Upload
mohammed-younus-al-bjari
View
219
Download
0
Embed Size (px)
Citation preview
7/31/2019 57688252 Cost Overrun
1/16
Time over run and Cost over run
7/31/2019 57688252 Cost Overrun
2/16
A cost overrun, also known as a costincrease or budget overrun, is anunexpected cost incurred in excess of a
budgeted amount due to an under-estimation of the actual cost duringbudgeting. Cost overrun should be
distinguished from cost escalation, whichis used to express an anticipatedgrowth ina budgeted cost due to factors such asinflation.
http://en.wikipedia.org/wiki/Costhttp://en.wikipedia.org/wiki/Cost_escalationhttp://en.wikipedia.org/wiki/Cost_escalationhttp://en.wikipedia.org/wiki/Cost7/31/2019 57688252 Cost Overrun
3/16
Cost overrun is common in infrastructure,
building, and technology projects. A
comprehensive study of cost overrunpublished in the Journal of the American
Planning Association in 2002 found that 9
out of ten construction projects had
underestimated costs
http://en.wikipedia.org/wiki/Infrastructurehttp://en.wikipedia.org/wiki/Buildinghttp://en.wikipedia.org/wiki/Technologyhttp://en.wikipedia.org/wiki/Projectshttp://en.wikipedia.org/wiki/Projectshttp://en.wikipedia.org/wiki/Technologyhttp://en.wikipedia.org/wiki/Buildinghttp://en.wikipedia.org/wiki/Infrastructure7/31/2019 57688252 Cost Overrun
4/16
Overruns of 50 to one hundred percent
were common.Cost underestimation was
found in each of 20 nations and fivecontinents covered by the study, and cost
underestimation had not decreased in the
70 years for which data were available
7/31/2019 57688252 Cost Overrun
5/16
For IT projects, an industry study by the
Standish Group found that the average cost
overrun was 43 percent; 71 percent ofprojects were over budget, exceeded time
estimates, and had estimated too narrow a
scope; and total waste was estimated at $55
billion per year in the US alone.
http://en.wikipedia.org/wiki/IT_projectshttp://en.wikipedia.org/wiki/Scopehttp://en.wikipedia.org/wiki/Scopehttp://en.wikipedia.org/wiki/IT_projects7/31/2019 57688252 Cost Overrun
6/16
7/31/2019 57688252 Cost Overrun
7/16
Three types ofexplanation for cost overrun exist:
technical, psychological, and political-economic.
Technical explanations account for cost overrun
in terms of imperfect forecasting techniques,inadequate data, etc. Psychological explanations
account for overrun in terms ofoptimism bias
with forecasters. Finally, political-economic
explanations see overrun as the result ofstrategic
misrepresentation of scope or budgets.
http://en.wikipedia.org/wiki/Explanationhttp://en.wikipedia.org/wiki/Technologyhttp://en.wikipedia.org/wiki/Psychologicalhttp://en.wikipedia.org/wiki/Politicalhttp://en.wikipedia.org/wiki/Economichttp://en.wikipedia.org/wiki/Forecastinghttp://en.wikipedia.org/wiki/Optimism_biashttp://en.wikipedia.org/wiki/Strategic_misrepresentationhttp://en.wikipedia.org/wiki/Strategic_misrepresentationhttp://en.wikipedia.org/wiki/Strategic_misrepresentationhttp://en.wikipedia.org/wiki/Strategic_misrepresentationhttp://en.wikipedia.org/wiki/Optimism_biashttp://en.wikipedia.org/wiki/Forecastinghttp://en.wikipedia.org/wiki/Economichttp://en.wikipedia.org/wiki/Politicalhttp://en.wikipedia.org/wiki/Psychologicalhttp://en.wikipedia.org/wiki/Technologyhttp://en.wikipedia.org/wiki/Explanation7/31/2019 57688252 Cost Overrun
8/16
Cost overrun is typically calculated in oneof two ways: either as a percentage,namely actual cost minus budgeted cost, in
percent of budgeted cost; or as a ratio ofactual cost divided by budgeted cost. Forexample, if the budget for building a new
bridge was $100 million, and the actualcost was $150 million, then the costoverrun may be expressed by the ratio 1.5,or as 50 percent.
http://en.wikipedia.org/wiki/Percentagehttp://en.wikipedia.org/wiki/Ratiohttp://en.wikipedia.org/wiki/Ratiohttp://en.wikipedia.org/wiki/Percentage7/31/2019 57688252 Cost Overrun
9/16
Cost over run (under run) to date
There is cost over run when the cost
incurred is more than the value of work
done. Similarly, there is cost under run when the
cost incurred is less than the value of work
done.
Cost over run is usually expressed in terms
of %age terms.
7/31/2019 57688252 Cost Overrun
10/16
Formula for cost over run:
Actual Cost Value of work completed
=
*100Value of work completed
7/31/2019 57688252 Cost Overrun
11/16
Value of work done to date
When costs are measured, an estimate
should also be made of the extent of the
work accomplished. The value of the workdone completed can be obtained as
follows:
= Budgeted Costs * %age work
accomplished
7/31/2019 57688252 Cost Overrun
12/16
For Eg.
A certain activity has a budgeted cost of
Rs. 80,000 and at the time of the periodic
process review it is estimated that 60% ofthe work has been accomplished. So, the
value of the work done
= Rs.80,000 * 60%
= Rs. 48,000
7/31/2019 57688252 Cost Overrun
13/16
Time over run (under run) to date
There is time over run if the project is
behind schedule. Likewise, there is time
under run if the project is ahead ofschedule.
Time over run is usually defined in terms
of months behind or months ahead.
7/31/2019 57688252 Cost Overrun
14/16
REASONS OF OVER RUN
Imperfect Forecasting techniques,
inadequate data, etc.
Optimism bias with forecasters Strategic misrepresentation of scope or
budgets
http://en.wikipedia.org/wiki/Forecastinghttp://en.wikipedia.org/wiki/Optimism_biashttp://en.wikipedia.org/wiki/Strategic_misrepresentationhttp://en.wikipedia.org/wiki/Strategic_misrepresentationhttp://en.wikipedia.org/wiki/Optimism_biashttp://en.wikipedia.org/wiki/Forecasting7/31/2019 57688252 Cost Overrun
15/16
RECOMMENDATIONS
All three explanations can be considered forms ofrisk. A project's budgeted costs should always include cost
contingency funds to cover risks. Poor risk analysis and contingency estimating
practices account for many project cost overruns. Numerous studies have found that the greatest causeof cost growth was poorly-defined scope at the timethat the budget was established. The cost growth, oroverrun of the budget before cost contingency isadded, can be predicted by rating the extent of scopedefinition, even on complex projects with newtechnology.
http://en.wikipedia.org/wiki/Riskhttp://en.wikipedia.org/wiki/Cost_contingencyhttp://en.wikipedia.org/wiki/Cost_contingencyhttp://en.wikipedia.org/wiki/Risk_analysishttp://en.wikipedia.org/wiki/Cost_contingencyhttp://en.wikipedia.org/wiki/Cost_contingencyhttp://en.wikipedia.org/wiki/Cost_contingencyhttp://en.wikipedia.org/wiki/Cost_contingencyhttp://en.wikipedia.org/wiki/Risk_analysishttp://en.wikipedia.org/wiki/Risk_analysishttp://en.wikipedia.org/wiki/Risk_analysishttp://en.wikipedia.org/wiki/Cost_contingencyhttp://en.wikipedia.org/wiki/Cost_contingencyhttp://en.wikipedia.org/wiki/Cost_contingencyhttp://en.wikipedia.org/wiki/Risk7/31/2019 57688252 Cost Overrun
16/16