7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 1/60
1 11-06 -2007GENERAL REVISION - ISSUED FOR
IMPLEMENTATIONDDC DRC HOD
0 26-06 -2000 ISSUED FOR IMPLEMENTATION DDC DRC HOD
Rev
. NoDate Purpose Prepared by Reviewed by Approved by
Template No. 5-0000-0001-T1 Rev. 1 Copyrights EIL – All rights reserved
Document No.8-2744-1003Rev. No. 1
Page 1 of 15
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
PROJECT PLANNING, SCHEDULING, MONITORING & CONTROLSYSTEM FOR LSTK CONTRACT
THIS SHALL FORM PART OF BID DOCUMENT
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 2/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 2 of 15
Abbreviations:
LSTK - Lumpsum TurnkeyPMC - Project Management ConsultantMR - Material Requisition AFC - Approved for ConstructionWBS - Work Breakdown StructureUOM - Unit of measurementPR - Purchase RequisitionPO - Purchase OrderP&ID - Piping & Instrumentation Diagram
Document Drafting Committee Members:
Mr. SP SinachoudhuryMr. R MohanMr. MK JainMr. TK NandaMr. R ShailendraMr. SS MadanMr. KN ChoudharyMr. Sudershan Kumar
Document Review Committee Members:
Mr. AK GautamMr. VK SawhneyMr. VL RajaniMr. R Mohan
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 3/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 3 of 15
CONTENTS
Clause Title Page No.
1.0
INTRODUCTION 4
2.0 DEFINITIONS 4
3.0
ABBREVIATIONS 4
4.0 DOCUMENTS ALONG WITH BID 4
5.0 AFTER AWARD OF WORK 5
6.0
PROJECT SCHEDULES 6
7.0
UPDATION OF PROJECT SCHEDULES 10
8.0
REVIEW MEETINGS 11
9.0 PROGRESS REPORTING 12
10.0
BULK MATERIAL CONTROL 13
11.0 PLANNING PACKAGE 14
12.0 CONTROL ROOM DISPLAY 14
13.0 SOFTWARE PACKAGES 15
14.0
PROVISION OF COMPUTER FACILITIES 15
ATTACHMENT
I PROJECT SCHEDULE HIERARCHY (1 Sheet)II WORK BREAK DOWN STRUCTURE (1 Sheet)III MONTHLY PROGRESS REPORT (37 Sheet)IV FLOW OF DOCUMENTS (3 Sheet)
V INDICATIVE PROGRESS MEASUREMENT WEIGHTAGE AT VARIOUS LEVELS (3 Sheet)
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 4/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 4 of 15
1.0 INTRODUCTION
To ensure timely completion, the Lumpsum Turnkey (LSTK) Contractor shall establish andmaintain an effective Planning, Scheduling, Monitoring and Control system, including
mobilization of required number of professionally qualified and experienced PlanningEngineers for design office and construction site. The system shall be capable of accurateand timely prediction of trend, evolution of adequate preventive actions for likely slippages,and formulation of suitable catch-up schedule for delays, if any, that have occurred.
Schedules, reports and documents to be prepared and submitted by the LSTK contractorfor review of Client/ Project Management Consultant (PMC) at various stages and detailsof meetings to be held are described here.
2.0 DEFINITIONS
Work Breakdown Structure (WBS) Work Breakdown Structure is a diagram that depicts various units in a project and each unit
is detailed with work items/equipments and major workloads.
Design Office Where Residual Basic Engineering, Detailed engineering, procurement activities for thecontract are performed by LSTK contractor.
FunctionsFunction means basic components of the projects e.g. Residual Basic Engineering,Detailed engineering, ordering, manufacturing & delivery, construction and commissioning.Each function is divided into various disciplines. In case of engineering, various disciplinesare architecture, civil, structure, piping etc.
3.0 ABBREVIATIONS
LSTK - Lumpsum TurnkeyPMC - Project Management ConsultantMR - Material Requisition AFC - Approved for ConstructionWBS - Work Breakdown StructureUOM - Unit of measurementPR - Purchase RequisitionPO - Purchase OrderP&ID - Piping & Instrumentation Diagram
4.0 DOCUMENTS ALONG WITH BID
The LSTK bidder shall submit following documents along with the bid:
a) Proposed Overall Project Schedule in network form showing all the details unit wise.b) Write up on Project Planning, Scheduling, Monitoring and Control system (proposed).c) Organizational set up for Planning, Scheduling, Monitoring & Control at LSTK
Contractor’s Design Office and Site Office.d) Progress Measurement Methodology with details such as weightages, milestones,
frequency etc.e) Project execution methodology.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 5/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 5 of 15
f) Function wise Resource Deployment Schedule (HO & Site manpower and constructionequipment).
g) Softwares to be used for planning and material control.h) Statement confirming compliance to the “Planning, Scheduling, Monitoring and Control
System” requirements regarding contents of the documents to be submitted to
Client/PMC.
5.0 AFTER AWARD OF WORK
5.1 90 DAYS FRONT END SCHEDULE
The LSTK Contractor shall prepare and submit a detailed 90 days front-end schedule withinone week of award. Pending finalisation of Overall Schedule, this schedule shall be the basisof monitoring of front-end activities. The schedule shall cover all activities to be carried outduring initial 90 days period of the contract. The schedule shall be reviewed in the kick-offmeeting.
5.2 KICK OFF MEETING
A Kick Off Meeting shall be organised within two weeks of award of contract. The meetingshall be attended by Client’s and PMC’s representatives. During the meeting, the followingwith respect to Planning, Scheduling, Monitoring and Control system shall be discussed andfinalized:
1. Planning deliverables required for Project Monitoring and Control.2. Work Breakdown Structure for Project Schedules, organisation and level of detailing
for Overall Project Schedule and Functional Schedules.3. Procedure for Project Planning, Scheduling, Monitoring & Control system including all
reporting formats.4. Progress Measurement Methodology and Unit, Function, Discipline, and Deliverable
wise weightage breakdown (refer Attachment V for indicative weightage).
5. List of engineering deliverables with indicative schedule for submission.6. List of unit wise milestones to be included in the network, in addition to milestones
specified in the Contract, if any (the number of milestones shall be at least 2 to 3 perunit per month).
7. List of critical equipment and materials for the fortnightly expediting report to beissued by the LSTK Contractor.
8. Procedure for Bulk material control.9. Cut off dates, distribution list with number of copies and Project calendar indicating
submission of various planning documents and revisions.10. Any other document as required.
5.3 PROGRESS MEASUREMENT METHODOLOGY
The LSTK Contractor shall submit during Kick Off Meeting, the detailed methodology ofprogress measurement of Residual Basic Engineering, Detailed Engineering, Ordering,Manufacturing & Delivery, Sub-contracting, Construction and Commissioning for review byClient/PMC. LSTK Contractor shall also furnish the methodology of progress measurementfor sub-contracted packages such as DM plant, Cooling tower etc. and integration of thesame with the overall progress.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 6/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 6 of 15
During the Kick Off meeting, Client/PMC shall finalise weighted values to be used for thefollowing:-a) Unit wise within the package, if applicable.b) Function wise within each unit.c) Milestone weightage within each deliverable.
Effort based weighted values for the following, along with the basis of their derivation, shallbe submitted by LSTK Contractor for review by Client/PMC, and the comments if any shallbe incorporated by LSTK Contractor before submission of functional schedules that usethese weighted values as the basis:a) Discipline wise within each function.b) Deliverable level weightage Percentage.
Progress figures at Unit / Function / Discipline level shall be summarized from deliverablelevel and indicated in the functional schedules.
6.0 PROJECT SCHEDULES
Following schedules shall be prepared and submitted by LSTK contractor to Client/PMC forapproval. A hierarchy of all schedules to be generated by LSTK Contractor is shown in Attachment – I.
6.1 OVERALL PROJECT SCHEDULE NETWORK (Summarised & Detailed)
The LSTK Contractor shall submit within four weeks of award a network based detailedoverall project schedule (unit wise) on time scale, for all units in the package and allfunctions of the work along with a Work Breakdown Structure indicating unit wise workload(sample format as Attachment - II). The schedule shall highlight interface activities in thescope of Client/PMC and clearly reflect strategies and philosophy of execution. Majormilestones for each unit shall be depicted at the beginning of the network. The projectschedule shall be developed for contractual duration and or target duration decided with
Client/PMC. Grace period, if any as per contract shall not be considered for schedule. The schedule shall be reviewed by Client/PMC and the comments if any shall beincorporated and the schedule shall be issued for implementation within one week fromthe receipt of comments. This schedule once approved by Client/PMC shall not be revisedwithout the prior written permission of Client/PMC.
Overall Project Schedule Network (Summarised) will be derived from Overall ProjectSchedule Network (Detailed) and will include all major / critical activities & summarisedactivities at macro-level.
Overall Project Schedule Network (Detailed) shall be used for trend / detailed analysiswhereas summarised Overall Schedule will be used to project status at a glance to highermanagement along with the Monthly Progress Report.
6.2 FUNCTIONAL SCHEDULES
The LSTK Contractor shall prepare resource based detailed Unit wise functional schedulesfor all functions in spreadsheet format in line with overall project schedule for monitoringand control. LSTK Contractor shall submit the same within six weeks of award for reviewexcept construction schedule, which shall be submitted within eight weeks of award. Unitwise “S” curves for schedule progress shall also be submitted along with the functional
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 7/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 7 of 15
schedules. The schedule shall be reviewed by Client/PMC and comments, if any, shall beincorporated and issued for implementation within one week from receipt of comments. The Schedule “S” curves shall remain firm during the execution of the project.
LSTK Contractor shall also ensure preparation, submission and updation of all functional
schedules as described herein for all sub contracted packages like Heaters, DM Plant,WWTP, Cooling Tower, Nitrogen Plant etc.
6.2.1 Residual Basic Engineering Schedule
The LSTK Contractor shall submit a Unit wise schedule for all Residual Basic Engineering Activities like finalisation including updation (incorporating vendor data) of P&IDs forprocess units and utilities & offsites, release of line schedules, finalisation of process datasheets for equipment etc. as per page 14 of Attachment - III.
6.2.2 Detailed Engineering Schedule
The LSTK Contractor shall submit a Unit wise schedule of all engineering
deliverable/documents such as AFC drawings, Isometrics, Specifications, MaterialRequisition, Purchase Requisition, Design calculations etc. as per page 14 of Attachment -III.
6.2.3 Ordering Schedule
The LSTK contractor shall submit a Unit wise schedule for all ordering activities as perpages 17 &18 of Attachment - III. This shall include all MRs listed in Engineering Schedule.
6.2.4 Manufacturing / Delivery Schedule
The LSTK contractor shall submit a Unit wise schedule for all Manufacturing & Deliveryactivities as per page 22 of Attachment - III. These shall include all orders listed in the
Ordering Schedule. The progress at Function/Unit level shall be summarised consideringweighted values of tagged items and bulk material to report overall Manufacturing andDelivery progress.
LSTK Contractor shall also submit along with Weekly Progress Report, status of drawingsand documents for all vendors on whom orders have been placed, as per page 16 of Attachment - III. In addition to the above, for critical items as mutually agreed betweenLSTK Contractor and Client/PMC, LSTK Contractor shall ensure that vendors prepares andupdates logical networks for Manufacturing & Delivery and submit the same on weekly /monthly basis to Client/PMC if asked for.
6.2.5 Sub-contracting Schedule
The contractor shall submit a Unit wise schedule for all Sub-contracting activities as perpage 23 of Attachment - III. This shall include all tenders envisaged for the Project.
6.2.6 CONSTRUCTION SCHEDULE
The LSTK Contractor shall prepare and submit a Detailed Construction Schedule unitwise for Client/PMC review. The LSTK Contractor shall describe resources (manpower andmachinery) required to be mobilised. The schedule shall have interface with Engineering,
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 8/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 8 of 15
Ordering and Manufacturing & Delivery activities and also interface required fromClient/PMC. The LSTK Contractor shall also define construction quantity for each activity.LSTK Contractor shall finalise discipline wise Construction ”S” Curves and quantumschedule.
6.3 OVERALL ‘S’ CURVES
The LSTK Contractor shall prepare unit wise and Overall “S” curves showing cumulativeschedule progress taking into consideration “S” curves for Residual Basic Engineering,Detailed Engineering, Ordering, Manufacturing & delivery, Sub-contracting and Construction“S” Curves. The overall “S” curves shall be updated immediately after finalisation ofconstruction schedule. The overall “S” curves shall be submitted for Client/PMC review, withnecessary back ups and shall form part of monthly progress report.
6.4 OTHER SCHEDULES
The control philosophy for construction activities involves monitoring at theunit/discipline/subcontract/area level from the initial stages of construction and
supplementing it with monitoring at the system/ loop level as construction advances towardsmechanical completion/ pre-commissioning/ commissioning stages. To meet this objective,the following schedules/deliverables shall be prepared by LSTK Contractor.
6.4.1 SUB CONTRACTOR SCHEDULE
LSTK Contractor shall ensure preparation of detailed schedules for all works in the scope ofeach subcontract awarded by them within two weeks of award of sub-contract, for monitoringof construction progress. These schedules shall have quantity/work load details of all workitems and “S” curve for each of the sub contracts. The LSTK Contractor shall ensureupdation of the same on fortnightly basis. Client/ PMC reserve the right to check theseschedules at any time.
6.4.2 MONTHLY PROGRAMME
LSTK Contractor shall prepare monthly quantitative programmes in line with functionalschedules for all the functions. These programmes shall be made keeping in view thecumulative targets as set in the schedules backlog and work front available in terms ofvendor inputs, drawings, materials and access as applicable. The programmes forconstruction shall be accompanied by list of resources (Manpower & machinery) planned tobe deployed to achieve the programmes. Current hold ups (Drawing, Materials, etc. ifany) required to be resolved for the execution of the programmes made, shall be indicatedwith proposed action plan for resolution.
Monthly programmes other than Construction shall be submitted to Client/PMC DesignOffice within three calendar days of monthly progress report cut-off date. In case of
Construction, monthly programme shall be finalised in consultation with Client/PMC’s siterepresentative and submitted within two calendar days of monthly progress report cut-off date. In all matters concerning the extent of targets set out in monthly programme, thedecision of Client/PMC shall be final and binding.
The monthly programmes shall be further broken down into weekly programmes andindicated in weekly reports for closer monitoring of progress.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 9/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 9 of 15
6.4.3 LOOPWISE PIPING COMPLETION SCHEDULE
LSTK Contractor shall prepare micro-level schedule for completion of piping activities andsubmit to Client/PMC for review at least two months before the start of hydrotesting asscheduled in Unit wise Construction schedules. The schedules shall cover unit wise/
system wise/ loop wise, the following activities remaining as of the date of preparation:
a) Status of balance piping materials (Details of items, quantities, vendors, POs andexpected date of receipt at site to be indicated)
b) Status of balance equipment and in-line instrument items (Details of tags, vendors andPOs and expected receipt to be indicated)
c) Welding (inch dia) workload separately for shop fabrication and field welding.d) Erection and supporting (inch meter)e) Radiography (number of joints)f) Stress relieving (number of joints)g) Hydrotesting (inch meter)
6.4.4 SYSTEMWISE COMPLETION SCHEDULE
After preparation of loop wise micro-level schedule for completion of piping activities, LSTKContractor shall prepare Unit wise/ System wise micro-level schedule for completion ofremaining activities. The schedules shall be submitted by LSTK Contractor to Client/PMCfor review, 6 weeks before scheduled system completion as per Unitwise ConstructionSchedules. The schedules shall cover disciplinewise remaining activities as mentionedbelow
a) Balance civil and structural work itemwiseb) Balance Mechanical erection work tagwisec) Alignment of Rotating Equipmentd) Balance Electrical worke) Balance Instrumentation works including loop checking
f) Schedule for issue of prescribed formats for handing over of system such as
Format I : Information regarding system completionFormat II : ChecklistFormat III : Ready for pre-commissioning / Mechanical completion certificateFormat IV : Ready for commissioning certificateFormat V : Completion of commissioning certificate
The description of the system and loop numbering mentioned in the schedules at 6.4.3 &6.4.4 above shall be as agreed with Client/PMC (Construction / Commissioning group). Theschedule shall be resource based and shall indicate total and remaining workload for eachactivity.
6.4.5 PRE-COMMISSIONING/COMMISSIONING SCHEDULE
LSTK Contractor shall prepare unitwise / systemwise pre-commissioning/ commissioningmicro-level schedule. These schedules shall be submitted by LSTK Contractor toClient/PMC for review two months before the Mechanical Completion milestone or onemonth before starting pre-commissioning activities, which ever is earlier .
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 10/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 10 of 15
The schedules shall be developed after considering the pre-commissioning/ commissioningpriorities & interface requirements and identify requirement of licensor’s/ vendor’srepresentatives stay at site. The description of system/ sub system mentioned in theschedule shall be as agreed with Client/PMC (Construction/ Commissioning groups).
6.5 CATCH-UP SCHEDULE
The LSTK Contractor shall generate and submit catch-up schedule for completion of allbalance activities without change in contractual completion date with detailed resourcereinforcement as and when asked by Client/PMC. The catch-up schedules shall besubmitted to Client/PMC for review. Accordingly the “S” curves for catch-up schedules shallbe made and shown along with the original schedules and actual “S” curves.
During updation of overall project schedule, the catch-up schedules shall be shown in barcharts along with the original schedule.
7.0 UPDATION OF PROJECT SCHEDULES
The various schedules as described herein shall be updated for submission to Client/PMC.Updation of the schedule is to determine the project trend, with the objective of takingpreventive/ corrective action. The reflection of delayed / anticipated completion by way ofcurrent trend does not in any manner absolve the LSTK Contractor of his contractualobligations as per the contract.
7.1 OVERALL PROJECT SCHEDULE
7.1.1 Overall Project Schedule Network (Detailed)
The schedule shall be updated on monthly basis and submitted in linked bar chart form in A4 size in soft form (native format). The updation shall be compared with the originalschedule.
While updating, the following shall be considered:- Actual date of start and completion for the activities.- Contractual completion dates for vendors and sub-contractors/turnkey agencies, any
change of duration due to offloading of vendors/sub-contractors/turnkey agencies to bereflected.
- Duration of activities not yet started shall remain the same as per the original schedule.- Anticipated dates of activities in progress.- Addition/deletion of any activity if required or any change on job logic.- Any change in drawing/material availability or change in activity duration.- Any change in resource planning.- Change in philosophy/strategy in execution of balance works, keeping in mind the
actual status of the project.
7.1.2 Overall Project Schedule Network (Summarised)
The schedule shall be as derived from the updated Overall Project Schedule Network(detailed) as above on monthly basis and submitted in linked bar chart form in A4 size withmonthly progress report. The updation shall be compared with the original schedule. Formatfor updated schedule will be as per Attachment-III page 31 of 37.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 11/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 11 of 15
7.2 FUNCTIONAL SCHEDULES
The updated functional schedule trend and original schedule shall be shown together andsubmitted to client / PMC on monthly basis, as part of Monthly Progress Report.
While updating, the following aspects shall be considered:- Actual dates of start and completion for the activities.- Actual work progress/balance work- Contractual completion date for sub-contractors and vendor delivery not reflected
earlier.- Any change in estimated activity durations- Material and drawing availability- Interfaces of one agency with other agencies- Various statutory reviews/approval- Interfaces between unit & offsite / utilities i.e. permanent power & water, waste
disposal etc.- Any change in execution logic/philosophy and engagement of number of agencies/
sub-contractors and resource planning/ offloading if resorted to.
7.3 OTHER SCHEDULES
The following schedules shall be updated on a weekly basis and submitted to Client/PMCbefore the weekly review meeting at site in bar chart format. The updated schedule trendshall be compared with original schedule.
- Loopwise piping completion schedule- Systemwise completion schedule- Pre-commissioning/commissioning schedule
8.0 REVIEW MEETINGS
The LSTK Contractor shall present project status, project highlights and action plan asapplicable at various review meetings as described below. The presentation materials shallbe submitted by LSTK contractor to Client/PMC at least two days before the date of themeeting for management level review meetings and Monthly/ Fortnightly review meetings.
8.1 Management level Review Meeting
Level of participation : Senior management of client, PMC andLSTK contractor.
Agenda frequency and venue : to be decided by Client/PMC.
8.2 Monthly/Fortnightly Review Meeting
Level of participation: Client, PMC and LSTK Contractor
Agenda: 1) Status against various commitments made during the previous reviewmeetings
2) Monthly programme v/s Progress Status/Statistics3) Project Completion Outlook4) Areas of concern with action plan
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 12/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 12 of 15
5) Catch-up schedule.
Venue and timing of the meeting shall be decided by Client/PMC. Frequency of Meeting(Monthly or Fortnightly) shall also be decided by Client/PMC, based on criticality of theproject status.
8.3 Weekly Review Meeting
8.3.1 For LSTK Design Office activities
Level of participation: Client, PMC & LSTK Contractor
Agenda: 1) Weekly programme v/s progress status/Statistics for ResidualBasic Engineering, Detailed Engineering, Ordering,Manufacturing & Delivery and Sub-contracting.
2) Action taken for slippages.3) Programme for next week4) Status of various resources deployed Vs planned
8.3.2 For Site Activities
Level of participation: Client, PMC & LSTK Contractor
Agenda: 1) Work front availability2) Weekly programme v/s Achievement3) Resource mobilisation4) Reasons for shortfall5) Catch-up Schedule6) Progress statistics7) Programme for next week.8) Status of resources deployed v/s planned.
Venue and timing of Weekly Review Meetings for shall be decided by Client /PMC.
9.0 PROGRESS REPORTING
The LSTK Contractor shall submit the following reports on regular basis for Client/PMC’sinformation/ review.
9.1 Monthly Progress Report
The report shall be submitted on monthly basis within 5 calendar days from cut-off date covering overall scenario of the project. A copy of the specified formats for the report isenclosed as Attachment – III.
9.2 Weekly Progress Report (Overall)
This report shall be prepared by LSTK Contractor and issued on weekly basis toClient/PMC with in three days of the cut off date. The report shall include the following:
• Executive Summary
• Project highlights with dates of achievements.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 13/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 13 of 15
• Project exception (work programmed but not achieved with reasons for non-achievement) and work programmed for next week
• Critical areas
• Action taken / to be taken for slippages
• Progress statistics
• Activities planned for next week• Status of Outstanding Documents from Licensor/PMC
This shall cover both for LSTK Contractor’s Design Office activities and constructionactivities at site.
9.3 Weekly Progress Report (Construction)
This report shall be prepared by LSTK Contractor and submitted on weekly basis within 2calendar days from cut off date. The report shall cover following items:
• Progress statistics
• Work item wise quantity completed against programme for the week includingreasons for shortfall
• Programme for next week
• Front available
• Constraints, if any.
• Resources deployed against planned with reasons for shortfall in resourcedeployment
• List of equipment/materials received at site during the week
9.4 Daily Progress Report (Construction)
LSTK Contractor shall submit (daily before noon), for status of previous working day adaily report including the following
Programme v/s Progress for the day Programme for next day Important achievements for the day Materials / Equipment receipt for the day. Man power / Machinery deployment report - Required v/s Deployed.
9.5 Expediting Report
LSTK Contractor shall submit fortnightly expediting reports based on his representative’svisit to vendor’s work for orders where delivery of materials is critical to project completion. A list of such critical items/vendors shall be specified by Client / PMC during the kick offmeeting or at a later date.
In addition to the above, Client / PMC may request expediting report based on visit of LSTKContractor’s representatives in case of orders which though not critical at the time of orderplacement become subsequently critical during project execution due to any reason.
10.0 BULK MATERIAL CONTROL
The LSTK Contractor shall follow an integrated material control system for the project. Thesystem shall be such that material identification in the design office, procurement and
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 14/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 14 of 15
allocation, are all channelised and controlled in an orderly manner. The LSTK Contractorshall follow material identification like unitwise/system wise/area wise/zone wise/Linewise,and shall give construction orientation to material control. The LSTK Contractor, right fromthe beginning, at the design office stage, shall start identifying materials system wise orarea wise as indicated above. The system shall be based upon tracking of material
requisitioning, placement of purchase order, manufacturing at vendor’s shop up to receiptat site for making the material available for performing planned and sequential constructionwork.
Through periodic reviews, the LSTK Contractor shall have a system of generating Hold upreports well in advance to identify exception on material availability and to track suchmaterial by the expeditors through a systematic follow up procedure from the vendors.
The LSTK contractor shall make a presentation on the bulk material control systemproposed to be implemented by them for the project during the kick-off meeting.
LSTK Contractor shall submit the following reports on monthly basis for each unit as wellas summary level.
• Bulk Material Status Report
• Material hold up/shortage report.
11.0 PLANNING PACKAGE
Details of time of submission, frequency of submission and tentative number of copiesrequired for all documents to be submitted by the LSTK contractor are tabulated inattachment IV.
Once the majority of the schedules are finalized, the LSTK contractor shall compile thesame and submit in the form of a Planning Package. (Not later than 12 weeks of award of
the job). The Planning Package shall consist of the following:
- Introduction- Overall Project Schedule Network (Summarised)- 90 days front end schedule- Project WBS/ Work load- Progress measurement methodology- Overall Project schedule Network (Detailed)- Functional schedules- Progress ‘S’ curves- Sample reporting formats- Manpower and Machinery deployment schedule
LSTK Contractor shall submit reports, updated schedules, programmes etc. as describedherein till the completion of all work in the scope of the contract. No chapter/annexure ofany report shall be deleted without prior written approval of Client/PMC.
12.0 CONTROL ROOM DISPLAY
LSTK Contractor shall have conference room at site to display charts featuring salient staticinformation of the project, schedules, status of progress, resource deployment, rainfall
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 15/60
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved
PROJECT PLANNING, SCHEDULING,MONITORING & CONTROL SYSTEM
FOR LSTK CONTRACT
Document No.8-2744-1003Rev. No. 1
Page 15 of 15
record, block flow diagram, plot plan, work break down structure etc. The status shall beupdated at least on weekly basis. The objectives of the control room are to provideinformation at a glance to project personnel including the management of clients and PMC.
13.0 SOFTWARE PACKAGES
For schedule preparation and updation, The LSTK contract shall use Internationallyacclaimed network analysis package such as Primavera Project Planner, Project Scheduler,MS Project etc. compatible with that being used by Client/PMC and submit the backup of theschedules (native format) along with the hard copy whenever submission of the schedulesare called for. The electronic files for all other deliverables shall be compatible with MicrosoftOffice.
14.0 PROVISION OF COMPUTER FACILITIES
LSTK Contractor shall provide the following facilities for use by PMC at LSTKContractor’s design office:
A. PC with latest hardware, A3 size colour laser jet printer and Internet Connection.
B. Software:i) Network Analysis Package such as Primavera Project Planner,
Project Scheduler, MS Project etc.ii) MS Officeiii) E-mail and internet facilities
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 16/60
ATTACHMENT - I
A B C D
SUB-CONTRACTOR SUB-CONTRACTOR SUB-CONTRACTOR SUB-CONTRACTOR
SUB-CONTRACTOR
SCHEDULE SCHEDULE SCHEDULE SCHEDULE
(UNITWISE)
SUB-CONTRACTOR SUB-CONTRACTOR SUB-CONTRACTOR
UNITWISE/DISCIPLINEWISE UNITWISE/DISCIPLINEWISE DELIVERY (UNITWISE)
FOR ENGINEERING FOR ORDERING MANUFACTURING & FOR SUB CONTRACTING
FUNCTIONAL * FUNCTIONAL *
SCHEDULE SCHEDULE SCHEDULE FOR SCHEDULE
(UNITWISE)
FUNCTIONAL * FUNCTIONAL *
PROJECT SCHEDULE HIERARCHY (TO BE GENERATED BY LSTK CONTRACTOR)
OVERALL PROJECT
SCHEDULE
CONSTRUCTION SCHEDULE
(UNITWISE)
90 DAYS FRONT END
SCHEDULE
(UNITWISE)
PACKAGE
CONTRACTOR
CATCH UP SCHEDULE
(AS APPLICABLE)
CATCH UP SCHEDULE
(AS APPLICABLE)
LEVEL - II
LEVEL - I
LEVEL - III
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 17/60
ATTACHMENT- II
WORK BREAKDOWN STRUCTURE (TYPICAL)
UNIT - 1 (CAPACITY,
LICENSORS NAME) VESSELS/ HEAT
REACTORS COLUMNS DRUMS EXCHANGER HEATERS COMPRESSORS
(HEAT DUTY)
NOS. NOS. NOS. NOS. NOS. NOS.
MATL MATL MATL MATL MATL STR STEEL KW RATING
SIZE & WT MA X. WT & HT MAX. SIZE & WT INDG/IMP REFRACTORY MOTOR/TURBINE DRIVEN
INDG/IMP INDG/IMP INDG/IMP TUBES M/ IN DIA INDG/IMP
BURNER/SOOT BLOWERS
CIVIL/
PUMPS PIPING STRUCTURAL ELECTRICAL INSTN.
NOS. A/G & U/G RCC IN FDN NOS. OF PANELS INSTRNS. IND/IMP
KW RATING (RANGE) KM ----- RCC IN S/STR TRANSFORMERS CONTROL CABLE
MOTOR/TURBINE " DIA BRICK WORK MCC/PCC TUBES
DRIVEN " MTR STRL STEEL CABLES HT < CONTROL PANELS
INDG/IMP MATL LIGHTING
INDG / IMP
UNIT - 2 (CAPACITY,
LICENSORS NAME)
SIMILAR TO UNIT - 1
PROJECT/PLANT
(CAPACITY)
UNIT - 3 (CAPACITY,
LICENSORS NAME)
SIMILAR TO UNIT - 1
UTILITY /
OFFSITES
RAW WATER COOLING FIRE DM WATER STEAM NON PLANT
SYSTEM WATER WATER SYSTEM SYSTEM BUILDINMGS
(CAPACITY) SYSTEM SYSTEM
PUMPS NO OF CELLS PUMPS CAPACITY BOILER CAPACITY NOS.PIPES PUMPS PIPE QUANTUM OF
PIPE WORK
COOLING TOWER
CWTP
STORAGE CIVIL/ YARD CONTROL OTHER UTILITY
W.W.T.P. YARD STRUCTURAL PIPING ELECTRICAL ROOM SYSTEMS INCLUDING
(SIZE) C.P.D. (IF ANY)
TANKAGES RCC A/G SWITCH GEAR CONTROL PANELS
SPHERES STRL STEEL MATERIAL TRANSFORMERS
KM/IM CABLES
NO. OF S/STN.
NOTE : ACTUAL QUANTUM / NOS. TO BE WRITTEN.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 18/60
ATTACHMENT - III
CLIENTPROJECT LOCATION
P R O J E C T UNIT (IF APPLICABLE)
PMC :- M/s. ENGINEERS INDIA LTD., NEW DELHI.
MONTHLY PROGRESS REPORT
PROGRESS REPORT NO. XXUPTO____ (DAY) ______ (MONTH)_______ (YEAR)
(REPORTING CUT-OFF DATE)
PREPARED BY : LSTK CONTRACTOR
PAGE 1 OF 37
INFORMATION/ACTION
DATE ISSUED FOR PREPD BY REVIEWED BY APPVD BY
DOCUMENT NO ___________
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 19/60
NAME OF LSTK CONTRACTCONTRACTOR
PROJECT
MONTH & YEARCLIENTPMC EILPAGE 2 OF 37
TABLE OF CONTENTS
SECTION DESCRIPTION PAGE NO. I INTRODUCTION 3 II EXECUTIVE SUMMARY 4 III DETAILED STATUS 5 IV AREAS OF CONCERN WITH ACTION PLAN 6 V PROGRESS STATISTICS 7 VI MILESTONE STATUS 9 VII PROBLEMS / HOLD-UPS 10 ANNEXURES
I PROGRESS CURVES 11
II STATUS REPORTS
A CHRONOLOGICAL ACHIEVEMENTS 12B.1 SUMMARY STATUS OF ENGINEERING DRAWINGS 13B.2 DRAWING / DOCUMENT RELEASE SCHEDULE (DCI) 14
B.3 MATERIAL CONTROL INDEX (MCI) 15 C VENDOR/PACKAGE CONTRACTOR DRAWINGS AND DOCUMENTS STATUS 16 D.1 ORDERING STATUS (SUMMARY) 17 D.2 ORDERING STATUS (DETAILED) 18
E.1 EQUIPMENT DELIVERY STATUS (SUMMARY) 19 E.2 EQUIPMENT RECEIPT AND ERECTION STATUS (DETAILED) 20 E.3 BULK MATERIAL STATUS (SUMMARY) 21 E.4 MANUFACTURING / DELIVERY STATUS 22
F SUB CONTRACTING STATUS 23 G1 UNITWISE STATUS OF CONSTRUCTION QUANTITIES RELEASED 24 G2 QUANTITATIVE MONTHLY CONSTRUCTION PROGRESS STATUS 25
H STATUS OF CONSTRUCTION 26 I LOOPWISE HYDROTESTING STATUS 27 J SYSTEM HANDING OVER STATUS 28 K.1 UNITWISE DEPLOYMENT OF LSTK PERSONNEL AT CONSTRUCTION SITE 29 K.2 UNITWISE RESOURCE DEPLOYMENT STATUS - EQUIPMENT AND MACHINERY 30
L UPDATED OVERALL PROJECT SCHEDULE 31 M STATUTORY APPROVAL STATUS 32 N INVOICING STATUS 33 O STATUS OF WAIVER / DEVIATIONS 34 P DELAY ANALYSIS 35-36 Q PROJECT PHOTOGRAPHS 37
III OTHER REPORTS
OTHER REPORTS SUCH AS
- QUALITY REPORT- HEALTH, SAFETY AND ENVIRONMENT REPORT- COST REPORTS ETC. AS CALLED FOR IN THE OTHER SECTION OF THE BID PACKAGE.
DISTRIBUTION AS PER DISTRIBUTION LIST IN CONTRACT.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 20/60
NAME OF LSTK CONTRACTCONTRACTOR
PROJECT
MONTH & YEARCLIENT
PMC : EIL
Page 3 of 37
I - INTRODUCTION
CLIENT :
PROJECT LOCATION :
PMC : M/s. EIL, NEW DELHI
DESIGN CAPACITY :
UNIT CAPACITY LICENSOR
CONTRACT VALUE : _____Rs.(IN CRORES)
SCOPE OF WORK :
PROJECT TARGET DATES (UNIT WISE)
EFFECTIVE START DATE :
TARGET COMPLETION DATE :
CONTRACTUAL COMPLN DATE :
CONTRACTUAL COMMNG DATE :
(If Applicable)
ANT. MECH COMPLN DATE :
ANT. COMMG DATE :
(If Applicable)
PROJECT DURATION :_________ MONTHS
TIME ELAPSED :__________MONTHS
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 21/60
NAME OF LSTK CONTRACTCONTRACTOR
PROJECT
MONTH & YEARCLIENT
PMC : EIL
Page 4 of 37
II - EXECUTIVE SUMMARY
EXECUTIVE SUMMARY SHALL SERVE AS SYNOPSIS OF THE PROJECT. IT NEEDS TOFOCUS ON THE FOLLOWING :
- OVERALL SCHEDULE AND ACTUAL PROGRESS TO BE SPECIFIED(CUMULATIVE AND DURING THE MONTH)
- LIMIT IT TO ONE PAGE AS FAR AS POSSIBLE.
- MAJOR MILESTONES ACHIEVED DURING THE MONTH.
- CONTINGENCY/ CRASH ACTION PLAN FOR MOST CRITICAL AREAS, IF ANY,
BEING FORMULATED / IMPLEMENTED.
- SIGNAL FOR THE AREAS LIKELY TO BECOME CRITICAL.
- ANY OTHER ISSUE NOT LISTED ABOVE.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 22/60
NAME OF LSTK CONTRACTCONTRACTOR
PROJECT
MONTH & YEARCLIENT
PMC : EIL
Page 5 of 37
III - DETAILED STATUS (UNITWISE / DISCIPLINEWISE)
A. RESIDUAL BASIC ENGINEERING
- ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH
B. DETAILED ENGINEERING - ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH
C. PROCUREMENTi) ORDERING
- ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH
ii) MFG/DELIVERY- ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH
D. SUB-CONTRACTING- ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH
E. CONSTRUCTION /PRE-COMMISSIONING & COMMISSIONING- ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH
F. PACKAGE SUB-CONTRACTOR STATUSPACKAGE SUB-CONTRACTORWISE STATUS TO BE GIVENFUNCTIONWISE AS APPLICABLE)
i) ENGINEERINGii) ORDERINGiii) MANUFACTURING & DELIVERYiv) CONSTRUCTION
- ACTIVITIES COMPLETED DURING THE MONTH- ACTIVITIES PLANNED FOR THE NEXT MONTH
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 23/60
NAME OF LSTK CONTRACT MONTH & YEAR
CONTRACTOR CLIENT
PROJECT PMC : EIL
PAGE 6 OF 37
IV - AREAS OF CONCERN WITH ACTON PLAN
(UNITWISE / DISCIPLINEWISE)
SR. IMPACT ON ACTION TARGET
NO. AREAS OF CONCERN CONSTRAINTS SCHEDULE ACTION PLAN BY DATE(IN MONTHS)
NOTE
1. THIS SHALL CONTAIN ONLY CRITICAL ITEMS/ISSUES WHICH ARE DIRECTLY AFFECTING THE PROJECT SCHEDULE
OTHER ITEMS CAN BE PLACED IN PROBLEMS & HOLD UPS CHAPTER.
2 TARGET DATES SHALL BE FURNISHED WITH ACTION PLAN.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 24/60
NAME OF LSTK CONTRACT
CONTRACTOR
PROJECT
V - PROGRESS STATISTICS
A OVERALL PROJECT PROGRESS
DESCRIPTION WTD % AGE DURING THE MONTH CUMULATIVE
COMPLEX SCHEDULE ACTUAL SCHEDULE ACTUAL
RESIDUAL BASIC ENGINEERING
DETAILED ENGINEERING
ORDERING
MANUFACTURING/DELIVERY
SUB-CONTRACTING
CONSTRUCTION
COMMISSIONING
OVERALL PROGRESS - PHYSICAL Σ Α=100%
B. PROCESS UNIT (UNITWISE)
B.1 UNIT NAME
DESCRIPTION WTD % AGE DURING THE MONTH CUMULATIVE
COMPLEX UNIT SCHEDULE ACTUAL SCHEDULE ACTUAL
RESIDUAL BASIC ENGINEERING
DETAILED ENGINEERING
ORDERING
MANUFACTURING/DELIVERY
SUB-CONTRACTING
CONSTRUCTION
COMMISSIONING
PHYSICAL PROGRESS UNIT- A1 A1 % 100
B.2 UNIT NAME
B.3 UNIT NAME
B.4 UTILITIES /OFFSITES
DESCRIPTION WTD % AGE DURING THE MONTH CUMULATIVE
COMPLEX UNIT SCHEDULE ACTUAL SCHEDULE ACTUAL
RESIDUAL BASIC ENGINEERING
DETAILED ENGINEERING
ORDERING
MANUFACTURING/DELIVERY
SUB-CONTRACTINGCONSTRUCTION #
COMMISSIONING
PHYSICAL PROGRESS
UTILITIES /OFFSITESA4 % 100
MONTH & YEAR
CLIENT
PMC : EIL
PAGE 7 OF 37
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 25/60
NAME OF LSTK CONTRACT
CONTRACTOR
PROJECT
C. SUB CONTRACTED PACKAGES (PROCESS UNIT,UTILITIES & OFFSITES) C.1 PACKAGE - 1
DESCRIPTION WTD %AGE DURING THE MONTH CUMULATIVE
w.r.t U/OFF UNIT SCHEDULE ACTUAL SCHEDULE ACTUAL
RESIDUAL BASIC ENGINEERING
DETAILED ENGINEERING
ORDERING
MANUFACTURING & DELIVERY
CONSTRUCTION
COMMISSIONING
PHYSICAL PROGRESS RWTP X1 100
C.2 PACKAGE - 2
C.3 PACKAGE -3
D. MAJOR REASONS FOR SHORTFALL
NOTE:
3. UNIT WISE ALL SUBCONTRACTED PACKAGES TO BE REPORTED UNDER SUBHEADING "SUB CONTRACTED PACKAGE".
4. # CONSTRUCTION INCLUDES %AGE PROGRESS OF SUB-CONTRACTED PACKAGES IF ANY IN THE RESPECTIVE UNIT /
OFFSITES & UTILITIES AS DETAILED IN THE ANNEXURE TO CONSTRUCTION PROGRESS.
1. WHEREIN THE GAP BETWEEN SCHEDULE & ACTUAL %AGE PROGRESS IS MORE THAN 5 % , EXPLANATION
FOR THE BACK LOG/GAP REQUIRED TO BE FURNISHED IN THIS SHEET.
2. ALL COMPONENTS OF THE PROJECT IN LSTK CONTRACTOR'S SCOPE AS PER THE CONTRACT, SHOULD BE REPORTED IN
IN THE PROGRESS STATISTICS.
MONTH & YEAR
CLIENT
PMC : EIL
PAGE 8 OF 37
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 26/60
NAME OF LSTK CONTRACT
CONTRACTORPROJECT
VI. MILESTONE STATUS
(CURRENT + 2 MONTHS)
STATUS AS ON :
S. MILESTONE DESCRIPTION SCHEDULE LATEST ACTUAL FORECAST STATUS/
NO.DATE
ALLOWABLE
DATEDATE DATE REMARKS
1 GENERAL
2 UNIT
2.1 RESIDUAL BASIC ENGINEERING
2.2 DETAILED ENGINEERING
2.3 PROCUREMENT
a) ORDERING
b) MANUFACTURING & DELIVERY
2.4 SUB-CONTRACTING
2.5 CONSTRUCTION
2.6 PRECOMMISSIONING
2.7 COMMISSIONING
NOTE : ALL MILESTONES (UNIT WISE AND FUNCTION WISE) AS AGREED DURING KICK OFF MEETING ARE TO BE LISTED.
MONTH & YEAR
CLIENT
PMC : EIL
PAGE 9 OF 37
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 27/60
NAME OF LSTK CONTRACT MONTH & YEAR
CONTRACTOR CLIENT
PROJECT PMC : EIL
PAGE 10 OF 37
VII - PROBLEMS / HOLD-UPS
(UNIT WISE / DISCIPLINE WISE)
SR.
NO.PROBLEM / HOLD-UPS ACTION PLAN ACTION BY TARGET DATE
1
2
3
4
5
NOTE : ONLY POINTS WHICH AFFECT THE PROGRESS BUT MAY NOT
HAVE THE IMPACT ON THE PROJECT SCHEDULE SHALL BE LISTED HERE.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 28/60
NAME OF LSTK CONTRACT MONTH & YEAR
CONTRACTOR CLIENT
PROJECT MC : EIL
PAGE 11 0F 3
ANNEXURE - I (A)
NOTE :
2. OVERALL (AT CONTRACT LEVEL) SEPARATELY FOR EACH FUNCTION AND ONE CURVE FOR PHYSICAL PROGRESS
1. UNIT WISE SEPARATE CURVE FOR EACH FUNCTION AND CURVE FOR PHYSICAL PROGRESS
PROJECT - (Name of contract)FUNCTION / PHYSICAL
0
10
20
30
40
50
60
70
80
90
100
C U M U L A T I V E % P
R O G R E S S
0
5
10
15
20
25
30
35
40
45
M O N T H L Y % P
R O G R E S S
SCH DURING THE MONTH 0 10 42.5 14.5 ACT. DURING THE MONTH 0 15 24 19
CUMM. SCH 5 15 57.5 72 80 85 90 95 100
CUMM. ACT 3 18 42 61
D'00 J'01 F'01 M'01 A'01 M'01 J'01 J'01 A'01
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 29/60
NAME OF LSTK CONTRACT
CONTRACTOR
PROJECT
ANNEXURE - II (A)
CHRONOLOGICAL ACHIEVEMENTS
S. NO. DESCRIPTION OF KEY MILESTONES SCH. DATE ACTUAL DATE OF
OCCURRENCE
1. GENERAL
2. UNITWISE (AS APPLICABLE)
2.1 RESIDUAL BASIC ENGINEERING
2.2 DETAILED ENGINEERING
2.3 ORDERING
2.4 MANUFACTURING & DELIVERY
2.5 SUB-CONTRACTING
2.6 CONSTRUCTION
2.7 SUB-CONTRACTED PACKAGES
2.8 PRECOMMISSIONING
2.9 COMMISSIONING
NOTE : MECHANICAL COMPLETION & COMMISSIONING DATES SHALL
ALSO BE RECORDED.
MONTH & YEAR
CLIENT
PMC : EIL
PAGE 12 OF 37
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 30/60
NAME OF LSTK CONTRACT MONTH & YEAR
CONTRACTOR CLIENT
PROJECT EIL
PAGE 13 OF 37
ANNEXURE :II (B.1)
SUMMARY STATUS OF ENGINEERING DRAWINGS
(SUMMARY LEVEL & UNIT WISE SEPARATELY)
TOTAL DRAWINGS RELEASED (NOS.) REVIEW STATUS (NOS.) SUBMISSION PROGM.
DISCIPLINE DRAWINGS DURING THE MONTH CUMULATIVE TOTAL DRGS. CO DE 1 C ODE 2 C ODE 3 FOR NEXT MONTH REMARKS
NOS. SCH. ACT. SCH ACT FOR REVIEW FRESH CODE 3
ARCHITECTURAL
GENERAL CIVIL
STRUCTURAL
PIPING
GAD's
ISO's
ELECTRICAL
INSTRUMENTATION
TOTAL
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 31/60
NAME OF LSTK CONTRACT
CONTRACTOR
PROJECT
PROJECT NAME
USE WTD. DRAFT CHECK IST % WTD REV.
CODE VALUE COMPL. COMPL. SUBM. CODE 2 CODE 1 PROG. PROG. CODE
* * * * *
SCH.A/F
SCH. A/F
SCH. A/FSCH. A/FSCH. A/FSCH. A/F
SCH. A/F
SCH. A/F
LEGEND I: INFORMATION R: REVIEW A : APPROVALS : STUDY A: STATUTORY / CLIENT REVIEWP: PURCHASE C: CONSTRUCTIONT: TENDERING L: CALCULATION
NOTE : 1. INDICATE A/F (ACTUAL / FORECAST)AS APPLICABLE WITH THE DATES.
2. * PERCENTAGE FOR AGREED MILESTONES AS PER PROGRESS MEASUREMENT METHODOLOGY.
3. THIS INCLUDES PROCESS / BASIC ENGG. DELIVERABLES.
REMARKS
CATEGORY (CAT.):
USE CODE :-
DRAWING / DOCUMENT TITLEDRG. NO. CAT.
REV
.
NO.
MILESTONESREVIEW
DISCIPLINE : PROCESS
DRAWINGS / DOCUMENTS RELEASE SCH. (DCI)
(UNITWISE / DISCIPLINEWISE)
ANNEXURE - II(B.2)
STATUS AS OF : DD/MM/YYYY
MONTH & YEAR
CLIENT
PMC : EIL
Page 14 of 37
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 32/60
MONTH & YEAR
CLIENT
PMC : EIL
PAGE : 15 OF 37
MCI: MATERIAL CONTROL INDEX (UNIT WISE / DISCIPLINE WISE)ANNEXURE : II (B.3)
STATUS AS ON: DD/MM/YY
ISSUE OF MR PREPARE TBA PREP OF PR
APPROVAL OF
PR / 1ST REVIEW
OF VENDOR
DRGS
APPROVAL OF
VENDOR
DRGS/DOCS
REMARKS / REASONS FOR DELAY
20% 30% 10% 10% 30%
<DISCIPLINE>1 SCH
ACT/FORECAST
2 SCH ACT/FORECAST
3 SCH
ACT/FORECAST
4 SCH
ACT/FORECAST
5 SCH
ACT/FORECAST
6 SCH
ACT/FORECAST
7 SCH
ACT/FORECAST
8 SCH
ACT/FORECAST
9 SCH
ACT/FORECAST
10 SCH
ACT/FORECAST
11 SCH
ACT/FORECAST
12 SCH
ACT/FORECAST
13 SCH
ACT/FORECAST
14 SCH ACT/FORECAST
15 SCH
ACT/FORECAST
TOTAL SCH ______%
ACT/FORECAST ______%
LEGEND: CATEGORY (CAT.) : I : INFORMATION R : REVIEW A : APPROVAL
S : STUDY A : STATUTORY / CLIENT REVIEW
USE CODE :- P : PURCHASE C : CONSTRUCTION
T : TENDERING L : CALCULATION
NOTE : 1. INDICATE A/F (ACTUAL / FORECAST) AS APPLICABLE WITH THE DATES.
2. * PERCENTAGE FOR AGREED MILESTONES AS PER PROGRESS MEASUREMENT METHODOLOGY.
3. THIS INCLUDES PROCESS / BASIC ENGG. DELIVERABLES.
S. NODRAWING/DOCUMENT
NUMBER
NAME OF LSTK CONTRACT :
CONTRACTOR :
PROJECT :
WEIGHTED
PROGRESS
CATERG
ORY
(A/R/I)
WTD
VALUE
DRAWING / DOCUMENT
DESCRIPTION
PLEASE REFER
ANNEXURE :
II (C)
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 33/60
NAME OF LSTK CONTRACT
CONTRACTOR
PROJECT
ANNEXURE - II(C)
PROJECT NAME
SL WTD. REV. NO. REVIEW PROG REMARKS &
NO VALUE CODE Ist SUBM. REV. CODE-2 CODE-1 (%) STATUS
* * *
NOTE :
2. ALL VENDOR / PACKAGE CONTRACTOR DRAWINGS DOCUMENTS TO BE LISTED.
1. * - AGREED MILESTONE PERCENTAGE
DRG. NO. DESCRIPTION
DATE
ENDOR / PACKAGE CONTRACTOR NAME : ……………………….
VENDOR/PACKAGE CONTRACTOR DRAWINGS & DOCUMENTS STATUS (UNITWISE / DISCIPLINEWISE)
STATUS AS OF : DD/MM/YYYY
MONTH & YEAR
CLIENT
PMC : EIL
PAGE 16 OF 37
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 34/60
NAME OF LSTK CONTRACT
CONTRACTOR
PROJECT
UNIT NAME / SUMMARY LEVEL
ANNEXURE : II (D.1)
ORDERING STATUS (SUMMARY)
(LOCAL(INDIAN) & FOREIGN PROCUREMENT SEPARATELY)
TOTAL MR ISSUE BIDS FOI/TOI PO
CATEGORYMRs ISSUED ENQUIRY DUE ISSUED ISSUED
SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT
EQUIPMENT
COLUMNS
EXCHANGERS
TOTAL
BULK
TOTAL
NOTE :
2. SEPERATE STATUS FOR EACH UNIT AND AT PROJECT SUMMARY LEVEL.
1. NUMBER OF MRs SHALL BE PROVIDED FOR EACH MILESTONE AGAINST EACH EQUIPMENT CATEGORY AS COLUMN,
EXCHANGERS, PUMPS ETC. AND BULK MATERIAL.
MONTH & YEAR
CLIENT
PMC : EIL
PAGE: 17 OF 37
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 35/60
NAME OF LSTK CONTRACT MONTH & YEAR
CONTRACTOR CLIENT
PMC : EIL
PROJECT PAGE: 18 OF 37
UNIT_______________
DESCRIPTION WTD. CAT MR ISSUE RECV TBA FOI/TOI PO L/C % VENDOR/ PO NO. PR REV. REV. CDD
MR NO. ITEM NO. VAL. RELS ENQ. BIDS ISSUED ISSUE ISSUE OPEN PROG LOCATION /DATE REVIEW CODE 2 CODE REMARKS
DATE
SCH.
A/F
SCH.
A/F
SCH.
A/F
SCH.
A/F
SCH.
A/F
SCH.
A/F
SCH.
A/F
1. INDICATE A/F (ACTUAL/FORECAST) AS APPLICABLE WITH THE DATES
2. CONTRACTUAL DELIVERY DATE (CDD) IS TO BE QUALIFIED IN REMARKS COLUMN
(I.E EX WORKS, FOT, FOB, AT SITE ETC.)
NOTE :
MECHANICAL
ORDERING STATUS (DETAILED)
(DISCIPLINEWISE FOR EACH UNIT)
ANNEXURE - II(D.2)
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 36/60
NAME OF LSTK CONTRACT
CONTRACTOR
PROJECT
UNIT / SUMMARY * ANNEXURE: II(E.1)
EQUIPMENT DELIVERY STATUS (SUMMARY)
EQUIPMENT TOTAL QTY IN DELIVERY FORECAST AT SITE FOR BAL. EQPT.
DESCRIPTION NOS DESPATCHED TRANSIT CALENDAR MONTHS --------->
SCH. ACT. (NOS.) SCH. ACT (NOS.) 1 2 3 4 5 6
COLUMNS
VESSELS
REACTORS
EXCHANGERS
AIR COOLERS
PUMPS
COMPRESSORS
FANS
MISC. (MAJOR CRITICAL ITEMS)
TOTAL
NOTE 1. STATUS FOR INDEGENOUS AND IMPORTED EQUIPMENT SHALL BE FURNISHED SEPARATELY
2. * SEPARATE STATUS FOR EACH UNIT AND AT SUMMARY LEVEL.
QUNTITY ORDERED
(NOS.)RECEIVED AT SITE (NO.)
MONTH & YEAR
CLIENT
PMC : EIL
PAGE: 19 OF 37
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 37/60
NAME OF LSTK CONTRACT
CONTRACTOR
PROJECT
UNIT / SUMMARY * ANNEXURE: II(E.2)
EQUIPMENT RECEIPT AND ERECTION STATUS (DETAILED)
(UNITWISE/DISCIPLINEWISE))
PO NO. EQPT EQUIPMENT ERECTION ENDOR NAME C.D.D DESPATCHED RECEIVED SITE FDN STRL. ERECTION HYDROTESTING
TAG NO. DESCRIPTION WT. LOCATION, ON AT SITE ASSEMBLY READY READY DATE DATE PAINTING NSULATION FIRE
( MT) COUNTRY (IF ANY) DATE DATE PROOFING
COLUMNS
a)
b)
VESSELS
REACTORS
EXCHANGERS
AIR COOLERS
PUMPS
COMPRESSORS
FANS/BLOWERS
OTHER ITEMS
ELECTRICAL EQUIPMENTS
NOTE : 1. ALL EQUIPMENT TO BE COVERED. TAGGED ITEMS WITH MULTIPLE SUFFIXES TO BE MENTIONED SEPARATELY. e.g 701-E-03 701-E-0 701-E-03C
2. * SEPARATE STATUS FOR UNIT AND AT SUMMARY LEVEL.
REQD. ATSITE (SCH,)
MONTH & YEAR
CLIENT
PMC : EIL
a e: 20 of 3
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 38/60
NAME OF LSTK CONTRACT
CONTRACTOR
PROJECT
UNIT NAME / SUMMARY LEVEL * ANNEXURE - II (E.3)
BULK MATERIAL STATUS (SUMMARY)
( LOCAL (INDIAN) AND FOREIGN PROCUREMENT SEPARATELY) STATUS AS OF : _______
QUANTITY FORECAST FOR
S.NO. ITEMWISE DESCRIPTION UOM TOTAL ORDERED RELEASED RECEIVED BALANCE STATUS/PROBLEMS
REQUIREMENT AT SITE DELIVERY
1 2 3 4 5
1 PIPES M
2 FITTINGS No.
3 FLANGES No.
4 VALVES No.
5 ELECTRICAL ITEMS (ALL)
ALL ITEMS
6 INSTRUMENTATION ITEMS
ALL ITEMS
NOTE : 1. SEPARATE STATUS FOR EACH UNIT AND AT SUMMARY LEVEL.
2. STATUS TO BE GIVEN SEPARATELY FOR LOCAL (INDIAN) AND IMPORTED PURCHASE.
MONTH & YEAR
CLIENT
PMC : EIL
PAGE: 21 OF 37
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 39/60
NAME OF LSTK CONTRACT MONTH & YEAR
CONTRACTOR CLIENT
PMC : EIL
PROJECT PAGE : 22 OF 37
ANNEXURE - II(E.4)
PROJECT NAME STATUS AS OF : DD/MM/YYYY
TAG NO./ DESCRIPTION WTD PO VENDOR/ INSPN ORDER RELSD RECD VENDOR RAW RAW MFG MFG FINAL CDD FOB/EX ARRIVAL ARRIVAL SITE %
ITEM OF ITEM VAL NO. LOCATION/ CAT QTY QTY QTY DRG MATL. MATL START FINISH INSPN WORKS INDIAN AT REQD PROG REMARKS
& COUNTRY REV. S/O RECPT DELY PORT SITE DATE
DATE * * * * * * * * *
SCH.
A/F
SCH.
A/F
SCH.
A/F
SCH.
A/F
SCH.
A/F
SCH.
A/F
SCH.
A/F
* - AGREED MILESTONE PERCENTAGE
INSPECTION CATEGORY ;- AS DESCRIBED IN INSPECTION METHODOLOGY. A/F :- ACTUAL / FORECAST
NOTE : 1 INDICATE A/F AS APPLICABLE WITH THE DATES (A/F :- ACTUAL / FORECAST)
2 BULK ITEMS LIST SHOULD INCLUDE PIPING, ELECTRICAL AND INSTRUMENTATION ITEMS.
3 IN CASE OF IMPORTED SHIPMENT NAME OF THE VESSEL AND PORT OF BOARDING TO BE INDICATED.
4 CONTRACTUAL DELIVERY DATE (CDD) IS TO BE QUALIFIED IN REMARKS COLUMN
(I.E. EX WORKS, FOT, FOB, AT SITE (AS APPLICABLE) ETC.)
INSPN. CAT.-
LEGEND
(LOCAL (INDIAN) AND FOREIGN PROCUREMENT SEPARATELY)
MANUFACTURING / DELIVERY STATUS(UNITWISE / DISCIPLINEWISE/ TAGWISE)
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 40/60
NAME OF LSTK CONTRACT MONTH & YEAR
CONTRACTOR CLIENT
PMC : EIL
PROJECT PAGE: 23 OF 37
ANNEXURE - II(F)
UNIT :
DESCRIPTION WTD ISSUE OF PREPARATION TENDER RECEIPT AWARD NAME DURATION CONTRACTUAL INTERMEDIATE
OF WORK VALUE TENDER OF TENDER ON OF BIDS OF %AGE OF OF COMPLETION CONTRACTUAL REMARKS
SPECS DOCUMENT SALE WORK PROGRESS AGENCY CONTRACT DATE MILESTONES
* * * * * (IF ANY)
SCH.
A/F
SCH.
A/F
SCH.
A/F
SCH.
A/F
SCH.
A/F
SCH.
A/F
SCH.
A/F
A/F :- ACTUAL/FORECAST
NOTE : 1. INDICATE A/F AS APPLICABLE WITH THE DATES.
* - AGREED MILESTONE PERCENTAGE
STATUS AS OF : DD/MM/YYYY
SUB-CONTRACTING STATUS
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 41/60
NAME OF LSTK CONTRACT
CONTRACTOR
PROJECT
UNIT ______________ ANNEXURE : II(G.1)
UNITWISE STATUS OF CONSTRUCTION QUANTITIES RELEASED ( DISCIPLINEWISE FOR EACH UNIT)
S. DISCIPLINE & LIKELY CUM BALANCE PROGRAMME FOR BALANCE QTY UNDER HOLDNO. MAJOR WORK ITEM UOM QTY RELEASED QTY TO BE MONTHS AND REASON FOR THE SAME
QTY RELEASED 1 ST 2ND 3RD 4TH 5TH 6TH
UOM : UNIT OF MEASUREMENT.
MONTH & YEAR
CLIENT
PMC : EIL
PAGE: 24 OF 37
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 42/60
NAME OF LSTK CONTRACT
CONTRACTOR
PROJECT
UNIT : ____________
QUANTITATIVE MONTHLY CONSTRUCTION PROGRESS STATUS ( UNITWISE/DISCIPLINEWISE)
ANNEXURE :II(G.2)
WORK ITEM UNIT OF TOTAL QUANTITY PROGRAM
DESCRIPTION MEASU- CUMMULATIVE DURING THE MONTH FOR NEXT
REMENT WORKLOAD FRONT COMPLETED PROGRAMME COMPLETED BACKLOG MONTH
EXCAVATION CM
BACK FILLING CM
RCC WORKS CM
BRICK WORK CM
A/G PPG - FAB ID
A/G PPG - ERN IM
U/G PPG - FAB ID
U/G PPG - ERN IM
INSTRUMENTATION
- LOOPCHECKING NOS
PERCENTAGE PROGRAMMED DURING THE MONTH :
PERCENTAGE ACHIEVED DURING THE MONTH : FRONT:
PERCENTAGE PROGRAMMED FOR NEXT MONTH : ACTUAL:
CUM. PERCENTAGE PROGRESS SCHEDULE :
MONTH & YEAR
CLIENT
PMC : EIL
PAGE: 25 OF 37
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 43/60
NAME OF LSTK CONTRACT MONTH & YEAR
CONTRACTOR CLIENT
PMC : EIL
PROJECT PAGE : 26 OF 37
UNIT :_______________ ANNEXURE : II (H)
SR. AGENCY DURATION CONTRACTUAL ACTUAL ACT/ANT CUM. % ACHIEVED
NO. SCOPE OF WORK (MONTHS) START COMPLN START COMPLN MONTHLY PROGRESS CONTRACTUAL FRONT* ACTUAL
DATE DATE DATE SCH. PROGM ACT. SCH AVAILABLE
SUMMARY
NOTE : 1. * FRONT INDICATES WORK THAT CAN BE TAKEN UP CONSIDERING AVAILABILITY OF DRAWINGS, MATERIALS AND ACCESS.
STATUS OF CONSTRUCTION
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 44/60
NAME OF LSTK CONTRACT MONTH & YEARCONTRACTOR CLIENT
PMC : EIL PROJECT PAGE : 27 of 37
UNIT :__________________ ANNEXURE : II (I)
LOOPWISE HYDROTESTING STATUS
NO. OF LOOPS
HYDROTESTED LOOPS UNDER HOLD REMARKS
THIS MONTH CUMULATIVE MATERIAL ERECTION TOTAL
SCH. ACT. SCH. ACT.
1.0 UNIT I 100 50 30 20 20 20 15 5 20 10 35 15 50
SERVICEWISE /
SYSTEMWISE
2.0 UNIT II
SERVICEWISE /
SYSTEMWISE
3.0 OFFSITES PART A
SERVICEWISE
4.0 OFFSITES PART B
SERVICEWISE
5.0 PACKAGES
SERVICEWISE
TOTAL
NOTE : REPORTING SHALL START AFTER PREPARATION OF LOOPWISE PIPING COMPLETION SCHEDULE
CHECK
LISTED
MECH.
CLEARED
RADIO-
GRAPHY
CLEARED
SR
CLEARED
FRONT
AVAILABLE
SR.
NO.DESCRIPTION
TOTAL
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 45/60
NAME OF LSTK CONTRACT MONTH & YEAR
CONTRACTOR CLIENT
PMC : EIL
PROJECT PAGE : 28 OF 37
UNIT : ______________ ANNEXURE : II (J)
SYSTEM HANDING OVER STATUS (UNITWISE)
S.NO. SYSTEM DESCRIPTION FORMAT I ISSUE DATE FORMAT II ISSUE DATE FORMAT III ISSUE DATE FORMAT IV ISSUE DATE FORMAT V ISSUE DATE
A. SYSTEM I TARGET DATE
ACTUAL DATE
B. SYSTEM II TARGET DATE
ACTUAL DATE
C. SYSTEM III TARGET DATE
ACTUAL DATE
TARGET DATE
ACTUAL DATE
TARGET DATE
ACTUAL DATE
GRAND TOTAL TARGET (NOS.)
ACTUAL (NOS.)
LEGEND :
FORMAT I : INFORMATION REGARDING SYSTEM COMPLETIONFORMAT II : CHECKLIST
FORMAT III : READY FOR PRE-COMMISSIONING \ MECH COMPLENTION CERTIFICATE
FORMAT IV : READY FOR COMMISSIONING CERTIFICATE
FORMAT V : COMPLETION OF COMMISSIONING CERTIFICATE
NOTE : 1. TO BE FURNISHED SEPARATELY FOR EACH UNIT
2. REPORTING SHALL START AFTER PREPARARTION OF SYSTEMWISE COMPLETION SCHEDULE
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 46/60
NAME OF LSTK CONTRACT
CONTRACTORS
PROJECTANNEXURE - II(K.1)
(1) LABOUR (2) MANAGEMENT & SUPERVISION
F O R E M A N
C A R P E N T E R S
B A R B E N D E R
M A S O N S
B A T C H P L A N T L A B .
W E L D E R S - S T R L .
W E L D E R S - P I P E
R I G G E R S
P I P E / F A B N . F I T T E R S
G A S C U T T E R
G R I N D E R S
E L E C T R I C I A N
I N S T . F I T T E R S
I N S U L A T O R S
O P E R A T O R / D R I V E R
S C A F F O L D E R S
S T R L . E R E C T O R S
P A I N T E R S
S T R L . F I T T E R S
I N S T R . T E C H N I C I A N S
M I L L W R I G H T F I T T E R S
M E C H A N I C S
S A N D B L A S T E R S
C R A N E O P E R A T O R S
T A C K W E L D E R S
F A B R I C A T O R S
D R I L L E R S
G U N I T O R
L A G G E R S
U N S K I L L E D L A B O U R
O T H E R S
S U B T O T A L : ( 1 )
M A N A G E R S
E N G . D E P T .
A D M N . D E P T .
P R O J E C T C O N T R O L
Q A / Q C D E P T .
S I T E E N G .
S I T E S U P E R V I S O R S
S A F E T Y D E P T .
S U R V E Y O R S
O T H E R S
S U B T O T A L : ( 2 )
G R A N D T O T A L : ( 1 ) + ( 2 )
PLAN
ACT
PLAN
ACT
PLAN
ACT
PLAN
ACT
GRAND PLAN
TOTAL ACT
NOTE : REASON FOR DEVIATION BETWEEN MONTHLY CONSTRUCTION PROGRAMME AND ACTUAL TO BE MENTIONED. (USE SEPARATE SHEET IF NECESSARY)
P L A N / A C T
NAME OF UNIT
UNITWISE DEPLOYMENT OF LSTK PERSONNEL AT CONSTRUCTION SITEMONTHLY CONSTN. PROGRAMME(%):
MONTHLY CONSTRN. ACTUAL (%) :
MONTH & YEAR
CLIENT
PMC : EIL
PAGE 29 OF 37
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 47/60
NAME OF LSTK CONTRACT
CONTRACTOR
PROJECT
UNITWISE RESOURCE DEPLOYMENT STATUS ( FOR THE MONTH OF : ___________)
EQUIPMENT & MACHINERY ANNEXURE : II (K.2)
SL NO NAME OF UNIT
E Q U
I P M E N T / M A C H I N E R Y
E X C A V A T O R S
D U M P L O A D E R S
C O N C M I X E R S
D O Z E R S
W A T E R T A N K S
D
G S E T S 1 2 5 / 8 2 . 5 K W
D W P
U M P S
R O L L I N G M A C H I N E S
J A C K
H A M M E R S
C O M P R E S S O R S
C O M P A C T O R S
V I B R A T O R S
W E L D I N G M A C H I N E
C O
A T I N G / W R A P P I N G M / C
R O A D R O L L E R S
V I B R O R O L L E R S
P A Y L O A D E R S
P I P E B E N D I N G M / C
D R I L L I N G M / C R I G S
R O C K B R E A K E R S
W A T E R P U M P S
S H E
A R I N G / G R O O V I N G M / C
B A T C H I N G P L A N T
M O T O R G R A D E R S
L O R R Y / C A R S / J E E P S
C R A N E S / H Y D . C R A N E S
W A G O N D R I L L E R S
T
R A C T O R S / T R A I L O R S
W I N C H / H O I S T
T R A N S I T M I X E R S
B A R B E N D I N G M / C
G R I N D I N G M / C ( A G )
O V E
N S M O T H E R / P O R T A B L E
P U G C U T T I N G M / C
S C R E W
J A C K
M
A G N E T I C D R I L L M / C
H
A N D C U T T I N G S E T S
P A V . B R E A K E R S
B A R C U T T I N G M / C
C U B E T E S T I N G M / C
S A
N D B L A S T I N G H O P E R
H O T M I X P L A N T
M O B I L E D G S E T S
H Y D R A ( 8 T )
2 5 0 M T C R A N E S
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
REQUIRED
DEPLOYED
TOTAL REQUIRED
DEPLOYED
PROGRAMME %AGE :-
%AGE PROGRESS ACHIEVED :-
MONTH & YEAR
CLIENT
PMC : EIL
PAGE 30 OF 37
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 48/60
UPDATED PROJECT SCHEDULE
NAME OF LSTK CONTRACT :
CONTRACTOR :
PROJECT :
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 49/60
NAME OF LSTK CONTRACT MONTH & YEAR
CONTRACTOR CLIENT
PMC : EIL
PROJECT PAGE 32 OF 37
ANNEXURE : II (M) .
REQUIRED BY RECEIVED ON
1CHIEF INSPECTOR OF FACTORIES FOR PLANT
LAYOUT
a) CONSTRUCTION
b) AS BUILT
2 MUNICIPAL CORPORATION FOR VARIOUS BUILDINGS
3CIVIL AVIATION FOR FLARE STACK OF CHARGE
HEATER
4 FIRE & NUISANCE DEPARTMENT FOR FURNACE
STACK ( CHARGE STACK)
5 NOC FROM MUNICIPAL CORP. FOR ALL FACILITIES
6 IBR FOR STEAM PIPING & EQUIPMENTS
7 IBR FOR CHARGE HEATER
8 TAC FOR FIRE WATER & FIRE FIGHTING SYSTEM
9CCE FOR PLANT LAYOUT, FIRE FIGHTING SYSTEM &
TANK
10CEI APPROVAL FOR H.V ELECTRICAL DISTRIBUTION
SYSTEM
11 ANY OTHER STATUTORY & GOVT. APPROVALS
(LIST THE SAME)
@@ NOTE : PROBLEMS IF ANY HOLDING APPROVAL SHALL BE HIGHLIGHTED IN THE STATUS COLUMN.
STATUTORY APPROVAL STATUS (APPROVALS TO BE LISTED UNDER THE HEADS OF (A) FOR DESIGN / DRAWINGS AND (B) FOR INSTALLATION)
APPROVAL DATE
REMARKS@@ STATUSAPPROVALSSL. NO.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 50/60
AMOUNT CERT.RECD
TOTAL 0 0 0 0 0 0
NUMBER & DATE VALUE NET AMOUNT DATE
INVOICING STATUS
SR.NO
SERVICE TAX
& OTHER
DEDUCTIONS
TOTAL
DEDUCTIONS
REASONS FOR OTHER
DEDUCTIONS/
REMARKS
DEDUCTIONS
INCOME TAX
INVOICE RECEIPT
PAGE 33 OF 37
ANNEXURE - II(N)
NAME OF LSTK CONTRACT
PROJECT
MONTH & YEAR
CONTRACTOR CLIENT
PMC : EIL
Sheet 1 of 1
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 51/60
MONTH & YEAR
CONTRACTOR CLIENT
PMC : EIL
PAGE 34 OF 37
ANNEXURE - II(O)
SR. NO WAIVER/ DEVIATION PERMIT NO/ LETTER REF NO DATE SUBJECT REMARKS STATUS
A
B DEVIATION PROPOSED
STATUS OF WAIVERS/ DEVIATIONS
SUBMITTED IN FORMAT
NAME OF LSTK CONTRACT
PROJECT
Sheet 1 of 1
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 52/60
ANNEXURE : II(P-i)
SCH ACT SCH ACT
1 HMTD
2 GENERAL CIVIL
3 ARCHITECTURE
4 STRUCTURAL
5 PIPING
6 PRESSURE VESSELS
7 ROT.EQUIPMENT
8 MECH.EQUIPMENT
9 ELECTRICAL
10 INSTRUMENTATION
TOTAL 100.0
100.0 97.4
PROJECT
NAME OF LSTK CONTRACT
DEVIATIONDURING THE
MONTH %
CUMULATIVE
PROGRESS %
DELAY ANALYSISANALYSIS
SR.
NOREMARKSDISCIPLINE
WTD
VALUE
%
MONTH & YEAR
CONTRACTOR CLIENT
PMC : EIL
PAGE 35 OF 37
Sheet 1 of 2
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 53/60
MONTH & YEAR
CONTRACTOR CLIENT
PMC : EIL
PAGE 36 OF 37
ANNEXURE - II(P-ii)
SCH ACT
1 HMTD
2 GEN. CIVIL
3 ARCHITECTURE
4 STRUCTURAL
5 PIPING
6 ROTATING EQPT
7 MECHANICAL
8 ELECTRICAL
9 INSTRUMENTATION
NAME OF LSTK CONTRACT
PROJECT
DELAY ANALYSIS
SR. NO REMARKSDISCIPLINE ACTIVITY/ ITEMDRG NO/
MR NODEVIATION
CUMULATIVE
PROGRESS %
Sheet 2 of 2
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 54/60
NAME OF LSTK CONTRACTCONTRCTOR
PROJECT
MONTH & YEARCLIENT
PMC : EIL
Page 37 of 37
ANNEXURE : II (Q) PROJECT PHOTOGRAPHS
NOTE : COLOUR PHOTOGRAPHS SHOWI NG KEY PROJECT ACTI VI TI ES e. g
MANUFACTURI NG OF CRI TI CAL EQUI PMENT, TRANSPORTATI ON OF ODC
I TEMS, CONSTRUCTI ON/ ERECTI ON OF MAI N AREAS / EQUI PMENT SHALL
BE I NCLUDED EVERY MONTH.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 55/60
FLOW OF DOCUMENTS FROM LSTK CONTRACTOR
Note : 1. Documents to be submitted by the bidder along with Bid are listed in clause 4.0
2. LSTK Contractor shall submit electronic file along with hard copy wherever “*” is marked below
3. Number of copies to be submitted by LSTK Contractor for each document indicated below are indicat
as per project requirement by Project Manager before including in the bid document.
S.NO. DESCRIPTION OF DOCUMENT FREQUENCY / TIME OF RECEIPT
NO. OF COPIES
CLIENT
(HO)
CLIENT
(SITE)
PMC
(HO)
PMC
(SITE) D
1. 90 Days Front End schedule With in one week of award 2 2 4* 2*
2a.
2b.
Procedure for Planning Scheduling and Monitoring
along with sample formats.
Progress Measurement Methodology
During kick off Meeting ( To be held within two
weeks of award )2 1 2 2
3a.
3b.
Overall Project Schedule ( Unit wise ) – Detailed &
Summarised
Updation of overall Project schedules
( Unit wise )
With in four weeks of award.
Monthly summarized schedule to be submitted
with monthly progress report. Detailed schedule
to be submitted separately on monthly basis.
4
2
2
1
4*
3*
2*
2*
4a. Unit wise Functional Schedules in resource based
bar chart with “s” curves
- Residual Basic Engineering Schedules
- Detailed Engineering Schedules
- Ordering Schedules
- Manufacturing & Delivery Schedule
- Sub-contracting Schedule
Within 6 weeks of award
Schedules of different disciplines to be
submitted as separate documents
- - 4* -
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 56/60
FLOW OF DOCUMENTS FROM LSTK CONTRACTOR
S.NO. DESCRIPTION OF DOCUMENT FREQUENCY / TIME OF RECEIPT
NO. OF COPIES
CLIENT
(HO)
CLIENT
(SITE)
PMC
(HO)
PMC
(SITE) D
4b. Updation of Functional Schedule and “S” Curve Monthly 2 1 2* 2*
5a.
5b.
Construction Network (Unit wise) with contract
level, unit level and discipline “S” curves.
Updation of Construction Network and “S” curves (
Unit wise )
Within eight weeks of award or one month
before start of construction activities, which
ever is earlier.
Monthly
1
1
1
1
3*
1
2*
2*
6a.
6b.
Loop wise piping completion schedule
Updation of loop wise piping completion schedule
Two months before start of hydro -testing as
scheduled in unit wise construction network
Weekly, to be submitted before review meeting
1
1
1
1
3*
1
2*
2*
7a.
7b.
System wise completion schedule
Updation of system wise completion schedule
Six weeks before scheduled completion as per
unit wise construction network
Weekly, to be submitted before review meeting
1
1
1
1
3*
1
2*
2*
8a.
8b.
Pre-commissioning / commissioning schedule
Updation of Pre-commissioning / commissioning
schedule
Two months before scheduled mechanical
completion or one month before starting of
Pre-commissioning activities as per unit wise
construction, whichever is earlier.
Weekly, to be submitted before review meeting
1
1
1
1
3*
1
2*
2*
9. Catch up Schedules
a. For Overall Project Schedule
b. For Construction Networks
c. Updation
As desired by Client/PMC
As per 3b & 5b.
2
2
2
14*
3*
2*
2*
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 57/60
FLOW OF DOCUMENTS FROM LSTK CONTRACTOR
S.NO. DESCRIPTION OF DOCUMENT FREQUENCY / TIME OF RECEIPT
NO. OF COPIES
CLIENT
(HO)
CLIENT
(SITE)
PMC
(HO)
PMC
(SITE) D
10a.
10b.
Sub-contractor schedules with “S” curves including
all Sub-Contractor Packages like Heater, DM Plant
etc,
Updation of Sub-contractor schedules with “S”
curves
To be made within two weeks of award of Sub-
Contract
To be submitted when called for by the owner /
PMC.
Fortnightly
As called for
11. Monthly Programme
a. Design Office Activities
b. Construction Activities
Within three calendar days of monthly progress
report cut off date
Within two calendar days of monthly progress
report cut off date
As desired 2
2
2
2
12. Monthly Progress Report Monthly, within 5 calendar days from cut off
date
4 2 2* Files as
mentioned
above
2* Files as
mentioned
above
13. Weekly Progress Report ( Over all ) Weekly / within 3 calendar days of cut off date. 1 1 2 2
14. Weekly Progress Report ( Construction ) Weekly / within 2 calendar days of cut off date. 1 1 2 2
15. Daily Progress Report ( Site ) Daily / before noon of next day 1 1 2 2
16. Expediting Report Fortnightly 1 1 2 2
17. Planning Package Within 12 weeks of award. 2 2 2 2
Note: All the above deliverables shall also be furnished in soft form (native format) along with hard copies.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 58/60
ATTACHMENT – V
Page 1 of 3
INDICATIVE PROGRESS MEASUREMENT WEIGHTAGE AT VARIOUS LEVELS
I Function Level
PROCESS UNITS UTILITIES & OFFSITEResidual basic engineering 01.0 01.0Engineering 10.0 10.0Ordering/purchase 03.0 03.0Manufacturing & delivery 54.0 30.0Construction. 30.0 54.0Pre-commg. and Commissioning 02.0 02.0and Handing over.
II Discipline Level
ENGINEERING: Avg Range
CIVIL/ STRUCTURAL 20 (15-25)PIPING 35 (30-40)HEAT EQUIPMENT 06 (03-09)PRESSURE VESSELS 06 (03-09)MECH.EQUITMENT/SYSTEMS 12 (08-16)ELECTRICAL 08 (06-18)INSTRUMENTATION 13 (08-24)
ORDERING & MANUFACTURING AND DELIVERY:PIPING 16HEAT EQUIPMENT 19PRESSURE VESSELS 18MECH.EQUIPMENT/SYSTEMS 28ELECTRICAL 07INSTRUMENTATION 12
CONSTRUCTION (PROCESS UNITS):PILING (IF APPLICABLE) 02CIVIL WORK 22STRUCTURAL 03PIPING & EQUIPMENT ERECTION 40HEATERS 10INSULATION 03PAINTING 01
ELECTRICAL 06INSTRUMENTATION 08MISCELLENEOUS 05
Note : In case of utilities and offsites, package/system wise weight factors and then todiscipline wise weight factors shall be developed. This will be more relevant in case theEPCC contractor is sub contracting some packages on turnkey basis. For example: RWSystem etc.
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 59/60
ATTACHMENT – V
Page 2 of 3
III Deliverable weightages
PROCESS:DESIGN BASIS 05
PFD 15PROCESS SUMMARY 05DATA SHEETS FOR MAJOREQUIPMENT 15P&IDs 30INSTRUMENT DATA SHEETS 10LINE SCHEDULE 10FINAL PROCESS PACKAGE 10
IV Milestone level
PROCESS:
FIRST ISSUE 50RECEIVE COMMENTS 20INCORPORATE COMMENTS 20ISSUE FOR PROCESS PACKAGE/FEED 10
ENGINEERING:Drawings & Documents:
Appl.Cat Info.Cat.DRAFTING COMPLETE 50 50CHECKING COMPLETE 10 10ISSUE FOR APPROVAL 10 --RECEIVE COMMENTS 10 --ISSUE FOR CONST. 10 30UPDATION & REVISIONS 10 10
Material Requisitions:Equipment Bulk
ISSUE M/R 20 20TECH.EVLN. 10 50ISSUE PR TO PMC 10 10REVIEW OF PR BY PMC 10 10ISSUE P/R TO VENDOR 10 10VENDOR DRAWINGREVIEW 40 --
ORDERING:ISSUE ENQUIRY 05RECEIVE BIDS 15TBA 25RELEASE TOI 45ISSUE PO/PR TO VENDOR 05UNPRICED PO/PR TO OWNER 05
7/23/2019 a3.8 planning scheduling_20090812_115626.pdf
http://slidepdf.com/reader/full/a38-planning-scheduling20090812115626pdf 60/60
ATTACHMENT – V
Page 3 of 3
MANUFACTURING & DELIVERY:Equipment:SUBMISSION OF MAJOR DRAWINGS 5.0 APPROVAL OF MAJOR DRAWINGS 5.0SUB ORDERING OF MAJOR MATERIALS 5.0
RECEIVE MAJOR MATERIALS 25.0FABRICATION WORK 40.0(Progressive)FINAL INSPECTION & TESTING 05.0DESPATCH TO SITE 05.0RECEIVE AT SITE 05.0SUBMIT FINAL DOCUMENTATION 05.0
Bulk material:START OF WORK 10.0DESPATCH 60.0(Progressive
Desp.qty./Total qty.)RECEIVE AT SITE 20.0(Progressive
Received.qty/Total qty.)FINAL DOCUMENTATION 10.0
CONSTRUCTIONIN CASE OF CONSTRUCTION ALL ITEMS OF WORK AND QUANTITIES SHALL
BE INDICATED AND % PROGRESS AT WORK ITEM LEVEL SHALL BE BASED
ON WORK COMPLETED VS. TOTAL QTY OF THE WORK ITEM. THE EPCC
CONTRACTORS SHALL GIVE DETAILS OF ARRIVING AT TOTAL CONTENTS.