US-95 Granite North Safety Improvements95Project Update - January 2019
The Idaho Transportation Department (ITD) held a public meeting on July 31, 2018, to share plans to add frontage roads along US-95 from just south of Homestead Rd. to Trails End Rd. and to widen approximately 1.5 miles of the highway. We heard your concerns and the project team is working to address as many as possible. The project team is working to refine the design and is meeting individually with several property owners to discuss right of way (ROW) needs and impacts. As a result, the ROW acquisition process will occur in spring 2019 rather than this winter. Construction is still anticipated to start in spring/summer of 2020.
ITD Project Websites - itdprojects.org
2018 2019O N D J F M A M J J A S O N D
Final Design Bidding & Advertisement
ROW Plans
ValueEngineering
Study
we are here
Conceptual & Final Roadway Design
ROW Acquisition Process
Meet with Property Owners
Schedule
US-95 Granite North Safety Improvements ProjectITD - District 1ATTN: Chance Cole600 W. Prairie AvenueCoeur d’Alene, ID 83814
Idaho Transportation DepartmentUS-95 Granite North Safety ImprovementsIf you have questions, please contact:Merrill SharpITD Project Manager208.334.4420ITD Projects Website - itdprojects.org
Granite Lake
Mara Meadows Road
Old House Road
Rock
Sprin
gs R
oad
Project AreaConceptual design shown as colored lines on map
Vintage 95 RoadSouthbound US-95Northbound US-95Mineral Ridge RoadCounty Road Connection
Legend
Granite Loop Road