PROCESS SUMMARY FOR BASE Set Up Number Operation Description Machine Tool Description 10Cut-off 0.50 in. x 2.25 in. cross sections of cast sheet acrylic stock to a length of 5.25 .015 in. Cut-off Saw 20Fabricate background housing on the planar surface opposite datum feature A 3 axis vertical machining center 30Polish all surfaces of the basePropane torch
Citation preview
Adrian AllenSteven LonaNicholas Tracy
Ideas-Unlimited
Changes since last time…•New logo was added to repertoire.
•Material change from ¾” to ½” acrylic.
•New through hole design for clock insert.
•New base design. (no adhesive)
•Inscription added to clock base.
PROCESS SUMMARY FOR BASE
Set Up Number Operation Description
Machine Tool Description
10 Cut-off 0.50 in. x 2.25 in. cross sections of cast sheet acrylic stock to a length of 5.25 .015 in.
Cut-off Saw
20 Fabricate background housing on the planar surface opposite datum feature A
3 axis vertical machining center
30 Polish all surfaces of the base Propane torch
B
5.25 +/- 0.015
2.25 +/- 0.015
0.125 +/- 0.01
A
Set Up 20 SketchScale: 1:1Units: Inches
0.4375 +/- 0.01
0.50
0.125+/- 0.01
Set Up 20 Descriptionfor Clock Base
REQUIRED TOOLS
MACHINE TOOLS: Vertical Machining Center, VF-OE
FIXTURE: Kurt Vise with 1 ¼” parallels
CUTTING TOOLS: 7/16 inch Double Flute End Mill
MISCELLANEOUS TOOLS: Edge Finder, Dial Indicator
Operation Number
Operation Description
Tool Number Tool Description
Important Process Parameters
1 Slot mill opposite datum feature A in one pass
1 7/16 inch end mill
d = .125 in.w = 5.25 in.V = 314 fpmF = 0.0042 in/th
Process 20 Description for Base
PROCESS SUMMARY FOR BACKGROUND
Set Up Number Operation Description Machine Tool Description
10 Cut-off a 0.50 in. x 5.25 in. cross section of cast sheet acrylic stock to a length of 8 .015 in.
Cut-off Saw
20 Fabricate clock housing, PSU logo, and circular contours on the planar surface opposite datum feature A.
3 axis vertical machining center
30 Polish all surfaces of the background
Propane torch
5.2500 +/- 0.015 in.
Diameter = 3.75 +/- 0.005in.Hole Diameter = 2.3125 +/-0.005 in.
8.00
+/-
0.01
5in. Logo goes here
Set up 20 Description for Clock Background
REQUIRED TOOLS
MACHINE TOOLS: Vertical Machining Center
FIXTURE: Kurt Vise with 1 ¼” parallels
CUTTING TOOLS: 1/2”, 1/4”, 1/8”, and 1/32” Double Flute End Mills
MISCELLANEOUS TOOLS: Edge Finder, Dial Indicator
Process 20 Description Clock BackgroundOperation Number
Operation Description
Tool Number
Tool Description
Important Process Parameters
1 End mill circular contours on the planar surface opposite datum feature A.
1 1/2 inch end mill
d = 0.60in.V = 314 fpmF = 0.0042 in/th
2 End mill clock housing on the planar surface opposite datum feature A.
2 1/2 inch end mill
d = 0.600 in.V = 314 fpmF = 0.0042 in/th
3 End Mill PSU logo on the planar surface opposite datum feature A.
3 1/4 inch, 1/8 inch, and 1/32 inch end mills
d = 0.02 in.V = 314 fpmF = 0.0042 in/th
Assembly for Acrylic Clock
Join the base and the background by press fitting Insert battery into clock insertPlace clock insert into clock housing
Bill of MaterialsAcrylic Sheet (48 x 96)inch = $215
Clock Insert = $5.90 (30 count) = $177
Batteries = $0.55 (30 count) = $16.50
Cost Analysis•Break even point – 22 clocks
–Selling Price of $50
•Want to produce 8 extra for the 3 group members and 5 professors.
Gantt Chart
ID Task Name Start1 Completed Second Prototype Thu 9/27/01
2 Create Production Schedule Tue 10/16/01
3 Order Acrylic Materials Thu 10/18/01
4 Order Batteries and Clock Inserts Thu 10/18/01
5 Receive Materials Thu 11/1/01
6 Production Run Tue 11/6/01
7 Thanksgiving Break Wed 11/21/01
8 Production Run Cont. (if necessary) Tue 11/27/01