CONSORTIUM
9PKE-16-2010-Rev00 - Power Line Carrier Equipment
Project Title Project FWEL-50 MW FOUNDATION WINDPOWER PLANT-II
Document Title SITE TEST REPORT FOR POWER LINECARRIER EQUIPMENT
Document Number 9PKE-16-2010-Rev00
FWEL ProjectNumber 8209
Revision Number 00
CONSORTIUM
9PKE-16-2010-Rev00 - Power Line Carrier Equipment
QIP No. E1 (Installation checks wiring, termination and earthing checks.)
Installation checks [ ] O.K. [ ] N.A.Wiring checks [ ] O.K. [ ] N.A.Termination checks [ ] O.K. [ ] N.A.Earthing checks [ ] O.K. [ ] N.A.
QIP No. E2 (Interfacing to SAS, PABX, power supply)
QIP No. E3 (Checking unit and system functions as far as possible)
FILE: 1KHW002587AE Commissioning Report ETL600R4; TEMPLATE: TECHN_DOC_STAND_P.dot R0; SKELETON: ; SAVEDATE: 5/15/2012 11:55:00 AM
COMMISSIONING REPORT
Powerline Carrier Equipment: Series ETL600R4
Project : ..
ABB Order N : ..
Station : ..
Link : ..
Equipment N : ..
Frequency : Tx = kHz Rx = kHz
Direction : ..
Commissioning Report contains
SAFETY INSTRUCTIONS
Designations and abbreviations used:
Designation Meaning
REVISION
Rev.ind.
Page (p.)Chapter (c.)
Description DateDept./Init.
TestNo. Test procedure Test point
Permissiblevalue Units
Testresult
C.1. General
C.1.1 Checking the line of communication
r
C.1.2 Visual checks
C.2. Check power supply B5LD Left Right
C.2.1C.2.2C.2.3
C.3. Upload configuration
C.4. Change configuration, if necessary
C.4.1 Reducing output power, if necessary
r min r r min
red
r min
red r min
red
TestNo. Test procedure Test point
Permissiblevalue Units
Testresult
C.5. Transmitter
C.5.1 Adjust Tx RF level
C.5.2 Adjust Tx alarm level
C.6. Receiver
C.6.1 Adjust Rx RF level
C.6.2 Connect RF cable and set alarmthresholds
TestNo. Test procedure Test point
Permissiblevalue Units
Testresult
C.6.3 Check link alarms
C.6.4 Tune hybrid on E5TH
C.6.5 SNR pilot
C.7. Equalization
C.7.1 Measure frequency response
C.7.2 Select Equalizer
C.8. R1BC, if present
C.9. Configure Real time Clock (RTC)
C.9.1 Setting real time clock
TestNo. Test procedure Test point
Permissiblevalue Units
Testresult
C.9.2 Test external real time clocksynchronization, if available
TestNo. Test procedure Test point
Permissiblevalue Units
Testresult
C.10. NSD600 / G4AI, if present
C.10.1 NSD600 loop test
C.10.2 Command transmissiontime
TestNo. Test procedure Test point
Permissiblevalue Units
Testresult
C.10.3 Reset counters
C.11. Testing of O4LE
C.11.1 Service Phone.
C.11.2 Hot line direct phone
C.11.3 Remote subscriber
TestNo. Test procedure Test point
Permissiblevalue Units
Testresult
C.11.4 Pax 2-wire
C.11.5 Pax 4-wire
C.11.6 Pax 4/2-wire
TestNo. Test procedure Test point
Permissiblevalue Units
Testresult
C.11.7 Transit mode for E&M wire
C.11.8 Testing the teleoperationports
C.11.9 Teleoperation AF1, if notused for telephony
C.11.10 Teleoperation AF2
TestNo. Test procedure Test point
Permissiblevalue Units
Testresult
C.11.11 Teleoperation AF3
C.11.12 Teleoperation AF4
C.11.13 Teleoperation AF4 used forext. teleprotection
C.12. V.11 ports
C.12.1 V.11 Port 1
C.12.2 V.11 Port 2
TestNo. Test procedure Test point
Permissiblevalue Units
Testresult
C.13. V.24 ports
C.13.1 V.24 Port 1
C.13.2 V.24 Port 2
C.13.3 V.24 Port 3
C.13.4 V.24 Port 4
C.14. Testing of LAN port
C.14.1 LAN Port 1
C.14.2 LAN Port 2
C.14.3 LAN Port 3
TestNo. Test procedure Test point
Permissiblevalue Units
Testresult
C.14.4 LAN Port 4
C.14.5 HMI over LAN
C.15. Testing of O4CV
C.15.1 Slot positions of O4CVboards
C.15.2 Service Phone
C.15.3 Hot line direct phone
TestNo. Test procedure Test point
Permissiblevalue Units
Testresult
C.15.4 Remote subscriber
C.15.5 Pax 2-wire
C.15.6 Pax 4-wire
C.16. Manual reset
C.17. Documentation
YES NO YES NO
Commissioning Approved: Exceptions Noted:
Pending Items List:
CONSORTIUM
9PKE-16-2010-Rev00 - Power Line Carrier Equipment
Test InstrumentType
TestInstrumentNo.
Remarks:
Date:
Tested by: Witnessed by:
ABB DESCON
Witnessed by: Witnessed by:
FWEL LI