7
A. Perin, CERN, TE-CRG, 13 June 2012 1 ICL, 13 June 2012 Consolidation of the DFBX CL control system

A. Perin, CERN, TE-CRG, 13 June 2012 1 ICL, 13 June 2012 Consolidation of the DFBX CL control system

Embed Size (px)

Citation preview

Page 1: A. Perin, CERN, TE-CRG, 13 June 2012 1 ICL, 13 June 2012 Consolidation of the DFBX CL control system

A. Perin, CERN, TE-CRG, 13 June 2012 1

ICL, 13 June 2012

Consolidation of the DFBX CL control system

Page 2: A. Perin, CERN, TE-CRG, 13 June 2012 1 ICL, 13 June 2012 Consolidation of the DFBX CL control system

A. Perin, CERN, TE-CRG, 13 June 2012 2

Outline

• The current control system has limitations on the current ramp rates and accelerations. For the 120 A the limitations are even more severe and do not allow the proper operation of these leads (cf LHC-DFBX-EC-0002 )

• The thermometer used to control the gas flow was installed during the commissioning phase. It is not redundant and it is exposed to potential damage during the interventions on the DFBXs.

• The control method that is currently being used does not give any information on the actual real cooling of the leads and allows just a minimal level of control.

• Goals of the project:

• Improve robustness of control system

• Remove the limitations due to the current control system

Page 3: A. Perin, CERN, TE-CRG, 13 June 2012 1 ICL, 13 June 2012 Consolidation of the DFBX CL control system

A. Perin, CERN, TE-CRG, 13 June 2012 3

Outline

• On the 8 DFBX there are

• 112 resistive 600A leads

• 80 resistive 120 A leads : 40 control loops

• For each DFBX (14 x 600 A) + (5x 120A) gas flows

Page 4: A. Perin, CERN, TE-CRG, 13 June 2012 1 ICL, 13 June 2012 Consolidation of the DFBX CL control system

A. Perin, CERN, TE-CRG, 13 June 2012 4

Main points

• Main technical features• Control in open loop: mass flow as a function of current in the leads

• Non radiation-hard flowmeters located in protected areas

• Gas flow to be routed to the flowmeters and back (max 100 m) (e.g. 0.1 g/s, diam. 15 mm tube, DP = 7 mbar)

• Get the information on electrical current and use it to regulate the mass flow

AMI 600 A 6 Lead Assembly Test DataVoltage Drop vs. Coolant Flow

3.0E-02

3.5E-02

4.0E-02

4.5E-02

5.0E-02

5.5E-02

6.0E-02

6.5E-02

7.0E-02

40 50 60 70 80 90 100

Lead Voltage Drop, mV

Co

ola

nt

Flo

w p

er

Le

ad

, g/s

ec

= Recommended Operating Point

Page 5: A. Perin, CERN, TE-CRG, 13 June 2012 1 ICL, 13 June 2012 Consolidation of the DFBX CL control system

A. Perin, CERN, TE-CRG, 13 June 2012 5

Main points

• Main technical features• Control in open loop: mass flow as a function of current in the leads

• Non radiation-hard flowmeters located in protected areas. (development of radtol flowmeters could not be done)

• Gas flow to be routed to the flowmeters and back (max 100 m) (e.g. 0.1 g/s, diam. 15 mm tube, DP = 7 mbar)

• Get the information on electrical current and use it to regulate the mass flow

What do we need?

- Install a rack (std. 19") with 19 flowmeters in a protected area for each DFBX

- Signal connection to the cryo racks (approx. 40 wires)

- Routing of 19 pipes diam. approx. 15 mm (inner diam) from DFBX to rack + routing of a 50 mm pipe back to the helium recovery line.

- Get the electrical current information to cryo PLC.

Page 6: A. Perin, CERN, TE-CRG, 13 June 2012 1 ICL, 13 June 2012 Consolidation of the DFBX CL control system

A. Perin, CERN, TE-CRG, 13 June 2012 6

Main points

What do we need?

- Install a rack (std. 19") with 19 flowmeters in a protected area for each DFBX

- Signal connection to the cryo racks (approx. 40 wires)

- Routing of 19 pipes diam. approx. 15 mm (inner diam) from DFBX to rack + routing of a 50 mm pipe back to the helium recovery line.

- Get the electrical current information to cryo PLC.

Installation of racks

- One standard rack / DFBX

- Located next to cryo rack where possible (R2E)

Page 7: A. Perin, CERN, TE-CRG, 13 June 2012 1 ICL, 13 June 2012 Consolidation of the DFBX CL control system

A. Perin, CERN, TE-CRG, 13 June 2012 7

Main points

Installation of racks

- One standard rack / DFBX (could be different shape if needed)

- Located next to cryo rack where possible (R2E)

- First analysis for possible locations

IR Locationof DFBX

Possible flowmeter rack location

Approx. distance from DFBX

Approx. distance between flowmeters and cryo rack

IR1 LIR1 R

UJ14UJ16

UL14UL16 20 m – 50 m 3 m – 20 m

IR2 LIR2 R

RA23UJ26

UA23UA27 < 30 m < 20 m

IR5 LIR5 R

RZ54UJ56 ? ? ?

IR8 LIR8 R

RA83UJ86

UA83UA87 < 30 m < 20 m