 1 11-06-2007 GENERAL REVISION - ISSUED FOR IMPLEMENTATION DDC DRC HOD 0 26-06-2000 ISSUED FOR IMPLEMENTATION DDC DRC HOD Rev . No Date Purpose Prepared by Reviewed by Approved by Template No. 5-0000-0001-T1 Rev. 1 Copyrights EIL All rights reserved Document No. 8-2744-1003 Rev. No. 1 Page 1 of 15 PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM FOR LSTK CONTRACT PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM FOR LSTK CONTRACT THIS SHALL FORM PART OF BID DOCUMENT

a3.8 planning scheduling_20090812_115626.pdf

Embed Size (px)

Citation preview

Page 1: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 1/60

 

1 11-06 -2007GENERAL REVISION - ISSUED FOR

IMPLEMENTATIONDDC DRC HOD

0 26-06 -2000 ISSUED FOR IMPLEMENTATION DDC DRC HOD

Rev

. NoDate Purpose Prepared by Reviewed by Approved by

Template No. 5-0000-0001-T1 Rev. 1 Copyrights EIL – All rights reserved

Document No.8-2744-1003Rev. No. 1 

Page 1 of 15

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT 

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROLSYSTEM FOR LSTK CONTRACT

THIS SHALL FORM PART OF BID DOCUMENT

Page 2: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 2/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 2 of 15

Abbreviations:

LSTK - Lumpsum TurnkeyPMC - Project Management ConsultantMR - Material Requisition AFC - Approved for ConstructionWBS - Work Breakdown StructureUOM - Unit of measurementPR - Purchase RequisitionPO - Purchase OrderP&ID - Piping & Instrumentation Diagram

Document Drafting Committee Members:

Mr. SP SinachoudhuryMr. R MohanMr. MK JainMr. TK NandaMr. R ShailendraMr. SS MadanMr. KN ChoudharyMr. Sudershan Kumar

Document Review Committee Members:

Mr. AK GautamMr. VK SawhneyMr. VL RajaniMr. R Mohan

Page 3: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 3/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 3 of 15

CONTENTS

Clause Title Page No.

1.0 

INTRODUCTION 4 

2.0  DEFINITIONS 4 

3.0 

 ABBREVIATIONS 4 

4.0  DOCUMENTS ALONG WITH BID 4 

5.0   AFTER AWARD OF WORK 5 

6.0 

PROJECT SCHEDULES 6 

7.0 

UPDATION OF PROJECT SCHEDULES 10 

8.0 

REVIEW MEETINGS 11 

9.0  PROGRESS REPORTING 12 

10.0 

BULK MATERIAL CONTROL 13 

11.0  PLANNING PACKAGE 14 

12.0  CONTROL ROOM DISPLAY 14 

13.0  SOFTWARE PACKAGES 15 

14.0 

PROVISION OF COMPUTER FACILITIES 15 

ATTACHMENT

I PROJECT SCHEDULE HIERARCHY (1 Sheet)II WORK BREAK DOWN STRUCTURE (1 Sheet)III MONTHLY PROGRESS REPORT (37 Sheet)IV FLOW OF DOCUMENTS (3 Sheet)

V INDICATIVE PROGRESS MEASUREMENT WEIGHTAGE AT VARIOUS LEVELS (3 Sheet)

Page 4: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 4/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 4 of 15

1.0 INTRODUCTION

To ensure timely completion, the Lumpsum Turnkey (LSTK) Contractor shall establish andmaintain an effective Planning, Scheduling, Monitoring and Control system, including

mobilization of required number of professionally qualified and experienced PlanningEngineers for design office and construction site. The system shall be capable of accurateand timely prediction of trend, evolution of adequate preventive actions for likely slippages,and formulation of suitable catch-up schedule for delays, if any, that have occurred.

Schedules, reports and documents to be prepared and submitted by the LSTK contractorfor review of Client/ Project Management Consultant (PMC) at various stages and detailsof meetings to be held are described here.

2.0 DEFINITIONS

Work Breakdown Structure (WBS) Work Breakdown Structure is a diagram that depicts various units in a project and each unit

is detailed with work items/equipments and major workloads. 

Design Office Where Residual Basic Engineering, Detailed engineering, procurement activities for thecontract are performed by LSTK contractor.

FunctionsFunction means basic components of the projects e.g. Residual Basic Engineering,Detailed engineering, ordering, manufacturing & delivery, construction and commissioning.Each function is divided into various disciplines. In case of engineering, various disciplinesare architecture, civil, structure, piping etc.

3.0 ABBREVIATIONS

LSTK - Lumpsum TurnkeyPMC - Project Management ConsultantMR - Material Requisition AFC - Approved for ConstructionWBS - Work Breakdown StructureUOM - Unit of measurementPR - Purchase RequisitionPO - Purchase OrderP&ID - Piping & Instrumentation Diagram

4.0 DOCUMENTS ALONG WITH BID

The LSTK bidder shall submit following documents along with the bid:

a) Proposed Overall Project Schedule in network form showing all the details unit wise.b) Write up on Project Planning, Scheduling, Monitoring and Control system (proposed).c) Organizational set up for Planning, Scheduling, Monitoring & Control at LSTK

Contractor’s Design Office and Site Office.d) Progress Measurement Methodology with details such as weightages, milestones,

frequency etc.e) Project execution methodology.

Page 5: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 5/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 5 of 15

f) Function wise Resource Deployment Schedule (HO & Site manpower and constructionequipment).

g) Softwares to be used for planning and material control.h) Statement confirming compliance to the “Planning, Scheduling, Monitoring and Control

System” requirements regarding contents of the documents to be submitted to

Client/PMC.

5.0 AFTER AWARD OF WORK

5.1 90 DAYS FRONT END SCHEDULE

The LSTK Contractor shall prepare and submit a detailed 90 days front-end schedule withinone week of award. Pending finalisation of Overall Schedule, this schedule shall be the basisof monitoring of front-end activities. The schedule shall cover all activities to be carried outduring initial 90 days period of the contract. The schedule shall be reviewed in the kick-offmeeting.

5.2 KICK OFF MEETING

 A Kick Off Meeting shall be organised within two weeks of award of contract. The meetingshall be attended by Client’s and PMC’s representatives. During the meeting, the followingwith respect to Planning, Scheduling, Monitoring and Control system shall be discussed andfinalized:

1. Planning deliverables required for Project Monitoring and Control.2. Work Breakdown Structure for Project Schedules, organisation and level of detailing

for Overall Project Schedule and Functional Schedules.3. Procedure for Project Planning, Scheduling, Monitoring & Control system including all

reporting formats.4. Progress Measurement Methodology and Unit, Function, Discipline, and Deliverable

wise weightage breakdown (refer Attachment V for indicative weightage). 

5. List of engineering deliverables with indicative schedule for submission.6. List of unit wise milestones to be included in the network, in addition to milestones

specified in the Contract, if any (the number of milestones shall be at least 2 to 3 perunit per month).

7. List of critical equipment and materials for the fortnightly expediting report to beissued by the LSTK Contractor.

8. Procedure for Bulk material control.9. Cut off dates, distribution list with number of copies and Project calendar indicating

submission of various planning documents and revisions.10. Any other document as required.

5.3 PROGRESS MEASUREMENT METHODOLOGY

The LSTK Contractor shall submit during Kick Off Meeting, the detailed methodology ofprogress measurement of Residual Basic Engineering, Detailed Engineering, Ordering,Manufacturing & Delivery, Sub-contracting, Construction and Commissioning for review byClient/PMC. LSTK Contractor shall also furnish the methodology of progress measurementfor sub-contracted packages such as DM plant, Cooling tower etc. and integration of thesame with the overall progress.

Page 6: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 6/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 6 of 15

During the Kick Off meeting, Client/PMC shall finalise weighted values to be used for thefollowing:-a) Unit wise within the package, if applicable.b) Function wise within each unit.c) Milestone weightage within each deliverable.

Effort based weighted values for the following, along with the basis of their derivation, shallbe submitted by LSTK Contractor for review by Client/PMC, and the comments if any shallbe incorporated by LSTK Contractor before submission of functional schedules that usethese weighted values as the basis:a) Discipline wise within each function.b) Deliverable level weightage Percentage.

Progress figures at Unit / Function / Discipline level shall be summarized from deliverablelevel and indicated in the functional schedules.

6.0 PROJECT SCHEDULES

Following schedules shall be prepared and submitted by LSTK contractor to Client/PMC forapproval. A hierarchy of all schedules to be generated by LSTK Contractor is shown in Attachment – I. 

6.1 OVERALL PROJECT SCHEDULE NETWORK (Summarised & Detailed)

The LSTK Contractor shall submit within four weeks of award a network based detailedoverall project schedule (unit wise) on time scale, for all units in the package and allfunctions of the work along with a Work Breakdown Structure indicating unit wise workload(sample format as Attachment - II). The schedule shall highlight interface activities in thescope of Client/PMC and clearly reflect strategies and philosophy of execution. Majormilestones for each unit shall be depicted at the beginning of the network. The projectschedule shall be developed for contractual duration and or target duration decided with

Client/PMC. Grace period, if any as per contract shall not be considered for schedule. The schedule shall be reviewed by Client/PMC and the comments if any shall beincorporated and the schedule shall be issued for implementation within one week  fromthe receipt of comments. This schedule once approved by Client/PMC shall not be revisedwithout the prior written permission of Client/PMC.

Overall Project Schedule Network (Summarised) will be derived from Overall ProjectSchedule Network (Detailed) and will include all major / critical activities & summarisedactivities at macro-level.

Overall Project Schedule Network (Detailed) shall be used for trend / detailed analysiswhereas summarised Overall Schedule will be used to project status at a glance to highermanagement along with the Monthly Progress Report.

6.2 FUNCTIONAL SCHEDULES

The LSTK Contractor shall prepare resource based detailed Unit wise functional schedulesfor all functions in spreadsheet format in line with overall project schedule for monitoringand control. LSTK Contractor shall submit the same within six weeks of award for reviewexcept construction schedule, which shall be submitted within eight weeks of award. Unitwise “S” curves for schedule progress shall also be submitted along with the functional

Page 7: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 7/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 7 of 15

schedules. The schedule shall be reviewed by Client/PMC and comments, if any, shall beincorporated and issued for implementation within one week from receipt of comments. The Schedule “S” curves shall remain firm during the execution of the project.

LSTK Contractor shall also ensure preparation, submission and updation of all functional

schedules as described herein for all sub contracted packages like Heaters, DM Plant,WWTP, Cooling Tower, Nitrogen Plant etc.

6.2.1 Residual Basic Engineering Schedule

The LSTK Contractor shall submit a Unit wise schedule for all Residual Basic Engineering Activities like finalisation including updation (incorporating vendor data) of P&IDs forprocess units and utilities & offsites, release of line schedules, finalisation of process datasheets for equipment etc. as per page 14 of Attachment - III.

6.2.2 Detailed Engineering Schedule

The LSTK Contractor shall submit a Unit wise schedule of all engineering

deliverable/documents such as AFC drawings, Isometrics, Specifications, MaterialRequisition, Purchase Requisition, Design calculations etc. as per page 14 of Attachment -III.

6.2.3 Ordering Schedule

The LSTK contractor shall submit a Unit wise schedule for all ordering activities as perpages 17 &18 of Attachment - III. This shall include all MRs listed in Engineering Schedule.

6.2.4 Manufacturing / Delivery Schedule

The LSTK contractor shall submit a Unit wise schedule for all Manufacturing & Deliveryactivities as per page 22 of Attachment - III. These shall include all orders listed in the

Ordering Schedule. The progress at Function/Unit level shall be summarised consideringweighted values of tagged items and bulk material to report overall Manufacturing andDelivery progress.

LSTK Contractor shall also submit along with Weekly Progress Report, status of drawingsand documents for all vendors on whom orders have been placed, as per page 16 of Attachment - III. In addition to the above, for critical items as mutually agreed betweenLSTK Contractor and Client/PMC, LSTK Contractor shall ensure that vendors prepares andupdates logical networks for Manufacturing & Delivery and submit the same on weekly /monthly basis to Client/PMC if asked for.

6.2.5 Sub-contracting Schedule

The contractor shall submit a Unit wise schedule for all Sub-contracting activities as perpage 23 of Attachment - III. This shall include all tenders envisaged for the Project. 

6.2.6 CONSTRUCTION SCHEDULE

The LSTK Contractor shall prepare and submit a Detailed Construction Schedule unitwise for Client/PMC review. The LSTK Contractor shall describe resources (manpower andmachinery) required to be mobilised. The schedule shall have interface with Engineering,

Page 8: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 8/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 8 of 15

Ordering and Manufacturing & Delivery activities and also interface required fromClient/PMC. The LSTK Contractor shall also define construction quantity for each activity.LSTK Contractor shall finalise discipline wise Construction ”S” Curves and quantumschedule.

6.3 OVERALL ‘S’ CURVES

The LSTK Contractor shall prepare unit wise and Overall “S” curves showing cumulativeschedule  progress taking into consideration “S” curves for Residual Basic Engineering,Detailed Engineering, Ordering, Manufacturing & delivery, Sub-contracting and Construction“S” Curves. The overall “S” curves shall be updated immediately after finalisation ofconstruction schedule. The overall “S” curves shall be submitted for Client/PMC review, withnecessary back ups and shall form part of monthly progress report.

6.4 OTHER SCHEDULES 

The control philosophy for construction activities involves monitoring at theunit/discipline/subcontract/area level from the initial stages of construction and

supplementing it with monitoring at the system/ loop level as construction advances towardsmechanical completion/ pre-commissioning/ commissioning stages. To meet this objective,the following schedules/deliverables shall be prepared by LSTK Contractor.

6.4.1 SUB CONTRACTOR SCHEDULE

LSTK Contractor shall ensure preparation of detailed schedules for all works in the scope ofeach subcontract awarded by them within two weeks of award of sub-contract, for monitoringof construction progress. These schedules shall have quantity/work load details of all workitems and “S” curve for each of the sub contracts. The LSTK Contractor shall ensureupdation of the same on fortnightly basis. Client/ PMC reserve the right to check theseschedules at any time.

6.4.2 MONTHLY PROGRAMME

LSTK Contractor shall prepare monthly quantitative programmes in line with functionalschedules for all the functions. These programmes shall be made keeping in view thecumulative targets as set in the schedules backlog and work front available in terms ofvendor inputs, drawings, materials and access as applicable. The programmes forconstruction shall be accompanied by list of resources (Manpower & machinery) planned tobe deployed to achieve the programmes. Current hold ups (Drawing, Materials, etc. ifany) required to be resolved for the execution of the programmes made, shall be indicatedwith proposed action plan for resolution.

Monthly programmes other than Construction shall be submitted to Client/PMC DesignOffice within three calendar days of monthly progress report cut-off date. In case of

Construction, monthly programme shall be finalised in consultation with Client/PMC’s siterepresentative and submitted within two calendar days of monthly progress report cut-off date.  In all matters concerning the extent of targets set out in monthly programme, thedecision of Client/PMC shall be final and binding.

The monthly programmes shall be further broken down into weekly programmes andindicated in weekly reports for closer monitoring of progress.

Page 9: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 9/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 9 of 15

6.4.3 LOOPWISE PIPING COMPLETION SCHEDULE

LSTK Contractor shall prepare micro-level schedule for completion of piping activities andsubmit to Client/PMC for review at least two months before the start of hydrotesting asscheduled  in Unit wise Construction schedules. The schedules shall cover unit wise/

system wise/ loop wise, the following activities remaining as of the date of preparation:

a) Status of balance piping materials (Details of items, quantities, vendors, POs andexpected date of receipt at site to be indicated)

b) Status of balance equipment and in-line instrument items (Details of tags, vendors andPOs and expected receipt to be indicated)

c) Welding (inch dia) workload separately for shop fabrication and field welding.d) Erection and supporting (inch meter)e) Radiography (number of joints)f) Stress relieving (number of joints)g) Hydrotesting (inch meter)

6.4.4 SYSTEMWISE COMPLETION SCHEDULE

 After preparation of loop wise micro-level schedule for completion of piping activities, LSTKContractor shall prepare Unit wise/ System wise micro-level schedule for completion ofremaining activities. The schedules shall be submitted by LSTK Contractor to Client/PMCfor review, 6 weeks before scheduled system completion as per Unitwise ConstructionSchedules.  The schedules shall cover disciplinewise remaining activities as mentionedbelow

a) Balance civil and structural work itemwiseb) Balance Mechanical erection work tagwisec) Alignment of Rotating Equipmentd) Balance Electrical worke) Balance Instrumentation works including loop checking

f) Schedule for issue of prescribed formats for handing over of system such as

Format I : Information regarding system completionFormat II : ChecklistFormat III : Ready for pre-commissioning / Mechanical completion certificateFormat IV : Ready for commissioning certificateFormat V : Completion of commissioning certificate

The description of the system and loop numbering mentioned in the schedules at 6.4.3 &6.4.4 above shall be as agreed with Client/PMC (Construction / Commissioning group). Theschedule shall be resource based and shall indicate total and remaining workload for eachactivity.

6.4.5 PRE-COMMISSIONING/COMMISSIONING SCHEDULE

LSTK Contractor shall prepare unitwise / systemwise pre-commissioning/ commissioningmicro-level schedule. These schedules shall be submitted by LSTK Contractor toClient/PMC for review two months before the Mechanical Completion milestone or onemonth before starting pre-commissioning activities, which ever is earlier .

Page 10: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 10/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 10 of 15

The schedules shall be developed after considering the pre-commissioning/ commissioningpriorities & interface requirements and identify requirement of licensor’s/ vendor’srepresentatives stay at site. The description  of system/ sub system mentioned in theschedule shall be as agreed with Client/PMC (Construction/ Commissioning groups).

6.5 CATCH-UP SCHEDULE

The LSTK Contractor shall generate and submit catch-up schedule for completion of allbalance activities without change in contractual completion date with detailed resourcereinforcement as and when asked by Client/PMC. The catch-up schedules shall besubmitted to Client/PMC for review. Accordingly the “S” curves for catch-up schedules shallbe made and shown along with the original schedules and actual “S” curves.

During updation of overall project schedule, the catch-up schedules shall be shown in barcharts along with the original schedule.

7.0 UPDATION OF PROJECT SCHEDULES

The various schedules as described herein shall be updated for submission to Client/PMC.Updation of the schedule is to determine the project trend, with the objective of takingpreventive/ corrective action. The reflection of delayed / anticipated completion by way ofcurrent trend does not in any manner absolve the LSTK Contractor of his contractualobligations as per the contract.

7.1 OVERALL PROJECT SCHEDULE

7.1.1 Overall Project Schedule Network (Detailed)

The schedule shall be updated on monthly basis and submitted in linked bar chart form in A4 size in soft form (native format). The updation shall be compared with the originalschedule.

While updating, the following shall be considered:-   Actual date of start and completion for the activities.-  Contractual completion dates for vendors and sub-contractors/turnkey agencies, any

change of duration due to offloading of vendors/sub-contractors/turnkey agencies to bereflected.

-  Duration of activities not yet started shall remain the same as per the original schedule.-   Anticipated dates of activities in progress.-   Addition/deletion of any activity if required or any change on job logic.-   Any change in drawing/material availability or change in activity duration.-   Any change in resource planning.-  Change in philosophy/strategy in execution of balance works, keeping in mind the

actual status of the project.

7.1.2 Overall Project Schedule Network (Summarised)

The schedule shall be as derived from the updated Overall Project Schedule Network(detailed) as above on monthly basis and submitted in linked bar chart form in A4 size withmonthly progress report. The updation shall be compared with the original schedule. Formatfor updated schedule will be as per Attachment-III page 31 of 37.

Page 11: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 11/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 11 of 15

7.2 FUNCTIONAL SCHEDULES

The updated functional schedule trend and original schedule shall be shown together andsubmitted to client / PMC on monthly basis, as part of Monthly Progress Report.

While updating, the following aspects shall be considered:- Actual dates of start and completion for the activities.- Actual work progress/balance work- Contractual completion date for sub-contractors and vendor delivery not reflected

earlier.- Any change in estimated activity durations- Material and drawing availability- Interfaces of one agency with other agencies- Various statutory reviews/approval- Interfaces between unit & offsite / utilities i.e. permanent power & water, waste

disposal etc.- Any change in execution logic/philosophy and engagement of number of agencies/

sub-contractors and resource planning/ offloading if resorted to.

7.3 OTHER SCHEDULES

The following schedules shall be updated on a weekly basis and submitted to Client/PMCbefore the weekly review meeting at site in bar chart format. The updated schedule trendshall be compared with original schedule.

-  Loopwise piping completion schedule-  Systemwise completion schedule-  Pre-commissioning/commissioning schedule

8.0 REVIEW MEETINGS

The LSTK Contractor shall present project status, project highlights and action plan asapplicable at various review meetings as described below. The presentation materials shallbe submitted by LSTK contractor to Client/PMC at least two days before the date of themeeting for management level review meetings and Monthly/ Fortnightly review meetings.

8.1 Management level Review Meeting

Level of participation : Senior management of client, PMC andLSTK contractor.

 Agenda frequency and venue : to be decided by Client/PMC.

8.2 Monthly/Fortnightly Review Meeting

Level of participation: Client, PMC and LSTK Contractor

 Agenda: 1) Status against various commitments made during the previous reviewmeetings

2) Monthly programme v/s Progress Status/Statistics3) Project Completion Outlook4) Areas of concern with action plan

Page 12: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 12/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 12 of 15

5) Catch-up schedule.

Venue and timing of the meeting shall be decided by Client/PMC. Frequency of Meeting(Monthly or Fortnightly) shall also be decided by Client/PMC, based on criticality of theproject status.

8.3 Weekly Review Meeting

8.3.1 For LSTK Design Office activities

Level of participation: Client, PMC & LSTK Contractor

 Agenda: 1) Weekly programme v/s progress status/Statistics for ResidualBasic Engineering, Detailed Engineering, Ordering,Manufacturing & Delivery and Sub-contracting.

2) Action taken for slippages.3) Programme for next week4) Status of various resources deployed Vs planned

8.3.2 For Site Activities

Level of participation: Client, PMC & LSTK Contractor

 Agenda: 1) Work front availability2) Weekly programme v/s Achievement3) Resource mobilisation4) Reasons for shortfall5) Catch-up Schedule6) Progress statistics7) Programme for next week.8) Status of resources deployed v/s planned.

Venue and timing of Weekly Review Meetings for shall be decided by Client /PMC.

9.0 PROGRESS REPORTING

The LSTK Contractor shall submit the following reports on regular basis for Client/PMC’sinformation/ review.

9.1 Monthly Progress Report

The report shall be submitted on monthly basis within 5 calendar days from cut-off date covering overall scenario of the project. A copy of the specified formats for the report isenclosed as Attachment – III.

9.2 Weekly Progress Report (Overall)

This report shall be prepared by LSTK Contractor and issued on weekly basis toClient/PMC with in three days of the cut off date. The report shall include the following:

•  Executive Summary

•  Project highlights with dates of achievements.

Page 13: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 13/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 13 of 15

•  Project exception (work programmed but not achieved with reasons for non-achievement) and work programmed for next week

•  Critical areas

•  Action taken / to be taken for slippages

•  Progress statistics

•  Activities planned for next week•  Status of Outstanding Documents from Licensor/PMC

This shall cover both for LSTK Contractor’s Design Office activities and constructionactivities at site.

9.3 Weekly Progress Report (Construction)

This report shall be prepared by LSTK Contractor and submitted on weekly basis within 2calendar days from cut off date.  The report shall cover following items:

•  Progress statistics

•  Work item wise quantity completed against programme for the week includingreasons for shortfall

•  Programme for next week

•  Front available

•  Constraints, if any.

•  Resources deployed against planned with reasons for shortfall in resourcedeployment

•  List of equipment/materials received at site during the week

9.4 Daily Progress Report (Construction)

LSTK Contractor shall submit (daily before noon), for status of previous working day adaily report including the following

  Programme v/s Progress for the day  Programme for next day  Important achievements for the day  Materials / Equipment receipt for the day.  Man power / Machinery deployment report - Required v/s Deployed.

9.5 Expediting Report

LSTK Contractor shall submit fortnightly expediting reports based on his representative’svisit to vendor’s work for orders where delivery of materials is critical to project completion. A list of such critical items/vendors shall be specified by Client / PMC during the kick offmeeting or at a later date.

In addition to the above, Client / PMC may request expediting report based on visit of LSTKContractor’s representatives in case of orders which though not critical at the time of orderplacement become subsequently critical during project execution due to any reason.

10.0 BULK MATERIAL CONTROL 

The LSTK Contractor shall follow an integrated material control system for the project. Thesystem shall be such that material identification in the design office, procurement and

Page 14: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 14/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 14 of 15

allocation, are all channelised and controlled in an orderly manner. The LSTK Contractorshall follow material identification like unitwise/system wise/area wise/zone wise/Linewise,and shall give construction orientation to material control. The LSTK Contractor, right fromthe beginning, at the design office stage, shall start identifying materials system wise orarea wise as indicated above. The system shall be based upon tracking of material

requisitioning, placement of purchase order, manufacturing at vendor’s shop up to receiptat site for making the material available for performing planned and sequential constructionwork.

Through periodic reviews, the LSTK Contractor shall have a system of generating Hold upreports  well in advance to identify exception on material availability and to track suchmaterial by the expeditors through a systematic follow up procedure from the vendors.

The LSTK contractor shall make a presentation on the bulk material control systemproposed to be implemented by them for the project during the kick-off meeting.

LSTK Contractor shall submit the following reports on monthly basis for each unit as wellas summary level.

•  Bulk Material Status Report

•  Material hold up/shortage report.

11.0 PLANNING PACKAGE

Details of time of submission, frequency of submission and tentative number of copiesrequired for all documents to be submitted by the LSTK contractor are tabulated inattachment IV.

Once the majority of the schedules are finalized, the LSTK contractor shall compile thesame and submit in the form of a Planning Package. (Not later than 12 weeks of award of

the job). The Planning Package shall consist of the following:

-  Introduction-  Overall Project Schedule Network (Summarised)-  90 days front end schedule-  Project WBS/ Work load-  Progress measurement methodology-  Overall Project schedule Network (Detailed)-  Functional schedules-  Progress ‘S’ curves-  Sample reporting formats-  Manpower and Machinery deployment schedule

LSTK Contractor shall submit reports, updated schedules, programmes etc. as describedherein till the completion of all work in the scope of the contract. No chapter/annexure ofany report shall be deleted without prior written approval of Client/PMC.

12.0 CONTROL ROOM DISPLAY

LSTK Contractor shall have conference room at site to display charts featuring salient staticinformation of the project, schedules, status of progress, resource deployment, rainfall

Page 15: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 15/60

 

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No.8-2744-1003Rev. No. 1

Page 15 of 15

record, block flow diagram, plot plan, work break down structure etc. The status shall beupdated at least on weekly basis. The objectives of the control room are to provideinformation at a glance to project personnel including the management of clients and PMC.

13.0 SOFTWARE PACKAGES 

For schedule preparation and updation, The LSTK contract shall use Internationallyacclaimed network analysis package such as Primavera Project Planner, Project Scheduler,MS Project etc. compatible with that being used by Client/PMC and submit the backup of theschedules (native format) along with the hard copy whenever submission of the schedulesare called for. The electronic files for all other deliverables shall be compatible with MicrosoftOffice.

14.0 PROVISION OF COMPUTER FACILITIES

LSTK Contractor shall provide the following facilities for use by PMC at LSTKContractor’s design office:

 A. PC with latest hardware, A3 size colour laser jet printer and Internet Connection.

B. Software:i) Network Analysis Package such as Primavera Project Planner,

Project Scheduler, MS Project etc.ii) MS Officeiii) E-mail and internet facilities

Page 16: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 16/60

ATTACHMENT - I

 A B C D

SUB-CONTRACTOR SUB-CONTRACTOR SUB-CONTRACTOR SUB-CONTRACTOR

SUB-CONTRACTOR

SCHEDULE SCHEDULE SCHEDULE SCHEDULE

(UNITWISE)

SUB-CONTRACTOR SUB-CONTRACTOR SUB-CONTRACTOR

UNITWISE/DISCIPLINEWISE UNITWISE/DISCIPLINEWISE DELIVERY (UNITWISE)

FOR ENGINEERING FOR ORDERING MANUFACTURING & FOR SUB CONTRACTING

FUNCTIONAL * FUNCTIONAL *

SCHEDULE SCHEDULE SCHEDULE FOR SCHEDULE

(UNITWISE)

FUNCTIONAL * FUNCTIONAL *

 PROJECT SCHEDULE HIERARCHY (TO BE GENERATED BY LSTK CONTRACTOR)

OVERALL PROJECT

SCHEDULE

CONSTRUCTION SCHEDULE

(UNITWISE)

90 DAYS FRONT END

SCHEDULE

(UNITWISE)

PACKAGE

CONTRACTOR

CATCH UP SCHEDULE

(AS APPLICABLE)

CATCH UP SCHEDULE

(AS APPLICABLE)

LEVEL - II

LEVEL - I

LEVEL - III

Page 17: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 17/60

ATTACHMENT- II

WORK BREAKDOWN STRUCTURE (TYPICAL)

UNIT - 1 (CAPACITY,

LICENSORS NAME) VESSELS/ HEAT

REACTORS COLUMNS DRUMS EXCHANGER HEATERS COMPRESSORS

  (HEAT DUTY)

NOS. NOS. NOS. NOS. NOS. NOS.

MATL MATL MATL MATL MATL STR STEEL KW RATING

SIZE & WT MA X. WT & HT MAX. SIZE & WT INDG/IMP REFRACTORY MOTOR/TURBINE DRIVEN

INDG/IMP INDG/IMP INDG/IMP TUBES M/ IN DIA INDG/IMP

BURNER/SOOT BLOWERS

CIVIL/

PUMPS PIPING STRUCTURAL ELECTRICAL INSTN.

NOS. A/G & U/G RCC IN FDN NOS. OF PANELS INSTRNS. IND/IMP

KW RATING (RANGE) KM ----- RCC IN S/STR TRANSFORMERS CONTROL CABLE

MOTOR/TURBINE " DIA BRICK WORK MCC/PCC TUBES

 DRIVEN " MTR STRL STEEL CABLES HT &LT CONTROL PANELS

INDG/IMP MATL LIGHTING

INDG / IMP

UNIT - 2 (CAPACITY,

LICENSORS NAME)

SIMILAR TO UNIT - 1

PROJECT/PLANT

 (CAPACITY)

UNIT - 3 (CAPACITY,

LICENSORS NAME)

SIMILAR TO UNIT - 1

UTILITY /

OFFSITES

  RAW WATER COOLING FIRE DM WATER STEAM NON PLANT

SYSTEM WATER WATER SYSTEM SYSTEM BUILDINMGS

  (CAPACITY) SYSTEM SYSTEM  

PUMPS NO OF CELLS PUMPS CAPACITY BOILER CAPACITY NOS.PIPES PUMPS PIPE QUANTUM OF

  PIPE WORK

  COOLING TOWER

CWTP

STORAGE CIVIL/ YARD CONTROL OTHER UTILITY

W.W.T.P. YARD STRUCTURAL PIPING ELECTRICAL ROOM SYSTEMS INCLUDING

  (SIZE)  C.P.D. (IF ANY)

  TANKAGES RCC A/G SWITCH GEAR CONTROL PANELS

SPHERES STRL STEEL MATERIAL TRANSFORMERS

KM/IM CABLES

NO. OF S/STN.

 

NOTE : ACTUAL QUANTUM / NOS. TO BE WRITTEN.

Page 18: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 18/60

 

 ATTACHMENT - III

CLIENTPROJECT LOCATION

P R O J E C T UNIT (IF APPLICABLE) 

PMC :- M/s. ENGINEERS INDIA LTD., NEW DELHI. 

MONTHLY PROGRESS REPORT 

PROGRESS REPORT NO. XXUPTO____ (DAY) ______ (MONTH)_______ (YEAR) 

(REPORTING CUT-OFF DATE) 

PREPARED BY : LSTK CONTRACTOR 

PAGE 1 OF 37

 

INFORMATION/ACTION 

DATE ISSUED FOR PREPD BY REVIEWED BY APPVD BY 

DOCUMENT NO ___________  

Page 19: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 19/60

NAME OF LSTK CONTRACTCONTRACTOR

PROJECT

MONTH & YEARCLIENTPMC EILPAGE 2 OF 37

TABLE OF CONTENTS

SECTION DESCRIPTION PAGE NO. I INTRODUCTION 3 II EXECUTIVE SUMMARY 4 III DETAILED STATUS 5 IV AREAS OF CONCERN WITH ACTION PLAN 6 V PROGRESS STATISTICS 7 VI MILESTONE STATUS 9 VII PROBLEMS / HOLD-UPS 10 ANNEXURES 

I PROGRESS CURVES 11 

II STATUS REPORTS 

 A CHRONOLOGICAL ACHIEVEMENTS 12B.1 SUMMARY STATUS OF ENGINEERING DRAWINGS 13B.2 DRAWING / DOCUMENT RELEASE SCHEDULE (DCI) 14

  B.3 MATERIAL CONTROL INDEX (MCI) 15  C VENDOR/PACKAGE CONTRACTOR DRAWINGS AND DOCUMENTS STATUS 16  D.1 ORDERING STATUS (SUMMARY) 17  D.2 ORDERING STATUS (DETAILED) 18

E.1 EQUIPMENT DELIVERY STATUS (SUMMARY) 19  E.2 EQUIPMENT RECEIPT AND ERECTION STATUS (DETAILED) 20  E.3 BULK MATERIAL STATUS (SUMMARY) 21  E.4 MANUFACTURING / DELIVERY STATUS 22

F SUB CONTRACTING STATUS  23  G1 UNITWISE STATUS OF CONSTRUCTION QUANTITIES RELEASED 24  G2 QUANTITATIVE MONTHLY CONSTRUCTION PROGRESS STATUS 25

  H STATUS OF CONSTRUCTION 26  I LOOPWISE HYDROTESTING STATUS 27  J SYSTEM HANDING OVER STATUS 28  K.1 UNITWISE DEPLOYMENT OF LSTK PERSONNEL AT CONSTRUCTION SITE 29  K.2 UNITWISE RESOURCE DEPLOYMENT STATUS - EQUIPMENT AND MACHINERY 30

L UPDATED OVERALL PROJECT SCHEDULE 31  M STATUTORY APPROVAL STATUS 32  N INVOICING STATUS 33  O STATUS OF WAIVER / DEVIATIONS 34  P DELAY ANALYSIS 35-36  Q PROJECT PHOTOGRAPHS 37

 III OTHER REPORTS 

OTHER REPORTS SUCH AS

- QUALITY REPORT- HEALTH, SAFETY AND ENVIRONMENT REPORT- COST REPORTS ETC. AS CALLED FOR IN THE OTHER SECTION OF THE BID PACKAGE.

DISTRIBUTION  AS PER DISTRIBUTION LIST IN CONTRACT. 

Page 20: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 20/60

NAME OF LSTK CONTRACTCONTRACTOR

PROJECT

MONTH & YEARCLIENT

PMC : EIL

Page 3 of 37

I - INTRODUCTION

CLIENT :

PROJECT LOCATION :

PMC : M/s. EIL, NEW DELHI

DESIGN CAPACITY :

UNIT CAPACITY LICENSOR

CONTRACT VALUE : _____Rs.(IN CRORES)

SCOPE OF WORK :

PROJECT TARGET DATES (UNIT WISE)

EFFECTIVE START DATE :

TARGET COMPLETION DATE :

CONTRACTUAL COMPLN DATE :

CONTRACTUAL COMMNG DATE :

(If Applicable)

ANT. MECH COMPLN DATE :

ANT. COMMG DATE :

(If Applicable)

PROJECT DURATION :_________ MONTHS

TIME ELAPSED :__________MONTHS 

Page 21: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 21/60

NAME OF LSTK CONTRACTCONTRACTOR

PROJECT

MONTH & YEARCLIENT

PMC : EIL

Page 4 of 37

 

II - EXECUTIVE SUMMARY

EXECUTIVE SUMMARY SHALL SERVE AS SYNOPSIS OF THE PROJECT. IT NEEDS TOFOCUS ON THE FOLLOWING :

- OVERALL SCHEDULE AND ACTUAL PROGRESS TO BE SPECIFIED(CUMULATIVE AND DURING THE MONTH)

-  LIMIT IT TO ONE PAGE AS FAR AS POSSIBLE.

-  MAJOR MILESTONES ACHIEVED DURING THE MONTH.

-  CONTINGENCY/ CRASH ACTION PLAN FOR MOST CRITICAL AREAS, IF ANY,

BEING FORMULATED / IMPLEMENTED.

- SIGNAL FOR THE AREAS LIKELY TO BECOME CRITICAL.

- ANY OTHER ISSUE NOT LISTED ABOVE. 

Page 22: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 22/60

NAME OF LSTK CONTRACTCONTRACTOR

PROJECT

MONTH & YEARCLIENT

PMC : EIL

Page 5 of 37

III - DETAILED STATUS (UNITWISE / DISCIPLINEWISE) 

A. RESIDUAL BASIC ENGINEERING 

- ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH 

B. DETAILED ENGINEERING - ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH

C. PROCUREMENTi) ORDERING

- ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH

ii) MFG/DELIVERY- ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH 

D. SUB-CONTRACTING- ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH 

E. CONSTRUCTION /PRE-COMMISSIONING & COMMISSIONING- ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH 

F. PACKAGE SUB-CONTRACTOR STATUSPACKAGE SUB-CONTRACTORWISE STATUS TO BE GIVENFUNCTIONWISE AS APPLICABLE)

i) ENGINEERINGii) ORDERINGiii) MANUFACTURING & DELIVERYiv) CONSTRUCTION

- ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH 

Page 23: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 23/60

NAME OF LSTK CONTRACT MONTH & YEAR

CONTRACTOR CLIENT

PROJECT PMC : EIL

PAGE 6 OF 37

IV - AREAS OF CONCERN WITH ACTON PLAN

 (UNITWISE / DISCIPLINEWISE)

SR. IMPACT ON ACTION TARGET

NO. AREAS OF CONCERN CONSTRAINTS SCHEDULE ACTION PLAN BY DATE(IN MONTHS)

NOTE

1. THIS SHALL CONTAIN ONLY CRITICAL ITEMS/ISSUES WHICH ARE DIRECTLY AFFECTING THE PROJECT SCHEDULE

OTHER ITEMS CAN BE PLACED IN PROBLEMS & HOLD UPS CHAPTER.

2 TARGET DATES SHALL BE FURNISHED WITH ACTION PLAN.

Page 24: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 24/60

 NAME OF LSTK CONTRACT

CONTRACTOR

 PROJECT

V - PROGRESS STATISTICS

A OVERALL PROJECT PROGRESS

DESCRIPTION WTD % AGE DURING THE MONTH CUMULATIVE

COMPLEX SCHEDULE ACTUAL SCHEDULE ACTUAL

RESIDUAL BASIC ENGINEERING

DETAILED ENGINEERING

ORDERING

MANUFACTURING/DELIVERY

SUB-CONTRACTING

CONSTRUCTION

COMMISSIONING

OVERALL PROGRESS - PHYSICAL Σ Α=100%

B. PROCESS UNIT (UNITWISE)

B.1 UNIT NAME

DESCRIPTION WTD % AGE DURING THE MONTH CUMULATIVE

COMPLEX UNIT SCHEDULE ACTUAL SCHEDULE ACTUAL

RESIDUAL BASIC ENGINEERING

DETAILED ENGINEERING

ORDERING

MANUFACTURING/DELIVERY

SUB-CONTRACTING

CONSTRUCTION

COMMISSIONING

 PHYSICAL PROGRESS UNIT- A1 A1 % 100

B.2 UNIT NAME

B.3 UNIT NAME

B.4 UTILITIES /OFFSITES

DESCRIPTION WTD % AGE DURING THE MONTH CUMULATIVE

COMPLEX UNIT SCHEDULE ACTUAL SCHEDULE ACTUAL

RESIDUAL BASIC ENGINEERING

DETAILED ENGINEERING

ORDERING

MANUFACTURING/DELIVERY

SUB-CONTRACTINGCONSTRUCTION #

COMMISSIONING

  PHYSICAL PROGRESS

UTILITIES /OFFSITESA4 % 100

MONTH & YEAR

CLIENT

PMC : EIL

PAGE 7 OF 37

Page 25: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 25/60

  NAME OF LSTK CONTRACT

CONTRACTOR

 PROJECT

C. SUB CONTRACTED PACKAGES (PROCESS UNIT,UTILITIES & OFFSITES) C.1 PACKAGE - 1

DESCRIPTION WTD %AGE DURING THE MONTH CUMULATIVE

w.r.t U/OFF UNIT SCHEDULE ACTUAL SCHEDULE ACTUAL

 RESIDUAL BASIC ENGINEERING

DETAILED ENGINEERING

ORDERING

 MANUFACTURING & DELIVERY

 CONSTRUCTION

 COMMISSIONING

 PHYSICAL PROGRESS RWTP X1 100

 C.2 PACKAGE - 2

 C.3 PACKAGE -3

D. MAJOR REASONS FOR SHORTFALL

NOTE:

  3. UNIT WISE ALL SUBCONTRACTED PACKAGES TO BE REPORTED UNDER SUBHEADING "SUB CONTRACTED PACKAGE".

  4. # CONSTRUCTION INCLUDES %AGE PROGRESS OF SUB-CONTRACTED PACKAGES IF ANY IN THE RESPECTIVE UNIT /

  OFFSITES & UTILITIES AS DETAILED IN THE ANNEXURE TO CONSTRUCTION PROGRESS.

  1. WHEREIN THE GAP BETWEEN SCHEDULE & ACTUAL %AGE PROGRESS IS MORE THAN 5 % , EXPLANATION

FOR THE BACK LOG/GAP REQUIRED TO BE FURNISHED IN THIS SHEET.

  2. ALL COMPONENTS OF THE PROJECT IN LSTK CONTRACTOR'S SCOPE AS PER THE CONTRACT, SHOULD BE REPORTED IN

IN THE PROGRESS STATISTICS.

MONTH & YEAR

CLIENT

PMC : EIL

PAGE 8 OF 37

Page 26: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 26/60

NAME OF LSTK CONTRACT

CONTRACTORPROJECT

VI. MILESTONE STATUS

 (CURRENT + 2 MONTHS)

STATUS AS ON :

S. MILESTONE DESCRIPTION SCHEDULE LATEST ACTUAL FORECAST STATUS/

NO.DATE

ALLOWABLE

DATEDATE DATE REMARKS

1 GENERAL

2 UNIT

2.1 RESIDUAL BASIC ENGINEERING

2.2 DETAILED ENGINEERING

2.3 PROCUREMENT

a) ORDERING

b) MANUFACTURING & DELIVERY

2.4 SUB-CONTRACTING

2.5 CONSTRUCTION

2.6 PRECOMMISSIONING

2.7 COMMISSIONING

NOTE : ALL MILESTONES (UNIT WISE AND FUNCTION WISE) AS AGREED DURING KICK OFF MEETING ARE TO BE LISTED.

MONTH & YEAR

CLIENT

PMC : EIL

PAGE 9 OF 37

Page 27: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 27/60

NAME OF LSTK CONTRACT MONTH & YEAR

CONTRACTOR CLIENT

PROJECT PMC : EIL

PAGE 10 OF 37

VII - PROBLEMS / HOLD-UPS

 (UNIT WISE / DISCIPLINE WISE)

SR.

NO.PROBLEM / HOLD-UPS ACTION PLAN ACTION BY TARGET DATE

1

2

3

4

5

NOTE : ONLY POINTS WHICH AFFECT THE PROGRESS BUT MAY NOT

  HAVE THE IMPACT ON THE PROJECT SCHEDULE SHALL BE LISTED HERE.

Page 28: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 28/60

NAME OF LSTK CONTRACT MONTH & YEAR

CONTRACTOR CLIENT

PROJECT MC : EIL

  PAGE 11 0F 3

ANNEXURE - I (A)

NOTE :

2. OVERALL (AT CONTRACT LEVEL) SEPARATELY FOR EACH FUNCTION AND ONE CURVE FOR PHYSICAL PROGRESS

1. UNIT WISE SEPARATE CURVE FOR EACH FUNCTION AND CURVE FOR PHYSICAL PROGRESS

PROJECT - (Name of contract)FUNCTION / PHYSICAL

0

10

20

30

40

50

60

70

80

90

100

   C   U   M   U   L   A   T   I   V   E   %    P

   R   O   G   R   E   S   S

0

5

10

15

20

25

30

35

40

45

   M   O   N   T   H   L   Y   %    P

   R   O   G   R   E   S   S

SCH DURING THE MONTH 0 10 42.5 14.5 ACT. DURING THE MONTH 0 15 24 19

CUMM. SCH 5 15 57.5 72 80 85 90 95 100

CUMM. ACT 3 18 42 61

D'00 J'01 F'01 M'01 A'01 M'01 J'01 J'01 A'01

Page 29: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 29/60

  NAME OF LSTK CONTRACT

CONTRACTOR

  PROJECT

 ANNEXURE - II (A)

CHRONOLOGICAL ACHIEVEMENTS

S. NO. DESCRIPTION OF KEY MILESTONES SCH. DATE ACTUAL DATE OF

OCCURRENCE

 1. GENERAL

 2. UNITWISE (AS APPLICABLE)

 2.1 RESIDUAL BASIC ENGINEERING

 2.2 DETAILED ENGINEERING

 2.3 ORDERING

 2.4 MANUFACTURING & DELIVERY

 2.5 SUB-CONTRACTING

 2.6 CONSTRUCTION

 2.7 SUB-CONTRACTED PACKAGES

2.8 PRECOMMISSIONING

2.9 COMMISSIONING

NOTE : MECHANICAL COMPLETION & COMMISSIONING DATES SHALL

ALSO BE RECORDED.

MONTH & YEAR

CLIENT

PMC : EIL

PAGE 12 OF 37

Page 30: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 30/60

  NAME OF LSTK CONTRACT MONTH & YEAR

  CONTRACTOR CLIENT

PROJECT EIL

PAGE 13 OF 37

ANNEXURE :II (B.1)

SUMMARY STATUS OF ENGINEERING DRAWINGS

 (SUMMARY LEVEL & UNIT WISE SEPARATELY)

TOTAL DRAWINGS RELEASED (NOS.) REVIEW STATUS (NOS.) SUBMISSION PROGM.

DISCIPLINE DRAWINGS DURING THE MONTH CUMULATIVE TOTAL DRGS. CO DE 1 C ODE 2 C ODE 3 FOR NEXT MONTH REMARKS

NOS. SCH. ACT. SCH ACT FOR REVIEW FRESH CODE 3

  ARCHITECTURAL

 GENERAL CIVIL

  STRUCTURAL

 PIPING

GAD's

ISO's

 ELECTRICAL

 INSTRUMENTATION

TOTAL

Page 31: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 31/60

NAME OF LSTK CONTRACT

CONTRACTOR

 PROJECT

PROJECT NAME

USE WTD. DRAFT CHECK IST % WTD REV.

CODE VALUE COMPL. COMPL. SUBM. CODE 2 CODE 1 PROG. PROG. CODE

 * * * * *

SCH.A/F

SCH. A/F

SCH. A/FSCH. A/FSCH. A/FSCH. A/F

SCH. A/F

SCH. A/F

LEGEND I: INFORMATION R: REVIEW A : APPROVALS : STUDY A: STATUTORY / CLIENT REVIEWP: PURCHASE C: CONSTRUCTIONT: TENDERING L: CALCULATION

NOTE : 1. INDICATE A/F (ACTUAL / FORECAST)AS APPLICABLE WITH THE DATES.

2. * PERCENTAGE FOR AGREED MILESTONES AS PER PROGRESS MEASUREMENT METHODOLOGY.

3. THIS INCLUDES PROCESS / BASIC ENGG. DELIVERABLES.

REMARKS

  CATEGORY (CAT.):

  USE CODE :-

DRAWING / DOCUMENT TITLEDRG. NO. CAT.

REV

.

NO.

MILESTONESREVIEW

DISCIPLINE : PROCESS

DRAWINGS / DOCUMENTS RELEASE SCH. (DCI)

  (UNITWISE / DISCIPLINEWISE)

ANNEXURE - II(B.2)

STATUS AS OF : DD/MM/YYYY

MONTH & YEAR

CLIENT

PMC : EIL

Page 14 of 37

Page 32: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 32/60

MONTH & YEAR

CLIENT

PMC : EIL

PAGE : 15 OF 37

MCI: MATERIAL CONTROL INDEX (UNIT WISE / DISCIPLINE WISE)ANNEXURE : II (B.3)

STATUS AS ON: DD/MM/YY 

ISSUE OF MR PREPARE TBA PREP OF PR

APPROVAL OF

PR / 1ST REVIEW

OF VENDOR

DRGS

APPROVAL OF

VENDOR

DRGS/DOCS

REMARKS / REASONS FOR DELAY 

20% 30% 10% 10% 30%

<DISCIPLINE>1 SCH

 ACT/FORECAST

2 SCH ACT/FORECAST

3 SCH

 ACT/FORECAST

4 SCH

 ACT/FORECAST

5 SCH

 ACT/FORECAST

6 SCH

 ACT/FORECAST

7 SCH

 ACT/FORECAST

8 SCH

 ACT/FORECAST

9 SCH

 ACT/FORECAST

10 SCH

 ACT/FORECAST

11 SCH

 ACT/FORECAST

12 SCH

 ACT/FORECAST

13 SCH

 ACT/FORECAST

14 SCH ACT/FORECAST

15 SCH

 ACT/FORECAST

TOTAL SCH ______%

 ACT/FORECAST ______%

LEGEND: CATEGORY (CAT.) : I : INFORMATION R : REVIEW A : APPROVAL

S : STUDY A : STATUTORY / CLIENT REVIEW

USE CODE :- P : PURCHASE C : CONSTRUCTION

T : TENDERING L : CALCULATION

NOTE : 1. INDICATE A/F (ACTUAL / FORECAST) AS APPLICABLE WITH THE DATES.

2. * PERCENTAGE FOR AGREED MILESTONES AS PER PROGRESS MEASUREMENT METHODOLOGY.

3. THIS INCLUDES PROCESS / BASIC ENGG. DELIVERABLES.

S. NODRAWING/DOCUMENT

NUMBER 

NAME OF LSTK CONTRACT :

CONTRACTOR :

PROJECT :

WEIGHTED

PROGRESS

CATERG

ORY

(A/R/I)

WTD

 VALUE

DRAWING / DOCUMENT

DESCRIPTION

PLEASE REFER

ANNEXURE :

II (C)

Page 33: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 33/60

NAME OF LSTK CONTRACT

CONTRACTOR

 PROJECT

ANNEXURE - II(C)

PROJECT NAME

SL WTD. REV. NO. REVIEW PROG REMARKS &

NO VALUE CODE Ist SUBM. REV. CODE-2 CODE-1 (%) STATUS

 * * *

NOTE :

2. ALL VENDOR / PACKAGE CONTRACTOR DRAWINGS DOCUMENTS TO BE LISTED.

1. * - AGREED MILESTONE PERCENTAGE

DRG. NO. DESCRIPTION

DATE

ENDOR / PACKAGE CONTRACTOR NAME : ……………………….

VENDOR/PACKAGE CONTRACTOR DRAWINGS & DOCUMENTS STATUS  (UNITWISE / DISCIPLINEWISE)

STATUS AS OF : DD/MM/YYYY

MONTH & YEAR

CLIENT

PMC : EIL

PAGE 16 OF 37

Page 34: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 34/60

NAME OF LSTK CONTRACT

CONTRACTOR

PROJECT

UNIT NAME / SUMMARY LEVEL

ANNEXURE : II (D.1)

ORDERING STATUS (SUMMARY)

(LOCAL(INDIAN) & FOREIGN PROCUREMENT SEPARATELY)

TOTAL MR ISSUE BIDS FOI/TOI PO

CATEGORYMRs ISSUED ENQUIRY DUE ISSUED ISSUED

SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT

  EQUIPMENT

COLUMNS

 EXCHANGERS

TOTAL

BULK

TOTAL

NOTE :

2. SEPERATE STATUS FOR EACH UNIT AND AT PROJECT SUMMARY LEVEL.

1. NUMBER OF MRs SHALL BE PROVIDED FOR EACH MILESTONE AGAINST EACH EQUIPMENT CATEGORY AS COLUMN,

EXCHANGERS, PUMPS ETC. AND BULK MATERIAL.

MONTH & YEAR

CLIENT

PMC : EIL

PAGE: 17 OF 37

Page 35: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 35/60

NAME OF LSTK CONTRACT MONTH & YEAR

CONTRACTOR CLIENT

PMC : EIL

 PROJECT PAGE: 18 OF 37

UNIT_______________ 

DESCRIPTION WTD. CAT MR ISSUE RECV TBA FOI/TOI PO L/C % VENDOR/ PO NO. PR REV. REV. CDD

MR NO. ITEM NO. VAL. RELS ENQ. BIDS ISSUED ISSUE ISSUE OPEN PROG LOCATION /DATE REVIEW CODE 2 CODE REMARKS

DATE

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

1. INDICATE A/F (ACTUAL/FORECAST) AS APPLICABLE WITH THE DATES

2. CONTRACTUAL DELIVERY DATE (CDD) IS TO BE QUALIFIED IN REMARKS COLUMN

(I.E EX WORKS, FOT, FOB, AT SITE ETC.)

NOTE :

MECHANICAL

ORDERING STATUS (DETAILED)

 (DISCIPLINEWISE FOR EACH UNIT)

ANNEXURE - II(D.2)

Page 36: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 36/60

  NAME OF LSTK CONTRACT

CONTRACTOR

  PROJECT

  UNIT / SUMMARY * ANNEXURE: II(E.1)

EQUIPMENT DELIVERY STATUS (SUMMARY)

EQUIPMENT TOTAL QTY IN DELIVERY FORECAST AT SITE FOR BAL. EQPT.

DESCRIPTION NOS DESPATCHED TRANSIT CALENDAR MONTHS --------->

SCH. ACT. (NOS.) SCH. ACT (NOS.) 1 2 3 4 5 6

  COLUMNS

  VESSELS

  REACTORS

  EXCHANGERS

  AIR COOLERS

  PUMPS

  COMPRESSORS

  FANS

  MISC. (MAJOR CRITICAL ITEMS)

TOTAL

NOTE 1. STATUS FOR INDEGENOUS AND IMPORTED EQUIPMENT SHALL BE FURNISHED SEPARATELY

2. * SEPARATE STATUS FOR EACH UNIT AND AT SUMMARY LEVEL.

QUNTITY ORDERED

(NOS.)RECEIVED AT SITE (NO.)

MONTH & YEAR

CLIENT

PMC : EIL

PAGE: 19 OF 37

Page 37: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 37/60

  NAME OF LSTK CONTRACT

CONTRACTOR

  PROJECT

  UNIT / SUMMARY * ANNEXURE: II(E.2)

EQUIPMENT RECEIPT AND ERECTION STATUS (DETAILED)

 (UNITWISE/DISCIPLINEWISE))

PO NO. EQPT EQUIPMENT ERECTION ENDOR NAME C.D.D DESPATCHED RECEIVED SITE FDN STRL. ERECTION HYDROTESTING

TAG NO. DESCRIPTION WT. LOCATION, ON AT SITE ASSEMBLY READY READY DATE DATE PAINTING NSULATION FIRE

 ( MT) COUNTRY (IF ANY) DATE DATE PROOFING

  COLUMNS

a)

b)

  VESSELS

  REACTORS

  EXCHANGERS

  AIR COOLERS

  PUMPS

  COMPRESSORS

  FANS/BLOWERS

 OTHER ITEMS

  ELECTRICAL EQUIPMENTS

NOTE : 1. ALL EQUIPMENT TO BE COVERED. TAGGED ITEMS WITH MULTIPLE SUFFIXES TO BE MENTIONED SEPARATELY. e.g 701-E-03 701-E-0 701-E-03C

  2. * SEPARATE STATUS FOR UNIT AND AT SUMMARY LEVEL.

REQD. ATSITE (SCH,)

MONTH & YEAR

CLIENT

PMC : EIL

a e: 20 of 3

Page 38: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 38/60

NAME OF LSTK CONTRACT

CONTRACTOR

 PROJECT

UNIT NAME / SUMMARY LEVEL * ANNEXURE - II (E.3)

BULK MATERIAL STATUS (SUMMARY)

  ( LOCAL (INDIAN) AND FOREIGN PROCUREMENT SEPARATELY) STATUS AS OF : _______ 

  QUANTITY FORECAST FOR

S.NO. ITEMWISE DESCRIPTION UOM TOTAL ORDERED RELEASED RECEIVED BALANCE STATUS/PROBLEMS

  REQUIREMENT AT SITE DELIVERY

1 2 3 4 5

1 PIPES M

2 FITTINGS No.

3 FLANGES No.

4 VALVES No.

5 ELECTRICAL ITEMS (ALL)

  ALL ITEMS

6 INSTRUMENTATION ITEMS

  ALL ITEMS

NOTE : 1. SEPARATE STATUS FOR EACH UNIT AND AT SUMMARY LEVEL.

2. STATUS TO BE GIVEN SEPARATELY FOR LOCAL (INDIAN) AND IMPORTED PURCHASE.

MONTH & YEAR

CLIENT

PMC : EIL

PAGE: 21 OF 37

Page 39: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 39/60

NAME OF LSTK CONTRACT MONTH & YEAR

CONTRACTOR CLIENT

PMC : EIL

 PROJECT PAGE : 22 OF 37

ANNEXURE - II(E.4)

PROJECT NAME STATUS AS OF : DD/MM/YYYY

TAG NO./ DESCRIPTION WTD PO VENDOR/ INSPN ORDER RELSD RECD VENDOR RAW RAW MFG MFG FINAL CDD FOB/EX ARRIVAL ARRIVAL SITE %

ITEM OF ITEM VAL NO. LOCATION/ CAT QTY QTY QTY DRG MATL. MATL START FINISH INSPN WORKS INDIAN AT REQD PROG REMARKS

& COUNTRY REV. S/O RECPT DELY PORT SITE DATE

DATE * * * * * * * * *

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

* - AGREED MILESTONE PERCENTAGE

INSPECTION CATEGORY ;- AS DESCRIBED IN INSPECTION METHODOLOGY. A/F :- ACTUAL / FORECAST

NOTE : 1 INDICATE A/F AS APPLICABLE WITH THE DATES (A/F :- ACTUAL / FORECAST)

2 BULK ITEMS LIST SHOULD INCLUDE PIPING, ELECTRICAL AND INSTRUMENTATION ITEMS.

3 IN CASE OF IMPORTED SHIPMENT NAME OF THE VESSEL AND PORT OF BOARDING TO BE INDICATED.

4 CONTRACTUAL DELIVERY DATE (CDD) IS TO BE QUALIFIED IN REMARKS COLUMN

(I.E. EX WORKS, FOT, FOB, AT SITE (AS APPLICABLE) ETC.)

INSPN. CAT.-

  LEGEND

 (LOCAL (INDIAN) AND FOREIGN PROCUREMENT SEPARATELY)

MANUFACTURING / DELIVERY STATUS(UNITWISE / DISCIPLINEWISE/ TAGWISE)

Page 40: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 40/60

NAME OF LSTK CONTRACT MONTH & YEAR

CONTRACTOR CLIENT

PMC : EIL

PROJECT PAGE: 23 OF 37

ANNEXURE - II(F)

UNIT :

DESCRIPTION WTD ISSUE OF PREPARATION TENDER RECEIPT AWARD NAME DURATION CONTRACTUAL INTERMEDIATE

OF WORK VALUE TENDER OF TENDER ON OF BIDS OF %AGE OF OF COMPLETION CONTRACTUAL REMARKS

SPECS DOCUMENT SALE WORK PROGRESS AGENCY CONTRACT DATE MILESTONES

* * * * * (IF ANY)

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

SCH.

 A/F

A/F :- ACTUAL/FORECAST

NOTE : 1. INDICATE A/F AS APPLICABLE WITH THE DATES.

  * - AGREED MILESTONE PERCENTAGE

STATUS AS OF : DD/MM/YYYY

SUB-CONTRACTING STATUS

Page 41: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 41/60

NAME OF LSTK CONTRACT

CONTRACTOR

 PROJECT

UNIT ______________ ANNEXURE : II(G.1)

UNITWISE STATUS OF CONSTRUCTION QUANTITIES RELEASED ( DISCIPLINEWISE FOR EACH UNIT)

S. DISCIPLINE & LIKELY CUM BALANCE PROGRAMME FOR BALANCE QTY UNDER HOLDNO. MAJOR WORK ITEM UOM QTY RELEASED QTY TO BE  MONTHS AND REASON FOR THE SAME

QTY RELEASED 1 ST 2ND 3RD 4TH 5TH 6TH

UOM : UNIT OF MEASUREMENT.

MONTH & YEAR

CLIENT

PMC : EIL

PAGE: 24 OF 37

Page 42: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 42/60

NAME OF LSTK CONTRACT

CONTRACTOR

PROJECT

UNIT : ____________ 

QUANTITATIVE MONTHLY CONSTRUCTION PROGRESS STATUS ( UNITWISE/DISCIPLINEWISE)

ANNEXURE :II(G.2)

WORK ITEM UNIT OF TOTAL QUANTITY PROGRAM

DESCRIPTION MEASU- CUMMULATIVE DURING THE MONTH FOR NEXT

REMENT WORKLOAD FRONT COMPLETED PROGRAMME COMPLETED BACKLOG MONTH

EXCAVATION CM

BACK FILLING CM

RCC WORKS CM

BRICK WORK CM

 A/G PPG - FAB ID

 A/G PPG - ERN IM

U/G PPG - FAB ID

U/G PPG - ERN IM

INSTRUMENTATION

- LOOPCHECKING NOS

PERCENTAGE PROGRAMMED DURING THE MONTH :

PERCENTAGE ACHIEVED DURING THE MONTH : FRONT:

PERCENTAGE PROGRAMMED FOR NEXT MONTH : ACTUAL:

CUM. PERCENTAGE PROGRESS SCHEDULE :

MONTH & YEAR

CLIENT

PMC : EIL

PAGE: 25 OF 37

Page 43: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 43/60

NAME OF LSTK CONTRACT MONTH & YEAR

CONTRACTOR CLIENT

PMC : EIL

 PROJECT PAGE : 26 OF 37

UNIT :_______________  ANNEXURE : II (H)

SR. AGENCY DURATION CONTRACTUAL ACTUAL ACT/ANT CUM. % ACHIEVED

NO. SCOPE OF WORK (MONTHS) START COMPLN START COMPLN MONTHLY PROGRESS CONTRACTUAL FRONT* ACTUAL

DATE DATE DATE SCH. PROGM ACT. SCH AVAILABLE

SUMMARY

NOTE : 1. * FRONT INDICATES WORK THAT CAN BE TAKEN UP CONSIDERING AVAILABILITY OF DRAWINGS, MATERIALS AND ACCESS.

STATUS OF CONSTRUCTION

Page 44: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 44/60

NAME OF LSTK CONTRACT MONTH & YEARCONTRACTOR   CLIENT

PMC : EIL PROJECT PAGE : 27 of 37

UNIT :__________________ ANNEXURE : II (I)

  LOOPWISE HYDROTESTING STATUS

NO. OF LOOPS

HYDROTESTED LOOPS UNDER HOLD REMARKS

THIS MONTH CUMULATIVE MATERIAL ERECTION TOTAL

SCH. ACT. SCH. ACT.

 1.0 UNIT I 100 50 30 20 20 20 15 5 20 10 35 15 50

SERVICEWISE /

SYSTEMWISE

 

2.0 UNIT II

SERVICEWISE /

SYSTEMWISE

 3.0 OFFSITES PART A

SERVICEWISE

 4.0 OFFSITES PART B

SERVICEWISE

5.0 PACKAGES

SERVICEWISE

TOTAL

NOTE : REPORTING SHALL START AFTER PREPARATION OF LOOPWISE PIPING COMPLETION SCHEDULE

CHECK

LISTED

MECH.

CLEARED

RADIO-

GRAPHY

CLEARED

SR

CLEARED

FRONT

AVAILABLE

SR.

NO.DESCRIPTION

TOTAL

Page 45: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 45/60

NAME OF LSTK CONTRACT MONTH & YEAR

CONTRACTOR CLIENT

PMC : EIL

PROJECT PAGE : 28 OF 37

UNIT : ______________  ANNEXURE : II (J)

SYSTEM HANDING OVER STATUS (UNITWISE)

S.NO. SYSTEM DESCRIPTION FORMAT I ISSUE DATE FORMAT II ISSUE DATE FORMAT III ISSUE DATE FORMAT IV ISSUE DATE FORMAT V ISSUE DATE

A. SYSTEM I TARGET DATE

ACTUAL DATE

B. SYSTEM II TARGET DATE

ACTUAL DATE

C. SYSTEM III TARGET DATE

ACTUAL DATE

TARGET DATE

ACTUAL DATE

TARGET DATE

ACTUAL DATE

GRAND TOTAL TARGET (NOS.)

  ACTUAL (NOS.)

LEGEND :

FORMAT I : INFORMATION REGARDING SYSTEM COMPLETIONFORMAT II : CHECKLIST

FORMAT III : READY FOR PRE-COMMISSIONING \ MECH COMPLENTION CERTIFICATE

FORMAT IV : READY FOR COMMISSIONING CERTIFICATE

FORMAT V : COMPLETION OF COMMISSIONING CERTIFICATE

NOTE : 1. TO BE FURNISHED SEPARATELY FOR EACH UNIT

2. REPORTING SHALL START AFTER PREPARARTION OF SYSTEMWISE COMPLETION SCHEDULE

Page 46: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 46/60

  NAME OF LSTK CONTRACT

CONTRACTORS

  PROJECTANNEXURE - II(K.1)

 (1) LABOUR (2) MANAGEMENT & SUPERVISION

   F   O   R   E   M   A   N

   C   A   R   P   E   N   T   E   R   S

   B   A   R   B   E   N   D   E   R

   M   A   S   O   N   S

   B   A   T   C   H   P   L   A   N   T   L   A   B .

   W   E   L   D   E   R   S  -   S   T   R   L .

   W   E   L   D   E   R   S  -   P   I   P   E

   R   I   G   G   E   R   S

   P   I   P   E   /   F   A   B   N .   F   I   T   T   E   R   S

   G   A   S   C   U   T   T   E   R

   G   R   I   N   D   E   R   S

   E   L   E   C   T   R   I   C   I   A   N

   I   N   S   T .   F   I   T   T   E   R   S

   I   N   S   U   L   A   T   O   R   S

   O   P   E   R   A   T   O   R   /   D   R   I   V   E   R

   S   C   A   F   F   O   L   D   E   R   S

   S   T   R   L .   E   R   E   C   T   O   R   S

   P   A   I   N   T   E   R   S

   S   T   R   L .   F   I   T   T   E   R   S

   I   N   S   T   R .   T   E   C   H   N   I   C   I   A   N   S

   M   I   L   L   W   R   I   G   H   T   F   I   T   T   E   R   S

   M   E   C   H   A   N   I   C   S

   S   A   N   D   B   L   A   S   T   E   R   S

   C   R   A   N   E   O   P   E   R   A   T   O   R   S

   T   A   C   K   W   E   L   D   E   R   S

   F   A   B   R   I   C   A   T   O   R   S

   D   R   I   L   L   E   R   S

   G   U   N   I   T   O   R

   L   A   G   G   E   R   S

   U   N   S   K   I   L   L   E   D   L   A   B   O   U   R

   O   T   H   E   R   S

   S   U   B   T   O   T   A   L  :   (   1   )

   M   A   N   A   G   E   R   S

   E   N   G .   D   E   P   T .

   A   D   M   N .   D   E   P   T .

   P   R   O   J   E   C   T   C   O   N   T   R   O   L

   Q   A   /   Q   C   D   E   P   T .

   S   I   T   E   E   N   G .

   S   I   T   E   S   U   P   E   R   V   I   S   O   R   S

   S   A   F   E   T   Y   D   E   P   T .

   S   U   R   V   E   Y   O   R   S

   O   T   H   E   R   S

   S   U   B   T   O   T   A   L  :   (   2   )

   G   R   A   N   D   T   O   T   A   L  :   (   1   )   +   (   2   )

PLAN

ACT

PLAN

ACT

PLAN

ACT

PLAN

ACT

GRAND PLAN

TOTAL ACT

 NOTE : REASON FOR DEVIATION BETWEEN MONTHLY CONSTRUCTION PROGRAMME AND ACTUAL TO BE MENTIONED. (USE SEPARATE SHEET IF NECESSARY)

   P   L   A   N   /   A   C   T

 NAME OF UNIT

UNITWISE DEPLOYMENT OF LSTK PERSONNEL AT CONSTRUCTION SITEMONTHLY CONSTN. PROGRAMME(%):

MONTHLY CONSTRN. ACTUAL (%) :

MONTH & YEAR

CLIENT

PMC : EIL

PAGE 29 OF 37

Page 47: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 47/60

NAME OF LSTK CONTRACT

CONTRACTOR

 PROJECT

UNITWISE RESOURCE DEPLOYMENT STATUS ( FOR THE MONTH OF : ___________)

EQUIPMENT & MACHINERY ANNEXURE : II (K.2)

SL NO NAME OF UNIT

   E   Q   U

   I   P   M   E   N   T   /   M   A   C   H   I   N   E   R   Y

   E   X   C   A   V   A   T   O   R   S

   D   U   M   P   L   O   A   D   E   R   S

   C   O   N   C   M   I   X   E   R   S

   D   O   Z   E   R   S

   W   A   T   E   R   T   A   N   K   S

   D

   G   S   E   T   S   1   2   5   /   8   2 .   5   K   W

   D   W    P

   U   M   P   S

   R   O   L   L   I   N   G   M   A   C   H   I   N   E   S

   J   A   C   K

   H   A   M   M   E   R   S

   C   O   M   P   R   E   S   S   O   R   S

   C   O   M   P   A   C   T   O   R   S

   V   I   B   R   A   T   O   R   S

   W   E   L   D   I   N   G   M   A   C   H   I   N   E

   C   O

   A   T   I   N   G   /   W   R   A   P   P   I   N   G   M   /   C

   R   O   A   D   R   O   L   L   E   R   S

   V   I   B   R   O   R   O   L   L   E   R   S

   P   A   Y   L   O   A   D   E   R   S

   P   I   P   E   B   E   N   D   I   N   G   M   /   C

   D   R   I   L   L   I   N   G   M   /   C   R   I   G   S

   R   O   C   K   B   R   E   A   K   E   R   S

   W   A   T   E   R   P   U   M   P   S

   S   H   E

   A   R   I   N   G   /   G   R   O   O   V   I   N   G   M   /   C

   B   A   T   C   H   I   N   G   P   L   A   N   T

   M   O   T   O   R   G   R   A   D   E   R   S

   L   O   R   R   Y   /   C   A   R   S   /   J   E   E   P   S

   C   R   A   N   E   S   /   H   Y   D .   C   R   A   N   E   S

   W   A   G   O   N   D   R   I   L   L   E   R   S

   T

   R   A   C   T   O   R   S   /   T   R   A   I   L   O   R   S

   W   I   N   C   H   /   H   O   I   S   T

   T   R   A   N   S   I   T   M   I   X   E   R   S

   B   A   R   B   E   N   D   I   N   G   M   /   C

   G   R   I   N   D   I   N   G   M   /   C   (   A   G   )

   O   V   E

   N   S   M   O   T   H   E   R   /   P   O   R   T   A   B   L   E

   P   U   G   C   U   T   T   I   N   G   M   /   C

   S   C   R   E   W

   J   A   C   K

   M

   A   G   N   E   T   I   C   D   R   I   L   L   M   /   C

   H

   A   N   D   C   U   T   T   I   N   G   S   E   T   S

   P   A   V .   B   R   E   A   K   E   R   S

   B   A   R   C   U   T   T   I   N   G   M   /   C

   C   U   B   E   T   E   S   T   I   N   G   M   /   C

   S   A

   N   D   B   L   A   S   T   I   N   G   H   O   P   E   R

   H   O   T   M   I   X   P   L   A   N   T

   M   O   B   I   L   E   D   G   S   E   T   S

   H   Y   D   R   A   (   8   T   )

   2   5   0   M   T   C   R   A   N   E   S

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

REQUIRED

DEPLOYED

TOTAL REQUIRED

  DEPLOYED

PROGRAMME %AGE :-

%AGE PROGRESS ACHIEVED :-

MONTH & YEAR

CLIENT

PMC : EIL

PAGE 30 OF 37

Page 48: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 48/60

UPDATED PROJECT SCHEDULE

NAME OF LSTK CONTRACT :

CONTRACTOR :

PROJECT :

Page 49: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 49/60

NAME OF LSTK CONTRACT MONTH & YEAR

CONTRACTOR CLIENT

PMC : EIL

 PROJECT PAGE 32 OF 37

ANNEXURE : II (M) .

REQUIRED BY RECEIVED ON

1CHIEF INSPECTOR OF FACTORIES FOR PLANT

LAYOUT

  a) CONSTRUCTION

  b) AS BUILT

2 MUNICIPAL CORPORATION FOR VARIOUS BUILDINGS

3CIVIL AVIATION FOR FLARE STACK OF CHARGE

HEATER

4 FIRE & NUISANCE DEPARTMENT FOR FURNACE

STACK ( CHARGE STACK)

5 NOC FROM MUNICIPAL CORP. FOR ALL FACILITIES

6 IBR FOR STEAM PIPING & EQUIPMENTS

7 IBR FOR CHARGE HEATER

8 TAC FOR FIRE WATER & FIRE FIGHTING SYSTEM

9CCE FOR PLANT LAYOUT, FIRE FIGHTING SYSTEM &

TANK

10CEI APPROVAL FOR H.V ELECTRICAL DISTRIBUTION

SYSTEM

11 ANY OTHER STATUTORY & GOVT. APPROVALS

(LIST THE SAME)

  @@ NOTE : PROBLEMS IF ANY HOLDING APPROVAL SHALL BE HIGHLIGHTED IN THE STATUS COLUMN.

STATUTORY APPROVAL STATUS (APPROVALS TO BE LISTED UNDER THE HEADS OF (A) FOR DESIGN / DRAWINGS AND (B) FOR INSTALLATION)

APPROVAL DATE

REMARKS@@ STATUSAPPROVALSSL. NO.

Page 50: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 50/60

 AMOUNT CERT.RECD

TOTAL 0 0 0 0 0 0

NUMBER & DATE VALUE NET AMOUNT DATE

INVOICING STATUS

SR.NO

SERVICE TAX

& OTHER

DEDUCTIONS

TOTAL

DEDUCTIONS

REASONS FOR OTHER

DEDUCTIONS/

REMARKS

DEDUCTIONS

INCOME TAX

INVOICE RECEIPT

PAGE 33 OF 37

 ANNEXURE - II(N)

NAME OF LSTK CONTRACT

PROJECT

MONTH & YEAR

CONTRACTOR CLIENT

PMC : EIL

Sheet 1 of 1

Page 51: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 51/60

MONTH & YEAR

CONTRACTOR CLIENT

PMC : EIL

PAGE 34 OF 37

 ANNEXURE - II(O)

SR. NO WAIVER/ DEVIATION PERMIT NO/ LETTER REF NO DATE SUBJECT REMARKS STATUS

A

B DEVIATION PROPOSED

STATUS OF WAIVERS/ DEVIATIONS

SUBMITTED IN FORMAT

NAME OF LSTK CONTRACT

PROJECT

Sheet 1 of 1

Page 52: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 52/60

 

 ANNEXURE : II(P-i)

SCH ACT SCH ACT

1 HMTD

2 GENERAL CIVIL

3 ARCHITECTURE

4 STRUCTURAL

5 PIPING

6 PRESSURE VESSELS

7 ROT.EQUIPMENT

8 MECH.EQUIPMENT

9 ELECTRICAL

10 INSTRUMENTATION

TOTAL 100.0

100.0 97.4

 PROJECT

NAME OF LSTK CONTRACT

DEVIATIONDURING THE

MONTH %

CUMULATIVE

PROGRESS %

 DELAY ANALYSISANALYSIS

SR.

NOREMARKSDISCIPLINE

WTD

VALUE

%

MONTH & YEAR

CONTRACTOR CLIENT

PMC : EIL

PAGE 35 OF 37

Sheet 1 of 2

Page 53: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 53/60

MONTH & YEAR

CONTRACTOR CLIENT

PMC : EIL

PAGE 36 OF 37

 ANNEXURE - II(P-ii)

SCH ACT

1 HMTD

2 GEN. CIVIL

3 ARCHITECTURE

4 STRUCTURAL

5 PIPING

6 ROTATING EQPT

7 MECHANICAL

8 ELECTRICAL

9 INSTRUMENTATION

NAME OF LSTK CONTRACT

PROJECT

 DELAY ANALYSIS

SR. NO REMARKSDISCIPLINE ACTIVITY/ ITEMDRG NO/

MR NODEVIATION

CUMULATIVE

PROGRESS %

Sheet 2 of 2

Page 54: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 54/60

NAME OF LSTK CONTRACTCONTRCTOR

PROJECT

MONTH & YEARCLIENT

PMC : EIL

Page 37 of 37

 

ANNEXURE : II (Q) PROJECT PHOTOGRAPHS 

NOTE : COLOUR PHOTOGRAPHS SHOWI NG KEY PROJECT ACTI VI TI ES e. g

MANUFACTURI NG OF CRI TI CAL EQUI PMENT, TRANSPORTATI ON OF ODC

I TEMS, CONSTRUCTI ON/ ERECTI ON OF MAI N AREAS / EQUI PMENT SHALL

BE I NCLUDED EVERY MONTH.  

Page 55: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 55/60

FLOW OF DOCUMENTS FROM LSTK CONTRACTOR

Note : 1. Documents to be submitted by the bidder along with Bid are listed in clause 4.0

2. LSTK Contractor shall submit electronic file along with hard copy wherever “*” is marked below

3. Number of copies to be submitted by LSTK Contractor for each document indicated below are indicat

as per project requirement by Project Manager before including in the bid document.

S.NO. DESCRIPTION OF DOCUMENT FREQUENCY / TIME OF RECEIPT

NO. OF COPIES

CLIENT

(HO)

CLIENT

(SITE)

PMC

(HO)

PMC

(SITE) D

1. 90 Days Front End schedule With in one week of award 2 2 4* 2*

2a.

2b.

Procedure for Planning Scheduling and Monitoring

along with sample formats.

Progress Measurement Methodology

During kick off Meeting ( To be held within two

weeks of award )2 1 2 2

3a.

3b.

Overall Project Schedule ( Unit wise ) – Detailed &

Summarised

Updation of overall Project schedules

( Unit wise )

With in four weeks of award.

Monthly summarized schedule to be submitted

with monthly progress report. Detailed schedule

to be submitted separately on monthly basis.

4

2

2

1

4*

3*

2*

2*

4a. Unit wise Functional Schedules in resource based

bar chart with “s” curves

- Residual Basic Engineering Schedules

- Detailed Engineering Schedules

- Ordering Schedules

- Manufacturing & Delivery Schedule

- Sub-contracting Schedule

Within 6 weeks of award

Schedules of different disciplines to be

submitted as separate documents

- - 4* -

Page 56: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 56/60

FLOW OF DOCUMENTS FROM LSTK CONTRACTOR

S.NO. DESCRIPTION OF DOCUMENT FREQUENCY / TIME OF RECEIPT

NO. OF COPIES

CLIENT

(HO)

CLIENT

(SITE)

PMC

(HO)

PMC

(SITE) D

4b. Updation of Functional Schedule and “S” Curve Monthly 2 1 2* 2*

5a.

5b.

Construction Network (Unit wise) with contract

level, unit level and discipline “S” curves.

Updation of Construction Network and “S” curves (

Unit wise )

Within eight weeks of award or one month

before start of construction activities, which

ever is earlier.

Monthly

1

1

1

1

3*

1

2*

2*

6a.

6b.

Loop wise piping completion schedule

Updation of loop wise piping completion schedule

Two months before start of hydro -testing as

scheduled in unit wise construction network

Weekly, to be submitted before review meeting

1

1

1

1

3*

1

2*

2*

7a.

7b.

System wise completion schedule

Updation of system wise completion schedule

Six weeks before scheduled completion as per

unit wise construction network

Weekly, to be submitted before review meeting

1

1

1

1

3*

1

2*

2*

8a.

8b.

Pre-commissioning / commissioning schedule

Updation of Pre-commissioning / commissioning

schedule

Two months before scheduled mechanical

completion or one month before starting of

Pre-commissioning activities as per unit wise

construction, whichever is earlier.

Weekly, to be submitted before review meeting

1

1

1

1

3*

1

2*

2*

9. Catch up Schedules

a. For Overall Project Schedule

b. For Construction Networks

c. Updation

 As desired by Client/PMC

 As per 3b & 5b.

2

2

2

14*

3*

2*

2*

Page 57: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 57/60

FLOW OF DOCUMENTS FROM LSTK CONTRACTOR

S.NO. DESCRIPTION OF DOCUMENT FREQUENCY / TIME OF RECEIPT

NO. OF COPIES

CLIENT

(HO)

CLIENT

(SITE)

PMC

(HO)

PMC

(SITE) D

10a.

10b.

Sub-contractor schedules with “S” curves including

all Sub-Contractor Packages like Heater, DM Plant

etc,

Updation of Sub-contractor schedules with “S”

curves

To be made within two weeks of award of Sub-

Contract

To be submitted when called for by the owner /

PMC.

Fortnightly

 As called for

11. Monthly Programme

a. Design Office Activities

b. Construction Activities

Within three calendar days of monthly progress

report cut off date

Within two calendar days of monthly progress

report cut off date

 As desired 2

2

2

2

12. Monthly Progress Report Monthly, within 5 calendar days from cut off

date

4 2 2* Files as

mentioned

above

2* Files as

mentioned

above

13. Weekly Progress Report ( Over all ) Weekly / within 3 calendar days of cut off date. 1 1 2 2

14. Weekly Progress Report ( Construction ) Weekly / within 2 calendar days of cut off date. 1 1 2 2

15. Daily Progress Report ( Site ) Daily / before noon of next day 1 1 2 2

16. Expediting Report Fortnightly 1 1 2 2

17. Planning Package Within 12 weeks of award. 2 2 2 2

Note: All the above deliverables shall also be furnished in soft form (native format) along with hard copies.

Page 58: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 58/60

  ATTACHMENT – V

Page 1 of 3

 

INDICATIVE PROGRESS MEASUREMENT WEIGHTAGE AT VARIOUS LEVELS

I Function Level

PROCESS UNITS UTILITIES & OFFSITEResidual basic engineering 01.0 01.0Engineering 10.0 10.0Ordering/purchase 03.0 03.0Manufacturing & delivery 54.0 30.0Construction. 30.0 54.0Pre-commg. and Commissioning 02.0 02.0and Handing over.

II Discipline Level

ENGINEERING:  Avg Range 

CIVIL/ STRUCTURAL 20 (15-25)PIPING 35 (30-40)HEAT EQUIPMENT 06 (03-09)PRESSURE VESSELS 06 (03-09)MECH.EQUITMENT/SYSTEMS 12 (08-16)ELECTRICAL 08 (06-18)INSTRUMENTATION 13 (08-24)

ORDERING & MANUFACTURING AND DELIVERY:PIPING 16HEAT EQUIPMENT 19PRESSURE VESSELS 18MECH.EQUIPMENT/SYSTEMS 28ELECTRICAL 07INSTRUMENTATION 12

CONSTRUCTION (PROCESS UNITS):PILING (IF APPLICABLE) 02CIVIL WORK 22STRUCTURAL 03PIPING & EQUIPMENT ERECTION 40HEATERS 10INSULATION 03PAINTING 01

ELECTRICAL 06INSTRUMENTATION 08MISCELLENEOUS 05

Note : In case of utilities and offsites, package/system wise weight factors and then todiscipline wise weight factors shall be developed. This will be more relevant in case theEPCC contractor is sub contracting some packages on turnkey basis. For example: RWSystem etc.

Page 59: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 59/60

  ATTACHMENT – V

Page 2 of 3

III Deliverable weightages

PROCESS:DESIGN BASIS 05

PFD 15PROCESS SUMMARY 05DATA SHEETS FOR MAJOREQUIPMENT 15P&IDs 30INSTRUMENT DATA SHEETS 10LINE SCHEDULE 10FINAL PROCESS PACKAGE 10

IV Milestone level

PROCESS:

FIRST ISSUE 50RECEIVE COMMENTS 20INCORPORATE COMMENTS 20ISSUE FOR PROCESS PACKAGE/FEED 10

ENGINEERING:Drawings & Documents: 

 Appl.Cat Info.Cat.DRAFTING COMPLETE 50 50CHECKING COMPLETE 10 10ISSUE FOR APPROVAL 10 --RECEIVE COMMENTS 10 --ISSUE FOR CONST. 10 30UPDATION & REVISIONS 10 10

Material Requisitions:Equipment Bulk

ISSUE M/R 20 20TECH.EVLN. 10 50ISSUE PR TO PMC 10 10REVIEW OF PR BY PMC 10 10ISSUE P/R TO VENDOR 10 10VENDOR DRAWINGREVIEW 40 --

ORDERING:ISSUE ENQUIRY 05RECEIVE BIDS 15TBA 25RELEASE TOI 45ISSUE PO/PR TO VENDOR 05UNPRICED PO/PR TO OWNER 05

Page 60: a3.8 planning scheduling_20090812_115626.pdf

7/23/2019 a3.8 planning scheduling_20090812_115626.pdf

http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 60/60

  ATTACHMENT – V

Page 3 of 3

MANUFACTURING & DELIVERY:Equipment:SUBMISSION OF MAJOR DRAWINGS 5.0 APPROVAL OF MAJOR DRAWINGS 5.0SUB ORDERING OF MAJOR MATERIALS 5.0

RECEIVE MAJOR MATERIALS 25.0FABRICATION WORK 40.0(Progressive)FINAL INSPECTION & TESTING 05.0DESPATCH TO SITE 05.0RECEIVE AT SITE 05.0SUBMIT FINAL DOCUMENTATION 05.0

Bulk material:START OF WORK 10.0DESPATCH 60.0(Progressive

Desp.qty./Total qty.)RECEIVE AT SITE 20.0(Progressive

Received.qty/Total qty.)FINAL DOCUMENTATION 10.0

CONSTRUCTIONIN CASE OF CONSTRUCTION ALL ITEMS OF WORK AND QUANTITIES SHALL

BE INDICATED AND % PROGRESS AT WORK ITEM LEVEL SHALL BE BASED

ON WORK COMPLETED VS. TOTAL QTY OF THE WORK ITEM. THE EPCC

CONTRACTORS SHALL GIVE DETAILS OF ARRIVING AT TOTAL CONTENTS.