Upload
amice-morgan
View
215
Download
1
Tags:
Embed Size (px)
Citation preview
A FEW THINGS WE LEARNED ON THE WAY…
(Tips/Tools for Success in your Project Environment)
Presenter: Wally Johnson PMP©, CBM©[email protected]
Tuesday, August 17, 2004
2
My Project Environment
Transforming the U.S. Customs Service
Enhancing and protect the supply chain
Replacing the aging Automated Commercial System (ACS), with the Automated Commercial Environment (ACE)
Enhancing our capability to protect America
Adm
inis
tra
tion
U.S.Customs
Imp
ort
s &
E
xpo
rts
Enf
orc
em
en
t &
P
asse
ng
ers
Managing emerging technologies (i.e. PerfectWave) R&D efforts
Establishing a PM competency & culture
3
Outline
Project Initiation
Integrated Baseline Reviews (IBRs)
“Hu-namics”
Reports
Information Station (Web Portal)
Lessons Learned / Project Closeout
Project Manager
Q & A
Project Initiation Tips
5
Questions Are Tools
Bringing Order to Chaos Begins as soon as you start asking QUESTIONS
Questions can be your friends; Questions create dialogueo “What are the parameters of the project or problem?”o “What are the known risks of this project?” o “If all goes well, what does success look like?”o “Who’s a player? Who should play?”o “What is the history?”o “What agreements should we establish?”Lessons Learned /
Project Closeout
SUCCESS begins as soon as answers to questions are implemented
Questions are the foundation to planning
“Plans are nothing, planning is everything.”
General Eisenhower
“Plans are nothing, planning is everything.”
General Eisenhower
7
1. DEFINE THE WORK AND ORGANIZE TEAMS
100
4060
1525
3030
2. SCHEDULE THE WORK
3. ALLOCATE BUDGETS
$
CONTRACT BUDGET BASE
TIMEIN
TEG
RATED B
ASELINE
Planning is a 3-Step Process
Integrated BaselineReview
9
What Is An IBR?
Schedule
Technical
Cos
t
Baseline
Evaluation of performance measurement baseline Baseline realism - Identify inherent risks
Continuous Part of integrated project management Should be seen as "Process" Not a stand alone
"Event“
Joint assessment o We jointly need to be able to answer this basic question:
“Can we execute this contract (technical work scope), given the available schedule and budget resources?”
o “Show Me” - prove to all this possible !
10
Some IBR Goals
Establish clear definition of work prior to beginning that work
Show how the plan / baseline was established
To ensure that the technical content of work packages and control accounts is consistent with the contract scope, the WBS, and the WBS dictionary
To ensure that there is a logical sequence of effort planned consistent with the contract schedule
To assess the validity of allocated control account and summary level planning package budgets, both in terms of total resources and time-phasing
To conduct a technical assessment of the:o Earned value methods that will be used o To measure progress to assure that objective and meaningful
performance data will be provided
11
The IBR - What Do We Look at?
“Rule of thumb”o Strive to review ~80% of contract value
Identified risks and their mitigations
Reviewo Significant elementso Risk areaso Elements on critical path
A show of a good understanding of the technical, schedule and cost risks involved in completing the assigned work
The earned value system planned to be used to manage day to day activities
The evidence that the work can completed within the schedule and budget constraints?
Technical team should agree on coverage
“Hu-namics”(Human Dynamics)
13
Sponsor
Players
Stakeholders
PM
Every Environment Contains People
“Help me, help you …”
14
Causes of Project Human Dynamics?
Projects have a defined start and finish
Projects also have an undefined amount of Stress and Pressure
Project resources interact and may form teams
Projects need/have leader(s)
Innovators
Ea rly M
a jor ity
Late A
dopters
Laggards
Early A
dopters
15
Project Human Dynamics
Stress/Pressureo Outlets needed
Workout / Sports Laugh Network of peers Breaks, vacations
o Deflectors Milestones / “Inchstones” Offsite (meetings, lunch, …)
Teamo Know them (Psychometrics e.g. Myers-Briggs)o Know their strengths & weaknesseso Learn their motivators
16
Human Dynamics (Cont.)
Leader (PM) o Be Real
No time for being fake No time to play politics Acquire a deputy or clone Know self
o Rewards Earn them Receive them Give them
o Stay Fresh Seminars Training Beware the ‘Death March’
A LIFE outside of work is REQUIRED
Reporting
18
Artifacts of the project support most maturity models
Chapters in the project ‘book’
Provide the most relevant information that will assist in making decisions and/or providing guidance.
Provide structure for the information/knowledge presentation(s)
Objectives of Snapshots
19
Customs Modernization Weekly Report
Project ID: JCE Report Period: 12 Aug 02 – 16 Aug 02
Project: TO2, Enterprise Architecture and Engineering Acquisition Director: Luke McCormack, 703-921-6710
ScopeTask Order 2 performs the enterprise architecture and engineering planning necessary tocoordinate Modernization activities.
Headlines
+ SME coordination mtg. To support Mini-ConOps: 8/12+ TO2 Phase 1 & 2 financial reconciliation mtg.: 8/14+ EA HTML Demo: 8/14+ TO2 Phase II Kick-off mtg.: 8/14+ “Target Infrastructure” PDD reviewed: 8/14+ TO2 Phase II Kick-off mtg.: 8/15+ ELCM Lessons Learned Report delivered: 8/15+ TO2 PDDs for Work Products delivered: 8/16
- No buy-in from ISD and SDD for participation in TIWG
Acquisition Director’s AssessmentStatusCategory
eCP CMO
Assessment Summary
Overall Project Y Y TO2 kickoff held, a few actions raisedFinancial Y Y Phase 1 /2 reconciliation almost complete; work continuing on
cleaning up the monthly CPR information.Schedule Y Y Subtask 2-1 needs dates and dependencies revisited. Schedule not
baselined yet.Process G G Processes being followed.Team Health G Y More MITRE resources need to be allocated to support eCP efforts.
MITRE resources split between TO5 & TO2 not able to coverreviews. Also, TAG resources are stretched thin across manyefforts. Not enough resources to complete CMO Portalfunctionality (~4 FTE needed).
Scope G G SOW to be baselined 8/22/02Stakeholders G GTechnical G G PDDs delivered being reviewed by MITREDependencies G G SME dependencies need to be embedded in schedule.Risk Posture G G Risks identified and being managed
Schedule Details*StatusKey Milestone Baseline Current
Estimate eCP CMO
2 Phase II Start Date 13 Feb 02 13 Feb 02 G GO Web Portal (Release 1) 22 Jun 02 22 Jun 02 G G Environment and Repository Training Material - Final 01 Apr 02 01 Apr 02 G Gterprise Transition & Sequencing Plan - Final 12 Apr 02 12 Apr 02 G Gterprise Infrastructure Plan - Final 12 Apr 02 12 Apr 02 G Gterprise Technology Insertion Plan - Final 12 Apr 02 12 Apr 02 G GT ELCM Change Process - Final 28 May 02 28 May 02 G GLC References Change Request Form - Final 11 Jun 02 11 Jun 02 G G Certification 21 Jun 02 26 Jun 02 G G2 Integrated Baseline Review (IBR) 24 Jul 02 24 Jul 02 G G
Sample Report
20
Sample Gantt View
Task Progress (% complete)
Task Baseline Task Estimate to Complete
Milestone Non Contractual Baseline
Milestone Contract Baseline
Milestone Estimate to Complete
Milestone Completed
ID Task Name BL ST BL FN1 Task Order XX 10/14/03 12/31/04
2 Milestones NA NA
3 Contractual Milestone - Completed on schedule 10/14/03 10/14/03
4 Contractual Milestone - Not Completed on schedule 10/14/03 10/14/03
5 Future Contractual Milestone - Projected Behind Baseline 11/22/04 11/22/04
6 Non Contractual Milestone - Projected Behind Baseline 12/1/03 12/1/03
7 Future Non Contractual Milestone - On schedule 6/15/04 6/15/04
8 Future Non Contractual Milestone - Projected Ahead Baseline 8/10/04 8/10/04
9 Level of Effort NA NA
10 LOE Line Item Full POP - Always on Schedule 10/14/03 12/31/04
11 LOE Line Item Partial POP - Always on Schedule 10/14/03 8/30/04
12 Baselined Tasks 10/14/03 5/17/04
13 Task - Completed before Baseline 10/14/03 11/10/03
14 Task - Started Early Completed on schedule 11/11/03 12/22/03
15 Task - Started Late, projected finish late & behind current plan 12/23/03 3/15/04
16 Task - In the future yet projected behind baseline 3/16/04 5/17/04
17 Task - In the future yet projected ahead of baseline 9/21/04 11/22/04
18 Task - Completed on schedule 10/14/03 11/10/03
19 Task - Started late and completed on schedule 10/28/03 12/15/03
20 Task - Started late and completed late 10/14/03 12/22/03
21 Task - Started late, projected to finish late, ahead of current plan 12/23/03 3/22/04
22 Non Baselined Tasks 10/14/03 3/22/04
23 Non baselined Task - Completed On Schedule NA NA
24 Non Baselined tasks - behind schedule NA NA
25 Non Baselined task in the future NA NA
10/14
12/8
12/31
3/14
6/15
7/23
10/14 12/31
10/14 8/30
10/14 11/3
11/4 12/22
1/19 4/9
4/12 6/11
7/26 9/24
10/14 11/10
11/4 12/15
11/7 1/15
1/16 4/15
10/14 11/14
10/14 3/12
7/26 9/24
1/29/04
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2003 2004 2005
*** LEGENDS ARE IMPORTANT ****** LEGENDS ARE IMPORTANT ***
Information Station
22
Repositories / Web Portals
Portal allows easy access to program information and tools
Portal is a good place to store project artifacts
Portal provides a means of supporting content sharing with teams
Portal provides Web based access to documents and Tools
Content and/or application sharing
Intended for use by project participants (i.e. stakeholders)
Sample Callout in 12-point type
V1468
Sample Callout in 12-point type
V1468
Sample Callout in 12-point type
V1468
Lessons Learned Meeting
24
Why ?
All good things must come to an end…o “Official” Project closeout
Share with the next generationo “Those who do not know the past may be doomed to repeat it”
Process improvement
One captured idea can save thousands …o Repeat successes & avoid pitfalls
Endings are also new beginnings
25
What It Looks Like?
“Pre-Meeting distributed” survey – capture knowledge / experience from those who will not attend a meeting
Use survey findings as catalyst
Agenda
Refreshments (i.e. pizza & coke)
Live engagemento Facilitatoro Video (audio record mtg.)o Scribe
Capture subjective & objective comments
The Project Manger
27
Know: worth, value, strengths, & weaknesses Resume current (within 6 months) Periodic “objective”, confidential reviews of resume
Monster.com, Hotjobs.com, etc… Friends and relatives
Be open to New Opportunities (internal & external) 1 yr. view of horizon 5 yr. plan 10 yr. vision
Find a mentor
Be a mentor and/or coach
The Project Manager – After Hours
Resources:1. “Women Don't Ask: Negotiation and the Gender Divide” by Linda Babcock and Sara Laschever
2. “The First 90 Days: Critical Success Strategies for New Leaders at All Levels” by Michael Watkins
Time for Questions & Answers