107
October 4, 2019 ADDENDUM NO. 1 EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT ADDENDUM NO. 1 TO THE EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT October 4, 2019 The following addendum shall be made part of the Contract Documents and the bidder shall acknowledge receipt thereof on Bid Form page 1 of 16. The deadline for submitting sealed bids is unchanged and remains as 2:00 p.m. on Thursday, October 24, 2019 at 1966 Olivenhain Road, Encinitas, CA 92024. ADDENDUM SECTION 1 – Changes to the Contract Documents 1. Table of Contents: REMOVE Table of Contents and REPLACE with Table of Contents-Revised. 2. Bid Form: REMOVE Bid Form and REPLACE with Bid Form-Revised. 3. Agreement: REMOVE Agreement and REPLACE with Agreement-Revised. 4. Section 00810 Supplemental to the General Provisions: REMOVE section 00810 and REPLACE section 00810 Supplemental to General Provisions-Revised. 5. Section 01043 Coordination with Owner’s Operations: REMOVE section 01043 and REPLACE with section 01043 Coordination with Owner’s Operations-Revised. 6. Section 01150 Measurement and Payment: REMOVE section 01150 and REPLACE with section 01150 Measurement and Payment-Revised. 7. Section 02222 Protecting Existing Underground Utilities: ADD section 02222 Protecting Existing Underground Utilities. 8. Section 02743 Asphalt Concrete Paving: REMOVE section 02743 and REPLACE with Section 02743 Asphalt Concrete Paving-Revised. 9. Section 17000 Special Provisions per the City of Encinitas: REMOVE section 17000 and REPLACE Section 17000 Special Provisions per the City of Encinitas-Revised. 10. Construction Drawings for the El Camino Real Pipeline Replacement and Green Bike Lane Project: REMOVE sheets TS-001 through TS -009 dated 06.07.2019 and REPLACE with sheets TS- 001 through TS-010 dated 10.03.2019. END OF ADDENDUM NO. 1 Attachments: Table of Contents-Revised Bid Form-Revised Agreement-Revised Section 00810 Supplemental to General Provisions-Revised Section 01043 Coordination with Owner’s Operations-Revised Section 01150 Measurement and Payment-Revised Section 02222 Protecting Existing Underground Utilities-Revised Section 02743 Asphalt Concrete Paving-Revised

ADDENDUM NO. 1 TO THE EL CAMINO REAL PIPELINE …...EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT ADDENDUM NO. 1 TO THE EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

October 4, 2019 ADDENDUM NO. 1 EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

ADDENDUM NO. 1

TO THE EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

October 4, 2019

The following addendum shall be made part of the Contract Documents and the bidder shall acknowledge receipt thereof on Bid Form page 1 of 16. The deadline for submitting sealed bids is unchanged and remains as 2:00 p.m. on Thursday, October 24, 2019 at 1966 Olivenhain Road, Encinitas, CA 92024. ADDENDUM SECTION 1 – Changes to the Contract Documents

1. Table of Contents: REMOVE Table of Contents and REPLACE with Table of Contents-Revised. 2. Bid Form: REMOVE Bid Form and REPLACE with Bid Form-Revised. 3. Agreement: REMOVE Agreement and REPLACE with Agreement-Revised. 4. Section 00810 Supplemental to the General Provisions: REMOVE section 00810 and REPLACE

section 00810 Supplemental to General Provisions-Revised. 5. Section 01043 Coordination with Owner’s Operations: REMOVE section 01043 and REPLACE

with section 01043 Coordination with Owner’s Operations-Revised. 6. Section 01150 Measurement and Payment: REMOVE section 01150 and REPLACE with section

01150 Measurement and Payment-Revised. 7. Section 02222 Protecting Existing Underground Utilities: ADD section 02222 Protecting Existing

Underground Utilities. 8. Section 02743 Asphalt Concrete Paving: REMOVE section 02743 and REPLACE with Section

02743 Asphalt Concrete Paving-Revised. 9. Section 17000 Special Provisions per the City of Encinitas: REMOVE section 17000 and REPLACE

Section 17000 Special Provisions per the City of Encinitas-Revised. 10. Construction Drawings for the El Camino Real Pipeline Replacement and Green Bike Lane

Project: REMOVE sheets TS-001 through TS -009 dated 06.07.2019 and REPLACE with sheets TS-001 through TS-010 dated 10.03.2019.

END OF ADDENDUM NO. 1 Attachments: Table of Contents-Revised

Bid Form-Revised Agreement-Revised

Section 00810 Supplemental to General Provisions-Revised Section 01043 Coordination with Owner’s Operations-Revised Section 01150 Measurement and Payment-Revised Section 02222 Protecting Existing Underground Utilities-Revised

Section 02743 Asphalt Concrete Paving-Revised

TABLE OF CONTENTS REVISED CONTRACT DOCUMENTS PAGE

ADDENDUM NO.1 TABLE OF CONTENTS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE - 1

PART I BIDDING AND CONTRACT REQUIREMENTS

DIVISION 0 BIDDING AND CONTRACT REQUIREMENTS NOTICE INVITING SEALED PROPOSALS (BIDS) --------------------------------------------- 1 to 4 White BID FORM ----------------------------------------------------------------------------------------------- 1 to 16 Yellow BID BOND ------------------------------------------------------------------------------------------------ 1 to 2 Yellow AGREEMENT ----------------------------------------------------------------------------------------------- 1 to 3 Blue PERFORMANCE BOND --------------------------------------------------------------------------------- 1 to 2 Blue PAYMENT BOND ----------------------------------------------------------------------------------------- 1 to 2 Blue CONTRACTOR'S CERTIFICATE REGARDING WORKERS' COMPENSATION ------------------------------------------------------------------------ 1 to 2 Blue CERTIFICATE OF INSURANCE (WORKERS' COMPENSATION) -------------------------- 1 to 3 Blue INSURANCE ENDORSEMENT (WORKERS' COMPENSATION) --------------------------- 1 to 2 Blue CERTIFICATE OF INSURANCE (LIABILITY) ------------------------------------------------------ 1 to 5 Blue INSURANCE ENDORSEMENT (LIABILITY) ------------------------------------------------------- 1 to 2 Blue CERTIFICATE OF INSURANCE (BUILDERS' RISK "ALL RISK") ---------------------------- 1 to 4 Blue INSURANCE ENDORSEMENT (BUILDERS' RISK "ALL RISK") ----------------------------- 1 to 2 Blue GENERAL PROVISIONS

TABLE OF CONTENTS -------------------------------------------------------------------- 1 to 3 Goldenrod MAIN BODY ----------------------------------------------------------------------------------- 1 to 42 Goldenrod SHOP DRAWING SUBMITTAL FORM ------------------------------------------------- 1 to 1 Goldenrod PROGRESS ESTIMATE AND PAYMENT FORM ----------------------------------- 1 to 1 Goldenrod CONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT ------ 1 to 1 Goldenrod CONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT --------------- 1 to 1 Goldenrod PROPOSED CHANGE ORDER ---------------------------------------------------------- 1 to 1 Goldenrod RESOLUTION OF CONSTRUCTION CLAIMS --------------------------------------- 1 to 4 Goldenrod PUBLIC CONTRACT CODE SECTION 20104, ET SEQ -------------------------- 1 to 4 Goldenrod

SECTION 00810 SUPPLEMENT TO GENERAL PROVISIONS REVISED------------1 to 21 Gray

PART II TECHNICAL SPECIFICATIONS

DIVISION 1 GENERAL REQUIREMENTS (Division 1 – 17 – White) SECTION 01010 SUMMARY OF WORK ---------------------------------------------------------------- 1 to 3 SECTION 01043 COORDINATION WITH OWNER’S OPERATIONS REVISED------------- 1 to 4 SECTION 01045 CUTTING AND PATCHING ---------------------------------------------------------- 1 to 2 SECTION 01070 ABBREVIATIONS AND SYMBOLS ------------------------------------------------ 1 to 3 SECTION 01080 DEFINITIONS ---------------------------------------------------------------------------- 1 to 4 SECTION 01090 REFERENCE STANDARDS --------------------------------------------------------- 1 to 4 SECTION 01150 MEASUREMENT AND PAYMENT REVISED---------------------------------- 1 to 9 SECTION 01201 PRECONSTRUCTION CONFERENCE ------------------------------------------ 1 to 2 SECTION 01202 PROGRESS MEETINGS ------------------------------------------------------------- 1 to 2 SECTION 01310 PROGRESS SCHEDULES ---------------------------------------------------------- 1 to 3

TABLE OF CONTENTS CONTRACT DOCUMENTS PAGE

ADDENDUM No.1 TABLE OF CONTENTS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE - 2

SECTION 01370 SCHEDULE OF VALUES ------------------------------------------------------------- 1 to 2 SECTION 01400 QUALITY CONTROL ------------------------------------------------------------------ 1 to 2 SECTION 01410 TESTING LABORATORY SERVICES -------------------------------------------- 1 to 3 SECTION 01510 TEMPORARY CONSTRUCTION FACILITIES ---------------------------------- 1 to 2 SECTION 01545 PROTECTION OF THE WORK AND PROPERTY ---------------------------- 1 to 4 SECTION 01550 SITE ACCESS --------------------------------------------------------------------------- 1 to 2 SECTION 01560 TEMPORARY CONTROLS ---------------------------------------------------------- 1 to 2 SECTION 01620 STORAGE OF MATERIAL ----------------------------------------------------------- 1 to 2 SECTION 01630 SUBSTITUTIONS ----------------------------------------------------------------------- 1 to 2 SECTION 01700 PROJECT CLOSEOUT --------------------------------------------------------------- 1 to 1 SECTION 01710 CLEANING ------------------------------------------------------------------------------- 1 to 2 SECTION 01720 RECORD DOCUMENTS ------------------------------------------------------------- 1 to 3

DIVISION 2 SITE WORK SECTION 02140 DEWATERING -------------------------------------------------------------------------- 1 to 5 SECTION 02222 PROTECTING EXISTING UNDERGROUND UTILITIES-------------------- 1 to 3 SECTION 02743 ASPHALT CONCRETE PAVING REVISED----------------------------------- 1 to 24

DIVISION 3 CONCRETE (NOT USED)

DIVISION 4 MASONRY (NOT USED)

DIVISION 5 METALS (NOT USED)

DIVISION 6 WOOD AND PLASTICS (NOT USED)

DIVISION 7 THERMAL AND MOISTURE PROTECTION (NOT USED)

DIVISION 8 DOORS AND WINDOWS (NOT USED)

DIVISION 9 FINISHES (NOT USED)

DIVISION 10 SPECIALTIES (NOT USED)

DIVISION 11 EQUIPMENT (NOT USED)

DIVISION 12 FURNISHINGS (NOT USED)

DIVISION 13 SPECIAL CONSTRUCTION (NOT USED)

DIVISION 14 CONVEYING SYSTEMS (NOT USED)

DIVISION 15 MECHANICAL

SECTION 15011 WET TAPS AND TEMPORARY PIPING SYSTEMS -------------------------- 1 to 5 SECTION 15294 FUSIBLE POLYVINYL CHLORIDE (PVC) PIPE ----------------------------- 1 to 20

TABLE OF CONTENTS CONTRACT DOCUMENTS PAGE

ADDENDUM No.1 TABLE OF CONTENTS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE - 3

DIVISION 16 ELECTRICAL (NOT USED)

DIVISION 17 OTHER SECTION 17000 SPECIAL PROVISIONS PER THE CITY OF ENCINITAS REVISED ---- 1 to 4

APPENDIX A: City of Encinitas Requirements APPENDIX B: Encina Wastewater Authority Special Use Discharge Permit Application APPENDIX C: California Well Standards: Bulletin 74-90, Part III and County of San Diego, Department of Environmental Health, L&WQ Div Fee Schedule

REFERENCE STANDARDS Olivenhain Municipal Water District, Standard Specifications and Drawings for the Construction of Water, Recycled Water, and Sewer Facilities, February 2017. City of Encinitas, Design and Construction Standards. City of Encinitas Urban Forest Management Program Standard Specifications for Public Works Construction, “Greenbook”, 2018. San Diego Regional Standard Drawings (Latest Edition).

PROJECT PLANS Construction Drawings for the El Camino Real Pipeline Replacement and Green Bike Lane Project (56 Sheets bound separately).

SUPPLEMENTAL DOCUMENTS Encina Wastewater Authority Pretreatment Ordinance Encina Wastewater Authority Source Control Program: https://www.encinajpa.com/environment-resource-management/source-control-program Geotechnical Investigation, Environmental Soil Testing, and Boring Completion Report California Well Standards: Bulletin 74-90 San Diego County: Department of Environmental Health; Land and Water Quality Division - https://www.sandiegocounty.gov/deh/

END TABLE OF CONTENTS

(BLANK)

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 1 OF 16

BID FORM REVISED

PROPOSAL TO OLIVENHAIN MUNICIPAL WATER DISTRICT

SAN DIEGO COUNTY, CALIFORNIA

FOR THE CONSTRUCTION OF

EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Name of Bidder:

Business Address:

Phone No.:

TO THE GOVERNING BODY OF THE OLIVENHAIN MUNICIPAL WATER DISTRICT

Pursuant to and in compliance with your Notice Inviting Sealed Proposals (Bids) and the other documents relating thereto, the undersigned Bidder, being fully familiar with the terms of the Contract Documents, local conditions affecting the performance of the Contract, the character, quality, quantities, and scope of the work, and the cost of the work at the place where the work is to be done, hereby proposes and agrees to perform within the time stipulated in the Contract, including all of its component parts and everything required to be performed, and to furnish any and all of the labor, material, tools, equipment, transportation, services, permits, utilities, and all other items necessary to perform the Contract and complete in a workmanlike manner, all of the work required in connection with the construction of said work all in strict conformity with the Plans and Specifications and other Contract Documents, including Addenda Nos. __, __ and __ for the prices hereinafter set forth.

The undersigned as Bidder, declares that the only persons or parties interested in this proposal as principals are those named herein; that this proposal is made without collusion with any person, firm, or corporation; and he proposes and agrees, if the proposal is accepted, that he will execute a Contract with the Owner in the form set forth in the Contract Documents.

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 2 OF 16

BIDDING INSTRUCTIONS

FOR THE CONSTRUCTION OF

EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Prior to the opening of bids, all questions relative to this project shall be directed to the Owner. Bidders are encouraged to submit their pre-bid questions as early as possible, in writing by fax or mail, so they can be answered in writing through addendum, if necessary. Questions may be taken verbally; however, written questions will be given priority, and verbal questions run the risk of not being answered. Pre-bid questions will be received up to 5:00 p.m., October 17, 2019, after which they will not be answered.

Bidders shall have a minimum of five (5) years of successful prior experience performing the type of work required by this Contract. Bidders failing to demonstrate this experience may be rejected as nonresponsive at the option of the Owner.

Bidders agree to obtain and maintain in full effect all required insurance with limits not less than the amounts indicated. Insurers must be authorized to do business and have an agent for service of process in California, have an "A" policyholder's rating and a financial rating of at least Class VI in accordance with the most current rating by A.M. Best Company. Bidders who fail to comply with the insurance requirements of this Contract may have their bids rejected as nonresponsive at the election of the Owner.

The Bidder's attention is directed to Article 3-1 "Award of Contract or Rejection of Bids" in the General Provisions concerning the above conditions.

There are multiple Bid Schedules. In order for the Owner to consider a Bidder's proposal and for a proposal to be considered responsive, all bid schedules must be completed. If any bid schedule is not filled in, the bid will be determined to be non-responsive and will be rejected. The Owner reserves the right to delete certain Bid Schedules, to select the Bid Schedules under which the bids are to be compared, to reject any and all bids, to waive any irregularity in the bids received and to award the Contract on the basis of the responsive bids. The low bid will be determined by the amount of the bid for only the work to be completed and based on the total of the Bid Schedules selected by the Owner.

Bidders must satisfy themselves as to the character of the work to be performed by examination of the site and review of the Contract Documents. After bids have been submitted, the Bidder expressly waives the right to assert that there was a misunderstanding concerning the nature of the work to be done. Any bid protests must be submitted within three (3) calendar days of the bid.

The Contract Documents contain the provisions required for the construction of the Project. Information obtained from an officer, agent, or employee of the Owner or any other personnel shall not affect the risks or obligations assumed by the Contractor, or relieve him from fulfilling any of the conditions of the Contract.

Bids shall be submitted on the Bid Form and Bid Bond included within these Contract Documents. Bidders shall designate the subcontractors and list the manufacturers of materials to be used in the Project on the Designation of Subcontractors form included with these Contract Documents. All subcontractors listed to perform any of the work must be licensed in the State of California. No single subcontractor may perform more than 25% of the work listed in the Bid Schedule unless specifically approved in advance by the District prior to the submission of bids. The Owner reserves the right to find a bid non-responsive in its sole discretion if a Bidder lists any unlicensed subcontractors to perform any of the work. Submit with the bid the completed Certificate of Drug-Free Workplace, Certificate of Nondiscrimination, Noncollusion Affidavit, Designation of Subcontractors, Bidder's Experience, and Insurance Acknowledgment included in the Bid Form. The Owner reserves the right to find a bid non-responsive in its sole discretion of a Bidder fails to

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 3 OF 16

complete or include any of the aforementioned certificates or acknowledgements. An optional one page Bid Form Checklist included in front of the Table of Contents has been provided to assist with ensuring all required documents are submitted, Contractors are encouraged to include the Completed Bid Form Checklist at the front of their submitted bid, however submittal of the Bid Form Checklist is optional.

The pay items listed in each Bid Schedule are described in Specification Section 1150 – Measurement and Payment.

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 4 OF 16

BID SCHEDULE I – EL CAMINO REAL PIPELINE REPLACEMENT

EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Item Item Description Quantity Unit Amount

I-A. Mobilization, Demobilization, Bonds, Permits, Insurance, & Cleanup for all work required under this Bid Schedule I:

1

LS

$

I-B. Excavation Support System for all work required by this Bid Schedule:

1

LS

$

I-C. Potholing for all work required by this Bid Schedule:

1

LS

$

I-D. Dewatering for all work required by this Bid Schedule:

1

LS

$

I-E. Hazardous Waste Disposal for all work required by this Bid Schedule:

Unit Price: $ ____________ / CY

300

CY

$

I-F. Pipeline Segment A (STA 1+00 to 7+35), HGL 482 Pipeline Section, including Stormwater Pollution Prevention Plan, Traffic Control, Restriping, Temporary Water Service, Over-Excavation and Backfill, Service Lines and Connections, Fire Hydrant Assemblies, Blowoffs, AVAR, and appurtenant items:

1

LS

$

I-G. Pipeline Segment B (STA 46+26 to 56+98), HGL 437 Pipeline Section, including Stormwater Pollution Prevention Plan, Traffic Control, Restriping, Temporary Water Service, Over-Excavation and Backfill, Service Lines and Connections, Fire Hydrant Assemblies, Blowoffs, AVAR, and appurtenant items:

1

LS

$

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 5 OF 16

BID SCHEDULE I – EL CAMINO REAL PIPELINE REPLACEMENT

EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Item Item Description Quantity Unit Amount

I-H. Pipeline Segment C (STA 37+29 to 46+26), HGL 437 Pipeline Section, including Stormwater Pollution Prevention Plan, Traffic Control, Restriping, Temporary Water Service, Over-Excavation and Backfill, Service Lines and Connections, Fire Hydrant Assemblies, Blowoffs, AVAR, and appurtenant items:

1

LS

$

I-I. Pipeline Segment D (STA 26+24 to 37+29), HGL 437 Pipeline Section, including Stormwater Pollution Prevention Plan, Traffic Control, Restriping, Temporary Water Service, Over-Excavation and Backfill, Service Lines and Connections, Fire Hydrant Assemblies, Blowoffs, AVAR, and appurtenant items:

1

LS

$

I-J. Pipeline Segment E (STA 10+00 to 26+24), HGL 437 Pipeline Section, including Stormwater Pollution Prevention Plan, Traffic Control, Temporary Water Service, Over-Excavation and Backfill, Restriping, Service Lines and Connections, Fire Hydrant Assemblies, Blowoffs, AVAR, and appurtenant items:

1

LS

$

I-K. Deep Anode Abandonment, including all work required for the proper abandonment of the cathodic deep well anode Station 20+32 and associated rectifier and meter:

1

LS

$

I-L. Base and Final Pavement Asphalt Concrete:

Unit Price: $ _____________ / TON

2000

TON

$

I-M. Emulsion Aggregate Slurry from Encinitas Blvd to Garden View Road (Striping STA 11+40 to 59+50):

Unit Price: $ ____________ / SY

52,200

SY

$

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 6 OF 16

BID SCHEDULE I – EL CAMINO REAL PIPELINE REPLACEMENT

EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Item Item Description Quantity Unit Amount

I-N. Additional Slurry Seal for all work required by this Bid Schedule:

Unit Price: $ ____________ / SY

1,500

SY

$

I-O. Restriping from Encinitas Blvd to Garden View Road (Striping STA 11+40 to 59+50):

1

LS

$

I-P. Potholing Utilities not Shown on Plans 25 EA $______________

I-Q. Allowance for Unsuitable Material 100 CY $______________

TOTAL AMOUNT OF BID SCHEDULE I

$

TOTAL AMOUNT OF BID SCHEDULE I (IN WORDS)

BID SCHEDULE II – GREEN BIKE LANE PROJECT

EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Item Item Description Quantity Unit Amount

II-A. Mobilization, Demobilization, Bonds, Permits, Insurance, & Cleanup for all work required under this Bid Schedule II:

1

LS

$

II-B. Emulsion Aggregate Slurry from Garden View Road to Leucadia Blvd (Striping STA 59+50 to 93+50):

Unit Price: $ ____________ / SY

42,600

SY

$

II-C. Restriping from Garden View Road to Leucadia Blvd (Striping STA 59+50 to 93+50):

1

LS

$

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 7 OF 16

BID SCHEDULE II – GREEN BIKE LANE PROJECT

EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Item Item Description Quantity Unit Amount

II-D. Thermoplastic Crosswalk Striping from Encinitas Blvd to Leucadia Blvd (Striping STA 11+40 to 93+50):

1

LS

$

II-E. Green Bike Lane Striping from Encinitas Blvd to Leucadia Blvd (Striping STA 11+40 to 93+50):

1

LS

$

TOTAL AMOUNT OF BID SCHEDULE II

$

TOTAL AMOUNT OF BID SCHEDULE II (IN WORDS)

TOTAL AMOUNT OF BID SCHEDULE I and II

$

TOTAL AMOUNT OF BID SCHEDULE I and II (IN WORDS)

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 8 OF 16

DESIGNATION OF SUBCONTRACTORS

In compliance with the provisions of Section 4100-4114 of the Public Contract Code of the State of California, and any amendments thereof, each Bidder shall set forth below, the name, license number, and location of the mill, shop or office of each subcontractor who will perform work or labor, or render service to the Contractor in an amount in excess of one-half (1/2) of one (1) percent (0.5%) of the total bid, and the portion of the work which will be done by each subcontractor. All subcontractors listed must be licensed to perform the subcontract work in the State of California. No single subcontractor may perform work in excess of 25% of the total work listed in the Bid Schedule unless specifically approved by the District in advance of submission of the Bid. Bidders who list any unlicensed subcontractors on this form may have their bid rejected as non-responsive in the sole discretion of Owner.

If the Bidder fails to specify a subcontractor for any portion of the work in excess of one-half (1/2) of one (1) percent (0.5%) of the total bid to be performed under the Contract, he shall be deemed to have agreed to perform such portion himself, and he shall not be permitted to subcontract that portion of the work except under conditions permitted by law.

Subletting or subcontracting any portion of the work as to which no subcontractor was designated in the original bid shall only be permitted in case of public emergency or necessity, or otherwise permitted by law, and then only after a finding is reduced to writing as a public record of the Owner.

Trade % of Work

To Be Done Name of

Subcontractor License

Number

Address

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 9 OF 16

LISTING OF MANUFACTURERS

The Contractor shall submit this sheet with his bid, completed, to list the manufacturers of materials he intends to use. It shall be understood that where the Contractor elects to not use the material manufacturers called for in the Specifications, he will substitute only items of equal quality, durability, functional character, and efficiency as determined and approved by the Owner. The Contractor should ascertain the acceptability of substitutes prior to bidding. Only one manufacturer shall be listed for each item.

Item or Material Manufacturer

Substitutions shall be allowed only if requested in accordance with Article 5-10 of the General Provisions within 35 calendar days of the date the Contract is awarded. Should a substitution be allowed, there will be no increase in the amount of the bid originally submitted.

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 10 OF 16

ACCOMPANYING THIS PROPOSAL IS (insert the words "cash", "a cashier's check", "a certified check", or "a Bidder's bond" as the case may be) in an amount equal to at least 10 percent of the total amount of the Bid, payable to the

OLIVENHAIN MUNICIPAL WATER DISTRICT

The undersigned deposits the above-named security as a proposal guarantee and agrees that it shall be forfeited to the Owner as liquidated damages in case this proposal is accepted by the Owner and the undersigned fails to execute a contract with the Owner as specified in the Contract Documents or fails to furnish the required payment and performance bonds, and insurance certificates and endorsements. Should the Owner be required to engage the services of an attorney in connection with the enforcement of this bid, Bidder promises to pay Owner's reasonable attorneys' fees, incurred with or without suit.

The names of all persons interested in the foregoing proposals as principals are as follows: (NOTICE - If Bidder or other interested person is a corporation, state legal name of corporation, also names of the president, secretary, treasurer, and manager thereof; if a general partnership, state true name of firm, also names of all individual partners composing firm; if a limited partnership, the names of all general partners and limited partners; if Bidder or other interested person is an individual, state first and last names in full; if the Bidder is a joint venture, state the complete name of each venturer).

The Owner has determined the license classification necessary to bid and perform the subject contract. In no case shall this Contract be awarded to a specialty contractor whose classification constitutes less than a majority of the project. When a specialty contractor is authorized to bid a portion of the work of this contract, all work to be performed outside of the contractor's license specialty, except work specifically authorized by the Owner, shall be performed by a licensed subcontractor in compliance with the Subletting and Subcontracting Fair Practices Act commencing with Section 4100 et seq., of the Public Contract Code. See Business and Professions Code Section 7059.

The Contractor's license classification(s) required for this project are as follows:

CLASS A – GENERAL ENGINEERING

It is the Owner's intent that "plans," as used in Public Contract Code Section 3300, is defined as the construction Contract Documents, which include both the Plans and the Specifications.

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 11 OF 16

Bidder warrants and represents that it has at least five (5) years of successful experience performing the type of work required by this Contract.

Bidder warrants and represents, under penalty of perjury, that license(s) required by California State Contractor's License Law for the performance of the subject project are in full effect and proper order. Bidders must state, under penalty of perjury, the Contractor's applicable license classification, license number, license expiration date, name of license holder, and relationship to Bidder. Any bid not containing this information may be considered nonresponsive and may be rejected by the Owner.

Bidders relying upon licenses of Responsible Managing Employees (RME) or Responsible Managing Officers (RMO) agree to provide the Owner with all information it determines necessary to verify that the Bidder complies with California State Contractor's License Law.

License Classification:

License Number:

Expiration Date:

Name of License Holder:

Relationship to Bidder:

Name of Bidder:

Signatures:

Dated: , 20____

NOTE: If Bidder is a corporation, the legal name of the corporation shall be set forth above, together with the signature of the officer or officers authorized to sign contracts on behalf of the corporation and the corporate seal; if Bidder is a partnership, the true name of the firm shall be set forth above, together with the signature of the partner or partners authorized to sign contracts on behalf of the partnership; if the Bidder is an individual, his signature shall be placed above; if the Bidder is a joint venture, the name of the joint venture shall be set forth above with the signature of an authorized representative of each venturer.

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 12 OF 16

CERTIFICATE OF DRUG-FREE WORKPLACE

BIDDER:

The Bidder named above hereby certifies compliance with Government Code Section 8355 in matters relating to providing a drug-free workplace. The above named Bidder will:

1. Publish a statement notifying employees that unlawful manufacture, distribution, dispensation, possession, or use of a controlled substance is prohibited and specifying actions to be taken against employees for violations, as required by Government Code Section 8355(a).

2. Establish a Drug-Free Awareness Program as required by Government Code Section 8355(b), to inform employees about all of the following:

(a) The dangers of drug abuse in the workplace,

(b) The person’s or organization’s policy of maintaining a drug-free workplace,

(c) Any available counseling, rehabilitation and employee assistance programs, and

(d) Penalties that may be imposed upon employees for drug abuse violations.

3. Provide as required by Government Code Section 8355(c), that every employee who works on the proposed contract or loan:

(a) Will receive a copy of the company’s drug-free policy statement, and

(b) Will agree to abide by the terms of the company’s statement as a condition of employment on the contract or loan.

CERTIFICATION

I, the official named below, hereby swear that I am duly authorized legally to bind the Bidder to the above described certification. I am fully aware that this certification, executed on the date and in the county below, is made under penalty of perjury under the laws of the State of California.

OFFICIAL’S NAME:

DATE EXECUTED: EXECUTED IN COUNTY OF:

OFFICIAL'S SIGNATURE:

TITLE:

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 13 OF 16

CERTIFICATE OF NONDISCRIMINATION

1. During the performance of this contract, Bidder and its subcontractors shall not unlawfully discriminate against any employee or applicant for employment because of race, religion, color, national origin, ancestry, physical handicap, medical condition, marital status, age (over 40) or sex. Bidders and subcontractors shall insure that the evaluation and treatment of their employees and applicants for employment are free of such discrimination. Bidder and subcontractors shall comply with the provisions of the Fair Employment and Housing Act (Government Code Section 12900 et seq.) and the applicable regulations promulgated thereunder (California Administrative Code, Title 2, Section 7285.0 et seq.). The applicable regulations of the Fair Employment and Housing Commission implementing Government Code, Section 12900, set forth in Chapter 5 of Division 4 of Title 2 or the California Administrative Code are incorporated into this contract by reference and made a part hereof as if set forth in full. Bidder and its subcontractor shall give written notice of their obligations under this clause to labor organizations with which they have a collective bargaining or other agreement.

2. This Bidder shall include the nondiscrimination and compliance provisions of this clause in all subcontracts to perform work under the contract.

THE UNDERSIGNED CERTIFIES THAT THE BIDDER WILL COMPLY WITH THE ABOVE REQUIREMENTS.

BIDDER NAME:

CERTIFIED BY:

NAME: TITLE:

SIGNATURE: DATE:

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 14 OF 16

NONCOLLUSION AFFIDAVIT

State of ) ) ss. County of )

I, , being duly sworn, deposes and says that he or she is of

, the party making the foregoing bid, that the bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation; that the bid is genuine and not collusive or sham; that the bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or that anyone shall refrain from bidding; that the bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference, with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder, or to secure any advantage against the public body awarding the contract of anyone interested in the proposed contract; that all statements contained in the bid are true; and, further, that the bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, or paid, and will not pay, any fee to any corporation, partnership, company association, organization, bid depository, or to any member or agent thereof the effectuate a collusive or sham bid.

Signature of Bidder:

Subscribed and sworn to before me on this day of , 20__.

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 15 OF 16

BIDDER'S EXPERIENCE

Name of Bidder:

License Number:

List a minimum of five (5) similar projects successfully completed by the Bidder during the last five (5) years. Projects not similar in scope, fee, and complexity will not be considered as representative of this project.

Project Name Project Owner's Name, Date and Location Address & Telephone No. Completed

I declare, under penalty of perjury, that the foregoing is true and correct.

Dated: , 20___ (Signature of Bidder)

ADDENDUM NO.1 BID FORM REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 16 OF 16

INSURANCE ACKNOWLEDGMENT

On behalf of the Bidder making this proposal, the undersigned warrants and represents that the Bidder has carefully read and understood all of the insurance requirements of the Contract Documents and has included the full cost of providing insurance meeting all requirements of the Contract Documents in the bid.

Upon request by Owner prior to the time of Award, the Bidder agrees to promptly provide Owner with letters from insurance companies meeting the requirements of the Contract Documents verifying that they are prepared to issue insurance to Bidder meeting all requirements of the Contract Documents. The failure of Bidder to provide Owner with this proof of insurance prior to the time of Award shall entitle Owner to reject the Bidder's bid as nonresponsive and to Award the bid to the next lowest Bidder at the sole discretion of Owner.

The failure of Bidder to provide Owner with insurance meeting all requirements of the Contract Documents within 15 calendar days after the Award, shall constitute a material breach of the Contract, entitling Owner to terminate the Contract and call the bid bond.

By dating and executing this Insurance Acknowledgment, Bidder hereby accepts all terms and conditions of this Insurance Acknowledgment and agrees to be bound by all of its terms.

Dated:________________, 20___

(Name of Bidder)

(Signature)

(Typed Name and Title)

OLIVENHAIN MWD BID BOND EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 1 OF 2

BID BOND

We, as Principal, and

as Surety, jointly and severally, bind ourselves, our heirs, representatives, successors and assigns, as set forth herein, to the

OLIVENHAIN MUNICIPAL WATER DISTRICT

(herein called Owner) for payment of the penal sum of Dollars ($____________), lawful money of the United States. Principal has submitted the accompanying bid for the construction of

EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

If the Principal is awarded the Contract and enters into a written contract, in the form prescribed by the Owner, at the price designated by his bid, and files two bonds with the Owner, one to guarantee payment for labor and materials and the other to guarantee faithful performance, in the time and manner specified by the Owner, and carries all insurance in type and amount which conforms to the Contract Documents and furnishes required certificates and endorsements thereof, then this obligation shall be null and void; otherwise it shall remain in full force and effect.

Forfeiture of this bond, or any deposit made in lieu thereof, shall not preclude the Owner from seeking all other remedies provided by law to cover losses sustained as a result of the Principal's failure to do any of the foregoing.

OLIVENHAIN MWD BID BOND EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 2 OF 2

Principal and Surety agree that if the Owner is required to engage the services of an attorney in connection with the enforcement of this bond, each shall pay Owner's reasonable attorney's fees incurred with or without suit.

Executed on , 20___

PRINCIPAL

By:

(Seal if Corporation) Title:

(Attach Acknowledgment of Authorized Representative of Principal)

Any claims under this bond may be addressed to: (name and address of Surety) (name and address of Surety's agent for service of process in California, if different from above) (telephone number of Surety’s agent in California)

(Attach Acknowledgment) SURETY

By: (Attorney-in-Fact)

NOTICE:

No substitution or revision to this bond form will be accepted. Sureties must be authorized to do business in and have an agent for service of process in California. A certified copy of the Power of Attorney must be attached.

ADDENDUM NO.1 AGREEMENT REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 1 OF 3

AGREEMENT REVISED

THIS AGREEMENT, made and entered into by and between the

OLIVENHAIN MUNICIPAL WATER DISTRICT

hereinafter referred to as "OWNER" and

;

a corporation under the laws of the state of ;

a partnership composed of

;

a joint venture composed of

;

an individual doing business as ;

hereinafter referred to as "CONTRACTOR."

OWNER and CONTRACTOR agree as follows:

(1) SCOPE OF WORK: CONTRACTOR will furnish all materials and will perform all of the work for the construction of the

EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

in accordance with the plans and specifications and other contract documents therefor.

(2) TIME OF COMPLETION: The work shall be completed within the times set forth in the Special Provisions. Time is of the essence.

(3) CONTRACT SUM: OWNER will pay CONTRACTOR in accordance with the prices shown in the Bid Form.

(4) PAYMENTS: Monthly progress payments and the final payment will be made in accordance with the General Provisions as modified by the Special Provisions. The filing of the notice of completion by OWNER shall be preceded by acceptance of the work made only by an action of the Governing Body of OWNER in session.

(5) COMPLIANCE WITH PUBLIC CONTRACTS LAW: OWNER is a public agency in the State of California and is subject to the provisions of law relating to public contracts. It is agreed that all provisions of law applicable to public contracts are a part of this Contract to the same extent as though set forth herein and will be complied with by CONTRACTOR.

ADDENDUM NO.1 AGREEMENT REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 2 OF 3

(6) CONTRACT DOCUMENTS: The complete contract includes all the contract documents set forth herein, to wit: Notice Inviting Sealed Proposals (Bids), Bid Form, Bid Bond, Agreement, Performance Bond, Payment Bond, Contractor's Certificate Regarding Workers' Compensation, Certificate of Insurance (Workers' Compensation and Employer’s Liability), Insurance Endorsement (Workers' Compensation and Employer’s Liability), Certificate of Insurance (Liability), Insurance Endorsement (Liability), Certificate of Insurance (Builders' Risk "All Risk"), Insurance Endorsement (Builders' Risk "All Risk"), General Provisions, Special Provisions, Standard Specifications, Standard Drawings, Referenced Permits, Drawings, Plans, and also addenda thereto and supplemental agreements.

This Agreement is executed by the OWNER pursuant to an action of its Governing Body in session on , 20 , authorizing the same, and CONTRACTOR has caused this Agreement to be duly executed.

Dated: , 20 By: (Authorized Representative of Owner)

Title:

GENERAL MANAGER

Dated: , 20

(Contractor)

By: (Authorized Representative of Contractor)

Title:

(Seal if Corporation)

(Attach Acknowledgment for Authorized Representative of Contractor)

APPROVED:

(Attorney for OWNER) Date

ADDENDUM NO.1 AGREEMENT REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 3 OF 3

CERTIFICATE OF CONTRACTOR

I, , certify that I am a/the

[designate sole proprietor, partner in partnership, or specify corporate office, e.g., secretary] in the entity named as CONTRACTOR in the foregoing contract.

I hereby expressly certify that the name of the entity to which I am associated is

;

that this entity is in good standing and has complied with all applicable laws and regulations, and that I have been expressly authorized by the proper parties in this entity to execute this contract on behalf of the above-named entity.

(Signature)

ATTEST:

Name: (Please Type)

Title:

(BLANK)

ADDENDUM NO. 1 PERFORMANCE BOND REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 1 OF 2

PERFORMANCE BOND

We, as Principal,

and as Surety, jointly and severally, bind ourselves, our heirs, representatives, successors and assigns, as set forth herein, to the

OLIVENHAIN MUNICIPAL WATER DISTRICT

(herein called Owner) for payment of the penal sum of

Dollars ($ ),

lawful money of the United States. Owner has awarded Principal a contract for the construction of

EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

THE CONDITION OF THIS OBLIGATION IS SUCH that if the Principal shall in all things abide by and well and truly keep and perform the covenants, and agreements in the said contract, and any alteration thereof made as therein provided, on his part to be kept and performed at the time and in the manner therein specified, including all guarantees of workmanship and/or materials for a three (3) year period, and shall indemnify and save harmless the Owner, District, the Engineer/Architect, the Owner's Representative, and their consultants, and each of their directors, officers, employees, and agents, as therein stipulated, this obligation shall become null and void, otherwise, it shall be and remain in full force and effect.

Surety agrees that no change, extension of time, alteration, or addition to the terms of the contract, or the work to be performed thereunder, or the plans and specifications shall in any wise affect its obligation on this bond, and it does hereby waive notice thereof.

Principal and Surety agree that if the Owner is required to engage the services of an attorney in connection with the enforcement of this bond, each shall pay Owner's reasonable attorney's fees incurred, with or without suit, in addition to the above sum.

ADDENDUM NO. 1 PERFORMANCE BOND REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 2 OF 2

Executed in four original counterparts on , 20

PRINCIPAL

By:

(Seal if Corporation) Title:

(Attach Acknowledgment of Authorized Representative of Principal)

Any claims under this bond may be addressed to:

(name and address of Surety) (name and address of Surety's agent for service of process in California, if different from above) (telephone number of Surety’s agent in California)

(Attach Acknowledgment) SURETY

By: (Attorney-in-Fact)

APPROVED:

(Attorney for OWNER) Date

NOTICE:

No substitution or revision to this bond form will be accepted. Sureties must meet all requirements of Code of Civil Procedure Section 995.660(a). A certified copy of the Power of Attorney must be attached.

ADDENDUM NO. 1 PAYMENT BOND REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 1 OF 2

PAYMENT BOND

We, as Principal,

and as Surety, jointly and severally, bind ourselves, our heirs, representatives, successors and assigns, as set forth herein, to the

OLIVENHAIN MUNICIPAL WATER DISTRICT

(herein called Owner) for payment of the penal sum of

Dollars ($ ),

lawful money of the United States. Owner has awarded Principal a contract for the construction of

EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

If Principal or any of his subcontractors fails to pay any of the persons named in Section 3181 of the California Civil Code, or amounts due under the Unemployment Insurance Code with respect to work or labor performed under the contract or during the three-year guarantee period, or for any amounts required to be deducted, withheld, and paid over to the Franchise Tax Board from the wages of employees of the contractor and his subcontractors pursuant to Section 13020 of the Unemployment Insurance Code, with respect to such work and labor, then Surety will pay the same in an amount not exceeding the sum specified above, and also will pay, in case suit is brought upon this bond, such reasonable attorney's fees as shall be fixed by the court.

This bond shall inure to the benefit of any of the persons named in Section 3181 of the California Civil Code, so as to give a right of action to them or their assigns in any suit brought upon this bond.

Surety agrees that no change, extension of time, alteration, or addition to the terms of the contract, or the work to be performed thereunder, or the plans and specifications shall in any wise affect its obligation on this bond, and it does hereby waive notice thereof.

Principal and Surety agree that should Owner become a party to any action on this bond that, each will also pay Owner's reasonable attorney's fees incurred therein in addition to the sum above set forth.

ADDENDUM NO. 1 PAYMENT BOND REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 2 OF 2

Executed in four original counterparts on , 20

PRINCIPAL

By:

(Seal if Corporation) Title:

(Attach Acknowledgment of Authorized Representative of Principal)

Any claims under this bond may be addressed to:

(name and address of Surety) (name and address of Surety's agent for service of process in California, if different from above) (telephone number of Surety’s agent in California)

(Attach Acknowledgment) SURETY

By: (Attorney-in-Fact)

APPROVED:

(Attorney for OWNER) Date

NOTICE:

No substitution or revision to this bond form will be accepted. Sureties must meet all requirements of Code of Civil Procedure Section 995.660(a). A certified copy of the Power of Attorney must be attached.

ADDENDUM NO. 1 CONTRACTOR’S CERTIFICATE (WORKERS’ COMP) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 1 OF 2

CONTRACTOR'S CERTIFICATE REGARDING WORKERS' COMPENSATION

Name of Contract: EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Name of Owner: OLIVENHAIN MUNICIPAL WATER DISTRICT

Labor Code Section 3700:

"Every employer except the State shall secure the payment of compensation in one or more of the following ways:

(a) By being insured against liability to pay compensation in one or more insurers duly authorized to write compensation insurance in this State.

(b) By securing from the Director of Industrial Relations a certificate of consent to self-insure, which may be given upon furnishing proof satisfactory to the Director of Industrial Relations of ability to self-insure and to pay any compensation that may become due to his employees.

(c) For all political subdivisions of the state, including each member of a pooling arrangement under a joint exercise of powers agreement (but not the state itself), by securing from the Director of Industrial Relations a certificate of consent to self-insure against workers' compensation claims, which certificate may be given upon furnishing proof satisfactory to the director of ability to administer workers' compensation claims that may become due to its employees. On or before March 31, 1979, a political subdivision of the state which, on December 31, 1978, was uninsured for its liability to pay compensation, shall file a properly completed and executed application for a certificate of consent to self-insure against workers' compensation claims. The certificate shall be issued and be subject to the provisions of Section 3702."

I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for workers' compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this Contract.

ADDENDUM NO. 1 CONTRACTOR’S CERTIFICATE (WORKERS’ COMP) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 2 OF 2

Dated: , 20 (Contractor)

By:

(Authorized Representative of Contractor)

Title:

(Seal if Corporation)

(Labor Code Section 1861 provides that the above certificate must be signed and filed by the Contractor with the Owner prior to performing any work under this Contract.)

ADDENDUM NO. 1 CERTIFICATE OF INSURANCE (WORKERS’ COMP) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 1 OF 3

CERTIFICATE OF INSURANCE

Name of Contract: EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Name of Owner: OLIVENHAIN MUNICIPAL WATER DISTRICT

Type of Insurance: WORKERS' COMPENSATION INSURANCE AND EMPLOYER’S LIABILITY INSURANCE

THIS IS TO CERTIFY that the following policy has been issued by the below-stated company in conformance with the requirements of Articles 8-1 and 8-2 of the General Provisions and is in force at this time.

The Company will give at least 30 days' written notice by certified mail to the Owner and Engineer/Architect prior to any material change or cancellation of said policy.

POLICY NUMBER EXPIRATION DATE TYPE OF INSURANCE LIMITS OF LIABILITY

A. WORKERS' COMPENSATION Statutory Limits

Under the Laws of the State of California

B. EMPLOYER’S LIABILITY Each

Employee Each Accident

Bodily Injury By Accident $ $

Bodily Injury By Disease $ $

Named Insured (Contractor) Insurance Company

Street Number Street Number

City and State City and State

By: (Company Representative) (SEE NOTICE ON PAGE 3 OF 3)

ADDENDUM NO. 1 CERTIFICATE OF INSURANCE (WORKERS’ COMP) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 2 OF 3

NOTARY PUBLIC State of ) ) ss. County of ) A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document On____________________________before me,_______________________________________________ Date Here Insert Name and Title of the Officer Personally appeared _____________________________________________________________________ Name(s) of Signer(s) ____________________________________________________________________________________ Who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subsicribed to the withing instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and official seal

NOTARY PUBLIC

Insurance Company Agent for Service of Process in California:

Name Agency

Street Number Street Number

City and State City and State

Telephone Number Telephone Number

This certificate or verification of insurance is not an insurance policy and does not amend, extend, or alter the coverage afforded by the policies listed herein. Notwithstanding any requirement, term, or condition of any contract or other document with respect to which this certificate or verification of insurance may be issued or may pertain, the insurance afforded by the policies described herein is subject to all the terms, exclusions, and conditions of such policies.

ADDENDUM NO. 1 CERTIFICATE OF INSURANCE (WORKERS’ COMP) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 3 OF 3

NOTICE:

No substitution or revision to the above certificate form will be accepted. If the insurance called for is provided by more than one insurance company, a separate certificate in the exact above form shall be provided for each insurance company.

Insurers must be authorized to do business and have an agent for service of process in California, have an "A" policyholder's rating and a financial rating of at least Class VI in accordance with the most current rating by A.M. Best Company.

(BLANK)

ADDENDUM NO. 1 INSURANCE ENDORSEMENT (WORKERS’ COMP) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 1 OF 2

INSURANCE ENDORSEMENT

Name of Contract: EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Name of Owner: OLIVENHAIN MUNICIPAL WATER DISTRICT

Type of Insurance: WORKERS' COMPENSATION INSURANCE AND EMPLOYER’S LIABILITY INSURANCE

This endorsement forms a part of Policy No. .

ENDORSEMENT:

It is agreed that with respect to such insurance as is afforded by the policy, the Company waives any right of subrogation it may acquire against the Owner, the Engineer/Architect, the Owner's Representative, and their consultants, and each of their directors, officers, employees, and agents by reason of any payment made on account of injury, including death resulting therefrom, sustained by any employee of the insured, arising out of the performance of the above-referenced contract.

This endorsement does not increase the Company's total limits of liability.

Named Insured (Contractor) Insurance Company

Street Number Street Number

City and State City and State

By: (Company Representative) (SEE NOTICE ON PAGE 2 OF 2)

ADDENDUM NO. 1 INSURANCE ENDORSEMENT (WORKERS’ COMP) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 2 OF 2

State of ) ) ss. County of ) A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document On____________________________before me,_______________________________________________ Date Here Insert Name and Title of the Officer Personally appeared _____________________________________________________________________ Name(s) of Signer(s) ____________________________________________________________________________________ Who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subsicribed to the withing instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and official seal

NOTARY PUBLIC

NOTICE:

No substitution or revision to the above endorsement form will be accepted. If the insurance called for is provided by more than one policy, a separate endorsement in the exact above form shall be provided for each policy.

Insurers must be authorized to do business and have an agent for service of process in California, have an "A" policyholder's rating and a financial rating of at least Class VI in accordance with the most current rating by A.M. Best Company.

ADDENDUM NO.1 CERTIFICATE OF INSURANCE (LIABILITY) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 1 OF 5

CERTIFICATE OF INSURANCE

Name of Contract: EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Name of Owner: OLIVENHAIN MUNICIPAL WATER DISTRICT

Type of Insurance: LIABILITY INSURANCE

THIS IS TO CERTIFY that the following policies have been issued by the below-stated company in conformance with the requirements of Articles 8-1 and 8-3 of the General Provisions and are in force at this time. The policy shall be an occurrence policy with a deductible not to exceed $5,000.

LIMITS OF LIABILITY

POLICY NUMBER In Thousands (000) EXPIRATION DATE TYPE OF INSURANCE Occurrence Aggregate

A. GENERAL LIABILITY Bodily Injury, Personal Injury, and Property Damage Combined

$

$

B. EXCESS GENERAL LIABILITY

$

$

C. AUTOMOBILE LIABILITY Bodily Injury and Property Damage Combined

$

$

D. EXCESS AUTOMOBILE LIABILITY

$

$

ADDENDUM NO.1 CERTIFICATE OF INSURANCE (LIABILITY) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 2 OF 5

The following types of coverage are included in said policies (indicate by "X" in space):

A. GENERAL LIABILITY

Comprehensive Form --------------------------------------------------------------------- YES___ NO___

Premises-Operations---------------------------------------------------------------------- YES___ NO___

Explosion and Collapse Hazard------------------------------------------------------------- YES____ NO____

Underground Hazard ---------------------------------------------------------------------- YES___ NO___

Products/Completed Operations Hazard -------------------------------------------- YES___ NO___

Contractual Insurance -------------------------------------------------------------------- YES___ NO___

Broad Form Property Damage Including Completed Operations -------------- YES___ NO___

Independent Contractors ----------------------------------------------------------------- YES___ NO___

Personal Injury ------------------------------------------------------------------------------ YES___ NO___

B. EXCESS GENERAL LIABILITY

Umbrella Form ------------------------------------------------------------------------------ YES___ NO___

Other Than Umbrella Form -------------------------------------------------------------- YES___ NO___

If other than Umbrella Form, please explain below:

C. AUTOMOBILE LIABILITY

Comprehensive Form Including Loading and Unloading ------------------------ YES___ NO___

Owned ---------------------------------------------------------------------------------------- YES___ NO___

Hired ------------------------------------------------------------------------------------------- YES___ NO___

Non-Owned ---------------------------------------------------------------------------------- YES___ NO___

D. EXCESS AUTOMOBILE LIABILITY

Umbrella Form ------------------------------------------------------------------------------ YES___ NO___

Other Than Umbrella Form -------------------------------------------------------------- YES___ NO___

If other than Umbrella Form, please explain below:

ADDENDUM NO.1 CERTIFICATE OF INSURANCE (LIABILITY) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 3 OF 5

This certificate or verification of insurance is not an insurance policy and does not amend, extend, or alter the coverage afforded by the policies listed herein. However, the insurance provided shall meet the requirements of the Contract Documents and include coverage as specified in this certificate.

The Company will give at least 30 days' written notice by certified mail to the Owner and the Engineer/Architect prior to any material change or cancellation of said policies.

Named Insured (Contractor) Insurance Company

Street Number Street Number

City and State City and State

By: (Company Representative) (SEE NOTICE ON PAGE 5 OF 5)

ADDENDUM NO.1 CERTIFICATE OF INSURANCE (LIABILITY) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 4 OF 5

State of ) ) ss. County of ) A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document On____________________________before me,_______________________________________________ Date Here Insert Name and Title of the Officer Personally appeared _____________________________________________________________________ Name(s) of Signer(s) ____________________________________________________________________________________ Who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subsicribed to the withing instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and official seal

NOTARY PUBLIC Insurance Company Agent for Service of Process in California:

Name Agency

Street Number Street Number

City and State City and State

Telephone Number Telephone Number

ADDENDUM NO.1 CERTIFICATE OF INSURANCE (LIABILITY) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 5 OF 5

NOTICE:

No substitution or revision to the above certificate form will be accepted. if the insurance called for is provided by more than one insurance company, a separate certificate in the exact above form shall be provided for each insurance company.

Insurers must be authorized to do business and have an agent for service of process in California, have an "A" policyholder's rating and a financial rating of at least Class VI in accordance with the most current rating by A.M. Best Company.

(BLANK)

ADDENDUM NO. 1 INSURANCE ENDORSEMENT (LIABILITY) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 1 OF 2

INSURANCE ENDORSEMENT

Name of Contract: EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Name of Owner: OLIVENHAIN MUNICIPAL WATER DISTRICT

Type of Insurance: LIABILITY INSURANCE

This endorsement forms a part of Policy No. .

ENDORSEMENT:

The Owner, the Engineer/Architect, the Owner's Representative, and their consultants, and each of their directors, officers, employees, and agents are included as additional insureds under said policies but only while acting in their capacity as such and only as respects operations of the named insured, his contractors, any subcontractor, any supplier, anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable in the performance of the above-referenced contract. This insurance shall not apply if the loss or damage is ultimately determined to be the result of the sole and exclusive negligence (including any connected with the preparation or approval of maps, drawings, opinions, reports, surveys, designs, or specifications) of one or more of the aforesaid additional insureds. The insurance afforded to these additional insureds is primary insurance. If the additional insureds have other insurance which might be applicable to any loss, the amount of this insurance shall not be reduced or prorated by the existence of such other insurance.

The Contractual Liability Insurance afforded is sufficiently broad to insure all of the matters set forth in the article entitled "Indemnity" in the General Provisions of the above-referenced contract except those matters set forth in the third paragraph thereof.

This endorsement does not increase the Company's total limits of liability.

Named Insured (Contractor) Insurance Company

Street Number Street Number

City and State City and State

By: (Company Representative) (SEE NOTICE ON PAGE 2 OF 2)

ADDENDUM NO. 1 INSURANCE ENDORSEMENT (LIABILITY) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 2 OF 2

State of ) ) ss. County of ) A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document On____________________________before me,_______________________________________________ Date Here Insert Name and Title of the Officer Personally appeared _____________________________________________________________________ Name(s) of Signer(s) ____________________________________________________________________________________ Who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subsicribed to the withing instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and official seal

NOTARY PUBLIC

NOTICE:

No substitution or revision to the above endorsement form will be accepted. If the insurance called for is provided by more that one policy, a separate endorsement in the exact form shall be provided for each policy.

Insurers must be authorized to do business and have an agent for service of process in California, have an "A" policyholder's rating and a financial rating of at least Class VI in accordance with the most current rating by A.M. Best Company.

ADDENDUM NO. 1 CERTIFICATE OF INSURANCE (BUILDERS’ RISK “ALL RISK”) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 1 OF 4

CERTIFICATE OF INSURANCE

Name of Contract: EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Name of Owner: OLIVENHAIN MUNICIPAL WATER DISTRICT

Type of Insurance: BUILDERS’ RISK “ALL RISK” INSURANCE

THIS IS TO CERTIFY that the following policy has been issued by the below-stated company in conformance with the requirements of Articles 8-1 and 8-4 of the General Provisions and is in force at this time:

POLICY NUMBER EXPIRATION DATE LIMITS OF LIABILITY

$

(Not Less Than Contract Amount)

Deductible:

$

(Not Sooner Than Contract Completion Date)

(Not More Than $100,000)

This certificate or verification of insurance is not an insurance policy and does not amend, extend, or alter the coverage afforded by the policies listed herein. Notwithstanding any requirement, term, or condition of any contract or other document with respect to which this certificate or verification of insurance may be issued or may pertain, the insurance afforded by the policies described herein is subject to all the terms, exclusions, and conditions of such policies.

ADDENDUM NO. 1 CERTIFICATE OF INSURANCE (BUILDERS’ RISK “ALL RISK”) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 2 OF 4

The Company will give at least 30 days' written notice by certified mail to the Owner and the Engineer/Architect prior to any material change or cancellation of said policy.

Named Insured (Contractor) Insurance Company

Street Number Street Number

City and State City and State

By: (Company Representative) (SEE NOTICE ON PAGE 4 OF 4)

ADDENDUM NO. 1 CERTIFICATE OF INSURANCE (BUILDERS’ RISK “ALL RISK”) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 3 OF 4

State of ) ) ss. County of ) A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document On____________________________before me,_______________________________________________ Date Here Insert Name and Title of the Officer Personally appeared _____________________________________________________________________ Name(s) of Signer(s) ____________________________________________________________________________________ Who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subsicribed to the withing instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and official seal

NOTARY PUBLIC

Insurance Company Agent for Service of Process in California:

Name Agency

Street Number Street Number

City and State City and State

Telephone Number Telephone Number

ADDENDUM NO. 1 CERTIFICATE OF INSURANCE (BUILDERS’ RISK “ALL RISK”) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 4 OF 4

NOTICE:

No substitution or revision to the above certificate form will be accepted. If the insurance called for is provided by more than one insurance company, a separate certificate in the exact above form shall be provided for each insurance company.

Insurers must be authorized to do business and have an agent for service of process in California, have an "A" policyholder's rating and a financial rating of at least Class VI in accordance with the most current rating by A.M. Best Company.

ADDENDUM NO. 1 INSURANCE ENDORSEMENT (BUILDERS’ RISK “ALL RISK”) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 1 OF 2

INSURANCE ENDORSEMENT

Name of Contract: EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

Name of Owner: OLIVENHAIN MUNICIPAL WATER DISTRICT

Type of Insurance: BUILDERS’ RISK “ALL RISK” INSURANCE

This endorsement forms a part of Policy No. .

ENDORSEMENT:

The Owner, the Engineer/Architect, the Owner's Representative, and their consultants, and each of their directors, officers, employees, and agents are included as additional insureds under said policy but only while acting in their capacity as such with respect to the above-referenced contract.

The insurance afforded to these additional insureds is primary insurance. If the additional insureds have other insurance which might be applicable to any loss, the amount of this insurance shall not be reduced or prorated by the existence of such other insurance.

This endorsement does not increase the Company's total limits of liability.

Named Insured (Contractor) Insurance Company

Street Number Street Number

City and State City and State

By: (Company Representative) (SEE NOTICE ON PAGE 2 OF 2)

ADDENDUM NO. 1 INSURANCE ENDORSEMENT (BUILDERS’ RISK “ALL RISK”) REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT 2 OF 2

State of ) ) ss. County of ) A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document On____________________________before me,_______________________________________________ Date Here Insert Name and Title of the Officer Personally appeared _____________________________________________________________________ Name(s) of Signer(s) ____________________________________________________________________________________ Who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subsicribed to the withing instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and official seal

NOTARY PUBLIC NOTICE:

No substitution or revision to the above endorsement form will be accepted. If the insurance called for is provided by more than one policy, a separate endorsement in the exact above form shall be provided for each policy.

Insurers must be authorized to do business and have an agent for service of process in California, have an "A" policyholder's rating and a financial rating of at least Class VI in accordance with the most current rating by A.M. Best Company.

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 1 OF 21

SECTION 00810 – SUPPLEMENT TO GENERAL PROVISIONS REVISED

1.01 DEFINITIONS

Whenever the following terms occur in the Contract Documents, the meaning shall be interpreted as follows:

ATTORNEY FOR Owner – Alfred E. Smith, Nossaman LLP, 777 South Figueroa Street, 34th Floor, Los Angeles, CA 90017, (213) 612-7831

BOARD OF DIRECTORS - Board of Directors of the Olivenhain Municipal Water District.

CITY – City of Encinitas, 505 South Vulcan Ave. Encinitas, CA 92024

CONTRACT TIME – The number of consecutive days stated in the contract documents commencing from the date of the notice of award, for completion of the Work.

DATE OF AWARD OF CONTRACT - The date of the District Resolution (formal action of the Board of Directors of the District) awarding the Contract.

DISTRICT - Olivenhain Municipal Water District (OMWD), 1966 Olivenhain Road, Encinitas, California 92024, (760) 753-6466.

DISTRICT'S REPRESENTATIVE - The Owner's Representative.

DRAWINGS or PLANS – Construction drawings entitled, “EL CAMINO REAL REPLACEMENT PIPELINE” and referenced Standard Drawings or Regional Standard Drawings and City of Encinitas “EL CAMINO REAL GREEN BIKE LANE”.

ENGINEER / DESIGN ENGINEER –

Balboa Engineering, Inc., 14204 Caminito Lazanja, San Diego, CA 92127, Tel: (858) 200-5044.

STC Traffic, Inc. 5865 Avenida Encinas, Ste. 142B, Carlsbad CA 92008 Tel: (760)602-4290

OWNER - Olivenhain Municipal Water District (OMWD), 1966 Olivenhain Road, Encinitas, California 92024, Tel: (760) 753-6466; Fax: (760) 753-1578.

OWNER'S REPRESENTATIVE - The person or engineering/architectural firm authorized by the District to represent it during the performance of the work and until final acceptance. The Owner's Representative is referred to throughout the Contract Documents as if singular in number and masculine in gender. The Owner's Representative means the Owner's Representative and his assistants.

PUBLIC WORKS SPECIFICATIONS - Standard Specifications for Public Works Construction Current Edition by APWA/AGC, the "GREENBOOK" with 2000 Regional Supplement Amendments.

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 2 OF 21

REGIONAL STANDARD DRAWINGS – Standard Drawings for Agencies in the San Diego Region as recommended by the Regional Standards Committee and published by the San Diego County Department of Public Works, Current Edition.

SPECIAL PROVISIONS - Section 00810 of the specifications.

SPECIFICATIONS - Division 1 to 15 of the technical specifications contained in these Contract Documents, and those technical specifications contained in the Drawings.

STANDARD DRAWINGS - Drawings A-1.1 through G-13 of the Olivenhain Municipal Water District, Standard Specifications and Drawings for the Construction of Water, Recycled Water, and Sewer Facilities, dated June 2008, with revisions.

STANDARD SPECIFICATIONS - Divisions 1 through 15 of the Olivenhain Municipal Water District, Standard Specifications and Drawings for the Construction of Water, Recycled Water, and Sewer Facilities, dated February 2017, with revisions.

STATE STANDARD SPECIFICATIONS - State of California, Department of Transportation, Standard Specifications, Current Edition, Caltrans.

STATE STANDARD PLANS - State of California, Department of Transportation, Standard Plans, Current Edition, Caltrans.

WATER AUTHORITY – San Diego County Water Authority

Whenever the following terms appear in the State Standard Specifications or Public Works Specifications, the meaning shall be interpreted as follows:

AGENCY, BOARD or DEPARTMENT - The Owner.

ENGINEER - The Owner's Representative.

1.02 TERMS

Command type sentences used in the Contract Documents refer to and are directed to the Contractor.

1.03 ABBREVIATIONS

Interpret abbreviations used on the Drawings and in the Specifications as explained on the Drawings.

1.04 MARKING AND ADDRESSING BID ENVELOPE

Bids shall be made on the Bid Form and Bid Bond included within the Contract Documents. Complete and include the Bid Form Checklist together with the completed Bid Form and Bid Bond when submitting a bid. Seal the Contract Documents with the filled out bid in an envelope marked and addressed as follows:

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 3 OF 21

BID FOR CONSTRUCTION OF: EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT

OLIVENHAIN MUNICIPAL WATER DISTRICT Attention: Jason P. Hubbard, Engineering Manager 1966 Olivenhain Road Encinitas, California 92024

1.05 AWARD OF CONTRACT OR REJECTION OF BIDS

Within a period of 60 calendar days after the opening of bids, the District will accept or reject the bids.

1.06 CONTRACTOR'S LICENSING REQUIREMENTS

The District has determined the license classification necessary to bid and perform the subject contract. In no case shall this contract be awarded to a specialty contractor whose classification constitutes less than a majority of the portion of the work of this contract, all work to be performed outside of the contractor's license specialty, except work specifically authorized by District, shall be performed by a licensed subcontractor in compliance with the Subletting and Subcontractor Fair Practices Act commencing with Section 4100 et seq., of the Public Contract Code. See Business and Professions Code Section 7059.

The Contractor's license classification required for this project is a California State Contractor's License Class A.

It is the District's intent that "plans", as used in Public Contract Code Section 3300, is defined as the construction Contract Documents, which include both the Drawings and the Specifications

1.07 TIME FOR COMPLETION AND FORFEITURE DUE TO DELAY

The work for Bid Schedule I shall be completed within THREE HUNDRED (300) CONSECUTIVE CALENDAR DAYS from and after the date of the Notice to Proceed. The work for Bid Schedule II shall be completed within SIXTY (60) CONSECUTIVE CALENDAR DAYS from the date of the Notice of Substantial Completion for all the work in Bid Schedule I.

The Contractor will not be permitted to begin work until the agreement, bonds or substitutes, insurance certificates and endorsements are acceptable to the District and Attorney for Owner. This period of time is set forth in Paragraph 3-2 Execution of Contract in the General Provisions. Time is of the essence in this contract.

The Contractor shall complete all work in its entirety as specified in the Contract Documents within these time periods. Time of completion shall also include time for all submittals and coordination required to satisfy the requirements of these Contract Documents.

The Contractor agrees that the work shall be prosecuted regularly, diligently, and uninterruptedly and at such rate of progress as will insure full completion thereof within the Time for completion stated above. It is expressly understood and agreed, by and between

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 4 OF 21

Contractor and Owner that the Time for completion is reasonable for the completion of the WORK, taking into consideration the average climatic range, usual industrial conditions prevailing in this locality, and lead time required to procure equipment.

Pursuant to Government Code 53069.85, forfeiture for each day completion is delayed beyond the time allowed for Bid Schedules I and II will be at the rate of $3,000.00 per day, except as noted below.

1.08 PERMITS

The Contractor shall obtain all required permits and provide copies of all permits to the District's Representative prior to starting work, including the San Diego County Air Pollution Control District’s permits for construction and operation of diesel generators. The Contractor shall comply with the ordinances, directives, and regulations of the respective agencies with jurisdiction over the area of the work. All work not specifically covered in the required permits shall conform to the requirements of these Specifications. The cost of all permits and plan check review shall be borne by the Contractor and included in the Contractor’s bid.

The Contractor shall be responsible for developing haul routes for the importing or exporting of materials or equipment for the project and obtaining all required permits from the affected agencies of jurisdiction, i.e., City of Encinitas. The Contractor shall provide copies of all permits to the District's Representative prior to starting work. The Contractor shall comply with the ordinances, directives, and regulations of the respective agencies with jurisdiction over the area of the work. All costs for transport fees, dump fees, plan or haul route reviews, permits, and related incidentals shall be borne by the Contractor and included in the Contractor’s bid.

1.09 USE OF ASBESTOS PRODUCTS NOT PERMITTED

The intent of the Contract Documents is to provide asbestos-free components throughout the project in accordance with the recent Environment Protection Agency stated policy seeking a ban on the use of all products containing asbestos. Where the Contract Documents or the referenced specifications, standards, codes, or tests refer to products containing asbestos, the Contractor shall provide acceptable alternatives under those documents, or in the absence of such referenced alternatives, he shall submit a proposed substitute to the District's Representative for review and acceptance.

1.10 ASBESTOS CEMENT PIPE REMOVAL AND DISPOSAL

If asbestos cement pipe must be cut and handled in the field to accomplish the work, the Contractor is solely responsible for and shall take all appropriate precautions for protecting against threats to health and safety of the work force and general public arising out of construction involving asbestos. The Contractor shall comply with all applicable regulations for the handling, cutting, shaping, installation and disposal of asbestos. Asbestos cement pipe to be disposed shall be properly manifested, prepared for transport following criteria of County of San Diego Department of Public Works, Solid Waste Division, and delivered to a landfill permitted for disposal of non-friable asbestos containing materials. The completed Generator copy (yellow) manifest shall be returned to the District's Representative. All cost for disposal of the AC pipe shall be included in the Contractor’s bid.

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 5 OF 21

1.11 ABATEMENT OF AIR POLLUTION

A. Comply with all applicable Federal, State, County, and City laws and regulations concerning the prevention and control of air pollution.

B. Conduct construction activities and equipment in a manner so as to minimize atmospheric emissions or discharges of air contaminants. Equipment or vehicles that show excessive emissions of exhaust gases shall not be operated on the site.

1.12 NOISE CONTROL REQUIREMENTS

A. The Contractor shall comply with all local sound control and noise level rules, regulations and ordinances which apply to any work performed pursuant to the Contract.

B. Each internal combustion engine, used for any purpose on the job or related to the job, shall be equipped with a muffler of a type recommended by the manufacturer. No internal combustion engine shall be operated on the project without said muffler.

C. Each vehicle equipped with a back-up alarm shall use a white noise back-up alarm Brigade BBS-97 or equal at all times.

D. Noise level requirements shall apply to all equipment on the job or related to the job, including but not limited to trucks and transient equipment that may or may not be owned by the Contractor. The use of loud sound signals shall be avoided in favor of light warnings except those required by safety for the protection of personnel.

1.13 AMOUNT OF LIABILITY INSURANCE

A. Employer’s Liability Insurance:

1. Bodily injury coverage by accident shall be for not less than $1,000,000 for each employee and $1,000,000 for each accident.

B. General Liability:

Bodily injury, personal injury, and property damage coverage shall be in a combined single limit of not less than $1,000,000 for each occurrence and $2,000,000 aggregate.

C. Automobile Liability:

Bodily injury and property damage coverage shall be in a combined single limit of not less than $1,000,000 for each occurrence and $2,000,000 aggregate.

D. Builder’s Risk Insurance:

Builder’s risk insurance shall be provided for the full contract amount.

E. Earthquake and Tidal Wave Insurance:

Earthquake and Tidal Wave Insurance is not required for this project.

F. Additional Insured:

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 6 OF 21

In addition to the additional insureds required for Liability insurance in the General Provisions, 8-3 LIABILITY INSURANCE, and 8-4 BUILDER’S RISK “ALL RISK” INSURANCE, the OWNER and each of its directors, officers, employees, and agents and its Design Engineer shall be named as additional insureds for all Liability insurance and Builders’ Risk Insurance provided herein.

1.14 USE OF THE STANDARD DRAWINGS

Where the Drawings or Specifications make reference to the Standard Drawings, construct the item in accordance with the details and materials as specified in the Contract Documents. For items not included in the Standard Drawings that are part of the Contract Documents, construct the item in accordance with the Olivenhain Municipal Water District, Standard Specifications and Drawings for the Construction of Water, Recycled Water, and Sewer Facilities dated June 2008 with revisions. These District Standard Drawings and Standard Specifications are available for purchase at the office of the District.

1.15 CONSTRUCTION SCHEDULE AND BID BREAKDOWN

The Contractor shall conform with the requirements of Article 6-3 Contractor’s CONSTRUCTION SCHEDULE AND COST BREAKDOWN of the General Provisions within 15 days after the date of award of contract. Submit to the District's Representative a construction progress schedule and bid breakdown in bar chart form. Divide each lump sum bid item into its major elements of work and show separately labor, materials and equipment costs. The District's Representative will use this cost breakdown as a basis for the monthly progress estimate and payment. The schedule shall specifically include and identify the construction sequence requirements defined on the plans.

1.16 STORM WATER POLLUTION PREVENTION

A. The Contractor shall prepare a Storm Water Pollution Prevention Plan (SWPPP) for the

project. The Contractor is responsible for Implementation, Maintenance, Inspection, Monitoring and Construction/Installation of all Best Management Practices (BMPs) required by the SWPPP, Construction General Permit (CGP), and the Erosion Control Plan for the purpose of preventing the discharge of pollutants from the construction site throughout the duration of the project. The Contractor is to provide all labor, materials and equipment to perform all work necessary to accomplish the work described below and per the Plans, Specifications, Special Provisions and applicable State Permits listed in the Bid Documents and References herein.

B. SCOPE OF WORK

1. The Contractor shall provide the Olivenhain Municipal Water District (District) with the SWPPP and the District will file the Notice of Intent (NOI), the necessary Annual Reports, and the Notice of Termination (NOT). The District will also designate a SWPPP Manager in writing to the Contractor. The Contractor shall provide the services of a Qualified Stormwater Practitioner (QSP) and will be responsible for adhering to and implementing the monitoring requirements set forth in the SWPPP and the CGP. The

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 7 OF 21

name of the QSP, together with their qualifications and certifications, shall be submitted to the District as a formal submittal.

2. No work shall commence on the project prior to the District submitting the Permit

Registration Documents (PRDs) and a Waste Discharge Identification Number (WDID#) being issued by the SWRCB.

3. The SWPPP shall remain within the project limits at all times during the duration of the

project or at a location approved by the District. The Contractor shall make the SWPPP available at all times per the requirements of the CGP.

4. The Contractor shall monitor the National Oceanic Atmospheric Administration (NOAA) website at www.noaa.gov for the current weather conditions on a daily basis. Contractor shall inform the District of any potential rain and/or storm conditions. A printed copy of the NOAA forecast shall be attached to all inspection reports.

5. The Contractor’s QSP shall perform all of the required inspections, reporting and maintenance according to the appropriate sections and attachments per the CGP for the established risk level of the project. Inspections and reporting shall continue for the duration of the project until the NOT has been accepted by the SWRCB.

6. Inspection reports shall be kept on site in the SWPPP binder. The Contractor shall be responsible to send an electronic copy of each inspection report to the District’s Project Manager and SWPPP Manager no later than the end of each week for review.

7. Each report must be accompanied with appropriate pictures to adequately document the effectiveness of installed BMPs and SWPPP practices.

C. DELIVERABLES

1. After the construction project is complete, the Contractor shall deliver hardcopies of all

inspections reports, an electronic copy of all pictures, and any miscellaneous SWPPP documents to the District.

2. The delivery of the required reports and pictures to the District shall be within 14 days of

project completion.

D. NON-COMPLIANCE

1. Should the Contractor not perform all required inspections per the CGP and SWPPP as

determined by the District’s SWPPP Manager, the site shall be deemed to be out of compliance. The Contractor will have 48 hours, upon notification by the District, to generate the proper reports and return the project back in compliance of the CGP. If after the 48 hour time frame the project is still considered out of compliance, the District may take any actions necessary to return the project back in compliance with the requirements of the CGP and SWPPP. Any and all costs expended by the District to bring the project back in compliance as determined by the SWPPP Manager, in his/her sole discretion, shall be charged to the Contractor.

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 8 OF 21

2. Should the Contractor not install all required BMPs per the CGP and SWPPP as

determined by the District’s SWPPP Manager, the site shall be deemed to be out of compliance. The Contractor will have 48 hours, upon notification by the District, to install or repair any BMPs necessary to keep the project in compliance with the CGP. If after the 48 hour time frame, the project is still considered out of compliance, the District may take any actions necessary to return the project back into compliance with the requirements of the CGP and SWPPP. Any and all costs expended by the District to bring the project back in compliance as determined by the SWPPP Manager, in his/her sole discretion, shall be charged to the Contractor.

3. If the District receives any non-compliance notifications or fines from Governing

Municipalities and/or the State, the Contractor shall indemnify and defend the District. Any and all costs resulting from a violation and/or fine will be borne by the Contractor to include District staff, legal, and consulting costs at the Contractor’s sole expense.

4. The District and the District’s SWPPP Manager will be onsite, throughout the duration of

the project, to monitor and verify that all reporting and BMP Implementation is being performed per the requirements of the CGP.

5. If at any time the site is deemed to be out of compliance as determined by the SWPPP

Manager, in his/her sole discretion, the District reserves the right to stop all construction activities. The site will remain inactive until the Contractor performs all the necessary actions to return the project back in compliance with the requirements of the CGP and SWPPP.

6. There will not be any days given to the Contractor for an extension of the contract for

the time the site is deemed to be out of compliance. The Contractor is solely responsible for maintaining all of the necessary BMPs at all times and ensure the project meets all of the CGP and SWPPP requirements.

E. IMPLEMENTATION OF BMPs

1. The Contractor shall be responsible to protect the site at all times per the requirements

of the CGP and the project SWPPP. 2. The Contractor shall be responsible to protect but is not limited to the following:

A. Stockpiles (Soil, Asphalt, Concrete, Sand, Gravel and other material) B. Concrete Washouts C. Trash Containers and Dumpsters D. Slopes and Disturbed areas E. Equipment and Vehicles F. Bagged and Boxed materials G. Liquid and Hazardous materials H. Portable Toilets and Storage Facilities

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 9 OF 21

3. The Contractor shall install, implement and maintain the BMPs to the Maximum Extent Practical (MEP) to prevent or reduce pollutant discharges to local storm drain, storm drain conveyance systems and/or receiving waters from construction activities. BMPs are to be installed per the California Stormwater Quality Association (CASQA) BMP Handbook (2009) and shall be applied to but not limited to the following:

A. Erosion Control on Slopes B. Erosion Control on Flat areas; or BMPs to desilt runoff from flat areas C. Runoff Velocity Reduction D. Sediment Control E. Offsite Sediment Tracking Control F. Materials Management G. Stockpile Management H. Waste Management I. Vehicle and Equipment Management J. Temporary Soil Stabilization K. Storm Drain Inlet Protection L. Wind Erosion Control M. De-watering an Hydrostatic Operations N. Materials Pollution Control O. Water Conservation P. Structure Painting and Construction Q. Paving Operations R. Planned Construction Operations S. Downstream Erosion Control T. Prevention of Non-Storm Water Discharges U. Protection of Ground Water

4. BMPs are to be installed by qualified personnel only. The Contractor’s QSP is

responsible to inspect all BMPs for proper installation per the CGP, CASQA BMP Handbook, Erosion Control Plan, and the SWPPP.

5. The Contractor shall inform the District of any BMP failures, malfunctions, breeches

and/or discharges during the course of construction. The Contractor will be responsible for the repair and clean up of any breech and or discharge caused or related to their work at no additional cost to the District.

6. The Contractor shall be responsible for maintaining proper dust control during the

course of construction per the (spell out first) Air Quality Management District (AQMD) standards.

7. All entrances and exits of work and storage areas shall be inspected on a daily basis.

Any dirt, dust, or debris leaving the project site will be the sole responsibility of the Contractor to correct immediately upon occurrence.

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 10 OF 21

8. All slopes and stockpiles that have been inactive for 14 days or in the event of a rain storm shall be properly protected per the requirements of the CGP and SWPPP.

9. Contractor shall be responsible to implement Post Construction BMPs for permanent

control of erosion from slopes and required vegetation areas. These BMPs shall include but are not limited to:

A. BMPs and Landscaping shown on the erosion control and project plans B. Structures to convey runoff safely from slopes and walls C. Vegetation or alternative stabilization of all disturbed slopes D. Re-vegetation of any natural drainage systems to the MEP

F. COMPLIANCE CERTIFICATION

1. An officer or other authorized representative of the Contractor shall certify that the site is

and/or was in full compliance with the CGP during construction activities.

2. The District will file all Annual Reports in the Storm Water Multiple Application and Report Tracking System (SMARTS). The Contractor shall provide the District with all of the necessary inspection reports, photos, corrective actions, BMP failures, sampling (if required by the SWPPP), etc. This data shall be given to the District’s SWPPP Manager no later than 30 days prior to the Annual Report’s due date.

G. TERMINATION

1. At the end of the project, the Contractor shall be responsible for removal of all temporary

BMP measures, all construction related materials, equipment, trash/litter/debris, portable toilets, stockpiles of materials and any trash and concrete washout containers. The Contractor is responsible to re-install, plant, repair or replenish, any vegetation, landscaping or permanent structure damaged or disturbed during the course of construction of which is not called out or listed on the bid documents and plans.

H. TRAINING

1. Prior to the commencement of construction, all personnel that will be on site shall go

through a formal SWPPP training provided by the District. This training will take place at a mutually agreed upon location and will last for 1 hour. Additional training shall take place at a minimum of once a month as determined by the Owner’s Representative throughout the course of construction and until such time that an NOT has been filed and accepted by the SWRCB.

I. REFERENCES

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 11 OF 21

1. State Water Resources Control Board (SWRCB) Construction General Permit (CGP) Order

No. 2010-0014-DWQ National Pollutant Discharge Elimination System (NPDES) General Permit No. CAS000002, Waste Discharge Requirements for Discharges of Storm Water Runoff Associated with Construction Activity.

2. California Stormwater Quality Association, CASQA Construction BMP

Handbook/Portal.

3. San Diego County Ordinance No. 9424 (Watershed Protection, Stormwater Management and Discharge Control)

1.17 ACCESS OF DISTRICT’S REPRESENTATIVE TO CONFINED SPACES IN STRUCTURES UNDER CONSTRUCTION

A. The Contractor shall be aware that some or all portions of the work may be designated as a PERMIT REQUIRED CONFINED SPACE. The Contractor is required to provide the Owner with a copy of the Contractor’s Confined Space Program for Owner’s review and acceptance prior to beginning work. Contractor’s Confined Space Program shall be in compliance with Cal-OSHA’s Confined Space regulatory requirements. The Contractor is required to perform all work in accordance with Cal-OSHA Confined Space requirements and Title 8, Subchapter 20 “Tunnel Safety Orders”.

B. The Contractor shall provide the following assistance to the personnel of the District’s Representative when said personnel must enter confined spaces in structures under construction or structures which have not been accepted by the District.

1. Training program for the personnel of the District’s Representative relevant to the specific structures being entered.

2. Testing equipment and personnel to operate said equipment for testing the atmosphere in the confined spaces for oxygen deficiency, explosive gases, and toxic gases.

3. Authorized competent person to stand by each confined space while entrants are inside the space.

4. Safety equipment (breathing apparatus, harnesses, and rescue equipment) in good working order.

5. Communication equipment.

6. Access equipment (hoists and ladders).

7. Signs.

8. Alarm system.

9. Ventilation system.

C. The Contractor shall identify confined spaces on the project, mark them with warning signs per CAL/OSHA requirements, and notify the District’s Representative that these structures now exist.

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 12 OF 21

1.18 PROTECTION OF EXISTING UTILITIES

The Contractor shall coordinate their efforts with the District and shall take every precaution to protect all existing utilities and structures at the project site. The Contractor shall be responsible for all Underground Service Alert notification and mark outs prior to the beginning of work.

1.19 COORDINATION WITH DISTRICT OPERATIONS

A. The Contractor shall coordinate all work with the District sufficiently ahead of time so as to not interfere with the District’s operation of their system. The Contractor shall submit a detailed sequence of work to the District for all work. This proposed sequence of work shall be reviewed with the District prior to construction for consistency with the Sequence of Work as described in these Contract Documents and the District’s required operation and shut-down plan.

B. The District will operate all existing valves. Therefore, the Contractor must coordinate connection work with the owner. Once the pipelines have been isolated, the Contractor shall dechlorinate and drain all lines.

1.20 PRE-CONSTRUCTION CONFERENCE AND PROGRESS MEETINGS

A Pre-Construction Conference shall be scheduled prior to start of project as described in Section 01201 Preconstruction Conference. The District, the Contractor, and the District’s Construction Manager shall be present. The Contractor’s detailed sequence of work and a list of labor, material and equipment rates for additional work shall be established and maintained throughout the project. Contractor shall identify all personnel assigned to the project and a complete set of approved submittal data for use by inspection personnel. Contractor shall have a designated representative for this project.

The Contractor shall also attend a project planning meeting as described in Specification Section 01202, Progress Meetings.

1.21 HOURS OF WORK

Hours of work shall be 8:00 P.M. to 6:00 A.M Monday through Thursday nights or as approved by the City of Encinitas traffic control permit. Saturday and daytime work will only be allowed with prior written approval by the Owner. Overtime and shift work may be established as short-term procedure by Contractor with written notice to and written permission from Owner. No work other than overtime and shift work approved by Owner shall be done between the hours of 6:00am and 8:00pm, nor on weekends, or District recognized holidays, except such work as is necessary for the proper care and protection of the work already performed, except in case of emergency, and as specified herein. The District recognized holidays are as follows: Veterans Day Monday, November 11, 2019 Thanksgiving Day Thursday, November 28, 2019 Day after Thanksgiving Friday, November 29, 2019 Christmas Day Wednesday, December 25, 2019

New Year’s Day Wednesday, January 1, 2020 Martin Luther King Day Monday, January 20, 2020

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 13 OF 21

Presidents’ Day Monday, February 17, 2020 Memorial Day Monday, May 25, 2020 Fourth of July Friday, July 3, 2020 Labor Day Monday, September 7, 2020 Veterans Day Wednesday, November 11, 2020 Thanksgiving Day Thursday, November 26 2020 Day after Thanksgiving Friday, November 27, 2020 Christmas Day Friday, December 25, 2020 New Year’s Day Friday, January 1, 2021 Martin Luther King Day Monday, January 18, 2021 Presidents’ Day Monday, February 15, 2021 Memorial Day Monday, May 31, 2021

1.22 CONSTRUCTION SURVEYS

A. LAND MONUMENTS

The Contractor shall notify the District and the District’s Representative of any existing Federal, State, City, County, and private land monuments encountered. All monuments shall be preserved, or if necessary to be destroyed during performance of the Work, shall be replaced by a licensed surveyor under contract to the Contractor. Appropriate record of survey drawings shall be filed with the City of Encinitas and County of San Diego for all replaced monuments. When government monuments are encountered, the Contractor shall notify the District’s Representative at least two (2) weeks in advance of the proposed construction and provide for surveying of the existing monument before it is disturbed or destroyed.

B. CONSTRUCTION STAKING

1. The Contractor shall furnish construction staking to execute the work as described in the Contract Documents. Preserve all construction stakes, reference points, and other survey points. In case of their loss or destruction, the Contractor shall be liable for their replacement. If the field survey stakes are not available for review by the District’s Representative, the work may not proceed.

2. The Contractor’s surveyor will establish the following minimum points along the pipeline alignment: one offset stake for line, station and grade at all angle points, beginning and ending of curves and points along the centerline of pipe with a maximum distance of 25.00 feet between stakes for pipeline to be constructed by open trench construction. Additional stakes may be requested for clarification of construction at the request of the Owner’s Representative at no additional cost to the Owner. All surveying staking is to be completed during normal, nighttime working hours Monday-Thursday, 8pm-6am

1.23 GEOTECHNICAL WORK

A. SUBSURFACE INVESTIGATIONS

The following reports were prepared and are available on the District’s website:

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 14 OF 21

”Geotechnical Investigation, Olivenhain Municipal Water District, El Camino Real Pipeline Replacement, Encinitas, California” February 26, 2018, SCST Project No. 170455P4, Report No. 1.

“Environmental Soils Testing, Olivenhain Municipal Water District, El Camino Real Pipeline Replacement, Encinitas, California” February 26, 2018, SCST Project No. 170455P4, Report No. 2.

“Boring Completion Report, Olivenhain Municipal Water District, El Camino Real Pipeline Replacement, Encinitas, California” November 20, 2018, SCST Project No. 170455P4, Report No. 3.

These reports, other available investigation reports and the project site should be thoroughly reviewed by each potential Contractor prior to submission of a bid.

1. The Contractor may make independent subsurface, soil, or geotechnical investigations of the project site in order to satisfy himself of the subsurface conditions that may be encountered. No additional compensation will be made for such investigations.

2. Bidders shall make their own independent evaluation of the rippability of rock and include all costs associated with the proper equipment to excavate, remove and dispose of rock in their bid. Blasting will only be permitted upon the approval of the District if a benefit to the District and the project can be demonstrated.

B. CONSTRUCTION TESTING

1. The Owner shall furnish compaction testing for all bedding, backfill, and soil compaction testing.

2. The Owner shall furnish all materials testing and special inspections called for in the Contract Documents.

3. When any work is determined to be unsatisfactory, faulty or defective, or does not conform to the requirements of the Contract Documents, the costs incurred by the Owner for additional tests or inspections shall be reimbursed by the Contractor. Said costs shall be paid by the Owner and deducted from progress payments to the Contractor.

1.24 CONSTRUCTION WATER

A. The Contractor shall obtain and pay for a construction water meter from the District and shall be responsible for all highlines and other temporary equipment and facilities necessary to provide adequate construction water to the project site. The Contractor shall coordinate the locations of water supply with the District. The following conditions must also be met:

1. Excess water must be available in the pipeline at the connection point.

2. The contractor shall submit a construction water service connection plan a minimum of two weeks prior to the need for water. This plan shall indicate all piping, valves, and other materials necessary to connect to District owned piping at designated blow-off,

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 15 OF 21

air vacuum, and air release structures located within the project site. Do not install piping, meter, or valves until the District’s Representative has approved the water service plan.

3. Accurately measure all water use and submit meter readings to the District’s Representative when the meter is installed, at the end of each month and when the meter is removed.

4. Securely lock the installed valve in the closed position at the end of each workday and during all times of inactivity. Avoid wasting water and prevent unauthorized use. Do not use water from the District on any other project.

5. Coordinate all use of water, flushing of pipelines and filling of pipelines with the District’s representative. All requests for use of water and for increases or decreases in quantity shall be made in writing to the District’s Representative two working days in advance.

1.25 POWER AND LIGHTING

A. The Contractor shall provide all power required for construction operations, and shall provide and maintain all temporary power facilities required to perform the work in a safe and satisfactory manner. All electrical facilities shall conform to the requirements of the of the requirements of Title 8, Industrial Relations, Subchapter 5, Electrical Safety Orders, of the California Code of Regulation; and Subpart K of the OSHA Safety and Health Standards for Construction.

B. The Contractor shall provide adequate light for work conducted at night or under low light conditions to provide adequate facilities for inspection and safe working conditions and to insure proper work.

C. Temporary connections for electricity shall be subject to approval of the District’s Representative and the power company representative. Remove temporary electrical connections in like manner prior to final acceptance of the work.

1.26 CONTRACTOR STAGING AND LAYDOWN AREA

For use of roadway right-of-way areas, Contractor shall apply for and obtain City of Encinitas approval for use. For any other area to be used by the Contractor, the Contractor shall coordinate with the property owner, obtain written permission from the property owner for use of the area, coordinate with any resource or permitting agency that may have jurisdiction over the area, obtain and pay for any permits or agreements and provide any environmental mitigation required, and pay any fees or rental charges required for use of the area. The Contractor shall provide to the District Representative a copy of the letter from the Property Owner giving permission to use their property as a staging/laydown area. The Contractor shall be responsible for returning all areas used to their original conditions. At least 14 days prior to moving onto any site, the Contractor shall submit to the District Representative a copy of the written permission letter from the Property Owner of that area, and a description of any permits and mitigation actions that are required for use of the area. Submittals shall be in accordance with Section 01300. All requests for the use of privately-owned land must be submitted to the Owner for written approval by the District’s General

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 16 OF 21

Manager prior to its use. The Owner may deny use of any privately owned property for this project in its sole discretion.

1.27 DUST CONTROL AND CLEANUP

A. Throughout all phases of construction, including suspension of work, and until final acceptance of the project, the Contractor shall keep the work site clean and free from rubbish and debris. The Contractor shall also abate dust nuisance by cleaning or sweeping and sprinkling with water or other means as necessary, in accordance with the San Diego Air Pollution Control District’s regulations. The use of water resulting in mud on public streets and/or private property will not be permitted as a substitute for cleaning, sweeping, or other methods. Every day, and as required by the Owner’s Representative, the Contractor shall furnish and operate a motorized, self-loaded sweeper with water spray nozzles to keep paved areas affected by the work acceptably clean and dust free.

B. The Contractor shall keep the premises free at all times from accumulations of waste materials and rubbish. Contractor shall provide adequate trash receptacles about the site, and shall promptly empty the containers when filled. Wastes shall not be buried or burned on the site or disposed of into storm drains, sanitary sewers, streams, or waterways. All wastes shall be removed from the site and disposed of in a manner complying with local ordinances and antipollution laws. Volatile wastes shall be properly stored in covered metal containers and removed daily. Construction materials shall be neatly stacked by the Contractor when not in use. The Contractor shall promptly remove splattered concrete, asphalt, oil, paint, corrosive liquids, and cleaning solutions from surfaces to prevent marring or other damage.

1.28 SANITATION AND DRINKING WATER

A. The Contractor shall provide toilet and wash-up facilities for his work force at the site of work. They shall comply with applicable laws, ordinances, and regulations pertaining to the public health and sanitation of dwellings and camps. The facilities shall be stored within the staging areas overnight and on weekends. The Contractor shall maintain the sanitary facilities in an acceptable condition from the beginning of work to completion and shall remove the facilities and disinfect the premises.

B. The Contractor shall provide safe drinking water at all times at the jobsite.

1.29 SAFETY

A. Owner and its inspectors, consultants, agents and other representatives are in no way responsible for safety and are there only to observe the work compliance with plans and specifications.

B. The Contractor acknowledges responsibility for jobsite and acknowledges that the District, Engineer and their agents, employees, consultants and representatives will not have any such responsibility. To the fullest extent permitted by law the Contractor shall indemnify, defend and hold harmless the District, Engineer, their present companies, subsidiaries, agents, and employees from and against all claims, damages, losses and expenses, including but not limited to attorney fees and claim costs, arising out of or resulting from performance of work by the Contractor, its subcontractors, or their agents and employees, which results in damage, loss or expense is caused in whole or in part by the negligence,

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 17 OF 21

active or passive, or District, Engineer, their parent and subsidiary companies, as well as their agents and employees, excepting only the sole negligence of District, Engineer, their parent or subsidiary companies and their agents and employees.

1.30 INDEMNIFICATION

A. Contractor hereby releases and agrees to indemnify, defend, hold harmless the District, the City, Engineer, their parent and subsidiary companies, agents, employees, consultants and representatives for any and all damage to persons or property or wrongful death regardless of whether or not such claim, damage, loss or expense is caused in whole or in part by the negligence, active or passive, of District, Engineer, their parent and subsidiary companies, as well as their agents and employees, excepting only the sole negligence of District, Engineer, their parent or subsidiary companies and their agents and employees to the fullest extent permitted by law. Such indemnification shall extend to all claims, demands, actions, or liability for injuries, death or damages occurring after completion of the project, as well as during the work’s progress. Contractor further agrees that it shall accomplish the above at its own cost, expense and risk exclusive of and regardless of any applicable insurance policy or position taken by any insurance company regarding coverage.

B. Contractor shall defend, indemnify and hold the District, the City, Engineer, its employees, officers, or agents, harmless against any and all claims by any parties arising from, or related to, any and all damages, including legal costs and attorney’s fees, resulting from interference with, interruption of, damage to, or any and all injuries which result from damage caused to subsurface installation, which is unforeseen and despite Engineer’s/Architect’s effort during the design process was not located, excepting only the gross negligence or willful misconduct of Engineer in providing its services.

1.31 AUDIO-VIDEO DOCUMENTATION OF PROJECT SITE

A minimum of two (2) weeks prior to start of construction and delivery of any equipment, materials or supplies to the site, the Contractor shall provide pre-construction digital color audio-video documentation as specified herein for the purpose of establishing the surface conditions existing in all of the areas to be affected by the construction and to avoid potential construction repair disputes. The Contractor shall be responsible for repairing any damage or defect not documented as existing prior to construction.

Digital color audio-video documentation shall consist of the recordation of surface features taken along the entire length of the project, including all work, storage, and staging areas and all intersecting roadways. Prior to audio-video taping of the project, all areas to be documented shall be investigated visually with notations made of items not readily visible by taping methods.

Coverage of the digital color audio-video documentation shall include, but not be limited to: all existing driveways, sidewalks, curbs, streets, signs, landscaping, trees, catch basins, fences, monuments, visible utilities and all buildings located within the zone of influence. Of particular concern are any existing faults, fractures, cracks, defects or other features. Front and/or side yard areas of residential homes within the zone of influence of construction shall also be recorded. Audio description shall be made simultaneously with and support the video coverage.

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 18 OF 21

Two (2) copies of the digital color audio-video documentation shall be provided to the Owner’s Representative on DVD, USB Flash Drive or other electronic data storage device suitable to the Owner prior to the start of construction. Utility mark out (USA) shall be completed prior to the audio-video documentation and shall be included in the pre-construction audio-video documentation. Any project areas not fully documented shall be re-shot as directed by the Owner’s Representative.

Construction work shall not commence until audio-video documentation has been delivered to the Owner’s Representative.

1.32 NOT USED

1.33 MEASUREMENT AND PAYMENT

A. General:

1. The measurement and payment provisions of these Contract Documents shall govern over those of referenced standards, if any.

2. The price set forth in the Bid Form for the work shall include all costs and expenses incidental to completing the work, and payment of the price bid will be payment in full under this contract, except as provided by Article 9-1 PAYMENT FOR CHANGES IN THE WORK of the General Provisions.

3. As a condition precedent to approval of the Contractor’s monthly payment application by the District’s Representative, the Contractor shall attend all progress or issue resolution meetings scheduled by the District’s Representative. In addition, the Contractor shall submit a monthly construction schedule properly updated and accurately showing the work completed to date and the work yet to be performed in the remaining Contract time. The Contractor agrees failure to comply with the foregoing to the satisfaction of the District’s Representative shall delay the monthly progress payment to the Contractor without penalty to the District.

B. Lump Sum Work Items Listed in the Bid Schedules:

1. The lump sum prices include full compensation for furnishing the labor, materials, tools, and equipment and doing all the work involved to complete the work included in lump sum work items listed in the Bid Schedules and defined by the Contract Documents.

2. The application for payment for a lump sum payment item will be for that specific work item based on the percentage completed. The percentage complete will be based on the value of partially completed work relative to the value of the item when entirely completed and ready for service. The application for payment will be in accordance with Article 9-2 PROGRESS PAYMENTS of the General Provisions.

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 19 OF 21

C. Unit Price Work Items Listed in the Bid Schedules:

1. The unit prices include full compensation for furnishing the labor, materials, tools, and equipment and doing all the work involved to complete the work included in the unit price work items listed in the Bid Schedules and defined by the Contract Documents.

2. The application for payment for a unit price payment item will be for that specific work item based on the units of work that are entirely completed and ready for service. The application for payment will be in accordance with Article 9-2 PROGRESS PAYMENTS of the General Provisions.

D. Work Items Not Listed in the Bid Schedules:

1. The General Provisions and items in the Special Provisions which are not listed in the Bid Schedules of the Bid Form are, in general, applicable to more than one listed work item, and no separate work item is provided therefor. Include the cost of work not listed but necessary to complete the project designated in the Contract Documents in the various listed work items of the Bid Form.

2. The bids for the work are intended to establish a total cost for the work in its entirety. Should the Contractor feel that the cost for the work has not been established by specific items in the Bid Form, he shall include the cost for that work in some related bid item so that his proposal for the project does reflect his total cost for completing the work in its entirety.

1.34 NOTICE OF COMPLETION

Contractor shall apply for acceptance of the work encompassed in Bid Schedules I and II. Upon substantial completion of the work encompassed in Bid Schedules I and II, the District, at the District’s sole discretion, will issue a Notice of Substantial Completion for this work.

Upon completion of all work in Bid Schedules I and II, Contractor shall apply for acceptance of the work. Upon acceptance of the work encompassed in Bid Schedules I and II, the District, at the District’s sole discretion, will issue a Notice of Completion for this work

1.35 GUARANTEE

For all work encompassed in Bid Schedules I and II, a two-year guarantee shall be furnished by the Contractor as required in the General Provisions, Article 5-14, except that any guarantee included for materials or equipment beyond the period specified herein shall be solely the responsibility of the guarantor and not the Contractor. This guarantee period shall commence with the District’s issuance of a Notice of Substantial Completion for Bid Schedules I and II.

1.36 LABOR COMPLIANCE PROGRAM AND CONTRACTOR REGISTRATION WITH STATE OF CALIFORNIA

In accordance with requirements defined by the California State Legislature via Senate Bill 854, all contractors and subcontractors involved with public works project shall be registered with the State Department of Industrial Relations. Registration is completed

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 20 OF 21

through an on-line application process and the payment of a fee to the State. The registration process requires contractors and subcontractors to provide workers’ compensation coverage to its employees, hold a valid Contractors State Board License, have no delinquent unpaid wage or penalty assessments, and not be subject federal or state debarment. The registration form is located on the State Department of Industrial Relations website:

http://www.dir.ca.gov/DLSE/dlsepublicworks.html

Prior to start of construction, the Contractor shall submit to the District evidence of completing this registration for the prime firm and all subcontracting firms. Failure to submit the requested documentation shall be cause for delay of the project and subject to forfeiture due to delay in accordance with paragraph 1.07 of the Supplement to General Provisions.

1.37 PUBLIC NOTICE BY CONTRACTOR

A. Contractor shall furnish and distribute public notices at least 1 week before starting construction in the form of door hangers using a format submitted to and approved by the District. This notice shall be distributed to all:

1. Residents and occupants within 300 feet of where construction work is to be performed, and;

2. Schools, sheriff sub-station, fire stations and businesses within 500 feet of where construction work is to be performed.

Notice format shall include, but is not limited to, project name, District’s project website address and hotline number. Contractor shall provide a draft notice to Owner’s Representative for approval a minimum of 15 calendar days prior to printing.

B. Contractor shall furnish and distribute public notices 72 hours in advance of shutdowns and low pressure notifications in the form of door hangers using a format submitted to and approved by the District. This notice shall be distributed to all:

C. All costs for printing, distributing and hanging of notices shall be included in the Contractor’s bid.

D. For all construction activity on taking place on private property outside of the public right-of-way or District easement areas, Contractor shall coordinate with the property owner, obtain written permission from the property owner for use of the area including the terms and conditions of use, coordinate with any resource or permitting agency having jurisdiction over the area, obtain and pay for any permits for use of the area, provide any environmental mitigation required, and pay any fees or rental charges required for use of the area. Prior to accessing the private property, Contractor shall contact each owner individually a minimum of 30 days prior to commencing the Work.

E. If the Work is delayed longer than 14 days from initial notification, re-notify residents and occupants of the new work schedule. A contact log containing the method of contact, contact information, date of contact, and responses, if any, shall be maintained and provided to the Owner’s Representative upon request.

ADDENDUM NO. 1 SUPPLEMENT TO GENERAL PROVISIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT SECTION 00810 - 21 OF 21

For work involving the temporary closure of a marked crosswalk or sidewalk, Contractor shall post a notice of the closure at each end of the crosswalk/sidewalk not less than 7 days prior to the scheduled date of closure. In addition to any other public notice requirements, the notice shall include the project name, project logo, District’s project hotline number, and estimated times and dates for closure.

1.38 PIPE ABANDONMENT

A. Contractor shall remove and dispose any existing pipeline or subsurface structure interfering with the construction of new improvements per the Contract Documents. Pipelines shown as abandoned or abandoned per the Contractors construction methods shall be plugged per the San Diego Regional Standard Drawings WP-03, including at intervals of 200 feet for pipelines 14” and smaller. Pipelines 16” and larger shall be filled along its entire length by pressured grout only.

1.39 DEEP ANODE ABANDONMENT

A. Contractor shall abandon the existing deep well anode per the requirements of the governing jurisdictional agency. Work shall include the removal and disposal of the associated electrical meter and rectifier, demolition of any equipment pads, and restoration of the site to match adjacent conditions.

END OF SECTION

(BLANK)

SECTION 01043 - COORDINATION WITH OWNER’S OPERATIONS REVISED

ADDENDUM NO.1 COORDINATION WITH OWNER'S OPERATIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 01043 - 1

PART 1 - GENERAL 1.1 CONTINUATION OF OPERATIONS A. The Contractor will be performing work in the vicinity of existing water transmission

and distribution facilities. Under these conditions, precautions will be necessary to assure that no damage or unscheduled shutdowns occur to any facilities, including piping, utilities, roads, and structures that are to remain in operation and are not to be modified or replaced. Any temporary facilities, materials, equipment and labor required to achieve this objective shall be provided by the Contractor at his own expense. At the completion of work, all such temporary facilities, materials and equipment remaining shall be removed from the site.

B. Regarding connection to existing buried piping and facilities at or adjacent to the site,

it shall be the responsibility of the Contractor to uncover and verify their locations; elevations; bearings and inclinations; joint locations relative to connection points; materials; and dimensions prior to beginning construction or fabrication of any new materials or facilities which are dependent on the location of existing facilities.

1.2 ORDER OF THE WORK A. The work shall be carried on at such places on the project and also in such order or

precedence as may be found necessary by the Engineer to expedite the completion of the project. After work has begun on any portion or designated part of the project, it shall be carried forward to its final completion.

1.3 SHUTDOWNS, RECONNECTIONS, TIE-INS, AND ABANDONMENTS A. Any proposed shutdowns must be indicated on the Contractor's preliminary schedule

to be submitted for review by the Engineer at the Pre-Construction Conference. The actual allowable durations of the shutdowns will be determined during the preparation of the detailed construction schedule.

B. No water system shutdowns or tie-ins to existing pipes will be allowed on a Monday

or a Friday. C. The Contractor shall give the Owner a minimum of fourteen (14) calendar days notice

prior to any proposed excavation or shutdown of existing mains or services. Scheduling shall be subject to Owner approval.

D. The Contractor shall compile a detailed list of all items of work which must be accomplished

during any shutdown. The Contractor shall coordinate his work to minimize the required number of shutdowns by accomplishing as many tasks as possible during each shutdown period. The Contractor shall submit this list of items to the District Representative for his review as a part of the construction schedule defined within Section 01310. The schedule shall indicate all periods and duration of each proposed shutdown and the items of work which will be accomplished. The Contractor shall make specific written requests for all shutdowns fourteen (14) calendar days in advance of the proposed shutdown for review and approval by the District

SECTION 01043 - COORDINATION WITH OWNER’S OPERATIONS REVISED

ADDENDUM NO.1 COORDINATION WITH OWNER'S OPERATIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 01043 - 2

Representative. The written request shall include a complete detailed plan of the Contractor's proposed activities including schedule, manpower, equipment, materials and methods which will be utilized to perform the required work during the proposed shutdown. If, in the opinion of the District Representative, the Contractor's proposed plan is insufficient to successfully complete the required work during the period of the shutdown, the Contractor shall make the appropriate revisions in his proposed plan to the satisfaction of the District Representative. The District reserves the right, at its sole discretion, to cancel any planned shutdown at any time for safety or operational reasons. A canceled shutdown will not constitute the basis for an increase in compensation due the Contractor.

E. All water services shall remain in service for the duration of construction except when

performing reconnections and tie-ins. The existing watermain shall remain in service until the new watermain is in service. .

F. Abandonment of the existing 12-inch may be staggered following the completion of

each phase as approved by the District. 1.4 SEQUENCE OF CONSTRUCTION A. Work under the Contract shall be scheduled and performed in such a manner as to

result in the least possible disruption to the operation of the existing District facilities and to the general public. The Contractor shall coordinate all connections to existing meters and mains with the Owner. The Contractor will install all highline piping required by the Owner for continuity of service.

B. The following construction constraints and requirements must be used as a guideline

in preparing the scheduling. At the sole discretion of the District Representative, deviation from these suggested sequences is permitted if techniques and methods known to the Contractor will result in reducing the disruption of the facility operation and upon the concurrence of the District Representative.

1. Potholing shall be performed two (2) weeks in advance of proposed pipeline

installation to resolve conflicts and minimize angles and bends in the pipe profile.

2. For the El Camino Real Pipeline Replacement work, the sequencing of the work shall follow Shutdown Phasing in numerical sequence, as shown on the drawings, starting with Phase 1. Phases 2 through 5 shall be constructed from north to south. Final paving shall be completed in each phase as the work progresses.

3. After the entire new pipeline is in service, the Contractor shall perform the

Deep Anode Abandonment at station 20+32.

4. Slurry seal and restriping for Schedule I to be completed at the conclusion of Phases 1-5 and Deep Anode Abandonment. Work may be coincide with similar work in Schedule II with written approval from the Owner.

SECTION 01043 - COORDINATION WITH OWNER’S OPERATIONS REVISED

ADDENDUM NO.1 COORDINATION WITH OWNER'S OPERATIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 01043 - 3

5. All work associated with Schedule II shall be completed within sixty (60) days from the completion of work associated with Schedule I.

C. Phasing of Work Guidelines. The following guidelines shall be used by the Contractor

for the scheduling and performance of the Work. Deviations from these guidelines shall be submitted to the Owner per Section 01300 and shall not be carried out until written approval is obtained from the Owner. The Work shall be completed in four Phases.

1. General - The following work shall precede the Work of any given phase.

a. Field stake the alignments and notify DigAlert for field mark out of all

existing utilities that are crossing or paralleling (within 5 feet horizontally) of the proposed construction.

b. A minimum of two (2) weeks prior to start of excavation, pothole all

existing utilities that are crossing or paralleling (within 5 feet horizontally) of the proposed pipeline including connection points to existing pipelines and as defined on the Drawings. Provide potholing results to the Owner and inform of any discrepancies at connection points, or at crossing or paralleling utilities, and allow sufficient time for District to make adjustments to the vertical and horizontal alignments, where necessary.

c. Each phase must be substantially complete prior to construction of the

subsequent phase. Substantially complete includes installation of all pipelines, appurtenances and service laterals, testing, placing the pipeline, appurtenances and service laterals back in service and base paving the trenches. The final cap paving for all phases may take place at one time.

2. Phase 1. The work in Phase 1 shall be substantially complete and the

pipeline and services placed back in service prior to commencing Phase 2.

a. Construct the improvements listed in Bid Item I-F and described in Specification Section 01150.

b. During Phase 1, work shall proceed at no more than one location within all areas encompassed by Bid Item I-F unless prior written approval is obtained from the Owner.

c. All pipelines and appurtenances listed in Bid Item I-F, as described in Specification Section 01150, shall be completed and fully operational and accepted by the Owner prior to the start of the next phase of work.

3. Phases 2 and 3. The work in Phases 2 & 3 shall be substantially complete

prior to commencing Phase 4. a. Construct the improvements listed in Bid Item I-G and I-H and described

in Specification Section 01150.

SECTION 01043 - COORDINATION WITH OWNER’S OPERATIONS REVISED

ADDENDUM NO.1 COORDINATION WITH OWNER'S OPERATIONS REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 01043 - 4

b. During Phases 2 and 3, work shall proceed at no more than two locations (including pipe headings) simultaneously unless prior approval is obtained from the Owner.

c. All pipelines and appurtenances listed in Bid Item I-G and I-H, as described in Specification Section 01150, shall be completed and fully operational and accepted by the Owner prior to the start of the next phase of work.

4. Phase 4. The work in Phase 4 shall be substantially complete prior to

commencing Phase 5.

a. Construct the improvements listed in Bid Item I-I and described in Specification Section 01150.

b. During Phase 4, work shall proceed at no more than one location within all areas encompassed by Bid Item I-I unless prior written approval is obtained from the Owner.

c. All pipelines and appurtenances listed in Bid Item I-I, as described in Specification Section 01150, shall be completed and fully operational and accepted by the Owner prior to the start of the next phase of work.

5. Phase 5.

a. Construct the improvements listed in Bid Item I-J and described in

Specification Section 01150. b. All pipelines and appurtenances listed in Bid Item I-J, as described in

Specification Section 01150, shall be completed and fully operational and accepted by the Owner prior to the start of the next phase of work.

END OF SECTION

SECTION 01150 – MEASUREMENT AND PAYMENT REVISED

ADDENDUM NO.1 MEASUREMENT AND PAYMENT REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 01150-1

PART 1 - GENERAL 1.1 DESCRIPTION A. The items described below in Paragraph 1.4 - Pay Items refer to and are the same

pay items listed in the Bid Form. They constitute all of the pay items for the completion of the Work. No direct or separate payment will be made for providing miscellaneous temporary or accessory works, plant, services, Contractor's or Engineer's field offices, layout surveys, job signs, sanitary requirements, testing, safety devices, shop drawings, record drawings, water supplies, power, maintaining traffic, removal of waste, watchmen, bonds, insurance, and all other requirements of the Contract Documents. Compensation for all such services, materials, and items shall be included in the prices stipulated for the lump sum or unit price pay items listed herein.

B. The lump sum bid prices and unit cost bid prices will be deemed to include an

amount considered by the Contractor to be adequate to cover Contractor's overhead and profit for each separately identified item.

1.2 SCOPE A. Payment shall include all compensation to be received by the Contractor for

furnishing all tools, equipment, supplies and manufactured articles and for all labor, operations and incidentals that are appurtenant to the items of Work and necessary to complete the various items of Work in accordance with the requirements of the Contract Documents. This shall include all appurtenances and the costs of compliance with the regulations of public agencies having jurisdiction, including Safety and Health Requirements of the California Division of Industrial Safety and the Occupational Safety and Health Administration of the U.S. Department of Labor (OSHA).

B. Payment shall include all measures necessary to comply with all applicable State

and Federal requirements for handling, transporting and disposal of asbestos containing materials (i.e., asbestos cement) including special handling these materials in a manner that will preclude their classification as regulated asbestos containing material and worker protection to reduce health and safety risks resulting from exposure to asbestos containing materials.

1.3 BREAKDOWN OF CONTRACT PRICE OF LUMP SUM CONTRACTS

A. Prior to the execution of a lump sum contract, the Contractor shall submit a detailed price breakdown showing the allocated portion of the total bid price to the various items of Work. Contractor must submit a preliminary price breakdown for the review and approval of the Engineer. The Owner reserves the right to reject any breakdown submitted by the Contractor which the Owner judges insufficient to allow for the preparation of accurate monthly progress payment estimates or extra work similar in nature to the Work included in the Contractor’s bid. The detailed price breakdown shall be listed by specification section number and shall include a separate cost item for all items of equipment or work. The price breakdown shall typically be a unit price type breakdown and shall include quantities, unit prices and total bid cost for each cost item. Where a unit price breakdown is judged impractical,

SECTION 01150 – MEASUREMENT AND PAYMENT

ADDENDUM NO. 1 MEASUREMENT AND PAYMENT REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 01150-2

the Owner may allow a breakdown by lump sum for certain cost items. This information will be used by the Owner in preparing monthly progress payment estimates.

1.4 PIPELINE PAY ITEMS

A. The following requirements, as applicable, shall apply to pipeline pay items listed in this Section, covering pipe Segment A, B, C, D, and E, together with the additional requirements listed under each pay item. Payment shall include, but is not limited to, field surveying and staking; pavement saw cutting; excavation; pavement disposal, removal of abandoned structures from within trench excavations; surplus material disposal; recessed trench plating; imported bedding and backfill material and compaction; pipe and fittings; concrete thrust blocks and/or restraint devices; isolation valves; combination air valve or manual air release assemblies, blow off assemblies; and backflow preventer assemblies; polyethylene encasement; valve stem extensions; valve wells and covers; tubing; corporation stops; linings and coatings for metallic pipe; cathodic protection anodes and test stations; fusion services for fusible PVC pipe if necessary; temporary highlining; connections to existing pipelines; abandonment of existing pipelines; removal and replacement of vegetation or trees; record of survey and replacement of monuments; traffic control services, equipment or permits not included in any other bid item; subgrade preparation and compaction; aggregate base; temporary asphalt concrete pavement; pressure testing; disinfection (of potable water pipelines); site restoration and replacement of existing improvements including curbs, gutters, medians, driveways, sidewalks, retaining and block walls, landscaping, and irrigation; and all incidental work, complete in place, in accordance with the Contract Documents. No adjustment to the Contract Price will be made for variations in trench width, pavement removal width, pavement material, or pavement thickness.

The pipeline payment shall also include, but not be limited to, furnishing all labor, materials, tools, and equipment and performing all work required for restoration of pavement striping and markings and traffic detector loops to existing conditions until such time as restriping can be completed for the Green Bike Lane Project in the respective segment per pay item #I-O.

The pipeline payment shall also include, but not be limited to, furnishing all labor, materials, tools, and equipment and performing all work required for over-excavation, placement of fabric in accordance with product manufacturer’s recommendations, and placement of crushed rock below the design trench subgrade elevation in accordance with the Contract Documents.

1.5 PAY ITEMS A. SCHEDULE I

I-A. Mobilization, Demobilization, Bonds, Permits, Insurance, & Cleanup

Payment shall include compensation for all labor, materials, tools and equipment including, but not limited to, the following principal items: obtaining and complying with permits not included in any other bid item; mobilizing labor force, equipment and construction facilities; providing Contractor field offices and storage yard;

SECTION 01150 – MEASUREMENT AND PAYMENT

ADDENDUM NO. 1 MEASUREMENT AND PAYMENT REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 01150-3

securing construction water supply; providing all temporary construction fencing and safety barriers; providing on-site sanitary facilities; obtaining groundwater discharge permits or waivers; posting OSHA requirements and establishing safety programs; daily cleanup; preparing the Schedule of Values prior to the pre-construction meeting; preconstruction/progress video and photographs; work not specified for payment in any other bid item; and all incidentals for the mobilization, demobilization, and permitting for construction of the project as described in the Contract Documents.

Payment shall also include bonds, insurance (including the City of Encinitas as additional insured with $1,000,000 coverage limits), permit applications and fees for City of Encinitas Right-of-Way Construction Permit and Traffic Control Permit and incidentals thereto to construct the project in its entirety in accordance with the Contract Documents. City of Encinitas construction inspection fees will be paid for by the Owner. Earthquake & Tidal Wave Insurance is not required.

Payment for this item shall be limited to five (5) percent of the total contract price.

I-B. Excavation Support System

Payment shall include, but is not limited to, obtaining and complying with all permits and regulations of the California Occupational Safety and Health (Cal/OSHA); preparing and submitting plans by a licensed Engineer and obtaining State Division of Industrial Safety permit(s) for excavations that are 5 feet deep or greater; and all incidental work for sheeting, shields, shoring, sloping or benching of excavation side slopes, or other protective systems necessary for the support of trench excavations and for worker protection from materials or equipment that could pose a hazard by falling or rolling into excavations.

I-C. Potholing

Payment for potholing for each Pipeline Segment shall include full compensation for all labor, materials, tools, equipment and incidentals for the potholing of utilities two (2) weeks in advance of propose pipeline installation that join, cross, or parallel the work (within 5 feet) prior to construction including surveying and staking, excavation, shoring, bracing, backfill, site restoration and incidental work necessary to verify the sizes, material types, elevations, inclinations and bearings of existing utilities within the work areas whether shown on the plans or located in the field in accordance with the Contract Documents. Potholing shall be conducted for the proposed pipelines and lateral piping for appurtenances. Potholing of existing utilities that parallel the proposed pipelines shall be conducted at an interval sufficient to establish their locations with respect to the centerline of the proposed construction. Payment for this bid item shall include costs for traffic control, permits and related drawings for potholing activities that are not included in any other bid item, if necessary, prepared to the satisfaction of the governing jurisdiction.

I-D. Dewatering

Payment for dewatering for each Pipeline Segment shall include, but is not limited to, all labor, materials, tools, equipment, supplies, supervision, and

SECTION 01150 – MEASUREMENT AND PAYMENT

ADDENDUM NO. 1 MEASUREMENT AND PAYMENT REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 01150-4

incidentals required for obtaining groundwater discharge permit(s) and performing dewatering as necessary to complete the Work in accordance with the Contract Documents. Payment for this bid item shall include compliance with the Regional Water Quality Control Board (RWQCB) requirements for groundwater discharge to the environment including, but not limited to, sampling, volumetric measurement, temporary containment, treatment, testing for clarity and constituents as required, monitoring and reporting. This bid item shall also include the installation and destruction of groundwater monitoring wells which may be required for the project including, but not limited to, permit applications, payment of fees, and submittal of well destruction reports by the Contractor to the County of San Diego, Department of Environmental Health. If Contractor elects to discharge to a sewer, this item shall also include compliance with the Leucadia Wastewater District (LWD) and Encina Wastewater Authority (EWA) requirements for groundwater discharge to a sewer including, but not limited to, permitting, insurance, submittals, inspection fees, sampling, volumetric measurement, temporary containment, treatment, testing for clarity and constituents as required, monitoring and reporting. Payment shall include all coordination, submittals, insurance, construction means and methods, and incidentals to comply with RWQCB, LWD and EWA requirements.

I-E. Hazardous Waste Disposal

There is a potential that hydrocarbon contaminated soils may be encountered along El Camino Real (Station 27+00 to Station 34+00). In the event that hydrocarbon contaminated soils are encountered, the soils shall be tested, managed and disposed of by a licensed facility in accordance with County of San Diego Department of Environmental Health requirements. For the purposes of the bid, an allowance for up to 300 cubic yards of hydrocarbon contaminated soils is assumed. Payment shall include, but is not limited to, all labor, materials, tools, equipment and incidentals for testing, identification, classification, temporary storage, removal and disposal of all such hazardous waste in accordance with all federal, state, and local rules and regulations applicable to such hazardous waste. Payment shall also include any permits and fees associated with identification, classification, temporary storage, removal and disposal of all such hazardous waste. The pay item in the Bid Schedule defines the unit price and maximum total allowance for this work. Payment for work under this Bid Schedule will occur only if the work is required and if it is approved by the Owner in writing. The Contractor shall make request for payment for work under this Bid Schedule in accordance with the General Provisions, Section 9-1 Payment of Changes in the Work.

I-F. El Camino Real Pipeline Replacement, Segment A

Payment shall include all labor, materials, tools, equipment and incidentals to construct approximately 635 lineal feet of 12-inch diameter PVC pipeline in El Camino Real (Station 1+00 to Station 7+35), and approximately 46 lineal feet of 1-inch diameter copper water service, 29 linear feet of 4-inch diameter PVC water service, and 32 linear feet of 6-inch diameter PVC fire service.

SECTION 01150 – MEASUREMENT AND PAYMENT

ADDENDUM NO. 1 MEASUREMENT AND PAYMENT REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 01150-5

I-G. El Camino Real Pipeline Replacement, Segment B

Payment shall include all labor, materials, tools, equipment and incidentals to construct approximately 1,070 lineal feet of 12-inch diameter PVC pipeline in El Camino Real (Station 46+26 to Station 56+98), and approximately 161 lineal feet of 1-inch diameter copper water service, 90 linear feet of 6-inch diameter PVC fire service, and 194 linear feet of 8-inch diameter PVC water service.

I-H. El Camino Real Pipeline Replacement, Segment C

Payment shall include all labor, materials, tools, equipment and incidentals to construct approximately 899 lineal feet of 12-inch diameter PVC pipeline in El Camino Real (Station 37+29 to Station 46+26), and approximately 115 lineal feet of 1-inch diameter copper water service, 90 linear feet of 6-inch diameter PVC fire service, 305 linear feet of 8-inch diameter PVC water service, and 75 linear feet of 12-inch water service.

I-I. El Camino Real Pipeline Replacement, Segment D

Payment shall include all labor, materials, tools, equipment and incidentals to construct approximately 1103 lineal feet of 12-inch diameter PVC pipeline in El Camino Real (Station 26+24 to Station 37+29), and approximately 164 lineal feet of 1-inch diameter copper water service, 87 linear feet of 6-inch diameter PVC fire service, 126 linear feet of 8-inch diameter PVC water service, 88 linear feet of 10-inch diameter PVC water service, and 104 linear feet of 12-inch water service and water main connection pipelines.

I-J. El Camino Real Pipeline Replacement, Segment E

Payment shall include all labor, materials, tools, equipment and incidentals to construct approximately 1,624 lineal feet of 12-inch diameter PVC pipeline in El Camino Real (Station 10+00 to Station 26+24), and approximately 221 lineal feet of 1-inch diameter copper water service, 48 linear feet of 4-inch diameter PVC water service, 312 linear feet of 6-inch diameter PVC fire service, 93 linear feet of 8-inch diameter PVC water service, and 176 linear feet of 10-inch diameter PVC water service.

I-K. Deep Anode Abandonment

Payment shall include all labor, materials, tools, equipment and incidentals for the proper abandonment of the cathodic deep well anode (Approx. Station 20+32) and removal of associated rectifier and electrical meter per the governing jurisdictional agencies requirements and the removal and restoration of the site including equipment pad, sidewalk, landscaping, and irrigation.

I-L. Base and Final Pavement Asphalt Concrete:

Payment for asphalt concrete shall include, but not be limited to, furnishing all labor, materials, tools and equipment necessary for Asphalt Concrete or Tire Rubber Modified Asphalt Concrete paving of the trench, both base and final overlay per Section 02743 and Appendix A, complete in place, and shall include

SECTION 01150 – MEASUREMENT AND PAYMENT

ADDENDUM NO. 1 MEASUREMENT AND PAYMENT REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 01150-6

permits and traffic control not included in any other item of work; pavement grinding, saw cutting, removal, and disposal; removal and disposal of temporary pavement; surface preparation; prime and tack coat; asphalt concrete of the class and grade specified; base paving flush to adjacent surface, grind and cap; pavement reinforcement membrane; and all other incidental work necessary to complete this item of work in its entirety in accordance with the Contract Documents. No measurement or payment shall be made for asphalt concrete paving that is not ordered by the Owner, that extends beyond the paving limits shown or specified on the Drawings or Standard Drawings, or for paving that is required to restore existing pavements damaged by the Contractor’s operations to the condition existing prior to the start of construction. Payment will not be adjusted for variations in trench width, pavement removal width, pavement material, or pavement thickness. Payment will include paving limits requirements per Section 02743, 3.12. The Owner reserves the right to vary the quantity of this bid Item from 0%-200% of the original bid quantity with no change in unit price.

I-M. Emulsion Aggregate Slurry

Payment for slurry seal work shall include, but not be limited to, furnishing all labor, materials, tools and equipment necessary for the application of Rubber Polymer Modified Slurry of the type specified and to the limits specified or ordered for the work from Encinitas Blvd to Garden View Road (Striping Station 11+40 to 59+50), including the intersections at Encinitas Blvd and Garden View Road and both northbound and southbound lanes from curb to curb, complete in place, and shall include permits and traffic control not included in any other item of work; application of herbicide; pavement surface and crack cleaning; crack sealing; slurry seal; curing and protection; and all other incidental work necessary to complete this item of work in its entirety in accordance with the Contract Documents. No measurement or payment shall be made for slurry seal that is not ordered by the Owner, or that extends beyond the limits shown or specified on the Drawings or Standard Drawings, or for slurry seal that is required to restore existing pavements damaged by the Contractor’s operations to the condition existing prior to the start of construction. The Owner reserves the right to vary the quantity of this bid Item from 0%-200% of the original bid quantity with no change in unit price.

I-N. Additional Slurry Seal

The Owner may request that the Contractor furnish and install additional slurry seal at locations to be specified by the Owner. For the purposes of the bid, an allowance for up to 1,500 square yards of slurry seal area is assumed. Payment for this work shall include, but not be limited to, furnishing all labor, materials, tools and equipment necessary for the application of slurry seal of the type specified and to the limits specified or ordered, complete in place, and shall include permits and traffic control not included in any other item of work; pavement surface and crack cleaning; crack sealing; slurry seal; curing and protection; pavement striping, markings and raised markers; and all other incidental work necessary to complete this item of work in its entirety in accordance with the Contract Documents. The pay item in the Bid Schedule defines the unit price and maximum total allowance for this work. Payment for

SECTION 01150 – MEASUREMENT AND PAYMENT

ADDENDUM NO. 1 MEASUREMENT AND PAYMENT REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 01150-7

work under this Bid Schedule will occur only if the work is requested and approved in writing by the Owner.

I-O. Restriping

Payment for restriping shall include, but not be limited to, furnishing all labor, materials, tools and equipment necessary for the application of pavement striping and markings of the type specified and to the limits specified or ordered for the Green Bike Lane Project (Striping Station 11+40 to 59+50), excluding thermoplastic crosswalk striping and green bike lane striping as covered in Schedule II, complete in place, and shall include permits and traffic control not included in any other item of work; removal of existing striping; pavement striping, markings and raised markers; and all other incidental work necessary to complete this item of work in its entirety in accordance with the Contract Documents. No measurement or payment shall be made for striping that is not ordered by the Owner, or that extends beyond the limits shown or specified on the Drawings or Standard Drawings, or for striping that is required to restore existing pavements damaged by the Contractor’s operations to the condition existing prior to the start of construction. Removal of existing striping shall be per Section 17000.

I-P. Potholing Not Shown on Plans

Payment shall include all labor, materials, tools, equipment and incidentals necessary to locate the utility marked out in the field by Dig Alert but not shown on plans by reasonable means. Payment shall include traffic control, surveying and staking, excavation, ensuring continued operations of the utility and temporarily supporting the utility if necessary, working around the utility during pipeline installation, compaction and backfill, any schedule impacts, site restoration and incidental work necessary to verify the sizes, material types, elevations, inclinations and bearings of existing utilities within the work areas. All other potholing is included in Pay Item I-C. Utilities located within 5-feet, center to center, are considered one (1) utility. The Owner reserves the right to vary the quantity of this bid Item from 0%-200% of the original bid quantity with no change in unit price.

I-Q. Unsuitable Material

Payment shall include all labor, materials, tools, equipment and incidentals necessary to remove and replace material determined to be unsuitable by the District for use in the trench or pipe zone. This bid item does NOT apply to pipe subgrade which is covered under Standard Specification 02223-3.10 and overexcavation paid for under the individual pipe segment pay items per Section 01150-1.4. Payment includes removal and disposal of unsuitable material, containment and clean-up of wet unsuitable material, additional shoring or dewatering, providing and placement of suitable backfill material, including hauling, mixing, and screening as necessary, compaction, and any schedule impacts. The Owner reserves the right to vary the quantity of this bid Item from 0%-200% of the original bid quantity with no change in unit price.

SECTION 01150 – MEASUREMENT AND PAYMENT

ADDENDUM NO. 1 MEASUREMENT AND PAYMENT REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 01150-8

B. SCHEDULE II

II-A. Mobilization, Demobilization, Bonds, Permits, Insurance, & Cleanup

Payment shall include compensation for all labor, materials, tools and equipment including, but not limited to, the following principal items: obtaining and complying with permits not included in any other bid item; mobilizing labor force, equipment and construction facilities; providing Contractor field offices and storage yard; securing construction water supply; providing all temporary construction fencing and safety barriers; providing on-site sanitary facilities; obtaining groundwater discharge permits or waivers; posting OSHA requirements and establishing safety programs; daily cleanup; preparing the Schedule of Values prior to the pre-construction meeting; preconstruction/progress video and photographs; work not specified for payment in any other bid item; and all incidentals for the mobilization, demobilization, and permitting for construction of the project as described in the Contract Documents.

Payment shall also include bonds, insurance (including the City of Encinitas as additional insured with $1,000,000 coverage limits), permit applications and fees for City of Encinitas Right-of-Way Construction Permit and Traffic Control Permit and incidentals thereto to construct the project in its entirety in accordance with the Contract Documents. City of Encinitas construction inspection fees will be paid for by the Owner. Earthquake & Tidal Wave Insurance is not required.

Payment for this item shall be limited to five (5) percent of the total contract price.

II-B. Emulsion Aggregate Slurry

Payment for slurry seal work shall include, but not be limited to, furnishing all labor, materials, tools and equipment necessary for the application of Rubber Polymer Modified Slurry of the type specified and to the limits specified or ordered for the work from Garden View Road to Leucadia Blvd (Striping Station 59+50 to 93+50) including both northbound and southbound lanes from curb to curb, complete in place, and shall include permits and traffic control not included in any other item of work; application of herbicide; pavement surface and crack cleaning; crack sealing; slurry seal; curing and protection; and all other incidental work necessary to complete this item of work in its entirety in accordance with the Contract Documents. No measurement or payment shall be made for slurry seal that is not ordered by the Owner, or that extends beyond the limits shown or specified on the Drawings or Standard Drawings, or for slurry seal that is required to restore existing pavements damaged by the Contractor’s operations to the condition existing prior to the start of construction. The Owner reserves the right to vary the quantity of this bid Item from 0%-200% of the original bid quantity with no change in unit price.

II-C. Restriping

Payment for restriping shall include, but not be limited to, furnishing all labor, materials, tools and equipment necessary for the application of pavement striping and marking of the type specified and to the limits specified or ordered for the Green Bike Lane Project (Striping Station 59+50 to 93+50), complete in place,

SECTION 01150 – MEASUREMENT AND PAYMENT

ADDENDUM NO. 1 MEASUREMENT AND PAYMENT REVISED EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 01150-9

and shall include permits and traffic control not included in any other item of work; removal of existing striping; pavement striping, markings and raised markers; and all other incidental work necessary to complete this item of work in its entirety in accordance with the Contract Documents. Payment for this item excludes thermoplastic crosswalks and green bike lane striping. No measurement or payment shall be made for striping that is not ordered by the Owner, or that extends beyond the limits shown or specified on the Drawings or Standard Drawings, or for striping that is required to restore existing pavements damaged by the Contractor’s operations to the condition existing prior to the start of construction.

II-D. Thermoplastic Crosswalk Striping

Payment for thermoplastic crosswalk striping shall include, but not be limited to, furnishing all labor, materials, tools and equipment necessary for the removal of existing striping and application of new thermoplastic crosswalk pavement striping of the type specified and to the limits specified or ordered for the Green Bike Lane Project (Striping Station 11+40 to 93+50), complete in place, and shall include permits and traffic control not included in any other item of work; removal of interfering existing striping; pavement striping; and all other incidental work necessary to complete this item of work in its entirety in accordance with the Contract Documents.

Payment for this item shall also include new vehicle and bike detection loops and associated work as detailed in the Green Bike Lane Project.

II-E. Green Bike Lane Striping

Payment for green bike lane striping shall include, but not be limited to, furnishing all labor, materials, tools and equipment necessary for the application of pavement striping of the type specified and to the limits specified or ordered for the Green Bike Lane Project (Striping Station 11+40 to 93+50), complete in place, and shall include permits and traffic control not included in any other item of work; removal of interfering existing striping; pavement striping, markings and raised markers; and all other incidental work necessary to complete this item of work in its entirety in accordance with the Contract Documents.

END OF SECTION

(BLANK)

SECTION 02222 – PROTECTING EXISTING UNDERGROUND UTILITIES

ADDENDUM NO.1 PROTECTING EXISTING UNDERGROUND UTILITIES EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 02222 - 1

PART 1 - GENERAL

1.1 DESCRIPTION

This section includes materials and procedures for protecting existing underground utilities.

1.2 RELATED WORK SPECIFIED ELSEWHERE

Trenching, Backfilling, and Compaction: Section 02223.

PART 2 - PRODUCTS

2.1 REPLACEMENT IN KIND

Except as indicated or as specifically authorized by the District's Representative, reconstruct utilities with new material of the same size, type, and quality as that removed.

2.2 CONTRACTOR SUPPLIED TEMPORARY MATERIALS

Contractor shall supply all materials, including but not limited to, steel beams and bracing, support straps, sheeting and shoring, timbers, and all other items necessary to protect existing underground utilities.

PART 3 - EXECUTION

3.1 GENERAL

A. Replace in kind street improvements, such as curbs and gutters; fences; signs; paved surfaces; etcetera, that are cut, removed, damaged, or otherwise disturbed by the construction.

B. Where utilities are parallel to or cross the pipeline trench but do not conflict with the permanent work to be constructed, follow the procedures given below and as indicated on the Drawings. Notify the utility owner 48 hours in advance of the crossing construction and coordinate the construction schedule with the utility owner's requirements. For utility crossings not shown on the Drawings, refer to the instructions of the District's Representative for guidance.

3.2 PROCEDURES

A. Protect in Place: Protect utilities in place, unless abandoned, and maintain the utility in service, unless otherwise specified.

B. Cut and Plug Ends: Cut abandoned utility lines and plug the ends with concrete plug. Pour a concrete lug completely around the plugged end of the abandoned utility line such that the line is encapsulated with a minimum of 6 inches of concrete on all sides. Dispose of the cut pipe as unsuitable material.

SECTION 02222 – PROTECTING EXISTING UNDERGROUND UTILITIES

ADDENDUM NO.1 PROTECTING EXISTING UNDERGROUND UTILITIES EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 02222 - 2

C. Remove and Reconstruct: Where necessary or as required by the District's Representative, remove the utility and, after passage, reconstruct it with new materials. Provide temporary service for the disconnected utility.

3.3 COMPACTION

A. Utilities Protected in Place: Backfill and compact under and around the utility so that no voids are left. Where utilities are concrete encased, use the alternative construction method (sand slurry) for backfill around the utility.

B. Alternative Construction - Sand Slurry: Sand slurry consisting of one sack (94 pounds) of portland cement per cubic yard of sand and sufficient moisture for workability may be required for backfill to aid in reducing compaction difficulties. Submit specific methods and procedures for the review of the District's Representative prior to construction.

3.4 ADJACENT PARALLEL UTILITIES

Protect existing parallel utilities from any disturbances and repair the lines and associated appurtenances if they are damaged in any way. All costs incurred for protection of utilities or any costs incurred due to the presence of the lines, whether or not they lie within the new construction, shall be borne in full by the Contractor.

3.5 POTHOLING EXISTING UTILITIES (THIS SECTION TAKES PRECEDECE IN CASE OF ANY DISCREPENCY)

A. The cost for potholing is included in applicable bid items if a separate bid item is not listed.

B. Contractor must follow all current and applicable laws regarding Underground Service Alert of Southern California (Dig Alert).

C. All existing utilities indicated on the drawings are shown diagrammatically and approximately are based on field research, as-built drawings and/or the original construction drawings. The Contractor shall take all precautionary measures to protect any existing utilities or structures at the work site. Any damage to utilizes shall be repaired by Contractor to the specifications of the utility that are located with 5 feet of the proposed pipe alignment (including all appurtenances) or structure and verify the size, material, horizontal & vertical locations, bearing and inclination of all existing utilizes prior to any demolition work or installation of new work.

D. Potholing shall proceed as follows:

1. Field stake the pipeline alignments and/or edges of structures and notify Dig Alert for field mark out of all existing utilities that are crossing or paralleling (within 5 feet horizontally) of the proposed construction. The field staking shall include elevation hubs to be used to determine the elevation of the potholed utilizes. Do not saw cut for pipe alignment or structures until potholing has been completed and any conflicts have been resolved.

2. The Contractor shall pothole all crossing utilities and parallel utilities marked out by Dig Alert that are located with 5 feet of the proposed pipe alignment or structure and verify the size, material, horizontal alignment & vertical elevation, bearing and inclination of all

SECTION 02222 – PROTECTING EXISTING UNDERGROUND UTILITIES

ADDENDUM NO.1 PROTECTING EXISTING UNDERGROUND UTILITIES EL CAMINO REAL PIPELINE REPLACEMENT AND GREEN BIKE LANE PROJECT PAGE 02222 - 3

existing utilities (top and bottom) prior to any demolition work or installation of new work. Backfill all potholes with ¾” rock to facilitate location during construction.

3. The Contractor shall pothole all crossing utilities and parallel utilities NOT SHOWN ON PLANS BUT MARKED OUT BY DIG ALERT that are located within 5 feet of the proposed pipe alignment or structure and verify the size, material, horizontal and vertical locations, bearing and inclination of hall existing utilities (top and bottom) prior to any demolition work or installation of new work.

4. The cost of potholing utilities marked out by Dig Alert but NOT SHOWN ON PLANS will be paid by the Potholing bid item based on field measured quantities. This bid quantity may vary 0%-200% with no change in bid price.

5. The Contractor must notify the District when they are unable to locate a utility marked out by Dig Alert and/or shown on plans and the Contractor has complied with the locating requirements of Dig Alert (i.e. 24” either side of the mark out or plan location to a reasonable depth without finding the utility). The District will provide additional direction for locating the utility and this work will be paid on a time and materials basis.

6. The Contractor may NOT be field verify the depths of storm drains or gravity sewer mains by measuring the depth to invert of the nearest manhole located on each side of the proposed pipeline or structure.

7. The Contractor shall schedule the potholing work to include a period of ten (10) working days after submission of the completed pothole form to the District to allow sufficient time for the District to make any design revisions. Contractor to provide clear, written pothole data to the owner (as a submittal) on the attached form.

END OF SECTION

SECTION 17000 SPECIAL PROVISIONS PER THE CITY OF ENCINITAS REVISED

REVISED Addendum No. 1 SECTION D: Part 3 Page 1

SECTION D: SPECIAL PROVISIONS TO GREENBOOK PART 2

SPECIAL PROVISIONS TO GREENBOOK: MATERIALS SECTION 214 – TRAFFIC STRIPING, CURB AND PAVEMENT MARKINGS, AND PAVEMENT MARKERS

214-1 GENERAL. ADD the following: Materials (paint and thermoplastic), equipment, mixing (paint), surface preparation, application and tolerances, shall conform to Sections 84---1 and 84---3 of the State of California, Department of Transportation’s Standard Specifications except as modified herein. Pavement markers shall conform to Section 85 and 95 of the State of California, Department of Transportation’s Standard Specifications. All details and dimensions for pavement markings shall conform to City---approved stencils. Thinner shall not be mixed with paint. Paint shall dry "tack---free" within thirty (30) minutes. Paint used for pavement legends and striping shall be a compound of paint and glass beads. All crosswalks and stop bars shall be thermoplastic. All “Bike Lane” and associated arrow legend pavement marking, Caltrans STD Plans A24A and A24D, shall be paint. All other pavement markings shall be thermoplastic. Traffic line paint shall be rapid dry paint and shall contain reflective material conforming to Section 84---1 and 84---3 of the Caltrans Standard Specifications. Paint shall comply with all application of local air pollution control regulations. Samples of traffic striping and pavement marking materials shall be submitted to the Engineer at least two weeks prior to application. All details and dimensions for traffic striping shall conform to the latest edition of the State of California, Department of Transportation’s Traffic Design Manual and Maintenance Manual. ADD the Following: 214-4.3 GREEN BIKE LANE PAINT. Green bike lane paint shall be Ennis-Flint 985206 green standard fast dry waterborne traffic paint or approved equal. Glass Beads associated with green bike lane paint shall meet the following specifications:

a. Beads suitable for inter-mix or drop-on applications and produced to meet all Federal, State, County and City specifications.

b. Size range shall be 20-325 US mesh or 45-850 microns. c. Roundness shall be greater than or equal to 70%. d. Refractive Index shall be greater than or equal to 1.51. e. Specific gravity shall be approximately 2.5.

SECTION 17000 SPECIAL PROVISIONS PER THE CITY OF ENCINITAS REVISED

REVISED Addendum No. 1 SECTION D: Part 3 Page 2

ADD the Following: 214-8 TRAFFIC SIGNING. All sign posts shall be 2”---square, perforated galvanized steel with break---away base, per City of San Diego Regional Standard Drawing No. SDM-104, unless otherwise specified. All sign posts shall be installed 2 feet behind the face of curb, unless otherwise specified. Contractor furnished custom “Yield to Bike” sign shall conform to the City of San Diego Bicycle Facilities Design Guidelines. Contractor shall submit product sign data sheets at the pre---construction meeting for approval by the City Engineer. ADD the Following: 214-9 BUFFER LANE BOLLARDS. All Buffer Lane Bollards shall be City Post type manufactured by Tapco or Pexco, or City approved equal. All Buffer Lane Bollards shall be 28” high with a 3” outside diameter. All Buffer Lane Bollards shall be green with white reflectors or as approved by the City Engineer. All Buffer Lane Bollards shall meet CAMUTCD requirements for channelizing devices, and NCHRP 350 for Category 1 devices.

SECTION D: SPECIAL PROVISIONS TO GREENBOOK PART 3

SPECIAL PROVISIONS TO GREENBOOK: CONSTRUCTION METHODS SECTION 314 – TRAFFIC STRIPING, CURB AND PAVEMENT MARKINGS, AND PAVEMENT MARKERS

314-1 GENERAL. ADD the following: Installation of all signs, striping, and pavement markers shall be the responsibility of the contractor and shall conform to the most recent edition of the following standard plans and specifications: a) California Manual on Uniform Traffic Control Devices (MUTCD) b) State of California Department of Transportation (Caltrans) Standard Plans c) State of California Department of Transportation (Caltrans) Standard Specifications d) Standard Specifications for Public Works Construction (“Greenbook”), including all current supplements Contractor shall submit product manuals and specifications for paint materials at the pre-construction meeting for approval by the City Engineer. 314-2 REMOVAL OF TRAFFIC STRIPING AND CURB AND PAVEMENT MARKINGS. 314-4.2 GENERAL. DELETE first paragraph and REPLACE with the following:

SECTION 17000 SPECIAL PROVISIONS PER THE CITY OF ENCINITAS REVISED

REVISED Addendum No. 1 SECTION D: Part 3 Page 3

Contractor shall remove the pavement paint stripes, markings and thermoplastic in a way that does not damage the underlying asphalt greater than 1/8” in depth. Contractor shall remove all conflicting striping and pavement markings by grinding method. Alternative methods must be pre---approved by the City Engineer. Any debris shall be promptly removed by the contractor. 314-4 APPLICATION OF TRAFFIC STRIPING AND CURB AND PAVEMENT MARKINGS. 314-4.2 CONTROL OF ALIGNMENT AND LAYOUT. 314-4.2.1 GENERAL. ADD the following: The final location of all signs, striping, pavement markings and pavement markers are subject to the approval of the City Engineer prior to installation and/or removal. Contractor shall notify the City Engineer or his representative a minimum of 1 week in advance to schedule a field “walk through” to “mark---out” all signs scheduled for removal, replacement and/or relocation, and to “mark---out” the locations for placement of new and/or relocated signs. Contractor shall clearly “mark---out” the locations of all new striping and pavement markings prior to installation. The contractor shall notify the City Engineer or his representative a minimum of 1 week in advance to schedule an inspection of the “mark---outs”. All traffic stripes and pavement markings shall be reflectorized. The Contractor shall apply two coats on all traffic striping. Control of alignment and layout shall be the responsibility of the Contractor and subject to approval by the Engineer. Contractor shall be responsible for maintaining safe traffic operation through the work area. Pavement markers shall conform to Section 85, Pavement Markers, of the Caltrans Standard Specifications and these Special Provisions.

SECTION D: SPECIAL PROVISIONS TO GREENBOOK PART 7

SPECIAL PROVISIONS TO GREENBOOK: STREET LIGHTING AND TRAFFIC SIGNAL SYSTEMS

SECTION 700 – MATERIALS 700-5 TRAFFIC SIGNAL MATERIALS 700-5.8 DETECTORS 700-5.8.2 Inductive Loop Detectors. Add the following: Vehicle detector loops shall be Type F per Caltrans RSP ES-5b, most recent edition. Bicycle loops shall be modified Type Q per Caltrans RSP ES-5B, most recent edition, size shall be as shown on the plans. 700-5.8.2.1 Conductors. Add the following:

SECTION 17000 SPECIAL PROVISIONS PER THE CITY OF ENCINITAS REVISED

REVISED Addendum No. 1 SECTION D: Part 3 Page 4

Loop detector lead-in cable shall be Type B conductor for each inductive detector loop, shall be continuous and unspliced, and shall conform to the provisions in Section 86-5.01A (4) of the Caltrans Standard Specifications, most recent edition, for Type 2 loop wire. 700-5.8.2.4 Sealants. Add the following: Loop sealant shall be the Hot-Melt Rubberized Asphalt sealant type, and shall conform to the provisions in Section 86-102W(4), unless otherwise directed by the Resident Engineer. Loop conductors and sealant shall be installed on the same day the loop slots are cut.

T

R

A

F

F

I

C

OWNER/ PERMITEE:

CITY OF ENCINITAS, CALIFORNIA

505 S. VULCAN AVE.

ENCINITAS, CA. 92024

CONSULTANTS / FIRMS

PROJECT DIRECTORY

CITY CONTACT / STAFF NAME & NO.

PROJECT DESCRIPTION

DECLARATION OF RESPONSIBLE CHARGE

CONSTRUCTION PLANS

CITY OF ENCINITAS

ENCINITAS, CALIFORNIA

FOR

EL CAMINO REAL GREEN BIKE LANE PROJECT

VICINITY MAP

CONTRACT NO. XXXXX

PROJECT LOCATION

NAME: STC TRAFFIC, INC.

CONTACT NAME: NICOLAS MINICILLI

ADDRESS: 5865 AVENIDA ENCINAS, STE 142B,

CARLSBAD, CA 92008

PHONE NO: 760-602-4290

FAX NO: 760-670-3445

EMAIL: [email protected]

STAFF NAME: ABRAHAM BANDEGAN

PHONE NO: 760-560-6035

FAX NO: 760-633-2818

EMAIL: [email protected]

AutoCAD SHX Text
VERTICAL
AutoCAD SHX Text
HORIZONTAL
AutoCAD SHX Text
EXP.
AutoCAD SHX Text
R.C.E. NO.
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
PLANS PREPARED UNDER SUPERVISION OF
AutoCAD SHX Text
PUBLIC IMPROVEMENT PLANS FOR:
AutoCAD SHX Text
CITY OF ENCINITAS
AutoCAD SHX Text
SHEET OF 10
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
ENGINEERING DEPARTMENT
AutoCAD SHX Text
APPROVALS
AutoCAD SHX Text
DATE
AutoCAD SHX Text
REFERENCES
AutoCAD SHX Text
DATE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
BENCHMARK
AutoCAD SHX Text
N/A
AutoCAD SHX Text
EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
DESIGNED BY
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
CHECKED BY
AutoCAD SHX Text
TWO WORKING DAYS BEFORE YOU DIG
AutoCAD SHX Text
811
AutoCAD SHX Text
CALL TOLL FREE
AutoCAD SHX Text
CALL BEFORE YOU DIG
AutoCAD SHX Text
Underground Service Alert
AutoCAD SHX Text
Dig Alert
AutoCAD SHX Text
BY:
AutoCAD SHX Text
BY:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
RECOMMENDED
AutoCAD SHX Text
74667
AutoCAD SHX Text
12-31-2021
AutoCAD SHX Text
AA
AutoCAD SHX Text
NM
AutoCAD SHX Text
JS
AutoCAD SHX Text
5865 AVENIDA ENCINAS, #142B
AutoCAD SHX Text
CARLSBAD, CA 92008
AutoCAD SHX Text
PH: 760-602-4290
AutoCAD SHX Text
WWW.STCTRAFFIC.COM
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
C
AutoCAD SHX Text
A
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
A
AutoCAD SHX Text
I
AutoCAD SHX Text
NO. 74667
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
V
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
N
AutoCAD SHX Text
O
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
P
AutoCAD SHX Text
D
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
T
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
O
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
S
AutoCAD SHX Text
M
AutoCAD SHX Text
.
AutoCAD SHX Text
M
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
Exp. 12-31-2021
AutoCAD SHX Text
100% PLANS - EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
NICOLAS M. MINICILLI
AutoCAD SHX Text
1"=40'
AutoCAD SHX Text
10-03-2019
AutoCAD SHX Text
1
AutoCAD SHX Text
TITLE SHEET
AutoCAD SHX Text
FIRM:
AutoCAD SHX Text
ADDRESS:
AutoCAD SHX Text
CITY, ST.:
AutoCAD SHX Text
TELEPHONE:
AutoCAD SHX Text
BY:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
I HEREBY DECLARE THAT I AM THE ENGINEER OF WORK FOR THIS PROJECT, THAT I HAVE EXERCISED RESPONSIBLE CHARGE OVER THE DESIGN OF THE PROJECT AS DEFINED IN SECTION 6703 OF THE BUSINESS AND PROFESSIONS CODE, AND THAT THE DESIGN IS CONSISTENT WITH CURRENT STANDARDS. I UNDERSTAND THAT THE CHECK OF PROJECT DRAWINGS AND SPECIFICATIONS BY THE CITY OF ENCINITAS DOES NOT RELIEVE ME AS ENGINEER OF WORK, OF MY RESPONSIBILITIES FOR PROJECT DESIGN.
AutoCAD SHX Text
STC TRAFFIC, INC.
AutoCAD SHX Text
5865 AVENIDA ENCINAS, SUITE 142B
AutoCAD SHX Text
CARLSBAD, CA
AutoCAD SHX Text
760-602-4290
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
SANTA FE DR.
AutoCAD SHX Text
BIRMINGHAM
AutoCAD SHX Text
DRIVE
AutoCAD SHX Text
SAN ELIJO AVE.
AutoCAD SHX Text
ENCINITAS
AutoCAD SHX Text
BLVD.
AutoCAD SHX Text
LEUCADIA
AutoCAD SHX Text
BLVD.
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
MANCHESTER
AutoCAD SHX Text
AVE.
AutoCAD SHX Text
RANCHO
AutoCAD SHX Text
MANCHESTER
AutoCAD SHX Text
AVE.
AutoCAD SHX Text
RANCHO
AutoCAD SHX Text
SANTA FE
AutoCAD SHX Text
RD.
AutoCAD SHX Text
ENCINITAS
AutoCAD SHX Text
BLVD.
AutoCAD SHX Text
VULCAN
AutoCAD SHX Text
S21
AutoCAD SHX Text
S21
AutoCAD SHX Text
SAN
AutoCAD SHX Text
ELIJO
AutoCAD SHX Text
LAGOON
AutoCAD SHX Text
S9
AutoCAD SHX Text
S9
AutoCAD SHX Text
S11
AutoCAD SHX Text
EL CAMINO
AutoCAD SHX Text
REAL
AutoCAD SHX Text
PACIFIC
AutoCAD SHX Text
OCEAN
AutoCAD SHX Text
ENCINITAS
AutoCAD SHX Text
5
AutoCAD SHX Text
SAN DIEGO FRWY.
AutoCAD SHX Text
SANTA FE RD.
AutoCAD SHX Text
JACK
AutoCAD SHX Text
LONE
AutoCAD SHX Text
LANE
AutoCAD SHX Text
JACKIE
AutoCAD SHX Text
RD.
AutoCAD SHX Text
N. COAST HWY 101
AutoCAD SHX Text
VIA CANTEBRIA
AutoCAD SHX Text
GARDEN VIEW RD
AutoCAD SHX Text
OLIVENHAIN
AutoCAD SHX Text
RD.
AutoCAD SHX Text
EL CAMINO REAL FROM LEUCADIA BLVD/OLIVENHAIN RD TO ENCINITAS BLVD
AutoCAD SHX Text
PROJECT CORRIDOR
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
REGISTRATION EXPIRATION DATE:
AutoCAD SHX Text
74667
AutoCAD SHX Text
12-31-2021
AutoCAD SHX Text
NICOLAS M. MINICILLI
AutoCAD SHX Text
INSTALLATION OF GREEN BIKE LANES, CONTINENTAL CROSSWALKS, AND BIKE LANE SIGNAGE.
AutoCAD SHX Text
TS-001
AutoCAD SHX Text
10-03-2019

T

R

A

F

F

I

C

AutoCAD SHX Text
VERTICAL
AutoCAD SHX Text
HORIZONTAL
AutoCAD SHX Text
EXP.
AutoCAD SHX Text
R.C.E. NO.
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
PLANS PREPARED UNDER SUPERVISION OF
AutoCAD SHX Text
PUBLIC IMPROVEMENT PLANS FOR:
AutoCAD SHX Text
CITY OF ENCINITAS
AutoCAD SHX Text
SHEET OF 10
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
ENGINEERING DEPARTMENT
AutoCAD SHX Text
APPROVALS
AutoCAD SHX Text
DATE
AutoCAD SHX Text
REFERENCES
AutoCAD SHX Text
DATE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
BENCHMARK
AutoCAD SHX Text
N/A
AutoCAD SHX Text
EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
DESIGNED BY
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
CHECKED BY
AutoCAD SHX Text
TWO WORKING DAYS BEFORE YOU DIG
AutoCAD SHX Text
811
AutoCAD SHX Text
CALL TOLL FREE
AutoCAD SHX Text
CALL BEFORE YOU DIG
AutoCAD SHX Text
Underground Service Alert
AutoCAD SHX Text
Dig Alert
AutoCAD SHX Text
BY:
AutoCAD SHX Text
BY:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
RECOMMENDED
AutoCAD SHX Text
74667
AutoCAD SHX Text
12-31-2021
AutoCAD SHX Text
AA
AutoCAD SHX Text
NM
AutoCAD SHX Text
JS
AutoCAD SHX Text
5865 AVENIDA ENCINAS, #142B
AutoCAD SHX Text
CARLSBAD, CA 92008
AutoCAD SHX Text
PH: 760-602-4290
AutoCAD SHX Text
WWW.STCTRAFFIC.COM
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
C
AutoCAD SHX Text
A
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
A
AutoCAD SHX Text
I
AutoCAD SHX Text
NO. 74667
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
V
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
N
AutoCAD SHX Text
O
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
P
AutoCAD SHX Text
D
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
T
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
O
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
S
AutoCAD SHX Text
M
AutoCAD SHX Text
.
AutoCAD SHX Text
M
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
Exp. 12-31-2021
AutoCAD SHX Text
100% PLANS - EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
NICOLAS M. MINICILLI
AutoCAD SHX Text
1"=40'
AutoCAD SHX Text
10-03-2019
AutoCAD SHX Text
%%UDESCRIPTION
AutoCAD SHX Text
%%USHEET NO
AutoCAD SHX Text
1 TITLE SHEET TITLE SHEET 2 SHEET INDEX SHEET INDEX 3 DETAILS SHEET DETAILS SHEET 4-7 SIGNING AND STRIPING PLAN: EL CAMINO REAL - FROM LEUCADIA BLVD/ SIGNING AND STRIPING PLAN: EL CAMINO REAL - FROM LEUCADIA BLVD/ OLIVENHAIN RD TO ENCINITAS BLVD 8-10 LOOP DETECTION MODIFICATION PLAN: EL CAMINO REAL - FROM LEUCADIA BLVD/ LOOP DETECTION MODIFICATION PLAN: EL CAMINO REAL - FROM LEUCADIA BLVD/ OLIVENHAIN RD TO ENCINITAS BLVD
AutoCAD SHX Text
#
AutoCAD SHX Text
%%UKEY MAP LEGEND
AutoCAD SHX Text
PLAN SHEET NUMBER
AutoCAD SHX Text
PROJECT LOCATION
AutoCAD SHX Text
CITY HALL
AutoCAD SHX Text
CITY OF ENCINITAS
AutoCAD SHX Text
SHEET INDEX
AutoCAD SHX Text
CITY OF ENCINITAS KEY MAP
AutoCAD SHX Text
5
AutoCAD SHX Text
REAL
AutoCAD SHX Text
EL
AutoCAD SHX Text
CAMINO
AutoCAD SHX Text
ENCINITAS
AutoCAD SHX Text
BLVD
AutoCAD SHX Text
COAST
AutoCAD SHX Text
SANTA
AutoCAD SHX Text
OCEAN
AutoCAD SHX Text
PACIFIC
AutoCAD SHX Text
HIGHWAY
AutoCAD SHX Text
OLIVENHAIN RD
AutoCAD SHX Text
LEUCADIA
AutoCAD SHX Text
BLVD
AutoCAD SHX Text
VULCAN
AutoCAD SHX Text
AVE
AutoCAD SHX Text
SAN ELIJO
AutoCAD SHX Text
AVE
AutoCAD SHX Text
AVE
AutoCAD SHX Text
RANCHO SANTA FE RD
AutoCAD SHX Text
MANCHESTER
AutoCAD SHX Text
GARDEN
AutoCAD SHX Text
VIEW
AutoCAD SHX Text
RD
AutoCAD SHX Text
VIA
AutoCAD SHX Text
CANTEBRIA
AutoCAD SHX Text
FE DR
AutoCAD SHX Text
4
AutoCAD SHX Text
UNDERGROUND SERVICE ALERT
AutoCAD SHX Text
SDG&E
AutoCAD SHX Text
AT&T
AutoCAD SHX Text
TIME WARNER CABLE
AutoCAD SHX Text
COX COMMUNICATIONS
AutoCAD SHX Text
8-1-1
AutoCAD SHX Text
(800) 611-7343
AutoCAD SHX Text
(800) 750-2355
AutoCAD SHX Text
(760) 438-7741
AutoCAD SHX Text
(760) 806-9809
AutoCAD SHX Text
CITY OF ENCINITAS (PUBLIC WORKS)
AutoCAD SHX Text
(760) 633-2840
AutoCAD SHX Text
CITY OF ENCINITAS (ENGINEERING)
AutoCAD SHX Text
(760) 633-2770
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
%%UUTILITY CONTACT INFORMATION
AutoCAD SHX Text
%%UCONSTRUCTION NOTES
AutoCAD SHX Text
APPLY 6" DASHED WHITE LINE PER CALTRANS 2015 STD PLAN A20A, DETAIL 9. APPLY 4" SOLID WHITE RIGHT EDGE LINE PER CALTRANS 2015 STD PLAN A20D, DETAIL 38. APPLY 8" DASHED WHITE LANE DROP LINE PER CALTRANS 2015 STD PLAN A20C, DETAIL 37B. APPLY 6" SOLID WHITE LINE PER CALTRANS 2015 STD PLAN A20D, DETAIL 39. APPLY CONFLICT ZONE STRIPING WITH 6" DASHED WHITE LINE PER CALTRANS 2015 STD PLAN A20D, DETAIL 39A. APPLY GREEN PAINT PER DETAIL "A" ON SHEET 3. APPLY 12" SOLID THERMOPLASTIC WHITE LIMIT LINE PER CALTRANS 2015 STD PLAN A24E. APPLY 6" SOLID WHITE 30 DEGREE DIAGONAL STRIPE AT 40' OC. INSTALL "BIKE LANE" AND ARROW LEGEND PAVEMENT MARKING PER CALTRANS STD PLANS A24A AND A 24D. SYMBOL SHALL BE CENTERED BETWEEN THE LEFT EDGE OF THE BIKE LANE AND THE CURB. INSTALL WHITE THERMOPLASTIC CONTINENTAL CROSSWALK PER DETAIL "B" ON SHEET 3. PAINT BIKE LANE AREA GREEN WITH ENNIS-FLINT 985206 GREEN STANDARD FAST DRY WATERBORNE TRAFFIC PAINT. INSTALL PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE VII (L) ARROW. INSTALL PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE VII (R) ARROW. INSTALL PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE IV (L) ARROW. INSTALL PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE IV (R) ARROW. FURNISH AND INSTALL 28" HIGH TAPCO CITY POST PER DETAIL "D" ON SHEET 3. INSTALL THERMOPLASTIC PAVEMENT MARKING PER PLAN PER CALTRANS STANDARD 2015 STD A24E. INSTALL NEW SIGN AND POST PER PLAN. BOTTOM OF SIGN SHALL HAVE A MINIMUM OF 7' CLEARANCE ABOVE FINISHED SURFACE. INSTALL SIGN PER PLAN ON EXISTING STREET LIGHT POLE. BOTTOM OF SIGN SHALL HAVE A MINIMUM OF 7' CLEARANCE ABOVE FINISHED SURFACE. FURNISH AND INSTALL TYPE E VEHICLE DETECTOR LOOP. LIMIT LINE LOOP SHALL BE VEHICLE/BIKE TYPE PER DETAIL "C" ON SHEET 3. FURNISH AND INSTALL 4'x6' MODIFIED TYPE Q BICYCLE DETECTOR LOOP PER DETAIL "D" ON SHEET 3. FURNISH AND INSTALL NEW DETECTOR CARDS IN CABINET IF NECESSARY. REFRESH EXISTING PAVEMENT MARKINGS AS NECESSARY PER SIGNING AND STRIPING PLANS. EXISTING TO REMAIN. REMOVE EXISTING STRIPING BY GRINDING.
AutoCAD SHX Text
E
AutoCAD SHX Text
%%UGENERAL NOTES
AutoCAD SHX Text
QUAIL
AutoCAD SHX Text
RDENS
AutoCAD SHX Text
DR
AutoCAD SHX Text
GA
AutoCAD SHX Text
SAXONY RD
AutoCAD SHX Text
5
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
2
AutoCAD SHX Text
SHEET INDEX
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
5
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
8
AutoCAD SHX Text
9
AutoCAD SHX Text
10
AutoCAD SHX Text
11
AutoCAD SHX Text
12
AutoCAD SHX Text
13
AutoCAD SHX Text
14
AutoCAD SHX Text
20
AutoCAD SHX Text
21
AutoCAD SHX Text
R
AutoCAD SHX Text
15
AutoCAD SHX Text
THE IMPROVEMENTS ARE TO COMPLY WITH THESE PLANS AND THE LATEST EDITIONS OF THE FOLLOWING STANDARDS, GUIDELINES, AND SPECIFICATIONS: CALTRANS STANDARD PLANS AND SPECIFICATIONS CAMUTCD CALTRANS TRAFFIC SIGNAL CONTROL EQUIPMENT SPECIFICATIONS CALTRANS FIBER OPTIC DESIGN MANUAL THE GREENBOOK, SPECIFICATION FOR PUBLIC WORKS CONSTRUCTION SAN DIEGO AREA REGIONAL STANDARD DRAWINGS CITY OF ENCINITAS ENGINEERING MANUAL CITY OF SAN DIEGO BICYCLE FACILITY DESIGN GUIDELINES (DRAFT) THE SPECIAL PROVISIONS MANUFACTURERS SPECIFICATIONS AND INSTALLATION RECOMMENDATIONS IN THE EVENT OF A CONFLICT BETWEEN PROJECT PLANS AND/OR SPECIFICATIONS AND/OR SPECIFICATIONS PUBLICATIONS, THE SUPERIOR STANDARD SHALL PREVAIL AS DETERMINED BY THE ENGINEER OR INSPECTOR. THE LATEST EDITIONS OF THE ABOVE REFERENCED DOCUMENTS APPLY.
AutoCAD SHX Text
CENTERLINE
AutoCAD SHX Text
EXISTING SIGN ON POST
AutoCAD SHX Text
EXISTING BACK OF SIDEWALK
AutoCAD SHX Text
RIGHT-OF-WAY
AutoCAD SHX Text
EXISTING TRAFFIC SIGNAL
AutoCAD SHX Text
S
AutoCAD SHX Text
EXISTING STREET NAME SIGN
AutoCAD SHX Text
PROPOSED SIGN ON POLE
AutoCAD SHX Text
PROPOSED SIGN ON POST
AutoCAD SHX Text
EXISTING GUTTER
AutoCAD SHX Text
EXISTING SIGN ON POLE
AutoCAD SHX Text
EXISTING CURB
AutoCAD SHX Text
%%ULEGEND
AutoCAD SHX Text
16
AutoCAD SHX Text
SIGNING AND STRIPING INSTALLATIONS SHALL CONFORM TO THE CURRENT STATE OF
AutoCAD SHX Text
CALIFORNIA DEPARTMENT OF TRANSPORTATION (CALTRANS) STANDARD PLANS AND (RSP)
AutoCAD SHX Text
SIGNS SHALL CONFORM TO THE CURRENT CALTRANS SIGN SPECIFICATIONS, AND 2014
AutoCAD SHX Text
CALIFORNIA MUTCD REV 2. SIGN SIZE SHALL BE THE STANDARD SIZE NOTED IN THE SIGN
AutoCAD SHX Text
SPECIFICATIONS UNLESS NOTED OTHERWISE ON THE PLAN.
AutoCAD SHX Text
ALL PAINT WORK SHALL BE DOUBLE COATED AND BEADED, CONFORMING TO THE
AutoCAD SHX Text
ANY PRE-LINED STRIPING AND MARKING LAYOUT WORK SHALL BE VERIFIED BY THE CITY
AutoCAD SHX Text
1.
AutoCAD SHX Text
2.
AutoCAD SHX Text
3.
AutoCAD SHX Text
REVISED STANDARD PLANS (DATED JULY 21, 2017), STANDARD SPECIFICATIONS, THE
AutoCAD SHX Text
PROJECT SPECIAL PROVISIONS, 2014 CALIFORNIA MUTCD REV 2, AND THE CITY OF ENCINITAS
AutoCAD SHX Text
PUBLIC WORKS DEPARTMENT STANDARD DRAWINGS AND SPECIFICATIONS, CURRENT EDITION.
AutoCAD SHX Text
REQUIREMENTS SET FORTH IN THE STANDARD SPECIFICATIONS.
AutoCAD SHX Text
4.
AutoCAD SHX Text
TRAFFIC ENGINEER PRIOR TO THE PLACEMENT OF FINAL PAINTED PAVEMENT STRIPING
AutoCAD SHX Text
OR MARKINGS.
AutoCAD SHX Text
ANY EXISTING CONFLICTING TRAFFIC STRIPING AND PAVEMENT MARKINGS AND R.P.M.'S
AutoCAD SHX Text
5.
AutoCAD SHX Text
SHALL BE REMOVED AS REQUIRED BY GRINDING (OR OTHER APPROVED METHOD).
AutoCAD SHX Text
PAVEMENT SURFACES ARE TO BE FREE OF ALL REMOVABLE RESIDUE PRIOR TO
AutoCAD SHX Text
APPLICATION OF PAINT.
AutoCAD SHX Text
A MINIMUM OF SEVEN DAYS SHALL BE PROVIDED BETWEEN FIRST AND SECOND PAINT
AutoCAD SHX Text
6.
AutoCAD SHX Text
WORK COATING.
AutoCAD SHX Text
THE CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS TO ENSURE SALVAGED
AutoCAD SHX Text
7.
AutoCAD SHX Text
EQUIPMENT IS NOT DAMAGED DURING THEIR OPERATIONS. MOVEMENT OF SALVAGED
AutoCAD SHX Text
EQUIPMENT SHALL BE COORDINATED WITH THE CITY. ALL SALVAGED ITEMS SHALL BE
AutoCAD SHX Text
DELIVERED TO THE CITY SERVICE YARD.
AutoCAD SHX Text
AB ABANDON. ABANDON. AVE AVENUE. AVENUE. BLVD BOULEVARD. BOULEVARD. CAMUTCD CALIFORNIA MANUAL ON TRAFFIC CONTROL DEVICES. CALIFORNIA MANUAL ON TRAFFIC CONTROL DEVICES. DR DRIVE. DRIVE. DWY DRIVEWAY. DRIVEWAY. EX EXISTING. EXISTING. MPH MILES PER HOUR. MILES PER HOUR. OC ON CENTER. ON CENTER. R/W RIGHT OF WAY. RIGHT OF WAY. SC SPLICE NEW TO EXISTING CONDUCTORS. SPLICE NEW TO EXISTING CONDUCTORS. RD ROAD. ROAD. SNS STREET NAME SIGN. STREET NAME SIGN. STD STANDARD. STANDARD. TYP TYPICAL.TYPICAL.
AutoCAD SHX Text
%%UABBREVIATIONS
AutoCAD SHX Text
22
AutoCAD SHX Text
TS-002
AutoCAD SHX Text
%%USTANDARDS
AutoCAD SHX Text
23

T

R

A

F

F

I

C

AutoCAD SHX Text
VERTICAL
AutoCAD SHX Text
HORIZONTAL
AutoCAD SHX Text
EXP.
AutoCAD SHX Text
R.C.E. NO.
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
PLANS PREPARED UNDER SUPERVISION OF
AutoCAD SHX Text
PUBLIC IMPROVEMENT PLANS FOR:
AutoCAD SHX Text
CITY OF ENCINITAS
AutoCAD SHX Text
SHEET OF 10
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
ENGINEERING DEPARTMENT
AutoCAD SHX Text
APPROVALS
AutoCAD SHX Text
DATE
AutoCAD SHX Text
REFERENCES
AutoCAD SHX Text
DATE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
BENCHMARK
AutoCAD SHX Text
N/A
AutoCAD SHX Text
EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
DESIGNED BY
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
CHECKED BY
AutoCAD SHX Text
TWO WORKING DAYS BEFORE YOU DIG
AutoCAD SHX Text
811
AutoCAD SHX Text
CALL TOLL FREE
AutoCAD SHX Text
CALL BEFORE YOU DIG
AutoCAD SHX Text
Underground Service Alert
AutoCAD SHX Text
Dig Alert
AutoCAD SHX Text
BY:
AutoCAD SHX Text
BY:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
RECOMMENDED
AutoCAD SHX Text
74667
AutoCAD SHX Text
12-31-2021
AutoCAD SHX Text
AA
AutoCAD SHX Text
NM
AutoCAD SHX Text
JS
AutoCAD SHX Text
5865 AVENIDA ENCINAS, #142B
AutoCAD SHX Text
CARLSBAD, CA 92008
AutoCAD SHX Text
PH: 760-602-4290
AutoCAD SHX Text
WWW.STCTRAFFIC.COM
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
C
AutoCAD SHX Text
A
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
A
AutoCAD SHX Text
I
AutoCAD SHX Text
NO. 74667
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
V
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
N
AutoCAD SHX Text
O
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
P
AutoCAD SHX Text
D
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
T
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
O
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
S
AutoCAD SHX Text
M
AutoCAD SHX Text
.
AutoCAD SHX Text
M
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
Exp. 12-31-2021
AutoCAD SHX Text
100% PLANS - EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
NICOLAS M. MINICILLI
AutoCAD SHX Text
1"=40'
AutoCAD SHX Text
10-03-2019
AutoCAD SHX Text
3
AutoCAD SHX Text
DETAILS SHEET
AutoCAD SHX Text
MIN 4'
AutoCAD SHX Text
%%UDETAIL B
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
CONTINENTAL CROSSWALK MARKINGS
AutoCAD SHX Text
12" WHITE THERMOPLASTIC LIMIT LINE
AutoCAD SHX Text
NOTES: 1. CONTINENTAL CROSSWALK MARKINGS SHALL BE ALIGNED PARALLEL TO THE DIRECTION OF VEHICULAR TRAVEL.CONTINENTAL CROSSWALK MARKINGS SHALL BE ALIGNED PARALLEL TO THE DIRECTION OF VEHICULAR TRAVEL.
AutoCAD SHX Text
TRAVEL
AutoCAD SHX Text
DIRECTION OF
AutoCAD SHX Text
%%UDETAIL C
AutoCAD SHX Text
MODIFIED TYPE Q BICYCLE DETECTOR
AutoCAD SHX Text
STRIPING DETAIL 39A (TYP.)
AutoCAD SHX Text
STREET CURB
AutoCAD SHX Text
GUTTER
AutoCAD SHX Text
GREEN PAINT
AutoCAD SHX Text
%%UDETAIL A
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
CONFLICT ZONE STRIPING
AutoCAD SHX Text
BUFFER
AutoCAD SHX Text
GREEN PAINT
AutoCAD SHX Text
ANGLED HATCHING
AutoCAD SHX Text
NOTES: 1. GREEN PAINT SHALL BE ENNIS-FLINT 985206 GREEN STANDARD FAST DRY WATERBORNE TRAFFIC PAINT WITH REFLEX REFLECTIVE GLASS BEADS. GREEN PAINT SHALL BE ENNIS-FLINT 985206 GREEN STANDARD FAST DRY WATERBORNE TRAFFIC PAINT WITH REFLEX REFLECTIVE GLASS BEADS. 2. BUFFER PAVEMENT MARKINGS SHALL BE 6 INCHES WIDE. BUFFER PAVEMENT MARKINGS SHALL BE 6 INCHES WIDE. 3. ANGLE HATCHING FOR BUFFERED BIKE LANES SHALL BE 6 INCHES WIDE, AT A 30 DEGREE ANGLE, AND SPACED AT 40 FEET.ANGLE HATCHING FOR BUFFERED BIKE LANES SHALL BE 6 INCHES WIDE, AT A 30 DEGREE ANGLE, AND SPACED AT 40 FEET.
AutoCAD SHX Text
TS-003
AutoCAD SHX Text
1. FOR WINDING AND SAW CUT INFORMATION SEE CALTRANS
AutoCAD SHX Text
NOTE:
AutoCAD SHX Text
STANDARD PLAN ES-5B.
AutoCAD SHX Text
2. LOOP PLACEMENT SHALL BE 44' BEFORE LIMIT LINE.
AutoCAD SHX Text
PROPOSED 4" DIAGONAL STRIPE
AutoCAD SHX Text
PROPOSED 6" WHITE LINE
AutoCAD SHX Text
PROPOSED BOLLARD (TYP.)
AutoCAD SHX Text
%%UDETAIL "D"
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
PROTECTED BIKE LANE BUFFER
AutoCAD SHX Text
PROPOSED 6" WHITE LINE
AutoCAD SHX Text
NOTES: 1. BOLLARD SHALL BE INSTALLED IN CENTER OF BUFFER UNLESS OTHERWISE SHOWN ON PLANS.BOLLARD SHALL BE INSTALLED IN CENTER OF BUFFER UNLESS OTHERWISE SHOWN ON PLANS.

T

R

A

F

F

I

C

MA

TC

HLIN

E - 37+

00

SE

E S

HE

ET

5

SE

E A

BO

VE

R

IG

HT

MA

TC

HLIN

E - 24+

00

M

A

T

C

H

L

IN

E

-

2

4

+

0

0

S

E

E

B

E

L

O

W

L

E

F

T

35

AutoCAD SHX Text
11
AutoCAD SHX Text
12
AutoCAD SHX Text
13
AutoCAD SHX Text
14
AutoCAD SHX Text
15
AutoCAD SHX Text
16
AutoCAD SHX Text
17
AutoCAD SHX Text
18
AutoCAD SHX Text
19
AutoCAD SHX Text
20
AutoCAD SHX Text
21
AutoCAD SHX Text
22
AutoCAD SHX Text
23
AutoCAD SHX Text
24
AutoCAD SHX Text
102'
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
R2-1(35)
AutoCAD SHX Text
E
AutoCAD SHX Text
R14-1 BUS STOP
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
SR56(CA)
AutoCAD SHX Text
E
AutoCAD SHX Text
R4-4
AutoCAD SHX Text
E
AutoCAD SHX Text
M1-1(5) D9-2 M6-3
AutoCAD SHX Text
E
AutoCAD SHX Text
BUS STOP
AutoCAD SHX Text
E
AutoCAD SHX Text
R2-1(35) R7-9A
AutoCAD SHX Text
6
AutoCAD SHX Text
56'
AutoCAD SHX Text
9
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
6
AutoCAD SHX Text
45'
AutoCAD SHX Text
6
AutoCAD SHX Text
52'
AutoCAD SHX Text
9
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
5
AutoCAD SHX Text
200'
AutoCAD SHX Text
6
AutoCAD SHX Text
28'
AutoCAD SHX Text
11
AutoCAD SHX Text
6
AutoCAD SHX Text
52'
AutoCAD SHX Text
E
AutoCAD SHX Text
SNS
AutoCAD SHX Text
R
AutoCAD SHX Text
1
AutoCAD SHX Text
100'
AutoCAD SHX Text
8
AutoCAD SHX Text
9
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
9
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
4
AutoCAD SHX Text
98'
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
8
AutoCAD SHX Text
4
AutoCAD SHX Text
747'
AutoCAD SHX Text
7
AutoCAD SHX Text
8
AutoCAD SHX Text
8
AutoCAD SHX Text
4
AutoCAD SHX Text
672'
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP).
AutoCAD SHX Text
5
AutoCAD SHX Text
200'
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
1
AutoCAD SHX Text
920'
AutoCAD SHX Text
8
AutoCAD SHX Text
E
AutoCAD SHX Text
4
AutoCAD SHX Text
140'
AutoCAD SHX Text
1
AutoCAD SHX Text
950'
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
21
AutoCAD SHX Text
E
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
E
AutoCAD SHX Text
21
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
5
AutoCAD SHX Text
200'
AutoCAD SHX Text
1
AutoCAD SHX Text
108'
AutoCAD SHX Text
10
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
6
AutoCAD SHX Text
78'
AutoCAD SHX Text
R
AutoCAD SHX Text
13
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
8
AutoCAD SHX Text
8
AutoCAD SHX Text
14
AutoCAD SHX Text
R
AutoCAD SHX Text
13
AutoCAD SHX Text
R
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
14
AutoCAD SHX Text
R
AutoCAD SHX Text
13
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
10
AutoCAD SHX Text
10
AutoCAD SHX Text
10
AutoCAD SHX Text
50'
AutoCAD SHX Text
50'
AutoCAD SHX Text
50'
AutoCAD SHX Text
R3-7R
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
10
AutoCAD SHX Text
70'
AutoCAD SHX Text
140'
AutoCAD SHX Text
10
AutoCAD SHX Text
60'
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
13
AutoCAD SHX Text
14
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
2
AutoCAD SHX Text
210'
AutoCAD SHX Text
2
AutoCAD SHX Text
140'
AutoCAD SHX Text
R
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
5
AutoCAD SHX Text
32'
AutoCAD SHX Text
5
AutoCAD SHX Text
68'
AutoCAD SHX Text
2
AutoCAD SHX Text
140'
AutoCAD SHX Text
2
AutoCAD SHX Text
160'
AutoCAD SHX Text
2
AutoCAD SHX Text
160'
AutoCAD SHX Text
15
AutoCAD SHX Text
(TYP).
AutoCAD SHX Text
15
AutoCAD SHX Text
(TYP).
AutoCAD SHX Text
24
AutoCAD SHX Text
25
AutoCAD SHX Text
26
AutoCAD SHX Text
27
AutoCAD SHX Text
28
AutoCAD SHX Text
29
AutoCAD SHX Text
30
AutoCAD SHX Text
31
AutoCAD SHX Text
32
AutoCAD SHX Text
33
AutoCAD SHX Text
34
AutoCAD SHX Text
35
AutoCAD SHX Text
36
AutoCAD SHX Text
37
AutoCAD SHX Text
5
AutoCAD SHX Text
102'
AutoCAD SHX Text
8
AutoCAD SHX Text
8
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
4
AutoCAD SHX Text
822'
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
E
AutoCAD SHX Text
R2-1(35) R7-9A
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
936'
AutoCAD SHX Text
E
AutoCAD SHX Text
BUS STOP
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
8
AutoCAD SHX Text
E
AutoCAD SHX Text
5
AutoCAD SHX Text
200'
AutoCAD SHX Text
R
AutoCAD SHX Text
6
AutoCAD SHX Text
22'
AutoCAD SHX Text
9
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
R
AutoCAD SHX Text
8
AutoCAD SHX Text
E
AutoCAD SHX Text
BUS STOP
AutoCAD SHX Text
4
AutoCAD SHX Text
108'
AutoCAD SHX Text
E
AutoCAD SHX Text
R14-1 M6-3
AutoCAD SHX Text
5
AutoCAD SHX Text
128'
AutoCAD SHX Text
5
AutoCAD SHX Text
200'
AutoCAD SHX Text
6
AutoCAD SHX Text
62'
AutoCAD SHX Text
1
AutoCAD SHX Text
938'
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
1
AutoCAD SHX Text
238'
AutoCAD SHX Text
1
AutoCAD SHX Text
242'
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
E
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
20
AutoCAD SHX Text
21
AutoCAD SHX Text
R2-1(35)
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
20
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
4
AutoCAD SHX Text
736'
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
11
AutoCAD SHX Text
14
AutoCAD SHX Text
6
AutoCAD SHX Text
36'
AutoCAD SHX Text
R
AutoCAD SHX Text
9
AutoCAD SHX Text
12
AutoCAD SHX Text
11
AutoCAD SHX Text
7
AutoCAD SHX Text
4
AutoCAD SHX Text
38'
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
R
AutoCAD SHX Text
14
AutoCAD SHX Text
13
AutoCAD SHX Text
R
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
10
AutoCAD SHX Text
50'
AutoCAD SHX Text
10
AutoCAD SHX Text
80'
AutoCAD SHX Text
8
AutoCAD SHX Text
10
AutoCAD SHX Text
130'
AutoCAD SHX Text
10
AutoCAD SHX Text
108'
AutoCAD SHX Text
10
AutoCAD SHX Text
38'
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
3'
AutoCAD SHX Text
3'
AutoCAD SHX Text
3.5'
AutoCAD SHX Text
R
AutoCAD SHX Text
3'
AutoCAD SHX Text
2
AutoCAD SHX Text
170'
AutoCAD SHX Text
13
AutoCAD SHX Text
2
AutoCAD SHX Text
140'
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
5
AutoCAD SHX Text
92'
AutoCAD SHX Text
2
AutoCAD SHX Text
180'
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
2
AutoCAD SHX Text
125'
AutoCAD SHX Text
15
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
15
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
VERTICAL
AutoCAD SHX Text
HORIZONTAL
AutoCAD SHX Text
EXP.
AutoCAD SHX Text
R.C.E. NO.
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
PLANS PREPARED UNDER SUPERVISION OF
AutoCAD SHX Text
PUBLIC IMPROVEMENT PLANS FOR:
AutoCAD SHX Text
CITY OF ENCINITAS
AutoCAD SHX Text
SHEET OF 10
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
ENGINEERING DEPARTMENT
AutoCAD SHX Text
APPROVALS
AutoCAD SHX Text
DATE
AutoCAD SHX Text
REFERENCES
AutoCAD SHX Text
DATE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
BENCHMARK
AutoCAD SHX Text
N/A
AutoCAD SHX Text
EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
DESIGNED BY
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
CHECKED BY
AutoCAD SHX Text
TWO WORKING DAYS BEFORE YOU DIG
AutoCAD SHX Text
811
AutoCAD SHX Text
CALL TOLL FREE
AutoCAD SHX Text
CALL BEFORE YOU DIG
AutoCAD SHX Text
Underground Service Alert
AutoCAD SHX Text
Dig Alert
AutoCAD SHX Text
BY:
AutoCAD SHX Text
BY:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
RECOMMENDED
AutoCAD SHX Text
74667
AutoCAD SHX Text
12-31-2021
AutoCAD SHX Text
AA
AutoCAD SHX Text
NM
AutoCAD SHX Text
JS
AutoCAD SHX Text
5865 AVENIDA ENCINAS, #142B
AutoCAD SHX Text
CARLSBAD, CA 92008
AutoCAD SHX Text
PH: 760-602-4290
AutoCAD SHX Text
WWW.STCTRAFFIC.COM
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
C
AutoCAD SHX Text
A
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
A
AutoCAD SHX Text
I
AutoCAD SHX Text
NO. 74667
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
V
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
N
AutoCAD SHX Text
O
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
P
AutoCAD SHX Text
D
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
T
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
O
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
S
AutoCAD SHX Text
M
AutoCAD SHX Text
.
AutoCAD SHX Text
M
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
Exp. 12-31-2021
AutoCAD SHX Text
100% PLANS - EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
NICOLAS M. MINICILLI
AutoCAD SHX Text
1"=40'
AutoCAD SHX Text
10-03-2019
AutoCAD SHX Text
SCALE 1"=40'
AutoCAD SHX Text
SCALE 1"=40'
AutoCAD SHX Text
40
AutoCAD SHX Text
20
AutoCAD SHX Text
40
AutoCAD SHX Text
80
AutoCAD SHX Text
120
AutoCAD SHX Text
SCALE: 1"=40'
AutoCAD SHX Text
0
AutoCAD SHX Text
ENCINITAS BLVD
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
VIA MOLENA
AutoCAD SHX Text
MOUNTAIN VISTA DR
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
45 MPH
AutoCAD SHX Text
35 MPH
AutoCAD SHX Text
35 MPH
AutoCAD SHX Text
45 MPH
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
R/W
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
35 MPH
AutoCAD SHX Text
R/W
AutoCAD SHX Text
4
AutoCAD SHX Text
SIGNING AND STRIPING PLAN
AutoCAD SHX Text
%%UPROPOSED
AutoCAD SHX Text
"BIKE" SIGN
AutoCAD SHX Text
(30 X 48)
AutoCAD SHX Text
YIELD TO BIKES
AutoCAD SHX Text
%%USIGN LEGEND
AutoCAD SHX Text
%%UEXISTING
AutoCAD SHX Text
P
AutoCAD SHX Text
BIKE LANE
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
(12 X 18)
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
(24 X 30)
AutoCAD SHX Text
R2-1
AutoCAD SHX Text
(30 X 36)
AutoCAD SHX Text
SPEED
AutoCAD SHX Text
LIMIT
AutoCAD SHX Text
TRUCK
AutoCAD SHX Text
ROUTE
AutoCAD SHX Text
R14-1
AutoCAD SHX Text
M6-3
AutoCAD SHX Text
MUST
AutoCAD SHX Text
TURN RIGHT
AutoCAD SHX Text
RIGHT LANE
AutoCAD SHX Text
R3-7R
AutoCAD SHX Text
(30 X 30)
AutoCAD SHX Text
(24 x 18)
AutoCAD SHX Text
(21 X 15)
AutoCAD SHX Text
R4-4
AutoCAD SHX Text
YIELD TO BIKES
AutoCAD SHX Text
BEGIN
AutoCAD SHX Text
RIGHT TURN LANE
AutoCAD SHX Text
(36 X 30)
AutoCAD SHX Text
PHOTO
AutoCAD SHX Text
ENFORCED
AutoCAD SHX Text
SR56(CA)
AutoCAD SHX Text
(36 X 54)
AutoCAD SHX Text
5
AutoCAD SHX Text
INTERSTATE
AutoCAD SHX Text
M1-1
AutoCAD SHX Text
(36 X 36)
AutoCAD SHX Text
D9-2
AutoCAD SHX Text
(30 x 30)
AutoCAD SHX Text
REMOVAL NOTES
AutoCAD SHX Text
EXISTING TO REMAIN.
AutoCAD SHX Text
REMOVE EXISTING STRIPING BY GRINDING.
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
CONSTRUCTION NOTES
AutoCAD SHX Text
APPLY 6" DASHED WHITE LINE PER CALTRANS 2015 STD PLAN A20A, DETAIL 9.
AutoCAD SHX Text
APPLY 8" SOLID WHITE CHANNELIZING LINE PER CALTRANS 2015 STD PLAN A20D, DETAIL 38.
AutoCAD SHX Text
APPLY 6" SOLID WHITE LINE PER CALTRANS 2015 STD PLAN A20B, DETAIL 27B.
AutoCAD SHX Text
APPLY CONFLICT ZONE STRIPING WITH 6" DASHED WHITE LINE PER CALTRANS 2015 STD PLAN A20D, DETAIL 39A. APPLY GREEN PAINT PER DETAIL "A" ON SHEET 3.
AutoCAD SHX Text
APPLY 12" SOLID THERMOPLASTIC WHITE LIMIT LINE PER CALTRANS 2015 STD PLAN A24E.
AutoCAD SHX Text
APPLY 6" SOLID WHITE 30 DEGREE DIAGONAL STRIPE AT 40' OC.
AutoCAD SHX Text
INSTALL "BIKE LANE" AND ARROW LEGEND PAVEMENT MARKING PER CALTRANS STD PLANS A24A AND A24D. SYMBOL SHALL BE CENTERED IN BIKE LANE.
AutoCAD SHX Text
INSTALL WHITE THERMOPLASTIC CONTINENTAL CROSSWALK PER DETAIL "B" ON SHEET 3.
AutoCAD SHX Text
PAINT BIKE LANE AREA GREEN WITH ENNIS-FLINT 985206 GREEN STANDARD FAST DRY WATERBORNE TRAFFIC PAINT.
AutoCAD SHX Text
INSTALL THERMOPLASTIC PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE VII (L) ARROW.
AutoCAD SHX Text
INSTALL THERMOPLASTIC PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE VII (R) ARROW
AutoCAD SHX Text
INSTALL THERMOPLASTIC PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE IV (L) ARROW.
AutoCAD SHX Text
INSTALL THERMOPLASTIC PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE IV (R) ARROW.
AutoCAD SHX Text
FURNISH AND INSTALL 28" HIGH TAPCO CITY POST PER DETAIL "D" ON SHEET 3.
AutoCAD SHX Text
INSTALL NEW SIGN AND POST PER PLAN. BOTTOM OF SIGN SHALL HAVE A MINIMUM OF 7' CLEARANCE ABOVE FINISHED SURFACE.
AutoCAD SHX Text
INSTALL SIGN PER PLAN ON EXISTING STREET LIGHT POLE. BOTTOM OF SIGN SHALL HAVE A MINIMUM OF 7' CLEARANCE ABOVE FINISHED SURFACE.
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
4
AutoCAD SHX Text
5
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
8
AutoCAD SHX Text
9
AutoCAD SHX Text
10
AutoCAD SHX Text
11
AutoCAD SHX Text
12
AutoCAD SHX Text
13
AutoCAD SHX Text
14
AutoCAD SHX Text
15
AutoCAD SHX Text
20
AutoCAD SHX Text
21
AutoCAD SHX Text
TS-004
AutoCAD SHX Text
SHEET 1 0F 4
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY

CLE

AR

KE

EP

CLE

AR

KE

EP

CLE

AR

KE

EP

T

R

A

F

F

I

C

MA

TC

HLIN

E 4

9+

00

SE

E B

ELO

W L

EF

T

SE

E S

HE

ET

4

MA

TC

HL

IN

E - 3

7+

00

M

A

T

C

H

L

IN

E

6

1

+

0

0

S

E

E

S

H

E

E

T

6

SE

E A

BO

VE

R

IG

HT

MA

TC

HLIN

E 49+

00

35

AutoCAD SHX Text
37
AutoCAD SHX Text
38
AutoCAD SHX Text
39
AutoCAD SHX Text
40
AutoCAD SHX Text
41
AutoCAD SHX Text
42
AutoCAD SHX Text
43
AutoCAD SHX Text
44
AutoCAD SHX Text
45
AutoCAD SHX Text
46
AutoCAD SHX Text
47
AutoCAD SHX Text
48
AutoCAD SHX Text
49
AutoCAD SHX Text
910'
AutoCAD SHX Text
1
AutoCAD SHX Text
E
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
E
AutoCAD SHX Text
R2-1(35)
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
5
AutoCAD SHX Text
200'
AutoCAD SHX Text
E
AutoCAD SHX Text
R5-1 R5-1a
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
BUS STOP
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
R14-1 M6-3 R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
R2-1(35)
AutoCAD SHX Text
5
AutoCAD SHX Text
200'
AutoCAD SHX Text
8
AutoCAD SHX Text
4
AutoCAD SHX Text
783'
AutoCAD SHX Text
4
AutoCAD SHX Text
8
AutoCAD SHX Text
E
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
8
AutoCAD SHX Text
4
AutoCAD SHX Text
8
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
7
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
21
AutoCAD SHX Text
9
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
72'
AutoCAD SHX Text
5
AutoCAD SHX Text
R
AutoCAD SHX Text
8
AutoCAD SHX Text
4
AutoCAD SHX Text
72'
AutoCAD SHX Text
13
AutoCAD SHX Text
9
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
27'
AutoCAD SHX Text
6
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
728'
AutoCAD SHX Text
4
AutoCAD SHX Text
R
AutoCAD SHX Text
20'
AutoCAD SHX Text
R
AutoCAD SHX Text
7
AutoCAD SHX Text
1
AutoCAD SHX Text
88'
AutoCAD SHX Text
R
AutoCAD SHX Text
72'
AutoCAD SHX Text
1
AutoCAD SHX Text
E
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
910'
AutoCAD SHX Text
1
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
21
AutoCAD SHX Text
R
AutoCAD SHX Text
21
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
8
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
7
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
8
AutoCAD SHX Text
6
AutoCAD SHX Text
36'
AutoCAD SHX Text
1
AutoCAD SHX Text
22'
AutoCAD SHX Text
4
AutoCAD SHX Text
5
AutoCAD SHX Text
33'
AutoCAD SHX Text
E
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
(45')
AutoCAD SHX Text
(45')
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
6
AutoCAD SHX Text
56'
AutoCAD SHX Text
12
AutoCAD SHX Text
1
AutoCAD SHX Text
33'
AutoCAD SHX Text
8
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
BUS STOP
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
(41')
AutoCAD SHX Text
125'
AutoCAD SHX Text
2
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
10
AutoCAD SHX Text
10
AutoCAD SHX Text
10
AutoCAD SHX Text
50'
AutoCAD SHX Text
30'
AutoCAD SHX Text
50'
AutoCAD SHX Text
10
AutoCAD SHX Text
72'
AutoCAD SHX Text
10
AutoCAD SHX Text
100'
AutoCAD SHX Text
10
AutoCAD SHX Text
10'
AutoCAD SHX Text
R
AutoCAD SHX Text
80'
AutoCAD SHX Text
10
AutoCAD SHX Text
R
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
R
AutoCAD SHX Text
6
AutoCAD SHX Text
64'
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
52'
AutoCAD SHX Text
6
AutoCAD SHX Text
2
AutoCAD SHX Text
75'
AutoCAD SHX Text
2
AutoCAD SHX Text
148'
AutoCAD SHX Text
16
AutoCAD SHX Text
KEEP
AutoCAD SHX Text
6
AutoCAD SHX Text
32'
AutoCAD SHX Text
6
AutoCAD SHX Text
32'
AutoCAD SHX Text
16
AutoCAD SHX Text
CLEAR
AutoCAD SHX Text
6
AutoCAD SHX Text
56'
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
4
AutoCAD SHX Text
13
AutoCAD SHX Text
2
AutoCAD SHX Text
105'
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
15
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
15
AutoCAD SHX Text
49
AutoCAD SHX Text
50
AutoCAD SHX Text
51
AutoCAD SHX Text
52
AutoCAD SHX Text
53
AutoCAD SHX Text
54
AutoCAD SHX Text
55
AutoCAD SHX Text
56
AutoCAD SHX Text
57
AutoCAD SHX Text
58
AutoCAD SHX Text
59
AutoCAD SHX Text
60
AutoCAD SHX Text
61
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
R2-1(35)
AutoCAD SHX Text
E
AutoCAD SHX Text
BUS STOP
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A R81(CA)
AutoCAD SHX Text
E
AutoCAD SHX Text
R3-7R
AutoCAD SHX Text
E
AutoCAD SHX Text
R3-7R
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
R2-1(35)
AutoCAD SHX Text
E
AutoCAD SHX Text
R81(CA)
AutoCAD SHX Text
E
AutoCAD SHX Text
R14-1 R7-9A BUS STOP
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
8
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
8
AutoCAD SHX Text
4
AutoCAD SHX Text
733'
AutoCAD SHX Text
8
AutoCAD SHX Text
4
AutoCAD SHX Text
780'
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
6
AutoCAD SHX Text
64'
AutoCAD SHX Text
6
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
151'
AutoCAD SHX Text
4
AutoCAD SHX Text
130'
AutoCAD SHX Text
R
AutoCAD SHX Text
27'
AutoCAD SHX Text
9
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
9
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
5
AutoCAD SHX Text
167'
AutoCAD SHX Text
1
AutoCAD SHX Text
955'
AutoCAD SHX Text
20
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
8
AutoCAD SHX Text
1
AutoCAD SHX Text
940'
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
R3-18
AutoCAD SHX Text
5
AutoCAD SHX Text
100'
AutoCAD SHX Text
21
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
E
AutoCAD SHX Text
R3-4
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
E
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
R
AutoCAD SHX Text
4
AutoCAD SHX Text
100'
AutoCAD SHX Text
5
AutoCAD SHX Text
42'
AutoCAD SHX Text
8
AutoCAD SHX Text
10
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
1
AutoCAD SHX Text
144'
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
8
AutoCAD SHX Text
4
AutoCAD SHX Text
100'
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
R3-4
AutoCAD SHX Text
40'
AutoCAD SHX Text
6
AutoCAD SHX Text
67'
AutoCAD SHX Text
6
AutoCAD SHX Text
46'
AutoCAD SHX Text
8
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
13
AutoCAD SHX Text
R
AutoCAD SHX Text
14
AutoCAD SHX Text
14
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
2
AutoCAD SHX Text
235'
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
100' TRANSITION
AutoCAD SHX Text
R
AutoCAD SHX Text
10
AutoCAD SHX Text
10
AutoCAD SHX Text
50'
AutoCAD SHX Text
50'
AutoCAD SHX Text
100'
AutoCAD SHX Text
10
AutoCAD SHX Text
80'
AutoCAD SHX Text
10
AutoCAD SHX Text
10
AutoCAD SHX Text
100'
AutoCAD SHX Text
R
AutoCAD SHX Text
100'
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
2
AutoCAD SHX Text
132'
AutoCAD SHX Text
13
AutoCAD SHX Text
2
AutoCAD SHX Text
120'
AutoCAD SHX Text
13
AutoCAD SHX Text
7
AutoCAD SHX Text
13
AutoCAD SHX Text
5
AutoCAD SHX Text
68'
AutoCAD SHX Text
5
AutoCAD SHX Text
80'
AutoCAD SHX Text
2
AutoCAD SHX Text
45'
AutoCAD SHX Text
R
AutoCAD SHX Text
14
AutoCAD SHX Text
14
AutoCAD SHX Text
13
AutoCAD SHX Text
2
AutoCAD SHX Text
280'
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
15
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
15
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
VERTICAL
AutoCAD SHX Text
HORIZONTAL
AutoCAD SHX Text
EXP.
AutoCAD SHX Text
R.C.E. NO.
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
PLANS PREPARED UNDER SUPERVISION OF
AutoCAD SHX Text
PUBLIC IMPROVEMENT PLANS FOR:
AutoCAD SHX Text
CITY OF ENCINITAS
AutoCAD SHX Text
SHEET OF 10
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
ENGINEERING DEPARTMENT
AutoCAD SHX Text
APPROVALS
AutoCAD SHX Text
DATE
AutoCAD SHX Text
REFERENCES
AutoCAD SHX Text
DATE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
BENCHMARK
AutoCAD SHX Text
N/A
AutoCAD SHX Text
EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
DESIGNED BY
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
CHECKED BY
AutoCAD SHX Text
TWO WORKING DAYS BEFORE YOU DIG
AutoCAD SHX Text
811
AutoCAD SHX Text
CALL TOLL FREE
AutoCAD SHX Text
CALL BEFORE YOU DIG
AutoCAD SHX Text
Underground Service Alert
AutoCAD SHX Text
Dig Alert
AutoCAD SHX Text
BY:
AutoCAD SHX Text
BY:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
RECOMMENDED
AutoCAD SHX Text
74667
AutoCAD SHX Text
12-31-2021
AutoCAD SHX Text
AA
AutoCAD SHX Text
NM
AutoCAD SHX Text
JS
AutoCAD SHX Text
5865 AVENIDA ENCINAS, #142B
AutoCAD SHX Text
CARLSBAD, CA 92008
AutoCAD SHX Text
PH: 760-602-4290
AutoCAD SHX Text
WWW.STCTRAFFIC.COM
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
C
AutoCAD SHX Text
A
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
A
AutoCAD SHX Text
I
AutoCAD SHX Text
NO. 74667
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
V
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
N
AutoCAD SHX Text
O
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
P
AutoCAD SHX Text
D
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
T
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
O
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
S
AutoCAD SHX Text
M
AutoCAD SHX Text
.
AutoCAD SHX Text
M
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
Exp. 12-31-2021
AutoCAD SHX Text
100% PLANS - EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
NICOLAS M. MINICILLI
AutoCAD SHX Text
1"=40'
AutoCAD SHX Text
10-03-2019
AutoCAD SHX Text
GARDEN VIEW RD
AutoCAD SHX Text
SCALE 1"=40'
AutoCAD SHX Text
SCALE 1"=40'
AutoCAD SHX Text
VIA MONTORO
AutoCAD SHX Text
CIRCUIT CITY DWY
AutoCAD SHX Text
35 MPH
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
35 MPH
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
35 MPH
AutoCAD SHX Text
40 MPH
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
25 MPH
AutoCAD SHX Text
R/W
AutoCAD SHX Text
%%UPROPOSED
AutoCAD SHX Text
"BIKE" SIGN
AutoCAD SHX Text
(30 X 48)
AutoCAD SHX Text
YIELD TO BIKES
AutoCAD SHX Text
%%USIGN LEGEND
AutoCAD SHX Text
%%UEXISTING
AutoCAD SHX Text
40
AutoCAD SHX Text
20
AutoCAD SHX Text
40
AutoCAD SHX Text
80
AutoCAD SHX Text
120
AutoCAD SHX Text
SCALE: 1"=40'
AutoCAD SHX Text
0
AutoCAD SHX Text
P
AutoCAD SHX Text
BIKE LANE
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
(12 X 18)
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
(24 X 30)
AutoCAD SHX Text
R2-1
AutoCAD SHX Text
(30 X 36)
AutoCAD SHX Text
SPEED
AutoCAD SHX Text
LIMIT
AutoCAD SHX Text
TRUCK
AutoCAD SHX Text
ROUTE
AutoCAD SHX Text
R14-1
AutoCAD SHX Text
M6-3
AutoCAD SHX Text
R5-1
AutoCAD SHX Text
R5-1a
AutoCAD SHX Text
(36 X 24)
AutoCAD SHX Text
WRONG
AutoCAD SHX Text
WAY
AutoCAD SHX Text
R3-4
AutoCAD SHX Text
R3-18
AutoCAD SHX Text
(30 X 30)
AutoCAD SHX Text
BIKE LANE
AutoCAD SHX Text
R81 (CA)
AutoCAD SHX Text
(30 X 20)
AutoCAD SHX Text
MUST
AutoCAD SHX Text
TURN RIGHT
AutoCAD SHX Text
RIGHT LANE
AutoCAD SHX Text
R3-7R
AutoCAD SHX Text
(24 X 24)
AutoCAD SHX Text
(30 X 30)
AutoCAD SHX Text
(36 X 36)
AutoCAD SHX Text
(24 x 18)
AutoCAD SHX Text
(21 X 15)
AutoCAD SHX Text
REMOVAL NOTES
AutoCAD SHX Text
EXISTING TO REMAIN.
AutoCAD SHX Text
REMOVE EXISTING STRIPING BY GRINDING.
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
5
AutoCAD SHX Text
SIGNING AND STRIPING PLAN
AutoCAD SHX Text
CONSTRUCTION NOTES
AutoCAD SHX Text
APPLY 6" DASHED WHITE LINE PER CALTRANS 2015 STD PLAN A20A, DETAIL 9.
AutoCAD SHX Text
APPLY 8" SOLID WHITE CHANNELIZING LINE PER CALTRANS 2015 STD PLAN A20D, DETAIL 38.
AutoCAD SHX Text
APPLY 6" SOLID WHITE LINE PER CALTRANS 2015 STD PLAN A20B, DETAIL 27B.
AutoCAD SHX Text
APPLY CONFLICT ZONE STRIPING WITH 6" DASHED WHITE LINE PER CALTRANS 2015 STD PLAN A20D, DETAIL 39A. APPLY GREEN PAINT PER DETAIL "A" ON SHEET 3.
AutoCAD SHX Text
APPLY 12" SOLID THERMOPLASTIC WHITE LIMIT LINE PER CALTRANS 2015 STD PLAN A24E.
AutoCAD SHX Text
APPLY 6" SOLID WHITE 30 DEGREE DIAGONAL STRIPE AT 40' OC.
AutoCAD SHX Text
INSTALL "BIKE LANE" AND ARROW LEGEND PAVEMENT MARKING PER CALTRANS STD PLANS A24A AND A24D. SYMBOL SHALL BE CENTERED IN BIKE LANE.
AutoCAD SHX Text
INSTALL WHITE THERMOPLASTIC CONTINENTAL CROSSWALK PER DETAIL "B" ON SHEET 3.
AutoCAD SHX Text
PAINT BIKE LANE AREA GREEN WITH ENNIS-FLINT 985206 GREEN STANDARD FAST DRY WATERBORNE TRAFFIC PAINT.
AutoCAD SHX Text
INSTALL THERMOPLASTIC PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE VII (R) ARROW
AutoCAD SHX Text
INSTALL THERMOPLASTIC PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE IV (L) ARROW.
AutoCAD SHX Text
INSTALL THERMOPLASTIC PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE IV (R) ARROW.
AutoCAD SHX Text
FURNISH AND INSTALL 28" HIGH TAPCO CITY POST PER DETAIL "D" ON SHEET 3.
AutoCAD SHX Text
INSTALL THERMOPLASTIC PAVEMENT MARKING PER PLAN PER CALTRANS STANDARD 2015 STD A24E.
AutoCAD SHX Text
INSTALL NEW SIGN AND POST PER PLAN. BOTTOM OF SIGN SHALL HAVE A MINIMUM OF 7' CLEARANCE ABOVE FINISHED SURFACE.
AutoCAD SHX Text
INSTALL SIGN PER PLAN ON EXISTING STREET LIGHT POLE. BOTTOM OF SIGN SHALL HAVE A MINIMUM OF 7' CLEARANCE ABOVE FINISHED SURFACE.
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
4
AutoCAD SHX Text
5
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
8
AutoCAD SHX Text
9
AutoCAD SHX Text
10
AutoCAD SHX Text
12
AutoCAD SHX Text
13
AutoCAD SHX Text
14
AutoCAD SHX Text
15
AutoCAD SHX Text
16
AutoCAD SHX Text
20
AutoCAD SHX Text
21
AutoCAD SHX Text
TS-005
AutoCAD SHX Text
SHEET 2 0F 4
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
LA GRAN AVE
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY

SE

E S

HE

ET

5

MA

TC

HLIN

E - 61

+0

0

MA

TC

HLIN

E 73+

00

SE

E B

ELO

W LE

FT

SE

E A

BO

VE

R

IG

HT

MA

TC

HLIN

E - 73+

00

M

AT

CH

LIN

E 85+

00

SE

E S

HE

ET

7

45

T

R

A

F

F

I

C

AutoCAD SHX Text
61
AutoCAD SHX Text
62
AutoCAD SHX Text
63
AutoCAD SHX Text
64
AutoCAD SHX Text
65
AutoCAD SHX Text
66
AutoCAD SHX Text
67
AutoCAD SHX Text
68
AutoCAD SHX Text
69
AutoCAD SHX Text
70
AutoCAD SHX Text
71
AutoCAD SHX Text
72
AutoCAD SHX Text
73
AutoCAD SHX Text
1145'
AutoCAD SHX Text
4
AutoCAD SHX Text
1200'
AutoCAD SHX Text
4
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
7
AutoCAD SHX Text
58'
AutoCAD SHX Text
5
AutoCAD SHX Text
375'
AutoCAD SHX Text
1200'
AutoCAD SHX Text
1
AutoCAD SHX Text
1200'
AutoCAD SHX Text
1
AutoCAD SHX Text
R
AutoCAD SHX Text
R2-1(45) BUS STOP
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A R26(CA)
AutoCAD SHX Text
E
AutoCAD SHX Text
R26(CA)
AutoCAD SHX Text
E
AutoCAD SHX Text
R14-1 R7-9A
AutoCAD SHX Text
R7-9A R81B(CA)
AutoCAD SHX Text
W73A(CA)
AutoCAD SHX Text
W4-2(R) R7-9A
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
8
AutoCAD SHX Text
8
AutoCAD SHX Text
8
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
20
AutoCAD SHX Text
8
AutoCAD SHX Text
8
AutoCAD SHX Text
8
AutoCAD SHX Text
8
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
10
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
770'
AutoCAD SHX Text
1
AutoCAD SHX Text
3
AutoCAD SHX Text
10
AutoCAD SHX Text
140'
AutoCAD SHX Text
R
AutoCAD SHX Text
280'
AutoCAD SHX Text
2
AutoCAD SHX Text
13
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
15
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
15
AutoCAD SHX Text
73
AutoCAD SHX Text
74
AutoCAD SHX Text
75
AutoCAD SHX Text
76
AutoCAD SHX Text
77
AutoCAD SHX Text
78
AutoCAD SHX Text
79
AutoCAD SHX Text
80
AutoCAD SHX Text
81
AutoCAD SHX Text
82
AutoCAD SHX Text
83
AutoCAD SHX Text
84
AutoCAD SHX Text
85
AutoCAD SHX Text
85
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
940'
AutoCAD SHX Text
4
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
765'
AutoCAD SHX Text
4
AutoCAD SHX Text
965'
AutoCAD SHX Text
1
AutoCAD SHX Text
200'
AutoCAD SHX Text
5
AutoCAD SHX Text
R
AutoCAD SHX Text
6
AutoCAD SHX Text
40'
AutoCAD SHX Text
R
AutoCAD SHX Text
BUS STOP
AutoCAD SHX Text
E
AutoCAD SHX Text
W74(CA) R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
R2-1(45) R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
BUS STOP
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
8
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
E
AutoCAD SHX Text
9
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
R
AutoCAD SHX Text
W73A(CA)
AutoCAD SHX Text
E
AutoCAD SHX Text
R2-1(45) R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
950'
AutoCAD SHX Text
1
AutoCAD SHX Text
115'
AutoCAD SHX Text
5
AutoCAD SHX Text
E
AutoCAD SHX Text
8
AutoCAD SHX Text
112'
AutoCAD SHX Text
1
AutoCAD SHX Text
4
AutoCAD SHX Text
112'
AutoCAD SHX Text
10
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
115'
AutoCAD SHX Text
1
AutoCAD SHX Text
R
AutoCAD SHX Text
W3-3
AutoCAD SHX Text
E
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
13
AutoCAD SHX Text
11
AutoCAD SHX Text
14
AutoCAD SHX Text
8
AutoCAD SHX Text
8
AutoCAD SHX Text
8
AutoCAD SHX Text
8
AutoCAD SHX Text
8
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
6
AutoCAD SHX Text
40'
AutoCAD SHX Text
R
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
20
AutoCAD SHX Text
6
AutoCAD SHX Text
75'
AutoCAD SHX Text
9
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
50'
AutoCAD SHX Text
10
AutoCAD SHX Text
10
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
E
AutoCAD SHX Text
50'
AutoCAD SHX Text
85'
AutoCAD SHX Text
R
AutoCAD SHX Text
2
AutoCAD SHX Text
10'
AutoCAD SHX Text
R
AutoCAD SHX Text
13
AutoCAD SHX Text
2
AutoCAD SHX Text
180'
AutoCAD SHX Text
13
AutoCAD SHX Text
2
AutoCAD SHX Text
13
AutoCAD SHX Text
200'
AutoCAD SHX Text
15
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
15
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
40
AutoCAD SHX Text
20
AutoCAD SHX Text
40
AutoCAD SHX Text
80
AutoCAD SHX Text
120
AutoCAD SHX Text
SCALE: 1"=40
AutoCAD SHX Text
0
AutoCAD SHX Text
TOWN CENTER DR
AutoCAD SHX Text
SCALE 1"=40'
AutoCAD SHX Text
SCALE 1"=40'
AutoCAD SHX Text
S
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
45 MPH
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
45 MPH
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
25 MPH
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
REMOVAL NOTES
AutoCAD SHX Text
EXISTING TO REMAIN.
AutoCAD SHX Text
REMOVE EXISTING STRIPING BY GRINDING.
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
%%UPROPOSED
AutoCAD SHX Text
"BIKE" SIGN
AutoCAD SHX Text
(30 X 48)
AutoCAD SHX Text
YIELD TO BIKES
AutoCAD SHX Text
%%USIGN LEGEND
AutoCAD SHX Text
%%UEXISTING
AutoCAD SHX Text
P
AutoCAD SHX Text
BIKE LANE
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
(12 X 18)
AutoCAD SHX Text
R81B(CA)
AutoCAD SHX Text
END
AutoCAD SHX Text
(8 X 5)
AutoCAD SHX Text
TRUCK
AutoCAD SHX Text
ROUTE
AutoCAD SHX Text
R14-1
AutoCAD SHX Text
(24 x 18)
AutoCAD SHX Text
R2-1
AutoCAD SHX Text
(30 X 36)
AutoCAD SHX Text
SPEED
AutoCAD SHX Text
LIMIT
AutoCAD SHX Text
R26(CA)
AutoCAD SHX Text
(12 X 18)
AutoCAD SHX Text
PARKING
AutoCAD SHX Text
ANY
AutoCAD SHX Text
TIME
AutoCAD SHX Text
NO
AutoCAD SHX Text
TURN
AutoCAD SHX Text
RIGHT
AutoCAD SHX Text
MUST
AutoCAD SHX Text
LANE
AutoCAD SHX Text
RIGHT
AutoCAD SHX Text
(36 X 36)
AutoCAD SHX Text
W73A
AutoCAD SHX Text
W4-2
AutoCAD SHX Text
(36 X 36)
AutoCAD SHX Text
MERGE
AutoCAD SHX Text
LEFT
AutoCAD SHX Text
TRAFFIC
AutoCAD SHX Text
THRU
AutoCAD SHX Text
(48"x48")
AutoCAD SHX Text
W74
AutoCAD SHX Text
W3-3
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
(24 X 30)
AutoCAD SHX Text
(36 X 36)
AutoCAD SHX Text
VERTICAL
AutoCAD SHX Text
HORIZONTAL
AutoCAD SHX Text
EXP.
AutoCAD SHX Text
R.C.E. NO.
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
PLANS PREPARED UNDER SUPERVISION OF
AutoCAD SHX Text
PUBLIC IMPROVEMENT PLANS FOR:
AutoCAD SHX Text
CITY OF ENCINITAS
AutoCAD SHX Text
SHEET OF 10
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
ENGINEERING DEPARTMENT
AutoCAD SHX Text
APPROVALS
AutoCAD SHX Text
DATE
AutoCAD SHX Text
REFERENCES
AutoCAD SHX Text
DATE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
BENCHMARK
AutoCAD SHX Text
N/A
AutoCAD SHX Text
EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
DESIGNED BY
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
CHECKED BY
AutoCAD SHX Text
TWO WORKING DAYS BEFORE YOU DIG
AutoCAD SHX Text
811
AutoCAD SHX Text
CALL TOLL FREE
AutoCAD SHX Text
CALL BEFORE YOU DIG
AutoCAD SHX Text
Underground Service Alert
AutoCAD SHX Text
Dig Alert
AutoCAD SHX Text
BY:
AutoCAD SHX Text
BY:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
RECOMMENDED
AutoCAD SHX Text
74667
AutoCAD SHX Text
12-31-2021
AutoCAD SHX Text
AA
AutoCAD SHX Text
NM
AutoCAD SHX Text
JS
AutoCAD SHX Text
5865 AVENIDA ENCINAS, #142B
AutoCAD SHX Text
CARLSBAD, CA 92008
AutoCAD SHX Text
PH: 760-602-4290
AutoCAD SHX Text
WWW.STCTRAFFIC.COM
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
C
AutoCAD SHX Text
A
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
A
AutoCAD SHX Text
I
AutoCAD SHX Text
NO. 74667
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
V
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
N
AutoCAD SHX Text
O
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
P
AutoCAD SHX Text
D
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
T
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
O
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
S
AutoCAD SHX Text
M
AutoCAD SHX Text
.
AutoCAD SHX Text
M
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
Exp. 12-31-2021
AutoCAD SHX Text
100% PLANS - EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
NICOLAS M. MINICILLI
AutoCAD SHX Text
1"=40'
AutoCAD SHX Text
10-03-2019
AutoCAD SHX Text
6
AutoCAD SHX Text
SIGNING AND STRIPING PLAN
AutoCAD SHX Text
CONSTRUCTION NOTES
AutoCAD SHX Text
APPLY 6" DASHED WHITE LINE PER CALTRANS 2015 STD PLAN A20A, DETAIL 9.
AutoCAD SHX Text
APPLY 8" SOLID WHITE CHANNELIZING LINE PER CALTRANS 2015 STD PLAN A20D, DETAIL 38.
AutoCAD SHX Text
APPLY 8" DASHED WHITE LANE DROP LINE PER CALTRANS 2015 STD PLAN A20C, DETAIL 37B.
AutoCAD SHX Text
APPLY 6" SOLID WHITE LINE PER CALTRANS 2015 STD PLAN A20B, DETAIL 27B.
AutoCAD SHX Text
APPLY CONFLICT ZONE STRIPING WITH 6" DASHED WHITE LINE PER CALTRANS 2015 STD PLAN A20D, DETAIL 39A. APPLY GREEN PAINT PER DETAIL "A" ON SHEET 3.
AutoCAD SHX Text
APPLY 12" SOLID THERMOPLASTIC WHITE LIMIT LINE PER CALTRANS 2015 STD PLAN A24E.
AutoCAD SHX Text
APPLY 6" SOLID WHITE 30 DEGREE DIAGONAL STRIPE AT 40' OC.
AutoCAD SHX Text
INSTALL "BIKE LANE" AND ARROW LEGEND PAVEMENT MARKING PER CALTRANS STD PLANS A24A AND A24D. SYMBOL SHALL BE CENTERED IN BIKE LANE.
AutoCAD SHX Text
INSTALL WHITE THERMOPLASTIC CONTINENTAL CROSSWALK PER DETAIL "B" ON SHEET 3.
AutoCAD SHX Text
PAINT BIKE LANE AREA GREEN WITH ENNIS-FLINT 985206 GREEN STANDARD FAST DRY WATERBORNE TRAFFIC PAINT.
AutoCAD SHX Text
INSTALL THERMOPLASTIC PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE VII (L) ARROW.
AutoCAD SHX Text
INSTALL THERMOPLASTIC PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE IV (L) ARROW.
AutoCAD SHX Text
INSTALL THERMOPLASTIC PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE IV (R) ARROW.
AutoCAD SHX Text
FURNISH AND INSTALL 28" HIGH TAPCO CITY POST PER DETAIL "D" ON SHEET 3.
AutoCAD SHX Text
INSTALL NEW SIGN AND POST PER PLAN. BOTTOM OF SIGN SHALL HAVE A MINIMUM OF 7' CLEARANCE ABOVE FINISHED SURFACE.
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
5
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
8
AutoCAD SHX Text
9
AutoCAD SHX Text
10
AutoCAD SHX Text
11
AutoCAD SHX Text
13
AutoCAD SHX Text
14
AutoCAD SHX Text
15
AutoCAD SHX Text
20
AutoCAD SHX Text
TS-006
AutoCAD SHX Text
SHEET 3 0F 4
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY
AutoCAD SHX Text
DWY

T

R

A

F

F

I

C

SE

E S

HE

ET

6

MA

TC

HLIN

E - 85

+0

0

45

AutoCAD SHX Text
85
AutoCAD SHX Text
87
AutoCAD SHX Text
88
AutoCAD SHX Text
89
AutoCAD SHX Text
90
AutoCAD SHX Text
91
AutoCAD SHX Text
92
AutoCAD SHX Text
93
AutoCAD SHX Text
85
AutoCAD SHX Text
INFO SIGN
AutoCAD SHX Text
E
AutoCAD SHX Text
"NO LITTERING" INFO SIGN R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
8
AutoCAD SHX Text
BUS STOP
AutoCAD SHX Text
E
AutoCAD SHX Text
R2-1(45) R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
8
AutoCAD SHX Text
R
AutoCAD SHX Text
85'
AutoCAD SHX Text
5
AutoCAD SHX Text
R
AutoCAD SHX Text
100'
AutoCAD SHX Text
5
AutoCAD SHX Text
R3-7R
AutoCAD SHX Text
E
AutoCAD SHX Text
R3-7R
AutoCAD SHX Text
E
AutoCAD SHX Text
R14-1 M6-6
AutoCAD SHX Text
E
AutoCAD SHX Text
10
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
E
AutoCAD SHX Text
8
AutoCAD SHX Text
7
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
4
AutoCAD SHX Text
455'
AutoCAD SHX Text
375'
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
9
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
9
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
E
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
E
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
21
AutoCAD SHX Text
530'
AutoCAD SHX Text
4
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
7
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
645'
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
637'
AutoCAD SHX Text
65'
AutoCAD SHX Text
6
AutoCAD SHX Text
8
AutoCAD SHX Text
85'
AutoCAD SHX Text
4
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
7
AutoCAD SHX Text
BIKE
AutoCAD SHX Text
21
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
1
AutoCAD SHX Text
80'
AutoCAD SHX Text
R
AutoCAD SHX Text
3
AutoCAD SHX Text
10
AutoCAD SHX Text
50'
AutoCAD SHX Text
140'
AutoCAD SHX Text
10
AutoCAD SHX Text
140'
AutoCAD SHX Text
10
AutoCAD SHX Text
85'
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
13
AutoCAD SHX Text
2
AutoCAD SHX Text
200'
AutoCAD SHX Text
13
AutoCAD SHX Text
200'
AutoCAD SHX Text
2
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
13
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
15
AutoCAD SHX Text
15
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
VERTICAL
AutoCAD SHX Text
HORIZONTAL
AutoCAD SHX Text
EXP.
AutoCAD SHX Text
R.C.E. NO.
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
PLANS PREPARED UNDER SUPERVISION OF
AutoCAD SHX Text
PUBLIC IMPROVEMENT PLANS FOR:
AutoCAD SHX Text
CITY OF ENCINITAS
AutoCAD SHX Text
SHEET OF 10
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
ENGINEERING DEPARTMENT
AutoCAD SHX Text
APPROVALS
AutoCAD SHX Text
DATE
AutoCAD SHX Text
REFERENCES
AutoCAD SHX Text
DATE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
BENCHMARK
AutoCAD SHX Text
N/A
AutoCAD SHX Text
EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
DESIGNED BY
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
CHECKED BY
AutoCAD SHX Text
TWO WORKING DAYS BEFORE YOU DIG
AutoCAD SHX Text
811
AutoCAD SHX Text
CALL TOLL FREE
AutoCAD SHX Text
CALL BEFORE YOU DIG
AutoCAD SHX Text
Underground Service Alert
AutoCAD SHX Text
Dig Alert
AutoCAD SHX Text
BY:
AutoCAD SHX Text
BY:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
RECOMMENDED
AutoCAD SHX Text
74667
AutoCAD SHX Text
12-31-2021
AutoCAD SHX Text
AA
AutoCAD SHX Text
NM
AutoCAD SHX Text
JS
AutoCAD SHX Text
5865 AVENIDA ENCINAS, #142B
AutoCAD SHX Text
CARLSBAD, CA 92008
AutoCAD SHX Text
PH: 760-602-4290
AutoCAD SHX Text
WWW.STCTRAFFIC.COM
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
C
AutoCAD SHX Text
A
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
A
AutoCAD SHX Text
I
AutoCAD SHX Text
NO. 74667
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
V
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
N
AutoCAD SHX Text
O
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
P
AutoCAD SHX Text
D
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
T
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
O
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
S
AutoCAD SHX Text
M
AutoCAD SHX Text
.
AutoCAD SHX Text
M
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
Exp. 12-31-2021
AutoCAD SHX Text
100% PLANS - EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
NICOLAS M. MINICILLI
AutoCAD SHX Text
1"=40'
AutoCAD SHX Text
10-03-2019
AutoCAD SHX Text
40
AutoCAD SHX Text
20
AutoCAD SHX Text
40
AutoCAD SHX Text
80
AutoCAD SHX Text
120
AutoCAD SHX Text
SCALE: 1"40'
AutoCAD SHX Text
0
AutoCAD SHX Text
LEUCADIA BLVD
AutoCAD SHX Text
SCALE 1"=40'
AutoCAD SHX Text
45 MPH
AutoCAD SHX Text
S
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
45 MPH
AutoCAD SHX Text
R/W
AutoCAD SHX Text
7
AutoCAD SHX Text
SIGNING AND STRIPING PLAN
AutoCAD SHX Text
REMOVAL NOTES
AutoCAD SHX Text
EXISTING TO REMAIN.
AutoCAD SHX Text
REMOVE EXISTING STRIPING BY GRINDING.
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
%%UPROPOSED
AutoCAD SHX Text
"BIKE" SIGN
AutoCAD SHX Text
(30 X 48)
AutoCAD SHX Text
YIELD TO BIKES
AutoCAD SHX Text
%%USIGN LEGEND
AutoCAD SHX Text
%%UEXISTING
AutoCAD SHX Text
R4-7
AutoCAD SHX Text
(24 X 30)
AutoCAD SHX Text
P
AutoCAD SHX Text
BIKE LANE
AutoCAD SHX Text
R7-9A
AutoCAD SHX Text
(12 X 18)
AutoCAD SHX Text
R2-1
AutoCAD SHX Text
(30 X 36)
AutoCAD SHX Text
SPEED
AutoCAD SHX Text
LIMIT
AutoCAD SHX Text
TRUCK
AutoCAD SHX Text
ROUTE
AutoCAD SHX Text
R14-1
AutoCAD SHX Text
(24 x 18)
AutoCAD SHX Text
M6-6
AutoCAD SHX Text
(21 x 15)
AutoCAD SHX Text
MUST
AutoCAD SHX Text
TURN RIGHT
AutoCAD SHX Text
RIGHT LANE
AutoCAD SHX Text
R3-7R
AutoCAD SHX Text
(30 X 30)
AutoCAD SHX Text
CONSTRUCTION NOTES
AutoCAD SHX Text
APPLY 6" DASHED WHITE LINE PER CALTRANS 2015 STD PLAN A20A, DETAIL 9.
AutoCAD SHX Text
APPLY 8" SOLID WHITE CHANNELIZING LINE PER CALTRANS 2015 STD PLAN A20D, DETAIL 38.
AutoCAD SHX Text
APPLY 8" DASHED WHITE LANE DROP LINE PER CALTRANS 2015 STD PLAN A20C, DETAIL 37B.
AutoCAD SHX Text
APPLY 6" SOLID WHITE LINE PER CALTRANS 2015 STD PLAN A20B, DETAIL 27B.
AutoCAD SHX Text
APPLY CONFLICT ZONE STRIPING WITH 6" DASHED WHITE LINE PER CALTRANS 2015 STD PLAN A20D, DETAIL 39A. APPLY GREEN PAINT PER DETAIL "A" ON SHEET 3.
AutoCAD SHX Text
APPLY 12" SOLID THERMOPLASTIC WHITE LIMIT LINE PER CALTRANS 2015 STD PLAN A24E.
AutoCAD SHX Text
APPLY 6" SOLID WHITE 30 DEGREE DIAGONAL STRIPE AT 40' OC.
AutoCAD SHX Text
INSTALL "BIKE LANE" AND ARROW LEGEND PAVEMENT MARKING PER CALTRANS STD PLANS A24A AND A24D. SYMBOL SHALL BE CENTERED IN BIKE LANE.
AutoCAD SHX Text
INSTALL WHITE THERMOPLASTIC CONTINENTAL CROSSWALK PER DETAIL "B" ON SHEET 3.
AutoCAD SHX Text
PAINT BIKE LANE AREA GREEN WITH ENNIS-FLINT 985206 GREEN STANDARD FAST DRY WATERBORNE TRAFFIC PAINT.
AutoCAD SHX Text
INSTALL THERMOPLASTIC PAVEMENT MARKING PER PLAN PER CALTRANS 2015 STD A24A TYPE IV (L) ARROW.
AutoCAD SHX Text
FURNISH AND INSTALL 28" HIGH TAPCO CITY POST PER DETAIL "D" ON SHEET 3.
AutoCAD SHX Text
INSTALL SIGN PER PLAN ON EXISTING STREET LIGHT POLE. BOTTOM OF SIGN SHALL HAVE A MINIMUM OF 7' CLEARANCE ABOVE FINISHED SURFACE.
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
5
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
8
AutoCAD SHX Text
9
AutoCAD SHX Text
10
AutoCAD SHX Text
13
AutoCAD SHX Text
15
AutoCAD SHX Text
21
AutoCAD SHX Text
TS-007
AutoCAD SHX Text
SHEET 4 0F 4
AutoCAD SHX Text
DWY

T

R

A

F

F

I

C

1. EL CAMINO REAL & ENCINITAS BLVD

2. EL CAMINO REAL & VIA MOLENA3. EL CAMINO REAL & MOUNTAIN VISTA DR

AutoCAD SHX Text
11
AutoCAD SHX Text
12
AutoCAD SHX Text
13
AutoCAD SHX Text
22
AutoCAD SHX Text
23
AutoCAD SHX Text
33
AutoCAD SHX Text
34
AutoCAD SHX Text
35
AutoCAD SHX Text
VERTICAL
AutoCAD SHX Text
HORIZONTAL
AutoCAD SHX Text
EXP.
AutoCAD SHX Text
R.C.E. NO.
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
PLANS PREPARED UNDER SUPERVISION OF
AutoCAD SHX Text
PUBLIC IMPROVEMENT PLANS FOR:
AutoCAD SHX Text
CITY OF ENCINITAS
AutoCAD SHX Text
SHEET OF 10
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
ENGINEERING DEPARTMENT
AutoCAD SHX Text
APPROVALS
AutoCAD SHX Text
DATE
AutoCAD SHX Text
REFERENCES
AutoCAD SHX Text
DATE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
BENCHMARK
AutoCAD SHX Text
N/A
AutoCAD SHX Text
EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
DESIGNED BY
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
CHECKED BY
AutoCAD SHX Text
TWO WORKING DAYS BEFORE YOU DIG
AutoCAD SHX Text
811
AutoCAD SHX Text
CALL TOLL FREE
AutoCAD SHX Text
CALL BEFORE YOU DIG
AutoCAD SHX Text
Underground Service Alert
AutoCAD SHX Text
Dig Alert
AutoCAD SHX Text
BY:
AutoCAD SHX Text
BY:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
RECOMMENDED
AutoCAD SHX Text
74667
AutoCAD SHX Text
12-31-2021
AutoCAD SHX Text
AA
AutoCAD SHX Text
NM
AutoCAD SHX Text
JS
AutoCAD SHX Text
5865 AVENIDA ENCINAS, #142B
AutoCAD SHX Text
CARLSBAD, CA 92008
AutoCAD SHX Text
PH: 760-602-4290
AutoCAD SHX Text
WWW.STCTRAFFIC.COM
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
C
AutoCAD SHX Text
A
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
A
AutoCAD SHX Text
I
AutoCAD SHX Text
NO. 74667
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
V
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
N
AutoCAD SHX Text
O
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
P
AutoCAD SHX Text
D
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
T
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
O
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
S
AutoCAD SHX Text
M
AutoCAD SHX Text
.
AutoCAD SHX Text
M
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
Exp. 12-31-2021
AutoCAD SHX Text
100% PLANS - EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
NICOLAS M. MINICILLI
AutoCAD SHX Text
1"=40'
AutoCAD SHX Text
10-03-2019
AutoCAD SHX Text
S
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
22
AutoCAD SHX Text
8
AutoCAD SHX Text
LOOP DETECTION MODIFICATION PLAN
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
AB
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
AB
AutoCAD SHX Text
CONSTRUCTION NOTES
AutoCAD SHX Text
FURNISH AND INSTALL TYPE F VEHICLE DETECTOR LOOP PER 2018 CALTRANS RSP ES-5B. REFRESH EXISTING PAVEMENT MARKINGS AS NECESSARY PER SIGNING AND STRIPING PLANS.
AutoCAD SHX Text
SC
AutoCAD SHX Text
SC
AutoCAD SHX Text
SC
AutoCAD SHX Text
SC
AutoCAD SHX Text
SC
AutoCAD SHX Text
SC
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
22
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
ENCINITAS BLVD
AutoCAD SHX Text
30
AutoCAD SHX Text
15
AutoCAD SHX Text
30
AutoCAD SHX Text
60
AutoCAD SHX Text
90
AutoCAD SHX Text
SCALE: 1"=30'
AutoCAD SHX Text
0
AutoCAD SHX Text
VIA MOLENA
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
MOUNTAIN VISTA DR
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
SCALE 1"=30'
AutoCAD SHX Text
SCALE 1"=30'
AutoCAD SHX Text
SCALE 1"=30'
AutoCAD SHX Text
TS-008
AutoCAD SHX Text
SHEET 1 0F 3
AutoCAD SHX Text
FURNISH AND INSTALL 4'X 6' MODIFIED TYPE Q BICYCLE DETECTOR PER 2018 CALTRANS RSP ES-5B, SIZE LOOP PER DETAIL "C" ON SHEET 3. FURNISH AND INSTALL NEW DETECTOR CARDS IN CABINET AS NECESSARY. REFRESH EXISTING PAVEMENT MARKINGS AS NECESSARY PER SIGNING AND STRIPING PLANS.
AutoCAD SHX Text
2'(TYP.)
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
SC
AutoCAD SHX Text
23
AutoCAD SHX Text
SC
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
SC
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
44'(TYP.)
AutoCAD SHX Text
2'(TYP.)
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
23
AutoCAD SHX Text
R/W
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
SC
AutoCAD SHX Text
R/W
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
R/W
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
R/W
AutoCAD SHX Text
SC

T

R

A

F

F

I

C

4. EL CAMINO REAL & VIA MONTORO

5. EL CAMINO REAL & CIRCUIT CITY DRWY

AutoCAD SHX Text
38
AutoCAD SHX Text
39
AutoCAD SHX Text
48
AutoCAD SHX Text
49
AutoCAD SHX Text
VERTICAL
AutoCAD SHX Text
HORIZONTAL
AutoCAD SHX Text
EXP.
AutoCAD SHX Text
R.C.E. NO.
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
PLANS PREPARED UNDER SUPERVISION OF
AutoCAD SHX Text
PUBLIC IMPROVEMENT PLANS FOR:
AutoCAD SHX Text
CITY OF ENCINITAS
AutoCAD SHX Text
SHEET OF 10
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
ENGINEERING DEPARTMENT
AutoCAD SHX Text
APPROVALS
AutoCAD SHX Text
DATE
AutoCAD SHX Text
REFERENCES
AutoCAD SHX Text
DATE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
BENCHMARK
AutoCAD SHX Text
N/A
AutoCAD SHX Text
EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
DESIGNED BY
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
CHECKED BY
AutoCAD SHX Text
TWO WORKING DAYS BEFORE YOU DIG
AutoCAD SHX Text
811
AutoCAD SHX Text
CALL TOLL FREE
AutoCAD SHX Text
CALL BEFORE YOU DIG
AutoCAD SHX Text
Underground Service Alert
AutoCAD SHX Text
Dig Alert
AutoCAD SHX Text
BY:
AutoCAD SHX Text
BY:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
RECOMMENDED
AutoCAD SHX Text
74667
AutoCAD SHX Text
12-31-2021
AutoCAD SHX Text
AA
AutoCAD SHX Text
NM
AutoCAD SHX Text
JS
AutoCAD SHX Text
5865 AVENIDA ENCINAS, #142B
AutoCAD SHX Text
CARLSBAD, CA 92008
AutoCAD SHX Text
PH: 760-602-4290
AutoCAD SHX Text
WWW.STCTRAFFIC.COM
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
C
AutoCAD SHX Text
A
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
A
AutoCAD SHX Text
I
AutoCAD SHX Text
NO. 74667
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
V
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
N
AutoCAD SHX Text
O
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
P
AutoCAD SHX Text
D
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
T
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
O
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
S
AutoCAD SHX Text
M
AutoCAD SHX Text
.
AutoCAD SHX Text
M
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
Exp. 12-31-2021
AutoCAD SHX Text
100% PLANS - EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
NICOLAS M. MINICILLI
AutoCAD SHX Text
1"=40'
AutoCAD SHX Text
10-03-2019
AutoCAD SHX Text
9
AutoCAD SHX Text
LOOP DETECTION MODIFICATION PLAN
AutoCAD SHX Text
CONSTRUCTION NOTES
AutoCAD SHX Text
FURNISH AND INSTALL TYPE F VEHICLE DETECTOR LOOP PER 2018 CALTRANS RSP ES-5B. REFRESH EXISTING PAVEMENT MARKINGS AS NECESSARY PER SIGNING AND STRIPING PLANS.
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
SC
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
22
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
SC
AutoCAD SHX Text
SC
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
AB
AutoCAD SHX Text
VIA MONTORO
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
CIRCUIT CITY DRWY
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
SCALE 1"=30'
AutoCAD SHX Text
SCALE 1"=30'
AutoCAD SHX Text
TS-009
AutoCAD SHX Text
SHEET 2 0F 3
AutoCAD SHX Text
FURNISH AND INSTALL 4' X 6' MODIFIED TYPE Q BICYCLE DETECTOR PER 2018 CALTRANS RSP ES-5B, SIZE LOOP PER DETAIL "C" ON SHEET 3. FURNISH AND INSTALL NEW DETECTOR CARDS IN CABINET AS NECESSARY. REFRESH EXISTING PAVEMENT MARKINGS AS NECESSARY PER SIGNING AND STRIPING PLANS.
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
SC
AutoCAD SHX Text
SC
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
SC
AutoCAD SHX Text
23
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
30
AutoCAD SHX Text
15
AutoCAD SHX Text
30
AutoCAD SHX Text
60
AutoCAD SHX Text
90
AutoCAD SHX Text
SCALE: 1"=30'
AutoCAD SHX Text
0

T

R

A

F

F

I

C

6. EL CAMINO REAL & GARDEN VIEW RD

7. EL CAMINO REAL & TOWN CENTER DR

8. EL CAMINO REAL & LEUCADIA BLVD

AutoCAD SHX Text
58
AutoCAD SHX Text
59
AutoCAD SHX Text
60
AutoCAD SHX Text
82
AutoCAD SHX Text
83
AutoCAD SHX Text
84
AutoCAD SHX Text
91
AutoCAD SHX Text
92
AutoCAD SHX Text
93
AutoCAD SHX Text
VERTICAL
AutoCAD SHX Text
HORIZONTAL
AutoCAD SHX Text
EXP.
AutoCAD SHX Text
R.C.E. NO.
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
PLANS PREPARED UNDER SUPERVISION OF
AutoCAD SHX Text
PUBLIC IMPROVEMENT PLANS FOR:
AutoCAD SHX Text
CITY OF ENCINITAS
AutoCAD SHX Text
SHEET OF 10
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
ENGINEERING DEPARTMENT
AutoCAD SHX Text
APPROVALS
AutoCAD SHX Text
DATE
AutoCAD SHX Text
REFERENCES
AutoCAD SHX Text
DATE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
BENCHMARK
AutoCAD SHX Text
N/A
AutoCAD SHX Text
EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
DESIGNED BY
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
CHECKED BY
AutoCAD SHX Text
TWO WORKING DAYS BEFORE YOU DIG
AutoCAD SHX Text
811
AutoCAD SHX Text
CALL TOLL FREE
AutoCAD SHX Text
CALL BEFORE YOU DIG
AutoCAD SHX Text
Underground Service Alert
AutoCAD SHX Text
Dig Alert
AutoCAD SHX Text
BY:
AutoCAD SHX Text
BY:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
R.C.E. NO.:
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
RECOMMENDED
AutoCAD SHX Text
74667
AutoCAD SHX Text
12-31-2021
AutoCAD SHX Text
AA
AutoCAD SHX Text
NM
AutoCAD SHX Text
JS
AutoCAD SHX Text
5865 AVENIDA ENCINAS, #142B
AutoCAD SHX Text
CARLSBAD, CA 92008
AutoCAD SHX Text
PH: 760-602-4290
AutoCAD SHX Text
WWW.STCTRAFFIC.COM
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
C
AutoCAD SHX Text
A
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
A
AutoCAD SHX Text
I
AutoCAD SHX Text
NO. 74667
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
V
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
N
AutoCAD SHX Text
O
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
P
AutoCAD SHX Text
D
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
T
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
O
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
S
AutoCAD SHX Text
M
AutoCAD SHX Text
.
AutoCAD SHX Text
M
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
C
AutoCAD SHX Text
I
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
I
AutoCAD SHX Text
Exp. 12-31-2021
AutoCAD SHX Text
100% PLANS - EL CAMINO REAL GREEN BIKE LANE PROJECT
AutoCAD SHX Text
NICOLAS M. MINICILLI
AutoCAD SHX Text
1"=40'
AutoCAD SHX Text
10-03-2019
AutoCAD SHX Text
10
AutoCAD SHX Text
LOOP DETECTION MODIFCATION PLAN
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
22
AutoCAD SHX Text
SC
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
SC
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
SC
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
AB
AutoCAD SHX Text
GARDEN VIEW RD
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
SC
AutoCAD SHX Text
AB
AutoCAD SHX Text
30
AutoCAD SHX Text
15
AutoCAD SHX Text
30
AutoCAD SHX Text
60
AutoCAD SHX Text
90
AutoCAD SHX Text
SCALE: 1"=30'
AutoCAD SHX Text
0
AutoCAD SHX Text
TOWN CENTER DR
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
EL CAMINO REAL
AutoCAD SHX Text
SCALE 1"=30'
AutoCAD SHX Text
LEUCADIA BLVD
AutoCAD SHX Text
SCALE 1"=30'
AutoCAD SHX Text
SCALE 1"=30'
AutoCAD SHX Text
SCALE 1"=30'
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
SC
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
SC
AutoCAD SHX Text
AB
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
22
AutoCAD SHX Text
SC
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
TS-010
AutoCAD SHX Text
SHEET 3 0F 3
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
CONSTRUCTION NOTES
AutoCAD SHX Text
FURNISH AND INSTALL TYPE F VEHICLE DETECTOR LOOP PER 2018 CALTRANS RSP ES-5B. REFRESH EXISTING PAVEMENT MARKINGS AS NECESSARY PER SIGNING AND STRIPING PLANS.
AutoCAD SHX Text
22
AutoCAD SHX Text
FURNISH AND INSTALL 4'X 6' MODIFIED TYPE Q BICYCLE DETECTOR PER 2018 CALTRANS RSP ES-5B, SIZE LOOP PER DETAIL "C" ON SHEET 3. FURNISH AND INSTALL NEW DETECTOR CARDS IN CABINET AS NECESSARY. REFRESH EXISTING PAVEMENT MARKINGS AS NECESSARY PER SIGNING AND STRIPING PLANS.
AutoCAD SHX Text
23
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
44'(TYP.)
AutoCAD SHX Text
2'(TYP.)
AutoCAD SHX Text
SC
AutoCAD SHX Text
SC
AutoCAD SHX Text
SC
AutoCAD SHX Text
22
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
AB
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W
AutoCAD SHX Text
R/W