Adv Antic a Presentation on Draft Report

  • Upload
    dan1956

  • View
    216

  • Download
    0

Embed Size (px)

Citation preview

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    1/63

    Safety Review of the Proposed Onshore

    Section of the Corrib Gas Pipeline- Draft Report

    Dr. Mike Acton and Dr. Bob Andrews (Consultants)

    Mr. Arwel Griffiths (Executive Director)

    Copyright 2005 Advantica, Inc. (USA Only) and Advantica Ltd. (Outside USA). All rights reserved by the respective owner.

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    2/63

    Overview

    Introduction to Advantica Company Overview Key Personnel

    Safety Review of the Corrib Gas Pipeline Background Scope of Safety Review

    Safety Review Process Draft Report

    Summary of Recommendations and Closing Remarks

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    3/63

    What Does Advantica Do?

    Provide engineering, consultancy andsoftware services to customers acrossthe hydrocarbon chain

    throughout the project lifecycle, frominfrastructure development through toasset management.

    Approximately 500 highly qualifiedscientific and engineering staff, including

    internationally renowned experts. Complete gas chain coverage.

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    4/63

    We are a Global Business

    Advantica Clients found in these locations

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    5/63

    Award Winning Technology

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    6/63

    Key Personnel

    Dr. Mike Acton (Hazard & Risk Management) 17 years oil & gas experience at Advantica (formerly British Gas R&T) Involved in many large and full scale pipeline tests

    Chairman of PIPESAFE Group of companies Extensive experience in the application of pipeline risk assessment Experienced incident investigator, including transmission pipeline failures

    Active member of IGEM Committees, and contributed to several IGEMCodes of Practice and Safety Recommendations

    Dr. Bob Andrews (Integrity Management) 20 years experience at The Welding Institute and then Advantica

    Extensive experience of structural integrity issues in components andstructures, particularly pipelines

    Specialist in pipeline integrity and fracture control

    Active member of IGEM and BSI Committees, and contributed to IGEM and

    BSI Codes of Practice and Standards

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    7/63

    Safety Review of the Corrib Gas Pipeline

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    8/63

    Background

    The pipeline industry has a good safetyrecord, but incidents have occasionally

    occurred

    The Corrib onshore pipeline is plannedto operate at high pressure, carrying

    untreated gas

    Serious concerns expressed by local

    residents over the safety of the pipeline,especially the consequences of failure

    Safety review commissioned inresponse to those concerns

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    9/63

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    10/63

    Scope of Safety Review

    Included: Review of the health and safety aspects of the proposed pipeline in terms of

    engineering design and risk to public safety

    Review of the available documentation for completeness and suitability NOT included

    Assessment of environmental impact

    Assessment of the risk to workers during construction

    Review of the onshore terminal, offshore pipeline or subsea equipment

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    11/63

    Safety Review Process

    Evaluate initial set of documents supplied by TAG

    Identify and request additional information from Shell

    Meeting with Shell for points of clarification and discussion of projectdesign selection process

    Documents classified as: Technical documents requiring detailed technical review by specialists

    Documents providing background information including project history Documents outside the scope of the review

    Site visit to confirm understanding of pipeline route and local conditions

    2 day oral hearing and opportunity for written submissions to raiseissues of concern and points to be taken into account in the review

    Draft report issued for comment

    Final report

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    12/63

    Draft Report

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    13/63

    Report Structure

    Executive Summary Main Report

    1. Introduction

    2. The Safety Review Process3. Overall Project Development Plan

    4. Review of Pipeline Design

    5. Quantified Risk Assessment

    6. Discussion7. Final Remarks and Recommendations

    AppendicesA. Advantica Personnel

    B. Summary of Oral and Written SubmissionsC. Geotechnical Analysis

    D. Societal Risk Analysis

    E. Geotechnical Investigations on Corrib Pipeline Route

    F. Comments on Rossport Pipeline Hazard Calculations by DJ Aldridge PhD

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    14/63

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    15/63

    Overall Project Development Plan

    High level review of constraints relevant to the onshore pipeline

    Assessment of consideration given to safety issues in the design optionselection process for:

    Sub-sea tie-back option Landfall and terminal locations

    Proposed onshore pipeline route

    This section considers the process followed Not a detailed technical review

    Consideration of alternative design options, terminal locations orpipeline routes was outside the scope of our work

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    16/63

    Overall Project Development Plan

    Terminal location, 9km inland, drives requirement for an onshorepipeline

    High pressure onshore pipeline required whether gas processed

    onshore or offshore Onshore processing introduces additional threats that must be

    managed

    Public safety was one of many factors in selection process, which alsoincluded: Visual impact

    Economic

    Environmental Technical

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    17/63

    Overall Project Development Plan

    QRA informed design and route selection

    Risk levels within recognised international criteria

    Ireland has no formal risk-based framework in place

    Consideration should be given by the Irish Government to establishinga risk-based framework for decisions on proposed and existing major

    hazard pipelines and related infrastructure

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    18/63

    Overall Project Development Plan

    Four route options considered: Pollatomish via Dooncarton landfall Brandy Point via Brandy Point landfall

    Via Struwaddacon Bay Rossport via Dooncarton landfall (preferred)

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    19/63

    Overall Project Development Plan

    Initial design based on pressure of 150 bar

    Subsequently adopted more cautious approach Wall thickness increased

    Withstand 345 bar theoretical worst case

    Most cautious approach to routing based on consequence distances,but in practice, rarely practical to avoid all population

    Design codes have more onerous requirements for Higher population density Proximity to housing (in some cases)

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    20/63

    Overall Project Development Plan

    Route through Rossport determined by Ground stability

    Avoidance of possible future land development

    Maximising distance from housing Nearest building 70m from pipeline

    Justified by QRA

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    21/63

    Review of Pipeline Design

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    22/63

    Integrity - fatigue

    Failure due to variations in pressure

    Several predictions from flowsimulations

    Stresses around cut-off in codes Recommend:

    Monitoring of pressure variations

    Check small attachments

    1000 10000 100000 10000002 3 4 5 6 7 2 3 4 5 6 2 3 4 5 6

    Cycles

    100

    30

    40

    50

    60

    70

    80

    90

    200

    Stressrang

    e(Nmm-2)

    165Nmm-2

    35Nmm-2

    Edition 4

    Edition 3

    I i i i

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    23/63

    Integrity impact protection

    Protection at road crossings using concrete slabs is accepted practice

    Concerns with the data supplied: Design left to contractor and not location specific

    Slabbing should extend the full width of the route already addressed Distance between slab and pipe may be too shallow Support slab from subsoil in peat areas

    Formal safety analysis for 72% SMYS operation at crossings notdocumented

    These issues should be addressed to provide best practice impactprotection

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    24/63

    I t it d t

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    25/63

    Integrity ground movement

    We also checked other failure modes such as buckling

    We considerother analyses are required to demonstrate integrity: Movement parallel to the pipe

    Effect of bends Increased depth of cover

    We recommend monitoring of stresses in critical areas

    Gro nd Mo ement

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    26/63

    Ground Movement

    Effects of pipeline on ground stability have been considered

    Dooncarton type slide on steep slopes will not affect the route as theslopes are too shallow

    Shallow slope slide has been addressed by Shells consultants All recommendations by these consultants should be implemented in

    full

    Materials

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    27/63

    Materials

    Pipe material to DNV OS-F101 Grade 485

    This grade (or equivalent) has been widely used for onshore andoffshore projects

    Plate produced by German and Japanese mills and pipe produced inUK

    Mill certificates examined requirements satisfied

    Formal fracture control plan not produced, but we have checked therequirements for the gas composition and consider material issatisfactory

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    28/63

    External Corrosion

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    29/63

    External Corrosion

    Mainline coating specificationgenerally satisfactory

    We recommend testing to assess

    possible long term UV degradationduring storage

    We are concerned with the quality offield joint coating and recommend a

    robust inspection regime during

    construction

    Cathodic protection system requiresan insulation jointat the beach to

    achieve separation from offshore

    system

    Construction

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    30/63

    Construction

    Welding to British Standards

    Toughness requirements exceed BS

    Actual levels above requirements

    Welds meet best practice

    Pressure Testing

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    31/63

    Pressure Testing

    We recommend: A high level pressure test to 105% SMYS should be carried out The test pressure should be calculated on nominal wall thickness not

    design We support the recommendation for a fingerprinting ILI run during

    commissioning

    Operations & Maintenance

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    32/63

    Operations & Maintenance

    Procedures were requested from Shell but we were advised that thesehad not yet been written and would be prepared prior to operation in

    accordance with BS 8010

    An Integrity Management System (IMS) is required and should include Inspections

    Management systems and management of change

    Audit and corrective actions

    IMS should be in place from the start of the project

    Frequency of inspections should be updated based on results

    We consider a leak detection system is not sufficient as an integrity

    management system A formal integrity management system should be established for the

    pipeline before construction is allowed to commence

    Operations & Maintenance

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    33/63

    Operations & Maintenance

    We recommend: Defect assessment and procedures should be defined in advance so that

    anomalies can be sentenced quickly

    Repair procedures should be developed for non-leaking damage Procedures are required for safe working in proximity to the pipeline

    Future Operation

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    34/63

    Future Operation

    We have not considered tie-ins of other fields to this pipeline

    We note the system is designed for sweet gas, ie no H2S

    Monitoring is required to check that H2S is not introduced into the

    system In the event that additional fields were proposed to be tied in to the

    pipeline at any future date, a full review would be required to consider

    issues such as extension of the life beyond the initial design life,

    changes in the fluids in the pipeline or changes in the operating

    pressures

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    35/63

    Risk Assessment

    HAZard IDentification (HAZID)

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    36/63

    HAZard IDentification (HAZID)

    Original HAZID covered main onshore pipeline hazards

    Some additional hazards identified

    Project Hazard Register prepared to track HAZID actions

    Some actions to be addressed in operations and maintenanceprocedures (not yet prepared)

    Action to address H2S threat needs to be more robust

    The Project Hazard Register should be maintained and updated and allHAZID actions addressed

    Population Density Analysis

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    37/63

    Population Density Analysis

    Area classification in accordance with BS8010, based on 345 bar Minimum proximity distance of 170m by extrapolation

    Population density found to be low (Class 1 or Rural)

    Ribbon development parallel to pipeline Anomaly of increasing population density with reducing pressure Not enough for Class 2 (Suburban) classification

    Consideration should be given to the nature of ribbon developmentsparallel to the pipeline in calculating population density in any future

    reassessment of the pipeline classification

    Quantified Risk Assessment (QRA)

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    38/63

    Quantified Risk Assessment (QRA)

    Pipeline risk assessment: Failure cause Failure mode

    Gas outflow Ignition Thermal radiation Thermal effects

    Risk calculations

    Risk reduction measures

    Input

    Parameters

    Failure cause?

    Failure mode?

    Calculation of

    Failure Frequency

    Outflow Dispersion IgnitionThermal

    radiation

    Radiation

    effects

    Consequence calculations

    Rupture or Puncture?

    Fatigue

    External

    interferenceGround

    movementCorrosion

    Causes

    Risk Calculations

    Risk Transect

    FN curve (PLL, EV)

    Societal

    Individual

    Review of JP Kenny QRA

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    39/63

    Review of JP Kenny QRA

    Failure frequencies included for: Third party interference Ground movement

    Inherent and construction defects Assumes measures against other threats effective and no H2S

    Inclusion of ground movement inconsistent

    Concluded that Individual Risk levels acceptable at all distances The measures to protect the pipeline integrity assumed in the QRAmust be established for the Corrib pipeline, and maintained throughout

    its life

    A procedure should be established for monitoring of the gas for H2S,specifying the actions to be taken and the threshold concentrations

    above which action would be required

    Review of JP Kenny QRA

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    40/63

    Review of JP Kenny QRA

    Consequence modelling simplistic

    No recognition of uncertainty at very high pressures

    Low value for ignition probability assumed for rupture case

    Consideration of Individual Risk only Risk unexpectedly insensitive to pipeline pressure

    Advantica Risk Assessment

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    41/63

    Advantica Risk Assessment

    Independent check on QRA results PIPESAFE package Validated at pressures up to 120 bar

    Assumes proposed measures AND those recommended in this report Range of hazard distances given

    Increasing uncertainty with higher pressures recognised

    Individual Risk levels lower than JP Kenny results Included Societal Risk analysis

    Individual Risk Analysis

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    42/63

    Individual Risk Analysis

    1.00E-11

    1.00E-10

    1.00E-09

    1.00E-08

    1.00E-07

    1.00E-06

    0 50 100 150 200 250 300

    Distance from Pipeline (m)

    Individua

    lRisk(peryear)

    144barg 240barg 345barg

    Societal Risk Analysis

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    43/63

    Societal Risk Analysis

    1 . 0 0 E - 1 3

    1 . 0 0 E - 1 2

    1 . 0 0 E - 1 1

    1 . 0 0 E - 1 0

    1 . 0 0 E - 0 9

    1 . 0 0 E - 0 8

    1 . 0 0 E - 0 7

    1 . 0 0 E - 0 6

    1 . 0 0 E - 0 5

    1 . 0 0 E - 0 4

    1 1 0 1 0 0 1 0 0 0

    N u m b e r o f C a s u a l t ie s (N )

    FrequencyofNo

    rMoreCasualtiesperYear(F)

    I G E / T D / 1 S o c ie t a l R is k C r ite r io n E n v e l o p e

    1 4 4 b a r g

    2 4 0 b a r g

    3 4 5 b a r g

    Risk Reduction Measures

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    44/63

    Risk Reduction Measures

    Risk levels within recognised limits

    Other possible risk reduction options considered

    Third party damage dominates residual risk

    Pipeline wall thickness main defence against failure The proposed arrangements for surveillance and landowner liaison

    should be specified in the operations and maintenance procedures

    Risk Reduction Measures

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    45/63

    Risk Reduction Measures

    Uncertainty increases with increasing pressure

    Highest pressure should be assumed Dormant defects may fail when pressure rises

    Limiting pressure reduces failure frequency and consequences Limiting design factor to 0.3 or less (~144 bar for Corrib pipeline)

    recognised as effective measure to allow pipelines to be routed in

    higher population density (Suburban) locations

    UKOOA Decision Framework

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    46/63

    Significance of Bases to

    Decision Making Process

    Means of Calibration Decision Context

    Codes and Standards

    Verification

    Peer Review

    Benchmarking

    Internal Stakeholder

    Consultation

    External StakeholderConsultation

    Codes &

    Standards

    Goo

    dPrac

    tice

    Engineerin

    gJudg

    emen

    t

    QRA

    CBA

    Company

    Values

    Societal Values

    Nothing new or unusual

    Well understood risks

    Established practice

    No major stakeholder

    implications

    No significant economic

    implications

    A

    B

    C

    Business risk or lifecycle

    implications

    Some risk trade-offs/transfer

    Some uncertainty

    Some deviation from standard

    or best practice

    Some significant economic

    implication

    Very novel or challenging

    Strong stakeholder views

    and perceptions

    Significant risk trade-offs

    or risk transfer

    Large uncertainties

    Perceived lowering of safetystandards

    Major economic implications

    Significance of Bases to

    Decision Making Process

    Means of Calibration Decision Context

    Codes and Standards

    Verification

    Peer Review

    Benchmarking

    Internal Stakeholder

    Consultation

    External StakeholderConsultation

    Codes &

    Standards

    Goo

    dPrac

    tice

    Engineerin

    gJudg

    emen

    t

    QRA

    CBA

    Company

    Values

    Societal Values

    Nothing new or unusual

    Well understood risks

    Established practice

    No major stakeholder

    implications

    No significant economic

    implications

    A

    B

    C

    Business risk or lifecycle

    implications

    Some risk trade-offs/transfer

    Some uncertainty

    Some deviation from standard

    or best practice

    Some significant economic

    implication

    Very novel or challenging

    Strong stakeholder views

    and perceptions

    Significant risk trade-offs

    or risk transfer

    Large uncertainties

    Perceived lowering of safetystandards

    Major economic implications

    Risk Reduction Measures

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    47/63

    Risk assessment powerful tool to inform decisions, but not only factor

    Corrib pipeline conventional in that the pipeline wall thickness isincreased to accommodate high design pressure and upstream pipeline

    technology is well-established BUT:

    It lies outside normal range of application on onshore design codes

    There is uncertainty in the risk analysis at such high pressures

    It gives rise to significant societal concerns

    We therefore recommend that the pressure in the onshore pipelineshould be limited to enable the pipeline to be reclassified as a Class 2

    (Suburban) pipeline, with a design factor not exceeding 0.3

    Pressure Safety Measures

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    48/63

    y

    Reliability assessment of subsea pressure control systems flawed

    Does not form a basis for selection of options

    A full and technically thorough reliability analysis should be carried out

    of the subsea pressure control and isolation systems specified in thefield design

    Additional pressure control measures should be implemented and theeffective limitation of the pressure in the onshore pipeline demonstrated

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    49/63

    Discussion

    Selection of Design Code

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    50/63

    We consider BS 8010 was an appropriate choice of design code Synthesis of accumulated UK experience IS 328 closely related

    Better safety levels than US or ISO codes see later Generally accepted practice to keep the original code on long running

    projects unless there are reasons for change

    IGE codes allow continued operation to an earlier edition

    Should have considered adopting PD 8010 O&M section

    Selection of Design Code

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    51/63

    Withdrawal of BS 8010 Some observations have been made that BS 8010 was obsolete This is incorrect, the withdrawal was a consequence of the introduction of

    European standards BSi paid for the conversion of the BS into a PD so that the guidance was

    still available

    UK National Foreword to EN 14161 states:

    that a more comprehensive approach to the design of pipelines is possible

    through using BS EN 14161 in association with the following Codes of

    Practice: PD 8010-1:2004

    Selection of Design Code

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    52/63

    Code Comparison BS 8010 calculates design thickness on minimum, not nominal wall BS 8010 allows a higher level hydrotest, giving a more searching test of

    integrity BS 8010 has minimum proximity distances based on pressure US andCanadian codes have no restrictions on proximity except for access

    If the onshore pipeline is reclassified as a Class 2 (Suburban) pipeline,

    the pipeline design should be revised in accordance with PD 8010, toensure that the pipeline is consistent with current best practice, while

    minimising the change required to the existing design

    Design Pressure

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    53/63

    High design pressure of 345 bar Higher than normal for onshore gas transmission Above range of onshore pipeline codes and standards

    Pressures over 100 bar increasingly used for new pipeline designs Cautious approach by Shell resulted in a very thick and strong pipe

    Maximum pressure falls steadily as gas extracted

    Advantica recognises the concerns and recommends limiting thepressure to ~144 bar, consistent with pipeline design factor used forpipelines in more densely populated suburban areas

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    54/63

    Untreated Gas Composition

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    55/63

    Corrib gas has unusually high natural methane content (~94%) Typical of methane content of treated gas Similar to composition used in validating Advantica models

    Other fluids contained in the gas stream present additional threats: Gas is wet - combined with CO2 can cause internal corrosion Hydrates - can cause blockage

    H2S - not detected, but can be formed during lifetime of a gas field

    Appropriate precautions have been identified to combat these additionalthreats

    Must be maintained and effectiveness monitored

    A plan should be in place in case H2S is detected

    Ground Stability

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    56/63

    Effects of ground movement on the pipeline JP Kenny analysis conservative for straight pipe Expected to withstand ground movement loading

    Analysis should be extended to other configurations (e.g. bends) If not acceptable, need to consider additional measures Techniques to stabilize pipelines in muskeg (similar to peat) used in

    Canada

    Effects of pipeline construction on future ground stability Raised as an issue in oral hearings

    Obtained advice on Irish peat issues from GSI

    Practical advice from contacts with experience of construction in peat

    Additional information supplied by Shell includes reports by AGEC

    The recommendations made by AGEC should be followed in full and theproposed construction methods revised accordingly, in order that the

    ground stability issues are managed appropriately

    Risk Mitigation Options

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    57/63

    Main additional measure identified is pressure limitation for onshoresection

    Scope for further risk reduction limited

    Very important that measures already identified and recommended inour report are in place not only when pipeline is new but also

    throughout the life of the pipeline

    Arrangements should be made for an independent audit of construction

    work and an inspection regime established to confirm safe operation ofthe pipeline in future

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    58/63

    Summary of Recommendations and

    Closing Remarks

    Summary of Recommendations (1)

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    59/63

    1. Consideration should be given by the Irish Government to establishing

    a risk-based framework for decisions on proposed and existing major

    hazard pipelines and related infrastructure, to ensure transparency and

    consistency of the decision-making process

    2. A formal integrity management plan should be established prior to

    construction, including the operational and maintenance philosophy,

    and that an independent audit and inspection regime for both the

    construction and operation of the pipeline is established3. The pressure in the onshore pipeline should be limited to enable the

    pipeline to be reclassified as a Class 2 (Suburban) pipeline, with a

    design factor not exceeding 0.3, and the pipeline design revised in

    accordance with PD 8010

    Summary of Recommendations (2)

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    60/63

    4. A full and technically thorough reliability analysis should be carried out

    of the subsea pressure control and isolation systems specified in the

    field design to enable appropriate additional pressure control measures

    to be implemented and the effective limitation of the pressure in the

    onshore pipeline demonstrated

    5. The recommendations made by AGEC should be followed in full and

    the proposed construction methods revised accordingly, in order that

    the ground stability issues are managed appropriately6. In the event that additional fields were proposed to be tied in to the

    pipeline at any future date, a full review would be required to consider

    issues such as extension of the life beyond the initial design life,

    changes in the fluids in the pipeline or changes in the operatingpressures

    Closing Remarks (1)

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    61/63

    We recognise the real concerns over the safety of the Corrib pipeline

    The review has been undertaken by independent, professional staff withwide-ranging experience of pipeline safety issues including pipeline

    incidents We have applied world class risk assessment tools and methodologies

    for the assessment of risk from gas pipelines, validated by full scale

    experiments and incident data

    In making our recommendations, we have taken into account thesocietal concerns and the uncertainty in risk analysis

    Our recommendations are in line with the principles embodied in soundengineering design standards for pipelines

    Closing Remarks (2)

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    62/63

    The fact that a new design is not fully covered by an existing standarddoes not make it unsafe, but it does make the requirement to

    demonstrate that the design is safe more onerous

    Based on a rigorous assessment of the detailed engineeringdocumentation, we have identified a number of areas where importanttechnical issues must be addressed

    Provided that these detailed recommendations are followed, the

    pressure is limited effectively as recommended, and a robust integritymanagement plan is in place to ensure that safety levels are maintained

    throughout the life of the pipeline, we believe that there will be a

    substantial safety margin in the pipeline design

    Closing Remarks (3)

  • 8/8/2019 Adv Antic a Presentation on Draft Report

    63/63

    We recognise that it is the nature of any review of this type that areaswhere problems are identified are given a high profile, whereas much of

    the engineering design work is satisfactory and receives little credit

    We would like to recognise the co-operation received from Shell andtheir contractors, including responses to requests for information

    We would also like to thank those that made submissions as part of theprocess, both written and oral, and in particular the courtesy shown to

    us at the oral hearings