34
Offshore Design Section Engineering Services ISO – 9001:2008 DESIGN CRITERIA PROCESS AND UTILITIES Volume No: II Section No: 3.2 “HRD-Process Platform” Project No: Page: 1 OF 34 FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010 PART – IV SECTION - 3.2 PROCESS DESIGN CRITERIA OIL AND NATURAL GAS CORPORATION LIMITED INDIA AB BSW AKR 05.05.12 34 0 PREPARED BY CHECKED BY APPROVED BY ISSUED FOR BID DATE No. of Pages REV

4.3 Vol II Sec.3.2 - Process Design Criteria

Embed Size (px)

DESCRIPTION

oil gas process

Citation preview

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 1 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    PART IV

    SECTION - 3.2

    PROCESS DESIGN CRITERIA

    OIL AND NATURAL GAS CORPORATION LIMITED

    INDIA

    AB BSW AKR

    05.05.12 34 0

    PREPARED

    BY

    CHECKED

    BY

    APPROVED BY

    ISSUED FOR BID

    DATE No. of

    Pages

    REV

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 2 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    TABLE OF CONTENTS

    ANNEXURES

    ANNEXURE-I WELL FLUID COMPOSITION (TYPICAL)

    HEERA FIELD

    ANNEXURE-II PRODUCED WATER ANALYSIS

    ANNEXURE-III DIESEL FUEL SPECIFICATIONS

    SECTION TITLE

    3.2 INTRODUCTION

    3.2.1 DESIGN CRITERIA HRD PROCESS PLATFORM

    3.2.2 DESIGN CRITERIA FOR MODIFICATIONS ON

    EXISTING HEERA COMPLEX (HRC, HRG, WIH)

    3.2.3 DESIGN CRITERIA OF PRE-INSTALLED RISERS

    3.2.4 DESIGN CRITERIA OF FUTURE EQUIPMENTS

    3.2.5 INSTRUMENTATION AND CONTROL

    3.2.6 SPARING PHILOSOPHY

    3.2.7 UNITS OF MEASUREMENT

    3.2.8 NUMBERING PHILOSPHY

    3.2.9 CODES AND STANDARDS

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 3 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    3.2 INTRODUCTION This section of bid package defines design criteria for Process and Utility

    systems required for HRD Process Platform (bridge connected to existing HRC

    platform) under HRD Re-development (Phase-II) Project. Under this project, the

    scope of work includes the following facilities:-

    a) HRD Process Platform. Section 3.2.1 covers the design criteria for process

    platform. b) Modifications at existing HEERA Process Complex (HRG/ H R C / WIH).

    Section 3.2.2 covers the design criteria for various facilities and modifications

    envisaged at HEERA HEERA Process Complex including bridge inter-

    connection between existing HRC Process Platform and new HRD Process

    Platform

    GENERAL REQUIREMENTS

    Contractor to note that this document provides the design criteria of various

    process facilities and utilities envisaged in the project. Contractor to strictly

    follow these criteria while designing various systems or units envisaged in the

    project. However, the sizes, capacities etc. of various units specified in this

    design criteria or specified elsewhere in the bid package shall be followed as

    minimum requirement. In case of any discrepancy between various documents,

    Contractor shall refer the same to the Company for resolution and proceed wi th

    the i r design and engineering only after companys decision with no impact to

    cost and schedule of the project.

    The sizes, specifications and drawings furnished in bid document for various

    facilities at HRD Process Platform and modifications at existing HEERA Process

    Complex are indicative & minimum to be provided by the Contractor. It is the

    Contractors responsibility to verify all the design/ data before proceeding for the

    detailed design and engineering. Under the scope of this contract, Contractor

    shall perform all necessary process simulation using HYSYS software (latest

    version), design calculations and consider adequate design margins while

    specifying equipment /instrumentations. Contractors responsibility also includes

    carrying out safety studies and review operability aspects of the facilities and

    incorporates findings of the same while designing the facilities. Any deviation

    shall require Companys approval.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 4 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    The process and utility flow diagrams and indicative P&ID s are enclosed

    in the bid document. Contractor shall develop detailed process design basis, process

    flow diagrams, material & energy balance, utility flow diagrams etc. for

    different cases indicated in this criteria and design the process and utility

    systems, accordingly. In case, simulation results show higher flow rates and

    varying pressure/ temperature ranges for some applications, the more conservative

    figures/ ranges shall be used for design and no. of process vessels/ equipment

    required under intended operations shall be so decided within the scope of this

    contract. Contractor may seek clarifications, if required any, during detailed

    engineering. The design of process and associated utility systems for HRD

    process platform and modifications at existing HEERA complex shall be

    suitably designed for these higher flow rates/ ranges. Accordingly, Contractor shall

    develop detailed utility balance and utility flow diagrams.

    Contractor shall develop detailed Piping and Instrumentation Diagrams, Cause &

    Effect Diagrams, SAFE charts etc. incorporating all suppliers information.

    Contractor shall prepare data sheets and specifications for all the equipment,

    instruments etc. Sufficient margins shall be taken on operating parameters viz.

    pressure/ pressure drop, temperature, flow, level etc. to take care of complete

    operating range and any other unforeseen eventualities. Contractor shall ensure that P&IDs shall include all required instrumentation

    for local as well as for remote monitoring and control of critical process

    parameters (including but not limited to pressure, temp., flow, level etc.).

    Additional instrumentation, if required based upon HAZOP study as well as

    operational requirement, shall be provided without any time and cost impact to

    the Company.

    Contractor shall develop sizes / routing / distribution of various utilities (namely

    Vent/ HP flare/ LP flare, Open/ Closed Hydrocarbon Drain, Open Deck Drain,

    Diesel, Instrument/ Utility/ Starting Air, Fire water, Utility water, Potable

    water, Cooling water, Inert gas, Chemicals etc.) and finalize the same during

    detail engineering.

    Contractor shall ensure that the design of process platform shall meet the relevant

    codes and standards requirements. A typical list of applicable codes is

    included in this Bid Package. This, however, cannot be taken as an exhaustive

    list and various codes and standards as mentioned in functional

    specifications as well as those applicable as per good engineering

    practices shall also form the basis and shall have to be followed by the

    Contractor in consultation with Company/ Companys engineering consultant.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 5 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    The various process and utility system hook-ups indicated under bridge inter-

    connections, between existing HRC platform and HRD platform are minimum

    indicative. It shall be the Contractors responsibility to get familiar with the

    existing process/ utility lines/ headers on HRC/ HRG platform, during pre-

    engineering survey (topside modifications) in order to ascertain the extent

    and completeness of work to be carried out for hook- up, extension and routing of

    such lines/ headers up to new bridge and their further hook-up with corresponding

    lines/ headers on HRD platform through bridge inter-connections.

    Contractor , during pre-engineering survey (topside modifications) of HEERA

    complex, shall also assess/ verify the deck space, hook-up points, routing of the

    lines, necessary inter-connections through bridge, integration with existing facilities

    etc. and finalize all essential aspects of modifications. Wherever as-built

    drawings of e x i s t i n g facilities are n o t a v a i l a b l e , Contractor shall

    develop the existing drawings relevant for the intended modifications to an as-built

    status for the detailed engineering. Since the existing HEERA complex will be operational, the Contractor shall

    develop detailed procedures for carrying out modification works and shall design/

    plan his works such that hot work and platform shutdown requirements are

    eliminated or reduced to bare minimum. Adequate care shall be exercised while

    developing the existing process platforms modification requirements with special

    emphasis towards safety, operability and hook-ups. Special attention shall be

    given to minimize the shut down time required at existing process platforms and

    safety for executing the modifications.

    All the process, utility, safety and instrumentation systems shall meet the

    requirements of API-RP-14C Recommended Practice for Analysis, Design,

    Installation and Testing of Basic Surface Safety Systems on Offshore

    Production Platforms Latest Edition.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 6 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    Contractor shall submit reports/ documents/ calculations/ drawings as per the list

    given below for Companys review and approval. Contractor to note that this is a

    typical list and shall be supplemented with additional detail engineering

    documents as felt necessary by the Company, during detail engineering:-

    - Pre-engineering Survey Report (Topside Modifications)

    - Process & utility design basis

    - Process & utility description

    - Process simulation report

    - PFDs / UFDs/ P&IDs (1st submission & subsequent

    revisions)

    - Process and utility calculation report (*)

    - CFD Report of all the major process flows/ vessels

    - Process control philosophy

    - Black start philosophy

    - Isolation philosophy

    - Blow down calculation report

    - Flare load calculation report

    - Vent dispersion analysis report

    - Equipment list

    - Tie-in schedule

    - Alarm & trip schedule

    - Process Data Sheets - Equipment

    - Process Data Sheets Instruments

    - Cause & effect chart

    - SAFE chart

    - Line list

    - Operating manual etc.

    (*) Process and utility calculation report shall include

    sizing calculations for process/ utility piping, equipments/ vessels,

    safety/ relief valves, control valves, choke valves, orifice

    plates etc.

    However, sizing of equipment/ instruments for which vendors

    information are required, preliminary calculations shall be

    submitted initially. Subsequently, same shall be updated by the

    Contractor based upon vendors information and shall be re-

    submitted for Companys review and approval. Also, hydraulic

    calculations shall be updated based on final routing/ layout etc.

    as per actual piping isometrics, and re-submitted for

    Companys review and approval.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 7 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    Contractor shall submit soft copy (including EXCEL sheets

    indicating mathematical correlations) of sizing calculations for

    review of results indicated in calculation report.

    Detailed CFD analysis shall be carried out for all the Process

    vessels, systems and PGCs during the design as well as

    manufacturing phase and the due results shall be submitted to

    ONGC.

    Contractor to note that based upon review and approval of aforesaid

    calculations/ documents/ drawings only, P&IDs shall be Approved

    For Construction (AFC).

    Engineering shall also be done for all specified future facilities

    wherever required.

    HAZOP STUDY Based upon review and approval of aforesaid reports/ documents/ calculation/

    drawings etc., P&IDs shall be issued for HAZOP study. Contractor shall

    engage an internationally reputed third party agency for carrying out HAZOP

    study. The venue and timing of HAZOP workshop shall be finalized

    through mutual consent between Contractor and the Company. The HAZOP

    observations/ recommendations shal l be deliberated in presence of/ with

    Companys representatives/ Operations representative/ Engineering

    consultant. The firmed-up HAZOP recommendations shall be incorporated

    in relevant doc./ drgs. and after their approval, P&IDs shall be issued for

    Approved for Construction (AFC).

    Contractor to note that all changes arising due to HAZOP study shall be

    considered and incorporated as part of firm scope of this contract without

    any time and cost impact to the Company. Also, any changes arising due to

    Companys review / approval, for whatsoever reason shall be

    implemented in the design of the facilities under the scope of this contract

    without any time and cost impact to the Company.

    DOCUMENTATION

    The Contractor shall submit all the documentation as per requirements

    given elsewhere in the bid document. In addition, Contractor shall prepare

    process packages and submit to the Company & their Consultant, within

    one month of approval of these documents. The process package shall

    consist of the following documents:

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 8 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    - Design basis (with approved deviations, if any)

    - AFC P&IDs /Suppliers P&IDs (A3 size & bound

    together)

    - AFC Equipment lay-outs (A0 &A3 size & bound

    together)

    - PFDs & UFDs including Heat and material balance.

    - Cause and Effect Diagram

    - SAFE Charts

    - Data sheet for Equipment

    - Data sheet for Instruments

    - Line list

    - Equipment list

    - All process /sizing calculations

    - CFD Report of all the major process flows/ vessels

    - Operating manual

    - Vendor Document/ Literature

    3.2.1 DESIGN CRITERIA HRD PROCESS PLATFORM

    3.2.1.1 DESIGN LIFE: 25 years

    3.2.1.2 PLATFORM LOCATION: Refer Structural Design Criteria Part

    - II

    3.2.1.3 SOURCE OF WELL FLUID : Additional well fluid from HP,HK

    AND HSD well platforms (from

    extended production manifold at

    HRC through HRC- HRD bridge

    inter-connection)

    3.2.1.4 DESTINATION OF OIL

    (AFTER HP SEPARATOR): HRC Oil manifold (through

    HRD-HRC

    interconnection)

    3.2.1.5 DESTINATION OF GAS

    (AFTER COMPRESSION): HRC-HRG net gas header on HRG

    (through HRD- HRC inter-

    connection

    3.2.1.6 DESTINATION OF PDODUCED WATER

    (AFTER HP SEPARATION): HRC-HRG produced water header on

    HRC platform (through HRD-

    HRC inter-connection).

    25 years

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 9 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    3.2.1.7 PROCESS DESCRIPTION

    Well fluid from HP,HK and HSD well platforms via existing HRC production

    manifold shall be received at HRD plat form through HRC-HRD bridge

    interconnection at operating pressure 8 16 kg/cm2g.

    The well fluid received at HRD Process Platform shall be first routed

    to the three phase cyclone separator with a provision to bypass the same.Then the

    WF is diverted to the well fluid heaters using hot oil and shall be heated from 210C

    to 600

    C and then shall be routed to the new 3 Phase HP separators (with in-built

    electrostatic coalescer) maintained at operating pressure range 7.5 -12 kg/cm2g.

    Gas from 3-Phase Cyclone separator shall be routed to compressor inlet manifold

    and liquid shall be routed for further processing at existing platform of HRC and

    HRG.

    Oil s t r e am from 3-Phase HP separator shall be sent to a location o n H R C

    p l a t f o r m a n d b e h o o k e d u p t o t h e o i l o u t l e t l i n e a t t h e

    d o w n s t r e a m o f H P s e p a r a t o r o n H R C p l a t f o r m . (through HRC-

    HRD bridge inter- connections). This partially stabilized oil shall combine with

    the crude oil from other sources and flow to the surge tanks at HRG and HRA for

    further separation and stabilization and subsequent pumping.

    Separated water (from HP Separator) shall be routed to the HRC platform and shall

    be connected to the produced water line at the outlet of the HP separator located at

    HRC platform via HRD-HRC Bridge,which shall be transported ultimately to HRG

    platform via HRC-HRG bridge up to the HRG produced water treatment system.

    The interconnection with produced water header is to be provided at HRC platform.

    A typical heat and mass balance is enclosed in bidding documents. Contractor

    shall, however, review the operating pressure range for w e l l fluid heater and

    HP separator based upon vendor data and carry out heat and mass balance for all

    the possible cases.

    The operation of PG compressors shall be facilitated through load sharing and

    capacity controls incorporated into the compressor skid control system. The new

    PG compressor shall be linked to the existing PG compressors on HRC as well

    as HRG platform via suction and discharge header. In normal operation, 6 nos.

    compressors (2 at HRC and 3 at HRG and 1 at HRD) will run in parallel

    maintaining 6 operating and one standby philosophy. If required, all 6 nos.

    compressors (including the new two at HRD) may also run in parallel.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 10 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    Gas will be compressed by the process gas compressor (PGC) up to 95 kg/cm2g

    followed with processing by the dehydration unit in HRG. A scrubber shall be

    provided on the discharge of PGC (after 3rd

    stage cooler) to prevent hydrocarbon

    liquid carryover from the compression train o n H R D to dehydration unit on

    HRG platforms respectively. G a s from HRD shall then be routed across the

    HRD-HRC and HRC-HRG bridge to mix with the compressed gas from the

    existing facility and then to the dehydration system of the exist ing platform

    - HRG. The outlet l ine of the compressors shall be routed up to the

    HRG platform and shall be connected to the outlet manifold of the

    compressors on the HRG platform.

    All necessary process and utility inter-connections shall be made through HRC-

    HRD bridge. Provision shall also be made to use gas separation, compression

    facilities of existing HEERA complex and HRD Process Platform from

    either of the platforms. The process inter-connections between HRD and HRC

    shall include but not be limited to hook-up of production manifolds,

    separated oil and produced water, compressor suction headers, compressor

    discharge headers . For utility inter-connections, refer Design Criteria Utilities.

    3.2.1.7 DESIGN CRITERIA PROCESS EQIPMENTS AND SYSTEM

    3.2.1.7.1 PRODUCTION H E A D E R / MANIFOLD

    No Production manifold has been envisaged at HRD platform. However, the

    production manifold of HRC platform shall be extended through the bridge of

    HRC-HRD and shall be routed up to the inlet of the De-sander and the

    wellfluid heater and then the HP separator. There shall be a flushing

    connection on extended inlet line. Also the line should hot insulated.

    The extended production header will be designed based on the following:-

    Operating pressure, kg/cm2g : 8 16

    Design pressure, kg/cm2g : 94.0

    Operating temperature, 0C : 21 60.

    Design temperature, 0C : 75.

    DESIGN CRITERIA PROCESS EQIPMENTS AND SYSTEM

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 11 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    3.2.1.7.2 THREE PHASE CYCLONE SEPARATOR

    One no. Three Phase Cyclone Separator shall be provided in the upstream of

    W.F. heater. The well fluid shall be de-gassed in a centrifugal type 3-Ph.

    Cyclone Separator.

    The 3-Phase Cyclone Separator will be designed based on the following:-

    Operating pressure, kg/cm2g : 8 16

    Design pressure, kg/cm2g : 94.0

    Operating temperature, 0C : 21 60.

    Design temperature, 0C : 75.

    The provision shall also be kept for bypassing it, if required .

    The cyclone separators are vertical vessels designed for 3 phase separation,

    primarily meant to knock-out gas from liquid and to drain the free water

    present in the fluid. This will be designed based on

    the following

    a) Operating conditions :

    - Pressure, kg/cm2g : 8.0 (Min.)

    : 16.0 (Max.).

    - Temperature, 0C : 21 - 60

    b) Design conditions :

    - Pressure, kg/cm2g : 94.0

    - Temperature, 0C : 75.0

    c) Flow rates (per unit)

    - Liquid, BLPD : 55000

    - Gas, MMSCMD : 2.0

    d) Surge factor : 25% of the maximum well fluid

    e) Swell factor : 15 % Minimum

    f) Maximum allowable : 13.4 Lit/MMSCM. Liquid Particle size in gas

    carry over liquid in gas shall not be more than 10 microns.

    g) Well fluid composition : Refer ANNEXURE

    centrifugal type 3-Ph.

    Cyclone Separator.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 12 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    3.2.1.7.3 WELL FLUID HEATERS

    The well fluid heaters are shell and tube type heat exchangers. The crude oil/

    water emulsion is passed through the tube side and heated by hot oil on the

    shell side. This temperature increase of the process fluid promotes the break

    down of the emulsion, thereby permitting downstream separation of the water

    phase.

    The well fluid heater will be designed based on the following:

    Heating medium: Hot oil

    Heating requirement: To heat well fluid from 210C (MIN) to 60

    0C(MAX.)

    Max. temp. heating medium(Hot oil ): 2500C .

    Min. temp. heating medium(Hot oil ): 1500C.

    3.2.1.7.4 HP SEPARATORS

    The HP Separators are horizontal vessels (with in-built electrostatic

    coalescer) designed for 3 phase separation of oil-gas-water by static

    electricity induced gravity settling. These will be designed based on the

    following:-

    a) Operating conditions :

    - Pressure, kg/cm2g : 7.5 (Normal)

    : 12 (Max.).

    - Temperature, 0C : 30-60

    b) Design conditions :

    - Pressure, kg/cm2g : 21.1

    - Temperature, 0

    C :104.0

    c) Flow rates:

    Oil (BOPD) Water

    (BWPD)

    Liquid (BLPD) Gas

    (MMSCMD)

    Maximum oil

    case

    20000 35000 55000 2.0

    Maximum

    water case

    5000 50000 55000 2.0

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 13 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    d) Residence time : Min 5 minutes for oil and water

    phase on maximum flow including

    surge & swell factor

    e) Maximum allowable : Centre line of vessel liquid level

    f) Allowable quantity of : 200 ppm ( V/V) max. oil in water

    g) Allowable quantity of : 1% ( V/V) max. water in oil

    h) Maximum allowable : 13.4 Lit/MMSCM.

    carry over liquid in gas Liquid Particle size in gas

    shall not be more than 10

    microns i) Well fluid composition : Refer ANNEXURE-I

    3.2.1.7.5 PROCESS GAS COMPRESSOR

    The process gas compressor takes suction from compressor Inlet

    Manifold on HRD platform and which is also interconnected to the

    compressor inlet manifold at HRC platform through HRD-HRC bridge

    inter-connection and delivers compressed gas to Discharge Manifold which

    is connected to compressed gas manifold at HRC through HRD-HRC

    bridge inter-connection. The process gas compressor will be designed based on the following

    i) No. of trains: 2 no. (1W+1S)

    ii) Flow:

    - Max. : 1.6 MMSCMD (dry basis)

    - Rated : 1.6 MMSCMD (dry basis)

    iii) Molecular Weight (*):

    - Max. : 23.5 (dry basis)

    - Min. : 20.5 (dry basis)

    (*) In case, simulation results show wider range, highest

    and lowest out of above and simulation results whichever

    are governing, shall be considered.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 14 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    iv) Pressure (at module battery limit):

    - Suction, kg/cm2g : 6.0 8.0

    - Discharge, kg/cm2g : 95.0

    v) Temperature (at module battery limit)

    - Suction, 0C : 30 - 60

    - Discharge, 0C :54

    vi) Type : Centrifugal (Dry gas seal type)

    vii) Driver : Gas turbine

    The gas shall be considered as saturated with water vapour at

    operating conditions of HP separator.

    Compressor package vendors scope shall include self-contained compressor

    skid having 1st stage, 2nd stage and 3rd stage compressor suction

    scrubber, inter- coolers, after-cooler, 3rd stage discharge scrubber, dedicated fuel gas conditioning unit, metering system, surge and speed

    controls, lube and seal oil system, local panel, unit control panels (located in central control room) and other utility and auxiliary systems. The fuel

    gas conditioning skid will consist as a minimum, suitable filters (specification to be decided by turbine vendor) and electric super heater designed to give a

    minimum super heat of 20 0C.

    Pressure and temperature at intermediate compressor stages indicated in the

    heat and mass balance is indicative. Contractor shall finalize the same in

    consultation with compressor vendor.

    The design pressure of suction side of compressor shall be maximum of the

    followings:

    i) Bid package specification

    ii) 110% of highest operating pressure

    iii) 1 kg/cm2 above the settle-out pressure.

    Compressor package vendors scope shall include self-contained compressor

    skid having 1st stage, 2nd stage and 3rd stage compressor suction

    scrubber, inter- coolers, after-cooler, 3rd stage discharge scrubber, dedicated fuel gas conditioning unit, metering system, surge and speed

    controls, lube and seal oil system, local panel, unit control panels (locatedin central control room) and other utility and auxiliary systems. The fuel

    gas conditioning skid will consist as a minimum, suitable filters (specificationto be decided by turbine vendor) and electric super heater designed to give a

    minimum super heat of 20 0C.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 15 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    The facilities of HP gas compressor system shall be designed for the performance under all environmental conditions as given in the enclosed environmental data. The air cooler shall be designed for cooling gas for 14 0C approach to maximum ambient temperature of 40 0C.

    The FG Skid as well as the L/O Cooler for individual compressors shall be

    considered to be the part of compressor module.

    Equipments exposed to process fluids shall be designed conforming to

    NACE MR-01-75.

    3.2.1.7.6 GAS DEHYDRATION & GLYCOL RE-GENERATION SYSTEM

    The dehydration and glycol regeneration system is not part of the present scope

    of this tender. However, for dehydrating the compressed gas from the new

    compressors at HRD, the feed from compressor discharge header shall be

    merged with the common discharge header on HRG. This shall be done

    through the extension of the discharge header on HRD platform up to HRC

    and then up to HRG platform through bridge inter-connections respectively.

    Equipments exposed to process fluids shall be designed conforming to

    NACE MR-01-75.

    3.2.1.7.7 PRODUCED WATER CONDITIONING SYSTEM

    Produced conditioning system is not part of the scope of present tender.

    However, for processing, the 35000 BWPD of Produced water from the new

    separator it has to be sent to PWC s -1 unit at HRC and 2 units of HRG

    platforms. The produced water outlet line from the outlet of the new separator

    on HRD platform, shall be extended and hooked up to the produced water line

    at HRC, outlet line of the PW of HP separator on HRC. The related piping,

    instrumentation modifications are also included along with in the tie ins.

    However the future space shall be provided on HRD platform for a new future

    PWC of 100, 000 BWPD Capacity, as shown in the EQ. Layout diagram as

    well as mentioned in other parts of the bid package.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 16 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    3.2.1.8 DESIGN CRITERIA UTILITIES

    3.2.1.8.1 ELECTRICAL GENERATION FACILITIES

    Main power generation unit (TG) not envisaged at HRD Process Platform .

    However, all electrical power requirements for auxiliaries as well as prime

    movers and lighting loads at HRD shall be met from the excess power available

    in the HEERA Complex which shall be brought via cables (HT and LT) via

    HRC-HRD interconnection bridge.

    An Emergency Gener a to r of 1.2 MW capacity shall be provided on HRD.

    The capacity is based on the load and governed by the electr ical

    scope of work and design cri teria.

    3.2.1.8.2 FLARE AND VENT SYSTEM

    The HEERA Process Complex has three waste gas collection systems.

    These are HP flare system, LP flare system and vent collection system.

    The HP, LP of the new HRD Process Platform shall be integrated with

    existing complex . The main header of the HP and LP flare header shall be

    extended up to the main complex via HRD-HRC bridge and shall be

    connected to the main header at an appropriate point in the upstream of the

    respective Flare KODs. The HP flare system at HRD w i l l collect high pressure flare gas which

    i s to r o u t e t o HP Flare header on HRC platform. HP flare gas header

    shall be hooked up with HP flare H e a d e r o n H R C p l a t f o r m . T h e

    H P f l a r e l i n e i s t o p a s s through HRD-HRC bridge inter-connection.

    The LP flare system collects low pressure gas which flows to LP K.O.

    Drum for separation of liquid carry over. LP flare gas h e a d e r is t o b e

    h o o k e d u p w i t h t h e L P f l a r e h e a d e r a t H R C , through HRC

    HRD bridge inter-connection.

    The vent collection system collects vent gas which is routed to the vent

    scrubber followed by a glycol seal drum before flowing into atmosphere via

    the independent vent line on the new HRD platform. The vent boom shall be

    located at a suitable position and safe location.

    Main power generation unit (TG) not envisaged at HRD Process Platform .

    An Emergency Gener a to r of 1.2 MW capacity shall be provided on HRD.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 17 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    The HP and LP flare systems are t o b e continuously purged with fuel

    gas at each dead end to assure a continuous flow through all headers.

    Further, the HP and LP flare headers to respective flare headers shall be

    provided with ultrasonic flow meters covering overall flare gas flow rates

    based on simulation and including design margins.

    The flare and vent system will be designed based on the following

    HP Flare:

    i) Header pipe dia.,inch : 20 (Min.) .

    ii) Max. back pressure, : 3.5 (NOTE-1) Kg/cm2.

    LP Flare

    i) Header pipe dia.,inch : 16 (Min.) .

    ii) Max. back pressure, : 0.2 (NOTE-1) kg/cm2g

    Vent Header

    i) Header pipe dia.,inch : 10 (Min.) .

    NOTE-1 Max. back-pressure for flare at existing HRC

    platform. However, new flare system at HRD shall be

    designed for back pressure considering its integration with

    existing flare system at HEERA complex.

    Flare system shall be designed for the following radiation level at the

    nearest process platform including HRD platform including solar radiation

    of 250 Btu/hr ft2

    Continuous (Normal ) : 400 Btu/hr ft2

    Emergency (Peak) : 1500 Btu/hr ft2

    The Flare piping network (piping including the header) on HRD shall be

    designed for new facilities only, However as the flare system shall be

    integrated with Heera complex as a whole. Thus, the changing the existing

    flare tip to the sonic tip will form the scope of present tender. The flare system

    and the Sonic flare Tip shall be designed for minimum load (purging),

    continuous load (compressor not available i.e. associated gas loads-

    Maximum up to 7.5 MMSCMD) and peak load (i.e. 5/6 nos. operating

    compressors capacity + blow down requirements).

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 18 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    3.2.1.8.3 FUELGAS SYSTEM

    The fuel gas conditioning system is designed to meet requirements of the

    following as a minimum Process gas compressor, HP and LP flare header

    purge. The fuel gas header shall be hooked up with existing fuel gas

    header at HRC platform through HRC-HRD bridge inter- connection.

    Dehydrated gas from HRC platform shall be used as source of fuel gas

    conditioning system.

    Operating pressure : 30.0 Kg/cm2g

    The Fuel gas shall be re-conditioned f o r the gas turbines of p r o c e s s gas

    compressor in accordance with the recommendations of the compressor

    manufacturer.

    FG skids for individual compressors shall be considered as a part of

    compressor modules.

    3.2.1.8.4 DIESEL FUEL SYSTEM

    The diesel fuel system is designed to meet requirements of the following as

    a minimum Pedestal cranes ; Start-up air compressor ; Fire water pump ;

    Emergency generator. The diesel fuel header shall also be hooked up with

    existing diesel fuel header at HRC platform through HRCHRD bridge

    inter- connection.

    The diesel fuel system shall consists of the following Diesel inlet filter,

    Diesel centrifuge, Diesel storage tank and Diesel transfer pumps.

    Diesel inlet filter (one no.)

    Particle removal size, : 99.99% removal of 0.8 micron and larger microns

    Pressure drop, kg/cm2g : 0.3 (dirty)

    Diesel Centrifuge (one no.)

    Water in diesel, : 50ppm by wt.

    The fuel gas conditioning system is designed to meet requirements of the

    following as a minimum Process gas compressor, HP and LP flare header

    purge.

    3.2.1.8.4 DIESEL FUEL SYSTEM

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 19 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    Diesel transfer

    pumps

    Nos. : 2 nos. (1 operating +1 standby)

    Pump Capacity : 10 M3/ hr.

    Diesel quality : Refer ANNEXURE-II

    Diesel storage shall be provided in crane pedestal. Storage volume is

    intended to meet the requirement of the following:-

    24 hours supply for running fire water pump and emergency

    generator plus 48 hours running of one deck crane.

    Additional day-tanks for diesel storage shall also be provided for fire

    water pump, emergency generator, deck cranes etc.

    3.2.1.8.5 INSTRUMENT AND UTILITY AIR SYSTEM

    The instrument and utility air system is designed to meet requirements of

    the following as a minimum Pedestal cranes ; Starting air receivers,

    Hypochlorite generator , instrument air etc.

    The instrument and utility air shall consists of 2 nos. Air compressors.

    The air stream from the compressors is scrubbed in the Utility air receiver

    and then split into two streams one, to utility air header for onward

    distribution and other, to air dryers (consisting of pre-filters, dryers and

    after filters) followed with instrument air header for onward distribution.

    The instrument and utility air system will be designed based on the

    following:

    Air compressors

    Nos.: 2 nos. (1 operating +1 standby)

    Air capacity (Dry): 700 (min.) Nm3/hr.

    Discharge pressure: 11.4 Kg/cm2g

    Type: Motor driven non-lubricating type screw

    compressor.

    INSTRUMENT AND UTILITY AIR SYSTEM

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 20 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    Instrument air dryers

    These shall consists of pre-filters, dryers and after filters.

    Nos.: 2 nos. (1 operating + 1 standby)

    Instrument air dew point: (-) 40 0C

    Operating pressure: 11.4 Kg/cm2g

    Utility air receiver

    Capacity: 30 minutes operation

    Operating Pressure: 10.0 Kg/cm2g

    Instrument air receiver

    Capacity: 30 minutes operation of all air consuming

    instruments

    Instrument air header: To supply instrument gas to all consumers

    Operating Pressure: 7.5 8.2 Kg/cm2g

    The instrument and utility air headers shall also be hooked up

    with respective headers at HRC platform through HRD-HRC bridge

    inter- connection.

    3.2.1.8.6 STARTING AIR SYSTEM

    The starting air system is designed to meet starting requirement of fire

    water pump and emergency generator. It consists of start-up air

    compressor, fire water pump starting air receiver and

    emergency generator starting air receiver.

    The starting air system will be designed based on the following:

    Start-up air compressor:

    Nos.: One no.

    Air capacity (Dry): 35 (min.) Nm3/hr.

    Discharge pressure: 17.6 Kg/cm2g

    Type: Diesel engine driven reciprocating compressor.

    STARTING AIR SYSTEM

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 21 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    3.2.1.8.7 INERT GAS SYSTEM

    The inert gas is primarily required for providing dry gas seal as well as

    use in purging and blanketing of various systems and other

    miscellaneous requirements, if any. The system shall have its own air

    compressor to meet its input air requirement.

    The inert gas system will be designed based on the following:

    Nos.: 1 no (1X100 %)

    Gas generated: Nitrogen

    Capacity per unit: 150 (min.) Nm3/hr.

    Dew point, C: (-) 40

    Discharge Pressure 4.0 - 7.0 kg/cm2g

    Discharge Temp, C: 43

    Purity, %: 99 (min.)

    Type of Adsorber : Membrane type

    The inert gas header at HRD platform shall be extended to HRC and

    HRG platform through HRC-HRD and HRC-HRG bridge inter-

    connections for meeting the inert gas requirement. Isolation valves

    along with blind flange, shall be provided at HRC and HRG platforms

    for necessary hook-ups.

    The N2 system shall also include N2 filter, N2 receiver and N2 cylinder

    cubicle separately.

    3.2.1.8.8 CHEMICAL STORAGE AND INJECTION SYSTEM

    There are three chemical systems for HRD platform. These

    systems include oil corrosion inhibitor (OCI) and gas corrosion

    inhibitor (GCI) shall be dosed at the new platform of HRD, and

    demulsifier shall be dosed at HRC platform.

    INERT GAS SYSTEM

    CHEMICAL STORAGE AND INJECTION SYSTEM

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 22 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    As a minimum chemical storage and injection facility shall consist

    the following:

    Facilities shall be suitable for chemicals available from at least two

    manufacturers for each type of chemical.

    Mixing, heating & blanketing facilities etc shall be provided as per

    chemical manufacturers specification/ Operational requirement.

    Chemicals chosen shall be compatible with each other and with well

    fluids / process stream / formation water as applicable.

    All chemicals will be stored in full strength in storage tanks based on 15

    days requirement at normal rates.

    Drums equivalent to 15 days normal consumption of each chemical

    shall be stored in the open. A suitable shelter shall be provided over the

    drum storage area as required to protect the chemicals from direct

    exposure to sun light (As per manufacturers recommendation).

    Two drum racks, each for 4 drums (min.) shall be provided for

    unloading of chemicals into respective tanks. All drum handling

    will be mechanized. Portable pneumatic pumps (one for each chemical)

    shall be provided for unloading drums into respective tanks.

    Eye wash plus safety shower shall be provided near the storage tanks

    and drum handling area (one each).

    Suitable dosing pumps - one operating and one standby as minimum

    shall be provided for each chemical. Dosing Pumps shall be sized to

    meet required dosing rates .

    Dosing rates and chemical type are tentative and shall be confirmed

    during detailed engineering as per chemical manufacturers

    recommendation. Chemical treatment package design shall take care

    of this requirement.

    CHEMICAL DOSING RATES

    Following indicative dosing rates for various chemicals are given

    below. These rates are to be confirmed during detailed engineering

    as per chemical manufacturers recommendation

    1) OCI 60 ppm at each injection point.

    2) GCI 16.7 L/ MMSCM at each injection point

    3) DEMULSIFIER 300 ppm based on maximum incoming

    fluid flow

    Eye wash plus safety shower shall be provided near the storage tanks

    and drum handling area (one each).

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 23 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    LOCATION OF CHEMICAL INJECTION

    Oil Corrosion Inhibitor

    It shall be injected in the oil header upstream and/ or downstream of the

    HP separator as is appropriate to the inhibitor system selected. Hence it

    is to be dosed on at new HRD platform

    Gas Corrosion Inhibitor

    It shall be injected upstream of the 1st, 2nd and 3rd stage coolers on

    the process gas compression system.

    Demulsifier

    It shall be injected to the production headers upstream of the respective

    well fluid heaters. Hence it is to be injected at HRC platform.

    CHEMICAL NAMES

    1) OCI Corexit 7730 or equivalent

    2). GCI Corexit 7730 or equivalent

    3) DEMULSIFIER Diatrolite DE 220 or equivalent .

    3.2.1.8.10 UTILITY WATER SYSTEM

    The utility water system is designed to meet requirements of

    hypochlorite generation, potable water, cooling water, fire water header

    (for pressurization) as a minimum. The utility water header shall also

    be hooked up with respective header at HRC platform through HRC-

    HRD bridge inter-connection.

    The utility water system will consist of 2 nos of submersible utility

    water pumps. Pump discharge pressure shall be 10.6 kg/cm2g.

    The potable water system consists of potable water tank and potable

    water pump and it shall be hooked-up with HRC platform through

    HRC-HRD bridge inter-connection. The potable water shall be

    supplied from HRC potable water header through HRC-HRD bridge

    inter-connection.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 24 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    The cooling water system consists of cooling water tank, cooling water

    circulation pumps and cooling water cooler. It shall include an on-

    line filter, chemical injection facilities for maintaining pH of the water,

    and an injection system for scale inhibitor. The cooling water header

    shall also be hooked up with respective header at HRC PLATFORM

    through HRD-HRC bridge inter-connection.

    The cooling water system will be designed based on the following:

    Cooling water circulation pumps:

    Nos.: 2 nos. (One operating + one standby)

    Pump diff. pressure: 5.0 Kg/cm2g

    Cooling water inlet supply temp. : 50.0 0C

    Cooling water outlet temp. : 60.0 0C

    3.2.1.8.11 DRAIN SYSTEM

    The drain system consists of open deck drain (ODD), open hydrocarbon

    drain (OHD) and closed hydrocarbon drain (CHD) for collection of

    hydrocarbon, chemicals and water.

    Open deck drain (ODD) is meant for collection of the following:-

    a) Storm water not in contact with hydrocarbon

    b) Deluge and fire water

    c) Utility water, potable water etc. spilled during cleaning

    and maintenance.

    Open deck drain system shall be designed for collection of rainwater

    considering heaviest monsoon rain fall and deluge. The rainfall for

    facilities design shall be taken as 100 mm rain in 2 hrs and this intensity

    to last over a period of 20 minutes. Water entering the open deck

    drain system shall be routed to sea through sump caisson.

    Open hydrocarbon drain (OHD) is meant for collection of the

    following:-

    a) Oil, oily water and chemicals from platform piping /equipment/

    storage tanks, spillage etc.

    b) Oily water from vessel cleanout and other operations and

    maintenance activities.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 25 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    c) Run-off water from process areas which may be contaminated

    accidentally with oil (e.g. water from around rotating

    equipment/skid mounted process equipment which may be

    contaminated with oil).

    Open hydrocarbon drain system shall be designed to accept minor

    volumes of hydrocarbons drained intermittently from equipment and

    instruments and chemical spillage/ leakages during handling of

    chemicals/ hydrocarbon. It is routed to sump caisson from where the oil

    is routed to closed drain drum. Recovered oil from closed drain drum is

    pumped to condensate header/ HP separator outlet and water to sump

    caisson for disposal into sea.

    Closed hydrocarbon drain (CHD) is meant for collection of

    hydrocarbon/ oily water from the pressurized vessel/ equipment/ pumps/

    compressors etc. which are required to be drained under pressure as a

    part of normal operational requirement.

    The condensate header shall also be hooked up with respective header at

    HRC platform through HRC-HRD bridge inter-connection. The drain

    system will be designed based on the following:

    Closed Drain Drum:

    The closed Drain Drum shall be utilized for receiving the all closed

    drain liquids from new HRD platform. 2 nos. of closed drain pumps

    shall also be used for transferring the crude. The required refurbishment

    shall be carried out for the existing pumps.

    The drain system will be designed based on the following Closed

    Drain Drum

    Storage Capacity : 10 M3

    (min.)

    Design pressure, : 3.5 Kg./cm2g

    Closed Drain Pumps:

    Nos. : 2 (One operating + one standby)

    Capacity, m3/hr. : 10 (min.)

    Diff. pressure, kg/cm2 : 10 (min.)

    Type : Electrical motor driven reciprocating

    Also, at HRC platform the same capacity and type of closed drain drum

    and pumps are to be provided.

    Closed Drain Drum:

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 26 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    Sump caisson with blow case

    The Sump Caisson shall be utilized for receiving all open, closed drain

    fluids separately from HRD Process Platform as well as from the

    PWCs on HRC and HRG platforms respectively. Sump caisson is to be

    provided with blow case for lifting skimmed oil to Closed Drain Drum.

    Sump Caisson shall be a vertical, partially submerged stand pipe with an

    open bottom (Min.length-30M, Min.dia.-60). Separation of oil

    from water is accomplished by differences in specific gravities. Sump

    caisson shall have gas sparger for separation of oil. Baffle arrangement

    inside the caisson enhances the separation of the entrained oil particles

    and water thus separated is discharged to the ocean. The oil collects

    inside the blow case (Min.length-3M, Min.dia.-12) is removed

    periodically by pressurizing the blow case with fuel gas to the closed

    drain drum. The caisson is vented to LP flare header.

    The oil content in sump caisson water outlet shall be less than 25 ppm.

    Sampling facility for collecting water sample from the outlet of

    sump caisson shall be provided.

    3.2.1.8.12 WASTE HEAT RECOVERY AND HOT OIL SYSTEM

    The waste heat recovery and hot oil system is designed to meet the

    heating requirements of well fluid heater (HRD), Heating of Closed

    drain drum at HRD and also the hot oil line to be extended upto HRC

    platform to meet the additional heat requirement of HRC. Waste heat

    recovery units (WHRUs) shall be installed in the exhaust of turbines of

    process gas compressors (PGC).

    The hot oil supply and return headers shall be hooked up with respective

    inlet and outlet hot oil header of new well fluid heater at HRC platform

    through HRD-HRC bridge inter-connections.

    The waste heat recovery and hot oil system shall consists of - hot oil

    expansion tank, hot oil circulation pumps, hot oil make-up pump, hot

    oil filter, gas compressors WHRU and hot oil dump cooler.

    Sump caisson is to be

    provided with blow case for lifting skimmed oil to Closed Drain Drum.

    Sump caisson with blow case

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 27 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    The waste heat recovery and hot oil system will be designed based on

    the following

    - Heating oil medium : Hytherm 500

    - Hot oil supply pressure : 5.0 kg/cm2g

    - Hot oil operating temp. : 250 oC

    Hot oil dump cooler is provided to remove excess heat to avoid damage

    to the WHRUs and to avoid degradation of the hot oil medium

    (Hytherm- 500). Its duty is based on 5% (indicative, to be confirmed

    by system vendor) of the total heat generated in the exhaust gases.

    3.2.1.8.13 FIRE WATER SYSTEM

    The fire water system is designed to primarily meet fire water

    requirement of HRD as per relevant codes and standards and

    good offshore engineering practices. However, Minimum capacity of

    1200 M3/ hr needs to be provided. Fire water deluge systems shall be

    provided on all decks and around all equipments containing

    hydrocarbons. Fire fighting equipment including hose reels, foam

    generators, fire monitors etc. shall be provided at locations determined

    by the safety studies. The fire water headers shall be hooked up with

    respective headers at HRC platform through HRC-HRD bridge inter-

    connection.

    The HRC and HRD fire water systems shall provide back-up to

    each other. In case of failure of start of FWP at HRC, HRD fire water

    pump to start automatically and also in case of HRD pump fails to start,

    HRC FWP to start automatically. Logic sequence is to be developed

    accordingly. Contractor shall ensure that the HRD fire pumps and

    ring main (including the bridge link to HRC) are capable of supplying

    the required flow rates and pressures of fire water to HRC in the event

    of failure of HRC fire water pump and ensure that there is mutual back-

    up.

    A chlorination system based on parallel plate electrolytic principle

    shall be provided to prevent fouling. Contractor shall design this

    system in a manner that ensures that contamination of the potable water

    system does not occur.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 28 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    The fire water system shall consists of fire water pump, FW pump

    caisson, deluge valves, fire water ring main, hose reels, foam

    generators, fire monitors, spray network etc.

    The fire water system will be designed based on the following:

    The fire water pump shall be capable of supplying total

    water requirements for the greatest single fire occurrence plus a

    minimum of two firewater hose reels maintained at main deck as a

    minimum.

    No.: One

    Capacity, m3/hr.: 1200 (min.)

    Discharge Pressure: Adequate to maintain fire water header

    pressure at 7 kg/cm2g

    Type: Diesel engine driven

    3.2.1.8.14 FIRE PROTECTION AND SAFETY SYSTEM

    The shutdown system for HRD shall be inter-connected with the

    corresponding HEERA complex systems.

    2 nos. of Survival Craft of 50 persons capacity shall be provided one

    at cellar deck and one at main deck.

    Clean Agent unit shall also be provided.

    The ESD and F&G systems shall be based on a high reliability, high

    availability type PLC, certified to TUV level AK6. The Contractor shall

    conduct a risk assessment of the ESD and F&T systems requirements

    prior to detailed design to assess the required Safety Integrity Level

    (SIL) in accordance with IEC-61508, and shall specify the associated

    equipment accordingly.

    For details on fire protection & safety system, refer Scope of Work

    Instrumentation.

    3.2.1.8.15 FIRE SUPPRESSION SYSTEM

    For details on fire suppression system, refer Scope of Work

    Mechanical.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 29 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    3.2.1.8.16 LAUNCHERS/ RECEIVERS

    On HRD platform, space provision shall be kept for installation of

    two nos. 12 and one no. 16 well fluid receivers.

    3.2.2 DESIGN CRITERIA FOR MODIFICATIONS ON

    EXISTING HEERA COMPLEX (HRC/ HRG/ WIH)

    For detailed scope of work for modifications envisaged on existing

    HEERA Complex (HRC/HRG/WIH platform), refer Clause - Section

    2.0 - Description of Work (Basic Bid Work).

    3.2.3 DESIGN CRITERIA FOR PRE-INSTALLED RISERS:

    Two numbers 12 and one number 16 pre-installed risers are to be

    provided with jacket. The design pressure and temperature for the same

    will be 93.7 Kg/Cm2g and 93 oC

    3.2.4 DESIGN CRITERIA FOR FUTURE EQUIPMENT:

    The Provision of space, access, process and utility tie-in locations

    for the equipment that has been identified as future requirement in

    Basic Bid work are to be provided.

    Provision for isolation valves to allow future tie-in without any

    requirement for hot work or shutdown.

    Provision for layouts and preliminary design and engineering so

    that the future equipment can be incorporated, supported and

    installed into the operating facility without the requirement for hot

    work.

    3.2.5 INSTRUMENTATION & CONTROL

    For instrumentation and control, refer Clause 2.3.6 Description of

    Work (Basic Bid work) and Section 3.6 - Instrumentation Design

    basis.

    3.2.6 SPARING PHILOSOPHY

    Sparing philosophy for unit, equipment etc. shall be as per

    bid documents. In general, all rotating equipment (pumps, compressors

    etc.) shall have one stand-by of same capacity.

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 30 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    3.2.7 UNITS OF MEASUREMENT

    Metric system of units shall be followed.

    3.2.8 NUMBERING PHILOSOPHY

    Tag numbering philosophy for equipment and instruments shall be

    adopted as per industry accepted practice, preferably 4 digits for process

    platform. Instrument and piping symbols shall be as per legend sheets.

    3.2.9 CODES AND STANDARDS

    The following are the minimum applicable Codes and Standards /

    relevant API Recommended Practices that shall be followed:-

    API 14C

    API 14E

    API 520

    API 521

    API 14G

    API 14J

    NFPA 15 & 20

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 31 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    ANNEXURE-I

    (SHT. 1 OF 2)

    WELL FLUID COMPOSITION (TYPICAL) HEERA FIELD

    COMPONENT MOL PERCENT

    (ON DRY

    BASIS)*(FOR GOR-

    275)

    N2 0.50

    CO2 0.940

    H2S 0.023

    C1 52.97

    C2 8.00

    C3 5.41

    IC4 0.99

    NC4 1.37

    IC5 0.43

    NC5 0.39

    C6 0.25

    NC7 0.05

    CUT-1 4.84

    CUT-2 6.63

    CUT-3 4.07

    CUT-4 2.39

    CUT-5 2.46

    CUT-6 2.66

    CUT-7 2.89

    CUT-8 1.16

    CUT-9 0.52

    CUT-10 0.36

    CUT-11 0.32

    CUT-12 0.39

    TOTAL 100.00

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 32 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    ANNEXURE-I

    (Sheet 2 of 2) PSEUDO-CUT DETAILS

    CUT ABP (DEG C) SP GR CUT-1 89.57 0.7219 CUT-2 110.10 0.7539 CUT-3 132.50 0.7781 CUT-4 160.80 0.8030 CUT-5 192.10 0.8254 CUT-6 228.90 0.8471 CUT-7 268.80 0.8670 CUT-8 307.70 0.8845 CUT-9 351.80 0.9030 CUT-10 402.50 0.9144 CUT-11 455.20 0.9362 CUT-12 524.00 0.9572 * THIS IS A TYPICAL WELL FLUID COMPOSITION. CONTRACTOR SHALL GENERATE

    THE COMPOSITION OF WELL FLUID FOR OTHER GORs.

    Characteristics of Crude oil of Heera Platform

    S.N. Parameter Result

    1 Density at 15C 0.8397

    2 Sp.gravity at 60/60F 0.8397

    3 API Gravity (60F) 36.93

    4 Pour Point C 33

    5 Water Content (% by vol.) -

    6 B.S.&W (% by vol.) -

    7 Kinematic Viscosity at 37.8 C

    (cst)

    4.44

    8 Asphaltene content (% w/w) 1.15

    9 Resin content (% w/w) 9.4

    10 Wax content (% w/w) 16.67

    11 KUOP 11.80

    12 Molecular weight 230

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 33 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    ANNEXURE-II

    PRODUCED WATER ANALYSIS

    Component mg/l

    Ca++ 290

    Mg++ 36

    Na+ & K+ as Na+ 9483

    Cl 14200

    SO4 230

    CO3 120

    HCO3 1281

    TDS 25640

    Salinity (as NaCl) 23400

    TSS 40

    pH 8.3

    Sp. Gr. at 30C 1.018

  • Offshore Design Section Engineering Services ISO 9001:2008

    DESIGN CRITERIA

    PROCESS AND UTILITIES

    Volume No: II

    Section No: 3.2

    HRD-Process Platform Project No:

    Page: 34 OF 34

    FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE: ODS/SOF/020B ODS/SOP/017 01 00 21.07.2010

    ANNEXURE-III

    DIESEL FUEL SPECIFICATION

    Sl.

    No.

    Property Unit Range of Value

    1 Distillation % recovery at 366

    deg C

    90 (min.)

    2 Specific Gravity @ 15/15 deg C 0.84 0.88

    (approx.)

    3 Copper strip corrosion @ 100 deg C for 3 hrs. No worse than

    No.1

    4 Kinematic viscosity cSt at 38 deg C 2 7.5

    5 Cetane Number - 41

    6 Flash Point deg C >50

    7 Sulphur Wt % 1.0 max.

    8 Water Ppmw 50 max.

    9 Sediment Wt% Nil

    10 Acidity inorganic - Nil

    11 Acidity total Mg KOH/g 0.05 0.5 max).

    12 Carbon Residue Wt % 0.2 max.

    13 Ash content Wt % 0.01 0.02 max.

    14 Lower heating value

    (approx.)

    Kcal/kg 9600 - 10000