Upload
wan-safwan
View
150
Download
3
Tags:
Embed Size (px)
Citation preview
Prepared by Associate Professor Sallehuddin Muhamad UTM City Campus
MAINTENANCE PLANNING AND SCHEDULE
1. Aircraft Reliability
Aircraft operators face with situation that demands priority of safety and the pressure of economy.
These demands lead to a very reliable aircraft. Aircraft reliability or sometime refers as schedule
reliability is defined as:
Other word, Rair is the probability of starting and completing a scheduled flight without interruption.
An aircraft with Rair = 1 has the ideal reliability.
Example:
An aircraft is fitted with two same components. After 100,000-flight hour and 80,000 departures:
Activity Times
Total removal 100
Unscheduled removal (failed or suspected) 80
Failures 50
Inoperative and caused system failure 26
Caused schedule interruption 4
Unjustified removal = Unscheduled removal – failures
= 80 – 50 = 30
The parts Mean Time Between Failures, MTBF
Mean Time Between Unscheduled removal, MTBUR
Rair = 1 - Schedule interruptions (delay/cancellation)
Total departure
MTBF = (no of part) (flight hour)
failures
= (2) (100,000)
50
= 4,000 flight hour
MTBUR = (no of part) (flight hour)
Unscheduled removal
= (2) (100,000)
80
= 2,500 flight hour
Prepared by Associate Professor Sallehuddin Muhamad UTM City Campus
Therefore;
Ideally, maintenance efficiency of 100% is what the operator aimed for.
2. Maintenance Concepts
There are four maintenance concepts that are used in maintaining aircraft. They are:
a) Fixed When It Breaks
b) Hard Time
c) On Condition
d) Condition Monitoring
Usage of these concepts varies with its importance to flight safety. The concepts (b) and (c) are
useful in maintenance schedule.
a) Fix When It Breaks
Using this concept aircraft parts are fixed or replaced when they failed. Unless their failure
periods are known, aircraft operators have to make unscheduled removal and this can reduce
aircraft reliability. Therefore, this concept can only be applied to unessential parts for flight
operation and safety such as cabin lighting, cabin seats, and toilet.
b) Hard Time
This concept is defined as a preventive process in which known deterioration of an item is
limited to an acceptable level. Maintenance actions are carried out at a period related to time in
the service scheduled maintenance control specified by:
i) calendar time
ii) number of cycles (takeoffs and landings)
iii) flight hours
The prescribed actions normally include servicing, fully or partial overhaul, replacement
according to instruction relevant documentation so that the part is restored to suitable condition
for further use for a specified period.
Maintenance efficiency = MTBUR
MTBF
= 2,500
4,000
= 63%
Prepared by Associate Professor Sallehuddin Muhamad UTM City Campus
Performance
Replace parts
limit
tlife month, flight hr, or cycles
Although this concept is convenient for scheduling, it is expensive and can be used on familiar
items. It however reduces schedule interruption and thus increase aircraft reliability.
c) On Condition
It is also a preventive process. However, item is inspected or tested at specific periods against
standards to determine whether it can continue in service. Thus, it requires collection of data at
regular intervals. These data are analyzed and evaluated to ascertain airworthiness.
Performance
Replace parts
limit
month, flight hr, or cycles
periodic inspections
This maintenance concept can extend the life of aircraft parts, thus reduces maintenance cost.
However, it cost saving benefit may be overwhelmed by additional man-hour requirement to
perform periodic inspections. It also causes schedule interruption due to part replacement.
Therefore, this concept is used on parts that are easy to replace such as aircraft tires or parts
with redundancy.
d) Condition Monitoring/Health Monitoring
It is not a preventive process, which causes unscheduled removals. It is a process in which
information on aircraft parts gained from operational experience is collected, analyzed, and
interpreted on a continuous basis as a mean of implementing corrective procedures.
Instruments are placed to monitor part performance.
Prepared by Associate Professor Sallehuddin Muhamad UTM City Campus
Performance
Replace parts
limit
continuous inspections month, flight hr, or cycles
Since it causes unscheduled interruption, it reduces aircraft reliability. It also requires regular
inspection and thus expensive to apply. Usually, condition monitoring is used for new part that
its hard time is not known yet.
3. Maintenance Program
The Maintenance Program development methods have been revised through out the years in an
effort to achieve higher levels of safety and cost-effectiveness. The initial philosophy of
maintenance program was "to overhaul everything at a specific time" which was based on concept
that primary failure mode was wear out. Since then, several philosophies have materialized and
each superseding or evolving from its predecessors.
Historical Background
i. In 1961 the Federal Aviation Authority (FAA)/Industry Reliability Program was developed
aimed solely at the propulsion system reliability.
ii. In 1968, the aviation industries and FAA developed Maintenance Steering Group Revision 1
(MSG-1) Handbook, Maintenance Evaluation and Program Development, based on new
analytic approach to maintenance of wide-body aircraft. The handbook was used developed
the B747 schedule maintenance program.
iii. In 1970, MSG-2: Airline/Manufacturer Maintenance Planning Document was developed based
on experiences gained with MSG-1. Amendments were made to exclude any specific B747
information to arrive at a universal document that could be used on subsequent new aircraft.
Through this maintenance program, the concept of Hard Time, On Condition, and Condition
Monitoring were introduced.
iv. In 1972, The Association of European Airlines developed EMSG-1 (European Maintenance
System Guide) to overcome deficiencies in MSG-2. It was used to develop British Airline (BA)/
Aerospatiale Concorde and A300. An improved version EMSG-2 was introduced later.
Prepared by Associate Professor Sallehuddin Muhamad UTM City Campus
v. In 1978, the concept of Reliability-Centered Maintenance (RCM) was published by United
Airlines under contract with the US Department of Defense. This concept contained many new
ideas notably maintenance process on hidden functions and generally provide through logic
analysis of maintenance program development process.
vi. With new regulation such as the structural damage tolerance rules (FAR 25.571) and new
development and ideas in maintenance program, aviation industry felt that MSG-3 must be
evolved. A task force was formed by Air Transport Association (ATA) in 1979 to produce
MSG-3. In 1980, MSG-3 produced Airline/Manufacturer Maintenance Program Development
Document and this document was used on new aircraft such as B767, A310, and F50.
The objectives of an optimal scheduled maintenance program are:
i. To ensure that equipment is maintained to the designed level of safety for aircraft safety.
ii. To ensure the equipment is maintained to the inherent level of reliability for aircraft operating
efficiency.
iii. To restore any deterioration of inherent levels of safety and reliability of equipment.
iv. To prevent or minimize on-aircraft failures especially those resulting in delays, cancellation of
services or loss of passenger good will.
v. To identify deficiencies in the inherent levels of safety and reliability of equipment and to seek
and initiate product improvement through modification or redesign.
vi. To accomplish the above objectives at minimal total costs, inclusive of maintenance costs and
the subsequent costs of residual failures.
There are two types of maintenance tasks contained within a maintenance program. They are:
a) Scheduled maintenance tasks
The tasks are performed at specified intervals. Its objectives are to prevent deterioration of the
inherent levels of safety and reliability. Tasks in the scheduled maintenance are:
- Lubrication / servicing - Restoration
- Operating crew monitoring - Discard
- Operational check - Inspection / functional checks
- Combination of above work
Prepared by Associate Professor Sallehuddin Muhamad UTM City Campus
b) Unscheduled maintenance task
The tasks arise on ad-hoc basis because of the following:
- Report of malfunction by operating crew or others (PIREP)
- Data analysis findings
- Scheduled task
- Accidental damage
The objective of these tasks is to restore the equipment to an acceptable standard.
4. AirAsia Maintenance - maintenance is sustenance
"Getting a rich partner is easy.
Keeping a rich partner is
tricky." AirAsia acknowledges
maintenance is sustenance.
AirAsia may be Asia's first and
only low fare no frills budget
air carrier. But in no way does
AirAsia penny-pinch on caring for its fleets AirAsia conducts line checks at transits, night-stops,
and "A" checks, low level maintenance checks that are conducted once a month. Hangar checks
are "C" and "D" checks conducted once yearly for between 10 to 21 days. The line check is
conducted by the AirAsia's maintenance crew, and the hangar check is conducted at the
Singapore Airlines Engineering Company. The engineering team attained JAR OPS1 or more
commonly referred to as M1 status. AirAsia is so well maintained; it has become more an
expectation than a requirement.
5. Planning and Control
Planning and control is important to determine duration, tasks, and tools required during
maintenance. Planning is a process that requires extensive analysis on problems so that plans can
be executed properly. The objectives of planning are:
a. to forecast the usage of resources,
b. to forecast cost for comparing with the expected income,
c. to prepare instructions and tasks for workers.
The outcome of planning is normally prepared in term of schedule. Resources are capital, workers,
parts, and equipment. An effective planning must include short-term, mid-term and long term plans
of an organization.
i. Long-term Planning
Prepared by Associate Professor Sallehuddin Muhamad UTM City Campus
An airline must prepare a long-term maintenance plan for at least five years. The plan is used
to prepare the airline fleet size, utilization of aircraft, number of workers, hangar size, tools,
and capital. With large number of workers, aircraft time in hangar is reduced. Thus, increases
flying hours at a higher maintenance cost.
ii. Mid-term planning
The mid-term planning covers 12 to 18 month of the airline operation. To ease scheduling,
maintenance plan and flight plan are prepared simultaneously. In mid-term planning,
maintenance dates for an aircraft is set.
iii. Short-term planning
The short-term planning is prepared for 30 to 60 day operations. The plan covers types of
aircraft, workload, hangar utilization and replacement parts requirement are prepared for daily
schedule. The plan is constantly updated to fit the rate of failure and traffic delays.
6. Critical Path Method (CPM)
Various methods were introduced in order to improve the effectiveness of planning and control.
In the 50s, a work schedule system was developed to enable a project to be completed at a shorter
time than previously required.
E.I. Du Pont de Nemours and Rand Corporation developed the Critical Path Method in 1956 to
control the construction and maintenance of chemical plants. The method involves time calculation
of an activity from the start to the end, based on the activity duration. It also analyzes float time in
the planning so that other activities do not interrupt the whole project. In 1970s, this method is
accepted and widely used.
The Critical Path Method is a management techniques in a project where its covers planning,
scheduling of activities and controlling. The method is divided into three phases, which are:
a. Planning Phase
It lists the fundamental objective of a project. It also identifies appropriate activities for the
project.
b. Scheduling of Activities Phase
It is the continuation of the Planning Phase. In this phase, all plans are scheduled according to
activity time with analysis on optimal resources requirements such as time, workload, and
equipment.
c. Controlling Phase
Prepared by Associate Professor Sallehuddin Muhamad UTM City Campus
In this phase, all activities for the project are controlled and updated so that they meet the
plans.
7. Gantt Chart
A Gantt chart is a horizontal bar chart developed as a production control tool in 1917 by Henry L.
Gantt, an American engineer and social scientist. Frequently used in project management, a Gantt
chart provides a graphical illustration of a schedule that helps to plan, coordinate, and track
specific tasks in a project. Gantt charts may be simple versions created on graph paper or more
complex automated versions created using project management applications such as Microsoft
Project or Excel.
A Gantt chart is constructed with a horizontal axis representing the total time span of the project,
broken down into increments (for example, days, weeks, or months) and a vertical axis
representing the tasks that make up the project. Horizontal bars of varying lengths represent the
sequences, timing, and time span for each task. A bar on the graph represents the amount of time
expected to spend on a task. Other tasks are added below the first one and representative bars at
the points in time they were undertaken. The bar spans may overlap if more than one task is
conducted during the same time span. As the project progresses, secondary bars, arrowheads, or
darkened bars may be added to indicate completed tasks, or the portions of tasks that have been
completed. A vertical line is used to represent the report date.
Gantt charts can be used:
Prepared by Associate Professor Sallehuddin Muhamad UTM City Campus
a. To schedule and monitor tasks within a project.
b. To assess time characteristics of a project.
c. To show links between scheduled tasks.
d. To give a clear illustration of a project status.
The advantages of Gantt charts are:
a. A wide audience can understand it.
b. It is easily comprehended for a small project.
c. It can coordinate activities to avoid ‘inferences’.
d. It provides a graphic schedule for the planning and controlling of work, and recording progress
towards stages of a project.
However, Gantt charts have these limitations:
a. It is not suitable for big activities (more than 30 activities).
b. It communicates relatively little information per unit area of display.
c. It does not represent the size of work elements; therefore, the magnitude of a behind-schedule
condition is easily misunderstood.
d. All activities show planned workload as constant. In practice, many activities have front-loaded
or back-loaded work plans.
The PERT chart, another popular project management charting method, is designed to do this.
Automated Gantt charts store more information about tasks, such as the individuals assigned to
specific tasks, and notes about the procedures. They also offer the benefit of being easy to change,
which is helpful. Charts may be adjusted frequently to reflect the actual status of project tasks as,
almost inevitably; they diverge from the original plan.
An example of an overhaul process flow chart for a PT6A engine with its Gantt chart is shown in
the class.
8. Maintenance Scheduling
Maintenance schedule lists works required on an aircraft through out its operational life. There are
two ways to prepare the schedule. They are:
a) Pyramid system
b) Progressive system
a. Pyramid System
In the Pyramid system, a set of works is grouped on a basic period, for an example every
200-flight hour. Another set of work will be performed at double period (i.e. 400, 800 and 1600
Prepared by Associate Professor Sallehuddin Muhamad UTM City Campus
flight hours).
The advantages of this system are:
ii. It reduces number of long inspection.
iii. Preparation and completion of job at each inspection.
iv. Optimize utilization of workers.
v. Planning and controlling the work is easy since each set of work has its own tasks.
Nevertheless, this system has the following disadvantages:
i. Workers idle time between inspections is large for air operators with small number of
aircraft.
ii. Long down time for inspection especially in the later period.
b. Progressive System
In the Progressive system, works are distributed through out the aircraft operational life so that
aircraft inspections and repairs can be performed at short intervals, thus reducing aircraft down
time. Factors affecting this system are:
i. Aircraft flight pattern and schedule.
ii. Number of aircraft per type.
iii. Aircraft reliability and failure rate.
iv. Number of workers.
v. Reliability to get spares.
vi. Maintenance cost
The aircraft Maintenance Schedule are divided into three categories, which are:
a) Line maintenance
b) Periodic maintenance
c) Heavy maintenance (overhaul)
a) Line Maintenance
Line maintenance is conducted daily and at every stopover. It is conducted prior to fly as
preflight check, correcting aircrew write-up (post-flight check) and routine airworthiness
inspections.
In civil aircraft, these checks are called transit check, stayover check, and supplement
stayover check. The Malaysia Airlines (MAS) line maintenance is given as follows:
Prepared by Associate Professor Sallehuddin Muhamad UTM City Campus
In military aircraft, these checks are labeled alphabetically.
Check Description of Check
A Preflight check (prior to the first flight of a day)
B End of day check (before night stop)
C Turn around check (between stops/ transit)
D Additional check (every 25 hr for Alluette III B helicopter)
E Cleaning (weekly-normal or daily for sea operation)
S Standby check (armament check)
b) Periodic Maintenance
The periodic maintenance is performed at specific intervals (flight hours, cycles, or days) as
prepared in maintenance program. These inspections determine the condition of an aircraft
and the maintenance required to return the aircraft to an acceptable airworthiness condition.
Functional checks and repairs are performed.
i) Small aircraft (less than 12,500 lb)
Small aircraft undergoes its annual and 100-h inspection to determine its airworthiness.
Checks are performed according to manufacturer checklists. However, aircraft operator
can prepare its own checklists but the checklists must be approved by the relevant
authority.
Example - Pyramid system
- Progressive system
ii) For civil aircraft larger than 12500lb or turbine-power multiengine aircraft, its periodic
checks are divided into four series of checks with specific recurring frequency. The checks
are:
A-check: primary inspection to disclose general condition
Aircraft Transit Stayover Supplement Stayover
B747-200/300/400 Every stop 6 hr planned 12 hr unplanned
-
DC10 Every stop 6 hr planned 12 hr unplanned
-
A300 Every stop 6 hr planned 12 hr unplanned
7 days
B737-400 Every stop Daily 18 days
B737-200 Every stop Daily -
F50 Every stop Daily 7 days
DHC6 Every stop Every night stop 125 hr or 75 days
Prepared by Associate Professor Sallehuddin Muhamad UTM City Campus
B-check: intermediate check
C-check: system and component check, airworthiness evaluation
D-check: structural inspection, determine airworthiness
An example of the periodic checks for large civil aircraft is shown in the following table.
Aircraft A-check B-check C-check D-check
B747-400 500FH or 7 weeks
B1 to B2: 1000FH C1 to C2: 5,000 FH 25,000 FH or 6 yrs on1st cycle. 20000 FH or 5yrs on subsequent cycle
B2 to B1: 1000FH or 14 wk
C2 to C1: 5,000 FH or 18 mth
B1 to B1: 2000FH or 28 wk
B737-400 375FH B1 to B2: 750FH C1 to C2: 3,000 FH H1 to H2: 10,000FH
B2 to B1: 750FH or 5 mth
C2 to C1: 3,000 FH H2 to H1: 10,000FH
H1 to H1: 20,000FH
F50 500FH or 3 month
1,000FH or 6 month C1 to C2: 3,000 FH D1 to D2: 12,000FH
C2 to C1: 3,000 FH or 18 mth
D2 to D1: 12,000FH or 6 yrs
iii) For military aircraft, the periodic checks are numbered from 1 to 5. Check 1 and check 2
are called Ordinary Level Maintenance (OLM) while Check 3 and Check 4 are called
Intermediate Level Maintenance (ILM). The final check, Check 5 is Depot Level
Maintenance (DLM). An example of the Periodic Maintenance for military aircraft is as
follow:
Check Type of Maintenance S61A-Nuri Alluette III B
1 Ordinary Level Maintenance
60 hr 150 hr (6mth)
2 180 hr 300 hr (12 mth)
3 Intermediate Level Maintenance
540 hr 900 hr (36 mth)
4 1080 hr 1800 hr (72 mth)
5 Depot Level Maintenance 4320 hr 3600 hr (108 mth)
c) Heavy Maintenance
Heavy Maintenance or generally known as overhaul involve major structural inspection. It involves
dismantling the aircraft, inspect all components, repair, and rebuild it required; systems and parts
are tested and repaired or replaced if necessary. Some modifications are made during heavy
maintenance.
9. Computerized Aircraft Maintenance Management
Maintenance of an aircraft is a complicated task since it involves pilots, mechanics, engineers,
Prepared by Associate Professor Sallehuddin Muhamad UTM City Campus
inspectors, and aircraft owners. In addition, the amount of information involved the process is very
large. This information is typically multi-modal and available in multiple storage media. Commonly,
this information is also geographically distributed. A major goal of the maintenance process is to
perform the most appropriate repairs on the most efficient way in the short time. Since
maintenance-related process relies on relevant information, comprehensive and timely information
delivery to the individuals involved in the maintenance can be significantly benefit the process.
Computerized Aircraft Maintenance Management (CAMM) system ease the task of keep tracking
of aircraft maintenance schedule. At the end of a flight or the day, pilot enters all of the recorded
flight data such as flight time, number of engine and airframe cycles, and over limit events in the
CAMM system. For each part, the cumulative number of hours of flight time is compared with the
life-cycle data specified in the maintenance documentation. These reference parameters are
initialized when the CAMM system is installed and updated whenever the aircraft manufacturer
issues modifications to the maintenance documentation. The results of the comparison are used to
define what maintenance work needs to be carried out on the aircraft, and allows maintenance
schedules to be drawn up.
Being able to plan maintenance work gives the operator a better overview of inventory movements
and allows new stocks to be ordered at the appropriate time. This enhanced predictability also
improves the management of invoicing procedures and the qualification management of pilots,
crews, and engineers.