing this project. In the same pattern, the knowledge that will be
generated by this Project will be instrumental in designing and managing subsequent phases of the LUSIP
and other new projects. The results from the various and other surveys, including the socio-economic
impact study and EIAs will inform the stakeholders on how to put the acquired knowledge attributes into
practical use for better results-oriented achievements and sustained benefit flows.
vi
RESULTS-BASED LOGICAL FRAMEWORK
Country and project name: Swaziland Lower Usuthu Smallholder Irrigation Project II (LUSIP - II)
Purpose of the project: To alleviate poverty in the project area
RESULTS CHAIN
PERFORMANCE INDICATORS MEANS OF
VERIFICATION RISKS/MITIGATION MEASURES
Indicator
(including CSI) Baseline Target
IMP
AC
T
Impact
Improved standard of living of
the population in the LUSIP-II
project area
Increase in average income of
farmers under the scheme)
No of beneficiary households
1.1 Household
income = SZL 5,000
1.2 No of beneficiary
households = 0
1.1 House hold income of SZL
32,940. (2020)
1.2 No of Beneficiary
households = 2,259
1.Case studies
2.SWADE reports
OU
TC
OM
ES
Outcome 1: Increased crop
production.
1. 1 Crop output
Total Production
a. Sugar cane= 0 mt
b. Banana = 0 mt
c. Maize = 0 mt
d. Sugar Bean = 0 mt
Total Production (2020)
Sugar cane = 440,000 mt
Banana = 14,790 mt
Maize = 5,792 mt
Sugar Bean = 1,622 mt
1.Ministry of Agric
Survey.
2.SWADE Progress
Reports
Risk: Reduction in water availability for
irrigation
Mitigation: Project area covered by Tripartite
Water Usage Agreement.
Risk: Fluctuations in Price of Sugar:
Mitigation: Crop Diversification
OU
TP
UT
S
Component 1
Main Conveyance System;
1 Siphon 1,
1.2 Lined main canal,
Five Bulk storage reservoirs
1.3 SCADA system
- 5,988m long
- 33,262m long
- Five reservoirs built
- 1 System installed
SWADE Progress
Reports
Risk: Project cost overruns due to the rise in the
cost of materials due to rising costs of raw
materials may lead to cost increases.
Mitigation: Efficient procurement timing to
address the increases, as well as adequate price
contingencies for the unavoidable increases will
mitigate the risk.
OU
TP
UT
S
Component 2
Secondary System;
Outputs
2.1 Distribution system
LUSIP2 incl. roads and
drainage systems;
2.2 Pump stations (irrigation)
including power lines and
transformers;
Distribution network
Bulk pump station and rising
mainline DN 1,200 mm
- Distribution system for the
Matata Block including
roads and drainage
systems
- Bulk pump station and DN
1,200mm pipeline
(1,081m)
SWADE Progress
Reports
vii
OU
TP
UT
S
Component 3
On Farm Development
Infrastructure
Size of Area developed for
cropping
Road network
Pipe systems and center
pivot or semi-solid
sprinkler systems,
Land preparation and
levelling for a total
5,217ha.
SWADE Progress
Reports
OU
TP
UT
S
Component 4 Project
Management and Engineering
Supervision
- No of design review report
- No of construction supervision
reports
- No of people resettled
- No of community mobilized = -
- No of Farmer companies
formed
– No of Quarterly Progress
Reports produced
- No of Annual Audited
Accounts produced
- 1 Design review report
- 4 quarterly reports
- 22 households
- 3 chiefdoms
- 10 farmer companies
- 4 per year
- 1 per year
SWADE Progress
Reports
Risk: Delay in providing counterpart funding by
Government
Mitigation: The Bank and the DP are for
infrastructure development. SWADE is well
staffed to manage the project, and GKOS has
given commitment make sufficient provision in
the Annual Budget.
Risk: Ineffective and uncoordinated project
supervision among financiers
Mitigation: Parallel financing; and project
activities are not required to start and end at the
same time.
KE
Y
AC
TIV
ITIE
S COMPONENTS INPUTS
Component 1
Component 2
Component 3
Component 4
Component 1 – ZAR 855.131 million (UA 44.36 million)
Component 2 – ZAR 498.958 million (UA 25.88 million)
Component 3 – ZAR 458.902 million (UA 23.80 million)
Component 4 - ZAR 194.986 million (11.22 million)
TOTAL ZAR 2,007.977 million (UA 104.15 million)
LUSIP II IMPLEMENTATION SCHEDULE Year 2015 2016 2017 2018 2019 2020 2021
Quarter 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Initial Activities
Appraisal
Loan and Grant negotiations and approval
Signature of loan agreement and fulfilment of first disbursement conditions
Publication of the General Procurement Notice
Project Launching
Procurement of property goods works and services for the PIUs / PCUs/First Disbursement
Construction of Irrigation Infraatructure
Award of contracts for the construction of infrastructure
Construction infrastructure/management committee
Project Management and Monitoring
Mnagement and monitoring
Mid Term Review
Project Completion
Disbursement Deadline
1
REPORT AND RECOMMENDATION OF THE MANAGEMENT OF THE AFDB
GROUP TO THE BOARD DIRECTORS ON A PROPOSED LOAN TO THE
KINGDOM OF SWAZILAND FOR LOWER USUTHU SMALLHOLDERS
IRRIGATION PROJECT II (LUSIP II)
Management submits the following Report and Recommendation on a proposed ADB loan of
ZAR855.13 million to finance the Lower Usuthu Smallholders Irrigation Project II (LUSIP
II) in Swaziland.
I STRATEGIC THRUST & RATIONALE
1.1 Project linkages with country strategy and objectives
1.1.1 The Swaziland Country Strategy Paper (CSP) 2014-2018 was approved by the Bank’s
Boards of Directors on April 22, 2014. The pillars of this strategy revolve around (i)
Supporting Infrastructure Development for Sustainable and Inclusive Growth and (ii)
Strengthening Governance and Institutional Capacity. Within the context of these two
themes, the CSP activities have been grouped into four “results clusters” – (1) Smallholder
Irrigation Infrastructure, (2) Water and Sanitation, (3) Transport infrastructure, and (4)
Governance - that take into account cross-sectoral synergies for maximum impact. The
activities in the proposed project are consistent with two of the Bank’s core operational
priorities (infrastructure and governance) and are aimed at supporting Swaziland achieve
high, inclusive, and sustainable growth. Despite the lack of an overall agricultural strategy in
the country, there are a number of policies in place, which have been developed over the
years. At national level, there is the National Development Strategy (NDS) (1997-2022),
Poverty Reduction Strategy and Action Plan (PRSAP), Programme of Action (2013-18) and
the Economic Recovery Strategy (ERS). In addition, there are a number of polices in place
addressing specific agricultural policy issues, which include: (i) a Comprehensive
Agricultural Sector Policy (CASP); (ii) National Food Security Policy; (iii) Livestock
Development Policy; (iv) Draft Land Policy; (v) National Forestry Policy; (vi) Resettlement
Policy; (vii) Swaziland National Irrigation Policy, (viii) Agricultural Diversification Strategy,
(ix) National Agricultural Research Policy, and (x) National Agriculture Investment Plan.
There are also supportive legislations and regulations, which enforce these polices especially
for animal health, plant health and water use and quality. Overall, the project is linked with
these policies and at completion it is expected to achieve the commercialization of
smallholder farming, enhanced productivity, agricultural diversification and food security,
and broader economic participation of rural communities and reducing poverty.
1.1.2 The first phase of the Lower Usuthu Smallholder Irrigation Project (LUSIP), which
was initiated in 1999 was supported by a group of donors that included AfDB, European
Union, IFAD, DBSA and BADEA. LUSIP is a significant part of the government water
management programmme to optimize the usage of the Usuthu River. Besides the AfDB,
LUSIP II has attracted other financiers such as the European Investment Bank, BADEA and
the Kuwait Fund. The proposed project which is a continuation of the LUSIP I will, among
other outcomes, deepen efficient water resources management through optimal use of the
facilities constructed under the first phase. The project will stimulate growth in the economy
through higher production, provision of job opportunities and increased income.
2
1.2 Rationale for Bank’s involvement
1.2.1 The Bank’s Ten Year Strategy (TYS) 2013-2022, identifies agriculture related infrastructure
development as a key factor in improving agricultural production, and agriculture and food security as
areas of special emphasis. The Bank’s 2014-2018 Gender Strategy calls for economic empowerment,
knowledge and capacity building for women. This project addresses all of these key Bank strategies and
policies in the areas of moving agriculture from development to commercialization and business
ownership, crop diversification, income enhancement, as well as more participation of rural dwellers in
economic activities. In addition, through the activities mentioned above, the proposed project is in
consonance with the three out of the Bank’s ‘High 5’ i.e. “Feed Africa”, “Integrate Africa”, and
“Improved the quality of lives of people of Africa”. The project, by diversifying into other crops, will also
achieve sustainable incomes for the beneficiaries in particular and the country at large.
1.2.2 The Bank has been active in Swaziland agriculture sector for many years. It has financed various
operations in Swaziland among which are: Ngwavuma Irrigation Study, Swaziland Sugar Project (1982),
On-Lending Agricultural Line of Credit to Swaziland Development And Savings Banks (1992), Lower
Usuthu Irrigation Project I (LUSIP I) which was completed in 2010, and the Komati Downstream
Development Project, which closed in 2011.
1.3 Donor coordination
Donor Support to Agriculture (2014/15)
Sector or subsector* Size
GDP Exports Labour Force
Agriculture (including
fisheries and forestry) 8.6% 27% 70%
Players - Public Annual Expenditure (average) : Budget
Government Donors EU 57%
USDm USD 37.8 m USD 12.2 m Taiwan 19%
% 76% 24% FAO 27%
Level of Donor Coordination
Existence of Thematic Working Groups (this sector/sub-sector) [Yes]
Existence of SWAps or Integrated Sector Approaches [No]
ADB's Involvement in Donors Coordination [Co-Leader]
Source ACMS (MoDP); Preliminary Estimates- External Assistance to Swaziland
1.3.1 Donor coordination is evolving in Swaziland, similar to the other middle-income countries in the
region. The AfDB played a key role in galvanizing donor support reforms in Swaziland. The Bank
supported the strengthening of the Aid Coordination and Monitoring Section (ACMS) in the Ministry of
Economic Planning and Development in 2009, which improved coordination of development assistance
and ensured country ownership.
1.3.2 At the agriculture sector level, the key Development Partners with on-going operations in the
sector are the AfDB, the European Union (EU), OPEC/OFID, Taiwan, World Food Program (WFP) and
the Food and Agriculture Organization (FAO). The Bank assisted in the establishments of the National
Agriculture Sector Working Group (NASWG), which the Bank is co-leading with the Government. The
Government is in the process of formalizing the National Taskforce, which is currently working on the
preparation of the Comprehensive Africa Agriculture Development Program (CAADP) documents into
the NASWG. The Bank has also been appointed the Lead Partner for the coordination of the donors for
the LUSIP-II Project.
1.3.3 The EU is currently supporting the Swaziland Agricultural Development Programme, which
ended in 2015. The EU has also earmarked 40 million Euros for the agriculture sector under EDF 11
Programme, which will target improvement of the horticulture value chains development and capacity
building among other key agricultural development initiatives in Swaziland. WFP has continued to pursue
3
its mandate of ensuring that people have access to adequate and decent food. There has been a gradual
shift of resources from relief to recovery-related activities which aimed at enhancing development rather
than creating dependency. The FAO has most of its interventions in the country falling under its
Technical Cooperation Programme (TCP). TCP projects are short-term in nature. The FAO also assists
the government in implementing emergency programmes aimed at addressing the drought problem.
II PROJECT DESCRIPTION
The objective of the project is to alleviate poverty in the project area by transforming the existing
subsistence farmers into commercial farmers on irrigated lands producing both food and cash crops
(principally sugarcane). It is to support the development and utilization of the water resources of the
Lower Usuthu River through provision of irrigation infrastructure to enable smallholder farmers to
intensify and diversify their agricultural production building on existing market linkages with the private
sector. It is also aimed at establishing an effective management of infrastructure and equipment for the
sustainable improvement of production and cost recovery.
2.1 Project Components
2.1.1 The LUSIP Phase II has four main components, namely: (i) Development of the Main
Conveyance System (MCS); (ii) Development of Secondary Irrigation Pipe Network supplying the
different irrigation blocks, each covering 100-700 ha; (iii) On Farm Infrastructure Development; and (iv)
Project Management and Engineering Supervision.
2.1.2 A summary of the project components are as follows:
Table 2.1: Project Components
Component name Est. cost
(ZAR million)
Component Outputs
1. Main
Conveyance
System;
855 Siphon 1,
Lined main canal,
Five bulk storage reservoirs
SCADA management system
2. Secondary
System
499
Distribution system LUSIP2 incl. roads and drainage systems;
Pump stations (irrigation) including power lines and transformers;
3. On Farm
Development
Infrastructure
459 Road network
Pipe systems and centre pivot or semi-solid sprinkler systems,
Land preparation and levelling
3. Project
Coordination and
Management
216 Design review and construction supervision
Resettlement and impact mitigation
Community mobilization, setting up of farming companies
Capacity building
Administrative and Financial Reporting M&E
Budget preparation and work programme and Audit
Total 2,008
2.2. Technical solution retained and other alternatives explore
2.2.1 The Main Canal South was constructed as part of LUSIP I project. The canal discharge was
calculated to convey water for only 5,217 ha of new development in addition to 455 ha of existing
plantation in the LUSIP 2 area. The GoS intends to include the Nsoko-Msele Block (4090 ha), Poortzicht
Scheme (750 ha) and Riverside Scheme (1000 ha) to the project which entails increasing the Main Canal
South capacity to accommodate such an extension.
4
The only viable solution is to raise the sides of the canal to increase the discharge, which would render
the project not economically viable, as the Nsoko-Msele Block is not ready for development now.
Therefore, it was agreed to maintain the Irrigation Canal South without remodelling.
Table 2.2: project alternative considered and reason for rejection
Alternative name Brief Description Reasons for Rejection
Raising of existing Main
Canal South
Canal sides raised to
accommodate water for
the Nsoko-Msele Block.
Increased cost makes the project
economically non-viable. The
increase will be included under
future phases if viable.
Conveyance system
downstream Main Canal
South
Open channel system to
supply water to LUSIP II
Matata Block and others
High cost of cut and fill in a
mountainous terrain.
2.3 Project type
LUSIP II is a stand-alone investment Project aimed at increasing agricultural production and incomes of
households in the Lower Usuthu River Basin. Like its predecessor (LUSIP I), the Lower Usuthu
Smallholders Irrigation Project is being jointly financed as an evidence of collaboration and leveraging
of expertise among the development partners (AfDB, EIB, KW and BADEA) involved in the project
financing.
2.4 Project Cost and financing arrangements
2.4.1 The total project cost, including physical and price contingencies, is estimated at ZAR 2.01 billion
(UA 104.15 million) net of taxes and duties. The price contingencies were based on projected local and
foreign inflation rates of 5% and 2% per annum, respectively. The physical contingencies ranged from
0% (consultants’ salaries) to 10% (works) based on common technical practices. This will be financed by
(i) AfDB Loan of ZAR 855.13 million (UA 44.35 million -42%) covering the cost of the Main Canal
System (Component 1); (ii) European Investment Bank loan of ZAR 498.958 million (UA 25.88 million -
25%) (Component 2); (iii) BADEA and Kuwait Fund Loans of ZAR437.56 million (UA 22.69 million-
22%) (Component 3); and Government counterpart contribution of ZAR 216.33 million (UA 11.22
million – 11%). The Government’s contribution will finance the cost of the Project Management
Component to the tune of ZAR 194.99 million (UA 10.11 million -10%), and a fund shortfall of ZAR
21.34 million (UA 1.11 million -1%) under Component 3. Summaries of the project costs by
components, sources of financing and schedule by component are presented in Tables 2.3 to 2.7. All the
donors have committed to parallel financing of the project.
Table 2.3: Project Cost Estimates by Component
Components ZAR '000 UA '000 Foreign
Exchange
Local Foreign Total Local Foreign Total (%)
1. Main Canal System 134,610 538,440 673,050 6,982 27,927 34,909 80%
2. Secondary supply system 77,400 309,600 387,000 4,015 16,058 20,073 80%
3. On farm development 72,267 289,069 361,337 3,748 14,993 18,742 80%
4. Project management 17,200 154,800 172,000 892 8,029 8,921 90%
Sub-Total 301,477 1,291,909 1,593,387 15,637 67,008 82,645
Physical Contingency 22,623 96,947 119,570 1,173 5,028 6,202 81%
Price Contingency 55,819 239,201 295,021 2,895 12,407 15,302 81%
Total 379,920 1,628,057 2,007,977 19,705 84,443 104,148
5
Table 2.4:Sources of Finance
Source of Financing UA '000
Local Foreign Total %
AfDB 8,871 35,482 44,353 43%
EIB 5,176 20,704 25,880 25%
BADEA/Kwuati Fund 4,536 18,159 22,695 22%
Govt of Swaziland 1,122 10,098 11,220 11%
Total 19,705 84,443 104,148 100%
Table 2.5 : Total Project Cost By Year (ZAR'000)
Components Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Total
1. Main Canal System - 128,270 205,231 307,847 213,783 - 855,131
2. Secondary supply system - 49,896 124,740 199,583 124,740 - 498,958
3. On farm development - - - 114,726 206,506 37,671 458,902
4. Project management 37,047 40,947 29,248 29,248 29,248 29,248 194,986
Total 37,047 219,112 359,219 651,404 574,276 166,919 2,007,977
Table 2.6: Project Cost Estimates by AfDB Financed Component
Component ZAR '000 UA '000
Local Foreign Total Local Foreign Total
Main Canal System
- Civil Works 132,610 530,440 663,050 6,878 27,512 34,391
- SCADA System 2,000 8,000 10,000 104 415 519
Sub-total 134,610 538,440 673,050 6,982 27,927 34,909
- Physical Contingency 13,461 53,844 67,305 698 2,793 3,491
- Price Contingency 22,955 91,821 114,776 1,191 4,762 5,953
Total 171,026 684,105 855,131 8,871 35,483 44,353
Table 2.7: Project Cost Estimates by AfDB Financed Component/Expenditue Category (Incl Contingencies)
Component ZAR '000 UA '000
Local Foreign Total Local Foreign Total
Main Canal System
- Civil Works 168,485 673,940 842,426 8,739 34,955 43,694
- SCADA System 2,541 10,164 12,705 132 527 659
Total 171,026 684,105 855,131 8,871 35,483 44,353
2.5 Project’s target area and population
2.5.1 Location: The project is located in the lower Usuthu area about 120 km from Mbabane. It is
naturally divided into Bovane Block consisting of 9,280 hectares and the Matata Block 7,120 hectares.
The LUSIP II area will have a gross area of 6,033 ha and a net area of 5,672 ha, with 5217ha to be
developed under the project. Therefore, the proposed on-farm development works will include 5,217 ha
of irrigation blocks. The communities under the project area are Matsenjwa, Mngometulu and
Ngcamphalala. There are adequate social and health services in the project area. The project
infrastructure allows for future expansion to the Nsoko-Msele Block of (4000 ha), Poortzicht Scheme
(750 ha) and Riverside Scheme (1000 ha) by raising the sides of the Main Canal South and installation of
a parallel syphon.
6
2.5.2 The mean annual rainfall ranges from 440 mm to 570 mm and the mean annual evapo-
transpiration is 2,057 m. About 70% of the annual rain fall within the hot summer rainy season from
October to March. The mean annual temperature in winter ranges from a minimum of 5° C to a maximum
of 20° C. Vegetation in the project area consists mainly of mixed tree and bush Savanah with mainly
Acacia species. Forests and woodlands are also found in the area.
2.5.3 The Soils: Different scenarios for development of land for irrigated sugarcane were analysed for
the LUSIP 2 area, with the most promising resulting in the availability of a total net area of approximately
5,672ha (455ha existing and 5,217ha new land), with 3,399 ha below the main conveyor and 2,273 ha
above the conveyor. In terms of suitability, half of this is suitable land, a quarter marginally suitable land,
with the remainder either being semi suitable or conditionally suitable.
2.6 Participatory process for project identification, design and implementation
2.6.1 The GOS has undertaken an extensive and unique participatory approach in the LUSIP area from
the very initial stages. It started extensive consultations with the communities in the area since 1998 and
this led to the establishment of various committees at the community level (e.g. women’s committees,
resource users group, water users, Zonal planning committee, and neighborhood committees). These
committees had the mandate to discuss and propose development solutions including issues relating to
resettlement, suitable and preferred crops, livestock grazing area etc. LUSIP participation process has
therefore had a strong bottom-up approach. These structures have been maintained and constant
collaboration exists. Consequently, the established participatory process will continue throughout the
implementation of the project through the involvement of the various committees.
2.6.2 A project steering committee and a project technical committee are in place and the relevant
stakeholders including representatives of the 3 affected chiefdoms are members. Women participation
was encouraged and representation was as high as 30%. The successful implementation of LUSIP I has
provided the Government of Swaziland and SWADE with a positive experience in a demand-driven
project and has increased the desire of beneficiaries to fully participate and engage in commercial
farming. SWADE technical team coordinated the stakeholder consultations, community mobilisation and
sensitisation during development of the LUSIP I, through LUSIP 2 identification, preparations and
appraisal processes. Consultative meetings were held with key stakeholders including Cooperating
Partners, Farmers Union, Local Commercial Banks and Credit Union, Sugar Association, National Maize
Corporation and other Private Sector units in the area to refine the project concept and design.
Preparation of the ESIA also went through the same process. As in LUSIP 1, mechanism for continuous
engagement with the stakeholders during the project implementation is already in place.
2.7 Bank Group experience, lessons reflected in project design
2.7.1 The Bank Group has 5 ongoing operations in Swaziland valued at UA 51.7 million. There are no
ongoing operations in the Agricultural Sector. The current portfolio is dominated by the transport sector
representing over 65 % of the entire portfolio followed by water and sanitation (31.5%), multi-sector (1.8
%) and power (1.4%). The portfolio is rather young with the oldest ongoing project approved in 2011.
The average age of the current portfolio is 2.2 years way below the Bank’s average. The overall
disbursement rate stands at only 1.13 % mainly due to the approval of the 3 new operations in 2014.While
there is no projects at risk, 2 projects experiencing issues related to slow disbursement and effectiveness
were highlighted in the portfolio flashlight (Statistical Capacity Building Programme - Phase II (SCB II)
and Energy Sector Technical Assistance Program).
2.7.2 In November 2003, the AfDB approved LUSIP 1 with a total cost of UA 85.39 Million out of which
the AfDB Group Loan was UA 9.31 Million (Rand 98.49 million) of ADB Resources. Other Sources of
Finance were, (1) BADEA - UA 8.05 million, (2) The EU - UA 8.27 million, (3) DBSA - UA 10.61
million, (4) IFAD - UA 13.15 million, (5) EIB - UA 18.67 million, (6) GOS - UA 13.79 million, and (7)
Beneficiaries - UA 3.54 million.
7
2.7.3 Apart from minor delays due to the consultation with communities, the project went on smoothly
and did not experience undue delays. The construction of infrastructure (concrete diversion weir, feeder
canal, Reservoir, and dams) was completed as per the desired quality. The PMU was able and
coordinated the implementation of project activities efficiently. The Bank and the Borrower ensured good
compliance with safeguards by implementing a Resettlement Plan and monitoring the Health care
delivery, water and sanitation facilities and impact of civil works. Box 1 below presents achievements of
LUSIP I.
2.7.4 In addition, the Bank’s knowledge work, such as the Fiscal Adjustment Roadmap (FAR) and the
Economic Diversification Study (EDS), have provided a better understanding of bottlenecks in policy and
program implementation. Institutional support activities, where the Bank and other development partners
are involved, are informed by the knowledge work. It is noted that a strong outreach and information
dissemination program to encourage debate and share information on available Bank instruments will
enhance dialogue and broaden the funding modalities in Bank interventions.
2.7.5 Swaziland has most of the institutions needed to implement economic and structural reforms but
their capacity had not been assessed. Development partners’ insistence on reform implementation without
significant institutional support and capacity building has therefore proven to be ineffective. Similar
observations have also been made at the project level, especially in critical areas such as procurement and
project management. Ensuring that prior conditions are met or that sufficient progress is made in that
regard is important in avoiding delays in project implementation after loan approval and signature.
2.7.6 Lessons drawn from the ongoing projects (six in number) and previous project completion reports
highlighted the following: (i) Participatory approach: It is imperative for a supply led irrigation to
integrate the distribution of water and associated land use within the expressed needs and preferences of
the local community and to recognise and ensure that the project addresses population needs for those
households not benefiting from access to irrigated land; (ii) an exit strategy for the project and its
management team that is based on empowering community and giving them more responsibilities in
operations and maintenance; and (iii) acknowledge the important roles played by the traditional chiefs in
land allocation as chiefs are custodians of lands under the Swazi Nation Land (SNL). These lessons
learnt have guided both the Bank and the Government in project design and will continue to guide the
implementation process of the project.
8
Box 1: Achievements of LUSIP I
1 As of December 2015 a total of 4,455ha had been developed with 4,275ha
planted with sugar cane and 180 ha developed for alternative crops.
2 A total of 91 farmer companies (which include livestock companies) with 3000
members had been established against a target of 75 with 10 water users
institutions registered against a target of 12.
3 1850 farmers out of 3000 received average of annual dividends of E35million per
annum translating to E2.7million (US$1450) per farmer in 2015.
4 The average tax revenue of government in targeted area increased from E11,
611,142.04 in 2012/13 (to E15, 002,039.48 by 2015/16.
5 The relocation of the Mahlabatsini Primary School in particular led to 16%
increase in school enrolment from 179 pupils in 2009 to an average of 207 pupils
by 2016.
6 Environmental compliance against comprehensive mitigation plan (CMP) was
achieved and a monitoring lab had been built and equipped at Siphofaneni.
7 A total of 2,186 households (84%) now have access to clean water with 2,771
households (106%) having VIP latrines against a target of 2,600.
8 Reduction in communicable and water borne deceases - Diarrhoea declined from
a prevalence of 14.3% in 2005 to zero cases reported in 2015.
2.8. Key performance indicators
2.8.1 The key performance indicators for monitoring the project achievements are identified and
captured in the results based logical framework. The key outcomes include increased crop production,
increased farmers’ income and better water management, which will result in improved standard of living
of the population in the Lower Usuthu Region. The key indicators are increased crop productivity and
increased land under irrigation. These indicators will be collected and analysed regularly by the M&E
unit of SWADE through crop trials and monitoring progress on drainage construction. The M&E unit
will collect and report data disaggregated by gender during project implementation.
2.8.2 SWADE will prepare quarterly project progress reports, presenting the progress made on
implementation and achievements on output indicators, which will be monitored through SWADE’s
management system and national statistics. Indicators will be updated in the Implementation Progress
Report (IPR) and necessary adjustments will be made as appropriate. A medium term report (MTR) and
Project Completion Report (PCR) will be prepared to provide an assessment of the project. All of these
reports will be circulated widely within the Government, the Bank and to other development partners.
III PROJECT FEASIBILITY
3.1 Economic and financial performance
Table 3.1: key economic and financial figures
FIRR, NPV (base case) 4.7% : ZAR 729.3 million
EIRR, (base case) 10.6%
Note: detailed calculations are available in Annex B6
9
3.1.1 The project is considered financially and economically viable. At full operation, each farmer
household will be making a net income of ZAR 32,940 (USD 3,100) per year. The analysis at the project
level has been carried out by comparing the project cost, on farm crop establishment and operational cost
with the benefits. It is estimated that the project will generate total net gross profit of ZAR 115 million
(USD 9.24 million) per annum at its full operational level. The discounted cash flow (DCF) analysis
carried out on the net cash-flow gave a Financial Net Present Value (NPV) of ZAR 729.3million (USD
52.82 million) at a discount rate of 4% (the average cost of borrowing).
3.1.2 In carrying out the economic analysis of the project, the financial costs and benefits streams have
been converted into their respective economic values and the discounted cash flow methodology applied
to the net cash flows. The DCF analysis carried out on the net cash-flow gave an Economic Internal Rate
of Return (EIRR) of 10.6%, with the Economic Net Present Value (ENPV) estimated at SZL 270.9
million, at a discount rate of 9%. In addition, the Government estimated that other benefits such as
employment generation, environmental benefits, and spin off effects of the investment to boosts local
economy further justify the implementation of the project. Assumptions made in the Economic Analysis
are detailed in Annex B of the Technical Annexes.
3.1.3 Sensitivity Analysis (Economic): The sensitivity analyses have been carried out under three (3)
assumptions and the results are as follows:
Table 4: Results of Discounted Cash-flow Analysis / Sensitivity Analysis
Assumptions IRR
(%)
NPV at 9% cost of
capital (SZL'000)
Base Figures 10.6% 270,863
Assumption 1: 10% increase in project costs 9.7% 135,010
Assumption 2: 10% fall in revenues 9.5% 87,880
Assumption 3: 1 Year Delay in Project Implementation 9.7% 131,365
3.2 Environmental and Social impacts
Environment
3.2.1 The project was validated as Category 2 on February 25, 2016 in line with the Bank’s
Environmental and Social Assessment Procedures (ESAP); mainly because most impacts are site specific
and have no significant and irreversible detrimental effect. The project will have both positive and
negative impacts and they differ according to the phase of the project. During construction, impacts will
include loss of grazing areas, loss of biological diversity, disruption of current household dynamics and
cultural structures, accidents and health impacts, waste generation, spillages and soil pollution,
eutrophication and water pollution, dust emissions and noise. In addition, during operation, further
impacts will emanate from construction activities that include difficulties with in-field soil & water
management, health impacts, especially with malaria and an increase in schistosomiasis, market
constraints of vegetables and other crops, sugar price instability, cane burning and its contribution to
climate change, alteration of soil quality, possible drowning of people and livestock, increased risk of
HIV/AIDS.
3.2.2 The project also brings about certain benefits that include training and capacity building of
communities, increased cropping intensity on more than 5,000 ha due to the provision of dry season
irrigation water, access to water supply, improved livestock husbandry and productivity, increased and
stabilised household incomes from agriculture for more than 2000 households, increased secondary
economic activities agriculturally-related goods and services and associated local employment, improved
institutional capacity of organisations responsible for water management and agricultural development,
improved access from constructed roads, improved gender mainstreaming initiatives, increased crop
yields and diversity due to improved drainage, inputs and crop husbandry.
10
3.2.3 Public participation is the cornerstone of the environment and social aspects of this project and it
is expected to result in the enhancement of all the identified benefits. The negative impacts will be
mitigated as outlined in the environment and social management plan (ESMP) which summary has been
posted on the Bank’s website on 26 February, 2016. Such mitigation measures include provision of waste
receptacles, identification of suitable and authorized disposal site, proper rehabilitation, contractor's
workers & public awareness campaigns on health and safety, biodiversity etc. Spill containment
structures will be put in place together with general spill clean-up guidelines. There will be regular
toolbox talks on safety, health and environmental topics. There will be regular servicing (at designated
areas) of vehicles and machinery to avoid oil leaks. A storm water management plan will be compiled and
implemented. Working methods that will be used shall minimize erosion, noise and dust emissions and
nuisance in general. Where necessary, there will be onsite treatment where turbidity and organic matter
(like settling ponds) are physically and biologically removed before discharge of the effluent to the
environment. Populations of threatened and protected species will be removed under the supervision of a
qualified and experienced botanist and relocated to adjacent representative habitat that has been selected
by the botanist. In the event of an outbreak of disease, public health authorities will be notified hence they
are an important stakeholder in the project. The cost of implementation of mitigation measures which will
be funded by the government is estimated at ZAR 16,000,000. In addition, the government will also
spend ZAR130,000/year for monitoring and ZAR24,000,000 for resettlement.
Climate Change
3.2.4 The issues of climate change impacts were addressed by SWADE under the MNRE & UNDP/
GEF’s January 2015 report titled “Integration of climate change and risks to the downstream development
project and Lower Usuthu smallholder irrigation projects”. It was agreed with the Swaziland Environment
Authority (SEA) that, the recommendations of the report will be integrated into the LUSIP II Climate
Mitigation Plan (CMP) to make the study part of the ESIA documentation. From the study it was found
that climate change will have a significant negative impact on the project if no adaptation measures are
implemented. The vulnerability studies indicate a reduced precipitation, increased temperature, change in
length of rainy season, increased incidences of drought and floods, increased vulnerability of
infrastructure, lack of policies and finally a negative impact on the economy.
3.2.5 The identified climate change impacts will be mitigated at three different levels. In the short
term, there will be (i) training of farmers and communities in the KDDP and LUSIP on the vulnerabilities
of their various livelihood activities to climate change; (ii) assisting the communities to select various
adaptation measures to assist them to adapt to climate change; (iii) training the communities to develop
climate proof community development plans by following the guidelines for climate proofing community
development plans; and (iv) assist communities identify quick wins in adapting to climate change e.g.
rainwater harvesting, rotational grazing, using drought tolerant varieties etc. In the medium term: (i)
climate proofed basin development plans will be introduced; (ii) guidelines for assisting communities
construct climate proofed structures that can deal with projected impacts of climate change i.e. severe
storms (floods, wind and hail) will be developed; and (iii) communities will be assisted to conduct
infrastructure vulnerability assessment to identify infrastructure vulnerable to climate change. In the long
term, overarching climate change policies and strategy for the government of Swaziland will be
developed and reliance on sugarcane as an export crop will be looked into with aims of diversifying to
other less water reliant crops e.g. cassava, sorghum etc.
Gender
3.2.6 Despite equality in rights guaranteed by the Constitution, women are still marginalized in
Swaziland. Swaziland has a gender inequality indicator of 0.529, and ranks number 115 among the
world’s countries, demonstrating that there are large disparities between men and women. The July 2005
Swaziland Constitution recognizes gender equality and provides for equality of all persons before and
under the law and prohibits discrimination on several grounds including gender. In 2010 the country also
adopted the National Gender Policy whose main objective is to achieve a gender balance in the socio-
economic, legal, cultural, religious, political processes by developing and implementing strategies and
11
interventions that recognize and acknowledge the needs and interests of both women and men in the
eradication of gender inequality, gender based violence, HIV/AIDS and poverty in the country.
3.2.7 In line with the Constitution and the National Policy, SWADE has developed a Gender Policy
and Strategy that is being used to mainstream gender related activities in the implementation of the
LUSIP. Against this backdrop, Swaziland remains a patriarchal society dominated by men in almost all
areas of social, cultural, economic and political activities. Implementation of the LUSIP II project has a
number of positive impacts on gender, which include economic empowerment of both women and men
through commercial farming leading to poverty reduction; capacity building particularly for women
through skills training; and changing social dynamics through promotion of equal participation. Evidence
from the implementation of LUSIP I indicates that women participation is increasing in decision-making
positions of farming companies (30%). The main challenge on gender that would require mitigation is the
use of head of household for registration in farming companies under the LUSIP project, which may limit
equal participation of women and men. This if not addressed would exacerbate the women vulnerability
to poverty. As such, there is need for capacity building and public education to help address this challenge
to build on the successes of LUSIP I to continuously main streaming gender in the project activities. In
addition, there is need for capacity building of women through artisanal skills development. In particular,
promote women participation through training and community sensitization. Traditional leaders will be
particularly targeted to ensure acceptance of equal participation for both men and women, and also
inclusion of the youth in the whole programme.
Social
3.2.8 Population: As of 2010 the total population of Swaziland was estimated at 1.2million with 38%
below the age of 15 and 58% between 15 and 65 years of age, while about 3.4% was 65 years and older.
80% of the population lives in rural areas and depend mostly on agriculture. According to 2010 World
Bank reports, the population density of the country was estimated at 61.37 per km² with the population
growth rate at 1.195%. However, while population is growing the production is on decline with maize
production declining between year 2000 and 2012 at a rate of 30%, dropping from an average 100,000
tons of maize per year in 2000 to an average harvest of 70,000 tons in 2012. According to the World
Food Programme, the outcome of the annual assessment by the Swaziland Vulnerability Assessment
Committee (Swazi VAC) indicated that 116,000 people (10 percent of the population) faced a food deficit
during the 2012/2013 lean season. This is a 30% increase on the 2011/12 figure of 89,000. As a result, the
pressure on food prices remains high.
3.2.9 On a good note, the forecasts for 2015/2016 predict slightly higher than average rainfall and may
indicate improved production. However, the many underlying factors that contribute to the trend of low
production - erratic weather, high fuel and input costs, the devastating impact of HIV and AIDS, and low
implementation of improved agricultural practices - are still much prevalent.
3.2.10 Land Tenure: In Swaziland there two systems of land ownership and use; (1) the Individual
Tenure Farms (ITF) and (2) the Swazi Nation Land (SNL). Swazi Nation Land is vested in the
Ingwenyama (the King) represent 57% of the total available land in the Kingdom. The king governs the
land through local chiefs, who act as the main administrators of the land tenure system. Chiefs allocate
land to individual households through the ‘kukhonta’ system. Under this system, an individual, seeking to
own or use land, approaches the chief who, in conjunction with the community in the chiefdom, may
decide to allocate land to the individual. Once the land is allocated, the individual allottee enjoys some
degree of security of tenure which include but not limited to the right to pass land on to offspring.
However, the chief can always reallocate the land or evict the household, although this occurs quite
infrequently.
3.2.11 Production on the SNL is primarily for subsistence and less than 10 per cent of total production is
offered for sale. Maize, the staple food of Swaziland, is the principal crop grown on the SNL and
occupies about 80 per cent of the total crop areas. Maize is quite frequently mix-cropped with cucurbits,
legumes, sweet potatoes, and sorghum. In recent years, SNL farmers have appreciably increased
12
production of some cash crops, such as cotton, tobacco, and vegetables, but this still represents a small
proportion of the total SNL agricultural production. SNL has increased at a rate of approximately 2.8 per
cent per annum over the past decade but this has not met the requirements of the population growing at a
higher rate.
3.2.12 Individual Tenure Farms: Individual Tenure Farms (ITFs) cover about 750,000 hectares and
average about 800 hectares each. About three-quarters of the freehold title holdings are held in equal
proportions between Swazis, and expatriates, and the balance belongs to large companies such as the
Commonwealth Development Corporation. The ITFs are predominantly cropland, livestock ranches,
timber and fruit plantations, and mining concessions. However, a large proportion of this subsector
consists of unused land, owned by absentees. Production techniques on most of the ITFs are modern and
capital intensive, including use of full inputs and mechanization. The bulk of output produced in this
subsector is intended for both domestic and foreign markets. Sugar and timber are the principal
commodities and account for a sizeable proportion of total merchandise exports. About 60 per cent of the
national agricultural production originates from the ITFs, and includes other important commercial crops
such as cotton, citrus, pineapples, tobacco, and livestock. The annual growth of this subsector is estimated
at 5 per cent.
3.2.13 The project is located under the SNL. Land allocated by the chief is rarely taken away, and if so the
person is compensated fairly. Presently, there are several irrigation schemes on SNL and experience has
shown that there have been no dispute in terms of ownership and usage by individuals. Moreover, while the
traditional land system on the SNL could be viewed as a major bottleneck to agricultural development,
beneficiary farmers are grouped into associations through which they obtain credit for irrigation development
finance and crop inputs, apply for water permits from the Water Apportionment Board, negotiate for sucrose quota
from the Swaziland Sugar Association (SSA), and access development finance and seasonal loans by
guaranteeing the loan repayment through ‘stoporder’ deductions from the sugar crop proceeds at the mill.
3.2.14 HIV/AIDS: Swaziland has one of the highest HIV/AIDS prevalence in the world with 26% of the
15 – 49 year old population living with HIV. Prevalence in adults aged 18 – 49 years is even higher at
31%. The country has been negatively affected by HIV/AIDS which has increased the incidence of other
opportunistic diseases such as tuberculosis thus affecting the quality and quantity of human capital and
has also increased the burden on health service delivery system. The Government is committed to
combating HIV/AIDS and an HIV prevention policy is in place. The National Response Framework was
revised in 2013. Drivers fuelling HIV/AIDS include high unemployment amongst women and youth,
having multiple sexual partners and this is exacerbated by the high rates of polygamy; sex work; HIV
stigma and discrimination; gender inequality and gender based violence. Implementation of the project
would help in creating jobs for both women and the youth, who are the principal victims, and as such will
reduce the incidences of poverty related HIV infections. The project will support the SWADE HIV/AIDS
mainstreaming programme. There would be need for strengthening collaboration with public health units
of the government and HIV/AIDS based NGOs to provide sensitization and public awareness activities in
the project impact areas. In addition, under the project management component financed by the
Government of Swaziland, ZAR 3,206,984.61 (approx. UA 165,000) has been earmarked for capacity
building of the communities including gender and HIV/Aids training.
Involuntary resettlement
3.2.15 A Resettlement Action Plan (RAP) for LUSIP Phase II was prepared in 2012. A total of 22
households will be affected by the construction of the canal out of which all will be relocated since they
fall within 100 metres of the preliminary canal alignment. Affected communities have been sensitized on
resettlement and affected households are positive about the implementation of relocation plan. The
affected families are to be provided with dwelling houses, water tanks and will become project
beneficiaries. The resettlement will also entail livelihood restoration including livestock and other
livelihood activities.
13
SWADE will be responsible for the implementation and coordination of the resettlement programme. All
affected assets have been assessed and asset inventory established for the affected households. The total
cost of compensation is estimated at ZAR 23,709,597.68 (approx. UA 1.22 million).
IV IMPLEMENTATION
4.1 Implementation arrangements
4.1.1 The Project will be implemented by the Swaziland Water and Agricultural Development
Enterprise Limited (SWADE), a government company established by the Government of Swaziland in
1999. The project will be managed through the existing structure of SWADE which comprise of a Chief
Executive Officer, a Chief Financial Officer, an Internal Auditor, Procurement Officers, Civil/Irrigation
Engineers, and M&E Officers. Given the focus and size of the project, SWADE will additionally recruit,
on competitive basis, an Agribusiness Specialist and an Assistant Procurement Specialist to complement
the existing team. To fill the technical capacity gaps, SWADE has engaged the services of Aurecon
Consulting Firm to provide support to the PCU during the entire project implementation period.
4.1.2 Procurement Arrangements Public procurement in Swaziland is regulated by the Public
Procurement Act, 2011. The Act has been effective since 2013 and describes the institutional framework,
methods of procurement, procedures, rules and ethical behavior. The Act established an independent
regulatory body; the Swaziland Public Procurement Regulatory Agency (SPPRA) with responsibility for
policy formulation, regulation, oversight, professional development and information management and
dissemination in the field of public procurement. The Act applies to all public procurement conducted by
procuring entities which are defined as any entity designated to conduct public procurement activities,
including Ministries, Departments, Agencies, category A public enterprise or Local Government
Authority, except where procurement is related to defense or national security or where an international
agreement is concluded between the Government of Swaziland and any donor organization and may
require use of procurement rules and procedures provided in the said agreement. The Government is still
facing some challenges as it relates to the operationalizing of the Act. The regulations are yet to be
finalized and approved by Parliament. National standard bidding documents are yet to be developed and
capacity building of procuring entities, and procurement institutions is yet to be done.
In view of the foregoing, procurement activities under the project will be done in accordance with Bank
Procurement Rules and Procedures, as amended from time to time, using the relevant standard bidding
documents, and the provisions stipulated in the Financing Agreement. The Bank financed components
will have two contracts that will both be procured using ICB. The Government of Swaziland has
requested for Bank no objection for advance contracting of the works contract for the Main Conveyance
System. In light of the PD No. 02/2015, the Bank has approved the request to allow disbursement to take
place without much delay after approval. Table 4.1 below presents a summary of the procurement
arrangements, while procurement details are presented in Annex B.5 of the Technical Annexes.
Table 4.1: Procurement Table:
International Competitive Bidding
(ZAR’000)
Total
(ZAR’000)
Works 842,426 842,426
Goods 12,705 12,705
Total 855,131 855,131
14
4.1.3 Financial Management: The financial management aspects of the Project Implementation will be
under the responsibility of SWADE using its existing structure to carry out the Financial Management
functions. The financial management capacity of SWADE was assessed and found to be adequate. In
addition, it has adequate experience in implementing donor funded projects including the previous Bank
financed LUSIP I project. SWADE has a functional Finance unit, which is headed by a Chief Financial
Officer. Its accounting system is fully computerised and therefore considered to be sufficient to meet the
Bank’s requirements of the financial management elements – budgeting, treasury management,
accounting and financial reporting, and internal controls. Overall, the Financial Management operations
assessment of SWADE reflected an adequate environment to provide, with reasonable assurance, accurate
and timely information on the status of the project and as such the existing systems shall be adopted for
budgeting, accounting, data/transactions processing and day to day work which shall be governed by the
existing Accounting Manuals.
4.1.4 Financial Reporting and Auditing Arrangement: To meet fiduciary requirements, SWADE
will submit to the Bank Interim Quarterly Financial Progress Reports no later than 45 days after the end
of each calendar quarter. The quarterly financial reports will include a statement of sources and uses of
funds, with the uses of funds analysed by activities/components and categories, comparing actual
expenditure with budget and notes explaining significant variations in expenditures.
4.1.5 Audit Arrangements: In line with the country requirements, the Office of the Auditor General of
the Kingdom of Swaziland will have direct access to the annual audited financial statements of SWADE
including the project accounts. The audit is currently being carried out by an Independent Audit Firm
recruited through a competitive process in line with the Public Enterprise Unit (PEU) Act. The process
leading to the recruitment of the existing external auditors of SWADE will be submitted to the Bank with
a view to ascertaining its competiveness and for them to carry out the project audit. In addition, the audit
Terms of Reference (TOR) would be submitted to the Bank for clearance in order to ensure adequate
coverage of the project. In the event that the current audit reports preparation timelines for SWADE meet
the six months requirements of the Bank for the submission of the audited accounts, it would not be
necessary to prepare a separate audited accounts for the project but appropriate disclosures would be
required to be made in the notes to the accounts. However, in the event that this requirement is not met,
annual audited accounts of the project will have to be done separately from the SWADE entity audited
account whereby the project shall submit a single audited financial statements (including a management
letter), showing the separate component funded by each donor (as applicable) to the Bank, within six
months following the closure of each financial year. The cost of the audit shall be borne by SWADE.
4.1.6 SWADE has an Internal Audit function (managed by one staff) which reports directly to the Audit
and Risk Sub-Committee of the Board. However, SWADE proposes a staffing complement of three,
including the existing Internal Audit Manager who will be complemented by an Internal Audit Officer
with immediate effect and an additional Internal Auditor to be recruited as required depending on the
work load. The project will be included in the Internal Audit work programme.
4.1.7 Disbursement Arrangements: This will be effected using only Direct Payment Methods in
accordance with the Bank’s rules and procedures as laid out in the Disbursement handbook as applicable,
given that the Bank will finance only one major construction work and related goods. A disbursement
letter spelling out the disbursement arrangements will be discussed during the negotiations of the
financing.
4.2 Monitoring
4.2.1 SWADE Monitoring and Evaluation unit has a very detailed and current database on the key
indicators of: (i) projects at various stages; (ii) water table; and (iii) crop yields in selected sites of the five
agricultural regions. The report of Socio-Economic Baseline Survey was submitted in 2015. The report
provided the physical and socio-economic baseline status of the project area as well as selected project
indicators. The baseline information, which included sex-disaggregated data and was based on gender
15
analysis covered areas such as education, health, income levels etc. The project will incorporate gender
sensitive results-based indicators and target values. The project will also conduct at its onset, a start-up
workshop, with the aim of sensitizing and training of SWADE staff, implementing partners and project
beneficiaries on the project objectives and scope and review the Results Based Logical Framework as
well as Bank’s Procedures.
4.2.2 Through SWADE’s Monitoring and Evaluation (M&E) department, the Project will provide: (i)
timely and accurate information on project implementation progress and constant feedback for decision
making and addressing potential work plan deviations and problems during implementation; and (ii) the
basis for assessing the achievements of the project as per the Results Based Logical Framework. The
project will submit quarterly progress reports to the Bank and the Bank will undertake two supervision
mission per year and prepare an Implementation Progress Report (IPR) for each supervision mission. An
MOU will be signed among the financiers to facilitate effective M &E for all the project component with
particular emphasis on the infrastructure of the main, secondary and tertiary canals.
Table 4.2: The key milestones are summarized in the table below:
Timeframe Milestone Monitoring process / feedback loop
Year 0
Year 0
Year 1 – 5
Prequalification of
contractors, preparation of
procurement packages etc.
Project approval, signature
and launching
Implementation
GoS, AfDB
AfDB Board, GoS
Beneficiaries, SWADE, MA & PCU
Year 1 – 5 Oversight Steering Committee (MOF, MA, , SWADE)
Year 1 – 5 Audit Reports Annually by PCU
Year 3 Mid-Term Review Bank and PCU to monitor
Year 5 Impact Study PCU
Year 5 Project Completion Report SWADE, MA and PCU to monitor; Bank to
participate
4.3 Governance
4.3.1 The 2015 Ibrahim Index of African Governance showed Swaziland positive performance at the
overall governance level, showing its largest improvement in Human Development. Although Swaziland
registers a marginal improvement in Participation & Human Rights, it remains the lowest scoring
Southern African country in this governance dimension. In Sustainable Economic Opportunity. Swaziland
shows one of the largest improvements in Rural Sector on the continent, contrary to the continental trend
of deterioration in this sub-category. In Human Development Swaziland’s positive trend is the result of
strong gains in Education, in which it has shown year-on-year improvement. Swaziland continues to
register low scores in Participation & Human Rights, notably in Participation where it is ranked third
weakest on the continent, above Somalia and Eritrea. Swaziland also shows deterioration in this sub-
category, the largest within its region. During the period under review, Swaziland was ranked 28 out of
54 countries, with a score of 49.6 (well below the regional average score of 59). Swaziland scores 50.3 in
Sustainable Economic Opportunity, ranking 16th on the continent. Within the Sustainable Economic
Opportunity category, Swaziland’s best sub-category performance is in Rural Sector, scoring 57.0.
Swaziland’s weakest sub-category performance in the Sustainable Economic Opportunity category is in
Infrastructure, scoring 46.6. Swaziland has shown an improvement (+0.8) in Sustainable Economic
Opportunity since 2011. This has been driven by improvement in three of the four sub-categories: Public
Management (+1.5), Infrastructure (+0.9) and Rural Sector (+3.9). In addition, the Bank’s Country Policy
and Institutional Assessment (CPIA) shows a weakening governance environment, with the country’s
score declining from 3.5 in 2010 to 3 in 2011. In 2012, the governance score improved to 3.3 but the
country’s ranking slipped to 47 from 44 in 2011. There are major weaknesses on the expenditure side due
to inefficient resource allocations. Strengthening the budgetary process to enhance resource allocation and
16
capacitating oversight bodies to ensure effective delivery of their core mandate and to foster transparency
in procurement and accountability will be important.
4.3.2 The Anti-Corruption Commission (ACC) was reestablished in 2008 after the repeal of the
Prevention of Corruption Order of 1993. In the past two years, the ACC has brought some high-profile
cases before the courts. Its effectiveness, however, is constrained by inadequate human and financial
resources. Nevertheless, Swaziland was ranked 69 out of 175 countries in the 2014 Corruption Perception
Index, a great improvement over 2012 rating which ranked the country 88 out of 176 countries.
4.3.3 As part of the Fiscal Adjustment Roadmap (FAR) the Government has put in place a
comprehensive Public Finance Management (PFM) action plan. Of the seven PFM-related actions
required under the Fiscal Adjustment Roadmap (FAR), only the enactment of the PFM Bill is
outstanding. The PFM Bill, which was recently approved by Cabinet, provides a good opportunity for
implementing the remaining reforms. The Bill sets out the key principles of good governance, including
broad participation, inclusiveness, transparency and accountability. The Bank has provided resources for
a long-term PFM Advisor to the Ministry of Finance. The IMF and the World Bank are jointly providing
technical assistance to strengthen the macro-fiscal framework. The Government has also established a
strong framework that will help monitor progress in implementing reforms aimed at improving the
business environment.
4.4 Sustainability
4.4.1 The project is financially sustainable. The analysis indicates that the farmers will be able to
service their loans, as well as obtain handsome net profits for re-investments in running the farms. The
Government is also in the process of appointing a service provider to manage the bulk infrastructure
facilities on its behalf. It is envisaged that under this new arrangement, farmers will be charged with the
full cost of the irrigation water management, which Government estimates at ZAR1,350 (US$ 84.00) per
ha, but are currently charging only ZAR 450 (US$ 28.00) per ha, with a Government subsidy of ZAR 900
(US$ 56.00) per ha. The Government, by putting in place a mechanism for full recovery of the operation
and maintenance cost will contribute significantly to the sustainability of the project. The Government
has committed to making yearly adequate budget provision for counterpart funding. The irrigation
development, marketing of value added products, provision of institutional support and development of
strong farmer groups will work in synergy to ensure sustainability. In particular it is expected that, as
under LUSIP I, the farmers who will be organized in Farmer Associations will operate as farming
businesses, recruiting farm managers and/or service providers to manage their farms, including operation
and maintenance.
4.5 Risk Management
4.5.1 Volatility of the world sugar market.
Mitigation: Government has concluded (in 2014) the European Partnership Agreement with the EU,
which entitles the country to some preferential treatment. The Country also enjoys preferential treatment
in the SADC market.
4.5.2 Project Cost Overruns: Project cost overruns due to exchange rate fluctuations, uncertainties in
economic situation of SADC and the rise in the cost of materials.
Mitigation: Though the project is costed in South African Rand (which is accepted in Swaziland as a local
currency), the procurement activities are already front-loaded by Advance Procurement Method which
will enhance timely procurement to address the price increases. In addition, adequate price contingencies
for the unavoidable increment in cost are provided in the project costing.
17
4.5.3 Reduction in Water availability for irrigation.
Mitigation: The project area is covered by the tripartite water usage agreement between South Africa,
Mozambique and Swaziland. Therefore, it is not envisaged that the project will experience inadequate
water for irrigation. Nevertheless, farmers will be trained in proper water management to reduce wastage
and to optimize returns for each drop of water.
4.5.4 Delay in providing counterpart funding could result in implementation delays. The
Mitigation: The resources of the Bank and other DP are earmarked to fund infrastructure while the
Government will fund Project Management and Coordination activities. SWADE which will manage the
project already exists and is well staffed. In addition, the Government has given commitment to make
adequate provision for the project implementation in the country’s annual budget.
4.5.5 Ineffective and uncoordinated project supervision: Given that financiers could have different
system and work plans, this could lead to uncoordinated and ineffective supervisions which could result
into development ineffectiveness.
Mitigation: The project is being parallel co-financed which means that each Development Partner has its
ear marked activities. Moreover the design of the project does not require all activities to start and
complete at the same time. Thus joint supervisions are not necessary.
4.5.6 Poor farmer organization:
Mitigation: Farmer mobilization underway.
4.6 Knowledge building
4.6.1 The knowledge gained and lessons learnt through the implementation of LUSIP I and other
Bank’s projects in Swaziland as well as studies carried out in the sector have been duly applied in
designing this project. Similarly, the knowledge that will be generated through implementation of this
Project will be instrumental in the designs and implementation of the anticipated LUSIP III. The results
from the various studies and other surveys, including the socio-economic impact study will inform the
stakeholders on how to put the acquired knowledge into practical use for better results-oriented
achievements and sustained benefit flows.
4.6.2 At the project level, the project implementation review, quarterly progress reports, audit, sector
M&E, ESMP monitoring, etc. as well as other reports will also provide information on various aspects of
the project for further diagnosis and improvement. The knowledge obtained will be shared within the
AfDB and with other development partners as well as with RMCs.
V LEGAL INSTRUMENTS AND AUTHORITY
5.1 Legal instrument
The Project will be financed with an ADB Loan.
5.2. Conditions associated with Bank’s intervention
5.2.1 Conditions Precedent to Entry into Force of the Loan Agreement: The entry into force of the
Loan Agreement shall be subject to the fulfilment by the Borrower of the provisions of Section 12.01 of
the General Conditions Applicable to Loans and Guarantee Agreements of the ADB.
5.2.2 Conditions Precedent to First Disbursement of the Loan: The obligation of the Bank to make
the first disbursement of the loan shall be conditional upon entry into force of Loan Agreement in
accordance with 5.2.1 above and the submission by the Borrower of evidence in form and substance
satisfactory to the Bank, of a duly concluded co-financing arrangements with BADEA, EIB and KF, or if
such arrangements have not been duly concluded, evidence by the Borrower that it has made appropriate
arrangements to cover any financing gap resulting from the failure to conclude the co-financing
agreements.
18
5.2.3 Undertaking: The Borrower shall cause the Executing Agency to implement the project in
compliance with national legislations and in accordance with the Environmental and Social Management
Framework (ESMF) and submit to the Bank on an annual basis an acceptable Environmental and Social
Monitoring Report.
5.3 Compliance with Bank Policies
This Project complies with all applicable Bank policies.
VI RECOMMENDATION
Management recommends that the Boards of Directors of the Bank approve the proposed ADB loan of
ZAR 855.131 million to the Kingdom of Swaziland for the purposes of financing the Lower Usuthu
Smallholder Irrigation Project - Phase II (LUSIP II), and subject to the conditions stipulated in this report.
I
APPENDIX 1: MAP OF PROJECT AREA
II
APPENDIX 2: SWAZILAND SOCIO-ECONOMIC INDICATORS
Indicators Unit 2000 2007 2008 2009 2010 2011 2012
National Accounts
GNI at Current Prices (Million US$) 1.702 3,433 3,566 3,365 3475 3971
GNI per Capital (US$) 1600 3030 3100 2880 2930 3300
GDP Current Prices(Million US$) 1517 3039 3020 3168 3894 4179 3705
GDP at 2000 Constant Prices (Million US $) 1517 1829 1873 1895 1931 1945 1939
Real GDP Growth Rate % 10.2 3.5 2.4 1.2 1.9 0.7 -0.3
Real per Capital GDP Growth Rate % 8.6 2.1 0.9 -0.4 0.4 -0.7 -1.7
Gross Domestic Investment % GDP 18.2 12.3 11 10.3 10.7 10.7 12.6
Public Investment % GDP 5.6 6.5 5.8 5.5 5.6 5.6 6.5
Private Investment % GDP 12.6 5.8 5.2 4.9 5 5 6.1
Gross National Saving % GDP 4.6 10.3 5.7 -0.1 1.7 0.1 10.6
Price and Money
Inflation (CPI)% 12.2 8.1 12.6 7.6 4.5 6.1 8.9
Exchange Rate (Annual Average)/Local currency/USD
6.9 7 8.3 8.5 7.3 7.3 8.2
Monetary Growth (M2)%
Money and Quasi Money as % of GDP 19.7 24.6 24.4 28.7 29.2 28.9
Government Finance
Total Revenue and Grants % of GDP 27 39.5 37.6 34.1 23.7 24.2 38.9
Total Expenditure and Net Lending % of GDP 28.3 30.6 39.6 40.1 37.9 33.8 35.9
Overall Deficit(-)/Surplus(+) % GDP -1.3 8.8 -2 -6 -14.3 -9.6 3
External Sector
Export Volume Growth (Goods)% 1.3 -4.4 -20.1 16 -8.9 7.9 11.4
Import Volume Growth (Goods) % -11.2 -6.9 -29.5 49.5 -18.1 -7.7 0.6
Terms of Trade Growth % -14.3 6.1 -7.2 20.8 -10.9 -11.7 -16.7
Current Account Balance (Million US$) -46 -141 -224 -410 -609 -433 -98
Current Account Balance % GDP -3 -4.7 -7.4 -12.9 -15.6 -10.3 -2.6
External Reserve Months of Import 2.3 2.3 2.6 3.1 2.2 1.6 ….
Debt and Financial Flows
Debt Service % Exports 1 2.3 1.7 1.7 2.3 3.1 3.4
External Debt % GDP 2.3.3 17.5 15.9 12.6 12.3 11.3 11.2
Net Total Financial Flows (Million US$) 35 55 54 38 70 102 …
Net Official Development Assistance (Million US$)
13 51 70 56 91 130 …
Net Foreign Direct Investment (Million US$) 106 37 106 66 136 95 …
Source: AfDB Statistics Department: Development Data Portal Database, United Nations: OECD, Reporting System Division, IMF: World
Economic Outlook, October 2012 and International Financial Statistics, October 2012; Notes:…Data Not Available (e) Estimations Last
update: March 2013
III
APPENDIX 3: TABLE OF ADB PORTFOLIO IN SWAZILAND
Swaziland ongoing portfolio as at January 2016
Division Long name Approval
date
Planned
project
completion
date
Amount App. Amount Dis. Age
ESTA2 STATISTICAL CAPACITY BUILDING
PROGRAMME - PHASE II (SCB II)
2/1/2012 12/31/2016 490,600.0 204,811.5 4.1
OSGE2 TA FOR PUBLIC FINC MGMT REFORMS 11/3/2011 11/30/2016 478,452.0 381,185.9 4.3
969,052.0 585,997.4 4.2
ONEC2 ENERGY SECTOR TECHNICAL
ASSISTANCE PROGRAM
12/8/2014 12/31/2016 717,652.0 0.0 1.2
717,652.0 0.0 1.2
OITC2 MANZINI-MBADLANE HIGHWAY PROJECT 5/28/2014 12/31/2019 33,314,220.6 0.0 1.8
OITC2 MANZINI-MBADLANE HIGHWAY PROJECT 5/28/2014 12/31/2019 1,200,000.0 0.0 1.8
34,514,220.6 0.0 1.8
OWAS2 EZULWINI SUSTAINABLE WATER AND
SANITATION SERVICE DELIVERY
6/18/2014 12/31/2018 16,702,835.7 503,128.8 1.7
16,702,835.7 503,128.8 1.7
TOTAL 52,903,760.3 1,089,126.2 2.6
IV
APPENDIX 4: ORGANOGRAM
LUSIP II Organogram
SWADE Organogram
Project Steering Committee
SWADE Board
CEO
LUSIP II Project Manager
Project Implementation Team
Economic Empowerment Unit
Business Development Support
Planning & Institutions Development Unit
Environmental Management Unit
Support Services
(IT; Procurement; Finance; Admin; M&E; HR; Communications)
Water Infrastructure & Management Unit
Engineering Consultants
Engineering Advisor
Environment Review Panel
MINISTER FOR AGRICULTURE
Board of Directors
Chief Executive
Officer
LUSIP I Project Manager
Internal Auditor
Executive Secretary
Human Resources & Administration
Manager
Chief Financial Officer
Information Management
Systems Manager
LUSIP II Extension Project
Manager
Strategic Planning Advisor
LUSLM National Project Manager
KDDP ACTING Project Manager
Executive Director