Microsoft Word - Cover3.0 PROJECT DESCRIPTION
3.0 PROJECT DESCRIPTION
City of Elk Grove Franklin Boulevard Widening February 2006 Draft
Environmental Impact Report
3.0-1
3.1 PROJECT BACKGROUND
Franklin Boulevard is a north/south roadway providing direct
connection to downtown Sacramento. Franklin Boulevard currently
operates as a three-lane facility with left turn lanes at the
southbound intersections between Poppy Ridge Road and Elk Grove
Boulevard. The east side of Franklin Boulevard has roadway
lighting, widened pavement, curb and gutter, and improved drainage
facilities. The west side includes a six-foot paved shoulder, dirt
drainage ditch, and utility poles within the existing right-of-way.
There is currently no curb and gutter on the entire west side of
Franklin Boulevard in the project area. Signals have been installed
at the Poppy Ridge Road, Blossom Ridge Drive, Percheron Drive, and
Elk Grove Boulevard intersections with Franklin Boulevard. There
are seven oak trees along the west side of Franklin Boulevard
between the Laguna South Channel, North Drainage and Blossom Ridge
Drive.
Elk Grove Boulevard is an east/west arterial connecting Interstate
5 in the west with Grant Line Road in the east. Elk Grove Boulevard
has three westbound and two eastbound through lanes with a paved
shoulder, curb and gutter and sidewalk on the north side from the
Union Pacific Railroad overhead structure to Franklin Boulevard.
Elk Grove Boulevard west of the UPRR overhead structure to Four
Winds Drive is fully improved as above and striped for three lanes
in each direction, but with the three eastbound lanes tapering to
two eastbound lanes just west of the UPRR overhead structure. Under
the project, some minor re-striping of the eastbound through lanes
would be required just west of the overhead structure and on the
structure itself to conform to the extra eastbound lane added east
of the overhead structure. Decorative lights have been placed in
the vicinity of their ultimate locations. The Union Pacific
overhead structure does not have a separate raised sidewalk,
although it was designed and built wide enough to accommodate a
future sidewalk. A sidewalk on the Union Pacific overhead structure
will not be constructed as part of the proposed project.
The City of Elk Grove General Plan and East Franklin Specific Plan
(EFSP) designates land surrounding the proposed project site for
urban use, except for the open space managed by Stone Lakes
National Wildlife Refuge on the west side of Franklin Boulevard.
The project segment of Franklin Boulevard borders the west side of
the EFSP area, a mixed-use community planned for 2,474 acres,
including over 4,100 approved or proposed single family residential
units, medium and high density residential housing, 313,632 square
feet of commercial space, and nine schools. Access to the EFSP
development is primarily from Franklin Boulevard on the west, Elk
Grove Boulevard on the north, and Bruceville Road on the east.
Franklin Boulevard serves as the primary western arterial to
Franklin High School and Toby Johnson Middle School on Poppy Ridge
Drive, approximately one mile east of Franklin Boulevard. In
addition, Elk Grove Boulevard serves as the major arterial from
Interstate 5 to existing and planned development east of the EFSP,
including downtown Elk Grove, the Elk Grove Automall, and the
approved and permitted Laguna Ridge Specific Plan mixed-use
community. The City anticipates rapid economic growth in the coming
years from commercial office, retail, and other
employment-generating uses. Consequently, the City is anticipated
to undergo sustained growth through the year 2025.
The proposed project has been identified as traffic mitigation
measures in the transportation and circulation elements of the East
Franklin Specific Plan EIR and the Elk Grove General Plan EIR. The
Franklin Boulevard bridge over the Laguna South Channel was widened
previously to accommodate up to six lanes as part of the Laguna
South Channel Improvements—East Franklin North Drainage project
designed to implement drainage improvements as required by the
County of Sacramento for the northern portion of the EFSP. This
project was constructed in 2003 under US Army Corps of Engineers
(ACOE) Individual 404 Permit # 200100562 dated September 9, 2002.
The portion of Elk Grove Boulevard in the project area was widened
to five lanes by the County in 1997.
3.0 PROJECT DESCRIPTION
Franklin Boulevard Widening City of Elk Grove Draft Environmental
Impact Report February 2006
3.0-2
The City altered the project design and footprint on the west side
of Franklin Boulevard after considering comments from the United
States Fish and Wildlife Service (USFWS) and ACOE to minimize
potential effects to sensitive biological resources on that side of
the road. Design changes included reducing road slope widths and
bus turnout widths, relocating utility poles to the road bench
instead of 15 feet west into the Stone Lakes National Wildlife
Refuge (SLNWR), and relocating bus stops to minimize impacts to
wetlands. The City has also reduced the width of widening on the
south side of Elk Grove Boulevard by eliminating sidewalk and
rerouting pedestrian traffic to the north side of Elk Grove
Boulevard.
The estimated cost of the project, in its entirety, is
approximately $5.6 million, and would be funded through the Elk
Grove Roadway Fee Program. The expected start date for construction
of the project is 2006.
3.2 PROJECT LOCATION
The Franklin Boulevard Widening Project (proposed project) site is
located entirely within the City of Elk Grove (“City”) limits
within Sacramento County. The project site is located in Section 5,
Township 6 North, Range 5 East, Sacramento County, California, as
shown on the Florin, California USGS Topographic Quadrangle. The
project area is four miles west of the central commercial district
of the City of Elk Grove. It is situated two miles east of
Interstate 5 and four miles west of State Route 99 (see Figure
3.0-1, Regional Location Map, and Figure 3.0-2, Project Location
Map).
Land east of Franklin Boulevard includes a Raley’s shopping center
currently being constructed on the parcel on the southeastern
corner of the Franklin Boulevard/Elk Grove Boulevard intersection,
a partially landscaped corridor of land approximately 120 feet wide
along the entire eastern side of Franklin Boulevard between the
Laguna South Channel and Poppy Ridge Road, and an existing
apartment complex on the southeastern corner of the Franklin
Boulevard/ Poppy Ridge Road intersection. Single-family residential
housing occurs east of the partially landscaped corridor on the
east side of Franklin Boulevard, except for an undeveloped parcel
zoned as commercial on the northeastern corner of the Franklin
Boulevard/ Poppy Ridge Road intersection. Single-family residential
housing is on the north side of Elk Grove Boulevard in the project
area.
New right-of-way would be required from Laguna Stone Lake, LLC, a
subsidiary of AKT Development Corporation, the property owner of
parcel APN 132-0020-003, which is adjacent to the west side of the
project. This 89-acre, undeveloped triangular parcel of land is
bounded by Union Pacific Railroad (UPRR) tracks on the West, Elk
Grove Boulevard on the North, and Franklin Boulevard on the East.
The property owner of this parcel has granted a perpetual
Conservation Easement to the Stone Lakes National Wildlife Refuge
(administered by the USFWS). The conservation easement was
established to protect biological habitat created/restored as an
element for mitigation for the Powers House and Elliott Ranch South
residential developments in the project vicinity. Right-of-way
acquisition for the land required to complete the proposed project
(up to 38 feet encroachment on the south side of Elk Grove
Boulevard, and up to 12 feet wide encroachment in areas along the
west side of Franklin Boulevard) would involve USFWS transferring
portions of their conservation easement to the City of Elk Grove.
The project would require 0.79 acres of the conservation easement
on along Elk Grove Boulevard and 0.43 acres along Franklin
Boulevard.
Sacramento
Concord
StocktonAntioch
PlacervillePlacerville
Discovery BayDiscovery Bay
Rancho MurietaRancho Murieta
Figure 3.0-1 Regional Vicinity Map
City of Elk Grove Development Services
Source: ESRI, 2005
§¦5
Bilby
Source: ESRI, 2005; City of Elk Grove, 2005
Project Site
3.0 PROJECT DESCRIPTION
City of Elk Grove Franklin Boulevard Widening February 2006 Draft
Environmental Impact Report
3.0-7
3.3 PROJECT PURPOSE AND OBJECTIVES
The proposed Franklin Boulevard Widening Project is outlined within
the Circulation Element of the City of Elk Grove General Plan. The
Guiding Goals of the General Plan as it relates to Transportation
and Circulation are as follows:
• A high quality of life for all residents; • Protection of the
natural environment; and • Preservation of the rural character of
Elk Grove.
The intent of the Franklin Boulevard Widening Project is to fulfill
the objectives of the General Plan by balancing the roadway
capacity needs with measures that will minimize environmental
impacts in the project area. The specific objectives of the
Franklin Boulevard Widening Project are to:
• Provide adequate roadway and intersection level of service to
accommodate future traffic anticipated in the area from planned and
approved development under the General Plan;
• Provide more efficient access to residential and commercial
developments and schools within the East Franklin Specific Plan
area and surrounding areas in the City of Elk Grove;
• Provide for improved roadway and intersection safety; •
Accommodate the needs of bicyclists and pedestrians; • Plan for
future transit service; and • Provide more efficient access to
residential and commercial developments and schools
within the East Franklin Specific Plan.
3.4 PROJECT DESCRIPTION
The proposed project, shown on Figures 3.0-3A and 3.0-3B, would
widen a portion of Elk Grove Boulevard from five lanes to six lanes
and a portion of Franklin Boulevard from three lanes to six lanes.
Elk Grove Boulevard would be widened approximately 24 feet on the
south side (eastbound) between the UPRR overcrossing and Franklin
Boulevard, a distance of approximately 0.25 mile. Franklin
Boulevard would be widened approximately 26 feet on the west side
from its intersection with Elk Grove Boulevard south to
approximately 80 feet south of Poppy Ridge Road, a distance of
approximately 1.1 mile, to provide for a six lane arterial with
median landscaping. The project would include new right-of-way to
accommodate new free right-turn lanes on eastbound Elk Grove
Boulevard and southbound Franklin Boulevard north of Laguna South
Channel, North Drainage, and for portions of the Franklin Boulevard
widening, including two bus turnouts, south of Laguna South
Channel, North Drainage along the west side of Franklin Boulevard.
The project would require 0.79 acres of the conservation easement
on along Elk Grove Boulevard and 0.43 acres along Franklin
Boulevard.
The proposed improvements to Elk Grove Boulevard would begin at the
UPRR overhead structure and end at the intersection of Franklin
Boulevard and Elk Grove Boulevard. Some minor road re-striping
would occur on the UPRR overhead structure and on the eastbound
lanes of Elk Grove Boulevard west of the overhead structure to its
intersection with Four Winds Drive.
The proposed improvements to Franklin Boulevard would begin at and
include the intersection of Franklin Boulevard and Elk Grove
Boulevard, and extend to the south approximately 80 feet south of
the Franklin Boulevard and Poppy Ridge Road intersection. The
existing lanes on Franklin Boulevard would become the ultimate
three northbound lanes, median, and one southbound lane, while two
new southbound lanes and two bus turnouts added to the west
side
3.0 PROJECT DESCRIPTION
Franklin Boulevard Widening City of Elk Grove Draft Environmental
Impact Report February 2006
3.0-8
of the existing road. Seven existing oak trees on the west side of
Franklin Boulevard would need to be removed, and an intermittent
open earthen storm water drainage ditch running adjacent to most of
the west side of existing Franklin Boulevard would be filled to
accommodate the new southbound lanes and bus turnouts. If feasible,
the City may install exclusionary netting in and around the Laguna
South Channel, North Drainage culvert to discourage use by nesting
and roosting animals. The project features are described
below.
Roadways
Elk Grove Boulevard: The Elk Grove Boulevard widening would include
an additional eastbound through lane and a four- to five-foot wide
bike lane, as well as an approximately 300 foot long dedicated
right turn lane onto southbound Franklin Boulevard. The UPRR
overcrossing will only require re-striping, and not include any
widening of the structure itself. The project would not require
widening the base of the current engineered slope created by the
County of Sacramento Public Works Department (County) as a ramp for
Elk Grove Boulevard leading up to the UPRR overcrossing. The
roadway portion of the Elk Grove Boulevard widening would
include:
• Grading; • Pavement delineation; • Drainage modifications and
installation; • New 4-5 foot wide bike lane; • Utility work; •
Possible decorative lighting relocation; • Signal modification; •
Signing; and • Construction traffic controls.
Franklin Boulevard: The Franklin Boulevard widening would include
an additional three through lanes, a four-foot bike lane, and a
three-foot curb/gutter on the southbound direction (west side). An
auxiliary lane of approximately 280 feet in length would extend
from the intersection of Elk Grove Boulevard in the southbound
direction to receive traffic from the free right turn lane on
eastbound Elk Grove Boulevard. Sidewalks on the west side would
only be constructed at two bus turnout locations, one just south of
Percheron Drive and one just north of Blossom Ridge Drive; and
short segments between the crosswalks at the Percheron Drive and
Blossom Ridge Drive intersections. The landscaped median would be
12 feet wide. The Franklin Boulevard widening would include:
• Grading; • Pavement delineation; • Drainage modifications and
installation; • Signal modifications; • Lighting; • Median planting
and irrigation; • Signing; • Utility relocation; and • Construction
traffic control.
3.0 PROJECT DESCRIPTION
City of Elk Grove Franklin Boulevard Widening February 2006 Draft
Environmental Impact Report
3.0-9
Roadway Median
The Franklin Boulevard median would be a combination of landscaped
islands and two-way left turn lanes, as designated by the traffic
study. The signalized intersections would provide for
U-turns.
The Sacramento Municipal Utility District (SMUD) would relocate its
utility poles along the west side of Franklin Boulevard on the new
3-foot wide bench behind the curb of the roadway, within the City’s
existing right-of-way, instead of relocating the poles within
SMUD’s 12.5 foot wide utility easement located within SLNWR’s
boundary. SMUD would perform maintenance service on the utility
poles from the roadway. Utility pole relocation is designed to
minimize impacts to vernal pools, seasonal wetlands, and elderberry
bushes to the maximum extent feasible.
Curb/Gutter and Drainage
Curb and gutter would be provided on the south side of Elk Grove
Boulevard and on the west side of Franklin Boulevard. The proposed
project will not alter the existing curb and gutter on the north
side of Elk Grove Boulevard and east side of Franklin
Boulevard.
The roadway storm water drainage system presently on the west side
of Franklin Boulevard consists of an open earthen intermittent
ditch that flows northward toward Laguna South Channel in the
northern half of Franklin Boulevard, and southward into vernal
pools in the southern half of Franklin Boulevard within the project
area. The proposed project would fill this earthen intermittent
drainage ditch and replace it with an underground storm water
conveyance system consisting of curb and gutter along the new
portion of the widened roadway with storm water catchment basins.
The majority of storm water catchment basins on the west side of
Franklin Boulevard would be routed across and under Franklin
Boulevard to the existing underground storm water pipe system on
the east side of the road, which, in turn, routes storm water
either northward to an outfall into Laguna South Channel, North
Drainage or southward to connect with the storm water system along
Poppy Ridge Road. A short segment of the proposed underground storm
water system on the west side of Franklin Boulevard closest to
Laguna South Channel would route storm water directly into the west
side of Laguna South Channel. Drainage for the new portion of Elk
Grove Boulevard would tie into the existing underground storm water
drainage system on Elk Grove Boulevard
Sidewalks/Pathways
To reduce the project impacts, no new sidewalks would be
constructed on the south side of Elk Grove Boulevard. Pedestrian
traffic would be routed by signage to use the north sidewalk on Elk
Grove Boulevard between Four Winds Drive and Franklin Boulevard.
Six-foot wide sidewalks on the west side of Franklin Boulevard
would only be constructed at two bus turnout locations, one just
south of Percheron Drive and one just north of Blossom Ridge Drive;
and short segments between the crosswalks at the Percheron Drive
and Blossom Ridge Drive intersections.
Landscaping
Landscaping consistent with the rural character of the area would
be used in the median, including Valley Oak trees used as
mitigation for the seven removed oak trees for the Franklin
Boulevard widening. At this time it is expected that only native
grasses and forbs will be planted outside of the paved areas of the
widening along the embankment slopes. Mitigation oak trees may also
be planted along the eastern edge of the SLNWR lands pursuant to
approval from USFWS.
3.0 PROJECT DESCRIPTION
Franklin Boulevard Widening City of Elk Grove Draft Environmental
Impact Report February 2006
3.0-10
Lighting
The City will use roadway lighting luminaries along the west side
of Franklin Boulevard and the south side of Elk Grove Boulevard
that will direct the majority of light (sodium-based) toward the
roads and away from the SLNWR lands to reduce night time light
impacts to wildlife. Current lighting luminaries along Elk Grove
Boulevard may require relocation to the south to accommodate
construction.
3.5 PROJECT CONSTRUCTION
Project construction is scheduled to begin in the spring of 2006
and be completed in the fall of 2006.
3.6 REQUIRED PROJECT APPROVALS
In order for the project to be implemented, a series of actions and
approvals would be required from agencies. Anticipated project
approvals would include, but are not limited to, the
following:
• Elk Grove City Council - Certification of the Environmental
Impact Report (EIR), adoption of the Mitigation Monitoring and
Reporting Program, and other actions associated with project
approval.
• United States Fish and Wildlife Service – Approve contract or
agreement to transfer portions of its conservation easement on
adjacent parcel APN # 132- 0020-003 to the City to construct
proposed project. Through formal Section 7 consultation with ACOE,
USFWS must issue a Biological Opinion regarding potential effects
and mitigation for all federally listed species affected by the
project, as presented in the City’s biological assessment included
in the 404 permit package.
3.7 OTHER PROJECT ASSUMPTIONS
The EIR assumes compliance with all applicable State, Federal, and
local codes and regulations including, but not limited to, City of
Elk Grove Development Standards, the California Building Code, the
Guidance Manual of On-site Storm Water Quality Control Measures,
the State Health and Safety Code, and the State Public Resources
Code. Additional permits may be required prior to beginning
construction. These include:
• California Regional Water Quality Control Board – 401 Water
Quality Certification;
• United States Army Corps of Engineers – Section 404 Individual
Permit;
• State Water Resources Control Board – Notice of Intent to comply
with the City of Elk Grove’s General storm Water Permit.
Proposed Project Layout
Laguna South Channel
Match Line
Bus Turnout
Stone Lakes National Wildlife Refuge - Managed Parcel
0 500250 FeetSource: City of Elk Grove, 2004; Wood Rodgers, 2005;
AirPhoto USA, 2004
Legend
Match Line
Bus Turnout
SLNWR - Managed Parcel
T: \G IS \E lk _G ro ve \P R O JE C TS \fr an kl in \E IR \fi gu re
_3 .4 -1 b. m xd
0 500250 FeetSource: City of Elk Grove, 2004; Wood Rodgers, 2005;
AirPhoto USA, 2004
Legend Existing City Right-of-Way
Proposed Edge of Construction
Proposed Curb and Median
3.0 PROJECT DESCRIPTION
City of Elk Grove Franklin Boulevard Widening February 2006 Draft
Environmental Impact Report
3.0-15
3.8 TECHNICAL STUDIES
Several technical studies were conducted as part of this EIR,
including:
• Wetland Delineation Report, September 29, 2005 • Arborist Report,
November 12, 2004 • Cultural Resources Report, January 2005 •
Initial Site Assessment, Wallace Kuhl & Associates, Inc., • Air
Quality Impact Evaluation, Donald Ballanti, • Noise Impact
Analysis, ATS Consulting, LLC., • Traffic Operations Analysis, Wood
Rodgers,
These technical studies are available for review weekdays between
the hours of 9:00 a.m. and 5:00 p.m. at the City of Elk Grove City
Hall, 8400 Laguna Palms Way, Elk Grove, California 95758. Some of
these reports are attached to the Draft EIR as appendices.
REFERENCES