Figure 3 : Basic Project Life Cycle Weiss & Wysocki (1994)

Activity on Node Network Diagram

Embed Size (px)

Citation preview

Page 1: Activity on Node Network Diagram

Figure 3 : Basic Project Life Cycle Weiss & Wysocki (1994)

Page 2: Activity on Node Network Diagram

FORWARD PASS:

EARLY START TIME + DURATION = EARLY FINISH TIME

BACKWARD PASS:

LATE FINISH TIME - DURATION = LATE START TIME

Page 3: Activity on Node Network Diagram

FREE FLOAT =

EARLIEST START TIME OF FINISH EVENT - EARLIEST START TIME OF START EVENT – DURATION

TOTAL FLOAT =

LATEST TIME OF FINISH EVENT – EARLIEST TIME OF START EVENT – DURATION

Page 4: Activity on Node Network Diagram

Warehouse

Soil Testing

Tender Evaluation

Civil

Plumbing

Electrical

Finishes

Staffing

Statutory Approvals

Approvals

Invitation to Bid

Bid Collection

Bid Review

Contract Award

Access

Structural Works

Beams

Roof

Block Works

Drainage

Piping

Sewerage

Fixtures

Wiring

Appliances

Painting

Tiling

Amenities

Access Roads

Final Inspection

Recruitment

TrainingFigure 3: Work Breakdown Structure for New Warehouse – Jimaga Ltd

Page 5: Activity on Node Network Diagram

Figure 1 : TRIPLE CONTRAINTS OF PROJECT MANAGEMENT

Page 6: Activity on Node Network Diagram

2, 11 Slight<2.5 MM < 0.5

month

Slight Acceptable with Slight Reworks

21, 23 1,3 Minor< 5MM < 1 month

Minor Acceptable with Limited Reworks

45, 46,47 12, 36, 38, 42, 50, 51,57

5, 32, 43,52,56,60,66,67,68

Local5 MM –25 MM

2 months Local Acceptable with Major Reworks

8, 9, 10, 18, 19, 44,54,64,65,74

7, 26, 30, 33, 34, 37, 41, 49,59,61,63,75

4, 14,5, 22,24, 27, 28, 29, 31, 35, 39, 48,53,62,69,70,71,73,76,77

Major25 MM – 50 MM

3 months Major Acceptable with Very Major Reworks

16, 17, 20 40,55,58,72 6, 25Very High>50 MM

> 3 months

Very major

Acceptable with total Reworks

0.5 Almost Certain

Cost Sched Scope Quality

Project Risk Matrix Chart

0..4 Very Likely

0.3 Likely

0.2 Unlikely

0.1 Improbable

0.1 Negligible 0.2 Slight 0.3 Low 0.4 Medium 0.5 High

PR

OB

AB

ILIT

Y

SEVERITY

= Low Risk

KEY

= Medium Risk

= High Risk

Page 7: Activity on Node Network Diagram

Risk I.D

Risk Description Probability

Impact Risk FactorR (f) = P (i) * I

(i)

Risk Owner

Treatment TriggerPoint

1 Sponsor not able to finalize requirements to begin construction

0.4 0.5 0.20 Jimaga Practice Requirements management

2 Changes to building capacity 0.5 0.4 0.20 Ensure change control system

3 Changing scope 0.4 0.5 0.20 Same as 2

4 Buried catalyst may not be safe 0.2 0.5 0.10 Conduct tests, identify alternative site

5 Approvals may be delayed 0.3 0.5 0.15 Develop system to track approvals

6 Site not geotechnically suitable for construction 0.1 0.5 0.05 Ensure proper tests and identify alternative

7 Change in sponsor 0.2 0.3 0.06 Prepare overview document of project

8 Change in Executive sponsor 0.2 0.3 0.06 Prepare overview document of project

9 Change in administration 0.2 0.3 0.06 Prepare overview document of project

10 Construction costs may escalate 0.5 0.4 0.20 Develop estimates with contingency

11 Skilled labor not available 0.3 0.4 0.12 Seek a secured supply for project

12 Failure to obtain permits and approvals on time:

13 1. Town and Country Planning approvals 0.2 0.5 0.10 Ensure that requirements of approval are implemented and follow up

14 1. Water and Sewerage 0.1 0.3 0.03 Ensure that requirements of approval are implemented and follow up

15 1. Electricity Commissioners 0.1 0.3 0.03 Ensure that requirements of approval are implemented and follow up

16 1. Fire 0.2 0.3 0.06 Ensure that requirements of approval are implemented and follow up

17 1. Regional Corporation ( 0.2 0.3 0.06 Ensure that requirements of approval are implemented and follow up

Risk Register for Construction of New Warehouse

Page 8: Activity on Node Network Diagram

18 Relocation of existing Gas, Oil, Methanol, Water, Electrical and other lines

0.1 0.3 0.03 Ensure that requirements of approval are implemented and follow up

19 Scope creep 0.4 0.4 0.16 Ensure a change control process is place

20 Hasty Planning 0.2 0.5 0.10 Develop a project definition and strategy plan

21 Inadequate resources for planning 0.4 0.4 0.16 Identify all resources needed and inform stakeholders

22 Poor Design Management 0.2 0.5 0.10 Implement a design management process

23 Design quality is poor 0.1 0.5 0.05 Implement a design management process

24 Contract is lose and venerable 0.2 0.4 0.08 Ensure that project manager and legal department work in tandem

25 Log lead procurement items not ordered in time 0.3 0.5 0.15 Identify all such items in project definition and schedule for procurement

26 Unrealistic estimates of time and cost 0.2 0.5 0.10 Practice proper estimating according to standards

27 Final design is not fit for purpose 0.2 0.5 0.10 Ensure that a design management system requires client sign –off

28 Multiple project dependencies not identified 0.2 0.4 0.08 Develop a project definition and strategy plan

29 Flawed estimates of cost and time leading to unrealistic schedules, budget and company estimates

0.2 0.5 0.10 Practice proper estimating according to standards

30 Stakeholders not fully identified and needs analysed 0.3 0.5 0.15 Develop a project definition and strategy plan

31 Poor access to building 0.2 0.4 0.08 Identify requirements and incorporate into design

Page 9: Activity on Node Network Diagram

32 Traffic congestion during and after construction 0.2 0.4 0.08 Estimate traffic issues and incorporate management into project plan

33 Communication problems with stakeholders 0.2 0.5 0.10 Develop a stakeholder analysis and communication plan

34 Conflicts with some stakeholders 0.3 0.4 0.12 Practice proactive conflict management

35 Poor quality of labor 0.2 0.4 0.08 Set benchmarks

36 A shortage of labor 0.3 0.4 0.12 Identify strategies to ensure that a supply is secured for project

37 Building not built to proposed OSHA requirements 0.2 0.5 0.10 Incorporate OSHA standards in all design and implement

38 Delays due to architect 0.1 0.4 0.04 Partner with architect and possibly include an incentive in contract

39 Quantity variations 0.2 0.4 0.08 Ensure that proper estimates according to standards are done

40 Construction schedule slips 0.3 0.4 0.12 Proactive monitor schedule and risks

41 Poor safety management by contractors 0.3 0.5 0.15 Ensure that stringent safety requirements are applied

42 Daily disputes by 0.2 0.3 0.06 Proactively manage conflicts ; partner with union

43 Contractor may not pay union rates 0.3 0.3 0.09 Ensure that contract requires union rates and monitor

44 Poor relations with union 0.3 0.3 0.09 Proactively partner with union

45 Adverse weather during construction 0.3 0.3 0.09 Develop contingencies for flooding, heavy rainfall etc

46 Coordination failure 0.2 0.5 0.10 Ensure that a project management process is used

47 Unmanageable change orders 0.2 0.4 0.08 Ensure that client understands the change control processes and the impact of heavy changes on project

Page 10: Activity on Node Network Diagram

48 Delay in evaluation and approval of change orders 0.3 0.4 0.12 Ensure that Change Control Board is aware of its role and disseminate the change control process

49 Design changes during planning and construction 0.3 0.4 0.12 Ensure that a project management process is used

50 Delayed management approvals 0.3 0.5 0.15 Ensure that management is aware of its role on the project and the impact of approval delays

51 Current budget for fiscal year exceeded 0.2 0.5 0.10 Develop estimates and budgets realistically

52 Political changes 0.2 0.3 0.06 Develop a project justification document

53 Planned quality is eroded during construction 0.1 0.4 0.04 Ensure that a quality management system is applied

54 Untimely payments to contractors 0.3 0.5 0.15 Ensure that both contractors and client understand their contractual role and the requirements or payment. Seek a point person from finance

55 Bureaucratic breakdowns and bottlenecks 0.3 0.4 0.12 Ensure that such constraints are identified and resources are allocated to pursue

56 Stakeholder complaints during construction about noise dust and traffic

0.1 0.4 0.04 Perform stakeholder analysis and proactively address concerns; Implement measure to reduce contaminants; seek a communication specialist

57 Inadequate internal resources for project management 0.2 0.4 0.08 Procure externally if required

58 Construction contractor may be adversarial and prone to litigation

0.3 0.5 0.15 Ensure that past litigation history and past performance is appropriately weighted in evaluation

59 Strong-arm tactics used by contractor 0.2 0.4 0.08 Ensure that contract is tight; inspire a partnership relationship and evaluation considers this factor

Page 11: Activity on Node Network Diagram

60 Poor coordination of multiple contractors that would be used if project were fast tracked

0.2 0.5 0.10 Develop a realistic project schedule and identify interfaces

61 Contractor claims prolonged 0.2 0.40.08

Ensure that all stakeholders understand their role in processing of claims; ensure that change control process is circulated to all

62 Lessons Learnt not captured 0.2 0.3 0.06 Applied process to each project phase and disseminate

63 Handover to client done without proper sign offs 0.2 0.3 0.06 Ensure a quality management system is applied

64 Inadequate understanding the client’s / stakeholders requirements

0.3 0.5 0.15 Practice requirements management

65 Inadequate project scope identification 0.3 0.5 0.15 Practice requirements management66 Inadequate implementation of the client’s /

stakeholders requirements0.3 0.5 0.15 Practice requirements management

67 Poor in-house project management 0.2 0.5 0.10 Ensure that project management processes are used

68 Loss of control of works by Architect / engineers / contractors, etc

0.2 0.5 0.10 Ensure proper project control systems

69 Poor supervision and quality control. 0.2 0.5 0.10 Ensure that a quality management system is utilsed

70 Not taking a holistic view of the project 0.1 0.4 0.04 Ensure that project is aligned to strategic focus

71 Non-identification and implementation of associated works, e.g.. access, drainage, landscaping, site selection based other facilities to be provided in the area, etc

0.2 0.5 0.10 Practice requirements management

72 Poor project records / reports. 0.2 0.3 0.06 Ensure that resources are allocated to maintain records etc.

73 Late submissions of items requiring internal and external approvals

0.2 0.4 0.08 Identify such items in project definition

74 Project Funding 0.2 0.5 0.10 Ensure that client procures funding75 Material Transfer 0.3 0.5 0.15 Develop a plan to ensure that

materials are safely transferred to project site

Page 12: Activity on Node Network Diagram

Figure 4 : Turner’s Goals & Methods Matrix

Page 13: Activity on Node Network Diagram

Activity On NodeNetwork Diagram Biscu Ltd

START

EST0 0

00 0

LEGEND:

EST : Early Start TimeLST: Late Start TimeEFT: Early Finish TimeLFT: Late Finish TimeDUR : DurationFLO: FloatCritical Path

0DUR

EFT LFTFLO

LST

A B

C

D

F

E

G

H

I

J

O

K

M

N

L

P

Q FINISH

0 4 4

40 0

4

4

2 6

0 6

6

6

3 9

9 3 12

6 12

6 0 12

12 2 14

12 0 14

14

14

14

14

14

18

20

21

1

8

2

4 18

22

16

15

22

22

22

22

4

0

6

7

22 4 26

22 0 26

26

26

2 28

0 28

28

28

28

6 34

34

34

0 34

1 29

3433 5

38

38

4

0

38

38

2

8

40

46

4644 6

38 0 46

46

46

1 47

47 0

47 47

4747

0

0

Appendix 1

Page 14: Activity on Node Network Diagram

Activity On NodeNetwork Diagram Juron Ltd

START

EST

0 0

00 0

LEGEND:EST : Early Start TimeLST: Late Start TimeEFT: Early Finish TimeLFT: Late Finish TimeDUR : DurationFLO: Float

0

DUR

EFT LFT FLO

LST

A

0 4

40 0

Figure 1

FINISH

B

C

D

E

F

G H

I

J

K L M N O

P Q

5

4

8

6

9

4 13 8 8

7

6

13 9 4 4

9 5

4

4

4

4

4

9

8

12

10

13

13 26 26 34

34

34

41

40

41 49 49 62 62 71 71 75 75 79

79 88 88 93 0 00

0 009388 8879

79757571716262494941

41

41

34

35

34262613

13

13

13

13

13

8

9

5

7

4

4

5

1

3

0

0 0

0

1

0 0 0 0 0

0 0

Critical Path A-F-G-H-I-K-L-M-N-O-P-Q

Page 15: Activity on Node Network Diagram

Table 1Activity (Tasks) Duration (Days) Preceded By

A 4 -

B 5 A

C 4 A

D 8 A

E 6 A

F 9 A

G 13 B,C,D,E,F

H 8 G

I 7 H

J 6 H

K 8 I, J

L 13 K

M 9 L

N 4 M

O 4 N

P 9 O

Q 5 P

Page 16: Activity on Node Network Diagram

TABLE 2: SENSIVITY ANALYSIS OF DELAYS IN PROJECT SCHEDULE

ACTIVITY DELAY SCHEDULE IMPACT OVERALL PROJECT IMPACT

B 2 days No effect Activity has float of 4 days and can be

delayed for as much as 4 days before any

impact can be made on the completion

date for the project.

P 2 days Delays succeeding

activities by 2 days;

project extended by 2

days

Activity is on the critical path with zero

float. A late start of 2 days resulting in an

increase in overall project from 93 days to

95 days.

O 1 day Delays succeeding

activities by 1 day;

overall project

extended by 1 day as a

result.

Activity is on the critical path with zero

float. The project extending to 94 days as a

result

.