Upload
leigh
View
33
Download
0
Embed Size (px)
DESCRIPTION
a ) Time Structure of CNGS Muon Spill. Activities for CNGS Concerning the OPERA Results. CNGS Secondary Beam Working Group (EN-MEF, EN-STI, EN-CV, EN-EL, BE-CO, BE-OP, DGS-RP, OPERA and ICARUS members). b ) LHC Beam to CNGS. - PowerPoint PPT Presentation
Citation preview
Activities for CNGS Concerning the OPERA
Results
Gianluigi Arduini, Thomas Bohl, Karel Cornelis, Ilias Efthymiopoulos, Edda Gschwendtner, Mike Lamont, Roberto Losito, Javier Serrano, Rende Steerenberg
b) LHC Beam to CNGS
a) Time Structure of CNGS Muon Spill
CNGS Secondary Beam Working Group(EN-MEF, EN-STI, EN-CV, EN-EL, BE-CO, BE-OP, DGS-RP,
OPERA and ICARUS members)
a) Motivation
horns muon detectors
muons
Any effect on protons/neutrinos in the secondary beam line should be seen in the muon signals
Edda Gschwendtner, CERN
targetmagnetichorns
decay tunnel
hadron absorber
muon detector 1
muon detector 2
SPG/OePG 2009 Edda Gschwendtner, CERN 4
60cm270cm
11.25cm
• 2 x 41 fixed monitors (Ionization Chambers)
• 2 x 1 movable monitor
LHC type Beam Loss Monitors• Stainless steel cylinder • Al electrodes, 0.5cm separation• N2 gas filling
CNGS
Muon Monitors
5
Muon Monitors: Expected Signals
pit 1 Horizontal
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
-157.5 -135 -112.5 -90 -67.5 -45 -22.5 0 22.5 45 67.5 90 112.5 135 157.5
cm
ch
/po
t
measurement
simulation
Horizontal Profile Pit 1pit 2 Horizontal
0
0.002
0.004
0.006
0.008
0.01
0.012
0.014
-157.5 -135 -112.5 -90 -67.5 -45 -22.5 0 22.5 45 67.5 90 112.5 135 157.5cm
ch
/po
t
measurement
simulation
Horizontal Profile Pit 2MeasurementsSimulations
P. S
ala
et a
l, FL
UKA
sim
ulati
ons
2008
~5 107 muons/cm2/10.5ms 8 105
muons/cm2/10.5ms
Challenges:
Pit 1: ~1 THz/cm2
Pit 2: ~10-100 GHz/cm2
Different energy spectra in muon profiles in pit 1 and pit 2Background signals smearing the timing signals
Detector choice
Simulations
Diamond DetectorsDetector (very fast!) +electronics system exists in a form that perfectly fits into the general accelerator data taking and logging system.– LHC experiments: Beam condition monitoring– LHC: e.g.: Beam loss monitoring before global LHC abort trigger
6
20 ns / div10 mV / div
SPS SignalIP7
Diamond Detectors for CNGS
7
4-5 x
Combine different diamonds and amplifiers: eg. Single-crystal or Poly-crystal with 2GHz/40dB I-amp
Use kicker extraction signal to trigger the scope (like done for BCFT)Measure the time structure of muon spills with ~1GS/s
Perform cable delay measurements
Planning• Installation during Technical Stop 7-11 Nov 2011
– Tight schedule! (cabling, Ethernet, detector installation,…)
8
LHC schedule
Injector schedule
• Measurements during last days of CNGS run until 21 Nov
LHC beam to CNGS 9
b) Motivation
7-10-2011
LHC beam to CNGS 10
Motivation
7-10-2011
versus
LHC beam to CNGS 11
Reminder – at present• 2*10.5 microseconds extractions from SPS
separated by 50 ms– ~1.8e13 per extraction– ~3.6e13 per cycle– Cycle length 6 s
7-10-2011
4e10
25 ns bins
LHC beam to CNGS 12
CNGS flat-out
7-10-2011
LHC beam to CNGS 13
CNGS & LHC
7-10-2011
LHC pilot
LHC 50 ns
LHC beam to CNGS 14
Duty cycle
• 30/45 of SPS time for CNGS in full production mode but:– LHC filling– Operational inefficiency
• Assumed delivery 2.1e17 pot/day– Corresponds to 9.8 hrs of CNGS cycles only
35.3 nu-events/day
7-10-2011
LHC beam to CNGS 15
Event rate
• 16,111 muon neutrino interactions recorded in 3 years with around 1020 pot– External and internal events
• ~1 event per 6 x 1015 pot• (1 tau event so far)
7-10-2011
LHC beam to CNGS 16
1) 4*single bunch
7-10-2011
• High bunch intensity• Higher neutrino event rate per bunch • Very clearly time delimited – easy to resolve bunch structure• Low overall production rate
Bunch intensity 2.5e11
Bunch spacing 500 ns
0.8 nu-events/day0.2 nu-events/bunch/day
LHC beam to CNGS 17
7*single bunch• An alternative scheme, using H21 at injection in the PS, could be
envisaged after some extra cabling in the RF hardware. We could the have 1, 3, or 7 bunches.
• 7 bunches could be done using a double batch injection from the PSB into the PS (4 + 3), requiring some local cabling.
• In this scheme we need nevertheless to verify if coupled bunch oscillations will be an issue and it will take a bit more time to set up (few days) in the PS.
• Not clear yet how tightly spaced high intensity bunches behave in SPS. Until now only 2 high intensity bunches with large spacing of 1.2us. must be tested.
• --> 7 x 2.5E11 per 7.2 sec.
7-10-2011
Heiko DamerauRende SteerenbergThomas Bohl
1.4 nu-events/day0.2 nu-events/bunch/day
LHC beam to CNGS 18
2) 50 ns
7-10-2011
Bunch intensity 1.5 e11
Bunch spacing 50 ns
Bunches/cycle 144
• Higher number of bunches, Higher overall production rate• Lower neutrino rate per bunch compared with single bunch• Probably beyond limit of OPERA’s ability to resolve bunch structure
5.9 nu-events/day0.04 nu-events/bunch/day
LHC beam to CNGS 19
3) 150 ns
7-10-2011
Bunch intensity 1.2 e11
Bunch spacing 150 ns
Bunches/cycle 48
• Less bunches, shorter cycle wrt 50 ns• Low neutrino rate per bunch • Easy to resolve bunch structure – aim of the exercise
1.9 nu-events/day0.04 nu-events/bunch/day
LHC beam to CNGS 20
4) Hybrid
7-10-2011
• Unambiguous bunch structure• Partially compensates loss in pot
3.9 nu-events/day0.2 nu-event/bunch/day
LHC beam to CNGS 21
Numbers
7-10-2011
Karel Cornelis
LHC beam to CNGS 22
Production per day
7-10-2011
BunchIntensity
bunches per batch
batchesper cycle
cycle length
protons percycle
total nocycles
pot per day
eventsper day
events/bunch/day
single 2.5E+11 4 1 7.2 1.00E+12 4900 4.9E+15 0.8 0.20
single 2.5E+11 7 1 7.2 1.75E+12 4900 8.58E+15 1.4 0.20
50 ns 1.5E+11 36 4 21.6 2.16E+13 1633 3.53E+16 5.9 0.04
150 ns 1.2E+11 12 4 18 5.76E+12 1960 1.13E+16 1.9 0.04
HYBRID 1.5E+11 4+36 1+2 18 1.18E+13 1960 2.31E+16 3.9 0.20
Now 6 3.60E+13 5880 2.12E+17 35.3
LHC beam to CNGS 23
Commissioning
• 2 days off-line preparation• PS have to dig out 150 ns• 2 days commissioning time with beam to checkout:– Interlocks– RF– Re-steer line, check matching, check beam
instrumentation• 7 single bunches, if feasible, would take some time
7-10-2011
LHC beam to CNGS 24
Beam Instrumentation
7-10-2011
TT41 BPM system can deal with LHC type beams.There is a choice of integration gate of 8us (used for regular CNGS operation) and 400ns (used for initial CNGS commissioning). The start of the gate is delayed in both cases by 1us from the autotrigger generated by the first bunch down the line. Hence in order to measure using this system you will need a train of bunches which is longer than 1.5us in duration. The system should, in principle, be able to handle any LHC style structure (25ns->150ns). The minimum intensity per bunch which still gives a measurable signal still needs to be verified.
Thierry BogeyRhodri Jones
LHC beam to CNGS 25
Target
7-10-2011
CNGS LHC
Normalized emittance [micron]
~10 ~1.6 (50 ns)After blow-up >3.0
(more radical blow-up possible)Beam size ratio 0.4
After blow-up >0.55Bunch intensity ~1e10 ~2.5e11
Bunch length [ns] 2 1.5
Target good for 3.5e13 in 10 microseconds, equally distributed
LHC beam to CNGS 26
Target• 4 x 2.5 10^11 is probably acceptable, but I would suggest to
take the time to have at least preliminary simulations of the stresses in the first 3 or 4 graphite rods to verify the margin that we have on paper.
• If we break this target, very probably we shall have to exchange the target station with the spare one, which would have a major impact on the schedule of the facility.
7-10-2011
Roberto Losito
LHC beam to CNGS 27
Issues• Extraction kicker heating with bunched beams• Satellites/ghosts– Single – clean– 150 ns – trickier
• Beam Quality Monitor– Needed? Compatibility with LHC?
• Does the beam hit the target cleanly?• Proton beam exit window, He-tank Ti window– In HiRadMat proton exit window: > 0.5mm
• OTR as BCT cross-check?
7-10-2011
LHC beam to CNGS 28
Issues
• Removing the 50 ns jitter induced by the free-running 20 MHz clock signal in OPERA could help in achieving results faster
7-10-2011
LHC beam to CNGS 29
Draft schedule 2012
7-10-2011