7/28/2019 5 Phases PMP
1/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project Management
7/28/2019 5 Phases PMP
2/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementWhat is a Project?
Complex and numerous
activities.
Uniquea one-time set of
events
Finitewith a begin and
end date.
Limited resources and
budget
Many people involved,
usually across several
functional areas in the
organizations.
Sequenced activities.
Goal-oriented.
End product or service
must result.
7/28/2019 5 Phases PMP
3/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementWhat is a Project Management?
PLANNING INVOLVES THE ESTABLISHMENT OF CLEAR AND PRECISE
OBJECTIVES IN ORDER TO REACH A FINAL, STATED GOAL
ORGANIZING ASSEMBLY OF NECESSARY RESOURCES FOR CARRYING OUT
THE WORK DEFINED IN THE PLAN
CONTROLLING MONITOR AND MAINTAIN AS THE PROJECT PROGRESSES
CHANGE
INSTITUTING MECHANISMS NEEDED FOR SITUATIONS THATREQUIRE CHANGE
7/28/2019 5 Phases PMP
4/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementThe 5-Phase Method
The 5-Phase Method contains specific steps thatexpand the general process into a detailed set ofprocedures.
1. Define (5 Action Steps)
2 Plan (5 Action Steps)
3. Organize (5 Action Steps)
4. Control (5 Action Steps)
5. Close (5 Action Steps)
1 & 2 = Planning; 3, 4 & 5 = Implementation
7/28/2019 5 Phases PMP
5/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementCauses of Project Failure
1. The Project is a solution in search of a problem.
2. Only the project team is interested in the end result.
3. No one is in charge.
4. The project plan lacks structure.5. The project plan lacks detail.
6. The project is under budgeted.
7. Insufficient resources are allocated.
8. The project is not tracked against its plan.
9. The project team is not communicating.
10. The project strays from its original goals.
7/28/2019 5 Phases PMP
6/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementProblem Identification
What is theproblem/opportunity?
What is to be done? Who is responsible for the
project?
When must the project be
completed?
7/28/2019 5 Phases PMP
7/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementProject Goals - Identification
Prepare and launch the new shuttle line Atlantisfrom Earthto the Moon Colony by March 5, 2025.
Connect Italy with Sicily via the new G.Garibaldiworld'slongest single-span suspension bridge and have it open for
traffic no later then July 2008. Design and complete testing by April, 2005, of MS Project
2005, Project Management software.
Obtain an MSc. Degree in the EESI program from theRoyal Institute of Technology by spring next year.
7/28/2019 5 Phases PMP
8/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementObjectives Milestones
The S.M.A.R.T. methodSpecif ic: Be specif ic in targeting an objective
Measurable: Establish a measurable indicator(s) of progress.
Aassignable: Make the objective capable of being assigned tosomeone for completion.
Reali stic: State what can be realistically achieved withinbudgeted time and resources.
Time-related: State when the objective can be achieved, that is,the duration.
7/28/2019 5 Phases PMP
9/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementResources, Assumptions and Risks
Determine preliminary resources:1. The resources were determined without project manager input.
2. The project manager determined the needed resources based on the plan.
Identify Assumptions and risks:1. What resources are required to realistically complete this objective? What risks
are associated with obtaining any of these resources in a timely manner?
2. What problems and delays are likely to occur in completing this objective?
3. What effect(s) will delays have on the budget and overall project schedule andplan?
4. What are the probable time, money, and personell cost overruns to completethis project?
5. What assumptions can be made to realistically correctfor delays in completing
this objective within given resources and constraints?
7/28/2019 5 Phases PMP
10/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementWBS Work Breakdown Structure (1)
WBS is a simple decomposition process, i.e. a
hierarchical representation of the project.
WBS identifies the activities that must be done tobegin
and complete a project.
WBS involves the envisioning of the project as a
hierarchy of a goal, objectives, activities, subactivities
and work packages.
Milestones are events that signify the accomplishment or
completion of major deliverables during a project.
7/28/2019 5 Phases PMP
11/20
7/28/2019 5 Phases PMP
12/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementSteps Work Breakdown Structure (3)
Step 1:
Divide the project into its major objectives such that the project is fullydefined by the objectives.
Step 2:
Partition each objective into the activities that must be done in order toaccomplish the objective.
Step 3:
For each activity having one or more missing characteristics divide thatactivity into the subactivities comprising it.
Step 4:
Repeat step 3 until all subactivities have the characteristics desired.
Step 5:
The lowest-level subactivities in the hierarchy will be the basis of the workpackages that must be done in order to complete the project.
7/28/2019 5 Phases PMP
13/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementGantt Charts (1)
History
developed by Henry Gantt (1861-1919)
First used in Frankford ammunition shops
in 1914 (World War I Naval Ships) Milestone markers, time outlines
Took 80 years to add task dependecies
popular since inception and is widely used
today
precusor of CPM/PERT
7/28/2019 5 Phases PMP
14/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementGantt Charts (2)
Project management tool
Horizontal line or bar chart
Time ordered listing of planned
events
Visual representation of an
organizations schedule for
milestones
Graph with bar representing
time for each activity
Ideal for starting project work
description schedules and plans activities
7/28/2019 5 Phases PMP
15/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementGantt Charts (3)
Helps identify
start of activities
end of activities
slack time
amount of time an activity can be
delayed without delaying the project
precedence relationships betweenactivities
7/28/2019 5 Phases PMP
16/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementPERT Charts (1)
What is a PERT Chart? Program Evaluation and Review Technique
Project management tool
Complex network diagrams
Used to schedule, coordinate and organize tasks within a project
History of PERT Charts United States Navy (Polaris Program) 1958
RAND Corporation Missile Development
Post World War II (1950s) Critical Path Method/Analysis (CPM) Developed by Du Pont 1957
Gives managers greater control of larger projects
7/28/2019 5 Phases PMP
17/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementHow Charts Are Made
Gantt Charts
Time across the
top Tasks listed
down the sides
Lines connecting
dependent tasks
PERT Charts
Grouped by most critical
path Dependencies are
clearly identified
Task times are included
in boxes / circles
7/28/2019 5 Phases PMP
18/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
The Critical Path for a project is that sequence of dependent tasks thathave the largest sum of most likely durations. The critical pathdetermines the earliest possible completion date of the project.
Tasks that are on the critical path cannot be delayed without delayingthe entire project schedule.
The slack time available for any noncritical task is the amount of delay
that can be tolerated between the starting time and completion time of atask without causing a delay in the completion date of the entire project.
For each path, sum the durations of all tasks in the path.The path withthe longest total duration is the Critical Path.The critical path for aproject is that sequence of dependent tasks that have the largest sum ofmost likely durations. The critical path determines the earliestcompletion date of the project.The slack time available for any
noncritical task is the amount of delay that can be tolerated between thestarting time and completion time of a task without causing a delay inthe completion date of the entire project.
5-Phase Project ManagementSteps Critical Path Method (CPM)
7/28/2019 5 Phases PMP
19/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementCritical Path Method (CPM)
The criticalpath is
highlightedin red
TASKC
Fri 2/9/01 2 days
Fri 2/9/01 0 days
TASKD
Tue 2/20/017 days
Tue 2/20/010 days
TASKI
Tue 2/27/015 days
Tue 2/27/010 days
TASKE
Mon 2/19/016 days
Tue 2/20/011 day
TASKB
Wed 2/7/01 2 days
Wed 2/7/01 0 days
TASKA
Mon 2/5/01 3 days
Mon 2/5/01 0 days
TASKH
Thu 2/15/011 day
Tue 2/20/013 days
TASKF
Wed 2/14/013 days
Fri 2/16/01 2 days
TASKG
Fri 2/16/01 2 days
Tue 2/20/012 days
Duration
Slack Time
7/28/2019 5 Phases PMP
20/20
Weiss & Wysocky, 1992. Sustainable
Project Management, 2005
5-Phase Project ManagementTime, Cost and Project Activities
Estimating Activity Time: Optimistic completion time
Pessimistic completion time
Most likely completion time
So we can use this formula to
calculate the EExpectedcompletion time of activity:
Average activity completion time=E = (O+4M+P)/6
Formula gives the weighted average
Estimating Activity Cost:
Labor
Materials
Other direct (travel, telephone,
contracted services, etc.)
Indirect (overhead)
CPM = Critical Path Method
(sequencing and identifying
critical project activities)