31
Theodore Smith, NRC Reactor Decommissioning Branch Buffalo, New York Division of Waste Management and Environmental Protection University of Michigan Ford Nuclear Reactor

University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

Theodore Smith, NRC

Reactor Decommissioning Branch

Buffalo, New York

Division of Waste Management and Environmental Protection

University of Michigan

Ford Nuclear Reactor

Page 2: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

2

University of Michigan Michigan Memorial Phoenix Project - Ford Nuclear Reactor

Located in Ann Arbor, Michigan– 2 MW (thermal) heterogeneous core open pool reactor

– Integrated lifetime power = 17,868 MW-days.

Regulatory Milestones• 1957 – Reactor operations begin

• July 2003 - Shutdown

• December 2003 - Fuel shipped to US Department of Energy

• June 2004 – Decommissioning Plan (DP) submitted

• January 2006 – Revised DP submitted, D&D begins

• October 2007 –major structures removed, incl pool wall & floor

• December 2007- Last waste shipment completed

• April 2011 to Sept 2012 (8 total) - Partial Survey Plans Submitted

• October 2012 - partial survey plans approved by NRC

Page 3: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

3

University of Michigan Michigan Memorial Phoenix Project - Ford Nuclear Reactor

Schedule� Nov - Dec 2012 - Final Status Surveys

� Dec 3-7, 2012 – Confirmatory Surveys

� Early 2013 – Submit remaining survey plans (subsurface areas)

� Spring 2013 – NRC approve subsurface survey plans

� Late 2013 Terminate License

Cost Estimate = $14,400,000 US ($9,800,0000 est.)

Page 4: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

4

University of Michigan Michigan Memorial Phoenix Project - Ford Nuclear Reactor

Cost Overrun Factors– Total overrun = $4,600,000 US

1. Concrete removal of reactor pool walls & floor

� Based on proposed facility reuse

� Cutting and removal of 10,500 feet3 (~300 meter3) of high density concrete

� Effort increased due to embedded components� Capped pipe containing lead shot

� Unanticipated piping and conduct runs

� Movement of structural materials during cutting

� Added time & effort cost = $1,750,000

Page 5: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

5

University of Michigan Michigan Memorial Phoenix Project - Ford Nuclear Reactor

Cost Overrun Factors

2. Waste Disposal Costs

� One low level waste facility in US

� Market rates changed after initial estimate

� Initial estimate excluded rigging cost for concrete block loading

� Added cost = $1,100,000 US

3. Increased oversight, decreased productivity, & delays

� Thermal column assembly conditions

� Insurance requirements

� Reactor pool draining delays

� Added cost = $1,150,000 US

4. Contingency added = $600,000 US

Page 6: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

6

Schedule

� Nov - Dec 2012 - Final Status Surveys

� Dec 3-7, 2012 – Confirmatory Surveys

� Early 2013 – Submit remaining survey plans (subsurface areas)

� Spring 2013 – NRC approve subsurface survey plans

� Late 2013 Terminate License

Cost Estimate = $14,400,000 US ($9,800,0000 est.)

� Concrete removal of reactor pool walls & floor (based on proposed facility reuse

University of Michigan Michigan Memorial Phoenix Project - Ford Nuclear Reactor

Page 7: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

7

University of Michigan Michigan Memorial Phoenix Project – Ford Nuclear Reactor

Site History

• May 1959 – 3,600 gallon (13,500 L) pool water leak through beam port

• May 1961 – 1st & 2nd floors contaminated with Ag-110m

• June 1963 – Beam port collimator leak, contaminating 1st floor

• Sept 1967 – Fuel element failure identified by air sampling

• Oct 1967 – Ventilation system contaminated

• Oct 1971 – Argon-41 release due to beam port flooding

• Jan 1977 – Pneumatic tube failure releases fission products

• Dec 1977 – New pneumatic system generates airborne release

• April 1987 – Spill of 1 quart (1 L) of heavy water on 3rd floor

• Jan 1989 – Fuel element failure identified by pool water chemistry

• Nov 1991 – Fuel element failure identified by air monitoring

• July 1993 – 7,500 gallons (28,000 L) of low level radioactive water released through building foundation drain over 36 days

• May 1998 – 75 gallons (280 L) pool water leak from resin column

• March 2001 – 3rd floor contaminated by flux measurement device

Page 8: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

8

FNR

Page 9: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

9

FNR

Page 10: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

10

FNR

Page 11: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

11

FNR

Page 12: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

12

FNR

Page 13: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

13

FNR

Page 14: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

14

FNR

Page 15: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

15

FNR

Page 16: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

16

FNR

Page 17: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

17

FNR

Page 18: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

18

FNR

Page 19: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

19

FNR

Page 20: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

20

FNR

Page 21: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

21

FNR

Page 22: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

22

FNR

Page 23: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

23

FNR

Page 24: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

24

FNR

Page 25: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

25

FNR

Page 26: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

26

FNR

Page 27: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

27

FNR

Page 28: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

28

FNR

Page 29: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

29

FNR

Page 30: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

30

FNR

Page 31: University of Michigan Ford Nuclear Reactor Documents... · MichiganMemorial Phoenix Project -Ford Nuclear Reactor Cost Overrun Factors – Total overrun = $4,600,000 US 1. Concrete

31

FNR