Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
A RACE AGAINST TIME: REPLACING A DAMAGED WTP INTAKE CRIB AT THE BOTTOM OF LAKE ONTARIO
Allan Choi, P.Eng. 1, Kimberly Sayers, M.A.Sc., PMP, P.Eng.1, Zoran Filinov, P.Eng. 1, Jim McGilton, P.Eng. 2
1R.V. Anderson Associates Limited, 2Regional Municipality of Durham
Intake Crib Design Alternatives
Evaluation
CriteriaWooden Crib Stainless Steel Crib Concrete Crib
Ease of
Constructability
Long fabrication time
Lightweight and easy to
transport, however must be
weighted or dragged to lake
bottom
Moderate fabrication time.
Steel structure is lightweight,
sinks by gravity.
Irregular shape requires
detailed precasting. Long
fabrication time.
Concrete structure is heavy.
Difficult to transport.
Susceptibility to
Damage
Medium
Boat anchors may catch on
timbers
Low
Smooth / circular surfaces
Low
Smooth surfaces. Heavy weight
prevent displacement
Thermal
Conductivity
Best resistance to frazil ice
formation
Least resistance to frazil ice
formation
Moderate resistance to frazil ice
formation
Construction
Cost
Medium
($140,000 est.)
High
($200,000 est.)
High
($200,000 est.)
Expected
Lifespan30 years 75 years 75 years
Environmental
Impacts
Medium
Pressure-treated wood may
be required
Low Low
Background Intake Design Marine Construction
Newcastle
< Oshawa
Lake Ontario
Newcastle Water Supply Plant
Intake Pipe
Intake Crib
HWY 401
Durham Region is the Owner and Operator of the Newcastle Water Supply Plant (WSP)
which services the communities of Newcastle and Newtonville in the Municipality of
Clarington. The plant uses low lift pumps to draw raw water from Lake Ontario through a
1.2 km long 600 mm diameter intake pipe. The current plant capacity is 8 MLD, and there
are plans to double this capacity in the future. The plant utilizes conventional filtration and
high lift pumps for pumping to the distribution system.
In May of 2014, Operations staff discovered that the wooden intake crib structure located
on the lake bottom was significantly damaged and moved approximately 6 m from its
original location. The raw water sample line and chlorination line for zebra mussel control
were also damaged at the intake. The cause of the accident is unknown.
Damaged wooden intake crib (above left). Unprotected raw water intake pipe (above right).
Durham Region retained R.V. Anderson Associates Limited to complete the design of a replacement intake crib
structure complete with chlorine feed, diffuser and raw water sampling lines, and to ultimately oversee the
construction of the crib replacement before the arrival of the winter season.
The design of the intake crib structure was based on recommendations provided by the Ministry of the
Environment and Climate Change Design Guidelines, and the Hydraulic Division of the American Society of
Civil Engineers (ASCE) guideline for Design of Water Intake Structures for Fish Protection (1981). The design
included considerations for crib maintenance in marine environments, risk of frazil ice formation, low entrance
velocities, and protection from damage due to boat anchors.
Three possible construction materials were evaluated for the structure, including wooden timbers, welded
stainless steel, and pre-cast reinforced concrete.
Based on the evaluation of the available materials, the preferred intake crib
design for the replacement of the Newcastle WSP intake crib was a
stainless steel structure. This option provided the Region of Durham with a
long-lasting solution, and due to its easier constructability, it offered the
fastest fabrication time with the least impact on the construction schedule.
The image on the left shows the final design for the new stainless steel crib
structure, which is bolted on top of the existing concrete pad. Access doors
are provided on the side of the structure for maintenance access to the
chlorine diffuser and raw water sampling piping.
An expedited approval was obtained from Transport Canada, as this work
was considered emergency works under the Navigation Protection Act. Dean
Construction Co. Ltd. was selected to construct the works. A jack-up barge
was positioned on the lake (left), over the intake pipe opening, which provided
a stationary working platform, and allowed the use of a crane to lower the new
structure onto the lake bottom.
The fabrication of the stainless steel intake crib was completed in a shop and
the unit was stored near a dock. However, rough waters on Lake Ontario
throughout the month of November prevented construction crews from
reaching the intake location. In early December, weather conditions finally
allowed the new stainless steel intake crib and the sample line and chlorine
diffuser to be installed, providing Durham Region with a long-lasting solution
at the Newcastle Water Supply Plant, and restoring the security of the
municipality’s water supply
The new crib is pictured in the image below, shown immediately before it was
lowered onto the lake bottom. The water treatment plant was shutdown during
the installation of the intake crib, which occurred at night to minimize
disruptions to the municipality’s water supply.
Jackup barge with crane
(top), Hinged FRP bar
screens (right), Chlorine
diffuser piping accessible
through maintenance
doors (below).
Divers were employed to
perform the installation of
the crib structure at the
lake bottom, and to
remove the damaged crib
(left and above).