3. EXISTING FACILITY CONDITIONS

3. ExiSting facility c onditoni S · the focus of this chapter is on the marquam Hill campus ... Sam Jackson donates 88 acres ... 3.6 EXISTING FACILITY CONDITIONS OHSU 20-Year Facilities

Embed Size (px)

Citation preview

3. ExiSting facility conditionS

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.1EXISTING FACILIT Y CONDITIONS

the focus of this chapter is on the marquam Hill campus where most of oHSu’s buildings are located. the process of building condition assessment is discussed, and each building is rated to enable assessment of its future uses. in addition to the physical condition of a building, its historical significance and its location also play a part in deciding upon its future. definitions of twenty-year facilities needs in the next chapter are used in conjunction with this assessment of building conditions to suggest logical scenarios for the use, adaptation or replacement of each building.

3. ExiSting facility conditionS

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.2 EXISTING FACILIT Y CONDITIONS

Campus Development Timeline

1900 302010 40 501931

the university’s first outpatient clinic building opens, now Sam Jackson Hall.

1939

oHSu library is opened (now oHSu auditorium).

third and final phase of mackenzie Hall completed (the western wing).

State tuberculosis Hospital opens (now campus Services Building).

1949

Baird Hall opens to house the department of physiology and administrative offices.

1954

crippled children’s division opens, now the child development and rehabilitation center (cdrc).

1956

the university of oregon dental School moves from northeast oregon Street to its present location on marquam Hill.

medical School Hospital opens (currently the western wing of oHSu Hospital). doernbecher children’s Hospital moved to the top three floors.

1913

Willamette university and the university of oregon merge programs to form the university of oregon medical School.

1919

the university of oregon medical School moves from downtown portland to its present location on marquam Hill in southwest portland.

the first building, mackenzie Hall, was named after Kenneth a.J. mackenzie, md, the railroad’s surgeon who had convinced the railroad company to donate the worthless land on top of the hill. the first class had 66 students, and a volunteer faculty of more than 40 instructors. the university of oregon in Eugene begins offering courses in nursing.

1922

Second phase of mackenzie Hall is completed.

1923

the new multnomah county Hospital, built for $1.1 million, opens. (the building is now called multnomah Hall.)

1924

oregon Journal publisher Sam Jackson donates 88 acres adjacent to the university for “healing of the sick and crippled and recreation of the public and play of children.”

1926

25 acres of the Sam Jackson donation is deeded to the united States government as the site for a veterans hospital.

doernbecher children’s Hospital opens in what is now dillehunt Hall. the first children’s hospital in the northwest is funded from a $200,000 donation from furniture manufacturer frank doernbecher.

1927

Emma Jones Hall opens as a dormitory for nursing students.

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.3EXISTING FACILIT Y CONDITIONS

2000807060 901960

Student activities center is built, now the oHSu Student center. an indoor pool was added in 1980.

1962

medical research Building (mrB) complete.

1963

oregon regional primate research center opens on 163 acres west of portland.

1969

multnomah county Hospital adds a six-story wing to the north.

1972

Basic Science Building is completed.

the East wing of oHSu Hospital opens.

1973

multnomah county Hospital is transferred from the county to the state and becomes multnomah pavilion (mnp) and the medical School Hospital becomes university Hospital (south), now oHSu Hospital (oHS).

1983

Shriners children’s Hospital opens on land leased from oHSu.

1987

construction is completed on the vollum institute for advanced Biomedical research.

1990

dotter institute is established at oHSu to honor the pioneer of interventional radiology.

1991

casey Eye institute opens on marquam Hill.

the Biomedical information communication center (Bicc) is completed.

1992

the vamc skybridge is completed.

the School of nursing building opens.

1993

physicians pavilion opens on marquam Hill.

1995

oHSu becomes a public corporation and separates from the oregon State System of Higher Education.

1998

the mark o. Hatfield research center is dedicated.

doernbecher children’s Hospital is opened.

2003

marquam Hill is designated a “plan district” by the portland city council.

2004

the Schnitzer investment corporation donates nearly 20 acres of riverfront property in South Waterfront to oHSu.

2005

Biomedical research Building (BrB) opens on marquam Hill.

2006

center for Health & Healing (cHH), one of oregon’s greenest buildings, opens on the South Waterfront.

city of portland’s aerial tram begins operating between oHSu’s marquam Hill campus and South Waterfront.

peter o. Kohler pavilion opens as state-of-the-art patient care facility on marquam Hill.

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.4 EXISTING FACILIT Y CONDITIONS

Facilities Condition Assessment

FACiliTieS COnDiTiOnoHSu facilities staff tracks the extent of outstanding maintenance on each building relative to core-and-shell insured replacement values. this information has been used to create a facilities condition index (fci). under the fci, the condition of each building is classified as ‘good’ if the cost of outstanding maintenance is less than 5% of the replacement value of a building; ‘fair’ if between 5% and 30%; and ‘poor’ if greater than 30% of replacement value.

although a helpful guide to the useful life of a building, the facilities condition index must be tempered by considerations of historical significance, and a building’s role, if any, in campus infrastructure systems. overall investment priorities will influence decisions to improve, remodel or replace a building. another consideration is the intrinsic flexibility of each building; its capacity for adaptation of its spaces to other uses.

poor (>30%)good fair 1 fair 2

5% 10% 30%

eXiSTing BUilDingS DeemeD DeFiCienTmarquam Hill campus buildings that received an fci score that rated as ‘poor’ are as follows: dillehunt, multnomah pavilion, Sam Jackson, Emma Jones, medical research Building, School of dentistry, mackenzie Hall, Baird Hall, gaines Hall, auditorium, and the physical plant.

this scoring was based on the total value of necessary maintenance yet to be implemented, and includes mechanical, electrical, and structural improvements related to the physical operation of the building. the building inventory was classified under the categories shown on the “facilities condition” plan.

Outstanding maintenance as a percentage of building value.

Facilities Condition index

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.5EXISTING FACILIT Y CONDITIONS

Facilities Condition (index score)

poor (>30%)

fair 2 (10-30%)

fair 1 (5-10%)

good (0-5%)

not applicable

historical significance, to be validated

architect evaluation of building FCI, to be validated*

*

*

*

*

*

*

*

0 300’N

SON

CSBBTE

GH CDRC

VA

DCH

OSC

SOD CEI

OHS

KPV

PPVSJH

MNP

EJH

HRCBICC

PP

BH

BRB

MRB

VIABR

AUD

RJH

sw ca

mpus drive

sw campus drive

sw us veterans hospital road

sw gaines street

sw sa

m jackso

n park ro

ad

sw terwilliger boulevard

MAC

DH

CDW

MBS

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.6 EXISTING FACILIT Y CONDITIONS

Hospital Ancillary Space these are spaces for the review, evaluation, diagnosing, and treatment of patients at oHSu requiring a stay in excess of 24 hours. Hospital ancillary space includes examination rooms, diagnostic imaging rooms, surgical suites, laboratories supporting surgery and diagnostic services, post anesthesia care unit space, mother-baby patient rooms, short stay rooms, and support spaces related to these uses.

Faculty faculty offices and any related support spaces are included.

Research research related laboratories with their associated offices and support spaces are included.

Central Services Spaces for the management and administration spaces include the office of the university president, legal department, real estate, design, construction, facilities maintenance, and traffic departments. also included are any departments working on the development and maintenance of oHSu campuses.

Student Space Student space includes classroom, laboratories, and office spaces for the four schools. limited examination, treatment and research spaces related to student instruction are also covered in this category.

Summary Assessments of Buildings

in the following pages is a summary of the condition of each building pertinent to the 20-year plan for marquam Hill campus, noting year of construction, size given in gross Square feet (gSf) or assignable Square feet (aSf) as appropriate, principal uses, fci rating and anticipated future actions.

Inpatient Space inpatient space consists of bedrooms for overnight patients at oHSu, with the exception of the mother-Baby patient rooms. also included are support spaces related to patient bedrooms, such as bathrooms, nurse’s stations, and waiting areas on patient floors.

Outpatient Space these are spaces for the review, evaluation, diagnosing, and treatment of patients not requiring a stay longer than 24 hours during the course of their treatment. outpatient space includes examination rooms, diagnostic imaging rooms, surgical suites, laboratories supporting surgery and diagnostic services, and offices for staff in each of these areas.

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.7EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

originally constructed in 1949, Baird Hall contains approximately 45,715 gSf on four floors. it was built to house the university’s administration and it continues to include the office of the president and senior executive leadership. other than administration, the main uses are: dermatology, obstetrics & gynecology, perinatology, and Student Services/affairs.

overall condition of the facility indicates normal wear for a building of its age. With a fci rating of 44%, Baird Hall has the fourth worst rating of university buildings. given its age and condition. Baird Hall will need extensive renovation if it is not replaced.

Baird Hall (BH)

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 135 0%

Faculty 4,167 15%Research 5,954 22%

Central 11,244 41%Student 5,712 21%

100%Assignable Square Footage 27,212 sf

Circulation, wall area, etc. 18,503 sfGross Bldg Area 45,715 sf

BAIRD HALL (BH)

11,244

10,000

12,000Assignable Square Footage by Category

15%

22%

21%

Inpatient

Outpatient

Hospital Ancillary

Faculty

0 0 135

4,167

5,9545,712

0

2,000

4,000

6,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

15%

22%

41%

21%Hospital Ancillary

Faculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 135 0%

Faculty 4,167 15%Research 5,954 22%

Central 11,244 41%Student 5,712 21%

100%Assignable Square Footage 27,212 sf

Circulation, wall area, etc. 18,503 sfGross Bldg Area 45,715 sf

BAIRD HALL (BH)

11,244

10,000

12,000Assignable Square Footage by Category

15%

22%

21%

Inpatient

Outpatient

Hospital Ancillary

Faculty

0 0 135

4,167

5,9545,712

0

2,000

4,000

6,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

15%

22%

41%

21%Hospital Ancillary

Faculty

Research

Central

Student

45,715 Gross Exterior Square Footage8,294,000$ 2011-2020 Deferred Maintenance Event Cost

19,064,150$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

43.51% FCI

33,368 Square Footage4,065,000$ 2011-2020 Deferred Maintenance Event Cost8,917,364$ Core & Shell Insured Replacement Value

267$ Replacement Cost / Square Foot45.59% FCI

90,627 Square Footage6,124,000$ 2011-2020 Deferred Maintenance Event Cost

13,115,246$ Core & Shell Insured Replacement Value145$ Replacement Cost / Square Foot

46.69% FCI

31,134 Square Footage4,237,000$ 2011-2020 Deferred Maintenance Event Cost

Physical Plant

Gaines Hall

Old Library & Auditorium

Baird Hall

4,237,000$ 2011-2020 Deferred Maintenance Event Cost8,304,187$ Core & Shell Insured Replacement Value

267$ Replacement Cost / Square Foot51.02% FCI

44 % FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.8 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1991, this facility contains 85,583 gSf on six floors. Serving as the main campus library, Bicc accommodates: medical informatics, Educational communications, information technology group and the library Services for students, faculty and staff. overall condition of the facility is rated ‘good’ with a fci rating of 2.5% reflecting some wear and tear.

Biomedical information and Communications Center (BiCC)

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 74 0%

Faculty 8,953 20%Research 6,991 16%Central 4,137 9%Student 23,919 54%

100%Assignable Square Footage 44,075 sfCirculation, wall area, etc. 41,507 sf

Gross Bldg Area 85,583 sf

BIOMEDICAL INFORM COMMUNITY CTR

23,91925,000

30,000Assignable Square Footage by Category

20%

16%

10%54%

Inpatient

Outpatient

Hospital AncillaryFaculty

0 0 74

8,953

6,991

4,137

23,919

0

5,000

10,000

15,000

20,000

25,000

30,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Assignable Square Footage by Category

20%

16%

10%54%

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 74 0%

Faculty 8,953 20%Research 6,991 16%Central 4,137 9%Student 23,919 54%

100%Assignable Square Footage 44,075 sfCirculation, wall area, etc. 41,507 sf

Gross Bldg Area 85,583 sf

BIOMEDICAL INFORM COMMUNITY CTR

23,91925,000

30,000Assignable Square Footage by Category

20%

16%

10%54%

Inpatient

Outpatient

Hospital AncillaryFaculty

0 0 74

8,953

6,991

4,137

23,919

0

5,000

10,000

15,000

20,000

25,000

30,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Assignable Square Footage by Category

20%

16%

10%54%

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

Student

85,583 Square Footage910,000$ 2011-2020 Deferred Maintenance Event Cost

35,691,534$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

2.55% FCI

339,694 Square Footage177,000$ 2011-2020 Deferred Maintenance Event Cost

106,080,000$ Core & Shell Insured Replacement Value312$ Replacement Cost / Square Foot

0.17% FCI

99,149 Square Footage1,088,000$ 2011-2020 Deferred Maintenance Event Cost

41,492,561$ Core & Shell Insured Replacement Value418$ Replacement Cost / Square Foot

2.62% FCI

10,443 Square Footage331,000$ 2011-2020 Deferred Maintenance Event Cost

BICC

BRB

Modular Building Structure

School of Nursing

331,000$ 2011-2020 Deferred Maintenance Event Cost3,551,951$ Core & Shell Insured Replacement Value

340$ Replacement Cost / Square Foot9.32% FCI

50,964 Square Footage3,158,000$ 2011-2020 Deferred Maintenance Event Cost

21,223,166$ Core & Shell Insured Replacement Value416$ Replacement Cost / Square Foot

14.88% FCI

98,169 Square Footage4,817,000$ 2011-2020 Deferred Maintenance Event Cost

40,940,400$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

11.77% FCI

Campus Services Building

Vollum Institute

2.5% FCI

© Cyril “Kent” Anderson

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.9EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 85 0%

Faculty 10,001 9%Research 93,644 80%Central 7,861 7%Student 4,980 4%

100%Assignable Square Footage 116,570 sfCirculation, wall area, etc. 223,124 sf

Gross Bldg Area 339,694 sf

BIOMEDICAL RESEARCH BUILDING (BRB)

93,644

70,000

80,000

90,000

100,000Assignable Square Footage by Category

9%

80%

7% 4%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0 85

10,001

93,644

7,8614,980

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Assignable Square Footage by Category

9%

80%

7% 4%Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

Student

Biomedical Research Building (BRB)

85,583 Square Footage910,000$ 2011-2020 Deferred Maintenance Event Cost

35,691,534$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

2.55% FCI

339,694 Square Footage177,000$ 2011-2020 Deferred Maintenance Event Cost

106,080,000$ Core & Shell Insured Replacement Value312$ Replacement Cost / Square Foot

0.17% FCI

99,149 Square Footage1,088,000$ 2011-2020 Deferred Maintenance Event Cost

41,492,561$ Core & Shell Insured Replacement Value418$ Replacement Cost / Square Foot

2.62% FCI

50,964 Square Footage3,158,000$ 2011-2020 Deferred Maintenance Event Cost

21,223,166$ Core & Shell Insured Replacement Value416$ Replacement Cost / Square Foot

14.88% FCI

BICC

BRB

Campus Services Building

School of Nursing

Built in 2005, the Biomedical research Building contains 339,694 gSf of total area over 7 usable floors. the building consists of over 162,000 sf of research/laboratory space and an advanced imaging research center that is 16,000 sf. a few of the multidisciplinary teams of scientists and clinicians that work together in this building are from Knight cancer institute, comparative medicine, pediatric and neurology departments.

With a fci rating of .17%, this lEEd certified research facility is in excellent condition.

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 85 0%

Faculty 10,001 9%Research 93,644 80%Central 7,861 7%Student 4,980 4%

100%Assignable Square Footage 116,570 sfCirculation, wall area, etc. 223,124 sf

Gross Bldg Area 339,694 sf

BIOMEDICAL RESEARCH BUILDING (BRB)

93,644

70,000

80,000

90,000

100,000Assignable Square Footage by Category

9%

80%

7% 4%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0 85

10,001

93,644

7,8614,980

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Assignable Square Footage by Category

9%

80%

7% 4%Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

Student

0.17% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.10 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in1962 and previously named the Hearing & Speech institute, this building was purchased in 2005. BtE contains 17,828 gSf on three floors. review of the facility indicates that this building could be demolished and it’s programs backfilled into other buildings.

Building 28 (BTe)

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,574 37%

Faculty 2,798 29%Research 874 9%

Central 1,532 16%Student 925 10%

100%Assignable Square Footage 9,703 sf

Circulation, wall area, etc. 8,125 sfGross Bldg Area 17,828 sf

BUILDING 28 (BTE)

3,574

2,7983,000

3,500

4,000Assignable Square Footage by Category

37%

29%9%

16%

9%

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

0 0

2,798

874

1,532

925

0

500

1,000

1,500

2,000

2,500

3,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

37%

29%9%

16% AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,574 37%

Faculty 2,798 29%Research 874 9%

Central 1,532 16%Student 925 10%

100%Assignable Square Footage 9,703 sf

Circulation, wall area, etc. 8,125 sfGross Bldg Area 17,828 sf

BUILDING 28 (BTE)

3,574

2,7983,000

3,500

4,000Assignable Square Footage by Category

37%

29%9%

16%

9%

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

0 0

2,798

874

1,532

925

0

500

1,000

1,500

2,000

2,500

3,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

37%

29%9%

16% AncillaryFaculty

Research

Central

Student

*

* no fci review/ rating done for BtE. architect evaluation shown.

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.11EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1939 as an isolated hospital for tuberculosis patients, this facility contains 50,964 gSf on seven floors. this building houses central service functions of design & construction as well as the public Health & preventative medicine department and itg. With a fci rating of 15%, the building is considered to be in ‘fair’ condition, but given its age, it could be demolished and its programs backfilled into other buildings.

Campus Services Building (CSB)

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 135 0%

Faculty 4,167 15%Research 5,954 22%

Central 11,244 41%Student 5,712 21%

100%Assignable Square Footage 27,212 sf

Circulation, wall area, etc. 18,503 sfGross Bldg Area 45,715 sf

BAIRD HALL (BH)

11,244

10,000

12,000Assignable Square Footage by Category

15%

22%

21%

Inpatient

Outpatient

Hospital Ancillary

Faculty

0 0 135

4,167

5,9545,712

0

2,000

4,000

6,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

15%

22%

41%

21%Hospital Ancillary

Faculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 135 0%

Faculty 4,167 15%Research 5,954 22%

Central 11,244 41%Student 5,712 21%

100%Assignable Square Footage 27,212 sf

Circulation, wall area, etc. 18,503 sfGross Bldg Area 45,715 sf

BAIRD HALL (BH)

11,244

10,000

12,000Assignable Square Footage by Category

15%

22%

21%

Inpatient

Outpatient

Hospital Ancillary

Faculty

0 0 135

4,167

5,9545,712

0

2,000

4,000

6,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

15%

22%

41%

21%Hospital Ancillary

Faculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 135 0%

Faculty 4,167 15%Research 5,954 22%

Central 11,244 41%Student 5,712 21%

100%Assignable Square Footage 27,212 sf

Circulation, wall area, etc. 18,503 sfGross Bldg Area 45,715 sf

BAIRD HALL (BH)

11,244

10,000

12,000Assignable Square Footage by Category

15%

22%

21%

Inpatient

Outpatient

Hospital Ancillary

Faculty

0 0 135

4,167

5,9545,712

0

2,000

4,000

6,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

15%

22%

41%

21%Hospital Ancillary

Faculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 135 0%

Faculty 4,167 15%Research 5,954 22%

Central 11,244 41%Student 5,712 21%

100%Assignable Square Footage 27,212 sf

Circulation, wall area, etc. 18,503 sfGross Bldg Area 45,715 sf

BAIRD HALL (BH)

11,244

10,000

12,000Assignable Square Footage by Category

15%

22%

21%

Inpatient

Outpatient

Hospital Ancillary

Faculty

0 0 135

4,167

5,9545,712

0

2,000

4,000

6,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

15%

22%

41%

21%Hospital Ancillary

Faculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 135 0%

Faculty 4,167 15%Research 5,954 22%

Central 11,244 41%Student 5,712 21%

100%Assignable Square Footage 27,212 sf

Circulation, wall area, etc. 18,503 sfGross Bldg Area 45,715 sf

BAIRD HALL (BH)

11,244

10,000

12,000Assignable Square Footage by Category

15%

22%

21%

Inpatient

Outpatient

Hospital Ancillary

Faculty

0 0 135

4,167

5,9545,712

0

2,000

4,000

6,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

15%

22%

41%

21%Hospital Ancillary

Faculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 135 0%

Faculty 4,167 15%Research 5,954 22%

Central 11,244 41%Student 5,712 21%

100%Assignable Square Footage 27,212 sf

Circulation, wall area, etc. 18,503 sfGross Bldg Area 45,715 sf

BAIRD HALL (BH)

11,244

10,000

12,000Assignable Square Footage by Category

15%

22%

21%

Inpatient

Outpatient

Hospital Ancillary

Faculty

0 0 135

4,167

5,9545,712

0

2,000

4,000

6,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

15%

22%

41%

21%Hospital Ancillary

Faculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 135 0%

Faculty 4,167 15%Research 5,954 22%

Central 11,244 41%Student 5,712 21%

100%Assignable Square Footage 27,212 sf

Circulation, wall area, etc. 18,503 sfGross Bldg Area 45,715 sf

BAIRD HALL (BH)

11,244

10,000

12,000Assignable Square Footage by Category

15%

22%

21%

Inpatient

Outpatient

Hospital Ancillary

Faculty

0 0 135

4,167

5,9545,712

0

2,000

4,000

6,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

15%

22%

41%

21%Hospital Ancillary

Faculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 135 0%

Faculty 4,167 15%Research 5,954 22%

Central 11,244 41%Student 5,712 21%

100%Assignable Square Footage 27,212 sf

Circulation, wall area, etc. 18,503 sfGross Bldg Area 45,715 sf

BAIRD HALL (BH)

11,244

10,000

12,000Assignable Square Footage by Category

15%

22%

21%

Inpatient

Outpatient

Hospital Ancillary

Faculty

0 0 135

4,167

5,9545,712

0

2,000

4,000

6,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

15%

22%

41%

21%Hospital Ancillary

Faculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 135 0%

Faculty 4,167 15%Research 5,954 22%

Central 11,244 41%Student 5,712 21%

100%Assignable Square Footage 27,212 sf

Circulation, wall area, etc. 18,503 sfGross Bldg Area 45,715 sf

BAIRD HALL (BH)

11,244

10,000

12,000Assignable Square Footage by Category

15%

22%

21%

Inpatient

Outpatient

Hospital Ancillary

Faculty

0 0 135

4,167

5,9545,712

0

2,000

4,000

6,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

15%

22%

41%

21%Hospital Ancillary

Faculty

Research

Central

Student

85,583 Square Footage910,000$ 2011-2020 Deferred Maintenance Event Cost

35,691,534$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

2.55% FCI

339,694 Square Footage177,000$ 2011-2020 Deferred Maintenance Event Cost

106,080,000$ Core & Shell Insured Replacement Value312$ Replacement Cost / Square Foot

0.17% FCI

99,149 Square Footage1,088,000$ 2011-2020 Deferred Maintenance Event Cost

41,492,561$ Core & Shell Insured Replacement Value418$ Replacement Cost / Square Foot

2.62% FCI

10,443 Square Footage331,000$ 2011-2020 Deferred Maintenance Event Cost

BICC

BRB

Modular Building Structure

School of Nursing

331,000$ 2011-2020 Deferred Maintenance Event Cost3,551,951$ Core & Shell Insured Replacement Value

340$ Replacement Cost / Square Foot9.32% FCI

50,964 Square Footage3,158,000$ 2011-2020 Deferred Maintenance Event Cost

21,223,166$ Core & Shell Insured Replacement Value416$ Replacement Cost / Square Foot

14.88% FCI

98,169 Square Footage4,817,000$ 2011-2020 Deferred Maintenance Event Cost

40,940,400$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

11.77% FCI

Campus Services Building

Vollum Institute

15% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.12 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 17,033 40%Hospital Ancillary 5,343 13%

Faculty 10,270 24%Research 7,934 19%

Central 928 2%Student 1,007 2%

100%Assignable Square Footage 42,515 sf

Circulation, wall area, etc. 51,136 sfGross Bldg Area 93,651 sf

CASEY EYE INSTITUTE (CEI)

17,033

14,000

16,000

18,000Assignable Square Footage by Category

40%

24%

19%

2% 2%

0

5,343

10,270

7,934

928 1,007

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

40%

13%24%

19%

Built in 1991, casey Eye institute contains 93,650 gSf on six floors and serves as the gateway to the marquam Hill campus from terwilliger Blvd. cEi is a world-recognized academic regional eye center that attracts top specialists from around the globe. cEi primarily houses ophthalmological research, adult and pediatric eye clinics. review of the facility indicates that this building is in fair condition with a rating of 14%

Casey eye institute (Cei)

265,289 Square Footage456,000$ 2011-2020 Deferred Maintenance Event Cost

155,090,675$ Core & Shell Insured Replacement Value585$ Replacement Cost / Square Foot

0.29% FCI

291,055 Square Footage6,175,000$ 2011-2020 Deferred Maintenance Event Cost

144,771,927$ Core & Shell Insured Replacement Value497$ Replacement Cost / Square Foot

4.27% FCI

501,064 Square Footage3,785,000$ 2011-2020 Deferred Maintenance Event Cost

230,241,301$ Core & Shell Insured Replacement Value460$ Replacement Cost / Square Foot

1.64% FCI

93,650 Gross Exterior Square Footage5,484,000$ 2011-2020 Deferred Maintenance Event Cost

Mark O Hatfield Research Center

OHSU Hospital

Casey Eye Institute

Doernbecher Childrens Hospital

5,484,000$ 2011-2020 Deferred Maintenance Event Cost39,055,796$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot14.04% FCI

Category ASF %Inpatient 0 0%

Outpatient 17,033 40%Hospital Ancillary 5,343 13%

Faculty 10,270 24%Research 7,934 19%

Central 928 2%Student 1,007 2%

100%Assignable Square Footage 42,515 sf

Circulation, wall area, etc. 51,136 sfGross Bldg Area 93,651 sf

CASEY EYE INSTITUTE (CEI)

17,033

14,000

16,000

18,000Assignable Square Footage by Category

40%

24%

19%

2% 2%

0

5,343

10,270

7,934

928 1,007

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

40%

13%24%

19%

14% FCI

© Laura Zeigen

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.13EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

located in the central district on portland’s South Waterfront at the foot of the aerial tram, cHH was built in 2005 and contains 421,000 gSf on sixteen floors. many oHSu Hospital and School of medicine faculty clinics and services are located in this building. the main lobby includes the casey optical Studio, a pharmacy, the daily café and coffee stand. the march Wellness spa and fitness center is located on the second floor. cHH has no fci rating because of its leased status when the fci was conducted.

Center For Health and Healing (CHH)

Category ASF %Inpatient 35 0%

Outpatient 61,448 28%Hospital Ancillary 70,035 32%

Faculty 18,025 8%Research 32,112 14%

Central 6,875 3%Student 33,181 15%

100%Assignable Square Footage 221,711 sf

Circulation, wall area, etc. 228,816 sfGross Bldg Area 450,527 sf

CENTER FOR HEALTH AND HEALING (CHH)

61,448

70,035

56,000

64,000

72,000

80,000Assignable Square Footage by Category

0%

28%14%

3% 15%

Inpatient

Outpatient

Hospital AncillaryFaculty

35

61,448

18,025

32,112

6,875

33,181

0

8,000

16,000

24,000

32,000

40,000

48,000

56,000

64,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

28%

32%8%

14%

3% 15% Hospital AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 35 0%

Outpatient 61,448 28%Hospital Ancillary 70,035 32%

Faculty 18,025 8%Research 32,112 14%

Central 6,875 3%Student 33,181 15%

100%Assignable Square Footage 221,711 sf

Circulation, wall area, etc. 228,816 sfGross Bldg Area 450,527 sf

CENTER FOR HEALTH AND HEALING (CHH)

61,448

70,035

56,000

64,000

72,000

80,000Assignable Square Footage by Category

0%

28%14%

3% 15%

Inpatient

Outpatient

Hospital AncillaryFaculty

35

61,448

18,025

32,112

6,875

33,181

0

8,000

16,000

24,000

32,000

40,000

48,000

56,000

64,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

28%

32%8%

14%

3% 15% Hospital AncillaryFaculty

Research

Central

Student

no fci review/ rating done for cHH. architect evaluation shown.*

*

© Cyril “Kent” Anderson

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.14 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1968, child development & rehabilitation center contains 119, 834 gSf on four floors. cdrc primarily houses pediatrics and child development & rehabilitation department offices as well as some inpatient space. review of the facility indicates that this building is in fair condition with a fci rating of 16%.

Child Development and Rehabilitation Center (CDRC)

Category ASF %Inpatient 924 2%

Outpatient 7,142 12%Hospital Ancillary 4,361 7%

Faculty 33,220 56%Research 6,887 12%

Central 1,730 3%Student 5,265 9%

100%Assignable Square Footage 59,529 sf

Circulation, wall area, etc. 60,305 sfGross Bldg Area 119,834 sf

CHILD DEVELOPMENT REHAB. CENTER (CDRC)

33,220

25,000

30,000

35,000Assignable Square Footage by Category

2% 12%7%

56%

12%

3% 9%Inpatient

Outpatient

Hospital AncillaryFaculty

924

7,142

4,361

6,887

1,730

5,265

0

5,000

10,000

15,000

20,000

25,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

56%

AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 924 2%

Outpatient 7,142 12%Hospital Ancillary 4,361 7%

Faculty 33,220 56%Research 6,887 12%

Central 1,730 3%Student 5,265 9%

100%Assignable Square Footage 59,529 sf

Circulation, wall area, etc. 60,305 sfGross Bldg Area 119,834 sf

CHILD DEVELOPMENT REHAB. CENTER (CDRC)

33,220

25,000

30,000

35,000Assignable Square Footage by Category

2% 12%7%

56%

12%

3% 9%Inpatient

Outpatient

Hospital AncillaryFaculty

924

7,142

4,361

6,887

1,730

5,265

0

5,000

10,000

15,000

20,000

25,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

56%

AncillaryFaculty

Research

Central

Student

265,289 Square Footage167,000$ 2011-2020 Deferred Maintenance Event Cost

155,090,675$ Core & Shell Insured Replacement Value585$ Replacement Cost / Square Foot

0.11% FCI

291,055 Square Footage6,118,000$ 2011-2020 Deferred Maintenance Event Cost

144,771,927$ Core & Shell Insured Replacement Value497$ Replacement Cost / Square Foot

4.23% FCI

501,064 Square Footage2,464,000$ 2011-2020 Deferred Maintenance Event Cost

230,241,301$ Core & Shell Insured Replacement Value460$ Replacement Cost / Square Foot

1.07% FCI

93,650 Gross Exterior Square Footage5,458,000$ 2011-2020 Deferred Maintenance Event Cost

39,055,796$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

13.97% FCI

119,833 Square Footage7,989,000$ 2011-2020 Deferred Maintenance Event Cost

49,975,571$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

15.99% FCI

31,513 Square Footage4,873,000$ 2011-2020 Deferred Maintenance Event Cost

13,342,325$ Core & Shell Insured Replacement Value423$ Replacement Cost / Square Foot

36.52% FCI

Child Development Rehab (CDRC)

Mark O Hatfield Research Center

OHSU Hospital

Casey Eye Institute

Dillehunt

Doernbecher Childrens Hospital

16% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.15EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

$$$

Facilities Condition Index

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1954, child development & rehabilitation center West contains 15,801 gSf on two floors. faculty offices for the Emergency medicine department occupy most of this space. review of the facility indicates this building will remain useful with moderate maintenance and repairs.

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 1,116 11%

Faculty 6,651 65%Research 0 0%

Central 286 3%Student 2,254 22%

100%Assignable Square Footage 10,308 sf

Circulation, wall area, etc. 5,494 sfGross Bldg Area 15,801 sf

CHILD DEVELOPMENT REHABILITATION WEST

6,651

5,000

6,000

7,000Assignable Square Footage by Category

11%

65%

3%22%

Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

1,116

0286

2,254

0

1,000

2,000

3,000

4,000

5,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

65%

3%22% Hospital

AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 1,116 11%

Faculty 6,651 65%Research 0 0%

Central 286 3%Student 2,254 22%

100%Assignable Square Footage 10,308 sf

Circulation, wall area, etc. 5,494 sfGross Bldg Area 15,801 sf

CHILD DEVELOPMENT REHABILITATION WEST

6,651

5,000

6,000

7,000Assignable Square Footage by Category

11%

65%

3%22%

Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

1,116

0286

2,254

0

1,000

2,000

3,000

4,000

5,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

65%

3%22% Hospital

AncillaryFaculty

Research

Central

Student

Child Development and Rehabilitation Center West (CDW)

* no fci review/ rating done for cdW. architect evaluation shown.

*

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.16 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1924 as the original doernbecher children’s Hospital, dillehunt Hall contains 31,513 gSf on six floors. dillehunt houses clinical laboratories and associated administrative offices. With a fci rating of nearly 37%, dillehunt Hall is considered to be in ‘poor’ condition and is a candidate for demolition.

Dillehunt Hall (DH)

Category ASF %Inpatient 0 0%

Outpatient 1,270 7%Hospital Ancillary 13,997 81%

Faculty 1,718 10%Research 0 0%

Central 238 1%Student 0 0%

100%Assignable Square Footage 17,222 sf

Circulation, wall area, etc. 14,291 sfGross Bldg Area 31,513 sf

DILLEHUNT HALL (DH)

13,997

12,500

15,000

7%

10%

2%

Inpatient

Outpatient

Hospital Ancillary

0

1,2701,718

0 238 00

2,500

5,000

7,500

10,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

7%

81%

10%

2%

Hospital Ancillary

Faculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 1,270 7%Hospital Ancillary 13,997 81%

Faculty 1,718 10%Research 0 0%

Central 238 1%Student 0 0%

100%Assignable Square Footage 17,222 sf

Circulation, wall area, etc. 14,291 sfGross Bldg Area 31,513 sf

DILLEHUNT HALL (DH)

13,997

12,500

15,000

7%

10%

2%

Inpatient

Outpatient

Hospital Ancillary

0

1,2701,718

0 238 00

2,500

5,000

7,500

10,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

7%

81%

10%

2%

Hospital Ancillary

Faculty

Research

Central

Student

265,289 Square Footage167,000$ 2011-2020 Deferred Maintenance Event Cost

155,090,675$ Core & Shell Insured Replacement Value585$ Replacement Cost / Square Foot

0.11% FCI

291,055 Square Footage6,118,000$ 2011-2020 Deferred Maintenance Event Cost

144,771,927$ Core & Shell Insured Replacement Value497$ Replacement Cost / Square Foot

4.23% FCI

501,064 Square Footage2,464,000$ 2011-2020 Deferred Maintenance Event Cost

230,241,301$ Core & Shell Insured Replacement Value460$ Replacement Cost / Square Foot

1.07% FCI

93,650 Gross Exterior Square Footage5,458,000$ 2011-2020 Deferred Maintenance Event Cost

39,055,796$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

13.97% FCI

119,833 Square Footage7,989,000$ 2011-2020 Deferred Maintenance Event Cost

49,975,571$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

15.99% FCI

31,513 Square Footage4,873,000$ 2011-2020 Deferred Maintenance Event Cost

13,342,325$ Core & Shell Insured Replacement Value423$ Replacement Cost / Square Foot

36.52% FCI

Child Development Rehab (CDRC)

Mark O Hatfield Research Center

OHSU Hospital

Casey Eye Institute

Dillehunt

Doernbecher Childrens Hospital

37% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.17EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1998, doernbecher contains 291,055 gSf on seven floors. dcH houses pediatric inpatient and outpatient services. the fci rating is ‘good’ with a rating of 4%.

Doernbecher Children’s Hospital (DCH)

Category ASF %Inpatient 50,881 40%

Outpatient 37,909 30%Hospital Ancillary 32,296 25%

Faculty 3,446 3%Research 0 0%

Central 2,055 2%Student 565 0%

100%Assignable Square Footage 127,153 sf

Circulation, wall area, etc. 163,902 sfGross Bldg Area 291,055 sf

DOERNBECHER CHILDREN'S HOSPITAL (DCH)

50,88150,000

60,000Assignable Square Footage by Category

3%

0% 2%0%

Inpatient

Outpatient

Hospital Ancillary

37,909

32,296

3,446

02,055

5650

10,000

20,000

30,000

40,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

40%

30%

25%

3% 0%

Hospital Ancillary

Faculty

Research

Central

Student

Category ASF %Inpatient 50,881 40%

Outpatient 37,909 30%Hospital Ancillary 32,296 25%

Faculty 3,446 3%Research 0 0%

Central 2,055 2%Student 565 0%

100%Assignable Square Footage 127,153 sf

Circulation, wall area, etc. 163,902 sfGross Bldg Area 291,055 sf

DOERNBECHER CHILDREN'S HOSPITAL (DCH)

50,88150,000

60,000Assignable Square Footage by Category

3%

0% 2%0%

Inpatient

Outpatient

Hospital Ancillary

37,909

32,296

3,446

02,055

5650

10,000

20,000

30,000

40,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

40%

30%

25%

3% 0%

Hospital Ancillary

Faculty

Research

Central

Student

265,289 Square Footage456,000$ 2011-2020 Deferred Maintenance Event Cost

155,090,675$ Core & Shell Insured Replacement Value585$ Replacement Cost / Square Foot

0.29% FCI

291,055 Square Footage6,175,000$ 2011-2020 Deferred Maintenance Event Cost

144,771,927$ Core & Shell Insured Replacement Value497$ Replacement Cost / Square Foot

4.27% FCI

501,064 Square Footage3,785,000$ 2011-2020 Deferred Maintenance Event Cost

230,241,301$ Core & Shell Insured Replacement Value460$ Replacement Cost / Square Foot

1.64% FCI

93,650 Gross Exterior Square Footage5,484,000$ 2011-2020 Deferred Maintenance Event Cost

Mark O Hatfield Research Center

OHSU Hospital

Casey Eye Institute

Doernbecher Childrens Hospital

5,484,000$ 2011-2020 Deferred Maintenance Event Cost39,055,796$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot14.04% FCI

4% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.18 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Established in 1990 when the university purchased and renovated a former fire station, dotter institute contains 9,506 gSf on two floors. this small building comprises faculty offices and a few laboratories for the study of interventional therapy. dotter has a fci rating of approximately 9% and is considered to be in ‘fair’ condition.

Dotter interventional institute (DOT)

13,960 Square Footage1,783,000$ 2011-2020 Deferred Maintenance Event Cost6,769,942$ Core & Shell Insured Replacement Value

485$ Replacement Cost / Square Foot26.34% FCI

9,506 Square Footage336,000$ 2011-2020 Deferred Maintenance Event Cost

3,695,533$ Core & Shell Insured Replacement Value389$ Replacement Cost / Square Foot

9.09% FCI

120,412 Square Footage16,224,000$ 2011-2020 Deferred Maintenance Event Cost50,216,620$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot32.31% FCI

299,103 Square Footage25,580,000$ 2011-2020 Deferred Maintenance Event Cost

Medical Research Building

Dotter Memorial Building

Energy Management Center

Basic Science

25,580,000$ 2011-2020 Deferred Maintenance Event Cost87,347,355$ Core & Shell Insured Replacement Value

292$ Replacement Cost / Square Foot29.29% FCI

147,916 Square Footage20,100,000$ 2011-2020 Deferred Maintenance Event Cost61,686,889$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot32.58% FCI

112,017 Square Footage15,711,000$ 2011-2020 Deferred Maintenance Event Cost46,715,570$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot33.63% FCI

School of Dentistry

MacKenzie Hall

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 108 2%

Faculty 3,829 54%Research 0 0%

Central 509 7%Student 2,701 38%

100%Assignable Square Footage 7,147 sf

Circulation, wall area, etc. 2,359 sfGross Bldg Area 9,506 sf

DOTTER RESEARCH LAB (DOT)

3,829

3,500

4,000

4,500Assignable Square Footage by Category

2%

54%

38%

0 0108

0

509

2,701

0

500

1,000

1,500

2,000

2,500

3,000

3,500

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

54%

7%

38%

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 108 2%

Faculty 3,829 54%Research 0 0%

Central 509 7%Student 2,701 38%

100%Assignable Square Footage 7,147 sf

Circulation, wall area, etc. 2,359 sfGross Bldg Area 9,506 sf

DOTTER RESEARCH LAB (DOT)

3,829

3,500

4,000

4,500Assignable Square Footage by Category

2%

54%

38%

0 0108

0

509

2,701

0

500

1,000

1,500

2,000

2,500

3,000

3,500

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

54%

7%

38%

9% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.19EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1926 as a residence hall for nursing students, EJH contains 27,970 gSf on five floors. Emma Jones Hall houses family medicine faculty offices and classrooms. With a fci rating of nearly 60%, EJH has the highest (worst) rating of any oHSu building. this is a prime candidate for demolition.

emma Jones Hall (eJH)

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 320 2%

Faculty 9,400 57%Research 1,111 7%

Central 208 1%Student 5,406 33%

100%Assignable Square Footage 16,445 sf

Circulation, wall area, etc. 11,524 sfGross Bldg Area 27,970 sf

EMMA JONES HALL (EJH)

9,400

7,000

8,000

9,000

10,000Assignable Square Footage by Category

2%

57%

7%1%

33%

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

0 0320

1,111

208

5,406

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

57%

7%1%

Faculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 320 2%

Faculty 9,400 57%Research 1,111 7%

Central 208 1%Student 5,406 33%

100%Assignable Square Footage 16,445 sf

Circulation, wall area, etc. 11,524 sfGross Bldg Area 27,970 sf

EMMA JONES HALL (EJH)

9,400

7,000

8,000

9,000

10,000Assignable Square Footage by Category

2%

57%

7%1%

33%

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

0 0320

1,111

208

5,406

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

57%

7%1%

Faculty

Research

Central

Student

210,910 Square Footage32,498,000$ 2011-2020 Deferred Maintenance Event Cost93,814,455$ Core & Shell Insured Replacement Value

445$ Replacement Cost / Square Foot34.64% FCI

144,915 Square Footage23,653,000$ 2011-2020 Deferred Maintenance Event Cost60,435,352$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot39.14% FCI

27,969 Square Footage5,086,000$ 2011-2020 Deferred Maintenance Event Cost8,477,582$ Core & Shell Insured Replacement Value

303$ Replacement Cost / Square Foot59.99% FCI

Emma Jones Hall

Multnomah Pavilion

Sam Jackson

60% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.20 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1931, gaines Hallcontains 33,368 gSf on four floors. it houses allied Health faculty and staff offices. With a fci rating of 46%, gH has the third worst rating of university buildings. gaines Hall will need extensive renovation if it is not demolished.

gaines Hall (gH)

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 89 1%Hospital Ancillary 0 0%

Faculty 11,227 68%Research 1,147 7%

Central 154 1%Student 3,938 24%

100%Assignable Square Footage 16,555 sf

Circulation, wall area, etc. 16,813 sfGross Bldg Area 33,368 sf

GAINES HALL (GH)

11,227

10,000

12,000Assignable Square Footage by Category

68%7%1%

24%

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

0 89 0

1,147

154

3,938

0

2,000

4,000

6,000

8,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

68%7%1%

24% AncillaryFaculty

Research

Central

Student

45,715 Gross Exterior Square Footage8,294,000$ 2011-2020 Deferred Maintenance Event Cost

19,064,150$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

43.51% FCI

33,368 Square Footage4,065,000$ 2011-2020 Deferred Maintenance Event Cost8,917,364$ Core & Shell Insured Replacement Value

267$ Replacement Cost / Square Foot45.59% FCI

90,627 Square Footage6,124,000$ 2011-2020 Deferred Maintenance Event Cost

13,115,246$ Core & Shell Insured Replacement Value145$ Replacement Cost / Square Foot

46.69% FCI

31,134 Square Footage4,237,000$ 2011-2020 Deferred Maintenance Event Cost

Physical Plant

Gaines Hall

Old Library & Auditorium

Baird Hall

4,237,000$ 2011-2020 Deferred Maintenance Event Cost8,304,187$ Core & Shell Insured Replacement Value

267$ Replacement Cost / Square Foot51.02% FCI

46% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.21EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1997, Hatfield research center contains 303,471 gSf on 12 floors. Hrc houses the Emergency department and offices for a variety of departments including Knight cancer institute, the department of neurology, and the Jungers center for neurosciences research. Hrc has the best fci rating (less than 1%) of hospital buildings and is in ‘good’ condition.

Hatfield Research Building (HRC)

Category ASF %Inpatient 0 0%

Outpatient 15,683 13%Hospital Ancillary 19,767 16%

Faculty 21,480 17%Research 55,191 45%

Central 4,273 3%Student 6,445 5%

100%Assignable Square Footage 122,840 sf

Circulation, wall area, etc. 180,631 sfGross Bldg Area 303,471 sf

HATFIELD RESEARCH CENTER (HRC)

55,191

48,000

56,000

64,000Assignable Square Footage by Category

0% 13%

16%

17%45%

3% 5%Inpatient

Outpatient

Hospital AncillaryFaculty

0

15,683

19,76721,480

4,2736,445

0

8,000

16,000

24,000

32,000

40,000

48,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

16%

17%45%

Hospital AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 15,683 13%Hospital Ancillary 19,767 16%

Faculty 21,480 17%Research 55,191 45%

Central 4,273 3%Student 6,445 5%

100%Assignable Square Footage 122,840 sf

Circulation, wall area, etc. 180,631 sfGross Bldg Area 303,471 sf

HATFIELD RESEARCH CENTER (HRC)

55,191

48,000

56,000

64,000Assignable Square Footage by Category

0% 13%

16%

17%45%

3% 5%Inpatient

Outpatient

Hospital AncillaryFaculty

0

15,683

19,76721,480

4,2736,445

0

8,000

16,000

24,000

32,000

40,000

48,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

16%

17%45%

Hospital AncillaryFaculty

Research

Central

Student

265,289 Square Footage456,000$ 2011-2020 Deferred Maintenance Event Cost

155,090,675$ Core & Shell Insured Replacement Value585$ Replacement Cost / Square Foot

0.29% FCI

291,055 Square Footage6,175,000$ 2011-2020 Deferred Maintenance Event Cost

144,771,927$ Core & Shell Insured Replacement Value497$ Replacement Cost / Square Foot

4.27% FCI

501,064 Square Footage3,785,000$ 2011-2020 Deferred Maintenance Event Cost

230,241,301$ Core & Shell Insured Replacement Value460$ Replacement Cost / Square Foot

1.64% FCI

93,650 Gross Exterior Square Footage5,484,000$ 2011-2020 Deferred Maintenance Event Cost

Mark O Hatfield Research Center

OHSU Hospital

Casey Eye Institute

Doernbecher Childrens Hospital

5,484,000$ 2011-2020 Deferred Maintenance Event Cost39,055,796$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot14.04% FCI

0.3% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.22 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 2005, Kohler pavilion contains 382,823 gSf on 13 floors. Kpv houses inpatient and outpatient facilities for a variety of departments including neurology/Ent, oncology, and cardiac care. no fci rating is available for this building but given its age, it is considered to be in very good condition.

Kohler pavilion (Kpv)

Category ASF %Inpatient 56,649 41%

Outpatient 13,769 10%Hospital Ancillary 58,858 42%

Faculty 2,596 2%Research 29 0%

Central 7,430 5%Student 0 0%

100%Assignable Square Footage 139,330 sf

Circulation, wall area, etc. 243,493 sfGross Bldg Area 382,823 sf

KOHLER PAVILION (KPV)

56,64958,858

48,000

56,000

64,000Assignable Square Footage by Category

41%

42%

2% 0%

5%

0%Inpatient

Outpatient

Hospital AncillaryFaculty

13,769

2,59629

7,430

00

8,000

16,000

24,000

32,000

40,000

48,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

41%

10%

42%

Hospital AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 56,649 41%

Outpatient 13,769 10%Hospital Ancillary 58,858 42%

Faculty 2,596 2%Research 29 0%

Central 7,430 5%Student 0 0%

100%Assignable Square Footage 139,330 sf

Circulation, wall area, etc. 243,493 sfGross Bldg Area 382,823 sf

KOHLER PAVILION (KPV)

56,64958,858

48,000

56,000

64,000Assignable Square Footage by Category

41%

42%

2% 0%

5%

0%Inpatient

Outpatient

Hospital AncillaryFaculty

13,769

2,59629

7,430

00

8,000

16,000

24,000

32,000

40,000

48,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

41%

10%

42%

Hospital AncillaryFaculty

Research

Central

Student

144,915 Square Footage23,680,000$ 2011-2020 Deferred Maintenance Event Cost60,435,352$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot39.18% FCI

27,969 Square Footage5,086,000$ 2011-2020 Deferred Maintenance Event Cost8,477,582$ Core & Shell Insured Replacement Value

303$ Replacement Cost / Square Foot59.99% FCI

408,652 Square FootageNA 2011-2020 Deferred Maintenance Event Cost

187,200,000$ Core & Shell Insured Replacement ValueNA Replacement Cost / Square Foot

0.00% FCI

Kohler Pavilion

Emma Jones Hall

Sam Jackson

*

© Cyril “Kent” Anderson

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.23EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1919, mackenzie Hall contains 112,018 gSf on five floors. mac primarily houses the School of medicine dean’s office, research development administration, classrooms, laboratories, and faculty offices for a variety of departments including Surgery, neurology, molecular and medical genetics. mac has a fci rating of 34% and is considered to be in ‘poor’ condition. moderate to extensive renovation will be needed in the future. given mackenzie Hall’s historic significance, it is doubtful that it would be demolished.

mackenzie Hall (mAC)

Category ASF %Inpatient 0 0%

Outpatient 98 0%Hospital Ancillary 12,020 18%

Faculty 21,358 32%Research 17,481 26%

Central 6,297 9%Student 9,465 14%

100%Assignable Square Footage 66,718 sf

Circulation, wall area, etc. 45,300 sfGross Bldg Area 112,018 sf

MACKENZIE HALL (MAC)

21,358

17,481

15,000

20,000

25,000Assignable Square Footage by Category

18%

32%26%

10%

14%

0 98

12,020

6,297

9,465

0

5,000

10,000

15,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

26%

Category ASF %Inpatient 0 0%

Outpatient 98 0%Hospital Ancillary 12,020 18%

Faculty 21,358 32%Research 17,481 26%

Central 6,297 9%Student 9,465 14%

100%Assignable Square Footage 66,718 sf

Circulation, wall area, etc. 45,300 sfGross Bldg Area 112,018 sf

MACKENZIE HALL (MAC)

21,358

17,481

15,000

20,000

25,000Assignable Square Footage by Category

18%

32%26%

10%

14%

0 98

12,020

6,297

9,465

0

5,000

10,000

15,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

26%

13,960 Square Footage1,783,000$ 2011-2020 Deferred Maintenance Event Cost6,769,942$ Core & Shell Insured Replacement Value

485$ Replacement Cost / Square Foot26.34% FCI

9,506 Square Footage336,000$ 2011-2020 Deferred Maintenance Event Cost

3,695,533$ Core & Shell Insured Replacement Value389$ Replacement Cost / Square Foot

9.09% FCI

120,412 Square Footage16,224,000$ 2011-2020 Deferred Maintenance Event Cost50,216,620$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot32.31% FCI

299,103 Square Footage25,580,000$ 2011-2020 Deferred Maintenance Event Cost

Medical Research Building

Dotter Memorial Building

Energy Management Center

Basic Science

25,580,000$ 2011-2020 Deferred Maintenance Event Cost87,347,355$ Core & Shell Insured Replacement Value

292$ Replacement Cost / Square Foot29.29% FCI

147,916 Square Footage20,100,000$ 2011-2020 Deferred Maintenance Event Cost61,686,889$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot32.58% FCI

112,017 Square Footage15,711,000$ 2011-2020 Deferred Maintenance Event Cost46,715,570$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot33.63% FCI

School of Dentistry

MacKenzie Hall

34% FCI

© Bill Niemeyer

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.24 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

the macadam Warehouse (oHSu logistics center) is a leased building in the South Waterfront district and contains 33,827 gsf of total area over multiple floors. mWc primarily houses support and warehouse space for hospital and clinic supplies for both the marquam Hill campus and cHH. offices for the logistics and facilities departments are also located at mWc. due to the building being leased, no fci review or rating has been done for mWc.

macadam Warehouse/ OHSU logistics Center (mCW)

* no fci review/ rating done for mcW. architect evaluation shown.

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 18,280 54%

Faculty 0 0%Research 0 0%

Central 15,547 46%Student 0 0%

100%Assignable Square Footage 33,827 sf

Circulation, wall area, etc. 3,840 sfGross Bldg Area 37,667 sf

Macadam Warehouse (MCW)

18,280

15,547

10,000

12,000

14,000

16,000

18,000

20,000

54%46%

0 0 0 0 00

2,000

4,000

6,000

8,000

10,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 18,280 54%

Faculty 0 0%Research 0 0%

Central 15,547 46%Student 0 0%

100%Assignable Square Footage 33,827 sf

Circulation, wall area, etc. 3,840 sfGross Bldg Area 37,667 sf

Macadam Warehouse (MCW)

18,280

15,547

10,000

12,000

14,000

16,000

18,000

20,000

54%46%

0 0 0 0 00

2,000

4,000

6,000

8,000

10,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

*

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.25EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1961 as the university’s first dedicated research building, the medical research Building contains 120,413 gSf on nine floors. mrB houses research laboratories and office space for a variety of departments including Behavioral neuroscience, Biochemistry, otolaryngology, molecular Biology, and the vollum institute. mrB has a fci rating of 32% and is considered to be in ‘poor’ condition. the building will need moderate to extensive renovation.

medical Research Building (mRB)

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 214 0%

Faculty 6,058 9%Research 52,341 82%Central 1,338 2%Student 4,223 7%

100%Assignable Square Footage 64,173 sfCirculation, wall area, etc. 56,239 sf

Gross Bldg Area 120,413 sf

MEDICAL RESEARCH BUILDING (MRB)

52,341

40,000

50,000

60,000Assignable Square Footage by Category

0% 9%

82%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

0 0 214

6,058

52,341

1,3384,223

0

10,000

20,000

30,000

40,000

50,000

60,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Assignable Square Footage by Category

0% 9%

82%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 214 0%

Faculty 6,058 9%Research 52,341 82%Central 1,338 2%Student 4,223 7%

100%Assignable Square Footage 64,173 sfCirculation, wall area, etc. 56,239 sf

Gross Bldg Area 120,413 sf

MEDICAL RESEARCH BUILDING (MRB)

52,341

40,000

50,000

60,000Assignable Square Footage by Category

0% 9%

82%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

0 0 214

6,058

52,341

1,3384,223

0

10,000

20,000

30,000

40,000

50,000

60,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Assignable Square Footage by Category

0% 9%

82%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

Student

13,960 Square Footage1,783,000$ 2011-2020 Deferred Maintenance Event Cost6,769,942$ Core & Shell Insured Replacement Value

485$ Replacement Cost / Square Foot26.34% FCI

9,506 Square Footage336,000$ 2011-2020 Deferred Maintenance Event Cost

3,695,533$ Core & Shell Insured Replacement Value389$ Replacement Cost / Square Foot

9.09% FCI

120,412 Square Footage16,224,000$ 2011-2020 Deferred Maintenance Event Cost50,216,620$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot32.31% FCI

299,103 Square Footage25,580,000$ 2011-2020 Deferred Maintenance Event Cost

Medical Research Building

Dotter Memorial Building

Energy Management Center

Basic Science

25,580,000$ 2011-2020 Deferred Maintenance Event Cost87,347,355$ Core & Shell Insured Replacement Value

292$ Replacement Cost / Square Foot29.29% FCI

147,916 Square Footage20,100,000$ 2011-2020 Deferred Maintenance Event Cost61,686,889$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot32.58% FCI

112,017 Square Footage15,711,000$ 2011-2020 Deferred Maintenance Event Cost46,715,570$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot33.63% FCI

School of Dentistry

MacKenzie Hall

32% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.26 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

9% FCI

Built in 1988 for staging construction, the modular Building Structure contains 10,443 gSf on two floors. these temporary structures accommodate offices for the Hospital’s medical affairs, Business development, and managed care. mBS has a fci rating of approximately 9% and is considered to be in ‘fair’ condition. these temporary structures occupy an important site and should be removed.

modular Building Structure (mBS)

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 7,336 100%

Faculty 0 0%Research 0 0%

Central 27 0%Student 0 0%

100%Assignable Square Footage 7,363 sf

Circulation, wall area, etc. 3,080 sfGross Bldg Area 10,443 sf

MODULAR BLDG. STRUCTURE (MBS)

7,336

4,000

5,000

6,000

7,000

8,000Assignable Square Footage by Category

100%

0 0 0 0 27 00

1,000

2,000

3,000

4,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 7,336 100%

Faculty 0 0%Research 0 0%

Central 27 0%Student 0 0%

100%Assignable Square Footage 7,363 sf

Circulation, wall area, etc. 3,080 sfGross Bldg Area 10,443 sf

MODULAR BLDG. STRUCTURE (MBS)

7,336

4,000

5,000

6,000

7,000

8,000Assignable Square Footage by Category

100%

0 0 0 0 27 00

1,000

2,000

3,000

4,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

85,583 Square Footage910,000$ 2011-2020 Deferred Maintenance Event Cost

35,691,534$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

2.55% FCI

339,694 Square Footage177,000$ 2011-2020 Deferred Maintenance Event Cost

106,080,000$ Core & Shell Insured Replacement Value312$ Replacement Cost / Square Foot

0.17% FCI

99,149 Square Footage1,088,000$ 2011-2020 Deferred Maintenance Event Cost

41,492,561$ Core & Shell Insured Replacement Value418$ Replacement Cost / Square Foot

2.62% FCI

10,443 Square Footage331,000$ 2011-2020 Deferred Maintenance Event Cost

BICC

BRB

Modular Building Structure

School of Nursing

331,000$ 2011-2020 Deferred Maintenance Event Cost3,551,951$ Core & Shell Insured Replacement Value

340$ Replacement Cost / Square Foot9.32% FCI

50,964 Square Footage3,158,000$ 2011-2020 Deferred Maintenance Event Cost

21,223,166$ Core & Shell Insured Replacement Value416$ Replacement Cost / Square Foot

14.88% FCI

98,169 Square Footage4,817,000$ 2011-2020 Deferred Maintenance Event Cost

40,940,400$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

11.77% FCI

Campus Services Building

Vollum Institute

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.27EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1919 as the original hospital on marquam Hill (aka the county Hospital), multnomah pavilion contains 210,910 gSf on seven floors. mnp now houses inpatient psychiatry, outpatient departments including ambulatory Surgery and adult Bone marrow transplant as well as offices for medical school faculty. mnp has a fci rating of 35% and is considered to be in ‘poor’ condition. given its historic significance and size, full demolition of mnp is unlikely; moderate to extensive renovations will be necessary.

multnomah pavilion (mnp)

Category ASF %Inpatient 5,735 6%

Outpatient 23,420 23%Hospital Ancillary 17,238 17%

Faculty 31,341 30%Research 12,010 12%

Central 9,298 9%Student 4,411 4%

100%Assignable Square Footage 103,453 sf

Circulation, wall area, etc. 107,457 sfGross Bldg Area 210,910 sf

MULTNOMAH PAVILION (MNP)

23,420

31,341

25,000

30,000

35,000Assignable Square Footage by Category

6%

23%

17%30%

12%

9%4%

5,735

23,420

17,238

12,010

9,298

4,411

0

5,000

10,000

15,000

20,000

25,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

23%

17%30%

12%

Category ASF %Inpatient 5,735 6%

Outpatient 23,420 23%Hospital Ancillary 17,238 17%

Faculty 31,341 30%Research 12,010 12%

Central 9,298 9%Student 4,411 4%

100%Assignable Square Footage 103,453 sf

Circulation, wall area, etc. 107,457 sfGross Bldg Area 210,910 sf

MULTNOMAH PAVILION (MNP)

23,420

31,341

25,000

30,000

35,000Assignable Square Footage by Category

6%

23%

17%30%

12%

9%4%

5,735

23,420

17,238

12,010

9,298

4,411

0

5,000

10,000

15,000

20,000

25,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

23%

17%30%

12%

119,833 Square Footage7,989,000$ 2011-2020 Deferred Maintenance Event Cost

49,975,571$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

15.99% FCI

10,443 Square Footage331,000$ 2011-2020 Deferred Maintenance Event Cost

3,551,951$ Core & Shell Insured Replacement Value340$ Replacement Cost / Square Foot

9.32% FCI

31,513 Square Footage4,873,000$ 2011-2020 Deferred Maintenance Event Cost

13,342,325$ Core & Shell Insured Replacement Value423$ Replacement Cost / Square Foot

36.52% FCI

210,910 Square Footage

Modular Building Structure

Child Development Rehab (CDRC)

Multnomah Pavilion

Dillehunt

210,910 Square Footage32,818,000$ 2011-2020 Deferred Maintenance Event Cost93,814,455$ Core & Shell Insured Replacement Value

445$ Replacement Cost / Square Foot34.98% FCI 35% FCI

© Liz Lynch

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.28 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1939 as the university’s original library, oHSu auditorium contains 90,629 gSf on four floors. aud continues to house library stacks, the main auditorium on campus, and student assembly rooms. receiving dock 4 was added to the south side of the building but is functionally inadequate and needs to be relocated. aud has a fci rating of 47%, which is the second worst rated university building. given aud’s historic significance, demolition is unlikely; extensive renovation will be necessary.

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 0 0%

Faculty 4,406 13%Research 0 0%Central 6,776 20%Student 21,923 66%

100%Assignable Square Footage 33,106 sfCirculation, wall area, etc. 57,523 sf

Gross Bldg Area 90,629 sf

OHSU AUDITORIUM (AUD)

21,923

20,000

25,000Assignable Square Footage by Category

13%

21%

66%

Inpatient

Outpatient

Hospital AncillaryFaculty

0 0 0

4,406

0

6,776

21,923

0

5,000

10,000

15,000

20,000

25,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Assignable Square Footage by Category

13%

21%

66%

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

Student

OHSU Auditorium (AUD)

45,715 Gross Exterior Square Footage8,294,000$ 2011-2020 Deferred Maintenance Event Cost

19,064,150$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

43.51% FCI

33,368 Square Footage4,065,000$ 2011-2020 Deferred Maintenance Event Cost8,917,364$ Core & Shell Insured Replacement Value

267$ Replacement Cost / Square Foot45.59% FCI

90,627 Square Footage6,124,000$ 2011-2020 Deferred Maintenance Event Cost

13,115,246$ Core & Shell Insured Replacement Value145$ Replacement Cost / Square Foot

46.69% FCI

31,134 Square Footage4,237,000$ 2011-2020 Deferred Maintenance Event Cost

Physical Plant

Gaines Hall

Old Library & Auditorium

Baird Hall

4,237,000$ 2011-2020 Deferred Maintenance Event Cost8,304,187$ Core & Shell Insured Replacement Value

267$ Replacement Cost / Square Foot51.02% FCI

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 0 0%

Faculty 4,406 13%Research 0 0%Central 6,776 20%Student 21,923 66%

100%Assignable Square Footage 33,106 sfCirculation, wall area, etc. 57,523 sf

Gross Bldg Area 90,629 sf

OHSU AUDITORIUM (AUD)

21,923

20,000

25,000Assignable Square Footage by Category

13%

21%

66%

Inpatient

Outpatient

Hospital AncillaryFaculty

0 0 0

4,406

0

6,776

21,923

0

5,000

10,000

15,000

20,000

25,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Assignable Square Footage by Category

13%

21%

66%

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

Student

47% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.29EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1956, oHSu Hospital contains 501,064 gSf on fifteen floors. oHS houses inpatient Services as well as Surgery and intensive care. the building has a fci rating of 2% and is considered to be in ‘good’ condition. Extensive recent upgrades have prolonged the expected life of oHS for another 50 years.

OHSU Hospital (OHS)

Category ASF %Inpatient 87,179 39%

Outpatient 3,167 1%Hospital Ancillary 116,221 52%

Faculty 3,467 2%Research 146 0%

Central 10,709 5%Student 2,559 1%

100%Assignable Square Footage 223,448 sf

Circulation, wall area, etc. 277,616 sfGross Bldg Area 501,064 sf

OHSU HOSPITAL (OHS)

116,221

100,000

120,000

140,000Assignable Square Footage by Category

39%

52%

2%0%

5%

1%

87,179

3,167 3,467146

10,709

2,5590

20,000

40,000

60,000

80,000

100,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

39%

1%

52%

Category ASF %Inpatient 87,179 39%

Outpatient 3,167 1%Hospital Ancillary 116,221 52%

Faculty 3,467 2%Research 146 0%

Central 10,709 5%Student 2,559 1%

100%Assignable Square Footage 223,448 sf

Circulation, wall area, etc. 277,616 sfGross Bldg Area 501,064 sf

OHSU HOSPITAL (OHS)

116,221

100,000

120,000

140,000Assignable Square Footage by Category

39%

52%

2%0%

5%

1%

87,179

3,167 3,467146

10,709

2,5590

20,000

40,000

60,000

80,000

100,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

39%

1%

52%

265,289 Square Footage456,000$ 2011-2020 Deferred Maintenance Event Cost

155,090,675$ Core & Shell Insured Replacement Value585$ Replacement Cost / Square Foot

0.29% FCI

291,055 Square Footage6,175,000$ 2011-2020 Deferred Maintenance Event Cost

144,771,927$ Core & Shell Insured Replacement Value497$ Replacement Cost / Square Foot

4.27% FCI

501,064 Square Footage3,785,000$ 2011-2020 Deferred Maintenance Event Cost

230,241,301$ Core & Shell Insured Replacement Value460$ Replacement Cost / Square Foot

1.64% FCI

93,650 Gross Exterior Square Footage5,484,000$ 2011-2020 Deferred Maintenance Event Cost

Mark O Hatfield Research Center

OHSU Hospital

Casey Eye Institute

Doernbecher Childrens Hospital

5,484,000$ 2011-2020 Deferred Maintenance Event Cost39,055,796$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot14.04% FCI

2% FCI

© Photo courtesy of OHSU Digital Resources Library

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.30 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1959 and expanded in 1990, the oHSu Student center contains 33,634 gSf on two floors. oSc houses the student bookstore, pool and gymnasium. as teaching facilities are removed to the Schnitzer campus, oSc functions may also move there incrementally. this building is in ‘fair’ condition and does not need to be demolished unless the site is needed for other uses.

OHSU Student Center (OSC)

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 0 0%

Faculty 0 0%Research 0 0%Central 334 1%Student 23,926 99%

100%Assignable Square Footage 24,261 sfCirculation, wall area, etc. 9,374 sf

Gross Bldg Area 33,634 sf

OHSU STUDENT CENTER (OSC)

23,92625,000

30,000Assignable Square Footage by Category

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

0 0 0 0 0 334

23,926

0

5,000

10,000

15,000

20,000

25,000

30,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Assignable Square Footage by Category

99%

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 0 0%

Faculty 0 0%Research 0 0%Central 334 1%Student 23,926 99%

100%Assignable Square Footage 24,261 sfCirculation, wall area, etc. 9,374 sf

Gross Bldg Area 33,634 sf

OHSU STUDENT CENTER (OSC)

23,92625,000

30,000Assignable Square Footage by Category

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

0 0 0 0 0 334

23,926

0

5,000

10,000

15,000

20,000

25,000

30,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Assignable Square Footage by Category

99%

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

Student

*

* no fci review/ rating done for oSc. architect evaluation shown.

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.31EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

the physical plant Building contains 31,134 gsf over two floors. physical plant primarily houses offices for the facilities department. pp has a fci rating of approximately 51% and is considered to be in poor condition. this building could be demolished and its office backfilled into other buildings.

physical plant (pp)

31,134 Square Footage

3,850,961$ Executive Summary Deferred Maintenance Current Need8,304,854$ Executive Summary Replacement Cost

46.37% Executive Summary FCI

4,237,000$ 2011-2020 Deferred Maintenance Event Cost8,304,187$ Core & Shell Insured Replacement Value

267$ Replacement Cost / Square Foot51.02% FCI

Physical Plant

31,134 Square Footage

3,850,961$ Executive Summary Deferred Maintenance Current Need8,304,854$ Executive Summary Replacement Cost

46.37% Executive Summary FCI

4,237,000$ 2011-2020 Deferred Maintenance Event Cost8,304,187$ Core & Shell Insured Replacement Value

267$ Replacement Cost / Square Foot51.02% FCI

Physical Plant

51% FCI

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 673 3%

Faculty 1,800 8%Research 481 2%

Central 18,685 85%Student 408 2%

100%Assignable Square Footage 22,046 sf

Circulation, wall area, etc. 9,088 sfGross Bldg Area 31,134 sf

PHYSICAL PLANT (PP)

18,685

14,000

16,000

18,000

20,000

3%

8%2%

2%

0 0673

1,800

481 408

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

85%

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.32 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1992, physicians pavilion contains 84,635 gSf on four floors. ppv houses outpatient facilities and clinics for a variety of departments including internal medicine, Surgery, Ear nose & throat, and perinatal care. due to ppv being a leased building, it does not have an fci rating but is considered to be in good condition.

physician’s pavilion (ppv)

Category ASF %Inpatient 0 0%

Outpatient 31,597 68%Hospital Ancillary 12,555 27%

Faculty 1,913 4%Research 0 0%

Central 538 1%Student 143 0%

100%Assignable Square Footage 46,745 sf

Circulation, wall area, etc. 37,890 sfGross Bldg Area 84,635 sf

PHYSICIANS PAVILION (PPV)

31,597

25,000

30,000

35,000Assignable Square Footage by Category

68%

27%

4% 1%

0

12,555

1,913

0 538 1430

5,000

10,000

15,000

20,000

25,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

68%

27%

Category ASF %Inpatient 0 0%

Outpatient 31,597 68%Hospital Ancillary 12,555 27%

Faculty 1,913 4%Research 0 0%

Central 538 1%Student 143 0%

100%Assignable Square Footage 46,745 sf

Circulation, wall area, etc. 37,890 sfGross Bldg Area 84,635 sf

PHYSICIANS PAVILION (PPV)

31,597

25,000

30,000

35,000Assignable Square Footage by Category

68%

27%

4% 1%

0

12,555

1,913

0 538 1430

5,000

10,000

15,000

20,000

25,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

68%

27%

* no fci review/ rating done for ppv architect evaluation shown.

*

© Photo courtesy of OHSU Digital Resources Library

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.33EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1967 and later expanded in 1992, richard Jones Hall contains 299,103 gSf on eight floors. it is essentially two buildings joined as one, the original Basic Science Building and the Basic Science addition/croEt which opened 20 years later. rJH primarily houses research laboratory space for a variety of departments including the center for research on occupational and Environmental toxicology (croEt), anatomic pathology, and Biochemistry and molecular Biology. rJH has a fci rating of approxi-mately 30% and is considered in fair condition; moderate renovations will be necessary.

Richard Jones Hall for Basic medical Sciences (RJH)

Category ASF %Inpatient 0 0%

Outpatient 105 0%Hospital Ancillary 3,014 2%

Faculty 29,287 19%Research 80,009 53%

Central 5,306 3%Student 34,445 23%

100%Assignable Square Footage 152,167 sf

Circulation, wall area, etc. 146,936 sfGross Bldg Area 299,103 sf

RICHARD T. JONES HALL (RJH)

80,009

70,000

80,000

90,000Assignable Square Footage by Category

2%

19%3%

23%

0 1053,014

29,287

5,306

34,445

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

19%

53%

3%23%

Category ASF %Inpatient 0 0%

Outpatient 105 0%Hospital Ancillary 3,014 2%

Faculty 29,287 19%Research 80,009 53%

Central 5,306 3%Student 34,445 23%

100%Assignable Square Footage 152,167 sf

Circulation, wall area, etc. 146,936 sfGross Bldg Area 299,103 sf

RICHARD T. JONES HALL (RJH)

80,009

70,000

80,000

90,000Assignable Square Footage by Category

2%

19%3%

23%

0 1053,014

29,287

5,306

34,445

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

19%

53%

3%23%

299,103 Square Footage25,580,000$ 2011-2020 Deferred Maintenance Event Cost87,347,355$ Core & Shell Insured Replacement Value

292$ Replacement Cost / Square Foot29.29% FCI

147,916 Square Footage20,100,000$ 2011-2020 Deferred Maintenance Event Cost61,686,889$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot32.58% FCI

112,017 Square Footage15,711,000$ 2011-2020 Deferred Maintenance Event Cost46,715,570$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot33.63% FCI

45,715 Gross Exterior Square Footage8,294,000$ 2011-2020 Deferred Maintenance Event Cost

19,064,150$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

43.51% FCI

School of Dentistry

MacKenzie Hall

Baird Hall

Basic Science

30% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.34 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1929 as the hospital’s original outpatient building, Sam Jackson Hall contains 144,915 gSf on eight floors. SJH houses various hospital support departments as well as faculty and staff offices for a number of School of medicine departments including neurology and the Jungers center for neurosciences research, diagnostic radiology, and the department of medicine. SJH has a fci rating of 40%, which is the third worst. review of this building suggests that it is a candidate for demolition.

Sam Jackson Hall (SJH)

Category ASF %Inpatient 0 0%

Outpatient 3,531 5%Hospital Ancillary 27,822 42%

Faculty 21,490 33%Research 2,004 3%

Central 5,398 8%Student 5,743 9%

100%Assignable Square Footage 65,990 sf

Circulation, wall area, etc. 78,925 sfGross Bldg Area 144,915 sf

SAM JACKSON HALL (SJH)

27,822

21,490

25,000

30,000Assignable Square Footage by Category

0% 5%

42%33%

3%

8%9%

0

3,531

21,490

2,004

5,398 5,743

0

5,000

10,000

15,000

20,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

42%33%

3%

Category ASF %Inpatient 0 0%

Outpatient 3,531 5%Hospital Ancillary 27,822 42%

Faculty 21,490 33%Research 2,004 3%

Central 5,398 8%Student 5,743 9%

100%Assignable Square Footage 65,990 sf

Circulation, wall area, etc. 78,925 sfGross Bldg Area 144,915 sf

SAM JACKSON HALL (SJH)

27,822

21,490

25,000

30,000Assignable Square Footage by Category

0% 5%

42%33%

3%

8%9%

0

3,531

21,490

2,004

5,398 5,743

0

5,000

10,000

15,000

20,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

42%33%

3%

144,915 Square Footage23,680,000$ 2011-2020 Deferred Maintenance Event Cost60,435,352$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot39.18% FCI

27,969 Square Footage5,086,000$ 2011-2020 Deferred Maintenance Event Cost8,477,582$ Core & Shell Insured Replacement Value

303$ Replacement Cost / Square Foot59.99% FCI

408,652 Square FootageNA 2011-2020 Deferred Maintenance Event Cost

187,200,000$ Core & Shell Insured Replacement ValueNA Replacement Cost / Square Foot

0.00% FCI

Kohler Pavilion

Emma Jones Hall

Sam Jackson

40% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.35EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1954, the School of dentistry contains 147,916 gSf on nine floors. Sod houses the School of dentistry classrooms, laboratories, and faculty offices as well as the outpatient dental clinic. the building has a fci rating of 33% and is considered to be in ‘poor’ condition. this building is a candidate for demolition.

School of Dentistry (SOD)

Category ASF %Inpatient 0 0%

Outpatient 5,726 7%Hospital Ancillary 2,422 3%

Faculty 18,844 22%Research 11,267 13%

Central 1,896 2%Student 47,031 54%

100%Assignable Square Footage 87,187 sf

Circulation, wall area, etc. 60,729 sfGross Bldg Area 147,916 sf

SCHOOL OF DENTISTRY (SOD)

47,031

35,000

40,000

45,000

50,000Assignable Square Footage by Category

0% 7% 3%

22%54%

0

5,726

2,422

18,844

11,267

1,896

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

22%

13%2%

54%

Category ASF %Inpatient 0 0%

Outpatient 5,726 7%Hospital Ancillary 2,422 3%

Faculty 18,844 22%Research 11,267 13%

Central 1,896 2%Student 47,031 54%

100%Assignable Square Footage 87,187 sf

Circulation, wall area, etc. 60,729 sfGross Bldg Area 147,916 sf

SCHOOL OF DENTISTRY (SOD)

47,031

35,000

40,000

45,000

50,000Assignable Square Footage by Category

0% 7% 3%

22%54%

0

5,726

2,422

18,844

11,267

1,896

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

22%

13%2%

54%

13,960 Square Footage1,783,000$ 2011-2020 Deferred Maintenance Event Cost6,769,942$ Core & Shell Insured Replacement Value

485$ Replacement Cost / Square Foot26.34% FCI

9,506 Square Footage336,000$ 2011-2020 Deferred Maintenance Event Cost

3,695,533$ Core & Shell Insured Replacement Value389$ Replacement Cost / Square Foot

9.09% FCI

120,412 Square Footage16,224,000$ 2011-2020 Deferred Maintenance Event Cost50,216,620$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot32.31% FCI

299,103 Square Footage25,580,000$ 2011-2020 Deferred Maintenance Event Cost

Medical Research Building

Dotter Memorial Building

Energy Management Center

Basic Science

25,580,000$ 2011-2020 Deferred Maintenance Event Cost87,347,355$ Core & Shell Insured Replacement Value

292$ Replacement Cost / Square Foot29.29% FCI

147,916 Square Footage20,100,000$ 2011-2020 Deferred Maintenance Event Cost61,686,889$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot32.58% FCI

112,017 Square Footage15,711,000$ 2011-2020 Deferred Maintenance Event Cost46,715,570$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot33.63% FCI

School of Dentistry

MacKenzie Hall

33% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.36 EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Built in 1991, the School of nursing contains 99,149 gSf on seven floors. Son houses the School of nursing classrooms and faculty offices as well as the center for Evidence Based policy. it has a fci rating of 3% and is considered to be in ‘good’ condition.

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 184 0%

Faculty 25,935 58%Research 5,229 12%

Central 791 2%Student 12,307 28%

100%Assignable Square Footage 44,446 sf

Circulation, wall area, etc. 54,703 sfGross Bldg Area 99,149 sf

SCHOOL OF NURSING (SON)

25,935

25,000

30,000Assignable Square Footage by Category

58%2%

28%

0 0 184

5,229

791

12,307

0

5,000

10,000

15,000

20,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

58%

12%

2%

28%

School of nursing (SOn)

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 184 0%

Faculty 25,935 58%Research 5,229 12%

Central 791 2%Student 12,307 28%

100%Assignable Square Footage 44,446 sf

Circulation, wall area, etc. 54,703 sfGross Bldg Area 99,149 sf

SCHOOL OF NURSING (SON)

25,935

25,000

30,000Assignable Square Footage by Category

58%2%

28%

0 0 184

5,229

791

12,307

0

5,000

10,000

15,000

20,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

58%

12%

2%

28%

85,583 Square Footage910,000$ 2011-2020 Deferred Maintenance Event Cost

35,691,534$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

2.55% FCI

339,694 Square Footage177,000$ 2011-2020 Deferred Maintenance Event Cost

106,080,000$ Core & Shell Insured Replacement Value312$ Replacement Cost / Square Foot

0.17% FCI

99,149 Square Footage1,088,000$ 2011-2020 Deferred Maintenance Event Cost

41,492,561$ Core & Shell Insured Replacement Value418$ Replacement Cost / Square Foot

2.62% FCI

10,443 Square Footage331,000$ 2011-2020 Deferred Maintenance Event Cost

BICC

BRB

Modular Building Structure

School of Nursing

331,000$ 2011-2020 Deferred Maintenance Event Cost3,551,951$ Core & Shell Insured Replacement Value

340$ Replacement Cost / Square Foot9.32% FCI

50,964 Square Footage3,158,000$ 2011-2020 Deferred Maintenance Event Cost

21,223,166$ Core & Shell Insured Replacement Value416$ Replacement Cost / Square Foot

14.88% FCI

98,169 Square Footage4,817,000$ 2011-2020 Deferred Maintenance Event Cost

40,940,400$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

11.77% FCI

Campus Services Building

Vollum Institute

3% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.37EXISTING FACILIT Y CONDITIONS

poor (>30%)good fair 1 fair 2

5% 10% 30%

Assignable Square Footage by Category

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Facilities Condition Index

$$$

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 3,787 14%

Faculty 3,835 14%Research 625 2%

Central 17,615 63%Student 1,979 7%

100%Assignable Square Footage 27,842 sf

Circulation, wall area, etc. 23,122 sfGross Bldg Area 50,964 sf

CAMPUS SERVICES BUILDING (CSB)

17,615

14,000

16,000

18,000

20,000Assignable Square Footage by Category

14%

14%

2%

7%Inpatient

Outpatient

Hospital AncillaryFaculty

0 0

3,787 3,835

625

1,979

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

2%

63%

Hospital AncillaryFaculty

Research

Central

Student

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 0 0%

Faculty 6,775 17%Research 27,459 70%Central 433 1%Student 4,316 11%

100%Assignable Square Footage 38,982 sfCirculation, wall area, etc. 59,188 sf

Gross Bldg Area 98,169 sf

VOLLUM INSTITUTE (VIABR)

27,459

25,000

30,000Assignable Square Footage by Category

17%1%

11%

Inpatient

Outpatient

Hospital AncillaryFaculty

0 0 0

6,775

27,459

433

4,316

0

5,000

10,000

15,000

20,000

25,000

30,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Assignable Square Footage by Category

17%

70%

1%11%

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

Student

Built in 1986, the vollum institute contains 98,169 gSf on six floors. viaBr houses research laboratories, support spaces, and offices for the vollum institute. the building has a fci rating of 12% and is considered to be in ‘fair’ condition, indicating that some renovation will be necessary.

vollum institute (viABR)

Category ASF %Inpatient 0 0%

Outpatient 0 0%Hospital Ancillary 0 0%

Faculty 6,775 17%Research 27,459 70%Central 433 1%Student 4,316 11%

100%Assignable Square Footage 38,982 sfCirculation, wall area, etc. 59,188 sf

Gross Bldg Area 98,169 sf

VOLLUM INSTITUTE (VIABR)

27,459

25,000

30,000Assignable Square Footage by Category

17%1%

11%

Inpatient

Outpatient

Hospital AncillaryFaculty

0 0 0

6,775

27,459

433

4,316

0

5,000

10,000

15,000

20,000

25,000

30,000

Inpatient Outpatient Hospital Ancillary

Faculty Research Central Student

Assignable Square Footage by Category

17%

70%

1%11%

Inpatient

Outpatient

Hospital AncillaryFaculty

Research

Central

Student

98,169 Square Footage4,817,000$ 2011-2020 Deferred Maintenance Event Cost

40,940,400$ Core & Shell Insured Replacement Value417$ Replacement Cost / Square Foot

11.77% FCI

13,960 Square Footage1,783,000$ 2011-2020 Deferred Maintenance Event Cost6,769,942$ Core & Shell Insured Replacement Value

485$ Replacement Cost / Square Foot26.34% FCI

9,506 Square Footage336,000$ 2011-2020 Deferred Maintenance Event Cost

3,695,533$ Core & Shell Insured Replacement Value389$ Replacement Cost / Square Foot

9.09% FCI

120,412 Square Footage16,224,000$ 2011-2020 Deferred Maintenance Event Cost50,216,620$ Core & Shell Insured Replacement Value

417$ Replacement Cost / Square Foot32.31% FCI

Vollum Institute

Dotter Memorial Building

Energy Management Center

Medical Research Building

12% FCI

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.38 EXISTING FACILIT Y CONDITIONS

Historically Significant Buildings

the university of oregon Schools of medicine, dentistry, and nursing were created in 1913 when Willamette university and the university of oregon merged their medical programs. in 1974, they became a single, freestanding state university. in 1880, during the western expansion of the railroad system, much of the marquam Hill campus had been bought, sight unseen, to build a railroad yard. the land was subsequently donated to the city for a beneficial public use: 20 acres from the oregon-Washington railroad and navigation company, and 88 acres from the owners of the oregon Journal. two years later, in 1919, the university of oregon medical center moved from downtown portland to the new campus, to a new building named to commemorate Kenneth a.J. mackenzie, md, the railroad’s surgeon who had suggested donation of the hilltop land for a hospital.

in 1923, the multnomah county Hospital joined mackenzie Hall to provide services to indigent patients. in 1926, the doernbecher memorial Hospital for children was built, and the next year a dormitory for nurses was added. in 1931 an outpatient clinic was established on the hill, and the following year, the department of nursing Education accepted its first students.

Within a dozen years of its establishment on marquam Hill, a substantial medical campus was in place. Survivors of that first building effort are the mackenzie Hall east wing completed in 1919 and the main hall added in 1922; the multnomah county Hospital, now known as multnomah pavilion, 1923; the first doernbecher children’s Hospital, now dillehunt Hall, 1926; Emma Jones Hall opened as a dormitory for nurses in 1927; and the first outpatient clinic, now Sam Jackson Hall, 1931.

OHSU 20-Year Facilities Master Plan: 2011–2030 I ZGF Architects I PKA Architects 3.39EXISTING FACILIT Y CONDITIONS

three buildings have been identified during this master plan process as possessing historic significance that distinguishes them from other buildings on campus due to their age, archi-tectural character, and importance within the context of the campus’ early development. it should be noted that the historical significance is from oHSu’s perspective and that none of these buildings are on the State Historical preservation office’s list of historical buildings.

mackenzie Hall (i.e. medical Sciences Building). opened in 1919.

multnomah pavilion (multnomah county Hospital) opened in 1923.

auditorium Building (old library). opened in 1939.