Upload
vanduong
View
215
Download
0
Embed Size (px)
Citation preview
New Meadowlands Stadium Project Final Environmental Impact Statement
4-58
4.10 Utilities and Infrastructure
4.10.1 Existing Conditions
The Meadowlands Sports Complex contains a network of existing utilities and related
infrastructure that supports its current facilities (i.e., Giants Stadium, Continental Airlines
Arena, and Meadowlands Racetrack). These utilities and infrastructure, which include
stormwater management, sanitary sewers, potable water, electric, gas, and
telecommunication services, are part of a larger, regional network serving not only the
Sports Complex but the entire HMD and portions of Bergen and Hudson Counties.
The following sections present a discussion of the types of utilities currently serving the
Meadowlands Sports Complex, including the Project Area. The existing roadway
infrastructure serving the Project Area and surrounding area is presented in Section
4.11.
4.10.1.1 Stormwater Management
4.10.1.1.1 Stormwater Conveyance System
The Meadowlands Sports Complex, including the Project Area, is served by a
stormwater management system that collects runoff from impervious surfaces (i.e.,
parking lot areas, roadways, buildings, etc.) and conveys the stormwater through a
network of underground pipes to a series of four man-made lagoons (Figure 4-16).
These lagoons, located within the NJSEA property, are currently used to store, transfer
and release stormwater runoff into Berry’s Creek (Jack McCormick and Associates,
1978). All the lagoons are located on the West Site of the Meadowlands Sports
Complex, but are outside of the Project Area.
Lagoon 1 is located adjacent to Berry’s Creek and serves as the final stormwater
detention area prior to discharging to Berry’s Creek (Figure 4-16). Lagoon 2 is located
next to Lagoon 1 and collects runoff from the southwest portion of the West Site.
Lagoon 3 is located on the west side of NJ Route 120 near its intersection with NJ
Route 3, and stores stormwater collected from the eastern portion of the parking area
for the Giants Stadium and from the majority of the parking area and roadways on the
Continental Airlines Arena Site. Lagoon 4 is located in the middle of the Meadowlands
New Meadowlands Stadium Project Final Environmental Impact Statement
4-60
Racetrack and stores stormwater runoff from the racetrack facilities and parking areas
to the north of Giants Stadium. The drainage areas of Lagoons 2, 3 and 4 are ultimately
conveyed to Lagoon 1 by a pump system prior to discharge to Berry’s Creek.
The lagoons are hydraulically interconnected with underground pipes that serve as
equalizer lines (NJSEA, 2004). Sluice gates and pumps regulate water flow so that the
water surface in Lagoons 2 through 4 is maintained at an approximate elevation of +2
feet NGVD, with the pipe inverts ranging between elevation -9.7 and -17.7 feet NGVD.
When the water level in Lagoon 3 reaches a high level, sluice gates are raised and
stormwater flows through an existing 84-inch concrete equalizer pipe, into a junction
chamber that releases water to a pipe that drains to Lagoon 2. Lagoon 4 also ultimately
drains to Lagoon 2 through a 96-inch concrete equalizer pipe to the junction chamber,
which releases water that flows in a southwesterly direction to Lagoon 2. Excess
stormwater from Lagoon 2 is then pumped up into Lagoon 1. Lagoon 1 maintains a
water surface elevation of approximately +13.3 feet NGVD. Stormwater is discharged
from Lagoon 1 to Berry’s Creek through sluice gates; however, the discharge capacity
of the gates is ultimately limited by the capacity of the pumps in Lagoon 2, which is 650
cubic feet per second (cfs).
4.10.1.1.2 Existing Drainage Characteristics
The site’s existing topography generally slopes from the stadium area to the
surrounding lagoons. As presented in the Stormwater Management Report (Appendix
C of the PEIS), the existing site drainage is divided into five main sub-drainage areas:
Drainage Area 2 (EX-DA-2), Drainage Area 3 (EX-DA-3), Drainage Area 4 (EX-DA-4),
Drainage Area 5 (EX-DA-5), and Drainage Area 6 (EX-DA-6) (Figure 4-16). The size of the
drainage area and the impervious coverage for these five existing drainage areas is
provided in Table 4-7. Characteristics of these sub-drainage areas are provided below.
Drainage Area 2 (EX-DA-2) is a 107.93-acre drainage area located west of Giants
Stadium that consists mainly of an existing parking lot, training facilities, and a portion of
the Giants Stadium. The runoff produced from these drainage areas is collected by
existing catch basins and conveyed through a network of underground pipes to Lagoon
2.
New Meadowlands Stadium Project Final Environmental Impact Statement
4-61
Table 4-7
Existing and Proposed Drainage Area Land Coverage
Drainage Area Area
Drained
Impervious Area
CN=98 (Acres)
Roof Area
CN=98 (Acres)
Pervious Area
CN=77 (Acres)
TOTAL AREA
(Acres)
Composite Curve Number
(CN Value)
Existing Drainage Areas EX-DA-2 Project Site 89.83 0 18.10 107.93 94
Project Site 50.71 10.19 13.09 73.99 94 Xanadu 44.9 3.6 2.5 51 97
EX-DA-3
Total 95.61 13.79 15.59 124.99 - EX-DA-4 Project Site 186.53 13.99 41.78 242.30 94
EX-DA-5* Project Site 1.67 0 4.41 6.08 83
EX-DA-6* Project Site 1.36 0 2.44 3.80 85 Proposed Drainage Areas
PA-DA-2 Project Site 80.11 3.68 23.62 107.41 93 Project Site 72.55 1.76 13.65 87.96 95
Xanadu 32.3 4.7 8.5 45.5 94
PA-DA-3 Total 104.85 6.46 22.15 133.46 -
PA-DA-4 Project Site 170.19 25.46 43.08 238.73 94
* These areas drain offsite, not to the Sports Complex lagoons. (Note impervious area is defined as pavement and hardscape (excludes roofs and main stadium field.)) Source: Langan, 2006a.
Drainage Area 3 (EX-DA-3), which is separated into two sub-drainage areas, is located
south of Giants Stadium and drains to Lagoon 3 near Stadium Club Road. The first sub-
drainage area is a 73.99-acre area located on the West Site that consists mainly of an
existing parking lot and a large portion of Giants Stadium. The second sub-drainage area
is a 51-acre area located on the East Site that consists of the existing Continental Arena
and paved parking areas. Runoff from these two sub-drainage areas is collected in
existing catch basins and conveyed through a network of underground pipes to Lagoon
3.
Drainage Area 4 (EX-DA-4) is a 242.30-acre area located north of Giants Stadium that
consists of an existing parking lot and the Meadowlands Racetrack. Drainage from this
area is collected in existing catch basins and conveyed through a network of
underground pipes to Lagoon 4.
New Meadowlands Stadium Project Final Environmental Impact Statement
4-62
Drainage Area 5 (EX-DA-5) is a 6.08-acre drainage area located east of Giants Stadium
that consists of an on-site parking lot (120 South Lot). Area EX-DA-5 discharges off-site
to a radio tower site located south of the East Site via a discharge pipe under Route
120.
Drainage Area 6 (EX-DA-6) is a 3.80-acre drainage area located east of Giants Stadium
that consists of ramps from Route 120 and infield areas. EX-DA-6 currently drains off-
site to the Cedar Ditch.
4.10.1.1.3 Existing Hydrology
Peak discharges for the drainage areas included in the Stormwater Management Report
were calculated using the SCS Method and a Type III 24-hour storm distribution for
select storm events (2-, 10-, 25-, and 100-year storm events) (Langan, 2006a) (Table 4-
8).
As discussed above, the lagoon system includes a pump system to regulate the water
levels of the lagoons and discharge of stormwater to Berry’s Creek. The pump station is
located between Lagoons 1 and 2 and is operated manually on an event-by-event basis.
Depending on the intensity of the anticipated storm, Lagoons 2, 3, and 4 are pumped
down to a level to provide storage capacity for new rain events (Langan, 2006a).
New Meadowlands Stadium Project Final Environmental Impact Statement
4-63
Table 4-8
Existing Drainage Area Peak Flows
Drainage Area Area (Ac)
CN
2-year, 24-hr
Storm Event (cfs)
10-year, 24-hr
Storm Event (cfs)
25-year, 24-hr
Storm Event (cfs)
100-year, 24-hr
Storm Event (cfs)
EX-DA-2 (To Lagoon 2)
107.93 94 199.02 323.47 405.53 548.06
EX-DA-3 (To Lagoon 3)*
124.99 94 268.81 430.36 537.11 722.84
EX-DA-4 (To Lagoon 4)
242.30 94 506.50 822.53 1030.89 1392.82
Total Area to Lagoons
475.22 - - - - -
EX-DA-5 (To Radio Tower Site) 6.08 83 10.01 19.33 25.68 36.82
EX-DA-6 (To Cedar Ditch)
3.8 85 6.84 12.74 16.72 23.67
Total Area to Offsite
9.88 -- -- -- -- --
Total 485.10 - 976.89 1584.56 1986.16 2684.10 Note: Total peak flows are taken from the sum of the hydrographs provided in the Stormwater Management Report (Appendix C of the PEIS). * Includes Xanadu flows Source: Langan, 2006a.
4.10.1.2 Sanitary Sewer Service
The Project Area is located within the area served by the Bergen County Utilities
Authority (BCUA) Little Ferry wastewater treatment facility (Figure 4-17) (NJMC, 2004).
BCUA provides sewage disposal for 46 of the 70 municipalities in Bergen County,
including East Rutherford where the Sports Complex is situated. The Little Ferry facility
operates under NJPDES Permit Number NJ0020028, with a permitted design flow of 94
million gallons per day (mgd) and has a peak month design capacity of 109 mgd (BCUA,
2005). The average daily flow for calendar year 2002 was 69.39 mgd (BCUA, 2003); for
2003 it was 85.19 mgd (NJSEA, 2004); for 2004 it was 81.58 mgd; and for 2005 was
85.87 mgd (BCUA, 2005).
New Meadowlands Stadium Project Final Environmental Impact Statement
4-65
The Little Ferry facility provides advanced secondary treatment of sanitary wastewater
and discharges the treated effluent to the Hackensack River. Of the flow processed
during 2005, an average of 1.418 mgd of treated effluent was supplied to Public Service
Electric & Gas Company (PSE&G) for use as cooling tower make-up water at its power
generating facilities located across the Hackensack River in Ridgefield, New Jersey from
Little Ferry (BCUA, 2005).
The NJSEA owns and operates the existing sanitary system for the Meadowlands
Sports Complex property. A 24-inch gravity sanitary sewer currently serves the existing
stadium. This 24-inch line increases in diameter to a 30-inch gravity line as it is joined by
the 10-inch line running from the area near Lagoon 2. The 30-inch line increases in
diameter again to a 36-inch trunk line as it continues north toward a pump station
located north of the Meadowlands Racetrack. The trunk-line discharges into a pump
station, located on the NJSEA property that is owned and maintained by the East
Rutherford Public Works Utility Commission (ERPWUC). Sanitary flows for the existing
stadium and training facility are presented in Table 4-9.
The ERPWUC pump station, located to the north of the Meadowlands Racetrack and
outside the Project Area, receives sewage from the 36-inch line and discharges it into a
sewer system that is owned and maintained by the ERPWUC. The sewage ultimately
discharges to the BCUA Little Ferry wastewater treatment plant through the East
Rutherford Extension and Southwest Trunk Services sewer lines. The ERPWUC pump
station includes three pumps installed in two wet wells. Two vertical pumps are
installed in one of the wet wells. The second wet well contains one submersible pump.
Each of the three pumps has a capacity of 5,500 gallons per minute (gpm). The pump
station has an overall capacity of approximately 10 mgd, however the three existing
pumps are capable of handling approximately 23 mgd (16,500 gpm). Existing flow data
from December 2002 to October 2004 provided by East Rutherford Public Works
documents an existing average daily flow to the pump station of approximately 0.6 mgd
with a peak flow of approximately 1.7 mgd.
4.10.1.3 Potable Water Service
The Project Area is located within the Hackensack River Basin as defined in the New
Jersey Water Supply Master Plan (CH2M, 1993). The Hackensack River Basin
comprises 131 square miles in Bergen County and 33 square miles in Hudson County.
4-66
Table 4-9
Existing and Proposed Sanitary Design Flows by Facility and Event
FACILITY EVENT
Use Sunday Game Day Flow (82,000
Person Event) (gpd)
Sunday No Game Day
Flow (gpd)
Weekday Game Flow (82,000
Person Event) (gpd)
Weekday Flow 20,000 Person
Event (gpd)
Weekday Flow 50,000 Person
Event (gpd)
Weekday Flow No Event
(gpd)
Saturday Flow 20,000 Person
Event (gpd)
Saturday Flow 50,000 Person
Event (gpd)
Existing Stadium
Stadium
Full Occupancy 240,726 1,350 242,076 61,350 151,350 N/A 61,350 151,350
Partial Occupancy N/A N/A N/A N/A N/A 1,350 N/A N/A
Training Facility 0 0 6,438 6,438 6,438 6,438 6,438 6,438
Proposed Stadium
Full Occupancy 161,473 N/A 164,357 41,884 100,034 N/A 39,000 97,150
Partial Occupancy N/A 22,349 N/A N/A N/A 16,175 N/A N/A
Tailgate Zones 1,000 0 1,000 0 1,000 0 0 1,000
Giants Training Facility
Practice 0 0 11,819 11,819 11,819 11,819 11,819 11,819
Future Expansion/Sponsor 14,361 0 14,361 14,361 14,361 14,361 14,361 14,361
Proposed Ancillary Development
Full Occupancy N/A N/A 223,422 223,422 223,422 223,422 223,422 223,422
Sunday Occupancy 175,297 175,297 N/A N/A N/A N/A N/A N/A
SUMMARY
Existing Stadium and Training 240,726 1,350 248,514 67,788 157,788 7,788 67,788 157,788
Proposed Stadium and Training 176,834 22,349 191,538 68,065 127,215 42,355 65,180 124,330
Proposed Ancillary Development 175,297 175,297 223,422 223,422 223,422 223,422 223,422 223,422
Total Proposed Sanitary 352,131 197,646 414,960 291,487 350,637 265,777 288,602 347,752
Net Additional Flow (Proposed -Existing)
111,405 196,296 166,446 223,699 192,849 257,989 220,814 189,964
General Notes:
A. Unit flow based on criteria from the New Jersey Administrative Code (N.J.A.C.) 7:14A-23. B. Stadium flow includes a 35% reduction in peak flow for waterless urinals. Source: Langan, 2006f.
New Meadowlands Stadium Project Final Environmental Impact Statement
4-67
The population within the Hackensack River Basin was approximately one million in
1980, decreased to approximately 0.98 million in 1990, and is anticipated to continue to
be just under one million through the year 2040. During 1990, the average per capita
water use rate in the Hackensack River Basin was 130 gallons per day (gpd). By 2040,
this rate is expected to increase to 142 gpd. This projection is due to anticipated
increased usage by industrial, commercial, and residential water consumers. The future
water supply demand is expected to be met with additional potable water supplied from
the adjacent Lower Passaic River and Saddle River Watersheds.
The water purveyor in the vicinity of the Project Area is United Water New Jersey, Inc.
(UWNJ), known as the Hackensack Water Company prior to 1995 (UWNJ, 2006).
During 2004, UWNJ delivered a total of 39.4 billion gallons of water to 750,000
residents of Bergen and Hudson counties. The average and peak daily demands for
Bergen and Hudson counties during 2004 were 108 million gallons. Most water
supplied by UWNJ for use by consumers in Bergen County is pumped from one of four
reservoirs: the Oradell, Woodcliff Lake, and Lake Tappan Reservoirs in New Jersey, and
the Lake DeForest Reservoir in New York. The potable water serving the Project Area
is supplied from the Haworth Water treatment plant located next to the Oradell
Reservoir (NJSEA, 2004). This treatment plant has a capacity of 200 mgd.
Existing potable water infrastructure within and adjacent to the Project Area includes a
system of water mains and several metering stations. The Project Area is serviced by
two water mains. The first main enters the site from the north at Paterson Plank Road
and is 16 inches in diameter. The second main enters the site from the west at New
Jersey State Route 120 and is 14 inches in diameter. Both mains connect to a water
main loop, located inside of the NJSEA property, that serves the existing stadium.
Approximately 8 fire hydrants and several on-site meter pits are located within the
Project Area. The NJSEA property is serviced by 17 United Water water meters. Water
bills provided by NJSEA for year 2005 for the existing stadium and training facility
(NJSEA meter numbers 4, 5 and 10) indicate a daily average usage of approximately
145,000 gpd during the football season, and 113,000 gpd on an annual basis. UWNJ is
currently reviewing the proposed water demands to confirm the proposed demands and
confirm that adequate capacity exists to support the Project. Peak game day flow rate
data will be coordinated with UWNJ and reviewed by the NJDEP as part of the Water
Main Extension Certification review process (see Section 6.2.8).
Flow tests conducted between 1980 and 2000 at various locations along the water
mains beneath and adjacent to Paterson Plank Road indicated the static pressure to be
New Meadowlands Stadium Project Final Environmental Impact Statement
4-68
between 103 and 108 pounds per square inch (psi) (NJSEA, 2004). A flow test
conducted in 2000 on a 12-inch line located at Outwater Place immediately northeast of
the Project Area indicated a static pressure of 108 psi. Flow tests for the Stadium
Project will be performed to confirm this previously documented water pressure.
4.10.1.4 Natural Gas Service
The natural gas purveyor in the vicinity of the Project Area is PSE&G. PSE&G is a
subsidiary company of Public Service Enterprise Group (PSEG). PSE&G supplies natural
gas to approximately 1.6 million consumers of natural gas within its 2,600-square-mile
service area (PSE&G, 2006).
A network of gas mains is present in the vicinity of the Project Area. A 24-inch and a
36-inch gas main are located beneath and adjacent to Paterson Plank Road. An 8-inch
gas main is located beneath the N.J. Route 120 right-of-way. The stadium is served by
a gas line that extends from the gas main located beneath Paterson Plank Road.
4.10.1.5 Electric Service
The company that supplies electricity in the vicinity of the Project Area is PSE&G.
PSE&G supplies electricity to approximately 2.1 million consumers within its 2,600-
square-mile service area (PSE&G, 2006). Electric lines in the vicinity of the Project Area
include both overhead and underground lines. Overhead electric lines are present along
NJ Route 120. Underground electric lines are present within the Project Area and serve
the buildings and various parking lot features (e.g., toll booths/kiosks, overhead lights)
that surround it. In addition to the electric lines, several transformer banks are located
within the Project Area. The Meadowlands Complex is serviced by four main
transformers (each at 10 megavolts (MVA)) within the NJSEA switchyard area. Power to
the transformers is supplied by PSE&G. The demand for the Meadowlands Sports
Complex, excluding Xanadu, is 20 MVA. The current game-day demand for the existing
stadium is approximately 9.5 MVA.
4.10.1.6 Telecommunication Service
Telephone service in the vicinity of the Project Area is provided by Verizon
Communications, Inc. Telephone lines in the vicinity of the Project Area include both
overhead and underground lines. Overhead telephone lines are present along NJ Route
New Meadowlands Stadium Project Final Environmental Impact Statement
4-69
120. Underground telephone lines serve the existing stadium and toll booths/ kiosks
throughout the existing parking lot areas.
4.10.2 Impacts and Mitigation
4.10.2.1 Stormwater Management
4.10.2.1.1 Stormwater Conveyance System
No changes are proposed to any of the existing lagoons from the construction of the
Stadium Project. Portions of the underground pipe network that conveys stormwater to
the lagoons will be modified as part of the Stadium Project (Figures 4-18 and 4-19). New
storm drain lines, including manholes and catch basins, will connect with parking lot
catch basins, hardscape area drains and roof drains. Storm drain sizes are proposed to
range from 15 to 54 inches in diameter.
Since many of the existing pipes will remain and the lagoons provide significant
tailwater depths at the outfalls, the stormwater collection system will continue to
operate under a “surcharged” condition, which is consistent with the existing system
(Langan, 2006a). All stormwater from the Stadium Project will continue to leave the
Project Area through discharge from Lagoon 1 into Berry’s Creek per the NJPDES
requirements.
The football fields of the new Stadium and Giants Training Facility will include
underdrainage systems composed of perforated pipes and crushed clean stone. The
new Stadium and lower seating bowl drainage systems will discharge into a pump
station that will accommodate 22,000 gpm, the equivalent of the 100-year storm event.
The pump station will discharge to the on-site stormwater conveyance system and
ultimately to Lagoon 4, consistent with the existing drainage pattern.
As required by the Stormwater Management Rules at N.J.A.C. 7:8-5.2(b), a Stormwater
Maintenance Plan has been prepared for the Stadium Project and was included as part
of the Stream Encroachment Permit Application submitted to the NJDEP (see Section
6.2.3). The Stormwater Maintenance Plan was prepared to ensure that the stormwater
management system used for the Stadium Project will operate efficiently and reliably.
The Plan identifies a responsible party to ensure the long-term/perpetual operation,
maintenance, repair and safety of the stormwater management facilities that will serve
the Stadium Project.
New Meadowlands Stadium Project Final Environmental Impact Statement
4-72
4.10.2.1.2 Proposed Drainage Characteristics
The proposed drainage areas consist of three proposed sub-drainage areas: Proposed
Drainage Area 2 (PR-DA-2), Proposed Drainage Area 3 (PR-DA-3), and Proposed
Drainage Area 4 (PR-DA-4) (Figure 4-20) (Langan, 2006a). PR-DA-2 and PR-DA-4 are
nearly identical to the existing drainage areas EX-DA-2 and EX-DA-4, respectively. PR-
DA-3 is a compilation of the three existing drainage areas EX-DA-3, EX-DA-5 and EX-DA-
6. By including the existing drainage areas EX-DA-5 and EX-DA6 (which both flow off-
site under the existing condition) into PR-DA-3 (which discharges to Lagoon 3), two
uncontrolled off-site discharges are eliminated. The inclusion of EX-DA-5 into the lagoon
system is proposed as part of the Stadium Project, and the inclusion of EX-DA-6 into the
lagoon system is part of the NJ Transit project. A summary of the drainage areas is
presented below, listed in Table 4-7, and depicted on Figure 4-20.
PR-DA-2 is a 107.41-acre drainage area that consists of parking areas and the Giants
Training Facility. Area PR-DA-2 drains directly to Lagoon 2.
PR-DA-3 is a 133.46-acre drainage area that is separated into two sub-areas. The first
sub-drainage area is an 87.96-acre area within the Project Area that consists of parking
areas and the future Ancillary Development. The second sub-drainage area is a 45.5-
acre area located on the East Site that consists of the Continental Airlines Arena, several
proposed buildings, roadway areas and parking areas. Both sub-drainage areas drain to
Lagoon 3.
PR-DA-4 is a 238.73-acre drainage area that consists of parking areas, the new Stadium,
and the Meadowlands Racetrack. Area PR-DA-4 drains to Lagoon 4.
The net increase in area draining to the lagoon system under proposed conditions will
be approximately 4.4 acres compared to existing conditions (existing 475.2 acres,
proposed 479.6 acres) (see Table 4-8 and Figure 4-20). To eliminate the two
uncontrolled off-site discharges (EX-DA-5 and EX-DA-6) a 2-percent increase in
stormwater runoff is proposed into the current lagoon system (Table 4-7). The existing
Lagoon system has the capacity to handle this minor increase in flows because water
levels in the lagoons are regulated by equalizer pipes and the ultimate discharge from
Lagoon 1 into Berry’s Creek will remain consistent with the current conditions.
New Meadowlands Stadium Project Final Environmental Impact Statement
4-74
The redevelopment activities within the Project Area will result in a minor decrease of
impervious coverage, resulting in a minor reduction in stormwater runoff (Table 4-7).
Approximately 7 acres of existing pavement will be converted to roof and/or structural
slab with artificial turf.
4.10.2.1.3 Proposed Hydrology
Peak flows for the three proposed drainage areas were calculated for select storm
events (2-, 10-, 25-, and 100-year storms) (Table 4-10). Comparing these proposed peak
flows with the existing flows (Table 4-8) shows that the Stadium Project will result in a
minor net reduction of stormwater runoff from the site. The calculations of the
proposed flows will be presented to the NJDEP as part of an overall Stream
Encroachment Permit Application to the NJDEP Land Use Regulation Program.
Table 4-10
Proposed Drainage Area Peak Flows
Drainage Area Area (Ac)
CN 2-year,
24-hr Storm Event (cfs)
10-year, 24-hr Storm Event (cfs)
25-year, 24-hr Storm Event (cfs)
100-year, 24-hr Storm Event (cfs)
PR-DA-2 (To Lagoon 2)
107.41 93 192.42 317.00 399.13 541.64
PR-DA-3 (To Lagoon 3)
133.46 95 312.76 504.23 630.55 850.16
PR-DA-4 (To Lagoon 4)
238.73 94 499.03 810.40 1015.70 1372.29
Total Area to Lagoons
479.60 -- -- -- -- --
Total Area to Offsite
0.00 -- -- -- -- --
Total* 479.60 -- 971.58 1578.95 1979.50 2675.30 *Existing Drainage Areas 5 and 6 (EX-DA-5 and EX-DA-6) are being directed to Lagoon 3 for the proposed condition. Proposed discharges for these areas (Transit lot and lot 120 South) are included in Proposed Discharge Area 3 (PR-DA-3). PRDA-3 also includes flows from the East Site. Source: Langan, 2006a.
4.10.2.2 Sanitary Sewer Service
The Stadium Project will require certain improvements to the existing sanitary sewer
collection system on the West Site to accommodate the new Stadium, Giants Training
Facility, and Ancillary Development. Approximately 1,800 linear feet of existing sanitary
sewer line from within the proposed Stadium footprint will be relocated to the northern
New Meadowlands Stadium Project Final Environmental Impact Statement
4-75
and eastern sides of the new Stadium. This relocated pipe will continue to service the
current facilities on the West Site (NM Stadco, 2006).
In addition to the modification of existing sewer lines, new lateral lines are proposed to
connect the new Stadium and Ancillary Development to the existing collection system
(Figure 4-21). The new Giants Training Facility will have new sewer laterals that will
discharge into a new on-site pump station. This pump station will discharge to a new
force main that will be connected to an existing onsite trunk main. New laterals will
also be run to future tailgate zones.
The potential replacement or restoration of approximately 3,000 linear feet of an existing
36-inch sanitary sewer line may be necessary. The condition of the piping will be
ascertained with video surveillance of the pipe. The results of this investigation will be
used to determine if replacement or restoration if required. There are no upgrades to
the existing ERPWUC pump station proposed or anticipated as part of the proposed
Project activities because adequate excess pump station capacity exists based on the
flow data provided by ERPWUC, as noted in Section 4.10.1.2.
All proposed sewer systems will be designed in accordance with the NJDEP Pollutant
Discharge Elimination System Act Subchapter 23: Technical Requirements for
Treatment Works Approval Applications. Sewer flows have been estimated based on
the existing pipe capacity plus the sewage generation projections from future
development using the categories outlined in Section 7:14A-23.3 of Subchapter 23
(Table 4-9).
The uses will produce different flows during different events. The flows were calculated
under several scenarios including Sunday game day, Sunday without a game, a
weekday game, weekday events and Saturday events (Langan, 2006f) (Table 4-9). For a
weekday game event, the existing stadium and training facility produce a maximum
flow of 248,514 gpd. The Stadium Project will increase this existing flow by 166,446
gpd during the peak flow period, for a total Project design flow of 414,960 gpd. The net
increase in flow is due to the proposed Ancillary Development, which could include
shops, sports medicine, sponsorship, restaurants and other uses that support the
Stadium. When a 35-percent reduction in stadium flows is considered for waterless
urinals, the proposed Stadium and Giants Training Facility will actually generate less
flow than the existing stadium and training facility during peak periods (Table 4-9). The
sanitary loads from the Stadium Project are predicted to remain below the maximum
capacity of the ERPWUC pump station, owned by East Rutherford Township.
New Meadowlands Stadium Project Final Environmental Impact Statement
4-77
As discussed in Section 6.2.6, Treatment Work Approval applications will be submitted
to the NJDEP for both the required sewer line relocation and the new sanitary sewer
collection lines proposed for the Stadium Project
4.10.2.3 Potable Water Service
New water lines will be required to service the proposed Stadium, Giants Training
Facility, associated offices, and future Ancillary Development and tailgate zones (NM
Stadco, 2006) (Figures 4-18 and 4-19). The sizes of the water lines are expected to
range from 12 to 16 inches. The proposed system will connect to the existing water
mains near the proposed NJ Transit Rail Facility and existing Meadowlands Racetrack
parking lot. These proposed water mains will provide domestic water and fire needs for
the Stadium, Giants Training Facility and future Ancillary Development and tailgate
zones. The peak flow for domestic water usage has been estimated to be 2,900 gpm
for the Stadium Project (NM Stadco, 2006).
As described in Section 6.0, a Water Main Extension Certification application will be
submitted to NJDEP for improvements, modifications and/or additions to the existing
potable water infrastructure for the Stadium Project. During the construction process,
temporary relocation of approximately 1,400 linear feet of existing water line will be
necessary to service the existing stadium. UWNJ is currently reviewing the proposed
water demands to confirm the proposed demands and confirm that adequate capacity
exists to support the Stadium Project.
4.10.2.4 Natural Gas Service
A new natural gas main will be installed to serve the proposed Stadium, Giants Training
Facility and future Ancillary Development and tailgate zones (NM Stadco, 2006) (Figures
4-18 and 4-19). The gas service to the new Stadium will terminate at a pressure
regulation/metering station to be located on the north side of the Stadium. Separate
meter and pressure regulator assemblies will be provided at each building.
The gas main will be sized to serve a connected load of approximately 105,320 cubic
feet/hour for the Stadium, 35,500 cubic feet/hour to serve the Ancillary Development,
15,950 cubic feet/hour for the Giants Training Facility and 1,160 cubic feet/hour for the
tailgate zones. These load totals are estimated based on existing NFL stadiums, known
connected loads for heating equipment and estimated loads for cooking and laundry
New Meadowlands Stadium Project Final Environmental Impact Statement
4-78
equipment. All proposed gas lines will be installed along the proposed loop road and
southwest entry drive.
4.10.2.5 Electrical Service
The NJSEA will provide electrical services to the proposed Stadium, Giants Training
Facility and future Ancillary Development and tailgate zones (NM Stadco, 2006). The
service will extend from the NJSEA 15kV service switchgear, through a system of
proposed underground duct bank and manholes throughout the Project Area. All service
will come directly from the NJSEA service switchgear. The operating conditions of the
existing NJSEA switchgear have been assessed by NJSEA’s consultant electrical
engineer. NJSEA and their consultant have verified that the existing switchyard can
provide the anticipated electrical demands for all components of the Stadium Project.
Close coordination will be required between all on-site parties during the conversion
from the old service feeds to the new services feeds.
To supply service to the replacement Stadium, a dedicated dual 13,800 volt service will
be delivered to the switchgear located in the main electric room. The electric lines will
be encased in eight 5-inch PVC conduits of the proposed duct bank system. Half of the
eight conduits entering the electric room will be active, the remaining half will be spare
conduits. To service the Ancillary Development, four 5-inch PVC conduits, two active
and two spare, will be provided from the proposed duct bank system. For the Giants
Training Facility, two 5-inch PVC conduits, one of which will be utilized as a spare
conduit, will provide the service to this facility.
Power and lighting for the overall Project Area will continue to use existing power lines,
which will be connected to the proposed duct bank systems in manholes. Additional
lighting and power distribution will be extended from the two existing Project Area
lighting and power feeders. These feeders will be relocated to the new duct bank
system as part of the proposed activities. Four 5-inch PVC conduits, two active and two
spare, will be utilized for the Project Area lighting.
Electrical distribution of lighting service for the Project Area will be accomplished
through strategically located pad mounted liquid filled 13,800 volt to 480/277 volt
transformers to provide electric service for parking lot lighting, pedestrian walkways,
future tailgate zone buildings and marquee signage. Control of the Project Area lighting
and marquee signage will be from the new Stadium command center and will be
coordinated with NJSEA.
New Meadowlands Stadium Project Final Environmental Impact Statement
4-79
During the construction phase of the Stadium Project, all currently operating stadium
power feeders will temporarily occupy future spare ducts in the new duct bank system
and will be removed upon demolition of the existing stadium.
The estimated demand for electricity by new Stadium was determined based on
historical data of recently built stadiums and the existing stadium, with adjustment
factors for the planned type of mechanical systems installed and an adjustment for the
breakdown of their spaces as compared to the new Stadium. The anticipated demand
for electrical service by the Stadium is 11.53 MVA. The total estimated peak demand for
the new Stadium, Giants Training Facility and Ancillary Development is 20.36 MVA.
For the other portions of the Project Area, lighting and power anticipated peak
coincidental demand is estimated at 4.08 MVA. This estimate accounts for power needs
of the new lighting for the reconfigured parking and pedestrian walkways. Service for
these demands will be provided by the NJSEA switchgear as previously noted.
4.10.2.6 Telecommunication Service
New telecommunications services for the proposed Stadium, Giants Training Facility
and future Ancillary Development and tailgate zones will be served by main and/or a
redundant underground telecommunication duct bank. The telecommunication service,
provided by Verizon, will be brought into the Project Area through a main connection
located at the northeast corner of the NJSEA property adjacent to Route 120 (Figures 4-
18 and 4-19).
Proposed conduit requirements for the main service at the Stadium include ten 5-inch
PVC conduits containing both fiber-optic and copper cables to support the information
transport system (NM Stadco, 2006). Secondary service will also provide ten 5-inch PVC
conduits of the same materials to support the information transport system. The main
and secondary service lines will be independently routed via underground duct banks
from the connection point at the NJSEA property line to the main telecommunications
conference room in the Stadium.
Proposed conduit requirements for the Ancillary Development include six 5-inch PVC
conduits, without redundant services, that will be routed through underground duct
banks to one of the utility connections points located at the NJSEA property line. From
the NJSEA property line, the service will be routed through the Project Area and the
Ancillary Development.
New Meadowlands Stadium Project Final Environmental Impact Statement
4-80
For the Giants Training Facility, main and secondary services will each use three 5-inch
conduits, containing fiber-optic and copper cables, to provide information transport
systems. Each service will be independently routed underground through a duct bank
from the connection point at the NJSEA property line to the main telecommunications
room in the Giants Training Facility.
All conduit systems will be provided in a reinforced duct bank. Proposed manholes and
duct bank systems are planned to run under roadways and parking lots, located on
approximately 300 foot centers.
In order to maintain the existing primary power for telecommunication and electrical
services to the existing stadium and the Meadowlands Sports Complex during the
construction of the new Stadium, additional segment duct banks with new service
cabling and manholes will be installed around the northern perimeter of the proposed
Stadium’s footprint. Temporary construction power will be derived from the existing
primary feeders by installing transformers located around the proposed Stadium
construction pad. These temporary transformers will be removed once the construction
of the new Stadium is substantially complete. A majority of the construction power will
be utilized during non-coincidental peak loads at the existing stadium.