Upload
others
View
10
Download
0
Embed Size (px)
Citation preview
1 | P a g e
A Narrative Report of the
Field Attachment Program Undertaken at the Department of Water Affairs, Lesotho
P.O. Box 772, Maseru
Presented to the Regional Universities Forum for Capacity Building in Agriculture (RUFORUM)
Submitted By:
Motseko Mots’ets’e
2 | P a g e
Introduction
The Field Attachment Program Award (FAPA) is a competitive grants program designed as
graduate student internship to link thesis research findings and recommendations to application
and use at community level. The FAPA grants are intended to provide opportunity for
dissemination of research outputs with a view to inform policy development and hone students
skills in participatory (with communities) articulation of complex research cycle. This report
presents the results and activities of a field attachment program grant (FAPA RU 2017 FAPA
174) which was intended to support work on Dissemination and review of Lesotho wetlands
monitoring protocols. This work came out as recommendations arising from an MSc thesis
research funded by the RUFORUM under the title Hydro-period, surface-ground water
interactions and water quality to assess wetland condition of Khalong-la-Lithunya. The
thesis research constitute part of the RUFORUM supported Research Project; Hydropedology
and water isotopic signatures of mountain wetlands of Lesotho, identification number:
RUGRG0314-018. The main purpose of the MSc research project was to assess wetland
ecological functioning of the Khalong-la-Lithunya from wetland hydrology and water quality
by specifically determining hydro-period from water levels in piezometers, interactions
between surface and ground water using water stable isotopes and the effect of the wetland on
water quality of the piezometers and adjacent streams.
In general the results of the research showed that there was observed short hydro-period, a
delayed response between surface and ground water as well as poor water quality in both
piezometers and adjacent streams. The conclusion was that due to the obtained results, the
Khalong-la-Lithunya wetlands were seasonal and this makes wetlands susceptible to drought
hence may indicate affected wetland ecological functioning. However, the hydro-period was
determined from a discontinuous data hence it was recommended that further consistent
monitoring of water levels be done using automated water level recorders for a better
estimation of wetland hydro-period. Again, it was observed that stable isotopes illustrate the
potential to clarify hydrological dynamics since hydro-period is subjected to hydrological
variability due to different landscape characteristics over comparatively small distances and
this makes it difficult to identify representative sample points to monitor hydro-period. Hence,
seasonal examination of water stable isotopes was highly recommended. Also a continuous
measuring of water quality was recommended. In order to achieve all these recommendations,
a field attachment program was applied for.
The important stakeholders towards this field attachment were the community, whom most
importantly through the herd boys and livestock owners interacts directly with the wetlands
because they graze their livestock on the same wetlands. In addition, there are rural
communities that depend on these resources for their livelihoods. As a result they temper with
instruments installed in the wetlands for monitoring. The National University of Lesotho was
also identified as one of the stakeholders since it’s a research institution which carries out
studies through students’ research project or commissioned research with private and public
sector on wetlands. The selected government ministries were also identified as important
stakeholders in this research and are; the Ministry of Water through the Department of Water
Affairs and the Ministry of Forestry, Range and Soil Conservation through the Department of
Range Management. The Department of Water Affairs was given the role of being the
implementing entity of the project on Wetlands Restoration and Conservation under the
administration by the Millennium Challenge Account Lesotho (MCA-L). The current study
was carried out on one of the project sites for the MCA-L project and was a continuation of
that previous project using the equipment in place that has already been installed by that project
3 | P a g e
and the protocols documented by MCA-L. The Department of Range Management on the other
side controls the grazing systems since wetlands are used for grazing.
However, the Department of Water Affairs was recognized as an important stakeholder in this
regard and therefore the Intern was placed at the Department of Water Affairs under the
supervision of Dr Botle Mapeshoane of the National University of Lesotho and Mr
Makomoreng Fanana of the Department of Water Affairs and also Head of the Water Resources
Division within the department. The objectives of the field attachment program were to
capacitate the Department of Water Affairs personnel on the use of water stable isotopes to
assess wetland hydrology, to promote and create awareness of wetlands wise use and finally to
review the monitoring protocols of wetlands to include the use of isotopes. But also the
program was intended to disseminate research findings to all stakeholders. The following
section presents the results based on the activities or work plan of the field attachment program.
Results
Dissemination of research findings
As per the dissemination of research findings a presentation event was held at the Department
of Water Affairs boardroom on May 09, 2017 where the attendance included all personnel from
all the major stakeholders except the community. The attendance also included the Technical
Task Team of the Khubelu Sponges Project (KSP). The presentation focused on the results of
the research project and also introducing the objectives of the field attachment program. It was
at the same event that the stakeholder’s personnel was showed the importance of using
automated water level recorders for consistent water level monitoring. It was explained how
the discontinuous data might have affected the results of the current study and how automated
water level recorders are the most preferred due to the disadvantages towards manual
inspection, an example of unfavorable climatic conditions was made. The personnel raised a
point that they are faced with a challenge of vandalism of instrumentation by the herders,
therefore it was agreed that there had to be a way of protecting these instruments, and one
suggestion was that maybe the military people need to be incorporated. Also the herd boys
need to be further capacitated and made aware of the importance of the instruments for wetland
monitoring for the benefit of their livestock.
Furthermore, the personnel was introduced to the concept of isotopes hydrology, where they
were capacitated on the use of water stable isotopes to monitor wetland hydrology. It was
explained to them what the obtained results on isotopes demonstrated in terms of the wetland
hydrology and proven to them why we think use of isotopes is a better method compared to
other ways of monitoring wetland hydrology such as hydro-period. They were further
challenged on the other uses of isotopes except the determining of the interactions between
surface and ground water that the current study did, these include the use of stable isotopes to
identify the wetland water source and estimating of the wetland mean residence time, both of
which are important for wetland management. They were also made aware of the need to
monitor wetland water quality and that research had to be done in order to identify source of
surface or stream flow pollution following the poorer stream water quality index that was
found. They were further made mindful of the study on the influence of land-use which could
give a better understanding of the wetlands condition.
As one way of research findings dissemination, a presentation of the results of the MSc research
project was made on August 23, 2017 to the panel of Department of Water Affair’s personnel
for both Lesotho and Namibia, Lesotho Range Department, the GIZ members from Lesotho,
4 | P a g e
Botswana and Namibia, Orange-Senqu River Basin Commission (ORASECOM)
representative, as well as undergraduate and honors students from the Namibia University of
Science and Technology (NUST) under the Department of Natural Resources. They had all
come to Lesotho on a weeklong field tour to observe and be taught about the wetlands
management, the interventions that have been made by the Government of Lesotho and GIZ to
try and rehabilitate the wetlands of Lesotho since they are sources of water for the Orange-
Senqu River Basin which Namibia and Botswana forms part. They were also interested in
seeing the large reservoirs that Lesotho have such as the Katse and Mohale Dam that Lesotho
use to sell water to South Africa under the Treaty of the Lesotho Highland Water Project of
1986. Figure 2 below shows me presenting to the panel.
Figure 2: NUST field tour presentation
Moreover, in an attempt to disseminate the research findings, a paper was produced which was
submitted for publication to Wetlands Journal. Unfortunately, the paper was recommended for
a rewrite before it could be reviewed for further stages. Currently, the paper is being prepared
in the correct format for publication under Wetlands Journal. With further efforts being made,
a policy brief on the implementation of the FAPA was produced and is currently under review
for publication. Furthermore, an abstract of the research project was submitted for
consideration for oral presentation for the 18th WaterNet/WARFSA/GWPSA Symposium on
“Integrated Water Resources Development and Management: Innovative Technological
Advances for Water Security in Eastern and Southern Africa” to be held in Swakopmund,
Namibia. I am happy to announce that it was strongly accepted for oral presentation and the
symposium is to be held on 25th – 27th October 2017. A full paper has also been requested for
submission to the Journal of Physics and Chemistry of the Earth.
Promoting and creating awareness of wetlands wise use
Upon arrival at the Department of Water Affairs I was appointed to be part of the two projects
that the department was carrying out, these are the Khubelu Sponges Project (KSP) and the
operationalization of the Integrated Catchment Management (ICM) project. The KSP project
was intended to ensure rehabilitation of the rangelands including wetlands of the Khubelu
Catchment. This encompasses securing land and water resources as a contribution to the overall
effort to protect resources of the highlands of Lesotho that have been heavily degraded by
uncontrolled grazing. Therefore, the objective of the project was to demonstrate a
5 | P a g e
methodological approach for the sustainable management of the wetlands benefiting the
population as well as the environment and securing long-term availability and quality of water
resources from the Upper Orange-Senqu catchment area. The pilot site consists of four sections
of former grazing areas based on the Range Resources Management Departments subdivisions
of the Khubelu Rangelands, namely Phapong, Moteaphala, Ramosetsana and Mots’eremeli.
The interventions were however restricted to just two of these sections (Phapong and
Ramosetsana) for trials. The project is implemented and administered by Department of Water
Affairs, but it also involves various other governmental departments. It is coordinated through
local stakeholders (traditional authorities and local community). The activities of the project
involved pilot interventions on physical rehabilitation of wetlands and biological rehabilitation
of rangelands especially through the holistic management approach and uprooting of invasive
species by the community and livestock vaccination. The following Figure 3 shows some of
the physical interventions that were made by the stakeholders involved in the project.
Figure 3: Physical structures
6 | P a g e
The following pictures (Figure 4) show where invasive species have been uprooted by the
community and made into several successive lines in an attempt to trap the silt and reduce soil
erosion. The main purpose of uprooting the invasive species is to improve the rangelands.
Figure 4: Uprooting of invasive species to improve rangelands and control soil erosion
The project further introduced new methodologies of revegetation through temporary kraaling
and high density grazing. Temporary kraaling is where the animals are made to sleep or kraal
on a particular area for a certain time in order to kill the invasive species and fertilise that area
with their droppings for palatable grasses regrowth. However, grazing has always been referred
to as the main cause of wetlands degradation through overgrazing, a new approach has been
introduced which has actually proved to be working very well towards revegetating the
wetlands and rangelands, that is the high density grazing. This is where the animals are
prohibited from scattering all over the area doing their selective grazing but they are grazed in
a way that they are broad together as a large flock and herded systematically from one place to
the next. In this way they trample and kill the non-palatable shrubs and grasses that invade the
wetlands and rangelands, this allows for dominance of the palatable grasses. Figure 5 shows
where these new methodologies were practiced.
Figure 5: Temporary kraaling and high density grazing
7 | P a g e
Figure 6 below shows the positive results that emerged from this new methodologies. The first
part (A) of the figure shows where after three nights of temporary kraaling of livestock, all the
uneaten plants have been destructed into litter, and some already incorporated into the top soil
by the animal hoofs. Also, the dung and urine have been incorporated, covering the bare patches
of the surface. Section (B) of the figure shows where old seeds begin to germinate while section
(C) shows the shrubs and moribund disintegration.
Figure 6: Results of temporary kraaling and high density grazing
I was also involved in the operationalization of the Integrated Catchment Management (ICM)
Framework. The ICM is part of a worldwide effort to reduce catchment degradation and ensure
sustainable water availability to increasing populations. Protection and proper management of
the water sources is essential, and must be undertaken by actively consulting the stakeholders
living in the watershed, involving them in the management and ensuring they benefit from this.
Land and water resources cannot be easily separated or managed independently of one another.
This implies that coordinated and integrated planning is required and this can be achieved by
instigating ICM approach within the country. The complexity of implementing ICM is also
exacerbated by multifaceted issues of land-use patterns and varied roles played by stakeholders,
communities and government. The integrated land and water resource management
programmes and investment plans therefore have to address soil erosion and desertification,
Treated Area
A)
B) C)
8 | P a g e
protect water sources, preserve mountain ecosystems, increase capacity of rangelands, extend
appropriate forest cover, and rejuvenate agricultural lands.
The specific objectives of this assignment are therefore, to support the institutional and legal
reforms for operationalising the ICM Framework, support the validation of prioritisation and
sequencing of sub-catchments as proposed, through workshops involving all stakeholders and
contribute to the development of catchment management plans for each of the prioritised pilot
sub-catchments including annual plans of action and tentative budgets. Six Priority Sub
Catchments (PSCs) were selected for this pilot stage out of the 74 automatic delineated sub-
catchments of the country. These are the Likhetla, Makhalaneng, Hlotse, Khubelu, Senqunyane
and Maletsunyane. However, for the phase one of the pilot study, two priority sub-catchments
have been selected and are Likhetla and Makhalaneng PSC’s.
As part of ICM I was involved in organising and carrying out of the ICM activities. The
activities include the ICM Inception Workshop held on May 11, 2017. It was intended to
introduce the concept of ICM to the respective Ministers of particular government ministries
and other stakeholder. This was one way of raising awareness on the usefulness of wetlands
within the catchments and their management. The other goal of the workshop was for
stakeholders to identify their stake in catchment management through the activities or projects
that they do within their ministries and also regulating acts that guide them. I also took part in
the ICM Brainstorming and Interaction Session on July 20, 2017, envisioned to forge and
inform an approach that will be taken to operationalise ICM by providing a neutral forum for
a review of the benefits, risks, challenges and opportunities from various actors in integrated
land and water management and their contribution to ecosystems and improved services in the
face of an increasing population and climate change. The target audience for the brainstorming
session included government representatives, NGOs, civil society organisations, academia,
research and development institutes, producer’s organisation and cooperatives that all shared
their experiences, challenges and lessons learnt.
More awareness activities that I took part in within ICM include the Stakeholder Consultation
Workshops of the two phase one PSCs; those are Likhetla and Makhalaneng. The general
objective of the consultation workshops was to consult with the actors in catchment
management that are below ministerial level. These included the District Administrators (DA),
District Council Secretary (DCS), Community Councils (CC), Community Council Secretary
(CCS), Chiefs and Land and Environment Committee as well as Social Service Committee.
This further went down to the area/local chiefs, community groups, private sector e.g. farmers,
industries. The Likhetla stakeholder consultation workshop was held on July 27, 2017 and the
goals were to introduce ICM and raise awareness and find out who are the users of land and
water in the catchment, for what purpose, their tasks in land and water management, observed
examples and causes of degradation in the catchment and what was there in the past that is not
there at the present. Figure 7 shows the pictures taken at the Likhetla Stakeholder Consultation
Workshop.
9 | P a g e
Figure 7: Likhetla stakeholder consultation workshop
The catchment management activities are implemented by the local councils and the
communities with a focus on benefits from water and natural resources resulting in improved
livelihoods in rural areas and economic development. Therefore, following the stakeholder
workshops the field visits were taken to the community councils. The following pictures on
Figure 8 show some of the visited areas in the Likhetla PSC within the Metsi-Maholo
community council. Section (A) of the figure shows a dried large wetlands of Ts’akholo while
section (B) shows an infrastructure that has been placed within a wetland not giving any chance
to the wetland to recover.
Figure 8: Ts’akholo wetland
The Makhalaneng Stakeholder Consultation Workshop was held on August 01, 2017. The
following pictures (Figure 9) were taken during this workshop which had the same goals as the
Likhetla workshop.
(A) (B)
10 | P a g e
Figure 9: Makhalaneng stakeholder consultation workshop
Likewise we visited particular areas in the Makhalaneng PSC and Figure 10 below depicts
some of the observed areas within the Manonyane community council with evidence of soil
erosion.
Figure 10: Evidence of soil erosion in Manonyane community council
Moreover on awareness, I embarked on a 5 days field trip or campaign around the highland
wetlands sites of the country with the personnel from Department of Water Affair’s for both
Lesotho and Namibia, Lesotho Range Department, the GIZ members from Lesotho, Botswana
and Namibia, Orange-Senqu River Basin Commission (ORASECOM) representatives, as well
as undergraduate and honors students from the Namibia University of Science and Technology
(NUST) under the Department of Natural Resources to show them where our wetlands are
located and the management activities that are being carried out. The tour included
demonstrations on wetland monitoring activities, presentations on studies that have been
carried out and the importance of our wetlands as water sources for our rivers. The tour began
11 | P a g e
on August 20, 2017 and ended on August 25, 2017. Figure 11 below indicates some of the
wetlands sites that were visited during the trip, section (A) is the Khalong-la-Lithunya wetland
where physical structures have been used to rehabilitate the wetland and section (B) is the
Bokong wetland which is a conserved area.
Figure 11: Khalong-la-Lithunya and Bokong wetland sites
Review of the wetlands monitoring protocols
Owing to the degradation of wetlands water resource it is important to monitor water quantity
and quality for better management of wetlands. Good quality data can be an enabler for better
planning of wise use of wetlands. Therefore, one of the recommendations of the research
project was to consistently monitor water levels and automated water level recorders be used
for a better estimation of wetland hydro-period. In addition to already existing monitoring
methods, seasonal examination of water stable isotopes to assess wetland hydrology was also
recommended. Even though automated water level recorders have not been installed in the
areas of Khalong-la-Lithunya as yet but a continuous monitoring of water levels is being done.
Moreover, in other areas where the department is working on, like Phapong, there are installed
automated water level loggers inside piezometers to monitor groundwater levels. Furthermore,
water quality of the wetlands is being measured continuously. Figure 12 below depicts where
I am manually recording water levels using the acoustic water level indicator and where I am
measuring in-situ, the temperature, pH, electrical conductivity (EC), dissolved oxygen (DO),
alkalinity and turbidity of the water.
(A) (B)
12 | P a g e
Figure 12: Water level recording and water quality measurements
The wetland monitoring protocols were reviewed to include the measurement of isotopes. In
an effort to strengthen this, the Department of Water Affairs is to embark on a project which I
am going to be part of its technical task team on “Isotopic Techniques for Assessment of
Hydrological Processes in the Khalong-la-Lithunya catchment” funded by IAEA. Already
there are equipment that have been bought for this project and some are being already used in
the everyday wetlands monitoring activities. These include the two weather stations which are
yet to be installed and the Radon isotope meter. Radon as opposed to the then studied water
stable isotopes is a radioactive isotope. The stable isotopes are excellent indicators of the
circulation of water, while the radioactive isotopes are of special value in detecting the
residence time. The naturally occurring radon isotope (Rn – 222) has been used as a natural
tracer to determine the residence time of groundwater, surface water interaction and the ability
of pollutant infiltration from surface water into groundwater. The advantages of using Radon
isotope instead of stable isotopes of Oxygen and Hydrogen are that; radon concentration is
measured directly, so it eliminates the loss of radon during sampling and transportation and
also individual measurements cannot be influenced by environmental parameters such as
temperature and pressure because the measurements are carried out in situ. However, where
possible the water samples are still taken for further analysis of Oxygen and Hydrogen stable
isotopes in order to complement the results of the Radon. Both the weather station and the
radon meter are shown in Figure 13 below.