Upload
johnathan-pitts
View
213
Download
0
Embed Size (px)
Citation preview
ACARP
Australian Roadway Development
Improvement Project
ROADWAY DEVELOPMENT OPERATORS’ WORKSHOPS
March 2009
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP Project C17010 2
SAFETY ASPECTS OF VENUE
As advised by venue
ACARP Project C17010 3
OBJECTIVE AND FORMAT
Provide a forum for roadway development operators to:
Learn of emerging best practice and roadway development initiatives
Learn of developments in equipment and technology
Network with peers, and share their experience and learnings (and not just their successes)
Identify areas for targeted research
ACARP Project C17010 4
FORMAT
Series of presentations not only outlining advances in roadway development research, technology and practice, but also challenging the way that we currently think about roadway development
Researchers giving us an update on roadway development related R&D
Operators detailing current and emerging operational practices and technologies
International OEM challenging our current roadway development practices
Presentations typically comprise a 20-30 minute presentation with a 10-15 minute open forum for discussion and sharing of experiences and learnings
Conclude with a review to capture key findings, identify opportunities to improve the workshop process, and to identify presentations for future workshops
Workshop report with copies of presentations to be provided to all participants
ACARP Project C17010 5
PREREQUISITES FOR ATTENDANCE
A passion for roadway development, and
A willingness to participate in discussions and share experiences
$150 ......
ACARP
Australian Roadway Development Improvement Project
CM2010 IMPLEMENTATION STRATEGY
March 2009
Jim Sandford, Xstrata CoalBob Miller, Centennial Coal
Guy Mitchell, BMA Coal
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP Project C17010 7
ROADWAY DEVELOPMENT CHALLENGE
• Significant improvements in longwall production and productivity are continuing to be made, with production doubling every 10 years or thereabouts
• Improvements in roadway development are generally failing to keep abreast of longwall improvements
• Higher capacity, new generation mines are being planned – 15 Mtpa
• Older mines are struggling to survive and it is becoming more difficult to find solutions and successfully apply them
• Unlikely that continuing increases in longwall production will be sustainable if current roadway development practices and trends remain unchanged
• Longwall sustainability!
ACARP Project C17010 8
ROADWAY DEVELOPMENT TASK GROUP
Previous attempts at ‘one off ‘ Company initiatives largely failed:
poor problem scope, planning and organisation
lack of mine involvement and commitment
loss of project champions
poor execution and patience
lack of critical mass to gain OEM support
ACARP considered it an industry wide problem requiring an industry wide approach to fund and resource the necessary improvements
RDTG formed in 2005 to develop and direct a roadmap for targeted R&D to improve roadway development
Member companies now include Anglo, Austar, BHPB, BMA, Centennial, Peabody, Rio Tinto, Vale, and Xstrata.
ACARP Project C17010 9
KEY ELEMENTS - CM2010 R&D STRATEGY The RDTG developed a Roadway Development R&D strategy based on input from
participants at the March 2007 round of Workshops:
Key enabling technologies underpinned by organisational and technical competencies
Project management of R&D and engagement of the corporate sector is essential to bring the CM2010 R&D strategy to fruition
Remotely Supervised Continuous
Miner
Automated Installation of Roof and Rib Support
Continuous Haulage
IntegratedPanel
Services
Improved Engineering Availability
Planning, Organisation and Process Control
People Behaviours and Skills
Project Management
of R&D Projects
High Capacity Roadway
DevelopmentSystem
Engagement of Corporate
Sector, OEMs, and
Mines
Key enabling technologies
Organisational and technical competencies
ACARP Project C17010 10
CM2010 R&D STRATEGY
The RDTG continued to refine the CM2010 R&D strategy to embrace a new generation high capacity roadway development system:
Vision
An integrated, remotely supervised high capacity roadway development mining system that enables 15 Mtpa longwall mines to be established and sustained with a single mining unit
The system will also enable mining to be safely undertaken under adverse or extreme mining conditions, or reserves previously considered unmineable
Measures
A sustained performance rate of 10 metres per operating hour (MPOH) for 20 hours per day, based on installing primary support of 6 roof and 2 rib bolts per metre advance together with roof and rib confinement measures (mesh)
Improved health and safety through reduced exposure to hazards in the immediate face area
ACARP Project C17010 11
KEY ENABLING TECHNOLOGIES – CM2010
“Self-steering” technologies and systems to enable mining equipment to maintain both azimuth, horizon and grade control within a variable seam horizon, and the total automation of the cutting and loading cycle (including mining breakaways).
Automated installation of conventional resin anchored bolts and self drilling bolts, and the feeding of bolts and mesh to the installation hardware without direct operator involvement.
Alternative skin reinforcement and confinement technologies and systems that eliminates the installation of roof and rib mesh and provides an enhanced roof and skin reinforcement medium.
Adaption and refinement of continuous haulage technologies, and their integration into an integrated, remotely supervised high capacity mining system.
Technologies and systems that enables face services to be extended within the 3 minute cut, load support cycle without direct operator involvement.
ACARP Project C17010 12
INTEGRATION OF KEY TECHNOLOGIES The roadway development system is built on a number of independent
subsystems that remain largely unchanged since their inception some 40 years ago
With few exceptions, new technologies have been adapted to existing machine designs rather than result in any fundamental review of machine design
The integration of emerging enabling technologies into an integrated, remotely supervised high capacity mining system is expected to pose a significant challenge to researchers and OEMs
Adoption of an industry standard communications protocol will be a prerequisite to system integration (as in Longwall automation)
Applied research and design simulation will be necessary to integrate the emerging technologies and subsystems, similar to that achieved with TBMs in the tunnelling sector
CSIRO and UOW are developing a collaborative framework to enable their core expertise to be applied to the task, together with participating OEMs and other key researchers
13
PROJECT ESTIMATE - CM2010 The level of funding required to successfully develop and
demonstrate all elements of the strategy over the next 3 -5 years is expected to be of the order of $31M, comprising some:
$8.5M for fundamental, ACARP funded research
$22.5M for capital purchases and operational expenditure associated with the purchase of equipment and conduct of “new technology” trials and demonstrations at mines, funded directly by mines
The RDTG proposes that the fundamental research component be funded by ACARP outside routine funding processes, similar to that adopted for the Longwall Automation Project ($5M)
ACARP Project C17010
ACARP Project C17010 14
ACARP FUNDING 2007- 08
Throughout 2007- 08 a number of roadway development related R&D projects have been funded by ACARP, including development of:
The technology and systems required develop a self steering continuous miner
An automated system for installing SDB and mesh, including an integrated logistics and materials handling system from the supplier to the face
A polymer based alternative skin reinforcement and confinement system
A simulation model to enable the limitations of current development processes to be understood
A Roadway Development Handbook to capture the industry’s current “body of knowledge” of roadway development practice
In addition, the RDTG is providing ongoing support for:
The development of self drilling bolts and installation systems
Continuation of the Roadway Development Operators’ Workshops and Benchmarking Study.
ACARP Project C17010 15
2009 AND BEYOND
Given the scope of the CM2010 project and the level of Industry support required to successfully develop and demonstrate the emerging technologies, the RDTG proposes to pursue major project status for Roadway Development within ACARP, similar to the Longwall Landmark Project recently completed.
The RDTG also proposes to support mine based initiatives to develop and demonstrate other key enabling technologies, including continuous haulage systems, remotely operated shuttle cars, services management systems
Strategies are also being developed to engage OEMs in the development and integration of the enabling technologies, both at a demonstration level and in full commercialisation.
The RDTG is also expected to review the industry’s approach to and the development of the organisational and technical competencies required to underpin the successful implementation of the enabling technologies now under development.
ACARP Project C17010 16
IN CONCLUSION
A number of presentations in today’s Workshop will outline progress in development of the key enabling technologies referred to earlier.
Clearly, most projects have many challenges to address in order to bring them to a successful conclusion, however, after today I hope you will agree that we are beginning to kick butt in roadway development R&D!
Please enjoy the Workshop. We trust you get a good insight into current developments with roadway development research, technology and practice.
ACARP
CONTINUOUS MINER AUTOMATION
– REMOTE SENSING AND SELF STEERING
David Reid, CSIRO Queensland Centre for Advanced Technologies (QCAT)
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
CONTINUOUS MINER AUTOMATION
– AUTOMATED BOLTING AND MESHING
Stephen Van Duin, University of Wollongong
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
MORNING TEA
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
TUNNEL BORING MACHINES AND THEIR APPLICATION IN ROADWAY
DEVELOPMENT
Charles Howarth and Christian Frenzel, Herrenknecht
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
TOUGH SKIN – A SPRAY ON POLYMERIC
REPLACEMENT FOR ROOF AND RIB MESH
Chris Lukey, University of Wollongong
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
undergroundcoal.com.au- THE AUSTRALIAN
UNDERGROUND COAL MINING WEB-SITE
Ernest Baafi, University of Wollongong
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
SELF DRILLING BOLT UPDATE
Gary Gibson, ACARP
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
ADVANCES IN STONEDUSTING
Matt Ryan, Mining Attachments (Qld)
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
LUNCH
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
INTRODUCTION OF SCROLLING HEADS AND PLOUGH SHOVELS ON CONTINUOUS
MINERS FOR IMPROVED STRATA CONTROL
Kyle Eager, Alan Ninness and Matt Reh, Dendrobium Mine
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
THE AQUILA CONTINUOUS HAULAGE EXPERIENCE AND APPLICATION OF CHS
IN GATEROAD DEVELOPMENT
Larry Cook, Bounty
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
INTRODUCTION OF CONTINUOUS MINER MONITORING AT CLARENCE
Bernard Vanderventer and Brian Nicholls, Clarence Colliery
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
AFTERNOON TEA
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
UNDERSTANDING THE ROADWAY DEVELOPMENT PROCESS
- FURTHER LEARNINGS FROM THE FUNDAMENTAL ANALYSIS OF ROADWAY
DEVELOPMENT
Richard Porteous, Xstrata NSW
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP
UNDERSTANDING THE ROADWAY DEVELOPMENT PROCESS
ROADSIM - GATEROAD DEVELOPMENT SIMULATION
Geoff Gray, Simulation Modelling Services
Ernest Baafi, University of Wollongong
Australian Coal Association Research ProgramAustralian Coal Association Research Program
ACARP Project C17010 32
WORKSHOP CRITIQUE
What improvements could we make to the structure and format of the Workshop:
Suitability of location, venue and facilities? Timing (eg; day of week, and actual times) What issues should be the subject of future
workshops? Any volunteer presenters? Anything else?
ACARP Project C17010 33
END OF WORKSHOP
Thank you!
Please join us for some for refreshments and further
networking!